CN116101881A - Counterweight Hoisting Method of Adjustable Combined Balance Beam for Crane - Google Patents
Counterweight Hoisting Method of Adjustable Combined Balance Beam for Crane Download PDFInfo
- Publication number
- CN116101881A CN116101881A CN202310147311.XA CN202310147311A CN116101881A CN 116101881 A CN116101881 A CN 116101881A CN 202310147311 A CN202310147311 A CN 202310147311A CN 116101881 A CN116101881 A CN 116101881A
- Authority
- CN
- China
- Prior art keywords
- balance beam
- main
- counterweight
- hook
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/22—Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16B—DEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
- F16B7/00—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections
- F16B7/10—Telescoping systems
- F16B7/14—Telescoping systems locking in intermediate non-discrete positions
- F16B7/1472—Telescoping systems locking in intermediate non-discrete positions with a clamping screw perpendicular to the axis of the telescoping members
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16B—DEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
- F16B7/00—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections
- F16B7/18—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements
- F16B7/182—Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements for coaxial connections of two rods or tubes
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Jib Cranes (AREA)
Abstract
Description
技术领域technical field
本发明涉及天车吊装技术领域,尤其涉及一种天车用可调组合式平衡梁的配重吊装方法。The invention relates to the technical field of crane hoisting, in particular to a counterweight hoisting method of an adjustable combined balance beam for a crane.
背景技术Background technique
在工业厂房内进行安装工程和生产检修工作时,总会有一部分设备的位置设计在天车走行轨道(厂房吊车梁)的正下方,例如大部分的车间管线主管路处于吊车梁正下方,沿着吊车梁长度方向进行布置。这种情况下超过了天车钩头的走行极限位置,进行设备和管道吊装时,天车无法直接吊装到位,多数时候使用汽车吊或履带吊吊装,大幅度增加了施工费用。When carrying out installation engineering and production maintenance work in industrial plants, there will always be some equipment located directly below the running track of the crane (plant crane beam). Arrange along the length direction of the crane girder. In this case, the travel limit position of the crane coupler head is exceeded, and the crane cannot be directly hoisted in place when hoisting equipment and pipelines. Most of the time, truck cranes or crawler cranes are used for hoisting, which greatly increases the construction cost.
即使采用天车吊装,也必须制作平衡梁,并采用配重的方法来实现吊装。在这种方式中,难以根据不同重量的吊件对配重进行更换或调节。并且一般只设计和准备一根平衡梁,天车钩头的小车方向走行极限位置是固定的,平衡梁其固定的长度也难以适应不同远近的吊件,其固定的结构和截面决定了其最大起重量也是固定的。因此,吊装过程存在诸多困难,当项目工程中设备、管道数量多,重量、位置差别大时,这些缺点尤为突出。Even if cranes are used for hoisting, balance beams must be made and counterweights must be used to achieve hoisting. In this way, it is difficult to replace or adjust the counterweight according to different weights of hangers. And generally only one balance beam is designed and prepared. The traveling limit position of the crane coupler head in the direction of the trolley is fixed, and the fixed length of the balance beam is also difficult to adapt to different hanging parts. The weight is also fixed. Therefore, there are many difficulties in the hoisting process, especially when the number of equipment and pipelines in the project is large, and the differences in weight and position are large.
发明内容Contents of the invention
有鉴于此,本发明的目的在于提出一种天车用可调组合式平衡梁的配重吊装方法,以解决上述问题。In view of this, the object of the present invention is to propose a counterweight hoisting method for an adjustable combined balance beam for a crane to solve the above problems.
基于上述目的,本发明提供了一种天车用可调组合式平衡梁的配重吊装方法,按以下步骤进行:Based on the above purpose, the present invention provides a counterweight hoisting method for an adjustable combined balance beam for a crane, which is carried out according to the following steps:
S1、制作主梁和副梁,在主梁下表面的两端分别焊接吊耳。S1. Make the main girder and the auxiliary girder, and weld lifting lugs at both ends of the lower surface of the main girder.
S2、将主梁和副梁组合固定成平衡梁。S2. Combining the main beam and the auxiliary beam to form a balance beam.
S3、确定天车类型,当天车的主钩为龙门吊钩组时,先用龙门吊钩组将配重吊起,再用天车的副钩将平衡梁吊起,将平衡梁一端穿入龙门吊钩组横梁正下方,并将平衡梁上靠近配重一端的吊耳与配重连接,再将另一个吊耳与吊件连接,进行吊装;当天车的主钩和副钩均为普通单吊钩时,先用主钩和副钩将平衡梁吊起,再将配重连接在平衡梁的一个吊耳上,将吊件连接在另一个吊耳上,进行吊装。S3. Determine the type of the crane. When the main hook of the crane is the gantry hook set, first use the gantry hook set to lift the counterweight, then use the auxiliary hook of the crane to lift the balance beam, and put one end of the balance beam into the gantry hook Just below the group beam, connect the lifting lug on the balance beam near the counterweight to the counterweight, and then connect the other lifting lug to the hanging piece for hoisting; the main hook and auxiliary hook of the day car are ordinary single hooks When using the balance beam, first use the main hook and the auxiliary hook to lift the balance beam, then connect the counterweight to one lug of the balance beam, and connect the hanger to the other lug for hoisting.
与现有技术相比,本发明的有益效果在于:Compared with prior art, the beneficial effect of the present invention is:
1、采用龙门钩或普通吊钩作为配重吊钩,承担了平衡吊件后剩余的配重重量,因此不会额外增加吊件一侧的吊钩荷载,实现了自动分配用于吊装平衡的配重重量;1. The gantry hook or ordinary hook is used as the counterweight hook, which bears the remaining counterweight weight after balancing the hoist, so it will not increase the hook load on the side of the hoist, and realizes the automatic distribution of hoisting balance. counterweight weight;
2、本发明增强了平衡梁平衡动荷载的能力,解决了配重难于更换或调节的问题,因此适应较大范围内不同重量的吊件吊装,并且具有更高的安全性,有效降低倾覆风险。2. The present invention enhances the ability of the balance beam to balance the dynamic load, and solves the problem that the counterweight is difficult to replace or adjust. Therefore, it is suitable for hoisting parts of different weights in a wide range, and has higher safety, effectively reducing the risk of overturning .
进一步地,S1中制作主梁的步骤包括:采用钢板制作成箱型梁结构,作为主梁。Further, the step of manufacturing the main girder in S1 includes: using a steel plate to form a box girder structure as the main girder.
进一步地,S1中制作副梁的步骤包括:采用钢板分别切割成两个横板和两个竖板,将两个横板上下平行设置,两个竖板均位于两个横板之间,两个竖板平行设置,竖板分别与两个横板焊接固定,组成副梁。Further, the steps of making the sub-beam in S1 include: cutting the steel plate into two horizontal plates and two vertical plates respectively, setting the two horizontal plates in parallel up and down, the two vertical plates are located between the two horizontal plates, and the two vertical plates Two vertical plates are arranged in parallel, and the vertical plates are respectively welded and fixed with two horizontal plates to form a secondary beam.
进一步地,S1中还包括:在主梁的两端分别焊接法兰;用于两个主梁之间的连接固定。Further, S1 also includes: welding flanges at both ends of the main girder; used for connection and fixation between the two main girders.
进一步地,S1中还包括:在主梁上表面的两端分别开设成对设置的第一螺栓孔;在副梁上表面以及副梁上表面的两端分别开设成对设置的第二螺栓孔;用于主梁与副梁之间的连接固定。Further, S1 also includes: opening first bolt holes in pairs at both ends of the upper surface of the main beam; opening second bolt holes in pairs at the upper surface of the sub-beam and at both ends of the upper surface of the sub-beam ; Used for the connection and fixation between the main beam and the auxiliary beam.
进一步地,S2的步骤包括:直接采用一根主梁作为平衡梁;或将副梁穿装在主梁中,并将固定螺栓依次穿过第一螺栓孔和第二螺栓孔,将副梁和主梁固定连接在一起,组成平衡梁;或将两个主梁的端部对接并固定连接在一起,组成平衡梁。平衡梁采用主梁和副梁内外套装(并联)组合的方式,解决了以往平衡梁因其固定的结构和截面决定了其最大起重量也固定的问题。副梁还可以采用逐级伸出的结构,使平衡梁的长度调节更为灵活。平衡梁在长度上采用串联组合的方式,解决了以往平衡梁因其固定的长度也难以适应不同远近的吊件的问题。Further, the step of S2 includes: directly adopting a main beam as the balance beam; or installing the sub-beam in the main beam, and passing the fixing bolts through the first bolt hole and the second bolt hole in sequence, and connecting the sub-beam and the second bolt hole. The main beams are fixedly connected together to form a balance beam; or the ends of two main beams are butted and fixedly connected together to form a balance beam. The balance beam adopts the combination of the main beam and the auxiliary beam inside and outside (parallel connection), which solves the problem that the maximum lifting capacity of the balance beam is also fixed because of its fixed structure and section. The auxiliary beam can also adopt a structure that protrudes step by step, so that the length adjustment of the balance beam is more flexible. The length of the balance beam is combined in series, which solves the problem that the balance beam is difficult to adapt to hanging parts of different distances due to its fixed length.
进一步地,S3中吊耳与配重之间以及吊耳与吊件之间均采用钢丝绳连接。Further, in S3, wire ropes are used to connect the lifting lug and the counterweight as well as between the lifting lug and the hanger.
附图说明Description of drawings
图1为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的主梁示意图;Fig. 1 is a schematic diagram of the main girder of the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图2为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的副梁示意图;Fig. 2 is a schematic diagram of the auxiliary beam of the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图3为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的主梁与副梁连接示意一图;Fig. 3 is a schematic diagram of the connection between the main beam and the sub-beam of the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图4为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的主梁与副梁连接示意二图;Fig. 4 is a schematic diagram of the connection between the main beam and the sub-beam of the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图5为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的双主梁连接示意图;Fig. 5 is a schematic diagram of double main girder connection of the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图6为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的天车的主钩为龙门吊钩组时的吊装示意图;Fig. 6 is a schematic diagram of hoisting when the main hook of the crane is a gantry hook set in the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图7为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的天车的主钩为龙门吊钩组时的吊装侧视图;Fig. 7 is a hoisting side view when the main hook of the crane is a gantry hook set in the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention;
图8为本发明实施例提供的天车用可调组合式平衡梁的配重吊装方法的天车的主钩和副钩均为普通单吊钩时的吊装示意图。Fig. 8 is a schematic diagram of hoisting when the main hook and auxiliary hook of the crane are both ordinary single hooks in the method for hoisting the counterweight of the adjustable combined balance beam for the crane provided by the embodiment of the present invention.
图中标记为:1、主梁;2、法兰;3、吊耳;4、副梁;5、第一螺栓孔;6、第二螺栓孔;7、平衡梁;8、配重;9、吊件;10、钢丝绳;11、主钩;12、副钩。Marked in the figure: 1. Main beam; 2. Flange; 3. Lifting lug; 4. Sub-beam; 5. First bolt hole; 6. Second bolt hole; 7. Balance beam; 8. Counterweight; 9 , hanger; 10, steel wire rope; 11, main hook; 12, auxiliary hook.
实施方式Implementation
为使本发明的目的、技术方案和优点更加清楚明白,以下结合具体实施例,对本发明进一步详细说明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with specific examples.
本发明提出的一种天车用可调组合式平衡梁的配重吊装方法, 按以下步骤进行:A method for hoisting the counterweight of an adjustable combined balance beam for a crane proposed by the present invention is carried out according to the following steps:
S1、如图1所示,采用钢板制作成箱型梁结构,作为主梁1。在本实施例中,主梁1的数量为两个。在主梁1下表面的两端分别焊接吊耳3,在主梁1的两端面分别焊接法兰2,在主梁1上表面的两端分别开设成对设置的第一螺栓孔5。S1. As shown in FIG. 1 , a steel plate is used to make a box-shaped beam structure as the main beam 1 . In this embodiment, there are two main girders 1 . The two ends of the lower surface of the main girder 1 are respectively welded with
采用钢板分别切割成两个横板和两个竖板,将两个横板上下平行设置,两个竖板均位于两个横板之间,两个竖板平行设置,竖板分别与两个横板焊接固定,组成副梁4,如图2所示。在副梁4上表面以及副梁4上表面的两端分别开设成对设置的第二螺栓孔6,副梁4上表面的第二螺栓孔6沿副梁4长度方向均匀分布。The steel plate is cut into two horizontal plates and two vertical plates respectively, and the two horizontal plates are arranged in parallel up and down. The transverse plate is welded and fixed to form the subbeam 4, as shown in Figure 2. On the upper surface of the sub-beam 4 and the two ends of the upper surface of the sub-beam 4 respectively open a pair of second bolt holes 6 , and the second bolt holes 6 on the upper surface of the sub-beam 4 are evenly distributed along the length direction of the sub-beam 4 .
主梁1与副梁4的结构简单,能够通过现场取材进行制作,加工工序少,制作费用低。The structure of the main girder 1 and the auxiliary girder 4 is simple, and can be manufactured by collecting materials on site, with few processing steps and low manufacturing cost.
S2、将主梁1和副梁4组合固定成平衡梁7,对于平衡梁7的结构,包括以下几种:S2. Combining the main beam 1 and the auxiliary beam 4 to form a
一、直接采用一根主梁1作为平衡梁7。1. A main beam 1 is directly used as the
二、将副梁4穿装在主梁1中,并将固定螺栓依次穿过第一螺栓孔5和第二螺栓孔6,将副梁4和主梁1固定连接在一起,组成平衡梁7,如图3所示。该结构适用于负荷较大,负荷超过单根主梁1的最大起重量的情况。将副梁4完全插入主梁1中,若副梁4的上下表面与主梁1之间存在空隙,则可以采用厚度为1至2mm的薄垫片先将两端塞实,再紧固固定螺栓。2. Put the sub-beam 4 in the main beam 1, and pass the fixing bolts through the
对于吊件9重量较小,但平衡梁7长度需要较小加长调整时,可以将副梁4部分插入主梁1中,进行连接固定,如图4所示。此时,副梁4端部不再设置吊耳3,采用在副梁4上表面加设挡块和在副梁4端部的四周包角的方式,进行钢丝绳10索具的栓挂,实现与吊件9的连接。需要注意的是,为保证吊装安全性,副梁4伸出于主梁1的最大长度不能超过副梁4全长的三分之二。When the weight of the hanger 9 is small, but the length of the
三、将两个主梁1的端部对接,通过螺栓以及两个主梁1端部连接的法兰2将两个主梁1固定连接在一起,组成平衡梁7,如图5所示。该连接方式适用于吊件9就位位置超过单主梁1平衡梁7长度能力的情况。3. The ends of the two main beams 1 are butted, and the two main beams 1 are fixedly connected together by bolts and
需要说明的是,副梁4还能够作为备用梁,在需要应急的情况下,当副梁4满足吊装要求时,可以在副梁4下表面两端分别焊接吊耳3,将副梁4单独作为平衡梁7使用,节省了材料,提高了效率。It should be noted that the sub-beam 4 can also be used as a spare beam. In the case of an emergency, when the sub-beam 4 meets the hoisting requirements, the lifting lugs 3 can be welded on the two ends of the lower surface of the sub-beam 4 to separate the sub-beam 4 Used as the
S3、确定天车类型,当天车的主钩11为龙门吊钩组时,如图6和图7所示,先用龙门吊钩组将配重8吊起。在本实施例中,采用钢包作为配重8,龙门吊钩直接与钢包的销轴钩挂,无需使用钢丝绳10,挂钩和摘钩操作便捷。再用天车的副钩12将平衡梁7吊起,将平衡梁7一端穿入龙门吊钩组横梁正下方。并采用钢丝绳10将平衡梁7上靠近配重8一端的吊耳3与配重8连接,再采用钢丝绳10将另一个吊耳3与吊件9连接,进行吊装。S3. Determine the type of the crane. When the
当天车的主钩11和副钩12均为普通单吊钩时,如图8所示,先用主钩11和副钩12将平衡梁7吊起,再采用钢丝绳10将配重8连接在平衡梁7的一个吊耳3上,采用钢丝绳10将吊件9连接在另一个吊耳3上,进行吊装。When the
因此,本发明既能实现自动调节有效配重8重量,又能视吊件9重量增加平衡梁7的最大起重量,同时也能调节平衡梁7的长度,增加吊装作业范围。吊装过程操作简便,能够根据吊件9重量和作业半径不同,对平衡梁7进行组装,且平衡梁7结构简单,拆装组合方便,有效提高了施工效率和施工质量。Therefore, the present invention can not only automatically adjust the weight of the
本发明的实施例旨在涵盖落入所附权利要求的宽泛范围之内的所有这样的替换、修改和变型。因此,凡在本发明的精神和原则之内,所做的任何省略、修改、等同替换、改进等,均应包含在本发明的保护范围之内。Embodiments of the present invention are intended to embrace all such alterations, modifications and variations that fall within the broad scope of the appended claims. Therefore, any omissions, modifications, equivalent replacements, improvements, etc. within the spirit and principles of the present invention shall be included within the protection scope of the present invention.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310147311.XA CN116101881A (en) | 2023-02-22 | 2023-02-22 | Counterweight Hoisting Method of Adjustable Combined Balance Beam for Crane |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310147311.XA CN116101881A (en) | 2023-02-22 | 2023-02-22 | Counterweight Hoisting Method of Adjustable Combined Balance Beam for Crane |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116101881A true CN116101881A (en) | 2023-05-12 |
Family
ID=86265442
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310147311.XA Withdrawn CN116101881A (en) | 2023-02-22 | 2023-02-22 | Counterweight Hoisting Method of Adjustable Combined Balance Beam for Crane |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116101881A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117003094A (en) * | 2023-07-13 | 2023-11-07 | 沪东中华造船(集团)有限公司 | A scale beam type hoisting device and hoisting method |
-
2023
- 2023-02-22 CN CN202310147311.XA patent/CN116101881A/en not_active Withdrawn
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117003094A (en) * | 2023-07-13 | 2023-11-07 | 沪东中华造船(集团)有限公司 | A scale beam type hoisting device and hoisting method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN217972205U (en) | A kind of balance hanger for box girder | |
| CN207244452U (en) | A kind of suspension bridge vice saddle adjusting apparatus in place | |
| CN201458582U (en) | A special spreader for ladle turret moving horizontally between spans | |
| CN101100267A (en) | Hoisting device for loop wheel machine | |
| CN112623921A (en) | Light lifting appliance for hoisting lattice beam cable of arch bridge | |
| CN201901516U (en) | Detachable steel structural hoisting fixture | |
| CN208980155U (en) | A kind of suspender of mill housing installation | |
| CN105780659A (en) | Lifting appliance special for erection of large-tonnage steel box beam segment in non-stayed cable area of cable-stayed bridge | |
| CN107161844B (en) | A kind of device of across the railway cluster lifting of large-tonnage railway single freely-supported trough girder | |
| CN206665952U (en) | A kind of novel hanging tool | |
| CN206088755U (en) | Girder | |
| CN211496571U (en) | Self-balancing lifting appliance | |
| CN217211450U (en) | A large bridge crane load test device | |
| CN209778062U (en) | An extension spreader for hoisting steel pipe arch bridge lattice girders | |
| CN112707304B (en) | An installation device and method for hanging objects on the bottom surface of an elevated beam | |
| CN205662256U (en) | High rises pergola side and hangs a semi -portal bridge crane | |
| CN215924140U (en) | Overhead hoist with barrier equipment above | |
| CN224160284U (en) | Adaptive Stabilizing Steel Beam Lifting Structure | |
| CN201907938U (en) | Self-disassembly falling crane for fixed pulley block | |
| CN106480824A (en) | A kind of handling method of cable wire tower | |
| CN209635709U (en) | Tooling for the lifting of box type rod piece cluster | |
| CN201099586Y (en) | Crane lifting device | |
| CN207986492U (en) | A kind of heat exchanger integral hoisting tooling | |
| CN202208603U (en) | Adjustable end beam fixing device for installing dry quenching hoister frame in slicing mode | |
| CN107840240B (en) | Hanging beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WW01 | Invention patent application withdrawn after publication | ||
| WW01 | Invention patent application withdrawn after publication |
Application publication date: 20230512 |