CN116024906A - A kind of construction method of steel truss bridge without support - Google Patents

A kind of construction method of steel truss bridge without support Download PDF

Info

Publication number
CN116024906A
CN116024906A CN202211743402.1A CN202211743402A CN116024906A CN 116024906 A CN116024906 A CN 116024906A CN 202211743402 A CN202211743402 A CN 202211743402A CN 116024906 A CN116024906 A CN 116024906A
Authority
CN
China
Prior art keywords
steel truss
truss bridge
construction
site
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211743402.1A
Other languages
Chinese (zh)
Inventor
马艺谭
牛宇飞
何亮
苗帅
魏家豪
陈宏博
白蒙珂
陆强
靳欣雨
欧兴婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Liujian Heavy Industry Co ltd
Original Assignee
Henan Liujian Heavy Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Liujian Heavy Industry Co ltd filed Critical Henan Liujian Heavy Industry Co ltd
Priority to CN202211743402.1A priority Critical patent/CN116024906A/en
Publication of CN116024906A publication Critical patent/CN116024906A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The method comprises the steps of constructing a site ground assembly jig frame at a construction site, transporting each girder section of the steel truss bridge from a processing plant to the construction site, and welding, riveting and assembling each girder section of the steel truss bridge on the site ground assembly jig frame; after the assembly of the steel truss bridge is completed on the ground, the erection of the steel truss bridge on the bridge pier is completed by a double crane lifting method; the construction method of the steel truss bridge without the support omits the traditional construction process of building the high-altitude support frame, so that the construction period and the construction cost are greatly reduced, and the construction safety is also greatly improved; meanwhile, when bolting, welding and assembling of each girder section of the steel truss bridge are carried out on the ground, the assembly linearity of the steel truss bridge is more convenient to measure and adjust, so that the construction difficulty is reduced, and the construction efficiency and the construction quality are also greatly improved.

Description

一种钢桁架桥梁无支架施工方法A kind of construction method of steel truss bridge without support

技术领域technical field

本发明涉及钢桁架桥梁施工技术领域,具体涉及一种钢桁架桥梁无支架施工方法。The invention relates to the technical field of steel truss bridge construction, in particular to a support-free construction method for steel truss bridges.

背景技术Background technique

钢桁架桥梁是公路或铁路桥梁的一种主要结构形式,其跨度通常较长,因公路、铁路、水路等运输条件限制,需将钢桁架桥梁结构拆分为若干梁段以方便运输;因此现有钢桁架桥梁现场施工方法为:在加工厂将钢桁架桥梁拆分的若干梁段运输至施工现场,在施工现场进行高空栓接、焊接等拼装作业,完成钢桁架桥梁整体结构的施工;因钢桁架桥梁现场施工前需要搭建高空支撑架,且需高空拼装,因此存在高空支撑架施工周期长、成本高、高空作业危险性高的问题,同时高空作业还存在施工难度大、施工质量控制困难等诸多问题,因此有待解决和改进。Steel truss bridge is a main structural form of highway or railway bridge, and its span is usually long. Due to transportation conditions such as road, railway, waterway, etc., it is necessary to split the steel truss bridge structure into several beam sections to facilitate transportation; therefore, the current The on-site construction method of the bridge with steel truss is as follows: several beam sections disassembled from the steel truss bridge are transported to the construction site in the processing plant, and assembly operations such as high-altitude bolting and welding are carried out on the construction site to complete the construction of the overall structure of the steel truss bridge; Steel truss bridges need to build high-altitude support frames before on-site construction, and high-altitude assembly is required. Therefore, there are problems such as long construction period, high cost, and high-altitude operations for high-altitude support frames. At the same time, high-altitude operations are also difficult to construct and difficult to control construction quality. And many other problems, so it needs to be solved and improved.

发明内容Contents of the invention

为了克服背景技术中的不足,本发明公开了一种钢桁架桥梁无支架施工方法,该方法在施工现场搭建现场地面拼装胎架,钢桁架桥各梁段从加工厂运输至施工现场,在现场地面拼装胎架上进行钢桁架桥各梁段的焊接、铆接拼装;在地面完成钢桁架桥的拼装后,通过双吊车抬吊的方法完成钢桁架桥在桥墩上的架设。In order to overcome the deficiencies in the background technology, the present invention discloses a construction method for a steel truss bridge without support. The method builds a tire frame assembled on the ground at the construction site, and each beam section of the steel truss bridge is transported from the processing plant to the construction site. Welding and riveting assembly of each beam section of the steel truss bridge are carried out on the tire frame assembled on the ground; after the assembly of the steel truss bridge is completed on the ground, the erection of the steel truss bridge on the pier is completed by lifting with double cranes.

为了实现所述发明目的,本发明采用如下技术方案:一种钢桁架桥梁无支架施工方法,在施工现场平整场地,搭建现场地面拼装胎架;钢桁架桥各梁段从加工厂运输至施工现场,在现场地面拼装胎架上进行钢桁架桥各梁段的焊接、铆接施工,完成钢桁架桥的地面拼装,然后通过双吊车抬吊的方法完成钢桁架桥在桥墩上的架设;该施工方法解决了钢桁架桥梁传统施工方法中搭建高空支撑架周期长、成本高、高空施工危险性高、施工难度大、施工质量难以控制等诸多问题。In order to achieve the purpose of the invention, the present invention adopts the following technical solutions: a construction method for a steel truss bridge without supports, leveling the site at the construction site, and building the on-site ground assembly tire frame; each beam section of the steel truss bridge is transported from the processing plant to the construction site , the welding and riveting construction of each beam section of the steel truss bridge is carried out on the ground assembly tire frame at the site, and the ground assembly of the steel truss bridge is completed, and then the erection of the steel truss bridge on the pier is completed by lifting with double cranes; the construction method It solves many problems in the traditional construction method of steel truss bridges, such as long period of construction of high-altitude support frames, high cost, high risk of high-altitude construction, difficult construction, and difficulty in controlling construction quality.

进一步的,所述现场地面拼装胎架为全新结构,其采用标准化模块结构设计,具有可重复使用的特点,相比传统的高空支撑架,具有搭建周期短、成本低的优点;现场地面拼装胎架包括垫板、可调支架、支撑分配梁、支撑柱;垫板平铺在拼装现场地面,可调支架固定设置在垫板上,支撑分配梁固定设置在可调支架顶部,支撑柱固定在支撑分配梁顶部;钢桁架桥各梁段设置在支撑柱顶部,施工人员在施工现场地面即可完成钢桁架桥各梁段的焊接、栓接拼装作业;由于钢桁架桥梁的拼装作业在地面实施,因此施工作业更加安全,在施工中钢桁架桥梁的各参数测量、调整、控制也更加方便,极大降低了施工难度、提高了施工效率,同时施工质量也得到良好控制。Further, the on-site ground-assembled tire frame is a brand-new structure, which adopts a standardized modular structure design and has the characteristics of reusability. Compared with the traditional high-altitude support frame, it has the advantages of short construction period and low cost; the on-site ground-assembled tire frame The frame includes a backing plate, an adjustable bracket, a supporting distribution beam, and a supporting column; the backing plate is laid flat on the ground of the assembly site, the adjustable bracket is fixed on the backing plate, the supporting distribution beam is fixed on the top of the adjustable bracket, and the supporting column is fixed on the The top of the supporting distribution beam; each beam section of the steel truss bridge is set on the top of the support column, and the construction personnel can complete the welding and bolting assembly of each beam section of the steel truss bridge on the ground at the construction site; since the assembly work of the steel truss bridge is carried out on the ground , so the construction work is safer, and the measurement, adjustment, and control of various parameters of the steel truss bridge are more convenient during construction, which greatly reduces the construction difficulty and improves the construction efficiency. At the same time, the construction quality is well controlled.

进一步的,现场地面拼装胎架的搭建方法为:Further, the construction method of the on-site ground-assembled tire frame is as follows:

S1、现场地面拼装胎架的搭建:在施工现场预先预平整出拼装场地,用振动压路机反复碾压6-8次,然后将600*600、厚度50mm的垫板按设计位置平铺在压实的地面上,可调支架临时设置在垫板上,支撑分配梁固定设置在可调支架顶部,支撑柱固定设置在支撑分配梁顶部,完成施工现场地面拼装胎架的初步搭建;支撑分配梁设有两根,调整两根支撑分配梁的平行度,然后将可调支架固定连接在垫板上部;S1. Construction of on-site ground assembly tire frame: Pre-level the assembly site at the construction site, use a vibratory roller to repeatedly roll it 6-8 times, and then flatten the 600*600, 50mm thick backing plate on the compaction according to the design position On the ground, the adjustable support is temporarily set on the backing plate, the support distribution beam is fixed on the top of the adjustable support, and the support column is fixed on the top of the support distribution beam to complete the preliminary construction of the ground assembly tire frame on the construction site; the support distribution beam is set There are two, adjust the parallelism of the two supporting distribution beams, and then fix the adjustable bracket on the top of the backing plate;

S2、现场地面拼装胎架的调整:通过激光水平仪测量所有可调支架的高度;调整时,设于同一根支撑分配梁的可调支架之间设有1-2mm的高度差,且位于同一根支撑分配梁中间的可调支架高度大于两边的可调支架的高度,使支撑分配梁呈向上隆起的弧度;现场地面拼装胎架的该种调整方法,是防止位于同一根支撑分配梁中间位置的可调支架因在前期承压较小,导致在后期钢桁架桥梁在拼装作业过程中出现不均匀沉降,造成拼装完成后的钢桁架桥梁出现线型控制不良问题;S2. Adjustment of the on-site ground assembly tire frame: measure the height of all adjustable supports with a laser level; when adjusting, there is a height difference of 1-2mm between the adjustable supports set on the same supporting distribution beam, and they are located on the same The height of the adjustable bracket in the middle of the support distribution beam is greater than the height of the adjustable brackets on both sides, so that the support distribution beam is in an upwardly raised arc; this adjustment method for the tire frame assembled on the ground on site is to prevent the same support distribution beam from being located in the middle Due to the small pressure of the adjustable support in the early stage, uneven settlement of the steel truss bridge in the later stage of assembly operation resulted in poor alignment control of the steel truss bridge after assembly;

S3、现场地面拼装胎架的沉降调整:将钢桁架桥梁各梁段逐段吊放在地面拼装胎架的支撑柱上,并调整好位置,静置3-5天;在此期间,每隔十二小时,用激光水平仪测量测量一次可调支架高度,如发现有可调支架的高度发生变化时,及时予以调整,最终使所有可调支架的高度保持一致,且保证两根支撑分配梁处于同一高度,且呈水平状态;虽然采用现场地面拼装胎架对钢桁架桥梁进行拼装前,为使现场地面拼装胎架的沉降趋于稳定而需静置三天时间,但与传统的高空支撑架所需的管桩孔施工、灌注桩(包括沉台)施工、高空支撑架搭建施工所需的十五天左右的周期相比,其施工周期仍得以大幅降低;S3. Settlement adjustment of the on-site ground-assembled tire frame: hoist each beam section of the steel truss bridge on the support column of the ground-assembled tire frame piece by piece, adjust the position, and let it stand for 3-5 days; during this period, every Twelve hours, use a laser level to measure the height of the adjustable bracket once. If the height of the adjustable bracket changes, adjust it in time, and finally make the height of all adjustable brackets consistent, and ensure that the two support distribution beams are in the same position. The same height, and in a horizontal state; although the steel truss bridge is assembled by using the on-site ground-assembled tire frame, in order to stabilize the settlement of the on-site ground-assembled tire frame, it needs to stand for three days, but it is different from the traditional high-altitude support frame. Compared with the required period of about 15 days for the construction of pipe pile holes, construction of cast-in-place piles (including platform sinking), and construction of high-altitude support frames, the construction period can still be greatly reduced;

S4、钢桁架桥各梁段之间高度差调整:现场地面拼装胎架的沉降趋于稳定后,使用液压千斤顶顶起各梁段,通过在支撑柱上设置垫片,调整钢桁架桥各梁段之间的高度差,该高度差用于控制钢桁架桥在地面拼装完成后的预变形量,保证成桥后钢桁架桥的线型达到所要求的控制线形。S4. Adjustment of the height difference between the beam sections of the steel truss bridge: After the settlement of the assembled tire frame on the site tends to be stable, use hydraulic jacks to jack up each beam section, and adjust the beams of the steel truss bridge by setting gaskets on the supporting columns The height difference between sections is used to control the pre-deformation of the steel truss bridge after the ground assembly is completed, so as to ensure that the line shape of the steel truss bridge reaches the required control line shape after the bridge is completed.

优选的,在某些施工现场,如果场地地基为淤泥质土或湿陷性黄土等软弱土质,荷载力不足时,现场地面放置垫板的位置采用局部换填垫层法,用级配良好的碎石、黏土混合料更换原基础土层;局部换填垫层法的面积为垫板面积的1.5-2倍,深度不低于0.5m;换填垫层后,再通过振动压路机碾压6-8次,以确保现场地面拼装胎架的沉降稳定性。Preferably, in some construction sites, if the ground of the site is soft soil such as silty soil or collapsible loess, and the load capacity is insufficient, the position of the backing plate on the site is partially replaced by the method of replacing the cushion layer with a well-graded Replace the original foundation soil layer with crushed stone and clay mixture; the area of partial cushion replacement method is 1.5-2 times the area of the backing plate, and the depth is not less than 0.5m; -8 times to ensure the settlement stability of the tire frame assembled on the ground on site.

进一步的,双吊车正式抬吊前,须进行预吊测试;预吊测试吊车稳定性,然后钢桁架桥重新设置在调整后的模拟桥墩支架的现场地面拼装胎架上,对钢桁架桥梁进行桥面挠度测试。Furthermore, before the double cranes are officially lifted, a pre-lift test must be carried out; the stability of the crane is tested by the pre-lift, and then the steel truss bridge is reset on the adjusted ground assembly frame of the simulated pier support, and the steel truss bridge is bridged. Face deflection test.

进一步的,每台吊车实际起吊重量不得大于吊车名义最大起吊重量的70-80%。Further, the actual lifting weight of each crane shall not be greater than 70-80% of the nominal maximum lifting weight of the crane.

进一步的,钢桁架桥吊装在桥墩上、且按设计要求就位后,须首先进行预固定,然后才可脱开吊装挂钩,确保钢桁架桥梁固定施工架设的安全。Further, after the steel truss bridge is hoisted on the pier and placed in place according to the design requirements, it must be pre-fixed first, and then the hoisting hook can be disengaged to ensure the safety of the fixed construction of the steel truss bridge.

由于采用如上所述的技术方案,本发明具有如下有益效果:本发明公开的一种钢桁架桥梁无支架施工方法,该方法在施工现场搭建现场地面拼装胎架,钢桁架桥各梁段从加工厂运输至施工现场,在现场地面拼装胎架上进行钢桁架桥各梁段的焊接、铆接拼装;在地面完成钢桁架桥的拼装后,通过双吊车抬吊的方法完成钢桁架桥在桥墩上的架设;该钢桁架桥梁无支架施工方法省去了传统的搭建高空支撑架的施工流程,因此施工周期及施工成本均得到大幅降低,施工安全性也得到大幅提高;同时在地面进行钢桁架桥各梁段的栓接、焊接拼装时,对钢桁架桥梁拼装线性的测量及调整更加方便,使得施工难度得以降低,施工效率和施工质量也得以大幅提高。Due to the adoption of the above-mentioned technical scheme, the present invention has the following beneficial effects: a steel truss bridge without support construction method disclosed by the present invention, the method builds on-site ground-assembled tire frames at the construction site, and each beam section of the steel truss bridge is processed from The steel truss bridge is transported to the construction site, and the steel truss bridge is welded and riveted on the ground assembly tire frame; after the steel truss bridge is assembled on the ground, the steel truss bridge is lifted on the pier by double cranes. The erection of the steel truss bridge without supports saves the traditional construction process of building high-altitude support frames, so the construction period and construction costs are greatly reduced, and the construction safety is also greatly improved; at the same time, the steel truss bridge is carried out on the ground. During the bolting and welding assembly of each beam section, it is more convenient to measure and adjust the linearity of the steel truss bridge assembly, which reduces the construction difficulty and greatly improves the construction efficiency and construction quality.

附图说明Description of drawings

图1为钢桁架桥梁现场拼装示意图;Figure 1 is a schematic diagram of on-site assembly of steel truss bridges;

图2为钢桁架桥梁双机抬吊施工示意图;Figure 2 is a schematic diagram of the construction of a steel truss bridge with two cranes;

图3为现场地面拼装胎架结构示意图;Figure 3 is a schematic diagram of the tire frame assembled on the ground on site;

图4为现场地面拼装胎架结构局部放大示意图;Figure 4 is a partially enlarged schematic diagram of the on-site ground-assembled tire frame structure;

图5为可调支架外观示意图;Figure 5 is a schematic diagram of the appearance of the adjustable bracket;

图6为可调支架结构爆炸示意图;Figure 6 is a schematic diagram of the explosion of the adjustable bracket structure;

图7为支架座外观示意图。Figure 7 is a schematic view of the appearance of the bracket seat.

图中:1.现场地面拼装胎架;1.1、垫板;1.2、可调支架;1.2.1、支架座;1.2.1.1、支撑套筒;1.2.1.1.1、防转销槽;1.2.1.2.1、磁力座孔;1.2.1.2、支撑底座;1.2.1.3、套筒法兰;1.2.2、丝杠;1.2.2.1、防转销;1.2.2.2、防转螺栓;1.2.3、调节螺母;1.2.4、顶板;1.2.5、压块;1.2.6、磁力座;1.2.7、螺栓;1.3、支撑分配梁;1.4、支撑柱;1.5、连接套;2、钢桁架桥;3、吊车;4、桥墩。In the figure: 1. On-site ground assembly tire frame; 1.1, backing plate; 1.2, adjustable bracket; 1.2.1, bracket seat; 1.2.1.1, support sleeve; 1.2.1.1.1, anti-rotation pin groove; 1.2. 1.2.1. Magnetic base hole; 1.2.1.2. Support base; 1.2.1.3. Sleeve flange; 1.2.2. Lead screw; 1.2.2.1. Anti-rotation pin; 1.2.2.2. Anti-rotation bolt; 1.2.3 , adjusting nut; 1.2.4, top plate; 1.2.5, press block; 1.2.6, magnetic base; 1.2.7, bolt; 1.3, supporting distribution beam; 1.4, supporting column; 1.5, connecting sleeve; 2, steel truss Bridge; 3. Crane; 4. Pier.

具体实施方式Detailed ways

通过下面的实施例可以详细的解释本发明,公开本发明的目的旨在保护本发明范围内的一切技术改进。The present invention can be explained in detail through the following examples, and the purpose of disclosing the present invention is to protect all technical improvements within the scope of the present invention.

实施例一:Embodiment one:

一种钢桁架桥梁无支架施工方法,在施工现场平整场地,搭建现场地面拼装胎架1;钢桁架桥各梁段从加工厂运输至施工现场,在现场地面拼装胎架1上进行钢桁架桥各梁段的焊接、铆接施工,完成钢桁架桥2的组装;通过双吊车3抬吊的方法完成钢桁架桥2在桥墩4上的架设;A construction method for a steel truss bridge without support. The site is leveled at the construction site, and the on-site ground assembly tire frame 1 is built; each beam section of the steel truss bridge is transported from the processing plant to the construction site, and the steel truss bridge is constructed on the site ground assembly tire frame 1. The welding and riveting construction of each beam section completes the assembly of the steel truss bridge 2; the erection of the steel truss bridge 2 on the pier 4 is completed by lifting the double crane 3;

在该钢桁架桥梁无支架施工方法中,采用了现场地面拼装胎架1,现场地面拼装胎架1包括:垫板1.1、可调支架1.2、支撑分配梁1.3、支撑柱1.4,具体参见说明书附图3-7;垫板1.1采用600*600、厚度50mm的结构钢板;可调支架1.2包括支架座1.2.1、丝杠1.2.2、调节螺母1.2.3、顶板1.2.4、压块1.2.5;支架座1.2.1包括圆筒状的支撑套筒1.2.1.1,底部焊接有槽钢支撑底座1.2.1.2,支撑套筒1.2.1.1与支撑底座1.2.1.2之间还通过焊接设置有四个加强筋,支撑底座1.2.1.2的底部对称设有磁力座孔1.2.1.2.1;支撑套筒1.2.1.1顶部焊接有圆环状的支撑法兰,支撑法兰端面上设有若干径向的储油槽;支撑套筒1.2.1.1侧壁对称设有贯穿的防转销槽1.2.1.1.1;丝杠1.2.2靠近下端设有防转销孔,丝杠1.2.2活动设置在支架座1.2.1的圆孔中,防转销孔中固定设置有防转销1.2.2.1,防转销1.2.2.1延伸至支架座1.2.1的防转销槽1.2.1.1.1中;调节螺母1.2.3活动设置在丝杠1.2.2上,位于支架座1.2.1顶部,底面与支撑法兰上端面接触,调节螺母1.2.3上下端面均设有径向的储油槽,支撑法兰与调节螺母1.2.3接触面之间的储油槽中涂抹有润滑脂,调节螺母1.2.3外圆周上均布设有六个撬杠孔;丝杠1.2.2顶部设有支撑盘,顶板1.2.4固定设置在丝杠1.2.2顶部的支撑盘上,通过焊接固定连接;顶板1.2.4上设有连接螺栓孔,压块1.2.5通过螺栓活动连接在顶板1.2.4顶面;可调支架1.2配套使用有磁力座1.2.6,磁力座1.2.6为圆柱状,外圆周上设有压紧环,顶部设有转动旋钮;In the steel truss bridge without support construction method, the on-site ground assembly tire frame 1 is adopted. The on-site ground assembly tire frame 1 includes: backing plate 1.1, adjustable bracket 1.2, support distribution beam 1.3, and support column 1.4. For details, refer to the appendix of the manual Figure 3-7; Backing plate 1.1 adopts 600*600, 50mm thick structural steel plate; Adjustable bracket 1.2 includes bracket base 1.2.1, lead screw 1.2.2, adjusting nut 1.2.3, top plate 1.2.4, pressing block 1.2 .5; the bracket seat 1.2.1 includes a cylindrical support sleeve 1.2.1.1, the bottom of which is welded with a channel steel support base 1.2.1.2, and a welding bracket is also arranged between the support sleeve 1.2.1.1 and the support base 1.2.1.2. Four reinforcing ribs, the bottom of the support base 1.2.1.2 is symmetrically provided with a magnetic seat hole 1.2.1.2.1; the top of the support sleeve 1.2.1.1 is welded with a ring-shaped support flange, and there are several diameters on the end surface of the support flange. The side wall of the support sleeve 1.2.1.1 is symmetrically provided with anti-rotation pin grooves 1.2.1.1.1; the screw 1.2.2 is provided with an anti-rotation pin hole near the lower end, and the screw 1.2.2 is movable. In the round hole of the bracket base 1.2.1, an anti-rotation pin 1.2.2.1 is fixedly arranged in the anti-rotation pin hole, and the anti-rotation pin 1.2.2.1 extends to the anti-rotation pin groove 1.2.1.1.1 of the bracket base 1.2.1; The adjusting nut 1.2.3 is movably set on the lead screw 1.2.2, located at the top of the support seat 1.2.1, the bottom surface is in contact with the upper end surface of the supporting flange, and the upper and lower end surfaces of the adjusting nut 1.2.3 are provided with radial oil storage tanks. Grease is smeared in the oil storage tank between the flange and the contact surface of the adjusting nut 1.2.3, and six crowbar holes are evenly distributed on the outer circumference of the adjusting nut 1.2.3; .4 fixedly arranged on the support plate at the top of the lead screw 1.2.2, and fixedly connected by welding; there are connecting bolt holes on the top plate 1.2.4, and the pressure block 1.2.5 is movably connected to the top surface of the top plate 1.2.4 through bolts; The adjustment bracket 1.2 is equipped with a magnetic base 1.2.6, which is cylindrical, with a compression ring on the outer circumference and a rotary knob on the top;

支撑分配梁1.3采用双拼工字钢型材,上下板面均设有若干连接螺栓孔;支撑柱4包括支撑柱本体、支撑柱垫板,支撑柱本体固定设置在调节柱垫板上部中间,支撑柱垫板绕支撑柱本体轴线均布设有四个连接通孔;The supporting distribution beam 1.3 is made of double I-shaped steel profiles, and several connecting bolt holes are provided on the upper and lower plates; Four connection through holes are evenly arranged around the axis of the supporting column body on the column backing plate;

现场地面拼装胎架1的搭建方法为:The construction method of the on-site ground-assembled tire frame 1 is as follows:

S1、现场地面拼装胎架1的搭建:在施工现场预先预平整出拼装场地,用振动压路机反复碾压八次,然后将600*600、厚度50mm的垫板1.1按设计位置平铺在压实的地面上,可调支架1.2临时设置在垫板1.1上,磁力座1.2.6设置在磁力座孔2.1.2.1中;将支撑分配梁1.3固定设置在可调支架1.2顶部,调整可调支架1.2的位置,然后锁紧压块1.2.5的螺栓,使支撑分配梁1.3固定连接在可调支架1.2顶部;支撑柱1.4根据实际需要设置有若干个,将支撑柱1.4固定设置在支撑分配梁1.3顶部,通过螺栓与支撑分配梁1.3固定连接,完成施工现场地面拼装胎架1的初步搭建;支撑分配梁1.3设有两根,调整两根支撑分配梁1.3的平行度,然后旋转磁力座1.2.6的转动旋钮,通过旋转磁力座1.2.6的压紧环使可调支架1.2与垫板1.1固定连接;S1. Construction of on-site ground assembly tire frame 1: Pre-level the assembly site at the construction site, roll it repeatedly eight times with a vibratory roller, and then spread the backing plate 1.1 of 600*600 and thickness of 50mm on the compaction according to the design position On the ground, the adjustable bracket 1.2 is temporarily set on the backing plate 1.1, and the magnetic base 1.2.6 is set in the magnetic base hole 2.1.2.1; the support distribution beam 1.3 is fixed on the top of the adjustable bracket 1.2, and the adjustable bracket 1.2 is adjusted position, and then lock the bolts of the pressure block 1.2.5, so that the support distribution beam 1.3 is fixedly connected to the top of the adjustable bracket 1.2; the support column 1.4 is provided with several according to actual needs, and the support column 1.4 is fixed on the support distribution beam 1.3 The top is fixedly connected with the support distribution beam 1.3 by bolts to complete the preliminary construction of the ground assembly tire frame 1 on the construction site; there are two support distribution beams 1.3, adjust the parallelism of the two support distribution beams 1.3, and then rotate the magnetic base 1.2. 6, the adjustable bracket 1.2 is fixedly connected with the backing plate 1.1 by rotating the compression ring of the magnetic base 1.2.6;

S2、现场地面拼装胎架1的调整:通过激光水平仪测量所有可调支架1.2的高度;当可调支架1.2的高度存在差异时,用撬杠插在调节螺母1.2.3的撬杠孔中,旋转调节螺母1.2.3,使丝杠丝杠1.2.2上下升降;调整时,设于同一根支撑分配梁1.3的可调支架1.2的顶板1.2.4之间设有1-2mm的高度差,且位于同一根支撑分配梁1.3中间的可调支架1.2的顶板1.2.4高度大于两边的可调支架1.2的顶板1.2.4高度;调整完成后,支撑分配梁1.3略微呈向上隆起的弧度;S2. Adjustment of the on-site ground assembly tire frame 1: measure the height of all adjustable brackets 1.2 with a laser level; when there is a difference in the height of the adjustable brackets 1.2, insert a crowbar into the crowbar hole of the adjustment nut 1.2.3, Rotate the adjusting nut 1.2.3 to make the screw screw 1.2.2 go up and down; when adjusting, a height difference of 1-2mm is provided between the top plate 1.2.4 of the adjustable bracket 1.2 of the same supporting distribution beam 1.3, And the height of the top plate 1.2.4 of the adjustable support 1.2 located in the middle of the same support distribution beam 1.3 is higher than the height of the top plate 1.2.4 of the adjustable support 1.2 on both sides; after the adjustment is completed, the support distribution beam 1.3 is slightly raised upward;

S3、现场地面拼装胎架1的沉降调整:将钢桁架桥梁各梁段逐段吊放在地面拼装胎架的支撑柱1.4上,并调整好位置,静置三天;在此期间,每隔十二小时,用激光水平仪测量测量一次可调支架1.2高度,如发现有可调支架1.2的顶板1.2.4的高度发生变化时,及时用撬杠旋转调节螺母1.2.3予以调整,最终使所有可调支架1.2的高度保持一致,保证两根支撑分配梁1.3处于同一高度,且呈水平状态;S3. Settlement adjustment of the on-site ground-assembled tire frame 1: hoist each beam section of the steel truss bridge on the support column 1.4 of the ground-assembled tire frame one by one, adjust the position, and let it stand for three days; during this period, every Twelve hours, measure the height of the adjustable bracket 1.2 once with a laser level, if it is found that the height of the top plate 1.2.4 of the adjustable bracket 1.2 changes, use a crowbar to rotate the adjustment nut 1.2. The height of the adjustable support 1.2 is kept consistent to ensure that the two supporting distribution beams 1.3 are at the same height and are in a horizontal state;

S4、钢桁架桥2各梁段之间高度差调整:现场地面拼装胎架1的沉降趋于稳定后,使用液压千斤顶顶起各梁段,通过在支撑柱1.4上设置垫片,调整钢桁架桥2各梁段之间的高度差,控制钢桁架桥2在地面拼装完成后的预变形量;S4. Adjustment of the height difference between the beam sections of steel truss bridge 2: After the settlement of the ground-assembled tire frame 1 tends to be stable, use a hydraulic jack to lift each beam section, and adjust the steel truss by setting gaskets on the support column 1.4 The height difference between the beam sections of the bridge 2 controls the pre-deformation of the steel truss bridge 2 after the ground assembly is completed;

在现场地面拼装胎架1上完成钢桁架桥梁各梁段的拼装;钢桁架桥梁各梁段在拼装过程中,用激光水平仪动态监测可调支架1.2的高度,当可调支架1.2高度变化超过设定2.0mm时,及时用撬杠旋转调节螺母1.2.3调整可调支架1.2高度,使其保持在设定范围内;The assembly of each beam section of the steel truss bridge is completed on the field ground assembly frame 1; during the assembly process of each beam section of the steel truss bridge, the height of the adjustable support 1.2 is dynamically monitored with a laser level. When the height of the adjustable support 1.2 changes beyond the design When the setting is 2.0mm, use the crowbar to rotate the adjusting nut 1.2.3 in time to adjust the height of the adjustable bracket 1.2 to keep it within the set range;

钢桁架桥梁完成地面拼装后,进行双吊车3整体吊装;在选择吊车时,应对吊车3实际起吊重量重量进行核算,每台吊车3的实际起吊重量不得大于吊车3公称最大起吊重量的70%;如钢桁架桥2总起吊重量为400吨,每台吊车3的实际起吊重量为200吨,以吊车3公称最大起吊重量的70%计算,应选择286吨的吊车,最终选取最大公称起吊重量为300吨的吊车;双吊车3正式抬吊前,须进行预吊测试;预吊测试吊车3稳定性,然后钢桁架桥2重新设置在调整后的现场地面拼装胎架1上,进行桥面挠度测试,测试合格后,通过双吊车3整体抬吊将钢桁架桥2吊装在桥墩4上,并且按设计要求调整到位,首先进行预固定,然后才可脱开吊装挂钩,再进行钢桁架桥梁的正式固定施工。After the steel truss bridge is assembled on the ground, the overall hoisting of the double crane 3 is carried out; when selecting the crane, the actual lifting weight of the crane 3 should be calculated, and the actual lifting weight of each crane 3 should not be greater than 70% of the nominal maximum lifting weight of the crane 3; For example, the total hoisting weight of the steel truss bridge 2 is 400 tons, and the actual hoisting weight of each crane 3 is 200 tons. Based on the calculation of 70% of the nominal maximum hoisting weight of the crane 3, a crane of 286 tons should be selected, and the maximum nominal hoisting weight is finally selected as 300-ton crane; before the double crane 3 is formally lifted, a pre-lift test must be carried out; the pre-lift test is to test the stability of the crane 3, and then the steel truss bridge 2 is reset on the adjusted on-site ground assembly tire frame 1, and the deflection of the bridge deck is carried out Test, after passing the test, the steel truss bridge 2 is hoisted on the pier 4 by the overall lifting of the double crane 3, and adjusted in place according to the design requirements, first pre-fixed, and then the hoisting hook can be disengaged, and then the steel truss bridge Formal fixed construction.

在某些施工现场,如果场地地基为淤泥质土或湿陷性黄土等软弱土质,荷载力不足时,现场地面放置垫板1.1的位置采用局部换填垫层法,用级配良好的碎石、黏土混合料更换原基础土层;局部换填垫层法的面积为垫板面积的2倍,深度为1.0m;换填垫层后,再通过振动压路机碾压8次,以确保现场地面拼装胎架的沉降稳定性。In some construction sites, if the foundation of the site is soft soil such as silt soil or collapsible loess, and the load capacity is insufficient, the position of the backing plate 1.1 on the site ground shall be partially replaced with the cushion layer method, and the well-graded crushed stone shall be used. , clay mixture to replace the original foundation soil layer; the area of the partial pad replacement method is twice the area of the pad, and the depth is 1.0m; after the pad is replaced, it is rolled 8 times by a vibratory roller to ensure that the ground The settlement stability of the assembled tire frame.

本发明未详述部分为现有技术。The unspecified parts of the present invention are prior art.

Claims (7)

1. A steel truss bridge bracket-free construction method is characterized by comprising the following steps: building a site ground assembling jig frame (1) on a construction site leveling site; transporting each girder segment of the steel truss bridge from a processing plant to a construction site, and carrying out welding and riveting construction on each girder segment of the steel truss bridge on an on-site ground assembly jig frame (1) to complete the assembly of the steel truss bridge (2); the erection of the steel truss bridge (2) on the bridge pier (4) is completed by a double crane (3) lifting method.
2. The steel truss bridge bracket-free construction method of claim 1, wherein the method comprises the following steps: the field ground assembling jig frame (1) comprises a base plate (1.1), an adjustable bracket (1.2), a supporting and distributing beam (1.3) and a supporting column (1.4); backing plate (1.1) tiling is in assembling scene ground, and adjustable support (1.2) are fixed to be set up on backing plate (1.1), and support distribution roof beam (1.3) are fixed to be set up at adjustable support (1.2) top, and support column (1.4) are fixed at support distribution roof beam (1.3) top.
3. The steel truss bridge bracket-free construction method according to claim 2, wherein the method comprises the following steps: the construction method of the site ground assembly jig frame (1) comprises the following steps:
s1, building a site ground assembling jig frame (1): pre-flattening an assembly site in a construction site, repeatedly rolling for a plurality of times by using a vibratory roller, then spreading a base plate (1.1) on the compacted ground according to a designed position, and temporarily arranging an adjustable bracket (1.2) on the base plate (1.1); fixedly arranging a supporting distribution beam (1.3) at the top of an adjustable bracket (1.2); the support columns (1.4) are fixedly arranged at the tops of the support distribution beams (1.3), and the preliminary construction of the ground assembly jig frame (1) on the construction site is completed; two support distribution beams (1.3) are arranged, the parallelism of the two support distribution beams (1.3) is adjusted, and then the adjustable bracket (1.2) is fixedly connected to the upper part of the base plate (1.1);
s2, adjusting the field ground assembling jig frame (1): measuring the heights of all adjustable brackets (1.2) by a laser level meter; when in adjustment, the height difference of 1-2mm is arranged between the adjustable brackets (1.2) arranged on the same supporting and distributing beam (1.3), and the height of the adjustable brackets (1.2) positioned in the middle of the same supporting and distributing beam (1.3) is larger than the height of the adjustable brackets (1.2) on two sides, so that the supporting and distributing beam (1.3) is in an upward-raised radian;
s3, sedimentation adjustment of the field ground assembly jig frame (1): each beam section of the steel truss bridge is hung on a supporting column (1.4) of the ground assembly jig frame section by section, the position is adjusted, and the steel truss bridge stands for 3-5 days; during the period, the height of the adjustable support (1.2) is measured and measured once every twelve hours by using a laser level meter, if the height of the adjustable support (1.2) is found to be changed, the height of all the adjustable supports (1.2) is adjusted in time, and finally, the heights of the two support distribution beams (1.3) are kept consistent, so that the two support distribution beams are in the same height and are in a horizontal state;
s4, adjusting the height difference among beam sections of the steel truss bridge (2): the spacer is arranged on the supporting column (1.4), so that the height difference between beam sections of the steel truss bridge (2) is adjusted, and the pre-deformation of the steel truss bridge (2) after the ground assembly is completed is controlled.
4. The steel truss bridge bracket-free construction method according to claim 3, wherein the method comprises the following steps: if necessary, the position of the base plate (1.1) placed on the ground on site adopts a local pad-changing method, and the original basic soil layer is replaced by crushed stone and clay mixture with good grading; the area of the local filling layer replacement method is 1.5-2 times of the area of the backing plate, and the depth is not less than 0.5m; after the cushion layer is replaced, the cushion layer is compacted by a vibratory roller.
5. The steel truss bridge bracket-free construction method of claim 1, wherein the method comprises the following steps: before the double cranes (3) are formally lifted, pre-lifting test is needed; and (3) testing the stability of the crane by pre-hanging, and then resetting the steel truss bridge (2) on the adjusted field ground assembly jig frame (1) to test the deflection of the bridge deck.
6. The steel truss bridge bracket-free construction method of claim 1, wherein the method comprises the following steps: the actual lifting weight of each crane (3) is not more than 70-80% of the nominal maximum lifting weight of the crane (3).
7. The steel truss bridge bracket-free construction method of claim 1, wherein the method comprises the following steps: after the steel truss bridge (2) is hoisted in place, the steel truss bridge is pre-fixed firstly, and then the hoisting hook can be detached.
CN202211743402.1A 2022-12-29 2022-12-29 A kind of construction method of steel truss bridge without support Pending CN116024906A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211743402.1A CN116024906A (en) 2022-12-29 2022-12-29 A kind of construction method of steel truss bridge without support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211743402.1A CN116024906A (en) 2022-12-29 2022-12-29 A kind of construction method of steel truss bridge without support

Publications (1)

Publication Number Publication Date
CN116024906A true CN116024906A (en) 2023-04-28

Family

ID=86080773

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211743402.1A Pending CN116024906A (en) 2022-12-29 2022-12-29 A kind of construction method of steel truss bridge without support

Country Status (1)

Country Link
CN (1) CN116024906A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117266564A (en) * 2023-09-08 2023-12-22 中建八局第三建设有限公司 A health monitoring construction method for long-span subway steel corridors

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204782011U (en) * 2015-06-08 2015-11-18 广西建工集团第五建筑工程有限责任公司 Bed -jig is assembled to height -adjustable steel construction
CN206693642U (en) * 2017-04-24 2017-12-01 中冶建工集团有限公司 A kind of positive assembled ground assembling jig frame of triangular truss
CN108396653A (en) * 2018-03-01 2018-08-14 成都佰人佰思科技有限公司 A kind of steel structural bridge beam construction method
CN113550223A (en) * 2021-08-23 2021-10-26 江苏京沪重工有限公司 Pre-assembly process of truss bridge with double-assembly bolt holes
CN114837086A (en) * 2022-04-23 2022-08-02 安徽中亚钢结构工程有限公司 Integral hoisting construction method for steel structure assembly type trestle

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204782011U (en) * 2015-06-08 2015-11-18 广西建工集团第五建筑工程有限责任公司 Bed -jig is assembled to height -adjustable steel construction
CN206693642U (en) * 2017-04-24 2017-12-01 中冶建工集团有限公司 A kind of positive assembled ground assembling jig frame of triangular truss
CN108396653A (en) * 2018-03-01 2018-08-14 成都佰人佰思科技有限公司 A kind of steel structural bridge beam construction method
CN113550223A (en) * 2021-08-23 2021-10-26 江苏京沪重工有限公司 Pre-assembly process of truss bridge with double-assembly bolt holes
CN114837086A (en) * 2022-04-23 2022-08-02 安徽中亚钢结构工程有限公司 Integral hoisting construction method for steel structure assembly type trestle

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117266564A (en) * 2023-09-08 2023-12-22 中建八局第三建设有限公司 A health monitoring construction method for long-span subway steel corridors

Similar Documents

Publication Publication Date Title
CN102864795B (en) Light steel factory post foundation suitable for sedimentation of filled-in ground and construction method
CN112227232B (en) Pier upright post underpinning method of pier-beam consolidation continuous beam bridge
CN108505522B (en) Pile stabilizing platform
CN206607614U (en) A kind of counterforce device for concrete tubular pile loading test
CN110820950B (en) Integral synchronous jacking construction method for large-span combined type overweight eccentric slope angle steel structure
CN204849607U (en) A continuous beam string basket pre -compaction device for bridge construction
CN105970835B (en) A kind of cable-stayed bridge rotator construction weighing structure and Weighing method
CN110792265A (en) Large-span combined overweight eccentric slope angle steel structure overall synchronous jacking equipment
CN116024906A (en) A kind of construction method of steel truss bridge without support
CN102877657B (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN212336080U (en) Assembled tower crane foundation structure
CN212582721U (en) Bearing platform of tower crane for vertical tower of top plate of foundation garage
CN115420630B (en) Field Load and Direct Shear Test Composite Vertical Loading Mechanism and Its Loading Method
CN202809636U (en) Light steel plant column foundation adapted to filling subgrade settlement
CN217651624U (en) Temporary support for bridge superstructure construction
CN219175021U (en) A steel truss bridge construction site assembled tire frame structure on the ground
CN104763005A (en) Large steel spherical tank inclination rectification method
CN214939311U (en) Prefabricated bridge pier and beam integrated bridge girder erection machine
CN116411520A (en) Control method for linear construction of tower column
CN222456200U (en) Buttress foundation structure for large-tonnage pile foundation static load test
CN201704698U (en) Detachable tower footing
CN111549678A (en) Rapid construction method of prefabricated segmental beam
CN115627694B (en) Construction method of composite support for upper formwork of cast-in-place bridge across debris flow gully
CN223017464U (en) Hydraulic synchronous jacking support changing structure
CN206844680U (en) Steel gallery ground assembly load transfer device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination