CN115977138B - Construction method of equipment foundation base based on metamaterial - Google Patents

Construction method of equipment foundation base based on metamaterial Download PDF

Info

Publication number
CN115977138B
CN115977138B CN202211660855.8A CN202211660855A CN115977138B CN 115977138 B CN115977138 B CN 115977138B CN 202211660855 A CN202211660855 A CN 202211660855A CN 115977138 B CN115977138 B CN 115977138B
Authority
CN
China
Prior art keywords
metamaterial
connecting rod
top surface
oblique connecting
oblique
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211660855.8A
Other languages
Chinese (zh)
Other versions
CN115977138A (en
Inventor
张庆
莫昀璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Agricultural University
Original Assignee
China Agricultural University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Agricultural University filed Critical China Agricultural University
Priority to CN202211660855.8A priority Critical patent/CN115977138B/en
Publication of CN115977138A publication Critical patent/CN115977138A/en
Application granted granted Critical
Publication of CN115977138B publication Critical patent/CN115977138B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Retaining Walls (AREA)

Abstract

The invention relates to a construction method of a device foundation base based on a metamaterial. According to the invention, the metamaterial with the anti-seismic and mechanical impact absorption properties, the sand and the reinforced concrete are integrated together to form the shooting equipment foundation base capable of well absorbing impact energy transmitted from the lower direction of the foundation surface of the equipment, so that the loss of processing precision of the vibration numerical control equipment can be greatly reduced.

Description

一种基于超材料的设备基础基座的施工方法A construction method for a device foundation based on metamaterials

技术领域Technical Field

本发明涉及设备减震技术领域,具体说是一种基于超材料的设备基础基座的施工方法。The invention relates to the technical field of equipment shock absorption, and in particular to a construction method of an equipment foundation pedestal based on metamaterials.

背景技术Background technique

数控机床是高精密加工机床,对设备基础的要求甚高,加工过程中如附近有震动源,震动会传递过来,会影响到数控机床的加工精度。因此传统的数控机床基础,其周围都会有一层防震带,能够隔离横向传播过来的震动。但对于比设备所在基础面还低的震动源,比如数控设备附近,例如十几米范围内的冲压设备在冲压工作时,其震动会从设备底部向上传递上来,影响机床的加工精度。经测量,会影响到加工精度0.01-0.03mm。CNC machine tools are high-precision processing machines, and the requirements for the equipment foundation are very high. If there is a vibration source nearby during the processing, the vibration will be transmitted, which will affect the processing accuracy of the CNC machine tool. Therefore, the foundation of traditional CNC machine tools is surrounded by a layer of shockproof belt to isolate the vibration transmitted laterally. However, for vibration sources that are lower than the foundation surface of the equipment, such as near CNC equipment, for example, when stamping equipment within a range of more than ten meters is working, its vibration will be transmitted from the bottom of the equipment to the top, affecting the processing accuracy of the machine tool. According to measurements, it will affect the processing accuracy by 0.01-0.03mm.

传统的数控机床设备基础,其底部是在素土夯实的基础上,先铺一层100-300mm厚的中砂或者碎石进行夯实,形成设备基础垫层,然后再在上面作100mm厚的C15的混凝土,之后才在上面制作设备基础。这种基础底座,无法减轻或避免从底部向上传来的震动,会影响到数控机床的加工精度。The bottom of the traditional CNC machine tool equipment foundation is based on the rammed soil. First, a layer of 100-300mm thick medium sand or gravel is laid and rammed to form the equipment foundation cushion layer, and then 100mm thick C15 concrete is made on it, and then the equipment foundation is made on it. This kind of foundation base cannot reduce or avoid the vibration transmitted from the bottom to the top, which will affect the processing accuracy of the CNC machine tool.

超材料(Metamaterials)是一种人工设计的材料/结构。人工设计的超材料不仅可用于结构承载,且具备功能材料的特殊性能,通过超材料/结构一体化优化设计可实现负刚度、负折射率、负泊松比、负热膨胀等,尤其是负泊松比超材料具有良好的抗震性能、能够吸收机械冲击能量。Metamaterials are artificially designed materials/structures. Artificially designed metamaterials can not only be used for structural bearing, but also have the special properties of functional materials. Through the integrated optimization design of metamaterials/structures, negative stiffness, negative refractive index, negative Poisson's ratio, negative thermal expansion, etc. can be achieved. In particular, negative Poisson's ratio metamaterials have good seismic resistance and can absorb mechanical impact energy.

发明内容Summary of the invention

针对现有技术中存在的缺陷,本发明的目的在于提供一种基于超材料的设备基础基座的施工方法。该超材料设备基础基座施工方法通过将具备抗震、吸收机械冲击性能的超材料与砂子、钢筋混凝土整合在一起,形成了一种能够很好的吸收从设备所在基础面下方向上传递的冲击能量的设备基础基座,可以大大减轻振动对数控设备的加工精度损失。In view of the defects existing in the prior art, the purpose of the present invention is to provide a construction method of a metamaterial-based equipment foundation. The metamaterial equipment foundation construction method integrates metamaterials with seismic resistance and mechanical impact absorption performance with sand and reinforced concrete to form an equipment foundation that can well absorb the impact energy transmitted upward from the bottom of the foundation where the equipment is located, which can greatly reduce the loss of machining accuracy of CNC equipment caused by vibration.

为达到以上目的,本发明采取的技术方案是:In order to achieve the above purpose, the technical solution adopted by the present invention is:

一种基于超材料的设备基础基座的施工方法,其特征在于,包括如下步骤:A construction method for a metamaterial-based equipment foundation base, characterized in that it comprises the following steps:

步骤1,在底面上挖出矩形的地面槽100,挖出的素土备用;在地面槽100底部的四周上预制底座1和挡土墙2的钢筋之后用水泥浇灌成型,制成底座1和挡土墙2的一体化结构,浇筑的挡土墙2的顶面要与地面齐平,挡土墙2外侧和地面槽100内壁之间用素土填充并夯实;底座槽区域内填充素土并夯实,制成素土层5,素土层5与底座1顶面齐平;Step 1, dig a rectangular ground trough 100 on the bottom surface, and keep the excavated soil for later use; prefabricate the steel bars of the base 1 and the retaining wall 2 on the four sides of the bottom of the ground trough 100, and then cast them with cement to form an integrated structure of the base 1 and the retaining wall 2. The top surface of the cast retaining wall 2 should be flush with the ground, and the outer side of the retaining wall 2 and the inner wall of the ground trough 100 are filled with soil and compacted; the base trough area is filled with soil and compacted to form a soil layer 5, and the soil layer 5 is flush with the top surface of the base 1;

步骤2,将超材料体整齐堆积成方形体3,置于素土层5顶面上,方形体3的四个侧壁分别与挡土墙2内侧壁接触;方形体3内的空隙填充砂子,砂子覆盖方形体3的整个顶面并夯实;Step 2, neatly stack the metamaterial bodies into a square body 3, and place it on the top surface of the plain soil layer 5, so that the four side walls of the square body 3 are in contact with the inner wall of the retaining wall 2 respectively; the gaps in the square body 3 are filled with sand, and the sand covers the entire top surface of the square body 3 and is compacted;

步骤3,在方形体3顶面的砂子顶上浇筑混凝土,制成覆盖整个砂子顶的砼垫层4;Step 3, pouring concrete on the top of the sand on the top surface of the square body 3 to form a concrete cushion layer 4 covering the entire top of the sand;

步骤4,在砼垫层4上预制钢筋,之后用水泥浇灌成基础座6,浇筑的基础座6的顶面与地面齐平,基础座6的四个面与其对应挡土墙2的内侧面之间留有间距,形成抗震沟17;基础座6的顶面上放置设备。Step 4, prefabricate steel bars on the concrete cushion layer 4, and then pour cement to form a foundation seat 6. The top surface of the poured foundation seat 6 is flush with the ground, and there is a gap between the four surfaces of the foundation seat 6 and the inner side surfaces of the corresponding retaining wall 2 to form an earthquake-resistant trench 17; equipment is placed on the top surface of the foundation seat 6.

在上述方案的基础上,方形体3由超材料体堆积而成;On the basis of the above scheme, the square body 3 is formed by stacking metamaterial bodies;

所述超材料体包括底板7、顶板8和四块垂直侧板9,底板7的顶面中心和顶板8的底面中心分别设有同一轴向的垂直连杆Ⅰ10和竖直连杆Ⅱ11;每块垂直侧板9的内侧面中心均设有水平连杆12,相对的竖直侧板9上的水平连杆12轴向相同;The metamaterial body comprises a bottom plate 7, a top plate 8 and four vertical side plates 9. A vertical connecting rod Ⅰ10 and a vertical connecting rod Ⅱ11 with the same axial direction are respectively arranged at the center of the top surface of the bottom plate 7 and the center of the bottom surface of the top plate 8; a horizontal connecting rod 12 is arranged at the center of the inner side surface of each vertical side plate 9, and the horizontal connecting rods 12 on the opposite vertical side plates 9 have the same axial direction;

垂直连杆Ⅰ10的顶端设有四条斜连杆Ⅰ13,各条斜连杆Ⅰ13向外倾斜向下设置;竖直连杆Ⅱ11的底端设有四条斜连杆Ⅱ14,各条斜连杆Ⅱ14向外倾斜向上设置;The top of the vertical link Ⅰ10 is provided with four oblique links Ⅰ13, each oblique link Ⅰ13 is arranged outwardly and downwardly; the bottom of the vertical link Ⅱ11 is provided with four oblique links Ⅱ14, each oblique link Ⅱ14 is arranged outwardly and upwardly;

各水平连杆12的末端分别设有斜连杆Ⅲ15、斜连杆Ⅳ16;斜连杆Ⅲ15向外倾斜向下设置,斜连杆Ⅲ15的末端与对应的斜连杆Ⅰ13的末端连接;斜连杆Ⅳ16向外倾斜向上设置,斜连杆Ⅳ16的末端与对应的斜连杆Ⅱ14的末端连接。The ends of each horizontal link 12 are respectively provided with an oblique link III15 and an oblique link IV16; the oblique link III15 is arranged outwardly and tilted downward, and the end of the oblique link III15 is connected to the end of the corresponding oblique link I13; the oblique link IV16 is arranged outwardly and tilted upward, and the end of the oblique link IV16 is connected to the end of the corresponding oblique link II14.

在上述方案的基础上,On the basis of the above scheme,

所述方形体3的具体结构为:位于上方的超材料体的底板7置于下方的超材料体的顶板8上,并与其对齐;位于左侧的超材料体的右竖直侧板9与右侧的超材料体的左竖直侧板9对齐并相互接触;位于前侧的超材料体的后竖直侧板9与后侧的超材料体的前竖直侧板9对齐并相互接触。The specific structure of the square body 3 is as follows: the bottom plate 7 of the metamaterial body located above is placed on the top plate 8 of the metamaterial body below and is aligned with it; the right vertical side plate 9 of the metamaterial body located on the left is aligned with the left vertical side plate 9 of the metamaterial body on the right and contacts each other; the rear vertical side plate 9 of the metamaterial body located on the front side is aligned with the front vertical side plate 9 of the metamaterial body on the rear side and contacts each other.

在上述方案的基础上,所述超材料体的制备方法为:On the basis of the above scheme, the preparation method of the metamaterial body is:

制作对应超材料体外形的树脂模具;Making a resin mold corresponding to the shape of the metamaterial body;

将SYLGARD-184聚二甲硅氧烷和SYLGARD-184有机硅弹性体固化剂按照7∶1的比例混合;Mix SYLGARD-184 polydimethylsiloxane and SYLGARD-184 silicone elastomer curing agent in a ratio of 7:1;

上述混合物在室温下静置12小时,待混合液体中的气泡完全排出之后,倒入树脂模具中加热成型;The mixture is allowed to stand at room temperature for 12 hours, and after the bubbles in the mixed liquid are completely discharged, it is poured into a resin mold and heated for molding;

超材料体成型后在室温下冷却静置,待完全固化后去除树脂模具。After the metamaterial body is formed, it is cooled and left to stand at room temperature, and the resin mold is removed after it is completely solidified.

在上述方案的基础上,On the basis of the above scheme,

步骤3中所述砼垫层4的厚度为80-130mm。The thickness of the concrete cushion layer 4 in step 3 is 80-130 mm.

本发明所述的一种基于超材料的设备基础基座的施工方法,其有益效果为:The construction method of a metamaterial-based equipment foundation base described in the present invention has the following beneficial effects:

(1)利用硅橡胶超材料体的优异抗震和吸能性能,配合砂子、混凝土构件,形成了一种能够很好的吸收地底向上传递的振动的基础基座,该基础基座上放置数控设备,能够有效降低振动对数控设备的加工精度的影响,能够使得震动对加工精度降低90%以上。(1) By utilizing the excellent anti-seismic and energy-absorbing properties of silicone rubber metamaterials, combined with sand and concrete components, a base pedestal is formed that can effectively absorb the vibration transmitted upward from the ground. CNC equipment is placed on the base pedestal, which can effectively reduce the impact of vibration on the processing accuracy of the CNC equipment, and can reduce the impact of vibration on processing accuracy by more than 90%.

(2)上述设备基础基座的施工方法充分考虑了生产车间实际条件,施工方法操作科学合理,便于执行,并且施工周期较短。(2) The construction method of the above-mentioned equipment foundation fully considers the actual conditions of the production workshop. The construction method is scientific and reasonable, easy to implement, and has a short construction period.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

本发明有如下附图:The present invention has the following accompanying drawings:

图1为本发明提供的超材料设备基础基座的结构示意图;FIG1 is a schematic structural diagram of a metamaterial device base provided by the present invention;

图2为本发明提供的超材料体的结构示意图;FIG2 is a schematic diagram of the structure of a metamaterial body provided by the present invention;

图3为本发明提供的超材料体去掉前侧的竖直侧板的结构示意图;FIG3 is a schematic structural diagram of a metamaterial body provided by the present invention without the vertical side plate on the front side;

图4为本发明提供的超材料体堆积形成的方形体的结构示意图。FIG. 4 is a schematic structural diagram of a square body formed by stacking metamaterial bodies provided by the present invention.

图中:100、地面槽;1、底座;2、挡土墙;3、方形体,4、砼垫层,5、素土层,6、基础座,7、底板,8、顶板,9、竖直侧板,10、竖直连杆Ⅰ,11、竖直连杆Ⅱ,12、水平连杆,13、斜连杆Ⅰ,14、斜连杆Ⅱ,15、斜连杆Ⅲ,16、斜连杆Ⅳ,17、抗震沟。In the figure: 100, ground trough; 1, base; 2, retaining wall; 3, square body, 4, concrete cushion layer, 5, plain soil layer, 6, foundation seat, 7, bottom plate, 8, top plate, 9, vertical side plate, 10, vertical connecting rod I, 11, vertical connecting rod II, 12, horizontal connecting rod, 13, oblique connecting rod I, 14, oblique connecting rod II, 15, oblique connecting rod III, 16, oblique connecting rod IV, 17, seismic trench.

具体实施方式Detailed ways

以下结合附图对本发明作进一步详细说明。The present invention is further described in detail below in conjunction with the accompanying drawings.

如图2、3所示,本发明所述的超材料体包括底板7、顶板8、竖直侧板9、竖直连杆Ⅰ10、竖直连杆Ⅱ11、水平连杆12、斜连杆Ⅰ13、斜连杆Ⅱ14、斜连杆Ⅲ15、斜连杆Ⅳ16;竖直侧板9设有四组,底板7、顶板8、竖直侧板9均为大小相同的正方形板体;四组竖直侧板9分别与底板7、顶板8的四个侧面平行;底板7顶面中心和顶板8的底面中心分别设有同一轴向的竖直连杆Ⅰ10和竖直连杆Ⅱ11;竖直连杆Ⅰ10的顶端设有四组斜连杆Ⅰ13,斜连杆Ⅰ13向外倾斜向下设置;竖直连杆Ⅱ11的下端设有四组斜连杆Ⅱ14,斜连杆Ⅱ14向外倾斜向上设置;竖直侧板9的内侧面中心分别设有一组水平连杆12,相对的竖直侧板9上的水平连杆12轴向相同;各组水平连杆12的末端分别设有斜连杆Ⅲ15、斜连杆Ⅳ16;斜连杆Ⅲ15向外倾斜向下设置,其末端与斜连杆Ⅰ13的末端连接;斜连杆Ⅳ16向外倾斜向上设置,其末端与斜连杆Ⅱ14的末端连接;As shown in Fig. 2 and Fig. 3, the metamaterial body of the present invention comprises a bottom plate 7, a top plate 8, a vertical side plate 9, a vertical connecting rod I 10, a vertical connecting rod II 11, a horizontal connecting rod 12, an oblique connecting rod I 13, an oblique connecting rod II 14, an oblique connecting rod III 15, and an oblique connecting rod IV 16; the vertical side plates 9 are provided with four groups, and the bottom plate 7, the top plate 8, and the vertical side plates 9 are all square plates of the same size; the four groups of vertical side plates 9 are parallel to the four side surfaces of the bottom plate 7 and the top plate 8 respectively; the center of the top surface of the bottom plate 7 and the center of the bottom surface of the top plate 8 are respectively provided with a vertical connecting rod I 10 and a vertical connecting rod II 11 of the same axial direction; the top end of the vertical connecting rod I 10 Four groups of oblique connecting rods Ⅰ13 are provided, and the oblique connecting rods Ⅰ13 are arranged outwardly and tilted downward; four groups of oblique connecting rods Ⅱ14 are provided at the lower end of the vertical connecting rod Ⅱ11, and the oblique connecting rods Ⅱ14 are arranged outwardly and tilted upward; a group of horizontal connecting rods 12 are respectively provided at the center of the inner side surface of the vertical side plate 9, and the horizontal connecting rods 12 on the opposite vertical side plates 9 have the same axial direction; the ends of each group of horizontal connecting rods 12 are respectively provided with oblique connecting rods Ⅲ15 and oblique connecting rods Ⅳ16; the oblique connecting rod Ⅲ15 is arranged outwardly and tilted downward, and its end is connected to the end of the oblique connecting rod Ⅰ13; the oblique connecting rod Ⅳ16 is arranged outwardly and tilted upward, and its end is connected to the end of the oblique connecting rod Ⅱ14;

竖直连杆Ⅰ10、竖直连杆Ⅱ11、水平连杆12的直径为12-20mm,斜连杆Ⅰ13、斜连杆Ⅱ14、斜连杆Ⅲ15、斜连杆Ⅳ16的直径为8-12mmThe diameters of the vertical connecting rod Ⅰ10, the vertical connecting rod Ⅱ11, and the horizontal connecting rod 12 are 12-20 mm , and the diameters of the oblique connecting rod Ⅰ13, the oblique connecting rod Ⅱ14, the oblique connecting rod Ⅲ15, and the oblique connecting rod Ⅳ16 are 8-12 mm .

每组水平连杆12及其对应的斜连杆Ⅰ13、斜连杆Ⅱ14、斜连杆Ⅲ15、斜连杆Ⅳ16组成的结构中:水平连杆12与斜连杆Ⅲ15的夹角、水平连杆12与斜连杆Ⅳ16的夹角均为60°;斜连杆Ⅲ15与斜连杆Ⅰ13的夹角、斜连杆Ⅳ16和斜连杆Ⅱ14的夹角均为30°;斜连杆Ⅰ13与竖直连杆Ⅰ10的夹角、斜连杆Ⅱ14与竖直连杆Ⅱ11的夹角均为60°;并且,这些连杆的轴线位于同一竖直面内。In the structure composed of each group of horizontal connecting rods 12 and their corresponding oblique connecting rods Ⅰ13, Ⅱ14, Ⅲ15 and Ⅳ16: the angle between the horizontal connecting rod 12 and the oblique connecting rod Ⅲ15, and the angle between the horizontal connecting rod 12 and the oblique connecting rod Ⅳ16 are both 60°; the angle between the oblique connecting rod Ⅲ15 and the oblique connecting rod Ⅰ13, and the angle between the oblique connecting rod Ⅳ16 and the oblique connecting rod Ⅱ14 are both 30°; the angle between the oblique connecting rod Ⅰ13 and the vertical connecting rod Ⅰ10, and the angle between the oblique connecting rod Ⅱ14 and the vertical connecting rod Ⅱ11 are both 60°; and the axes of these connecting rods are located in the same vertical plane.

上述超材料体的制备方法包括以下步骤:The method for preparing the metamaterial body comprises the following steps:

制作树脂模具,然后将SYLGARD-184聚二甲硅氧烷和SYLGARD-184有机硅弹性体固化剂按照7∶1的比例混合,并在室温下静置12小时,待混合液体中的气泡完全排出之后,再将其倒入事先准备好的树脂模具中并进行烘烤,然后室温冷却静置,待其完全固化后冷却,将树脂模具去除,即得。Make a resin mold, then mix SYLGARD-184 polydimethylsiloxane and SYLGARD-184 silicone elastomer curing agent in a ratio of 7:1, and let it stand at room temperature for 12 hours. After the bubbles in the mixed liquid are completely discharged, pour it into the pre-prepared resin mold and bake it, then cool it to room temperature and let it stand. After it is completely cured, cool it and remove the resin mold.

如图1、4所示,超材料设备基础基座的施工方法,包括以下步骤:As shown in FIGS. 1 and 4 , the construction method of the metamaterial device foundation base includes the following steps:

A、在地面上挖出方形的地面槽,挖出的素土备用;在地面槽100底部四周上预制底座1和挡土墙2的钢筋,之后用水泥浇灌成型制成混凝土组合件,挡土墙2顶面与地面齐平,挡土墙2外侧和地面槽内壁之间用素土填充并夯实;底座1和挡土墙2围成的底座槽区域内填充素土并夯实,制成素土层5,素土层5与底座1顶面齐平;A. Dig a square ground trough on the ground, and keep the excavated soil for later use; prefabricate the steel bars of the base 1 and the retaining wall 2 around the bottom of the ground trough 100, and then pour cement to form a concrete assembly, the top surface of the retaining wall 2 is flush with the ground, and the space between the outer side of the retaining wall 2 and the inner wall of the ground trough is filled with soil and compacted; fill the base trough area surrounded by the base 1 and the retaining wall 2 with soil and compact it to form a soil layer 5, and the soil layer 5 is flush with the top surface of the base 1;

B、将超材料体整齐堆积成方形体3,置于素土层5顶面上,方形体3的四个侧壁分别与挡土墙2内侧壁接触;方形体3内的空隙上填充砂子,砂子覆盖方形体3的整个顶面并夯实;B. neatly stack the metamaterial bodies into a square body 3, and place it on the top surface of the plain soil layer 5, so that the four side walls of the square body 3 are in contact with the inner wall of the retaining wall 2 respectively; fill the gaps in the square body 3 with sand, and the sand covers the entire top surface of the square body 3 and is compacted;

超材料体堆积成方形体3的具体结构为:位于上方的超材料体的底板7置于下方的超材料体的顶板8上,并与其对齐;位于左侧的超材料体的右竖直侧板9与右侧的超材料体的左竖直侧板9对齐并相互接触;位于前侧的超材料体的后竖直侧板9与后侧的超材料体的前竖直侧板9对齐并相互接触。暨超材料体层层堆积成方形体3,各超材料体的各个侧板9相互接触对齐;另外,除了最顶层的和最底层的超材料体之外,各超材料体的顶板8与其上方的超材料体的底板7接触并对齐,各超材料体的底板7与其下方的超材料体的顶板8接触并对齐。The specific structure of the metamaterial bodies stacked into a square body 3 is as follows: the bottom plate 7 of the metamaterial body located above is placed on the top plate 8 of the metamaterial body below and aligned with it; the right vertical side plate 9 of the metamaterial body located on the left is aligned with the left vertical side plate 9 of the metamaterial body on the right and in contact with each other; the rear vertical side plate 9 of the metamaterial body located on the front side is aligned with the front vertical side plate 9 of the metamaterial body on the rear side and in contact with each other. The metamaterial bodies are stacked layer by layer into a square body 3, and the side plates 9 of each metamaterial body are in contact and aligned with each other; in addition, except for the top and bottom metamaterial bodies, the top plate 8 of each metamaterial body is in contact and aligned with the bottom plate 7 of the metamaterial body above it, and the bottom plate 7 of each metamaterial body is in contact and aligned with the top plate 8 of the metamaterial body below it.

C、方形体3顶面的砂子顶上浇筑C15混凝土,制成覆盖整个砂子顶面的砼垫层4;C. Pour C15 concrete on the top of the sand on the top surface of the square body 3 to form a concrete cushion 4 covering the entire top surface of the sand;

D、砼垫层4上预制钢筋,之后用水泥浇灌成型,制成基础座6,基础座6顶面与地面齐平,基础座6四个面与其对应挡土墙2的内侧面之间留有200mm间距,形成抗震沟17;基础座6顶面上放置设备。D. Prefabricated steel bars are placed on the concrete cushion layer 4 and then poured with cement to form a foundation seat 6. The top surface of the foundation seat 6 is flush with the ground. A 200mm gap is left between the four surfaces of the foundation seat 6 and the inner side surfaces of the corresponding retaining wall 2 to form an earthquake-resistant trench 17. Equipment is placed on the top surface of the foundation seat 6.

本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

Claims (3)

1.一种基于超材料的设备基础基座的施工方法,其特征在于,包括如下步骤:1. A construction method for a metamaterial-based equipment foundation, characterized in that it comprises the following steps: 步骤1,在底面上挖出矩形的地面槽(100),挖出的素土备用;在地面槽(100)底部的四周上预制底座(1)和挡土墙(2)的钢筋之后用水泥浇灌成型,制成底座(1)和挡土墙(2)的一体化结构,浇筑的挡土墙(2)的顶面要与地面齐平,挡土墙(2)外侧和地面槽(100)内壁之间用素土填充并夯实;底座槽区域内填充素土并夯实,制成素土层(5),素土层(5)与底座(1)顶面齐平;Step 1, digging a rectangular ground trough (100) on the bottom surface, and keeping the excavated soil for later use; prefabricating the steel bars of the base (1) and the retaining wall (2) on the four sides of the bottom of the ground trough (100), and then pouring cement to form an integrated structure of the base (1) and the retaining wall (2); the top surface of the cast retaining wall (2) should be flush with the ground, and the outer side of the retaining wall (2) and the inner wall of the ground trough (100) are filled with soil and compacted; the base trough area is filled with soil and compacted to form a soil layer (5), and the soil layer (5) is flush with the top surface of the base (1); 步骤2,将超材料体整齐堆积成方形体(3),置于素土层(5)顶面上,方形体(3)的四个侧壁分别与挡土墙(2)内侧壁接触;方形体(3)内的空隙填充砂子,砂子覆盖方形体(3)的整个顶面并夯实;Step 2, neatly stacking the metamaterial bodies into a square body (3), placing the square body (3) on the top surface of the plain soil layer (5), with the four side walls of the square body (3) respectively contacting the inner wall of the retaining wall (2); filling the gaps in the square body (3) with sand, with the sand covering the entire top surface of the square body (3) and compacting it; 步骤3,在方形体(3)顶面的砂子顶上浇筑混凝土,制成覆盖整个砂子顶的砼垫层(4);Step 3, pouring concrete on the top of the sand on the top surface of the square body (3) to form a concrete cushion layer (4) covering the entire top of the sand; 步骤4,在砼垫层(4)上预制钢筋,之后用水泥浇灌成基础座(6),浇筑的基础座(6)的顶面与地面齐平,基础座(6)的四个面与其对应挡土墙(2)的内侧面之间留有间距,形成抗震沟(17);基础座(6)的顶面上放置设备;Step 4, prefabricating steel bars on the concrete cushion layer (4), and then pouring cement to form a foundation seat (6), the top surface of the poured foundation seat (6) is flush with the ground, and a gap is left between the four surfaces of the foundation seat (6) and the inner side surface of the corresponding retaining wall (2), forming an earthquake-resistant groove (17); placing equipment on the top surface of the foundation seat (6); 所述方形体(3)由超材料体堆积而成;The square body (3) is formed by stacking metamaterial bodies; 所述超材料体包括底板(7)、顶板(8)和四块垂直侧板(9),底板(7)的顶面中心和顶板(8)的底面中心分别设有同一轴向的垂直连杆Ⅰ(10)和竖直连杆Ⅱ(11);每块垂直侧板(9)的内侧面中心均设有水平连杆(12),相对的竖直侧板(9)上的水平连杆(12)轴向相同;The metamaterial body comprises a bottom plate (7), a top plate (8) and four vertical side plates (9); a vertical connecting rod I (10) and a vertical connecting rod II (11) with the same axial direction are respectively arranged at the center of the top surface of the bottom plate (7) and the center of the bottom surface of the top plate (8); a horizontal connecting rod (12) is arranged at the center of the inner side surface of each vertical side plate (9); and the horizontal connecting rods (12) on the opposite vertical side plates (9) have the same axial direction; 垂直连杆Ⅰ(10)的顶端设有四条斜连杆Ⅰ(13),各条斜连杆Ⅰ(13)向外倾斜向下设置;竖直连杆Ⅱ(11)的底端设有四条斜连杆Ⅱ(14),各条斜连杆Ⅱ(14)向外倾斜向上设置;The top end of the vertical connecting rod I (10) is provided with four oblique connecting rods I (13), each of which is inclined outward and downward; the bottom end of the vertical connecting rod II (11) is provided with four oblique connecting rods II (14), each of which is inclined outward and upward; 各水平连杆(12)的末端分别设有斜连杆Ⅲ(15)、斜连杆Ⅳ(16);斜连杆Ⅲ(15)向外倾斜向下设置,斜连杆Ⅲ(15)的末端与对应的斜连杆Ⅰ(13)的末端连接;斜连杆Ⅳ(16)向外倾斜向上设置,斜连杆Ⅳ(16)的末端与对应的斜连杆Ⅱ(14)的末端连接;The ends of each horizontal connecting rod (12) are respectively provided with an oblique connecting rod III (15) and an oblique connecting rod IV (16); the oblique connecting rod III (15) is arranged outwardly and tilted downward, and the end of the oblique connecting rod III (15) is connected to the end of the corresponding oblique connecting rod I (13); the oblique connecting rod IV (16) is arranged outwardly and tilted upward, and the end of the oblique connecting rod IV (16) is connected to the end of the corresponding oblique connecting rod II (14); 所述超材料体的制备方法为:The preparation method of the metamaterial body is: 制作对应超材料体外形的树脂模具;Making a resin mold corresponding to the shape of the metamaterial body; 将SYLGARD-184聚二甲硅氧烷和SYLGARD-184有机硅弹性体固化剂按照7∶1的比例混合;Mix SYLGARD-184 polydimethylsiloxane and SYLGARD-184 silicone elastomer curing agent in a ratio of 7:1; 上述混合物在室温下静置12小时,待混合液体中的气泡完全排出之后,倒入树脂模具中加热成型;The mixture is allowed to stand at room temperature for 12 hours, and after the bubbles in the mixed liquid are completely discharged, it is poured into a resin mold and heated for molding; 超材料体成型后在室温下冷却静置,待完全固化后去除树脂模具。After the metamaterial body is formed, it is cooled and left to stand at room temperature, and the resin mold is removed after it is completely solidified. 2.如权利要求1所述的一种基于超材料的设备基础基座的施工方法,其特征在于:2. The construction method of a metamaterial-based equipment foundation base according to claim 1, characterized in that: 所述方形体(3)的具体结构为:位于上方的超材料体的底板(7)置于下方的超材料体的顶板(8)上,并与其对齐;位于左侧的超材料体的右竖直侧板(9)与右侧的超材料体的左竖直侧板(9)对齐并相互接触;位于前侧的超材料体的后竖直侧板(9)与后侧的超材料体的前竖直侧板(9)对齐并相互接触。The specific structure of the square body (3) is as follows: the bottom plate (7) of the metamaterial body located at the top is placed on the top plate (8) of the metamaterial body located at the bottom and is aligned with it; the right vertical side plate (9) of the metamaterial body located at the left is aligned with the left vertical side plate (9) of the metamaterial body at the right and they are in contact with each other; the rear vertical side plate (9) of the metamaterial body located at the front is aligned with the front vertical side plate (9) of the metamaterial body at the rear and they are in contact with each other. 3.一种如权利要求1所述的基于超材料的设备基础基座的施工方法,其特征在于:3. A construction method for a metamaterial-based device foundation according to claim 1, characterized in that: 步骤3中所述砼垫层(4)的厚度为80-130mm。The thickness of the concrete cushion layer (4) in step 3 is 80-130 mm.
CN202211660855.8A 2022-12-22 2022-12-22 Construction method of equipment foundation base based on metamaterial Active CN115977138B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211660855.8A CN115977138B (en) 2022-12-22 2022-12-22 Construction method of equipment foundation base based on metamaterial

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211660855.8A CN115977138B (en) 2022-12-22 2022-12-22 Construction method of equipment foundation base based on metamaterial

Publications (2)

Publication Number Publication Date
CN115977138A CN115977138A (en) 2023-04-18
CN115977138B true CN115977138B (en) 2024-06-18

Family

ID=85964232

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211660855.8A Active CN115977138B (en) 2022-12-22 2022-12-22 Construction method of equipment foundation base based on metamaterial

Country Status (1)

Country Link
CN (1) CN115977138B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101522A (en) * 2020-01-13 2020-05-05 戴向胜 Transverse oblique connection truss support structure assembly
CN211498941U (en) * 2019-12-12 2020-09-15 中建二局第三建筑工程有限公司 Concrete retaining wall structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100736269B1 (en) * 2006-03-24 2007-07-06 주식회사 스마텍엔지니어링 Indented block retaining wall with continuous through hole in vertical direction and construction method
KR101871186B1 (en) * 2018-02-09 2018-06-27 조문선 Retaining Wall Construction Method
KR102224943B1 (en) * 2020-09-18 2021-03-09 김인성 Precast retaing wall structure with improved seismic performance and construction method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN211498941U (en) * 2019-12-12 2020-09-15 中建二局第三建筑工程有限公司 Concrete retaining wall structure
CN111101522A (en) * 2020-01-13 2020-05-05 戴向胜 Transverse oblique connection truss support structure assembly

Also Published As

Publication number Publication date
CN115977138A (en) 2023-04-18

Similar Documents

Publication Publication Date Title
CN101935995B (en) Rockfill concrete and cemented sand and gravel composite dam and its design and construction method
CN107945646A (en) A kind of assembled tunnel model structure and preparation method thereof
CN111660409A (en) Large-span tunnel lining model prefabricating device and method in geomechanical model test
CN105401592A (en) Shock-insulation and vibration-reduction table and construction method thereof
CN115977138B (en) Construction method of equipment foundation base based on metamaterial
CN117668973A (en) Tunnel anchor rock bearing arch safety coefficient verification and correction method
CN104297029B (en) For making the die trial of mine tailing-filled slip test block
CN219261098U (en) Equipment foundation base based on metamaterial
CN111676739A (en) A kind of foam lightweight soil structure and construction method applied to large-scale filling engineering
CN108956226B (en) Large-size cement soil test piece forming device and forming method
CN218027787U (en) A connection structure used for stiffness adjustment device and prefabricated hollow pile
CN117847145A (en) A seismic isolation device and method based on inner hexagonal negative Poisson's ratio super foundation
CN102505794A (en) Heat-preservation building block and production method thereof
CN216552495U (en) Concrete temperature release area
CN101324094A (en) Ball type relief component cast-in-situ hollow building roof and construction method thereof
CN210194456U (en) Steel bellows culvert fill structure
CN220927857U (en) Energy storage protection foundation pouring template construction structure
CN111425704B (en) Spliced air floatation vibration isolation platform and mounting method
CN110469042A (en) A kind of prefabricated wallboard, its manufacturing method and its mold
CN205116120U (en) An assembled U-shaped channel
CN221502013U (en) Light backfill structure for pipeline
CN222880212U (en) A double-mass vibration isolation structure for a boiling cooling bed
CN120206618A (en) A method for preparing a special-shaped curved surface table mold
CN222719277U (en) Material freeze-thawing resistance performance test mould
CN113882210B (en) Asphalt pavement structure with three-dimensional space honeycomb structure with zero Poisson effect

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant