CN115853246A - Aluminum alloy operation hanging frame for overhead arc door and building method thereof - Google Patents
Aluminum alloy operation hanging frame for overhead arc door and building method thereof Download PDFInfo
- Publication number
- CN115853246A CN115853246A CN202211647986.2A CN202211647986A CN115853246A CN 115853246 A CN115853246 A CN 115853246A CN 202211647986 A CN202211647986 A CN 202211647986A CN 115853246 A CN115853246 A CN 115853246A
- Authority
- CN
- China
- Prior art keywords
- aluminum alloy
- truss
- arc
- hanger
- door
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Gates (AREA)
Abstract
Description
技术领域technical field
本发明涉及施工脚手架领域,尤其是涉及一种用于高空弧门的铝合金作业挂架及其搭建方法。The invention relates to the field of construction scaffolding, in particular to an aluminum alloy work hanger for high-altitude arc doors and a construction method thereof.
背景技术Background technique
作业挂架是指工程领域中用于挂载重物且供施工工人进行作业施工的脚手架,其通常具有承载性能强、拆装方便和经济实惠等优点。The work hanger refers to the scaffold used in the engineering field to hang heavy objects and for construction workers to carry out construction. It usually has the advantages of strong bearing capacity, convenient disassembly and assembly, and economic benefits.
在水利工程施工作业过程中,弧形工作闸门工况结构复杂,常年工作状态的坡度为17°,由于弧门支臂离江面距离较高,因此现场难以沿着从下往上的方向搭设落地式工作架对弧门支臂焊缝及螺栓进行检修,存在明显不足。During the construction of water conservancy projects, the working condition of the arc-shaped gate is complex, and the slope of the working condition is 17° all the year round. Because the arm of the arc gate is far away from the river surface, it is difficult to set up and land on the site from the bottom to the top. There are obvious deficiencies in checking and repairing the welding seams and bolts of the arc door support arm with the traditional working frame.
发明内容Contents of the invention
为了改善现场难以沿着从下往上的方式搭建落地式工作架的问题,本申请提供一种用于高空弧门的铝合金作业挂架及其搭建方法。In order to improve the problem that it is difficult to build a floor-standing work frame from bottom to top on site, the application provides an aluminum alloy work hanger for high-altitude arc doors and a construction method thereof.
第一方面,本申请提供一种用于高空弧门的铝合金作业挂架,采用如下的技术方案:In the first aspect, the application provides an aluminum alloy work hanger for high-altitude arc doors, which adopts the following technical solution:
一种用于高空弧门的铝合金作业挂架,包括设置在弧门顶部的多个磁吸座,所述磁吸座上设置有桁架,所述桁架的两端分别设有用于对其实现支撑的承载挂架;所述承载挂架包括两个相对设置的门架片、设置于两个所述门架片之间的多个安装横杆。An aluminum alloy work hanger for high-altitude arc doors, including a plurality of magnetic seats arranged on the top of the arc doors, the magnetic seats are provided with trusses, and the two ends of the trusses are respectively provided with Supported load hanger; the load hanger includes two opposite door frame pieces and a plurality of installation cross bars arranged between the two door frame pieces.
通过采用上述技术方案,工人根据弧门坡面的角度将磁吸座调整至合适的角度,使得磁吸座的顶板保持水平,之后将磁吸座安装在弧门的坡面上。然后在磁吸座的顶板上安装桁架,以桁架为起点,沿着从上往下的方向搭设承载挂架。本申请打破了传统钢管工作架的搭设方式,将悬挑架的理念与工作架理念结合,以从上往下的方式实现作业挂架整体的搭建,整体构造简单,受力明确,解决了弧门高空维修作业的难题。By adopting the above technical solution, the worker adjusts the magnetic seat to an appropriate angle according to the angle of the slope of the arc door, so that the top plate of the magnetic seat remains horizontal, and then installs the magnetic seat on the slope of the arc door. Then install the truss on the top plate of the magnetic seat, and use the truss as the starting point to set up the bearing hanger along the direction from top to bottom. This application breaks the way of erecting the traditional steel pipe work frame, combines the concept of the cantilever frame with the concept of the work frame, and realizes the overall construction of the work hanger from top to bottom. The overall structure is simple, the force is clear, and the arc is solved. Difficulties in door maintenance operations at heights.
可选的,相对的两个所述门架片之间还设置有多个加强横杆,所述加强横杆包括第一杆体和位于所述第一杆体下方的第二杆体,所述第一杆体和所述第二杆体均水平设置且相互平行,所述第一杆体和所述第二杆体之间设置有多个撑杆。Optionally, a plurality of reinforcing cross bars are also provided between the two opposite door frame pieces, and the reinforcing cross bars include a first rod body and a second rod body located below the first rod body, the first rod body The rod body and the second rod body are arranged horizontally and parallel to each other, and a plurality of struts are arranged between the first rod body and the second rod body.
通过采用上述技术方案,加强横杆的设置将相对的门架片连接,以此能够提高想对两个门架片之间的连接强度。By adopting the above technical solution, the arrangement of the reinforcing cross bar connects the opposite door frame pieces, thereby improving the connection strength between the two door frame pieces.
可选的,相对的两个所述门架片之间还设置有多个斜杆。Optionally, a plurality of oblique rods are further arranged between the two opposite door frame pieces.
通过采用上述技术方案,斜杆的设置进一步提高了相对两个门架片之间的连接强度,有利于提高作业挂架整体的稳固性。By adopting the above technical solution, the setting of the oblique rod further improves the connection strength between the two opposite door frame pieces, which is beneficial to improving the overall stability of the work hanger.
可选的,相对两个所述门架片之间的所述加强横杆上沿着从上往下的方向挂接有多个直挂梯,相对竖向相邻两个所述直挂梯之间位置的所述加强横杆上挂接有用于供工人行走的踏板。Optionally, a plurality of straight-hanging ladders are mounted on the reinforcing cross bar between the two relative door frame pieces along the direction from top to bottom, and the two vertically adjacent ladders are relatively vertically adjacent. Steps for workers to walk are attached to the reinforcing cross bars at the intermediate positions.
通过采用上述技术方案,工人通过直挂梯和踏板能够移动至合适的高度对弧门实现安装或维修,具有安全性高和省力等优点。By adopting the above technical solution, workers can move to a suitable height to install or maintain the arc door through the vertical ladder and the pedal, which has the advantages of high safety and labor saving.
可选的,所述桁架在弧门的顶部设置有多个,不同的所述桁架之间设置有加强连杆。Optionally, multiple trusses are arranged on the top of the arc door, and reinforcing links are arranged between different trusses.
通过采用上述技术方案,加强连杆将不同的桁架连接,以此有利于提高不同桁架之间的结构强度。By adopting the above technical solution, the reinforcing connecting rod connects different trusses, which is beneficial to improve the structural strength between different trusses.
可选的,所述承载挂架上设置有多个顶撑于弧门外侧壁的可调式防侧倾撑杆。Optionally, the load hanger is provided with a plurality of adjustable anti-roll braces supporting the outer wall of the arc door.
通过采用上述技术方案,可调式防侧倾撑杆对弧门的顶撑作用能够对作业挂架起一定的限位作用,减小了作业挂架侧倾的可能性。By adopting the above-mentioned technical scheme, the supporting action of the adjustable anti-roll strut on the arc door can limit the position of the work hanger to a certain extent, reducing the possibility of the work hanger to roll.
可选的,两个所述承载挂架对应的所述加强横杆之间设置有多个加强件,所述加强件包括转杆、位于所述转杆两端其与其同轴的两个拉杆,所述拉杆的一端与所述转杆螺纹连接,另一端可拆卸连接在所述加强横杆上。Optionally, a plurality of reinforcements are provided between the reinforcing cross bars corresponding to the two bearing hangers, and the reinforcements include a rotating rod, two tie rods coaxial with the rotating rod at both ends of the rotating rod , one end of the pull rod is threadedly connected to the rotating rod, and the other end is detachably connected to the reinforcing cross bar.
通过采用上述技术方案,工人转动转杆,在螺纹配合的作用下,两个拉杆对对应的承载挂架施加一定的拉力,以此进一步提高作业挂架整体的稳固性。By adopting the above-mentioned technical solution, the worker rotates the rotating rod, and under the action of the thread fit, the two pull rods apply a certain pulling force to the corresponding bearing hanger, thereby further improving the overall stability of the working hanger.
第二方面,本申请提供一种用于高空弧门的铝合金作业挂架的搭建方法,采用如下的技术方案:In the second aspect, the present application provides a method for building an aluminum alloy work hanger for high-altitude arc doors, and adopts the following technical solution:
一种用于高空弧门的铝合金作业挂架的搭建方法,包括如下步骤:A method for building an aluminum alloy work hanger for high-altitude arc doors, comprising the following steps:
S1、根据弧门坡面的角度将所述磁吸座调整至合适的角度,使得所述磁吸座的顶板保持水平,之后将所述磁吸座安装在弧门的坡面上;S1. Adjust the magnetic seat to a suitable angle according to the angle of the slope of the arc door, so that the top plate of the magnetic seat remains horizontal, and then install the magnetic seat on the slope of the arc door;
S2、在所述磁吸座的顶板上安装对应的所述桁架;S2. Install the corresponding truss on the top plate of the magnetic seat;
S3、以所述桁架为起点,沿着从上往下的方向搭设有多组所述承载挂架。S3. Taking the truss as a starting point, erect multiple sets of the load-bearing hangers along the direction from top to bottom.
通过采用上述技术方案,工人根据弧门坡面的角度将磁吸座调整至合适的角度,使得磁吸座的顶板保持水平,之后将磁吸座安装在弧门的坡面上。然后在磁吸座的顶板上安装桁架,以桁架为起点,沿着从上往下的方向搭设承载挂架,通过从上往下的方式搭建作业挂架整体,能够对弧门实现挂载支撑。By adopting the above technical solution, the worker adjusts the magnetic seat to an appropriate angle according to the angle of the slope of the arc door, so that the top plate of the magnetic seat remains horizontal, and then installs the magnetic seat on the slope of the arc door. Then install the truss on the top plate of the magnetic suction seat. Starting from the truss, set up the load-bearing hanger along the direction from top to bottom. By building the whole work hanger from top to bottom, the arc door can be mounted and supported. .
综上所述,本申请包括以下至少一种有益技术效果:In summary, the present application includes at least one of the following beneficial technical effects:
1.本申请打破了传统钢管工作架的搭设方式,将悬挑架的理念与工作架理念结合,以从上往下的方式实现作业挂架整体的搭建,整体构造简单,受力明确,解决了弧门高空维修作业的难题;1. This application breaks the way of erecting the traditional steel pipe work frame, combines the concept of the cantilever frame with the concept of the work frame, and realizes the overall construction of the work hanger from top to bottom. The overall structure is simple, the force is clear, and the solution Solved the problem of high-altitude maintenance of arc doors;
2.工人转动转杆,在螺纹配合的作用下,两个拉杆对对应的承载挂架施加一定的拉力,以此进一步提高作业挂架整体的稳固性。2. The worker rotates the rotating rod, and under the action of the thread cooperation, the two pull rods exert a certain pulling force on the corresponding bearing hanger, thereby further improving the overall stability of the working hanger.
附图说明Description of drawings
图1是本申请实施例的结构示意图。FIG. 1 is a schematic structural diagram of an embodiment of the present application.
图2是本申请实施例中弧门、磁吸座和桁架的结构示意图。Fig. 2 is a structural schematic diagram of an arc door, a magnetic seat and a truss in the embodiment of the present application.
图3是本申请实施例中门架片、安装横杆、斜杆的结构示意图。Fig. 3 is a structural schematic diagram of the door frame piece, the installation cross bar, and the oblique bar in the embodiment of the present application.
附图标记说明:1、弧门;2、磁吸座;3、桁架;4、承载挂架;41、门架片;42、安装横杆;43、加强横杆;431、第一杆体;432、第二杆体;433、撑杆;44、斜杆;45、直挂梯;46、踏板;5、加强连杆;6、扣件;71、转杆;72、拉杆。Explanation of reference signs: 1. arc door; 2. magnetic seat; 3. truss; 4. bearing hanger; 41. door frame piece; 432, the second rod body; 433, the strut; 44, the oblique rod; 45, the vertical ladder; 46, the pedal; 5, the reinforcing connecting rod; 6, the fastener; 71, the rotating rod;
具体实施方式Detailed ways
以下结合附图1-3对本申请作进一步详细说明。The present application will be described in further detail below in conjunction with accompanying drawings 1-3.
实施例1Example 1
本申请实施例公开一种用于高空弧门的铝合金作业挂架。The embodiment of the present application discloses an aluminum alloy work hanger for high-altitude arc doors.
参照图1和图2,用于高空弧门的铝合金作业挂架包括栓接在弧门1顶部的三个磁吸座2,三个磁吸座2呈品字型分布,其中两个磁吸座2处于同一水平,该两个磁吸座2低于另外的一个磁吸座2。Referring to Figure 1 and Figure 2, the aluminum alloy work hanger for high-altitude arc doors includes three
参照图1、图2和图3,高度较低的两个磁吸座2的顶部共同栓接有一个桁架3,高度较高的磁吸座2的顶部单独栓接一个桁架3,两个桁架3相互平行。Referring to Fig. 1, Fig. 2 and Fig. 3, a truss 3 is bolted to the top of the two lower
两个桁架3之间通过现有技术中的扣件6安装有两个加强连杆5,加强连杆5将两个桁架3连接,从而形成整体,以此有利于提高作业挂架整体的结构强度。Two reinforcing
两个桁架3相对的端部共同设置有用于对其实现支撑的承载挂架4,承载挂架4包括两个相对设置的门架片41、通过上述的扣件6安装于两个门架片41之间的多个安装横杆42。The opposite ends of the two trusses 3 are jointly provided with a load-
通过多个安装横杆42将两个门架片41连接,以此拼装而成的承载挂架4对桁架3的端部实现支撑。此外桁架3靠近端部的位置同样通过上述的扣件6安装在安装横杆42上,以此实现桁架3与承载挂架4的装配,有利于提高桁架3在承载挂架4上挂设的稳固性。The two
参照图1、图2和图3,相对的两个门架片41之间通过上述的扣件6还安装有多个加强横杆43,加强横杆43包括第一杆体431和位于第一杆体431下方的第二杆体432,第一杆体431和第二杆体432均水平设置且相互平行,第一杆体431和第二杆体432之间一体成型有多个撑杆433。Referring to Fig. 1, Fig. 2 and Fig. 3, a plurality of reinforcing cross bars 43 are also installed between the two opposite
由第一杆体431、第二杆体432和多个撑杆433一体成型的加强横杆43相较于单一的安装横杆42具有较高的结构强度,能够提高相对的两个门架片41之间连接的稳固性,进而提高作业挂架整体的使用效果。Compared with the single
参照图1、图2和图3,相对的两个门架片41之间通过上述的扣件6还安装有多个斜杆44,斜杆44斜向对门架片41实现支撑,有利于进一步提高相对的两个门架片41之间的结构强度。Referring to Fig. 1, Fig. 2 and Fig. 3, a plurality of slanting
参照图1、图2和图3,相对两个门架片41之间的加强横杆43上沿着从上往下的方向挂接有多个直挂梯45,相对竖向相邻两个直挂梯45之间位置的加强横梁上挂接有用于供工人行走的踏板46。Referring to Fig. 1, Fig. 2 and Fig. 3, a plurality of vertical hanging
踏板46与直挂梯45配合,能够使得工人移动至合适的高度,对弧门1进行安装或维修。相较于手动攀爬的方式,本申请中的踏板46与直挂梯45具有安全性较高和省力的优点。The
参照图1、图2和图3,承载挂架4的安装横杆42和加强横杆43上合适的位置上通过上述扣件6挂接有多个可调式侧倾撑杆433(图中未示出),可调式侧倾撑杆433顶撑弧门1的外侧壁,可调式侧倾撑杆433能够对弧门1的侧边起到一定的支撑作用,减小了作业挂架侧倾的可能性。Referring to Fig. 1, Fig. 2 and Fig. 3, a plurality of adjustable roll braces 433 (not shown in the figure) are articulated with the above-mentioned
参照图1、图2和图3,两个承载挂架4对应的加强横杆43之间布置有多个加强件,加强件包括转杆71、位于转杆71两端且与其同轴设置的两个拉杆72,拉杆72的一端与转杆71螺纹连接,另一端通过上述的扣件6可拆卸连接在加强横杆43上。Referring to Fig. 1, Fig. 2 and Fig. 3, a plurality of reinforcements are arranged between the reinforcement cross bars 43 corresponding to the two bearing
参照图1、图2和图3,使用时,工人首先将转杆71和两个拉杆72螺纹连接在一起,然后将扣件6安装在对应的加强横杆43上,最后转动转杆71。Referring to Fig. 1, Fig. 2 and Fig. 3, during use, the worker first threads the rotating
由于扣件6对拉杆72能够起一定的限位作用,因此转杆71转动时,拉杆72无法转动。在螺纹配合的作用下,两个拉杆72相互靠近,从而对对应的加强横杆43施加一定的拉力。Since the
加强件的设置能够提高两个承载挂架4之间的连接强度,有利于减小承载挂架4意外坍塌的可能性。The setting of the reinforcing member can improve the connection strength between the two bearing
实施例1的实施原理为:首先根据弧门1坡面的角度将三个磁吸座2调整至合适的角度,使得磁吸座2的顶板保持水平,并将磁吸座2栓接在弧门1的坡面上,然后在磁吸座2的顶板上栓接对应的桁架3,并通过扣件6在两个桁架3之间安装加强连杆5,之后在桁架3上靠近两端的位置分别预先安装多个扣件6,将承载挂架4对应的安装横杆42与桁架3端部预留的扣件6连接,接下来依次安装门架片41、安装横杆42、加强横杆43、斜杆44、踏板46和直挂梯45。以桁架3为起点,根据弧门1实际的高度,沿着从上往下的方向搭设有多组承载挂架4,在承载挂架4上合适的位置通过扣架安装多个顶撑弧门1外侧壁的可调式防侧倾撑杆433。最后将加强件挂接在两个承载挂架4对应的加强横杆43之间,转动转杆71直至难以转动。The implementation principle of
实施例2Example 2
本申请实施例2公开了一种用于高空弧门的铝合金作业挂架的搭建方法,包括如下步骤:
S1、根据弧门1坡面的角度将三个磁吸座2调整至合适的角度,使得磁吸座2的顶板保持水平,之后将磁吸座2栓接在弧门1的坡面上;S1. Adjust the three
S2、在磁吸座2的顶板上栓接对应的桁架3,并通过扣件6在两个桁架3之间安装加强连杆5;S2. Bolt the corresponding truss 3 on the top plate of the
S3、在桁架3上靠近两端的位置分别预先安装多个扣件6;S3, pre-installing a plurality of
S4、将承载挂架4对应的安装横杆42与桁架3端部预装的扣件6连接,之后依次安装门架片41、安装横杆42、加强横杆43、斜杆44、踏板46和直挂梯45;S4. Connect the
S5、以桁架3为起点,根据弧门1实际的高度,沿着从上往下的方向搭设有多组承载挂架4,在承载挂架4上合适的位置通过扣架安装多个顶撑弧门1外侧壁的可调式防侧倾撑杆433;S5. Taking the truss 3 as the starting point, according to the actual height of the
S6、将加强件挂接在两个承载挂架4对应的加强横杆43之间,转动转杆71直至难以转动。S6. Hook the reinforcing piece between the reinforcing
以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。All of the above are preferred embodiments of the application, and are not intended to limit the protection scope of the application. Therefore, all equivalent changes made according to the structure, shape, and principle of the application should be covered by the protection scope of the application. Inside.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211647986.2A CN115853246A (en) | 2022-12-21 | 2022-12-21 | Aluminum alloy operation hanging frame for overhead arc door and building method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211647986.2A CN115853246A (en) | 2022-12-21 | 2022-12-21 | Aluminum alloy operation hanging frame for overhead arc door and building method thereof |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115853246A true CN115853246A (en) | 2023-03-28 |
Family
ID=85674831
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211647986.2A Pending CN115853246A (en) | 2022-12-21 | 2022-12-21 | Aluminum alloy operation hanging frame for overhead arc door and building method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115853246A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116988646A (en) * | 2023-08-22 | 2023-11-03 | 江苏速捷模架科技有限公司 | Aluminum alloy hanger operating platform suitable for high-altitude arc door structure |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201053198Y (en) * | 2007-04-20 | 2008-04-30 | 银川高盟机械有限公司 | Folding scaffold |
| CN202031308U (en) * | 2010-12-31 | 2011-11-09 | 青建集团股份公司 | Inverted-hanging type scaffold |
| CN204059925U (en) * | 2014-08-05 | 2014-12-31 | 云南路桥股份有限公司 | Total sub-semigroup safety climbing ladder |
| CN211817871U (en) * | 2019-12-25 | 2020-10-30 | 海达建设集团有限公司 | Construction hanging basket |
| CN112227692A (en) * | 2020-09-29 | 2021-01-15 | 中建三局第三建设工程有限责任公司 | A welding work platform that can be used for inverted triangular truss |
| CN112609953A (en) * | 2020-12-21 | 2021-04-06 | 中建科工集团有限公司 | A operation platform for managing truss |
| CN113622365A (en) * | 2021-08-20 | 2021-11-09 | 中国长江电力股份有限公司 | Quick-assembling operation platform capable of movably walking on radial gate support arm and support hinge |
-
2022
- 2022-12-21 CN CN202211647986.2A patent/CN115853246A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201053198Y (en) * | 2007-04-20 | 2008-04-30 | 银川高盟机械有限公司 | Folding scaffold |
| CN202031308U (en) * | 2010-12-31 | 2011-11-09 | 青建集团股份公司 | Inverted-hanging type scaffold |
| CN204059925U (en) * | 2014-08-05 | 2014-12-31 | 云南路桥股份有限公司 | Total sub-semigroup safety climbing ladder |
| CN211817871U (en) * | 2019-12-25 | 2020-10-30 | 海达建设集团有限公司 | Construction hanging basket |
| CN112227692A (en) * | 2020-09-29 | 2021-01-15 | 中建三局第三建设工程有限责任公司 | A welding work platform that can be used for inverted triangular truss |
| CN112609953A (en) * | 2020-12-21 | 2021-04-06 | 中建科工集团有限公司 | A operation platform for managing truss |
| CN113622365A (en) * | 2021-08-20 | 2021-11-09 | 中国长江电力股份有限公司 | Quick-assembling operation platform capable of movably walking on radial gate support arm and support hinge |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116988646A (en) * | 2023-08-22 | 2023-11-03 | 江苏速捷模架科技有限公司 | Aluminum alloy hanger operating platform suitable for high-altitude arc door structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN114412158B (en) | Aluminum alloy-steel combined attached lifting scaffold and installation method thereof | |
| CN110748139B (en) | A hanging basket support system | |
| CN105888230B (en) | A kind of lowering or hoisting gear and its construction method for building curtain wall construction | |
| CN215803108U (en) | Attached beam type hanging basket | |
| CN111236688A (en) | Liftable construction platform for reinforcing circular silo in vitro | |
| CN101503908B (en) | Construction method for spacing suspension cable structural template support platform | |
| CN104847102A (en) | Wall attaching method and device of attached self-lifting scaffold on retraction section of building outer wall | |
| CN110185247A (en) | Mobile outrigger platform | |
| CN108331335A (en) | A kind of pre-splicing separation type hydraulic of steel and wood composite is from climbing support | |
| CN205747445U (en) | The outer machine suspension strut structure of grid basket ceiling type air conditioner | |
| CN115853246A (en) | Aluminum alloy operation hanging frame for overhead arc door and building method thereof | |
| CN210316599U (en) | A curtain wall annular track for roof frame beams | |
| CN114876176A (en) | Adjustable long cantilever combined hanging basket and application thereof | |
| CN111764623B (en) | Hanging construction platform module and construction method of high altitude large cantilever steel roof frame | |
| CN211341686U (en) | A hanging basket support system | |
| CN211691525U (en) | Construction device for overhanging type inclined curtain wall | |
| CN211949737U (en) | A liftable construction platform for external reinforcement of circular silos | |
| CN220014395U (en) | Can have enough to meet need mounting bracket by intelligent integrated platform system bailey frame of equipping | |
| CN216921297U (en) | A fixed support structure for a hanging basket | |
| CN219157423U (en) | Foldable box girder diaphragm construction hanging basket | |
| CN205955156U (en) | Elevartor shaft steel platform | |
| CN209817424U (en) | A mobile adjustable cantilevered operating platform suitable for super-long cantilevered structures | |
| CN211736289U (en) | Operation platform | |
| CN207453448U (en) | A kind of bar type wall-attached frame | |
| CN206001627U (en) | Large Central Air Conditioning System outer machine intersection cable-stayed type suspension strut structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20230328 |