CN116084427A - Construction method of raft inner foundation pit for water-rich foundation in quicksand layer - Google Patents
Construction method of raft inner foundation pit for water-rich foundation in quicksand layer Download PDFInfo
- Publication number
- CN116084427A CN116084427A CN202211672961.8A CN202211672961A CN116084427A CN 116084427 A CN116084427 A CN 116084427A CN 202211672961 A CN202211672961 A CN 202211672961A CN 116084427 A CN116084427 A CN 116084427A
- Authority
- CN
- China
- Prior art keywords
- raft
- concrete
- foundation pit
- steel sheet
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 28
- 238000010276 construction Methods 0.000 title claims abstract description 15
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 64
- 239000010959 steel Substances 0.000 claims abstract description 64
- 239000004567 concrete Substances 0.000 claims abstract description 60
- 239000011178 precast concrete Substances 0.000 claims abstract description 34
- 238000000034 method Methods 0.000 claims description 8
- 238000013461 design Methods 0.000 claims description 6
- 230000002787 reinforcement Effects 0.000 claims description 3
- 230000002457 bidirectional effect Effects 0.000 claims 1
- 239000004576 sand Substances 0.000 abstract description 5
- 238000005266 casting Methods 0.000 abstract 2
- 238000004873 anchoring Methods 0.000 abstract 1
- 230000000903 blocking effect Effects 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 28
- 239000002689 soil Substances 0.000 description 7
- 239000011449 brick Substances 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 239000012528 membrane Substances 0.000 description 3
- 230000004888 barrier function Effects 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 239000010881 fly ash Substances 0.000 description 2
- 241001640558 Cotoneaster horizontalis Species 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 239000011229 interlayer Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工技术领域,特别涉及一种流沙层富水地基筏板内基坑施工方法。The invention relates to the technical field of building construction, in particular to a method for constructing a foundation pit in a water-rich foundation raft in a quicksand layer.
背景技术Background technique
一般情况下,工程电梯基坑及集水坑位于基槽下方, 集水坑及电梯坑采用放坡开挖形式(45°至60°),如遇到地质情况不好的条件,放坡不成形,常规做法为砖砌导墙和土钉墙喷锚等形式进行护坡施工,但是遇到细沙(层或砂质粉土层)地质,如果水位偏高的情况下,放坡不成形,且形成流沙和管涌现象。Under normal circumstances, the engineering elevator foundation pit and sump pit are located under the foundation trench, and the sump pit and elevator pit are excavated with slopes (45° to 60°). Forming, the conventional method is to carry out slope protection construction in the form of brick guide wall and soil nail wall spray anchor, but when encountering fine sand (layer or sandy silt layer) geology, if the water level is too high, the slope will not be formed. And the formation of quicksand and piping phenomenon.
电梯基坑和集水坑开挖时坑内会出现大量涌水,因该层土质为粉砂、细砂层,自稳性差,受渗流作用影响极易造成坑边流沙、坍塌,影响基坑安全。施工期间如正值雨季,大量雨水下渗、冲刷严重影响边坡稳定性。尤其是有地基处理区域,集水坑和电梯基坑连成片,内部有大量水泥粉煤灰碎石桩,若不妥善处理,甚至会导致水泥粉煤灰碎石桩断裂、偏位,对结构造成不利影响。When the elevator foundation pit and sump pit are excavated, there will be a lot of water gushing in the pit. Because the soil of this layer is silt and fine sand layer, the self-stability is poor, and it is easy to cause quicksand and collapse at the edge of the pit due to the influence of seepage, which will affect the safety of the foundation pit. During the construction period, if it is the rainy season, a large amount of rainwater infiltrates and scours seriously affects the stability of the slope. Especially in the foundation treatment area, the sump pit and the elevator foundation pit are connected into one piece, and there are a large number of cement fly ash gravel piles inside. If they are not handled properly, the cement fly ash gravel piles may even break and deviate. structure is adversely affected.
发明内容Contents of the invention
为了克服现有技术存在的问题,本发明提供一种流沙层富水地基筏板内基坑施工方法,能够起到在流沙层富水地基内开挖筏板内基坑中阻水阻流沙的作用。In order to overcome the problems existing in the prior art, the present invention provides a method for constructing a raft inner foundation pit in a water-rich foundation in a quicksand layer, which can block water and quicksand in excavating the raft inner foundation pit in a water-rich foundation in a quicksand layer effect.
一种流沙层富水地基筏板内基坑施工方法,包括以下步骤:A method for constructing a foundation pit in a water-rich foundation raft in a quicksand layer, comprising the following steps:
步骤1)根据图纸上筏板内基坑布置设计,距离筏板内基坑外壁第一间距处打入拉森钢板桩;Step 1) According to the layout design of the foundation pit in the raft slab on the drawing, drive Larsen steel sheet piles at the first distance from the outer wall of the foundation pit in the raft slab;
步骤2)在拉森钢板桩内垂直开挖土方,开挖到筏板内基坑坑底,距离拉森钢板桩内壁第二间距处,筏板内基坑坑底上采用C20混凝土浇筑混凝土垫层;Step 2) Excavate the earthwork vertically in the Larsen steel sheet pile, excavate to the bottom of the foundation pit in the raft, at the second distance from the inner wall of the Larsen steel sheet pile, and use C20 concrete to pour concrete pads on the bottom of the foundation pit in the raft layer;
步骤3)在混凝土垫层上放入预制混凝土模块,使预制混凝土模块顶标高同筏板垫层底标高,预制混凝土模块与拉森钢板桩之间的缝隙采用C20混凝土浇筑填实缝隙;Step 3) Put the precast concrete module on the concrete cushion, so that the top elevation of the precast concrete module is the same as the bottom elevation of the raft cushion, and the gap between the precast concrete module and the Larsen steel sheet pile is filled with C20 concrete;
步骤4)拉森钢板桩等浇筑混凝土初凝后,拔出拉森钢板桩,预制混凝土模块上口周边采用与筏板基础垫层同标号的混凝土浇筑,拔出拉森钢板桩的槽内捆扎钢筋,浇筑混凝土做筏板内基坑的壁,在预制混凝土模块上做90°弯锚钢筋锚固,混凝土浇筑形成筏板垫层,完成筏板内基坑的施工。Step 4) After the Larsen steel sheet piles are poured and the concrete is initially set, the Larsen steel sheet piles are pulled out, and the upper mouth of the precast concrete module is poured with the same grade of concrete as the raft foundation cushion, and the Larsen steel sheet piles are pulled out and bound in the groove Reinforcement, concrete is poured as the wall of the foundation pit in the raft slab, anchored by 90° bent anchor steel bars on the prefabricated concrete module, and concrete is poured to form the cushion of the raft slab to complete the construction of the foundation pit in the raft slab.
进一步,在步骤1中,拉森钢板桩打入筏板内基坑地基的嵌固深度为筏板内基坑深度的一倍,所述拉森钢板桩顶端标高至少高于所述筏板垫层底标高300mm,所述第一间距大于等于350mm。Further, in
进一步,在步骤2中,所述第二间距大于等于50mm,所述混凝土垫层厚度为100mm~150mm。Further, in
进一步,在步骤3中,所述预制混凝土模块厚度为200mm,预制混凝土模块采用Ø8@200双层双向钢筋网片和C20混凝土浇筑而成, 预制混凝土模块阴角处为圆弧角。Further, in
进一步,在步骤4中,所述筏板垫层厚度为100mm~150mm。Further, in step 4, the thickness of the raft cushion layer is 100mm-150mm.
本发明有益效果在于:本发明采用的拉森钢板桩有效阻止流沙涌向集水坑和电梯基坑,防止边坡塌方,避免塌方部位造成对周边地基土的扰动,增加地基处理措施和费用,预制混凝土模块较传统砖胎膜有施工快捷,有效阻水阻流沙的作用,对流沙富水地质情况有着良好的阻隔作用,且面层光滑平整,保障防水基层的平整有效。The beneficial effects of the present invention are: the Larsen steel sheet pile adopted in the present invention effectively prevents quicksand from rushing to the sump and the elevator foundation pit, prevents the side slope from collapsing, avoids the disturbance of the surrounding foundation soil caused by the collapsed part, and increases the foundation treatment measures and costs, Compared with the traditional brick membrane, the prefabricated concrete module has faster construction, effectively blocks water and quicksand, and has a good barrier effect on quicksand and water-rich geological conditions, and the surface layer is smooth and flat, ensuring the smooth and effective waterproof base.
附图说明Description of drawings
图1是本发明流沙层富水地基筏板内基坑俯视图;Fig. 1 is the top view of the foundation pit in the quicksand layer water-rich foundation raft of the present invention;
图2是本发明流沙层富水地基筏板内基坑剖面图。Fig. 2 is a sectional view of the foundation pit in the raft of the quicksand layer water-rich foundation of the present invention.
附图中的符号说明:Explanation of symbols in the accompanying drawings:
1.筏板内基坑内径,2.防水层,3.预制混凝土模块层,4.C20混凝土浇筑填实缝隙,1. Inner diameter of the foundation pit in the raft, 2. Waterproof layer, 3. Precast concrete module layer, 4. C20 concrete pouring to fill the gap,
5.拉森钢板桩,6.预制混凝土模块圆弧阴角,7.混凝土垫层,8.原土,9.预留原土。5. Larsen steel sheet pile, 6. Precast concrete module arc inner corner, 7. Concrete cushion, 8. Original soil, 9. Reserved original soil.
具体实施方式Detailed ways
为使本领域技术人员更好地理解本发明的技术方案,下面结合附图和具体实施方式对本发明进一步详细描述。In order to enable those skilled in the art to better understand the technical solutions of the present invention, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
其中,附图仅用于示例性说明,表示的仅是示意图,而非实物图,不能理解为对本专利的限制;为了更好地说明本发明的实施例,附图某些部件会有省略、放大或缩小,并不代表实际产品的尺寸;对本领域技术人员来说,附图中某些公知结构及其说明可能省略是可以理解的。Wherein, the accompanying drawings are only for illustrative purposes, showing only schematic diagrams, rather than physical drawings, and should not be construed as limitations on this patent; in order to better illustrate the embodiments of the present invention, some parts of the accompanying drawings will be omitted, Enlargement or reduction does not represent the size of the actual product; for those skilled in the art, it is understandable that certain known structures and their descriptions in the drawings may be omitted.
本发明实施例的附图中相同或相似的标号对应相同或相似的部件;在本发明的描述中,需要理解的是,若出现术语“上”、“下”、“左”、“右”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此附图中描述位置关系的用语仅用于示例性说明,不能理解为对本专利的限制,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语的具体含义。In the drawings of the embodiments of the present invention, the same or similar symbols correspond to the same or similar components; , "inner", "outer" and other indicated orientations or positional relationships are based on the orientations or positional relationships shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred devices or elements must It has a specific orientation, is constructed and operated in a specific orientation, so the terms describing the positional relationship in the drawings are for illustrative purposes only, and should not be understood as limitations on this patent. For those of ordinary skill in the art, the specific understanding of the specific meaning of the above terms.
在本专利的描述中,除非另有明确的规定和限定,若出现术语“连接”等指示部件之间的连接关系,该术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个部件内部的连通或两个部件的相互作用关系。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of this patent, unless otherwise clearly stipulated and limited, if the term "connection" appears to indicate the connection relationship between parts, the term should be understood in a broad sense, for example, it can be a fixed connection or a detachable connection. Connection, or integration; it can be mechanical connection or electrical connection; it can be direct connection or indirect connection through an intermediary, and it can be the internal communication of two parts or the interaction relationship between two parts. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
一种流沙层富水地基筏板内基坑施工方法,包括以下步骤:A method for constructing a foundation pit in a water-rich foundation raft in a quicksand layer, comprising the following steps:
步骤1)根据图纸上筏板内基坑布置设计,距离筏板内基坑外壁第一间距处打入拉森钢板桩;Step 1) According to the layout design of the foundation pit in the raft slab on the drawing, drive Larsen steel sheet piles at the first distance from the outer wall of the foundation pit in the raft slab;
进一步,在步骤1中,所述拉森钢板桩打入筏板内基坑地基的嵌固深度为筏板内基坑深度的一倍,拉森钢板桩顶端标高至少高于所述筏板垫层底标高300mm,所述第一间距大于等于350mm。Further, in
根据筏板内基坑布置设计,确定筏板内基坑的位置,以及筏板内基坑外壁的位置,在筏板内基坑设计外围也就是距离筏板内基坑外壁第一间距的地方,打入拉森钢板,拉森钢板桩围起来的范围进行挖土施工,挖掘筏板内基坑。在流沙层富水地基上挖掘筏板内基坑,容易出现大量涌水,因该层土质为粉砂、细砂层,自稳性差,受渗流作用影响极易造成坑边流沙、坍塌,影响基坑安全,设置拉森钢板防止流沙和水汇集到拉森钢板桩围起来的范围内,既是筏板内基坑内。设置第一间距是为了后续放入预制混凝土模块。拉森钢板桩打入筏板内基坑地基的深度是筏板内基坑深度的一倍。在本实施例中,筏板内基坑的设计深度是4米,打入筏板内基坑基础内拉森钢板桩的深度是9米。拉森钢板桩顶端标高至少高于所述筏板垫层底标高300mm。设置拉森钢板桩顶端标高至少高于筏板垫层底标高300mm,是为了后续将拉森钢板桩拔出来时,有使加力的地方。出于实际情况和成本的考虑,拉森钢板桩顶端标高高出筏板垫层底标高的高度不能大于1m。According to the layout design of the inner foundation pit of the raft, determine the position of the inner foundation pit of the raft and the position of the outer wall of the inner foundation pit of the raft. , drive into the Larsen steel plate, excavate the area enclosed by the Larsen steel sheet pile, and excavate the foundation pit in the raft. Excavating the foundation pit in the raft on the water-rich foundation of the quicksand layer is prone to a large amount of water gushing, because the soil in this layer is silt and fine sand layer, which has poor self-stability, and is easily affected by seepage to cause quicksand and collapse at the side of the pit, affecting the foundation. To ensure the safety of the pit, Larsen steel plates are installed to prevent quicksand and water from collecting into the area enclosed by Larsen steel sheet piles, which is the foundation pit inside the raft. The purpose of setting the first spacing is to put the precast concrete modules in later. The depth of the Larsen steel sheet pile driven into the foundation pit in the raft is twice the depth of the foundation pit in the raft. In this embodiment, the design depth of the foundation pit in the raft is 4 meters, and the depth of the Larsen steel sheet piles driven into the foundation of the foundation pit in the raft is 9 meters. The top elevation of the Larsen steel sheet pile is at least 300mm higher than the bottom elevation of the raft cushion. The top elevation of the Larsen steel sheet pile is set at least 300mm higher than the bottom elevation of the raft cushion, so that there will be a place to add force when the Larsen steel sheet pile is pulled out later. Considering the actual situation and cost, the height of the top elevation of the Larsen steel sheet pile above the bottom elevation of the raft cushion cannot be greater than 1m.
步骤2)在拉森钢板桩内垂直开挖土方,开挖到筏板内基坑坑底,距离拉森钢板桩内壁第二间距处,筏板内基坑坑底上采用C20混凝土浇筑混凝土垫层;Step 2) Excavate the earthwork vertically in the Larsen steel sheet pile, excavate to the bottom of the foundation pit in the raft, at the second distance from the inner wall of the Larsen steel sheet pile, and use C20 concrete to pour concrete pads on the bottom of the foundation pit in the raft layer;
进一步,在步骤2中,所述第二间距大于等于50mm,所述混凝土垫层厚度为100mm~150mm。Further, in
将拉森钢板桩打入筏板内基坑基础内后,在拉森钢板桩内垂直开挖土方,既是开始挖掘筏板内基坑,开挖到筏板内基坑坑底,距离拉森钢板桩内壁第二间距处,坑底原土采用C20混凝土浇筑混凝土垫层。设置第二间距,是防止混凝土垫层与拉森钢板桩接触,混凝土将发森钢板桩固定住,不易将拉森钢板桩拨出。根据工程规定,筏板内基坑底层混凝土垫层的厚度设定范围为100mm~150mm。在本实施例中,混凝土垫层的厚度为150mm。After the Larsen steel sheet piles are driven into the foundation pit foundation in the raft slab, the earthwork is excavated vertically in the Larsen steel sheet piles. At the second interval of the inner wall of the steel sheet pile, the original soil at the bottom of the pit is made of C20 concrete to pour the concrete cushion. The second distance is set to prevent the concrete cushion from contacting the Larsen steel sheet piles, and the concrete will fix the Larsen steel sheet piles, making it difficult to pull out the Larsen steel sheet piles. According to the engineering regulations, the thickness setting range of the concrete cushion at the bottom of the foundation pit in the raft is 100mm to 150mm. In this embodiment, the thickness of the concrete cushion is 150mm.
步骤3)在混凝土垫层上放入预制混凝土模块,使预制混凝土模块顶标高同筏板垫层底标高,预制混凝土模块与拉森钢板桩之间的缝隙采用C20混凝土浇筑填实缝隙;Step 3) Put the precast concrete module on the concrete cushion, so that the top elevation of the precast concrete module is the same as the bottom elevation of the raft cushion, and the gap between the precast concrete module and the Larsen steel sheet pile is filled with C20 concrete;
进一步,在步骤3中,所述预制混凝土模块厚度为200mm,预制混凝土模块采用Ø8@200双层双向钢筋网片和C20混凝土浇筑而成, 预制混凝土模块阴角处为圆弧角。Further, in
现有技术中,筏板内基坑需要砌筑砖胎模,在流沙层富水地基上筏板内基坑内砌筑砖胎膜无法止住流沙。因此在本发明中,首先在筏板内基坑外设置拉森钢板桩止住地基中的层间水,从而不会形成流沙,然后放入预制混凝土模块,预制混凝土模块有效阻水阻流沙的作用,对流沙富水地质情况有着良好的阻隔作用。并且,预制混凝土模块可以在施工现场预先用混凝土浇筑而成,或者在现场外加工成预先浇筑而成,使用时,直接吊装放置于混凝土垫层上。缩短了施工周期,同时不扰动集水坑周边天然地基,保证施工质量。在本实施例中,预制混凝土模块在现场预先制备,采用C20混凝土和Ø8@200双层双向钢筋网片浇筑而成。根据筏板内基坑的深度,计算得到预制混凝土模块的厚度为200mm,能够满足力学受力的要求,也能够满足工程上尺寸的要求。预制混凝土模块阴角处为圆弧角,是为了黏贴防水卷材时,使防水卷材贴合,形成的防水层平整。预制混凝土模块是200mm厚度的块状,因此放置于混凝土垫层上,与拉森钢板桩之间必然产生缝隙,这些缝隙采用同预制混凝土模块的混凝土强度一致的C20混凝土浇筑到缝隙中填是缝隙,形成预制混凝土模块层。In the prior art, the inner foundation pit of the raft needs to be built with brick tire molds, and the brick mold in the inner foundation pit of the raft on the water-rich foundation of the quicksand layer cannot stop the quicksand. Therefore, in the present invention, Larsen steel sheet piles are first arranged outside the foundation pit in the raft to stop the interlayer water in the foundation, so that quicksand will not form, and then put into the prefabricated concrete module, which effectively blocks water and quicksand It has a good barrier effect on the quicksand and water-rich geological conditions. Moreover, the prefabricated concrete module can be pre-cast with concrete at the construction site, or processed to be pre-cast outside the site, and can be directly hoisted and placed on the concrete cushion when in use. The construction period is shortened, and the natural foundation around the sump is not disturbed at the same time, so as to ensure the construction quality. In this embodiment, the prefabricated concrete modules are pre-prepared on site and poured with C20 concrete and Ø8@200 double-layer two-way steel mesh. According to the depth of the foundation pit in the raft, the thickness of the prefabricated concrete module is calculated to be 200mm, which can meet the requirements of mechanical force and engineering size. The internal corners of the precast concrete modules are arc corners, which are used to make the waterproof membranes stick together and form a smooth waterproof layer when the waterproof membrane is pasted. The precast concrete module is a block with a thickness of 200mm, so it is placed on the concrete cushion, and there must be gaps between the Larsen steel sheet piles. These gaps are filled with C20 concrete that is consistent with the concrete strength of the precast concrete module. , forming precast concrete module layers.
步骤4)拉森钢板桩等浇筑混凝土初凝后,拔出拉森钢板桩,预制混凝土模块上口周边采用与筏板基础垫层同标号的混凝土浇筑,拔出拉森钢板桩的槽内捆扎钢筋,浇筑混凝土做筏板内基坑的壁,在预制混凝土模块上做90°弯锚钢筋锚固,混凝土浇筑形成筏板垫层,完成筏板内基坑的施工。进一步,所述筏板垫层厚度为100mm~150mm。Step 4) After the Larsen steel sheet piles are poured and the concrete is initially set, the Larsen steel sheet piles are pulled out, and the upper mouth of the precast concrete module is poured with the same grade of concrete as the raft foundation cushion, and the Larsen steel sheet piles are pulled out and bound in the groove Reinforcement, concrete is poured as the wall of the foundation pit in the raft slab, anchored by 90° bent anchor steel bars on the prefabricated concrete module, and concrete is poured to form the cushion of the raft slab to complete the construction of the foundation pit in the raft slab. Further, the thickness of the raft cushion layer is 100mm-150mm.
规定优质黏土地基设计,60度放坡,钢筋也是沿着60度坡来安装,而本发明中预制混凝土模块是垂直放置在基坑的混凝土垫层上的,相应钢筋也由60度弯变成垂直的90度。捆扎完钢筋,采用C20混凝土浇筑筏板垫层,完成筏板内基坑的施工。根据工程规定,筏板垫层的厚度为100mm~150mm之间,在本实施例中,筏板垫层的厚度为150mm。The high-quality clay foundation design is stipulated, the slope is set at 60 degrees, and the steel bars are also installed along the 60-degree slope. In the present invention, the precast concrete module is placed vertically on the concrete cushion of the foundation pit, and the corresponding steel bars are also bent at 60 degrees. 90 degrees from vertical. After binding the steel bars, use C20 concrete to pour the raft cushion to complete the construction of the foundation pit in the raft. According to engineering regulations, the thickness of the raft cushion is between 100 mm and 150 mm. In this embodiment, the thickness of the raft cushion is 150 mm.
需要声明的是,上述具体实施方式仅仅为本发明的较佳实施例及所运用技术原理。本领域技术人员应该明白,还可以对本发明做各种修改、等同替换、变化等等。但是,这些变换只要未背离本发明的精神,都应在本发明的保护范围之内。另外,本申请说明书和权利要求书所使用的一些术语并不是限制,仅仅是为了便于描述。It should be declared that the above specific implementation manners are only preferred embodiments of the present invention and applied technical principles. Those skilled in the art should understand that various modifications, equivalent replacements, changes and the like can be made to the present invention. However, as long as these changes do not deviate from the spirit of the present invention, they should all be within the protection scope of the present invention. In addition, some terms used in the specification and claims of this application are not limiting, but are only for convenience of description.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211672961.8A CN116084427A (en) | 2022-12-26 | 2022-12-26 | Construction method of raft inner foundation pit for water-rich foundation in quicksand layer |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211672961.8A CN116084427A (en) | 2022-12-26 | 2022-12-26 | Construction method of raft inner foundation pit for water-rich foundation in quicksand layer |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116084427A true CN116084427A (en) | 2023-05-09 |
Family
ID=86212972
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211672961.8A Pending CN116084427A (en) | 2022-12-26 | 2022-12-26 | Construction method of raft inner foundation pit for water-rich foundation in quicksand layer |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116084427A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117027031A (en) * | 2023-08-07 | 2023-11-10 | 北京建工海亚建设工程有限公司 | A method for treating groundwater in a pit in a water-rich pebble formation |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103912009A (en) * | 2014-04-18 | 2014-07-09 | 二十二冶集团第一建设有限公司 | Quicksand high-rise residence foundation sump construction method |
| CN111119219A (en) * | 2020-01-06 | 2020-05-08 | 中国一冶集团有限公司 | Reinforced foundation tire membrane structure and construction method thereof |
| WO2020173100A1 (en) * | 2019-02-26 | 2020-09-03 | 济南轨道交通集团有限公司 | Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum |
| CN112554203A (en) * | 2020-12-03 | 2021-03-26 | 九冶建设有限公司 | Miniature open caisson prefabricated molding bed construction method for silt flow sand area with abundant underground water |
| CN114045838A (en) * | 2021-10-28 | 2022-02-15 | 浙江国进建设有限公司 | Foundation pit enclosure construction method |
| CN217231837U (en) * | 2022-01-12 | 2022-08-19 | 中建国际建设有限公司 | Construction system for pit-in-pit in mucky soil layer |
-
2022
- 2022-12-26 CN CN202211672961.8A patent/CN116084427A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103912009A (en) * | 2014-04-18 | 2014-07-09 | 二十二冶集团第一建设有限公司 | Quicksand high-rise residence foundation sump construction method |
| WO2020173100A1 (en) * | 2019-02-26 | 2020-09-03 | 济南轨道交通集团有限公司 | Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum |
| CN111119219A (en) * | 2020-01-06 | 2020-05-08 | 中国一冶集团有限公司 | Reinforced foundation tire membrane structure and construction method thereof |
| CN112554203A (en) * | 2020-12-03 | 2021-03-26 | 九冶建设有限公司 | Miniature open caisson prefabricated molding bed construction method for silt flow sand area with abundant underground water |
| CN114045838A (en) * | 2021-10-28 | 2022-02-15 | 浙江国进建设有限公司 | Foundation pit enclosure construction method |
| CN217231837U (en) * | 2022-01-12 | 2022-08-19 | 中建国际建设有限公司 | Construction system for pit-in-pit in mucky soil layer |
Non-Patent Citations (2)
| Title |
|---|
| 李伟等: "建筑工程安全生产管理与技术实用手册", vol. 1, 31 December 2021, 中国建材工业出版社, pages: 178 - 180 * |
| 牛季收;: "潜水含水层中近河岸基坑工程的施工", 施工技术, no. 01, 18 January 2008 (2008-01-18) * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117027031A (en) * | 2023-08-07 | 2023-11-10 | 北京建工海亚建设工程有限公司 | A method for treating groundwater in a pit in a water-rich pebble formation |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106958256A (en) | A kind of placement layer by layer, the open caisson construction technique repeatedly sunk | |
| CN112627212B (en) | A kind of dry excavation construction method of dewatering method of inner tube well in waterfront cofferdam | |
| CN108517893A (en) | A kind of big cross section push pipe suitable under the conditions of shallow earthing wears river construction method | |
| CN104358275B (en) | Darker elevator shaft or collecting well construction method | |
| CN113431065A (en) | Rapid construction method and structure of occlusive pile and steel sleeve combined cofferdam | |
| CN113431097A (en) | Protection structure of shallow foundation building next to deep foundation pit engineering and construction method | |
| CN110344394A (en) | A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method | |
| CN110080248A (en) | Nearly depth of water foundation pit supporting construction | |
| CN115434335B (en) | A support structure for an elevator shaft foundation pit in deep silt strata and a construction method thereof | |
| CN116084427A (en) | Construction method of raft inner foundation pit for water-rich foundation in quicksand layer | |
| CN109024657B (en) | Construction method of super high-rise core tube deep pit edge tower crane foundation under complex conditions | |
| CN113026816B (en) | Underpinning reverse-acting open caisson supporting structure for grouting reinforcement soil body and construction method | |
| CN107326932B (en) | A quasi-semi-reverse construction method for an underground garage | |
| CN112281891A (en) | A kind of multi-pile type composite pile foundation structure, pile foundation and construction method thereof | |
| CN209555967U (en) | An H-shaped concrete slab assembled ecological retaining wall | |
| CN218933931U (en) | A reinforcement structure for deep foundation pit adjacent to existing buildings | |
| CN114809015B (en) | Temporary support system and permanent structure combined construction method for open cut subway station | |
| CN217325470U (en) | Basement outer wall post-cast strip department assembled retaining wall | |
| AU2021105983A4 (en) | A Construction Method for Reinforced-hoop Gravel Piles by Means of Immersed Tubes for Strengthening Soft Foundations | |
| CN214832441U (en) | Underwater throwing-filling type isolation dam | |
| CN209760248U (en) | Composite submerged foundation pit enclosure structure | |
| CN108677960B (en) | Construction method for pit-in-pit under complex geological conditions | |
| CN218933184U (en) | Cast-in-situ assembled pit and elevator shaft foundation pit supporting structure | |
| CN206428711U (en) | A kind of prefabricated bed course for mud class weak fault | |
| CN114809010B (en) | Construction method of elevator shaft and foundation retaining wall of sump pit in easy-to-collapse soil |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |