CN116145936A - Assembled construction platform and installation method for elevator installation - Google Patents
Assembled construction platform and installation method for elevator installation Download PDFInfo
- Publication number
- CN116145936A CN116145936A CN202310177492.0A CN202310177492A CN116145936A CN 116145936 A CN116145936 A CN 116145936A CN 202310177492 A CN202310177492 A CN 202310177492A CN 116145936 A CN116145936 A CN 116145936A
- Authority
- CN
- China
- Prior art keywords
- horizontal
- pipe
- horizontal pipe
- vertical
- construction platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 27
- 238000010276 construction Methods 0.000 title claims abstract description 24
- 238000000034 method Methods 0.000 title claims abstract description 8
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 32
- 239000010959 steel Substances 0.000 claims abstract description 32
- 238000010586 diagram Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000012467 final product Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/24—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
- E04G3/246—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the inside contour of a building
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/20—Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
- E04G5/046—Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B50/00—Energy efficient technologies in elevators, escalators and moving walkways, e.g. energy saving or recuperation technologies
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Types And Forms Of Lifts (AREA)
Abstract
本发明涉及一种用于电梯安装时的组装式施工平台及安装方法,施工平台的横向管(9)设在两水平管(6)之间,竖向管(2)设在水平管(6)上,槽形卡块(1)设在竖向管(2)上,钢绳(5)两端分别与水平管(6)和竖向管(2)连接。安装方法包括:a、将槽形卡块(1)卡在剪力墙(10)上;b、将第一根横向管(9)两端安到连接套(3)上;c、水平管(6)穿过连接套(3)后固定;d、将水平限位卡(4)安在水平管(6)上并卡在楼地面(8),将钢绳(5)与水平管(6)端部连接;e、将钢绳(5)与竖向管(2)固定;f、安装剩余横向管(9);g、铺设木板。解决现有技术在电梯井内搭设钢管费时费力,且安全性难保证的问题。
The invention relates to an assembled construction platform used for elevator installation and an installation method. The horizontal pipe (9) of the construction platform is arranged between two horizontal pipes (6), and the vertical pipe (2) is arranged on the horizontal pipe (6). ), the groove-shaped block (1) is arranged on the vertical pipe (2), and the two ends of the steel rope (5) are respectively connected with the horizontal pipe (6) and the vertical pipe (2). The installation method includes: a. clamping the groove-shaped clamping block (1) on the shear wall (10); b. installing the two ends of the first horizontal pipe (9) on the connecting sleeve (3); c. (6) Fix after passing through the connecting sleeve (3); d, install the horizontal limit card (4) on the horizontal pipe (6) and be stuck on the floor (8), connect the steel rope (5) to the horizontal pipe ( 6) End connection; e, fixing the steel rope (5) and the vertical pipe (2); f, installing the remaining horizontal pipe (9); g, laying planks. It solves the problems of time-consuming and labor-intensive erection of steel pipes in the elevator shaft in the prior art, and the problems that safety is difficult to guarantee.
Description
技术领域technical field
本发明涉及一种用于电梯安装时的组装式施工平台及安装方法,属于电梯安装技术领域。The invention relates to an assembled construction platform used for elevator installation and an installation method, belonging to the technical field of elevator installation.
背景技术Background technique
众所周知高层建筑均有用于安装电梯的电梯井,而现有的电梯井内壁光滑垂直,四周封闭,层高基本一致,传统方式的电梯井内电梯上部配重安装,钢丝绳穿束等工作常用钢管等材料搭设,不仅搭设费时费力,同时存在极大的施工安全隐患,造成实际的安装效率低,劳动强度大,后期组装和拆除都不方便。It is well known that all high-rise buildings have elevator shafts for installing elevators, and the existing elevator shafts have smooth and vertical inner walls, closed surroundings, and basically the same floor height. In the traditional way, steel pipes and other materials are commonly used for the installation of the upper counterweight of the elevator in the elevator shaft, and the wire rope threading. Erecting not only takes time and effort, but also has great construction safety hazards, resulting in low actual installation efficiency, high labor intensity, and inconvenient assembly and dismantling in the later stage.
发明内容Contents of the invention
本发明所要解决的技术问题是现有技术在电梯井内搭设钢管费时费力,且安全性难保证。The technical problem to be solved by the present invention is that it takes time and effort to erect steel pipes in the elevator shaft in the prior art, and it is difficult to guarantee the safety.
本发明解决其技术问题所采用的技术方案是:用于电梯安装时的组装式施工平台,包括槽形卡块、竖向管、水平管、横向管和钢绳,所述水平管至少为两根且对称设置,横向管设置在两水平管之间且端部分别与对应侧的水平管连接,竖向管对应垂直设置在水平管一端部外侧壁上,槽形卡块设置在竖向管的上部,且开口朝外,钢绳的一端与水平管远离竖向管的端部连接,另一端与竖向管上端连接。The technical solution adopted by the present invention to solve the technical problem is: an assembled construction platform used for elevator installation, including groove blocks, vertical pipes, horizontal pipes, horizontal pipes and steel ropes, the horizontal pipes are at least two The root and symmetrical arrangement, the horizontal pipe is arranged between the two horizontal pipes and the ends are respectively connected with the horizontal pipes on the corresponding side, the vertical pipe is correspondingly vertically arranged on the outer side wall of one end of the horizontal pipe, and the groove-shaped block is arranged on the vertical pipe and the opening is outward, one end of the steel rope is connected to the end of the horizontal pipe away from the vertical pipe, and the other end is connected to the upper end of the vertical pipe.
其中,上述结构中所述竖向管、水平管和横向管为方管结构。Wherein, the vertical tubes, horizontal tubes and horizontal tubes in the above structure are square tube structures.
其中,上述结构中所述水平管为长度可调的伸缩杆结构。Wherein, the horizontal pipe in the above structure is a telescopic rod structure with adjustable length.
其中,上述结构中还包括连接套,所述连接套套设在水平管上,且位于水平管端部的横向管9端部可固定在连接套后与水平管连接,竖向管下端与连接套上端垂直连接。Wherein, the above-mentioned structure also includes a connecting sleeve, the connecting sleeve is set on the horizontal pipe, and the end of the
其中,上述结构中还包括滑轮,所述滑轮分别设置在竖向管上端和水平管远离竖向管的端部,且钢绳连接在滑轮上。Wherein, the above structure also includes pulleys, the pulleys are respectively arranged on the upper end of the vertical pipe and the end of the horizontal pipe away from the vertical pipe, and the steel rope is connected to the pulley.
进一步,上述结构中所述水平管上间隔设置有若干通孔,使得连接套和横向管可通过螺栓与水平管可拆卸连接。Further, in the above structure, the horizontal pipe is provided with several through holes at intervals, so that the connecting sleeve and the horizontal pipe can be detachably connected to the horizontal pipe by bolts.
其中,上述结构中还包括水平限位卡,所述水平限位卡包括两块开口正对的F形本体,且水平限位卡套设在水平管上,并与水平管可拆卸连接。Wherein, the above structure also includes a horizontal limit card, which includes two F-shaped bodies with openings facing each other, and the horizontal limit card is sleeved on the horizontal pipe and detachably connected with the horizontal pipe.
其中,上述结构中所述横向管为若干根,且沿水平管长度方向间隔设置。Wherein, in the above structure, there are several transverse tubes, which are arranged at intervals along the length direction of the horizontal tubes.
用于电梯安装时的组装式施工平台的安装方法,包括步骤:The installation method of the assembled construction platform used for elevator installation, including steps:
a、将竖向管和槽形卡块连接后对应卡在电梯门两端剪力墙上;a. After connecting the vertical pipe and the grooved block, they are correspondingly stuck on the shear walls at both ends of the elevator door;
b、将第一根横向管两端安装到竖向管下端的连接套上;b. Install the two ends of the first horizontal pipe to the connecting sleeve at the lower end of the vertical pipe;
c、将水平管穿过竖向管下方的连接套后并固定;c. Pass the horizontal pipe through the connecting sleeve under the vertical pipe and fix it;
d、将水平限位卡对称安装在水平管上并卡在楼地面内口,同时将钢绳通过滑轮与水平管端部连接固定;d. Install the horizontal limit card symmetrically on the horizontal pipe and clamp it to the inner opening of the floor, and at the same time connect the steel rope to the end of the horizontal pipe through the pulley;
e、水平管伸出到位后将钢绳另一端与竖向管顶端固定;e. After the horizontal pipe is stretched out in place, fix the other end of the steel rope with the top of the vertical pipe;
f、安装剩余的横向管,使得横向管两端与水平管内侧连接;f. Install the remaining horizontal pipe so that both ends of the horizontal pipe are connected to the inside of the horizontal pipe;
g、铺设木板或者轻型钢板。g. Laying planks or light steel plates.
本发明的有益效果是:本结构组装简便,可重复使用,安全性高,保证了施工的质量和效率。本结构的水平管带有螺栓孔,方便水平管伸缩调节固定;竖向管与水平管通过连接套进行连接固定;槽形卡块通过高强螺栓固定于竖向管顶端适当位置,然后套卡在电梯洞口两端剪力墙上;最后通过钢绳将水平管前端与竖向管顶端相连形成三角受力体系,水平管间按适当步距布置横向管,便于形成合理的施工作业面。同时本结构降低室内电梯井顶部电梯配重等构件安装时安全风险,提高作业效率,可循环拆装使用。The beneficial effects of the invention are: the structure is easy to assemble, can be used repeatedly, has high safety, and ensures the quality and efficiency of construction. The horizontal pipe of this structure has bolt holes, which is convenient for the telescopic adjustment and fixing of the horizontal pipe; the vertical pipe and the horizontal pipe are connected and fixed through the connecting sleeve; Shear walls at both ends of the elevator opening; finally, the front ends of the horizontal pipes are connected to the tops of the vertical pipes by steel cables to form a triangular stress system, and horizontal pipes are arranged at appropriate steps between the horizontal pipes to form a reasonable construction work surface. At the same time, this structure reduces the safety risk when installing components such as the elevator counterweight on the top of the indoor elevator shaft, improves operation efficiency, and can be recycled and disassembled for use.
附图说明Description of drawings
图1为本发明结构示意图。Fig. 1 is a schematic diagram of the structure of the present invention.
图2为本发明左视结构示意图。Fig. 2 is a left view structural schematic diagram of the present invention.
图3为本发明俯视结构示意图。Fig. 3 is a schematic diagram of the top view structure of the present invention.
图中标记为:1、槽形卡块,2、竖向管;3、连接套;4、水平限位卡;5、钢绳;6、水平管;7、滑轮;8、楼地面;9、横向管;10、剪力墙;11、电梯井。The marks in the figure are: 1. Groove block, 2. Vertical pipe; 3. Connecting sleeve; 4. Horizontal limit card; 5. Steel rope; 6. Horizontal pipe; 7. Pulley; 8. Floor; 9 , Horizontal tube; 10, Shear wall; 11, Elevator shaft.
具体实施方式Detailed ways
下面结合附图对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings.
如图1至图3所示,本发明的用于电梯安装时的组装式施工平台,包括槽形卡块1、竖向管2、水平管6、横向管9和钢绳5,所述水平管6至少为两根且对称设置,横向管9设置在两水平管6之间且端部分别与对应侧的水平管6连接,竖向管2对应垂直设置在水平管6一端部外侧壁上,槽形卡块1设置在竖向管2的上部,且开口朝外,钢绳5的一端与水平管6远离竖向管2的端部连接,另一端与竖向管2上端连接。本领域技术人员能够理解的是,本结构主要用于电梯井11内的施工,水平管6作为主要的支撑主体,实际优选水平管6至少为两根且对称设置,实际优选水平管6为2根即可,且竖向管2与水平管6垂直连接固定,故竖向管2的数量应与水平管6对应。而槽形卡块1固定于竖向管2顶端适当位置,然后套卡在电梯洞口两端剪力墙10上,实现水平管6的固定。通过钢绳5将水平管6前端与竖向管2顶端相连形成三角受力体系,水平管6之间按适当步距布置横向管9,便于形成合理的施工作业面,这种结构设置使得本结构可现场组装,由于采用悬挑梁的结构方式,提高了作业的安全性。As shown in Figures 1 to 3, the assembled construction platform used for elevator installation of the present invention includes a
优选的,上述结构中所述竖向管2、水平管6和横向管9为方管结构。本领域技术人员能够理解的是,为了方便定位,本结构优选竖向管2、水平管6和横向管9为方管结构,且具体可优选为4mm的镀锌方管。Preferably, the
优选的,上述结构中所述水平管6为长度可调的伸缩杆结构。本领域技术人员能够理解的是,为了方便不同宽度的电梯井的安装使用需要,本装置优选水平管6为长度可调的伸缩杆结构,这种结构设置使得整个结构长度可调节。Preferably, the
优选的,上述结构中还包括连接套3,所述连接套3套设在水平管6上,且位于水平管6端部的横向管9端部可固定在连接套3后与水平管6连接,竖向管2下端与连接套3上端垂直连接。本领域技术人员能够理解的是,为了方便竖向管2连接,本结构优选在竖向管2的下端设置连接套3,而连接套3可穿设在水平管6上,实际通过螺杆或螺栓固定在水平管6上即可。同时位于水平管6端部的横向管9端部可固定在连接套3后与水平管6连接,也即是位于水平管6端部的横向管9通过连接套3与水平管6连接。Preferably, the above structure also includes a connecting sleeve 3, the connecting sleeve 3 is sleeved on the
优选的,上述结构中还包括滑轮7,所述滑轮7分别设置在竖向管2上端和水平管6远离竖向管2的端部,且钢绳5连接在滑轮7上。本领域技术人员能够理解的是,本领域技术人员能够理解的是,为了方便调节钢绳5长度,本结构优选将滑轮7分别设置在竖向管2上端和水平管6远离竖向管2的端部,且钢绳5连接在滑轮7上。Preferably, the above structure further includes a
优选的,上述结构中所述水平管6上间隔设置有若干通孔,使得连接套3和横向管9可通过螺栓与水平管6可拆卸连接。本领域技术人员能够理解的是,为了方便水平管6和连接套3以及横向管9的连接,本结构优选在水平管6上间隔设置有若干通孔,使得连接套3和横向管9可通过螺栓与水平管6可拆卸连接,这种结构设置可降低结零部件的重量,方便运输和搬运。Preferably, in the above structure, the
优选的,上述结构中还包括水平限位卡4,所述水平限位卡4包括两块开口正对的F形本体,且水平限位卡4套设在水平管6上,并与水平管6可拆卸连接。本领域技术人员能够理解的是,为了实现水平杆的水平限位,本结构优选还包括水平限位卡4,优选水平限位卡4包括两块开口正对的F形本体,两本体通过螺杆连接成一体,上部开口直接套设在水平管6上,使得水平限位卡4并与水平管6可拆卸连接。Preferably, the above-mentioned structure also includes a
优选的,上述结构中所述横向管9为若干根,且沿水平管6长度方向间隔设置。本领域技术人员能够理解的是,由于横向管9和水平管6主要用于支撑工人,故为了保证支撑点的数量,本结构优选横向管9为若干根,且沿水平管6长度方向间隔设置,使得横向管9和水平管6形成交叉的支撑点,实际后期可直接在其上方铺设木板即可。Preferably, in the above structure, there are several
用于电梯安装时的组装式施工平台的安装方法,包括步骤:The installation method of the assembled construction platform used for elevator installation, including steps:
a、将竖向管2和槽形卡块1连接后对应卡在电梯门两端剪力墙10上;a. After connecting the
b、将第一根横向管9两端安装到竖向管2下端的连接套3上;b. Install the two ends of the first
c、将水平管6穿过竖向管2下方的连接套3后并固定;c. Pass the
d、将水平限位卡4对称安装在水平管6上并卡在楼地面8内口,同时将钢绳5通过滑轮7与水平管6端部连接固定;d. Install the
e、水平管6伸出到位后将钢绳5另一端与竖向管2顶端固定;e. Fix the other end of the
f、安装剩余的横向管9,使得横向管9两端与水平管6内侧连接;f, install the remaining
g、铺设木板或者轻型钢板。本领域技术人员能够理解的是,主要施工方法,施工作业时,将竖向管2的上部和槽形卡块1连接后暂时卡在电梯门两端剪力墙10上;然后将第一根横向管9安装到连接套3起到对竖向管2横向支撑作用;将水平管6穿过竖向管2下方的连接套3后用螺栓固定;水平管6穿过连接套3后到位时将水平限位卡4对称安装在水平管6上并能卡在楼地面8内口,同时将钢绳5进行水平管6端部的滑轮7处进行连接固定;水平管6伸出到位后将钢绳5的另一端与竖向管2顶端固定;安装其他横向方管,保持横向管9两端与水平管6内侧连接;在相关构件安装完毕后根据需要在悬臂平台面铺设木板或者轻型钢板进行作业。g. Laying planks or light steel plates. Those skilled in the art can understand that the main construction method is that during construction work, the upper part of the
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202310177492.0A CN116145936A (en) | 2023-02-27 | 2023-02-27 | Assembled construction platform and installation method for elevator installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202310177492.0A CN116145936A (en) | 2023-02-27 | 2023-02-27 | Assembled construction platform and installation method for elevator installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN116145936A true CN116145936A (en) | 2023-05-23 |
Family
ID=86373398
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202310177492.0A Pending CN116145936A (en) | 2023-02-27 | 2023-02-27 | Assembled construction platform and installation method for elevator installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN116145936A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009051574A (en) * | 2007-08-23 | 2009-03-12 | Yahagi Elevator Kk | Elevator construction work scaffold and method of installing the scaffold using the same |
CN203846756U (en) * | 2014-05-15 | 2014-09-24 | 中天建设集团有限公司西南分公司 | Overhanging profile steel anchor device |
CN206707237U (en) * | 2017-04-27 | 2017-12-05 | 重庆建工第四建设有限责任公司 | Cable-stayed type top layer construction platform for elevator installation |
CN207484935U (en) * | 2017-10-16 | 2018-06-12 | 山西六建集团有限公司 | Shear wall elevator adjustable operating platform |
CN109972849A (en) * | 2019-04-23 | 2019-07-05 | 杭州昂创科技有限公司 | Inside and outside self-stabilising in sliding type electric stair shaft safety device construction method |
CN210738053U (en) * | 2019-09-28 | 2020-06-12 | 中建三局集团有限公司 | Turnover operation platform suitable for elevator counterweight installation |
CN211473318U (en) * | 2019-09-29 | 2020-09-11 | 李秋影 | Outdoor corollary equipment installation construction equipment of building |
CN112627560A (en) * | 2020-12-04 | 2021-04-09 | 中国十九冶集团有限公司 | Horizontal protective structure of elevator shaft |
CN214575524U (en) * | 2021-01-06 | 2021-11-02 | 中国建筑第七工程局有限公司 | Multifunctional elevator shaft platform |
-
2023
- 2023-02-27 CN CN202310177492.0A patent/CN116145936A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009051574A (en) * | 2007-08-23 | 2009-03-12 | Yahagi Elevator Kk | Elevator construction work scaffold and method of installing the scaffold using the same |
CN203846756U (en) * | 2014-05-15 | 2014-09-24 | 中天建设集团有限公司西南分公司 | Overhanging profile steel anchor device |
CN206707237U (en) * | 2017-04-27 | 2017-12-05 | 重庆建工第四建设有限责任公司 | Cable-stayed type top layer construction platform for elevator installation |
CN207484935U (en) * | 2017-10-16 | 2018-06-12 | 山西六建集团有限公司 | Shear wall elevator adjustable operating platform |
CN109972849A (en) * | 2019-04-23 | 2019-07-05 | 杭州昂创科技有限公司 | Inside and outside self-stabilising in sliding type electric stair shaft safety device construction method |
CN210738053U (en) * | 2019-09-28 | 2020-06-12 | 中建三局集团有限公司 | Turnover operation platform suitable for elevator counterweight installation |
CN211473318U (en) * | 2019-09-29 | 2020-09-11 | 李秋影 | Outdoor corollary equipment installation construction equipment of building |
CN112627560A (en) * | 2020-12-04 | 2021-04-09 | 中国十九冶集团有限公司 | Horizontal protective structure of elevator shaft |
CN214575524U (en) * | 2021-01-06 | 2021-11-02 | 中国建筑第七工程局有限公司 | Multifunctional elevator shaft platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100557168C (en) | A high-altitude installation method for long-span steel truss | |
CN106241618A (en) | A kind of curtain wall profiles boom hoisting | |
CN108560895B (en) | Adjustable elevator shaft operation platform and erection method thereof | |
CN114508231B (en) | Quick combination construction method for I-steel component | |
CN102561669A (en) | Cantilever scaffold and construction method thereof | |
CN104695752A (en) | Rapid repairing tower system and erection method thereof | |
WO2023208250A1 (en) | Curtain wall construction platform | |
CN109138431A (en) | A kind of Super High pump line Overbridge device and its construction method | |
CN113931313A (en) | Super high-rise core tube horizontal structure construction method | |
CN109869153A (en) | The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method | |
CN209780193U (en) | Suspension type scaffold | |
CN109629447B (en) | Variable cross-section cast-in-situ box girder construction and concrete pouring method | |
CN116145936A (en) | Assembled construction platform and installation method for elevator installation | |
CN206051364U (en) | A kind of curtain wall profiles boom hoisting | |
CN108483212A (en) | Cladding glass installation self-control electric hoist hanger system and its hanging method | |
CN220365282U (en) | Electric translation type hanging basket | |
CN114991126B (en) | Non-prestress post-inserted composite anchor cable anti-pulling pile construction equipment | |
CN216713867U (en) | Fixed bolster of prefabricated wallboard and contain braced system of this support | |
CN111764623B (en) | Hanging construction platform module and construction method of high altitude large cantilever steel roof frame | |
CN115787996A (en) | Overhung construction method and overhung frame for super-high building | |
CN111042519B (en) | An early dismantling system for floor formwork containing beam and slab structure buildings | |
CN221031335U (en) | Climbing frame attached steel upright post of roof framework layer and climbing system | |
CN214329836U (en) | Construction hanging bracket for slip form system | |
CN220267177U (en) | Elevator well operation platform | |
CN214575559U (en) | Elevator shaft assembly type construction operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |