CN116145721A - A rapid construction method of semi-prefabricated buttress retaining wall - Google Patents
A rapid construction method of semi-prefabricated buttress retaining wall Download PDFInfo
- Publication number
- CN116145721A CN116145721A CN202310359930.5A CN202310359930A CN116145721A CN 116145721 A CN116145721 A CN 116145721A CN 202310359930 A CN202310359930 A CN 202310359930A CN 116145721 A CN116145721 A CN 116145721A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- buttress
- wall
- reserved
- semi
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0283—Retaining or protecting walls characterised by constructional features of mixed type
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Retaining Walls (AREA)
Abstract
Description
技术领域technical field
本发明涉及土建施工技术领域,尤其涉及一种半预制扶壁式挡土墙快速施工方法。The invention relates to the technical field of civil construction, in particular to a rapid construction method of a semi-prefabricated buttress-type retaining wall.
背景技术Background technique
扶壁式挡土墙是一种薄壁式钢筋混凝土挡土墙,一般由底板、立壁、扶壁等主要部分组成。其结构简单、自身重量轻,可以抵抗较大的水压和地震力,有效防止土体滑动;而且,可以根据需要调整扶壁尺寸,以适应不同的地形,得到了较为广泛的应用。Buttress retaining wall is a kind of thin-walled reinforced concrete retaining wall, which is generally composed of base plate, vertical wall, buttress and other main parts. Its structure is simple, its own weight is light, it can resist large water pressure and earthquake force, and effectively prevent the soil from sliding; moreover, the size of the buttress can be adjusted according to needs to adapt to different terrains, and it has been widely used.
目前扶壁式挡土墙常用的施工方法有整体浇筑和预制拼装等。At present, the commonly used construction methods of buttress retaining walls include integral pouring and prefabricated assembly.
采用现浇法施工需要钢筋绑扎、模板安装加固、混凝土浇筑等施工工序;尤其是挡墙的扶壁结构属于薄壁异型变截面结构,在钢筋绑扎、模板安装过程比较耗费工期,不利于快速施工。采用预制拼装工艺,则结构的整体稳定性相对不足。The cast-in-place method requires construction procedures such as steel bar binding, formwork installation and reinforcement, and concrete pouring; especially the buttress structure of the retaining wall is a thin-walled special-shaped variable-section structure, which is time-consuming in the process of steel bar binding and formwork installation, which is not conducive to rapid construction . If the prefabricated assembly process is adopted, the overall stability of the structure is relatively insufficient.
申请人根据工程经验,结合目前常用的预制模块设计以及施工工艺,综合考虑整体强度、施工效率等,特改进设计了本施工方法。Based on engineering experience, combined with the commonly used prefabricated module design and construction technology, and comprehensively considering the overall strength and construction efficiency, the applicant specially improved and designed this construction method.
发明内容Contents of the invention
本发明的目的是为了解决现有技术中,扶壁式挡土墙施工还存在一些不足的问题,而提出的一种半预制扶壁式挡土墙快速施工方法。The purpose of the present invention is to solve the problem of some deficiencies in the construction of the buttress-type retaining wall in the prior art, and proposes a quick construction method for the semi-prefabricated buttress-type retaining wall.
为了实现上述目的,本发明采用了如下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:
一种半预制扶壁式挡土墙快速施工方法,包括以下步骤:A semi-prefabricated buttress type retaining wall rapid construction method, comprising the following steps:
S1、工厂预制扶壁;S1. Factory prefabricated buttresses;
S2、施工现场浇筑底板、立壁;S2. Pouring the floor and vertical walls at the construction site;
S3、安装预制扶壁,浇筑预制扶壁与立壁之间的湿接缝。S3. Install the prefabricated buttress, and pour the wet joint between the prefabricated buttress and the vertical wall.
在一些实施例中,所述预制扶壁的底部预留插筋孔;In some embodiments, rib insertion holes are reserved at the bottom of the prefabricated buttress;
所述底板上设置与预制扶壁对应的预留插筋。Reserved ribs corresponding to the prefabricated buttresses are set on the base plate.
在一些实施例中,所述所述预制扶壁的侧面设置有与预留插筋孔联通的灌浆孔;In some embodiments, the side of the prefabricated buttress is provided with a grouting hole communicating with the reserved reinforcement hole;
在步骤S3中,通过灌浆孔注入水泥浆。In step S3, inject grout through the grout hole.
在一些实施例中,所述立壁与预制扶壁的结合面分别设置有预留勾筋。In some embodiments, reserved hook ribs are respectively provided on the joint surfaces of the vertical wall and the prefabricated buttress.
在一些实施例中,在步骤S2中,包括以下步骤:In some embodiments, in step S2, the following steps are included:
S201、底板施工:施工底板钢筋,在与扶壁结构结合部位设置预留插筋,浇筑底板混凝土;S201. Base plate construction: construct base plate steel bars, set reserved bars at the junction with the buttress structure, and pour base plate concrete;
S202、立壁施工:安装立壁结构的钢筋,在与扶壁结构结合部位设置预留勾筋,分层浇筑立壁混凝土至立壁结构顶部标高。S202. Standing wall construction: install steel bars for the standing wall structure, set reserved hook bars at the junction with the buttress structure, and pour concrete for the standing wall in layers to the top level of the standing wall structure.
在一些实施例中,在步骤S3中,包括以下步骤:In some embodiments, in step S3, the following steps are included:
S301、扶壁拼装:按照预留插筋和预留插筋孔的定位,将预制扶壁放在预留插筋上;S301. Buttress assembly: according to the positioning of the reserved ribs and the reserved rib holes, place the prefabricated buttress on the reserved ribs;
S302、模板安装:预制扶壁与立壁的结合部位安装模板;S302. Formwork installation: install the formwork at the junction of the prefabricated buttress and vertical wall;
S303、湿接缝现浇:分层浇筑与结构等级一致的细石混凝土,分层高度不大于0.5米,将混凝土振捣密实,浇筑至设计顶部标高,做好养护、拆模等工作;S303. Wet joint cast-in-place: pour fine stone concrete with the same grade as the structure in layers, and the height of the layer is not more than 0.5 meters. The concrete is vibrated and compacted, poured to the design top elevation, and maintenance, formwork removal, etc. are done well;
S304、灌浆加固:通过预制扶壁底部侧面预留的灌浆孔,注入水泥浆,使预制扶壁和底板相结合成一个整体。S304. Grouting reinforcement: inject cement slurry through the grouting hole reserved on the bottom side of the prefabricated buttress, so that the prefabricated buttress and the bottom plate are combined into a whole.
在一些实施例中,所述预留插筋的外侧浇筑有凸起台;In some embodiments, the outer side of the reserved rib is poured with a raised platform;
所述预制扶壁的下端设置有适配凸起台的槽口。The lower end of the prefabricated buttress is provided with a notch adapted to the raised platform.
在一些实施例中,在步骤S3中,还包括浇筑加强柱;In some embodiments, in step S3, pouring reinforcement columns is also included;
在步骤S302中,预制扶壁与立壁的结合部位安装模板;In step S302, a formwork is installed at the junction of the prefabricated buttress and the vertical wall;
在步骤S303中,与湿接缝一体浇筑加强柱。In step S303, the reinforcement column is poured integrally with the wet joint.
在一些实施例中,所述加强柱为包覆在湿接缝、预制扶壁外侧的方柱体或三角体。In some embodiments, the reinforcing column is a square column or a triangle covering the wet joint or the outside of the prefabricated buttress.
在一些实施例中,所述预制扶壁的端部设置有加强柱结合筋。In some embodiments, the ends of the prefabricated buttresses are provided with reinforcing column binding ribs.
与现有技术相比,本发明提供了一种半预制扶壁式挡土墙快速施工方法,具备以下有益效果。Compared with the prior art, the present invention provides a rapid construction method for semi-prefabricated buttress-type retaining walls, which has the following beneficial effects.
1、本发明,采用标准模块施工和异型模块施工相结合,现浇结构和预制构建相搭配,可加快工程进度、提高施工效率和工程质量,可减少人工、材料投入,减少对环境的污染。1. The present invention adopts the combination of standard module construction and special-shaped module construction, and the matching of cast-in-place structure and prefabricated construction, which can speed up the project progress, improve construction efficiency and project quality, reduce labor and material input, and reduce environmental pollution.
2、本发明,在工厂提前预制扶壁结构,避免现浇过程产生蜂窝、麻面、孔洞、漏筋等质量缺陷,既能保证混凝土的外观质量,又能满足强度要求;水平缝采用预留插筋灌浆加固,竖直方向采用预留钢筋浇筑砼标号细石混凝土的施工工艺,保证预制扶壁1的稳固;浇筑加强柱10使得立壁3与预制扶壁1充分结合,提供更大的支撑面。2. In the present invention, the buttress structure is prefabricated in the factory in advance to avoid quality defects such as honeycomb, pockmarked surface, holes, and missing bars during the cast-in-place process, which can not only ensure the appearance quality of the concrete, but also meet the strength requirements; the horizontal joints are reserved Reinforcing by inserting reinforcement and grouting, the vertical direction adopts the construction technology of reserved reinforced concrete and pouring concrete grade fine stone concrete to ensure the stability of the
本发明的其他优点、目标和特征,在某种程度上将在随后的说明书中进行阐述;并且在某种程度上,基于对下文的考察研究,对本领域技术人员而言将是显而易见的;或者,可以从本发明的实践中得到教导。Other advantages, objects and features of the present invention will be set forth in the following description to some extent; and will be obvious to those skilled in the art based on the investigation and research below to some extent; or , can be taught from the practice of the present invention.
附图说明Description of drawings
图1为现有技术的示意图。Figure 1 is a schematic diagram of the prior art.
图2为本发明的结构示意图。Fig. 2 is a structural schematic diagram of the present invention.
图3为浇筑湿接缝前的结构示意图。Figure 3 is a schematic diagram of the structure before pouring wet joints.
图4为浇筑湿接缝前的侧视结构示意图。Figure 4 is a schematic side view of the structure before pouring the wet joint.
图5为未安装预制扶壁状态的结构示意图。Fig. 5 is a schematic structural view of a state where prefabricated buttresses are not installed.
图6为预制扶壁的下侧结构示意图。Fig. 6 is a schematic diagram of the lower side structure of the prefabricated buttress.
图7为设置凸起台状态的结构示意图。Fig. 7 is a structural schematic diagram of the state where the raised platform is set.
图8为设置三角体加强柱转状态的结构示意图。Fig. 8 is a structural schematic diagram of the state of setting the triangular reinforced column in rotation.
图9为设置方柱体加强柱转状态的结构示意图。Fig. 9 is a structural schematic diagram of a state where a square column reinforcing column is set.
图10为浇筑加强柱前的结构示意图。Figure 10 is a schematic diagram of the structure before pouring the reinforcement column.
图11为图10中A处的放大结构示意图。FIG. 11 is a schematic diagram of an enlarged structure at point A in FIG. 10 .
图中:In the picture:
1、预制扶壁;2、底板;3、立壁;4、湿接缝;5、预留插筋;6、灌浆孔;7、预留勾筋;8、凸起台;9、槽口;10、加强柱;11、加强柱结合筋。1. Prefabricated buttresses; 2. Floors; 3. Standing walls; 4. Wet joints; 5. Reserved ribs; 6. Grouting holes; 7. Reserved hook ribs; 10. Strengthening column; 11. Strengthening column combined with ribs.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention.
如图1所示,传统的扶壁式挡土墙施工方法多为一体式现浇结构;包括底板、立壁、扶壁,都为现场一体浇筑。As shown in Figure 1, the traditional buttress-type retaining wall construction method is mostly an integral cast-in-place structure; including the bottom plate, vertical wall, and buttress, all are cast on site.
为了解决扶壁式挡土墙的扶壁结构现浇过程中钢筋绑扎、模板安装加固等施工工序占用工期时间长,以加快施工进度、缩短施工工期;同时,避免预制拼装工艺造成的结构整体稳定性不足等;本申请的整体思路为:将扶壁式挡土墙的扶壁部分与底板、立壁结构从整体现浇变为分先后施工;先施工扶壁式挡土墙的底板和立壁结构,再施工预制的扶壁结构,最终形成一个整体结构。In order to solve the construction process of steel bar binding, formwork installation and reinforcement in the cast-in-situ process of the buttress structure of the buttress retaining wall, it takes a long time to speed up the construction progress and shorten the construction period; at the same time, to avoid the overall stability of the structure caused by the prefabricated assembly process Insufficient performance, etc.; the overall idea of this application is: change the buttress part, bottom plate and vertical wall structure of the buttress retaining wall from integral cast-in-place construction to sequential construction; construct the bottom plate and vertical wall structure of the buttress retaining wall first , and then construct the prefabricated buttress structure, and finally form a whole structure.
实施例一。Embodiment one.
参照图2-5,一种半预制扶壁式挡土墙快速施工方法,包括以下步骤:With reference to Fig. 2-5, a kind of semi-prefabricated buttress type retaining wall rapid construction method comprises the following steps:
S1、工厂预制扶壁1;S1, factory prefabricated buttress 1;
S2、施工现场浇筑底板2、立壁3;S2, pouring
S3、安装预制扶壁1,浇筑预制扶壁1与立壁3之间的湿接缝4。S3. Install the prefabricated buttress 1 and pour the wet joint 4 between the prefabricated buttress 1 and the
其中,预制扶壁1的底部预留插筋孔;相应的,在底板2上设置与预制扶壁1对应的预留插筋5。Wherein, the bottom of the prefabricated buttress 1 is reserved for inserting ribs; correspondingly, the
优选的,预留插筋5的长度为15d,间距15~20厘米;其中,d为预留插筋5的直径。Preferably, the length of the
可以理解的是,预留插筋孔与底部预留插筋5的间距一致,深度不小于15d。It can be understood that the distance between the reserved rib insertion hole and the
进一步的,在预制扶壁1的侧面设置有与预留插筋孔联通的灌浆孔6;以使得,扶壁式挡墙的底板2和预制扶壁1用预留插筋5和灌浆加固的形式结合,保证稳固。Further, the side of the prefabricated buttress 1 is provided with a
具体的,在步骤S3中,用灌浆法施工;通过灌浆孔6注入水泥浆或其他化学灌浆材料,使预留插筋5和预制扶壁1相结合,以使底板2与预制扶壁1稳定连接。Specifically, in step S3, the grouting method is used for construction; cement slurry or other chemical grouting materials are injected through the
进一步的,在立壁3与预制扶壁1的结合面分别设置有预留勾筋7。Further, reserved
其中,预留勾筋7为L型。Wherein, the
扶壁式挡墙的现浇立壁3和预制扶壁1用预留勾筋7二次浇筑混凝土的湿接缝形式结合;立壁3与预制扶壁1之间采用立模浇筑同等级的细石混凝土。The cast-in-place
优选的,湿接缝4的宽度为20d,d为预留勾筋7的直径。Preferably, the width of the
可以理解的是,优选的,预留勾筋7与预留插筋5采用同规格的钢筋。It can be understood that, preferably, the reserved hook bars 7 and the reserved insert bars 5 are steel bars of the same specification.
优选的,预留勾筋7的水平段长度为15d,垂直段长度为5d。Preferably, the length of the horizontal section of the reserved
优选的,预留勾筋7设置有两排,竖向间距为15~20厘米。Preferably, the
可以理解的是,如图4所示;立壁3与预制扶壁1的预留勾筋7垂直段延伸方向相反;即,立壁3的预留勾筋7向下延伸,则预制扶壁1的预留勾筋7向上延伸。It can be understood that, as shown in Figure 4; the extension direction of the vertical section of the vertical section of the
在一些实施例中,在步骤S2中,包括以下步骤。In some embodiments, in step S2, the following steps are included.
S201、底板施工:S201. Floor construction:
施工扶壁式挡土墙的底板钢筋,在与扶壁结构结合部位设置预留插筋5,浇筑扶壁式挡土墙的底板混凝土至立壁结构上200~400mm,做好养护工作。For the bottom slab reinforcement of the buttress-type retaining wall, set the
优选的,浇筑底板混凝土300mm。Preferably, 300mm of bottom slab concrete is poured.
S202、立壁施工:S202. Standing wall construction:
安装立壁结构的钢筋,在与扶壁结构结合部位设置预留勾筋7;分层浇筑扶壁式挡土墙的立壁混凝土至立壁结构顶部标高,做好养护工作。Install the steel bars of the vertical wall structure, and set the reserved
在一些实施例中,在步骤S3中,包括以下步骤。In some embodiments, in step S3, the following steps are included.
S301、扶壁拼装:S301, buttress assembly:
按照预留插筋5和预留插筋孔的定位,将预制扶壁1放在预留插筋5上。Place the prefabricated buttress 1 on the
S302、模板安装:S302. Template installation:
预制扶壁1与立壁3的结合部位安装模板;保证拼缝密实、平整度符合规范要求,进行模板加固。Install formwork at the junction of prefabricated buttress 1 and
S303、湿接缝现浇:S303, cast-in-place wet joints:
分层浇筑与结构等级一致的细石混凝土,分层高度不大于0.5米;将混凝土振捣密实,浇筑至设计顶部标高,做好养护、拆模等工作。The fine stone concrete with the same grade as the structure is poured in layers, and the layer height is not more than 0.5 meters; the concrete is vibrated and compacted, poured to the design top elevation, and maintenance and formwork removal are done well.
S304、灌浆加固:S304. Grouting reinforcement:
通过预制扶壁1底部侧面预留的灌浆孔6,注入水泥浆或其他化学灌浆材料,使预制扶壁1和底板2相结合成一个整体。Through the
本申请的目的是减少大规模扶壁式挡土墙施工工期,提高施工效率和工程质量,解决施工产值与施工效率不匹配问题。其既能提高施工效率,又能保证结构的稳定性。The purpose of this application is to reduce the construction period of large-scale buttress-type retaining walls, improve construction efficiency and project quality, and solve the problem of mismatch between construction output value and construction efficiency. It can not only improve the construction efficiency, but also ensure the stability of the structure.
具体表现在以下方面。Specifically in the following aspects.
(1)优化施工工艺:(1) Optimizing the construction process:
在施工现场浇筑扶壁式挡土墙的底板和立壁结构,在工厂提前预制扶壁结构;待扶壁式挡土墙底板和立壁施工完成后,再将扶壁与其连接成一个整体;水平缝采用预留插筋灌浆加固,竖直方向采用预留钢筋浇筑砼标号细石混凝土的施工工艺。The bottom plate and vertical wall structure of the buttress-type retaining wall are poured at the construction site, and the buttress structure is prefabricated in the factory; after the construction of the bottom plate and vertical wall of the buttress-type retaining wall is completed, the buttress is connected with it as a whole; horizontal joints Grouting with reserved reinforcement is used for reinforcement, and the construction technology of pouring concrete grade fine stone concrete with reserved reinforcement is used in the vertical direction.
(2)加快施工进度:(2) Speed up the construction progress:
由于扶壁式挡土墙为薄壁式钢筋混凝土结构,扶壁为异型结构,在钢筋安装、模板安装加固过程中占用工期长,施工效率底,施工产值与施工效率不匹配。将扶壁结构在工厂内提前预制,待扶壁式挡土墙底板和立壁施工完成后,再将扶壁与其连接成一个整体,则可加快施工进度。Since the buttress-type retaining wall is a thin-walled reinforced concrete structure, and the buttress is a special-shaped structure, it takes a long time in the process of steel bar installation and formwork installation and reinforcement, and the construction efficiency is low, and the construction output value does not match the construction efficiency. The buttress structure is prefabricated in the factory in advance, and after the construction of the buttress-type retaining wall bottom plate and vertical wall is completed, the buttress is connected with it as a whole, which can speed up the construction progress.
(3)保证施工质量:(3) Guarantee the construction quality:
扶壁式挡墙的扶壁顶部为斜面,在现浇过程中由于顶部振捣不到位及气体无法及时排放,容易产生蜂窝、麻面、孔洞、漏筋等质量缺陷。在工厂提前预制扶壁结构,则可避免上述质量缺陷的产生,既能保证混凝土的外观质量,又能满足强度要求。The top of the buttress of the buttress-type retaining wall is inclined. During the cast-in-place process, quality defects such as honeycombs, pockmarks, holes, and missing ribs are prone to occur due to insufficient vibration of the top and inability to discharge gas in time. Prefabricating the buttress structure in the factory in advance can avoid the above-mentioned quality defects, which can not only ensure the appearance quality of the concrete, but also meet the strength requirements.
实施例二。Embodiment two.
参照图6-7,与上述实施例不同的是:With reference to Figure 6-7, the difference from the above-mentioned embodiment is:
在预留插筋5的外侧浇筑有凸起台8;相应的,在预制扶壁1的下端设置有适配凸起台8的槽口9。A protruding
通过搭配的凸起台8、槽口9,增加了预制扶壁1与底板2的连接面,可增强稳固性。The connection surface between the prefabricated buttress 1 and the
进一步的,槽口9的内端贯穿至湿接缝4。Further, the inner end of the
在现场浇筑湿接缝4时,部分混凝土可进入槽口9内进行充填,增强连接。When the
可以理解的是,凸起台8与底板2一体浇筑成型。It can be understood that the raised
优选的,底板2设置为向上收缩的凸台结构。Preferably, the
实施例三。Embodiment three.
参照图8-11,与上述实施例不同的是:Referring to Figures 8-11, the difference from the above-mentioned embodiment is:
在步骤S3中,还包括浇筑加强柱10。In step S3, pouring of
具体的:specific:
在步骤S302中,预制扶壁1与立壁3的结合部位安装模板;In step S302, a formwork is installed at the junction of the prefabricated buttress 1 and the
在步骤S303中,与湿接缝一体浇筑加强柱10。In step S303, the reinforcing
可以理解的是,在前述实施例中,模板安装后构成与预制扶壁1厚度一致的内腔结构;在本实施例中,则增大模板的内腔空间,以形成包覆形态的立柱。It can be understood that, in the foregoing embodiments, the formwork is installed to form an inner cavity structure consistent with the thickness of the prefabricated buttress 1; in this embodiment, the inner cavity space of the formwork is increased to form a covered column.
如图8、9所示;加强柱10为包覆在湿接缝4、预制扶壁1外侧的方柱体或三角体。As shown in Figures 8 and 9 ; the
可以理解的是,结合部位是受力薄弱区域,通过设置的加强柱10现场浇筑,使得立壁3与预制扶壁1充分结合;同时,包覆的外部结构,增加了与立壁3的接触面积,提供更大的支撑面,效果更佳。It can be understood that the joint part is a weak force-bearing area, and the
此外,在选择设置为三角体形态的加强柱10时,每侧仅需设置一块模板,可进一步加快施工速度。In addition, when the reinforced
进一步的,在预制扶壁1的端部设置有加强柱结合筋11,以充分保证与现浇加强柱10的结合。Further, reinforcing
可以理解的是,同样的可在立壁3上预留适配加强柱10的加强柱结合筋11。It can be understood that, similarly, the reinforcement column
本发明中,采用半预制的施工方法,与现有常规的整体现浇法和整体预制拼装法相比,可以达到如下的效果。In the present invention, the semi-prefabricated construction method is adopted, compared with the existing conventional integral cast-in-place method and integral prefabricated assembly method, the following effects can be achieved.
(1)加快进度,缩短工期;(1) Speed up the progress and shorten the construction period;
扶壁式挡墙的底板和立壁为常规的标准结构,施工快,扶壁为异性结构,施工效率底;将二者分开施工,前者现浇、后者预制拼装,则可加快施工进度。The bottom plate and the vertical wall of the buttress retaining wall are conventional standard structures, and the construction is fast, while the buttresses are heterogeneous structures, and the construction efficiency is low; the two are separately constructed, the former is cast-in-situ, and the latter is prefabricated and assembled, which can speed up the construction progress.
(2)保证工程实体质量;(2) Guarantee the quality of the project entity;
对比现浇结构,预制扶壁结构的混凝土外观质量和强度等级更优。Compared with the cast-in-place structure, the concrete appearance quality and strength grade of the prefabricated buttress structure are better.
(3)结构整体受力性能好;(3) The overall mechanical performance of the structure is good;
整体预制拼装的结构,在结合部位是受力薄弱部位,半预制的立壁与扶壁结合部位采用现浇方法,相比螺栓拼装连接受力性能更好。The overall prefabricated and assembled structure has a weak force-bearing part at the joint part, and the semi-prefabricated vertical wall and buttress joint adopts the cast-in-place method, which has better mechanical performance than the bolted joint.
(4)减少模板用量,提高周转材料的利用率。(4) Reduce the amount of formwork and improve the utilization rate of turnover materials.
本发明中,采用标准模块施工和异型模块施工相结合,现浇结构和预制构建相搭配,可加快工程进度,可减少人工、材料投入,减少对环境的污染,具有一定的推广应用价值。In the present invention, the combination of standard module construction and special-shaped module construction is adopted, and the cast-in-place structure is matched with prefabricated construction, which can speed up the project progress, reduce labor and material input, and reduce environmental pollution, which has certain promotion and application value.
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, any person familiar with the technical field within the technical scope disclosed in the present invention, according to the technical solution of the present invention Any equivalent replacement or change of the inventive concepts thereof shall fall within the protection scope of the present invention.
在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不必须针对的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任一个或多个实施例或示例中以合适的方式结合。此外,在不相互矛盾的情况下,本领域的技术人员可以将本说明书中描述的不同实施例或示例以及不同实施例或示例的特征进行结合和组合。In the description of this specification, descriptions referring to the terms "one embodiment", "some embodiments", "example", "specific examples", or "some examples" mean that specific features described in connection with the embodiment or example , structure, material or feature is included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms are not necessarily directed to the same embodiment or example. Furthermore, the described specific features, structures, materials or characteristics may be combined in any suitable manner in any one or more embodiments or examples. In addition, those skilled in the art can combine and combine different embodiments or examples and features of different embodiments or examples described in this specification without conflicting with each other.
尽管上面已经示出和描述了本发明的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本发明的限制,本领域的普通技术人员在本发明的范围内可以对上述实施例进行变化、修改、替换和变型。Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are exemplary and should not be construed as limiting the present invention, those skilled in the art can make the above-mentioned The embodiments are subject to changes, modifications, substitutions and variations.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310359930.5A CN116145721A (en) | 2023-04-06 | 2023-04-06 | A rapid construction method of semi-prefabricated buttress retaining wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310359930.5A CN116145721A (en) | 2023-04-06 | 2023-04-06 | A rapid construction method of semi-prefabricated buttress retaining wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116145721A true CN116145721A (en) | 2023-05-23 |
Family
ID=86360311
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310359930.5A Pending CN116145721A (en) | 2023-04-06 | 2023-04-06 | A rapid construction method of semi-prefabricated buttress retaining wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116145721A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN119801033A (en) * | 2025-01-10 | 2025-04-11 | 中国五冶集团有限公司 | A method for constructing a prefabricated formwork buttress structure for basements and long strip foundations |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2830028A1 (en) * | 2001-09-27 | 2003-03-28 | Chapsol | Inverted T-shaped prefabricated component for retaining wall has apertures through lower ends of buttresses for reinforcing elements |
| CN107338808A (en) * | 2017-07-18 | 2017-11-10 | 中交第三航务工程勘察设计院有限公司 | Arch form counterfort vertical type soil-baffling structure |
| CN110241847A (en) * | 2018-03-09 | 2019-09-17 | 韦随庆 | It is a kind of ecology cantilevered and buttress type assemble retaining wall |
| CN209907429U (en) * | 2019-03-27 | 2020-01-07 | 安徽省交通规划设计研究总院股份有限公司 | Industrialized dense rib plate type retaining wall |
| CN111236302A (en) * | 2020-03-09 | 2020-06-05 | 上海市城市建设设计研究总院(集团)有限公司 | Assembled structure and construction method of prefabricated buttress type retaining wall |
| CN212129215U (en) * | 2020-03-11 | 2020-12-11 | 王雅 | Counterfort type retaining wall capable of being constructed quickly |
-
2023
- 2023-04-06 CN CN202310359930.5A patent/CN116145721A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2830028A1 (en) * | 2001-09-27 | 2003-03-28 | Chapsol | Inverted T-shaped prefabricated component for retaining wall has apertures through lower ends of buttresses for reinforcing elements |
| CN107338808A (en) * | 2017-07-18 | 2017-11-10 | 中交第三航务工程勘察设计院有限公司 | Arch form counterfort vertical type soil-baffling structure |
| CN110241847A (en) * | 2018-03-09 | 2019-09-17 | 韦随庆 | It is a kind of ecology cantilevered and buttress type assemble retaining wall |
| CN209907429U (en) * | 2019-03-27 | 2020-01-07 | 安徽省交通规划设计研究总院股份有限公司 | Industrialized dense rib plate type retaining wall |
| CN111236302A (en) * | 2020-03-09 | 2020-06-05 | 上海市城市建设设计研究总院(集团)有限公司 | Assembled structure and construction method of prefabricated buttress type retaining wall |
| CN212129215U (en) * | 2020-03-11 | 2020-12-11 | 王雅 | Counterfort type retaining wall capable of being constructed quickly |
Non-Patent Citations (2)
| Title |
|---|
| 徐健;刘泽;黄天棋;陈丽;: "装配式挡土墙设计与施工的关键问题研究", 城市建设理论研究(电子版), no. 06, 25 February 2018 (2018-02-25) * |
| 蒋建;: "预制装配式挡土墙施工关键技术探究", 湖南水利水电, no. 02, 20 March 2020 (2020-03-20), pages 2 - 3 * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN119801033A (en) * | 2025-01-10 | 2025-04-11 | 中国五冶集团有限公司 | A method for constructing a prefabricated formwork buttress structure for basements and long strip foundations |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100445488C (en) | A cavity component for cast-in-place concrete molding | |
| CN102296837B (en) | Multi-storey building with prefabricated parts and its semi-prefabricated construction method | |
| CN206545215U (en) | A kind of precast spliced sinking type garage parking | |
| CN211114066U (en) | Assembled lightweight concrete slab type house structure | |
| CN208023601U (en) | A kind of prefabricated pile foundation support table side form of mutual buckle type | |
| CN116240987A (en) | A post-cast prefabricated protective wall and its construction method | |
| CN116290075B (en) | Back wall of jacking pipe capable of being used in turnover mode and construction process of back wall | |
| CN116145721A (en) | A rapid construction method of semi-prefabricated buttress retaining wall | |
| CN113323262A (en) | 3D printed prefabricated wall module, wall and construction method of wall | |
| CN110886311A (en) | Large-volume assembly type ground tire mold | |
| CN216809966U (en) | Foundation cushion cap side form construction structures in foundation ditch | |
| CN210369335U (en) | Assembled integrated house structure | |
| CN210421568U (en) | Assembled beam and plate structure | |
| CN109881699B (en) | Fabrication and installation method of concrete tire mold for prefabricated tongue and groove Miller type universal raft foundation | |
| CN111851804A (en) | A prefabricated formwork-free structural body formwork and a cast-in-place formwork-free structural body | |
| US20240209625A1 (en) | Method for preparing concrete-filled steel tubular edge-constrained laminated shear wall | |
| CN207110035U (en) | Assembled steel tendon concrete frame structure based on steel plate connection joint | |
| CN216194868U (en) | PC brick fetal membrane structure | |
| CN116265671A (en) | Thermal insulation prefabricated wall panel and construction method for using the thermal insulation prefabricated wall panel to construct a wall | |
| CN212835365U (en) | Construction structure of PHC tubular pile | |
| CN111535339B (en) | Construction process of concrete dam body of refuse landfill | |
| CN212452765U (en) | A two-wall-integrated underground pipe gallery structure | |
| CN211499159U (en) | An energy-saving and stable building structure | |
| CN105951980B (en) | Concrete modular splicing frame building structure | |
| CN216765909U (en) | Prefabricated plate structure and prefabricated plate integrated configuration |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |