CN116122656A - Chimney verticality control and deviation correction construction method - Google Patents

Chimney verticality control and deviation correction construction method Download PDF

Info

Publication number
CN116122656A
CN116122656A CN202211706643.9A CN202211706643A CN116122656A CN 116122656 A CN116122656 A CN 116122656A CN 202211706643 A CN202211706643 A CN 202211706643A CN 116122656 A CN116122656 A CN 116122656A
Authority
CN
China
Prior art keywords
chimney
center
construction method
steps
deviation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211706643.9A
Other languages
Chinese (zh)
Inventor
王玉
张彬
郭少东
周雄
刘建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN202211706643.9A priority Critical patent/CN116122656A/en
Publication of CN116122656A publication Critical patent/CN116122656A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/341Arrangements for casting in situ concrete towers or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/28Chimney stacks, e.g. free-standing, or similar ducts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a chimney verticality control and deviation correction construction method, which comprises the following steps: s1: determining a basic center point of the chimney body; s2: determining and checking the central position of the chimney body; s3: centering, checking and positioning of chimney body steel bars and an outer template; s4: correcting: and (3) determining a center deviation direction according to a chimney shaft bottom measurement result, increasing lifting times for 5-10 hydraulic jacks in the center deviation direction, and closing needle valves of other hydraulic jacks at the same time, so that one side of an operation platform is intentionally improved to correct the center. The method is visual, clear and concise, and only after the lifting process and jacking in place, the relative position coincidence of the center of the plumb and the center reference object at the bottom of the chimney is observed at any time, so that the whole operation platform is proved to be parallel to the ground, and no front-back left-right offset occurs.

Description

Chimney verticality control and deviation correction construction method
Technical Field
The invention relates to the technical field of building construction, in particular to a chimney verticality control and deviation correction construction method.
Background
The chimney is gradually raised, so that the verticality control and correction are important, and at present, the control technology adopted for the verticality control and correction of the chimney is monitored by a multi-directional total station from the outside of the chimney. The multi-azimuth observation is needed, the measuring instrument is easy to receive, the technical level and the environmental influence of measuring staff are not intuitive, the adjustment is not rapid, and the correction difficulty is high.
Disclosure of Invention
In view of the above, the invention provides a chimney verticality control and deviation rectifying construction method, which is regulated by a local hydraulic device on the same side as the eccentric, and has the advantages of simple operation and outstanding effect.
The invention provides a chimney verticality control and deviation correction construction method, which adopts the following technical scheme:
a chimney verticality control and deviation correction construction method comprises the following steps:
s1: determining a basic center point of the chimney body: welding the central point of the foundation slab to +0.10m by using a detection part, measuring that the central point of the chimney shaft coincides with the coordinate point of the chimney shaft, and sawing a cross wire on the upper surface of the detection part by using a hacksaw blade;
s2: determining and checking the central position of the chimney body barrel: firstly, lifting a lifting cage at the center of a platform well frame to be higher than an operation platform by using a winch, determining the center point position of a chimney shaft through angle steel measurement, marking the center point position on the chimney shaft, and then hanging down a heavy weight by adopting a thin steel wire rope to align with a foundation center point;
s3: chimney body steel bar and outer template centering inspection and positioning: each 1.50m section of cylinder body construction steel bar is installed, centered, inspected and positioned, so that the center point position of the upper cylinder wall is determined, then the radius size of a template at the position of the cylinder body is measured to install the template, centering, inspecting and positioning are carried out on an outer template, centering and rechecking of an outer mold, steel bars, embedded parts and an inner template are carried out before concrete pouring, and recording is carried out;
s4: correcting: and (3) determining a center deviation direction according to a chimney shaft bottom measurement result, increasing lifting times for 5-10 hydraulic jacks in the center deviation direction, and closing needle valves of other hydraulic jacks at the same time, so that one side of an operation platform is intentionally improved to correct the center.
Optionally, the center point of the foundation base plate is determined according to the central line of the chimney body.
Optionally, the detecting member is made of Φ25 deformed steel bar.
Optionally, 200mm terrace C20 concrete in the chimney body is poured for stabilization.
Optionally, a wind shield is additionally arranged at the door and window opening of the chimney body.
Optionally, in step S4, the jack is leveled every 1800mm of calibration center and every 300mm of lifting.
Alternatively, the support rods of the operating platform are steel tubes of phi 48 x 3.5.
Optionally, the portal frame and the radiation beam on the operation platform adopt four-side rigid diagonal rods.
Optionally, after the step S5, the center verticality of the chimney body needs to be rechecked and controlled, when the center verticality of the chimney body is rechecked and controlled, a theodolite is adopted to recheck every 20m of ascending height of the cylinder construction, the theodolite is arranged at a point (the other point forms 90 degrees with the point) outside the 20m of the chimney body, the theodolite is well adjusted to measure two cross directions of the verticality of the chimney body, the center deviation condition of the cylinder is checked, and detailed records are well made.
Optionally, in step S4, the operation platform is an inclined plane in the deviation rectifying process.
In summary, the beneficial technical effects of the invention are as follows: the vertical correction device is visual, clear and concise, and only needs to observe the coincidence of the relative positions of the center of the plumb and the center reference object at the bottom of the chimney at any time after the lifting process and the jacking in place, so that the whole operation platform is proved to be parallel to the ground, and the front, back, left and right deflection does not occur, so that the chimney taking the operation platform as the reference is ensured to be vertical upwards, the verticality is controlled, the same reason is that even if the deflection occurs, the hydraulic jack is regulated by gradually sectioning and grouping at the same side of the deflection, and the correction can be effectively performed.
Drawings
FIG. 1 is a schematic illustration of a correction of an embodiment of the present invention.
Reference numerals illustrate: 1. and (5) operating the platform.
Detailed Description
The present invention will be described in further detail with reference to fig. 1.
The embodiment of the invention discloses a chimney verticality control and deviation correction construction method.
Referring to fig. 1, a method for controlling verticality and correcting deviation of a chimney includes the following steps:
s1: determining a basic center point of the chimney body: welding the central point of the foundation slab to +0.10m by using a detection part, measuring that the central point of the chimney shaft coincides with the coordinate point of the chimney shaft, and sawing a cross wire on the upper surface of the detection part by using a hacksaw blade;
s2: determining and checking the central position of the chimney body barrel: firstly, lifting a lifting cage at the center of a platform well frame to be higher than an operation platform by using a winch, determining the center point position of a chimney shaft through angle steel measurement, marking the center point position on the chimney shaft, and then hanging down a heavy weight by adopting a thin steel wire rope to align with a foundation center point;
s3: chimney body steel bar and outer template centering inspection and positioning: each 1.50m section of cylinder body construction steel bar is installed, centered, inspected and positioned, so that the center point position of the upper cylinder wall is determined, then the radius size of a template at the position of the cylinder body is measured to install the template, centering, inspecting and positioning are carried out on an outer template, centering and rechecking of an outer mold, steel bars, embedded parts and an inner template are carried out before concrete pouring, and recording is carried out;
s4: correcting: and (3) determining a center deviation direction according to a chimney shaft bottom measurement result, increasing lifting times for 5-10 hydraulic jacks in the center deviation direction, and closing needle valves of other hydraulic jacks at the same time, so that one side of an operation platform is intentionally improved to correct the center.
In the embodiment, the center point of the foundation base plate is determined according to the central line of the chimney shaft.
In this embodiment, the sensing element is implemented using Φ25 deformed steel bar. In the S1 step, phi 25 screw steel is welded to +0.10m, the central point of the chimney shaft is measured to be identical with the coordinate point of the chimney shaft, then 200mm terrace C20 concrete in the chimney shaft is poured to stabilize, and then a cross wire is sawn on the upper surface of the screw steel head by a steel saw blade.
In the embodiment, the angle steel is 2000mm long and 63 multiplied by 6, the position of the central point of the chimney shaft is determined by measurement and marked on the angle steel, and then a 20kg heavy weight is hung down by adopting a 5mm thin steel wire rope to be aligned with the central point of the foundation.
In the step S3, each 1.50m section of the drum body construction steel bar is installed, centered, inspected and positioned, thereby determining the center point position of the upper drum wall, namely the center point position of the correction template,
a wind shield is additionally arranged at the door and window opening of the chimney body.
Because the load distribution on the operation platform is uneven in the construction process, the concrete pouring is asymmetric, the diameter adjustment is not performed symmetrically, the operation platform can be displaced due to factors such as wind direction and wind force, the center of the lifting platform is easy to deviate due to the large wind force, and therefore the rigidity of the supporting rod of the operation platform is a key for preventing the center deviation phenomenon. Thus, the support rods of the operating platform are of Φ48×3.5 steel pipe. The upper door frame and the radiation beam of the operation platform adopt four-side rigid diagonal rods so as to improve the rigidity of the operation platform and prevent center deviation.
In step S4, the inclination of each deviation correction should not exceed 1/200 of the platform span. In the correction process, the platform is required to be in an inclined plane, and a folding plane cannot be generated. Larger deviations need to be corrected step by step and cannot be corrected once. Once every 1800mm of correction center, the jack is leveled every 300mm of lifting, and the general deviation value should not exceed 10mm, otherwise, the correction is needed once.
In the step S4, the operating platform in the deviation correcting process is in an inclined plane, and a folded surface state cannot be generated at the derrick. When the center deviation occurs, the correction is needed in time, and the correction is started when the common deviation value is not more than 10mm, so that the center deviation is prevented from being too large and difficult to correct.
After the step S5 is adjusted, the center verticality of the chimney body is required to be rechecked and controlled, when the center verticality of the chimney body is rechecked and controlled, a theodolite is adopted to recheck every 20m of rising height of the cylinder body construction, the theodolite is arranged at a point (the other point forms 90 degrees with the point) outside the chimney body 20m, the theodolite is well adjusted to measure two cross directions of the vertical degree of the chimney body, the center deviation condition of the cylinder body is checked, and detailed records are well made.
Is visual, clear and concise. As long as the relative positions of the center of the plumb and the center reference object at the bottom of the chimney are observed to coincide at any time after the lifting process and the jacking in place, the whole operation platform is proved to be parallel to the ground, and no front-back left-right offset occurs, so that the chimney taking the operation platform as a reference is ensured to be vertical upwards, and the verticality is controlled. In the same way, even if the deviation occurs, the hydraulic jack is adjusted by gradually dividing and grouping on the same side of the deviation, so that the deviation can be effectively corrected.
The above embodiments are not intended to limit the scope of the present invention, so: all equivalent changes in structure, shape and principle of the invention should be covered in the scope of protection of the invention.

Claims (10)

1. A chimney verticality control and deviation rectifying construction method is characterized in that: the method comprises the following steps:
s1: determining a basic center point of the chimney body: welding the central point of the foundation slab to +0.10m by using a detection part, measuring that the central point of the chimney shaft coincides with the coordinate point of the chimney shaft, and sawing a cross wire on the upper surface of the detection part by using a hacksaw blade;
s2: determining and checking the central position of the chimney body barrel: firstly, lifting a lifting cage at the center of a platform well frame to be higher than an operation platform by using a winch, determining the center point position of a chimney shaft through angle steel measurement, marking the center point position on the chimney shaft, and then hanging down a heavy weight by adopting a thin steel wire rope to align with a foundation center point;
s3: chimney body steel bar and outer template centering inspection and positioning: each 1.50m section of cylinder body construction steel bar is installed, centered, inspected and positioned, so that the center point position of the upper cylinder wall is determined, then the radius size of a template at the position of the cylinder body is measured to install the template, centering, inspecting and positioning are carried out on an outer template, centering and rechecking of an outer mold, steel bars, embedded parts and an inner template are carried out before concrete pouring, and recording is carried out;
s4: correcting: and (3) determining a center deviation direction according to a chimney shaft bottom measurement result, increasing lifting times for 5-10 hydraulic jacks in the center deviation direction, and closing needle valves of other hydraulic jacks at the same time, so that one side of an operation platform is intentionally improved to correct the center.
2. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: the central point of the foundation base plate is determined according to the central line of the chimney body.
3. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: the detection part adopts phi 25 screw steel.
4. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: and pouring concrete of a terrace C20 with the thickness of 200mm in the chimney body for stabilizing.
5. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: a wind shield is additionally arranged at the door and window opening of the chimney body.
6. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: in the step S4, the jack is leveled every 1800mm of calibration center and every 300mm of lifting.
7. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: the supporting rod of the operating platform adopts phi 48 multiplied by 3.5 steel pipes.
8. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: the upper door frame of the operation platform and the radiation beam adopt four-side rigid diagonal rods.
9. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: after the step S5 is adjusted, the center verticality of the chimney body is required to be rechecked and controlled, when the center verticality of the chimney body is rechecked and controlled, a theodolite is adopted to recheck every 20m of rising height of the cylinder body construction, the theodolite is arranged at a point (the other point forms 90 degrees with the point) outside the chimney body 20m, the theodolite is well adjusted to measure two cross directions of the vertical degree of the chimney body, the center deviation condition of the cylinder body is checked, and detailed records are well made.
10. The chimney verticality control and deviation rectification construction method according to claim 1, wherein the method comprises the following steps: in the step S4, the operation platform is in an inclined plane in the correction process.
CN202211706643.9A 2022-12-29 2022-12-29 Chimney verticality control and deviation correction construction method Pending CN116122656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211706643.9A CN116122656A (en) 2022-12-29 2022-12-29 Chimney verticality control and deviation correction construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211706643.9A CN116122656A (en) 2022-12-29 2022-12-29 Chimney verticality control and deviation correction construction method

Publications (1)

Publication Number Publication Date
CN116122656A true CN116122656A (en) 2023-05-16

Family

ID=86293898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211706643.9A Pending CN116122656A (en) 2022-12-29 2022-12-29 Chimney verticality control and deviation correction construction method

Country Status (1)

Country Link
CN (1) CN116122656A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118881154A (en) * 2024-08-07 2024-11-01 中国二十二冶集团有限公司 Method for controlling vertical deviation of silo wall in slipform construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118881154A (en) * 2024-08-07 2024-11-01 中国二十二冶集团有限公司 Method for controlling vertical deviation of silo wall in slipform construction

Similar Documents

Publication Publication Date Title
CN111236217B (en) A device and method for positioning the elevation and centering of a pile foundation steel cage
CN210766774U (en) A positioning device for reinforcement cage and lattice column
CN113605390B (en) Accurate positioning structure for pile connection and construction method
CN110219326B (en) Reverse construction method one-column one-pile underwater verticality adjusting construction process
CN104328799A (en) Accurate positioning method for steel pipe column in cover and cut top-down subway station
CN205718762U (en) A kind of stake holes measuring instrument
CN105525625A (en) Construction method and device of pre-embedded bolts of fixed steel column base
CN216283541U (en) Quick and accurate measuring device for verticality in mounting of assembled building column
US7530176B2 (en) Method and apparatus for monitoring element alignment
CN113293869A (en) Construction method for rear insertion of steel upright post
CN102493471A (en) Suspending installation construction process method of structural foot margin anchor bolt
CN116122656A (en) Chimney verticality control and deviation correction construction method
CN111663525A (en) Method for controlling perpendicularity of pile body of cement mixing pile
CN112663613A (en) Verticality control device and verticality control method for latticed column
CN105569351A (en) Mounting construction technology of steel structure steel column
CN116592838A (en) Underground component lowering installation verticality measuring and monitoring method
CN106639500A (en) One-time slip-form construction method for square variable-section multi-layer platform chimney under high air pressure
CN212077907U (en) A kind of pile foundation reinforcement cage elevation and centering positioning device
CN109680970B (en) Correction method for verticality of steel column
CN219195930U (en) Steel reinforcement cage holding ring
CN217027064U (en) A long protective tube installation verticality positioning detection device
CN218933239U (en) A verticality controller for tower crane high pile cap level meter column foundation
CN114703834A (en) Lattice column hoisting precision control construction method
CN206346201U (en) A kind of sand control alignment system for being used to lay lattice column
CN214116620U (en) Adjustable support for accurate positioning of permanent double-steel-pipe column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination