CN115928957A - A kind of unorganized drainage system of aluminum plate flat roof and its installation method - Google Patents
A kind of unorganized drainage system of aluminum plate flat roof and its installation method Download PDFInfo
- Publication number
- CN115928957A CN115928957A CN202211613043.8A CN202211613043A CN115928957A CN 115928957 A CN115928957 A CN 115928957A CN 202211613043 A CN202211613043 A CN 202211613043A CN 115928957 A CN115928957 A CN 115928957A
- Authority
- CN
- China
- Prior art keywords
- aluminum
- roof
- aluminum plate
- catchment
- corner
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A20/00—Water conservation; Efficient water supply; Efficient water use
- Y02A20/108—Rainwater harvesting
Landscapes
- Building Environments (AREA)
Abstract
Description
技术领域technical field
本发明涉及铝板平屋顶排水技术领域,具体涉及一种铝板平屋顶无组织排水系统及其安装方法。The invention relates to the technical field of aluminum plate flat roof drainage, in particular to an aluminum plate flat roof unorganized drainage system and an installation method thereof.
背景技术Background technique
建筑物作为生活与工作的场所,实用性与美观性是最基本的要求,但屋面排水问题多年来一直未得到有效的解决,建筑屋面渗漏成为影响人民居住水平提高的一个最常见的质量通病。Buildings are places for living and working, practicality and aesthetics are the most basic requirements, but the problem of roof drainage has not been effectively solved for many years, building roof leakage has become one of the most common quality problems that affect the improvement of people's living standards .
屋面排水设计的因素包括:地域设计暴雨强度与屋面坡度大小。屋面排水通常采用无组织排水或有组织排水方式,根据规范要求大中型屋面与对屋面排水有特殊要求的通常采用有组织排水方式,对于中小型屋面与对屋面排水无特殊要求通常采用无组织排水方式。无组织排水又称为自由落水,是指屋面雨水直接从檐口落至室外地面的一种排水方式,具有构造简单、造价低廉的优点。对于中小型屋面设计时为满足排水要求,屋面沿排水坡度方向需要设置出墙面一定宽度的排水用檐口与滴水线,但雨水自由落下会溅湿墙面,外墙墙脚常被飞溅的雨水侵蚀,影响到外墙的坚固耐久性。有时为满足立面与屋面完美交接效果,保证墙立面防水没问题的情况下对屋面排水问题不做过多考虑,使雨水沿墙面自由向下流淌,此时,不仅存在腐蚀墙面的情况,还可能影响人行道的交通。Factors in roof drainage design include: regional design rainstorm intensity and roof slope. Roof drainage usually adopts unorganized drainage or organized drainage. According to the specifications, large and medium-sized roofs and those with special requirements for roof drainage usually adopt organized drainage. For small and medium-sized roofs and those without special requirements for roof drainage, unorganized drainage is usually used. Way. Unorganized drainage, also known as free fall, refers to a drainage method in which roof rainwater falls directly from the cornice to the outdoor ground. It has the advantages of simple structure and low cost. In order to meet the drainage requirements in the design of small and medium-sized roofs, it is necessary to set a drainage cornice and drip line with a certain width on the wall along the direction of the drainage slope, but the rainwater falling freely will splash the wall, and the foot of the outer wall is often eroded by splashing rainwater , affecting the firmness and durability of the exterior wall. Sometimes in order to meet the perfect transition effect between the facade and the roof, and ensure that the wall and facade are waterproof, the roof drainage problem is not considered too much, so that the rainwater flows freely down the wall. At this time, not only the wall is corroded The situation may also affect the traffic on the sidewalk.
发明内容Contents of the invention
发明目的:本发明目的在于针对现有技术的不足,提供一种铝板平屋顶无组织排水系统及其安装方法,通过改变屋面雨水排水方向,使雨水汇集一处,设置简易排水檐口,满足屋面排水效果,保证建筑外立面整体设计造型。Purpose of the invention: The purpose of the invention is to address the deficiencies in the prior art, to provide a non-organized drainage system for aluminum plate flat roofs and its installation method, by changing the drainage direction of the roof rainwater, the rainwater can be collected in one place, and a simple drainage eaves can be set to meet the needs of roof drainage. Effect, to ensure the overall design of the building facade.
技术方案:本发明所述铝板平屋顶无组织排水系统,包括铝板屋面和铝板墙面,其特征在于:所述铝板屋面设有铝制汇水角条、铝制阻水角条,所述铝制汇水角条具有一短边、一长边,短边与长边之间形成的夹角为钝角,其中,短边沿屋面排水方向一侧边设置,长边沿屋面倾斜向下设置,所述铝制阻水角条贴合屋面排水方向另一侧边设置,所述铝制汇水角条长边末端与所述铝制阻水角条底端形成的缺口为排水口;所述排水口下方贴合铝板墙面设有铝制跌水角条,所述铝制跌水角条具有一短边、一长边,所述跌水角条的短边贴合铝板墙面设置,所述跌水角条的长边与短边之间形成的角度在90°~110°之间,所述铝制汇水角条、铝制阻水角条与所述铝板屋面接触缝隙处注满硅酮耐候密封胶,所述铝制跌水角条与所述铝板墙面接触缝隙处注满硅酮耐候密封胶。Technical solution: The unorganized drainage system of the aluminum plate flat roof of the present invention includes an aluminum plate roof and an aluminum plate wall, and is characterized in that: the aluminum plate roof is provided with aluminum catchment corner strips and aluminum water blocking corner strips, and the aluminum plate roof The catchment corner strip has a short side and a long side, and the angle formed between the short side and the long side is an obtuse angle, wherein, the short side is arranged along one side of the roof drainage direction, and the long side is arranged obliquely downward along the roof. The aluminum water-blocking corner strip is set on the other side of the roof drainage direction, and the gap formed between the long side end of the aluminum water-blocking corner strip and the bottom end of the aluminum water-blocking corner strip is a drain; the drain The lower part of the aluminum plate wall is provided with an aluminum drop corner strip. The aluminum drop corner strip has a short side and a long side. The angle formed between the long side and the short side of the water drop corner strip is between 90°~110°, and the contact gap between the aluminum catchment corner strip, the aluminum water blocking corner strip and the aluminum plate roof is filled with silicon Ketone weather-resistant sealant, the contact gap between the aluminum drop corner strip and the aluminum plate wall is filled with silicone weather-resistant sealant.
进一步完善上述技术方案,所述铝制汇水角条与铝制阻水角条的截面高度根据所述铝制屋面的汇水面积、降水历时、设计排水要求计算得出。To further improve the above technical solution, the section heights of the aluminum catchment corner strips and the aluminum water blocking corner strips are calculated according to the catchment area of the aluminum roof, the duration of precipitation, and the design drainage requirements.
进一步地,所述铝制汇水角条、铝制阻水角条通过st4.2不锈钢十字盘头自攻自钻螺钉带胶固定在所述铝板屋面上,所述铝制跌水角条通过st4.2不锈钢十字盘头自攻自钻螺钉带胶固定在所述铝板墙面上。Further, the aluminum catchment corner strips and aluminum water blocking corner strips are fixed on the aluminum plate roof with glue through st4.2 stainless steel cross pan head self-tapping self-drilling screws, and the aluminum drop water corner strips are passed through st4.2 stainless steel cross pan head self-tapping self-drilling screws are fixed on the aluminum plate wall with glue.
进一步地,所述铝制跌水角条的宽度大于所述排水口的宽度。Further, the width of the aluminum drop corner strip is greater than the width of the water outlet.
进一步地,所述铝制跌水角条短边长度为20mm,长边长度为60mm。Further, the length of the short side of the aluminum drop corner strip is 20mm, and the length of the long side is 60mm.
进一步地,所述铝板屋面形成的排水坡度为3%,所述铝制汇水角条短边与长边的夹角为123°,所述铝制跌水角条短边与长边的夹角为97°。Further, the drainage slope formed by the aluminum plate roof is 3%, the angle between the short side and the long side of the aluminum catchment angle strip is 123°, and the angle between the short side and the long side of the aluminum drop corner strip is The angle is 97°.
进一步地,采用上述铝板平屋顶无组织排水系统的安装方法,包括如下步骤:Further, the installation method of the above-mentioned unorganized drainage system on the aluminum plate flat roof includes the following steps:
S1:根据幕墙施工图纸、现场幕墙龙骨间距完成铝板屋面、铝板墙面的下单,下单铝制汇水角条一根、铝制阻水角条一根、铝制跌水角条一根;材料到货,验收合格后,根据深化设计要求安装铝板屋面和铝板墙面;S1: According to the curtain wall construction drawings and the on-site curtain wall keel spacing, complete the order for the aluminum plate roof and the aluminum plate wall, place an order for one aluminum catchment corner strip, one aluminum water blocking corner strip, and one aluminum drop corner strip ; After the materials arrive and pass the acceptance inspection, install the aluminum plate roof and aluminum plate wall according to the detailed design requirements;
S2:根据铝板屋面汇水面积、降雨历时、雨水不得沿墙面自由向下流淌的排水要求计算铝制汇水角条、铝制阻水角条的截面高度;S2: Calculate the cross-sectional height of the aluminum water catchment corner strips and aluminum water blocking corner strips according to the water catchment area of the aluminum plate roof, the duration of rainfall, and the drainage requirements that rainwater must not flow freely downward along the wall;
S3:铝板屋面、铝板墙面安装完成后进行现场淋水实验,实验合格后,根据深化设计要求切割铝制汇水角条弯折呈具有短边、长边的钝角结构,采用st4.2不锈钢十字盘头自攻自钻螺钉将铝制汇水角条以短边沿铝板屋面一侧边的布局带胶固定在铝板屋面上;采用st4.2不锈钢十字盘头自攻自钻螺钉带胶将铝制阻水角条固定在铝板屋面另一侧边,固定后铝制汇水角条的长边末端与铝制阻水角条底端形成排水口,采用st4.2不锈钢十字盘头自攻自钻螺钉带胶固定铝制跌水角条至铝制墙面上且正对排水口的下方;将铝制汇水角条、铝制阻水角条与铝板屋面接触缝隙处注满硅酮耐候密封胶,将铝制跌水角条与铝板墙面接触缝隙处注满硅酮耐候密封胶;S3: After the installation of the aluminum plate roof and the aluminum plate wall is completed, the on-site water spraying test is carried out. After the test is passed, the aluminum catchment corner strip is cut and bent according to the design requirements to form an obtuse angle structure with short sides and long sides, and st4.2 stainless steel is used. The cross pan head self-tapping and self-drilling screws fix the aluminum water catchment corner strips on the aluminum roof with glue in the layout of the short edge along the side of the aluminum plate roof; use st4.2 stainless steel cross pan head self-tapping self-drilling screws The water-blocking corner strip is fixed on the other side of the aluminum plate roof. After fixing, the long end of the aluminum catchment corner strip and the bottom end of the aluminum water-blocking corner strip form a drainage outlet. The st4.2 stainless steel cross pan head is self-tapping and self-tapping. Drill screws with glue to fix the aluminum drop corner strip to the aluminum wall and directly below the drain; fill the contact gap between the aluminum catchment corner strip, the aluminum water blocking corner strip and the aluminum plate roof with silicone weather-resistant Sealant, fill the contact gap between the aluminum drop corner strip and the aluminum plate wall with silicone weather-resistant sealant;
S4:自我检查合格后,申请专项验收,验收合格后交付使用。S4: After passing the self-inspection, apply for special acceptance, and deliver it for use after passing the acceptance.
进一步地,所述铝板屋面采用2.5mm厚的铝制单板拼接,所述铝板墙面采用2.5mm厚的铝制单板拼接形成外立面。Further, the aluminum plate roof is spliced with 2.5mm thick aluminum veneers, and the aluminum plate wall is spliced with 2.5mm thick aluminum veneers to form the facade.
有益效果:与现有技术相比,本发明的优点在于:本发明通过在铝板屋面安装铝制汇水角条、铝制阻水角条以改变屋面雨水排水方向,对屋面雨水进行汇流,使雨水汇集一处,铝板墙面设置跌水角条以形成类似屋面排水檐口,雨水通过跌水角条端部自由向下排水,避免雨水沿墙面自由向下流淌,满足屋面排水效果,保证建筑外立面整体设计造型;屋面雨水自由落下溅到铝板墙面,由于铝板防水较好,可以有效保证室内墙面不会因雨水下溅潮湿,影响墙面结构的耐久性、安全性。本发明通过对屋面与墙面简单处理达到屋面雨水排水效果,排水构造措施简单、方便、实用。Beneficial effects: Compared with the prior art, the advantage of the present invention is that: the present invention installs aluminum catchment corner strips and aluminum water-blocking corner strips on the aluminum plate roof to change the drainage direction of roof rainwater, converging roof rainwater, and making The rainwater gathers in one place, and the aluminum plate wall is provided with falling water corner strips to form a roof drainage eaves. The rainwater is freely drained downward through the end of the falling water corner strips, preventing rainwater from freely flowing downward along the wall, satisfying the roof drainage effect and ensuring the building The overall design of the exterior facade; the rainwater from the roof falls freely and splashes onto the aluminum plate wall. Since the aluminum plate is waterproof, it can effectively ensure that the indoor wall will not be wet due to rainwater splashing, which will affect the durability and safety of the wall structure. The invention achieves the rainwater drainage effect of the roof by simply treating the roof and the wall, and the drainage structure measures are simple, convenient and practical.
附图说明Description of drawings
图1是本发明提供的铝板平屋顶无组织排水系统形成的平屋顶汇流平面图;Fig. 1 is the flat roof confluence plan view that the unorganized drainage system of aluminum flat roof provided by the invention forms;
图2是屋面挡水条构造剖面图;Figure 2 is a structural sectional view of the roof water retaining strip;
图3是20x50铝制汇水、阻水角条剖面图;Figure 3 is a sectional view of 20x50 aluminum water catchment and water blocking corner strips;
图4是20x60铝制跌水角条剖面图。Figure 4 is a sectional view of a 20x60 aluminum drop corner bar.
图中:1为20x50铝制汇水角条(表面氟碳喷涂颜色同屋面);2为20x50铝制阻水角条(表面氟碳喷涂颜色同屋面);3为20x60铝制跌水角条(表面氟碳喷涂颜色同屋面);4为80x60x4mm热浸镀锌钢管;5为2.5mm立面铝单板;6为泡沫棒&硅酮耐候密封胶;7为120x120x4mm热浸镀锌钢管;8为L50 x 3mm热浸镀锌角钢。In the picture: 1 is 20x50 aluminum water catchment corner strip (the color of fluorocarbon spraying on the surface is the same as the roof); 2 is 20x50 aluminum water blocking corner strip (the surface is fluorocarbon spraying color is the same as the roof); 3 is 20x60 aluminum falling water corner strip (The color of fluorocarbon spraying on the surface is the same as that of the roof); 4 is 80x60x4mm hot-dip galvanized steel pipe; 5 is 2.5mm facade aluminum veneer; 6 is foam rod & silicone weather-resistant sealant; 7 is 120x120x4mm hot-dip galvanized steel pipe; 8 For L50 x 3mm hot-dip galvanized angle steel.
具体实施方式Detailed ways
下面通过附图对本发明技术方案进行详细说明,但是本发明的保护范围不局限于所述实施例。The technical solutions of the present invention will be described in detail below with reference to the accompanying drawings, but the protection scope of the present invention is not limited to the embodiments.
实施例1:如图1所示的铝板平屋顶无组织排水系统,包括铝板屋面和铝板墙面,铝制屋面形成由上至下3%的排水坡度,铝板屋面设有铝制汇水角条1、铝制阻水角条2,铝制汇水角条1、铝制阻水角条2改变屋面雨水排水方向,使雨水汇集至排水口。Embodiment 1: The unorganized drainage system of the flat aluminum roof as shown in Figure 1, including the aluminum roof and the aluminum wall, the aluminum roof forms a drainage slope of 3% from top to bottom, and the aluminum roof is provided with aluminum catchment corner strips 1. Aluminum water-blocking corner strip 2, aluminum catchment corner strip 1, aluminum water-blocking corner strip 2 Change the direction of roof rainwater drainage, so that rainwater can be collected to the drain.
如图2所示,铝板墙面通过2.5mm厚的铝单板5连接形成外立面,相邻铝单板5弯折后通过U型连接件与内部的热浸镀锌钢管4相连,相邻铝单板与U型连接件的连接处设置泡沫棒并通过硅酮耐候密封胶6密封。铝板墙面顶部位于排水口的下方设置铝制跌水角条3。As shown in Figure 2, the aluminum plate walls are connected by 2.5 mm
铝制汇水角条1具有一短边、一长边,短边与长边之间形成的夹角为钝角,其中,短边沿屋面排水方向一侧边设置,长边沿屋面倾斜向下设置,铝制阻水角条2贴合屋面排水方向另一侧边设置,铝制汇水角条1长边末端与铝制阻水角条2底端形成的缺口为排水口。铝制跌水角条3具有一短边、一长边,跌水角条3的短边贴合铝板墙面设置,跌水角条3的长边与短边之间形成的角度在90°~110°之间,铝制汇水角条1、铝制阻水角条2与铝板屋面接触缝隙处注满硅酮耐候密封胶,铝制跌水角条3与铝板墙面接触缝隙处注满硅酮耐候密封胶。The aluminum water catchment corner strip 1 has a short side and a long side, and the angle formed between the short side and the long side is an obtuse angle, wherein the short side is arranged along one side of the roof drainage direction, and the long side is arranged obliquely downward along the roof. The aluminum water-blocking corner strip 2 is arranged on the other side of the roof drainage direction, and the gap formed between the end of the long side of the aluminum water-catching corner strip 1 and the bottom end of the aluminum water-blocking corner strip 2 is the drain. The aluminum
铝板平屋顶无组织排水系统的安装方法,包括如下步骤:The installation method of the unorganized drainage system of the aluminum plate flat roof includes the following steps:
首先,根据幕墙施工图纸、现场幕墙龙骨间距完成屋面与墙面的铝板下单,同时进行铝制汇水角条1、铝制阻水角条2、铝制跌水角条3的下单,材料到现场后进行铝板屋面和铝板墙面的安装;Firstly, according to the curtain wall construction drawings and the on-site curtain wall keel spacing, the order for the aluminum plate on the roof and the wall is completed, and the order for the aluminum catchment corner strip 1, the aluminum water blocking corner strip 2, and the aluminum
其次,计算屋面汇水面积、降雨历时、设计排水要求,得出铝制汇水角条1与铝制阻水条截面高度,对铝制汇水角条1、铝制阻水角条2进行深化设计;Secondly, calculate the water catchment area of the roof, the rainfall duration, and the design drainage requirements, and obtain the section height of the aluminum water catchment corner strip 1 and the aluminum water blocking strip, and carry out the aluminum water catchment corner strip 1 and the aluminum water blocking corner strip 2 Deepen the design;
然后,现场采用st4.2不锈钢十字盘头自攻自钻螺钉将铝制汇水角条1、铝制阻水角条2安装至铝制屋面,采用st4.2不锈钢十字盘头自攻自钻螺钉将铝制跌水角条3安装至铝制墙面,与铝制屋面、铝制墙面接触缝隙注满硅酮耐候密封胶,所有不锈钢十字盘头自攻钉需带胶作业;Then, st4.2 stainless steel cross pan head self-tapping and self-drilling screws are used to install the aluminum catchment corner strip 1 and aluminum water blocking corner strip 2 to the aluminum roof, and st4.2 stainless steel cross pan head self-tapping and self-drilling Install the aluminum
最后,自我检查合格后,申请专项验收,验收合格后交付使用。Finally, after passing the self-inspection, apply for special acceptance, and deliver it for use after passing the acceptance.
通过铝制汇水角条1、铝制阻水角条2对屋面雨水进行汇流,使雨水汇集一处,墙面设置铝制跌水角条3形成类似屋面排水檐口,雨水通过铝制跌水角条3端部自由向下排水,避免雨水沿墙面自由向下流淌,屋面雨水自由落下溅到铝板墙面,由于铝板防水较好,可以有效保证室内墙面因雨水下溅潮湿,影响墙面结构的耐久、性安全性。通过对屋面与墙面简单处理达到屋面雨水排水效果,排水构造措施简单、方便、实用。The rainwater on the roof is converged through the aluminum catchment corner strip 1 and the aluminum water-blocking corner strip 2, so that the rainwater gathers in one place, and the aluminum falling
实施例2:本实施例提供了铝板平屋顶无组织排水系统具体安装方法,包括如下步骤:Embodiment 2: This embodiment provides a specific installation method for the unorganized drainage system of an aluminum plate flat roof, including the following steps:
S1:根据幕墙施工图纸、现场幕墙龙骨间距定尺下单屋面与墙面所需2.5mm厚铝单板,下单20x50铝角条3467mm长1根、1000mm长1根,20x60铝角条300mm长1根,加工图如图3与图4所示;材料到货验收合格后根据深化设计要求安装铝单板。S1: Order the 2.5mm thick aluminum veneer required for the roof and wall according to the curtain wall construction drawings and the on-site curtain wall keel spacing, order 20x50 aluminum corner strips 3467mm long, 1 piece 1000mm long, and 20x60 aluminum corner strips 300mm long 1, the processing diagram is shown in Figure 3 and Figure 4; after the material arrives and is accepted, the aluminum veneer is installed according to the detailed design requirements.
S2:屋面汇水面积为20㎡、降雨历时5分钟、雨水不得沿墙面自由向下流淌,得出汇水条与阻水条截面高度为50mm。S2: The water catchment area of the roof is 20㎡, the rain lasts for 5 minutes, and the rainwater cannot flow down freely along the wall, so the cross-sectional height of the water catchment strip and the water blocking strip is 50mm.
S3:铝板屋面与铝板墙面安装完成后,现场淋水实验合格后;首先根据深化设计要求将3467mm长20x50铝角条弯折成123度角作为屋面汇水角条1,使用st4.2不锈钢十字盘头自攻自钻螺钉带胶固定屋面汇水角条1;其次安装1000mm长20x50铝制阻水角条2,带胶固定屋面阻水条;然后安装300mm长20x60铝角条,使用st4.2不锈钢十字盘头自攻自钻螺钉带胶固定墙面跌水条;最后将铝制角条所有接触缝隙注满硅酮耐候密封胶。S3: After the installation of the aluminum plate roof and the aluminum plate wall is completed, and the on-site water spraying test is passed; first, according to the detailed design requirements, the 3467mm long 20x50 aluminum corner strip is bent into an angle of 123 degrees as the roof catchment corner strip 1, using st4.2 stainless steel Cross pan head self-tapping self-drilling screws with glue to fix the roof catchment corner strip 1; secondly, install the 1000mm long 20x50 aluminum water-blocking corner strip 2, and fix the roof water-blocking strip with glue; then install the 300mm long 20x60 aluminum corner strip, using st4 .2 Stainless steel cross pan head self-tapping self-drilling screws with glue to fix the wall drop strips; finally, fill all the contact gaps of the aluminum corner strips with silicone weather-resistant sealant.
S4:自我检查合格后,申请专项验收,合格后交付使用。S4: After passing the self-inspection, apply for special acceptance, and deliver it for use after passing the inspection.
如上所述,尽管参照特定的优选实施例已经表示和表述了本发明,但其不得解释为对本发明自身的限制。在不脱离所附权利要求定义的本发明的精神和范围前提下,可对其在形式上和细节上作出各种变化。As stated above, while the invention has been shown and described with reference to certain preferred embodiments, this should not be construed as limiting the invention itself. Various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211613043.8A CN115928957A (en) | 2022-12-15 | 2022-12-15 | A kind of unorganized drainage system of aluminum plate flat roof and its installation method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211613043.8A CN115928957A (en) | 2022-12-15 | 2022-12-15 | A kind of unorganized drainage system of aluminum plate flat roof and its installation method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115928957A true CN115928957A (en) | 2023-04-07 |
Family
ID=86555367
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211613043.8A Pending CN115928957A (en) | 2022-12-15 | 2022-12-15 | A kind of unorganized drainage system of aluminum plate flat roof and its installation method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115928957A (en) |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6073400A (en) * | 1998-10-28 | 2000-06-13 | Balisle; Tony R. | Roof drip edge construction, corner assemblies therefor and methods of making same |
| JP3166276U (en) * | 2010-12-15 | 2011-02-24 | 有限会社鉢屋 | Building with gutter |
| RU2494199C1 (en) * | 2012-04-09 | 2013-09-27 | Алексей Алексеевич Палей | Arrangement of building and structure roof |
| CN113089940A (en) * | 2021-03-16 | 2021-07-09 | 浙江司邦齐环境科技有限公司 | Separation device and separation method for rainwater interception of roof |
-
2022
- 2022-12-15 CN CN202211613043.8A patent/CN115928957A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6073400A (en) * | 1998-10-28 | 2000-06-13 | Balisle; Tony R. | Roof drip edge construction, corner assemblies therefor and methods of making same |
| JP3166276U (en) * | 2010-12-15 | 2011-02-24 | 有限会社鉢屋 | Building with gutter |
| RU2494199C1 (en) * | 2012-04-09 | 2013-09-27 | Алексей Алексеевич Палей | Arrangement of building and structure roof |
| CN113089940A (en) * | 2021-03-16 | 2021-07-09 | 浙江司邦齐环境科技有限公司 | Separation device and separation method for rainwater interception of roof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108590185A (en) | Building exterior wall heat preserving construction technology | |
| CN217105857U (en) | Gutter edge-closing anti-seepage structure in parapet wall | |
| CN204850273U (en) | Steel sheet gutter in steel construction building | |
| CN115928957A (en) | A kind of unorganized drainage system of aluminum plate flat roof and its installation method | |
| JP2021001489A (en) | Plate straight repair roof material | |
| CN219298619U (en) | Steel structure roof cornice | |
| CN209855080U (en) | An ancient building roof cornice waterproofing construction structure | |
| CN206328963U (en) | Non-exposed formula steel structural roof waterproof construction | |
| CN212897214U (en) | Slope roofing hidden roofing pipeline | |
| CN111576749B (en) | Slope roof concealed roof outlet pipeline ventilation device and construction process | |
| CN107401216B (en) | A kind of housing basement's waterproof construction method | |
| CN209277419U (en) | A kind of stealthy drainage arrangement on roof stone decoration ground | |
| CN114541656B (en) | Construction method and structure for well type house roof drainage | |
| CN209556742U (en) | A kind of rain-proof window mounting structure | |
| CN223164130U (en) | Drainage system at junction of inclined roof and flat roof | |
| JP3414711B2 (en) | Balcony with solar panels | |
| CN221567701U (en) | A water installation node structure of fasciating for municipal transformation engineering | |
| CN207499264U (en) | A kind of roof overflow device | |
| CN207110272U (en) | A kind of glass sunlight house platform waterproof construction | |
| CN220848408U (en) | A water-collecting awning cover embedded in a steel structure building | |
| CN221524016U (en) | Waterproof structure of inlet for stom water | |
| CN218621759U (en) | Glass trestle with drainage function | |
| CN217975097U (en) | An architectural design roof cornice waterproof structure | |
| CN223017872U (en) | Anti-leakage structure for deformation joints between corridors and main buildings | |
| CN222066586U (en) | A new window sill waterproof structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20230407 |