CN115852936A - An improved Larsen steel sheet pile and its construction method - Google Patents

An improved Larsen steel sheet pile and its construction method Download PDF

Info

Publication number
CN115852936A
CN115852936A CN202211643404.3A CN202211643404A CN115852936A CN 115852936 A CN115852936 A CN 115852936A CN 202211643404 A CN202211643404 A CN 202211643404A CN 115852936 A CN115852936 A CN 115852936A
Authority
CN
China
Prior art keywords
steel sheet
larsen steel
sheet pile
hangers
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211643404.3A
Other languages
Chinese (zh)
Other versions
CN115852936B (en
Inventor
张顺
李陆野
孙凯
曹荣华
高雅东
巩宝柱
李佳霖
刘航
郭宇
汲星宇
贾政达
白兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Communications Construction Group First Engineering Co ltd
Original Assignee
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd filed Critical Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
Priority to CN202211643404.3A priority Critical patent/CN115852936B/en
Publication of CN115852936A publication Critical patent/CN115852936A/en
Application granted granted Critical
Publication of CN115852936B publication Critical patent/CN115852936B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model belongs to the technical field of the construction and specifically relates to a Larsen steel sheet pile and construction method after improvement is related to, including the pile sheet, connect in the curb plate of pile sheet both sides and be fixed in the hangers at curb plate both ends, adjacent hanger junction is provided with locking Assembly, locking Assembly includes the end plate, and the lower fixed surface of end plate is provided with two sets of panels, and every group panel is two, and two panels of every group are just right each other and be the heliciform setting to be used for inlaying the hangers and locate between two panels, the fixed inserted bar that is provided with the ellipse circular of department of bottom central point of end plate, the inserted bar be used for inserting the central point who establishes two sets of hangers butt joints put and with the central lateral wall butt of hangers, have the advantage that realizes improving the stability that adjacent Larsen steel sheet pile connects.

Description

一种改进后的拉森钢板桩及其施工方法An improved Larsen steel sheet pile and its construction method

技术领域technical field

本申请涉及建筑施工领域,尤其是涉及一种改进后的拉森钢板桩及其施工方法。The application relates to the field of building construction, in particular to an improved Larsen steel sheet pile and a construction method thereof.

背景技术Background technique

拉森钢板桩在工程上通常作为围堰或基坑支护结构,在施工时,拉森钢板桩垂直打入施工地面,将多个拉森钢板桩首尾相连形成屏障,从而保护施工现场。Larsen steel sheet piles are usually used as a cofferdam or foundation pit support structure in engineering. During construction, Larsen steel sheet piles are driven vertically into the construction ground, and multiple Larsen steel sheet piles are connected end to end to form a barrier to protect the construction site.

相关技术中,拉森钢板桩的施工工艺主要包括以下步骤:首先,将第一组拉森钢板桩打入地面以下,完成初步安装,然后,将另一组拉森钢板桩的挂耳对准已打入地面的拉森钢板桩的挂耳,对准后继续将第二组拉森钢板桩打入,以此类推,从而使得多组拉森钢板桩依次连接。In related technologies, the construction process of Larsen steel sheet piles mainly includes the following steps: First, drive the first group of Larsen steel sheet piles into the ground to complete the preliminary installation, and then align the lugs of another group of Larsen steel sheet piles After aligning the lugs of the Larsen steel sheet piles that have been driven into the ground, continue to drive in the second group of Larsen steel sheet piles, and so on, so that multiple groups of Larsen steel sheet piles are connected in sequence.

但是上述技术方案中,相邻的拉森钢板桩在安装后,仅仅依靠相邻挂耳之间形成的连接不够稳定。However, in the above technical solution, after the adjacent Larsen steel sheet piles are installed, the connection formed between adjacent hanging lugs is not stable enough.

发明内容Contents of the invention

本申请为了实现提高相邻拉森钢板桩连接的稳定性,提供了一种改进后的拉森钢板桩及其施工方法。In order to improve the stability of the connection of adjacent Larsen steel sheet piles, the present application provides an improved Larsen steel sheet pile and a construction method thereof.

本申请的上述技术目的是通过以下技术方案得以实现的:The above-mentioned technical purpose of the application is achieved through the following technical solutions:

一方面,本申请提供一种改进后的拉森钢板桩,包括桩板、连接于桩板两侧的侧板以及固定于侧板两端的挂耳,相邻的挂耳连接处设置有锁紧组件,所述锁紧组件包括端板,端板的下表面固定设置有两组嵌板,每组嵌板为两个,且每组的两个嵌板相互正对、并呈螺旋状设置,以用于将挂耳嵌设于两个嵌板之间,端板的底部中心位置处固定设置有椭圆状的插杆,插杆用于插设两组挂耳对接的中心位置且与挂耳的中心侧壁抵接。On the one hand, the present application provides an improved Larsen steel sheet pile, which includes a pile plate, side plates connected to both sides of the pile plate, and hanging lugs fixed to both ends of the side plate, and locking lugs are provided at the joints of adjacent hanging lugs. Assemblies, the locking assembly includes an end plate, two sets of panels are fixedly arranged on the lower surface of the end plate, each set of panels is two, and the two panels of each group face each other and are arranged in a spiral shape, It is used to embed the hanging ears between the two panels. The center of the bottom of the end plate is fixed with an elliptical insertion rod. The central sidewall abuts.

可选的,所述插杆的相对两侧设置有与端板底面固定的侧杆,侧杆的两侧呈与两组不同的嵌板相对的侧壁相适配的弧形。Optionally, side bars fixed to the bottom surface of the end plate are provided on the opposite sides of the insertion rod, and the two sides of the side bar are arc-shaped to match the opposite side walls of two groups of different panels.

可选的,所述侧杆的底端固定设置有多根竖直设置的助插轴,侧杆顶部至助插轴底部的距离小于侧板的高度。Optionally, the bottom end of the side rod is fixedly provided with a plurality of vertically arranged auxiliary shafts, and the distance from the top of the side rod to the bottom of the auxiliary shaft is smaller than the height of the side plate.

可选的,所述插杆的底部设置有竖直向上贯穿的置土槽。Optionally, the bottom of the insertion rod is provided with a vertically upwardly penetrating soil groove.

可选的,所述端板于同组的两个嵌板之间的区域开设有嵌槽,嵌槽用于与挂耳的端部嵌合。Optionally, the end plate is provided with a slot in the area between the two panels of the same group, and the slot is used for fitting with the end of the hanging ear.

可选的,两组所述挂耳中心段的顶端位置处开设有水平正对的连接槽口,连接槽口内横插有连接条,端板的底部中心位置处开设有供连接条嵌设的安装槽。Optionally, a horizontally facing connection notch is provided at the top positions of the center sections of the two groups of hanging lugs, and a connecting bar is inserted horizontally in the connecting notch, and a hole for the connecting bar to be embedded is opened at the center of the bottom of the end plate. Mounting slot.

可选的,所述侧板于与挂耳的连接位置处固定设置有半圆弧板,半圆弧板背离侧板表面的一侧呈外凸圆弧状。Optionally, the side plate is fixedly provided with a semi-circular arc plate at the connection position with the hanging ear, and the side of the semi-circular arc plate facing away from the surface of the side plate is in a convex arc shape.

可选的,所述插杆的长度大于侧板的高度。Optionally, the length of the insertion rod is greater than the height of the side plate.

另一方面,本申请提供一种改进后的拉森钢板桩的施工方法,包括如下步骤:On the other hand, the present application provides an improved Larsen steel sheet pile construction method, including the following steps:

S1、将首个拉森钢板桩按照既定位置打入地面,并预留自身高度的二分之一高出地面以上部分;S1. Drive the first Larsen steel sheet pile into the ground according to the predetermined position, and reserve half of its height above the ground;

S2、将新的拉森钢板桩的挂耳对准已打入地面部分拉森钢板桩的挂耳,并继续将新的拉森钢板桩打入地面以下部分,保持两组拉森钢板桩高度平齐;S2. Align the lugs of the new Larsen steel sheet piles with the lugs of the Larsen steel sheet piles that have been driven into the ground, and continue to drive the new Larsen steel sheet piles into the part below the ground to maintain the height of the two sets of Larsen steel sheet piles flat;

S3、调整两组拉森钢板桩的挂耳处连接位置,利用锁紧组件将相邻的挂耳进行连接;具体为将插杆插入两组挂耳对接的中心位置处,并将插杆的底端插入地面以下,直至挂耳嵌设于嵌板之间、连接条插入连接槽口、且端板底面与挂耳上端面抵接;S3. Adjust the connection position of the hanging lugs of the two sets of Larsen steel sheet piles, and use the locking components to connect the adjacent hanging lugs; The bottom end is inserted below the ground until the hanging lug is embedded between the panels, the connecting strip is inserted into the connecting notch, and the bottom surface of the end plate abuts against the upper end surface of the hanging lug;

S4、重复步骤S2和步骤S3,继续完成所有拉森钢板桩的安装工作。S4. Steps S2 and S3 are repeated to continue to complete the installation of all Larsen steel sheet piles.

通过采用上述技术方案,在相邻的拉森钢板桩之间通过锁紧组件,使得两个拉森钢板桩能够保持紧密连接,并且端板的中心设置有插杆,插杆一方面能够与挂耳内壁接触,并挤压两个挂耳相互背离,而插杆的底端插入地面以下,保持整个锁紧组件的稳定,另一方面在挤压的同时,挂耳又能够被限制在嵌板之间,从而使得挂耳的连接处能够保持紧密接触;与此同时,侧杆也与挂耳的侧壁抵接,进一步提高挂耳连接的紧密性。综上所述,本发明通过设置锁紧组件,能够大大提高相邻的拉森钢板桩的连接紧密性,从而使得拉森钢板桩连接后形成的围护结构更加稳定牢固。By adopting the above technical scheme, the two Larsen steel sheet piles can be kept tightly connected through the locking assembly between the adjacent Larsen steel sheet piles, and the center of the end plate is provided with an insertion rod. On the one hand, the insertion rod can be connected with the hanging The inner wall of the ear contacts and squeezes the two hanging ears away from each other, and the bottom end of the insertion rod is inserted below the ground to keep the entire locking assembly stable. On the other hand, while squeezing, the hanging ears can be limited to the panel Between, so that the joints of the hanging ears can maintain close contact; at the same time, the side bars also abut against the side walls of the hanging ears, further improving the tightness of the connection of the hanging ears. To sum up, the present invention can greatly improve the connection tightness of adjacent Larsen steel sheet piles by setting the locking components, so that the enclosure structure formed after the Larsen steel sheet piles are connected is more stable and firm.

综上所述,本申请具有以下技术效果:In summary, the application has the following technical effects:

1.通过在相邻的拉森钢板桩的挂耳连接处设置锁紧组件,使得相邻的拉森钢板桩连接更加紧密牢固;1. By setting a locking component at the lug connection of adjacent Larsen steel sheet piles, the connection of adjacent Larsen steel sheet piles is made tighter and firmer;

2.通过在端板的底部中心位置设置插入地面的插杆,使得嵌板嵌设包围挂耳更加稳定,同时插杆会保持两个挂耳之间的距离恒定、利用插杆形成稳定连接;2. By setting the insertion rod inserted into the ground at the center of the bottom of the end plate, the panel embedded around the hanging ears is more stable, and at the same time, the insertion rod will keep the distance between the two hanging ears constant, and use the insertion rod to form a stable connection;

3.通过在端板的底部设置位于插杆两侧的侧杆,并且侧杆的底部通过助插轴插入地面以下,使得挂耳的两侧被侧杆以及插杆挤压定位,进一步提高了挂耳的连接紧密性。3. By setting the side rods on both sides of the insertion rod at the bottom of the end plate, and the bottom of the side rod is inserted below the ground through the auxiliary insertion shaft, so that the two sides of the hanging ears are squeezed and positioned by the side rods and the insertion rod, which further improves the The connection tightness of the mounting ear.

附图说明Description of drawings

图1是本申请实施例中相邻拉森钢板桩连接的结构示意图;Fig. 1 is a schematic structural diagram of the connection of adjacent Larsen steel sheet piles in the embodiment of the present application;

图2是本申请实施例中锁紧组件的结构示意图;Fig. 2 is a schematic structural view of the locking assembly in the embodiment of the present application;

图3是本申请实施例中锁紧组件的爆炸示意图;Fig. 3 is an exploded schematic diagram of the locking assembly in the embodiment of the present application;

图4是相邻挂耳连接后隐藏端板的结构示意图。Fig. 4 is a schematic structural diagram of a hidden end plate after adjacent hanging lugs are connected.

图中,1、桩板;2、侧板;3、挂耳;31、连接槽口;4、锁紧组件;41、端板;411、嵌槽;42、嵌板;43、插杆;431、置土槽;44、侧杆;441、助插轴;5、连接条;6、安装槽。In the figure, 1, pile plate; 2, side plate; 3, hanging lug; 31, connection notch; 4, locking component; 41, end plate; 411, embedded groove; 42, panel; 43, inserting rod; 431, put soil groove; 44, side bar; 441, help inserting shaft; 5, connecting bar; 6, installation groove.

具体实施方式Detailed ways

以下结合附图对本申请作进一步详细说明。The application will be described in further detail below in conjunction with the accompanying drawings.

参照图1,本申请提供一种改进后的拉森钢板桩,包括桩板1、侧板2以及挂耳3,其中,侧板2设置有两组,且两组侧板2分设于桩板1两侧,两组侧板2向着背离桩板1中心的方向延伸,挂耳3设置于侧板2背离桩板1的一端、且桩板1、侧板2、挂耳3一体成型。相邻的拉森钢板桩利用挂耳3形成扣接并打入地面,挂耳3连接处设置有用于将两组相邻的拉森钢板桩定位连接的锁紧组件4。Referring to Fig. 1, the present application provides an improved Larsen steel sheet pile, including a pile plate 1, a side plate 2 and hanging ears 3, wherein two sets of side plates 2 are provided, and the two sets of side plates 2 are separately arranged on the pile plate On both sides of 1, two sets of side plates 2 extend away from the center of pile plate 1. Hanging lug 3 is set on the end of side plate 2 away from pile plate 1, and pile plate 1, side plate 2, and hanging ear 3 are integrally formed. Adjacent Larsen steel sheet piles are buckled and driven into the ground by means of hanging lugs 3 , and locking components 4 for positioning and connecting two groups of adjacent Larsen steel sheet piles are provided at the joints of the hanging lugs 3 .

结合图2和图3,锁紧组件4包括端板41、嵌板42、插杆43以及侧杆44,具体地,端板41为水平板状结构,其平面形状可以为圆形、方形、或其他任意形状;端板41用于覆盖在挂耳3连接处的上方。嵌板42设置有两组,每组嵌板42数量为相对的两个,本实施例中,嵌板42固定于端板41下表面,每组的两个嵌板42以挂耳3为中心围绕呈螺旋状设置,且两个嵌板42之间的距离与挂耳3厚度保持一致,端板41下表面于两个嵌板42之间的区域开设有嵌槽411。在安装锁紧组件4时,将挂耳3端部对准两个嵌板42之间,然后下压端板41,使得挂耳3顶端嵌入两个嵌板42之间并最终卡入嵌槽411,利用嵌板42与挂耳3表面的过盈配合,来实现挂耳3的定位。2 and 3, the locking assembly 4 includes an end plate 41, a panel 42, an insertion rod 43 and a side rod 44. Specifically, the end plate 41 is a horizontal plate structure, and its planar shape can be circular, square, Or any other shape; the end plate 41 is used to cover the top of the connection of the hanging ear 3 . There are two groups of panels 42, and the number of panels 42 in each group is two opposite. In this embodiment, the panels 42 are fixed on the lower surface of the end plate 41, and the two panels 42 of each group are centered on the hanging ear 3 The surrounding is arranged in a spiral shape, and the distance between the two panels 42 is consistent with the thickness of the hanging ear 3 , and the lower surface of the end plate 41 is provided with a slot 411 in the area between the two panels 42 . When installing the locking assembly 4, align the end of the hanging ear 3 between the two panels 42, and then press down on the end plate 41, so that the top of the hanging ear 3 fits between the two panels 42 and finally snaps into the slot 411 , using the interference fit between the panel 42 and the surface of the hanging ear 3 to realize the positioning of the hanging ear 3 .

进一步地,插杆43固定于端板41下表面中心位置处,插杆43横截面为椭圆状,以用于与两组嵌板42中位于中心相对部分的内侧表面贴合,插杆43的整体长度大于整个拉森钢板桩的长度,且插杆43的底端自下至上开设有置土槽431,在安装锁紧组件4时,插杆43插设于两组嵌板42所围成的中间区域,从而对两个挂耳3向外侧相互挤压,同时挂耳3被嵌入嵌板42之间,相互配合,从而使得两个拉森钢板桩的挂耳3连接处保持紧密稳定的连接。Further, the inserting rod 43 is fixed at the center position of the lower surface of the end plate 41. The cross section of the inserting rod 43 is elliptical, so as to fit with the inner surfaces of the parts opposite to the center of the two groups of panels 42. The inserting rod 43 The overall length is greater than the length of the entire Larsen steel sheet pile, and the bottom end of the insertion rod 43 is provided with a soil groove 431 from bottom to top. When the locking component 4 is installed, the insertion rod 43 is inserted into the two groups of panels 42 In the middle area, the two hanging lugs 3 are pressed against each other outwards, and at the same time, the hanging lugs 3 are embedded between the panels 42 and cooperate with each other, so that the connection of the hanging lugs 3 of the two Larsen steel sheet piles remains tight and stable. connect.

本实施例中,为了更进一步地提高相邻的拉森钢板桩的连接紧密性,在插杆43相对的两侧均设置有侧杆44,侧杆44的长度小于拉森钢板桩的整体深度,侧杆44顶端固定于端板41下表面,侧杆44表面为圆弧状,以用于与拉森钢板桩的相对表面贴合,在设置侧杆44长度时,确保其长度至少有一半插入地面以下。In this embodiment, in order to further improve the connection tightness of adjacent Larsen steel sheet piles, side rods 44 are provided on opposite sides of the insertion rod 43, and the length of the side rods 44 is less than the overall depth of the Larsen steel sheet piles , the top of the side bar 44 is fixed on the lower surface of the end plate 41, and the surface of the side bar 44 is arc-shaped to fit the opposite surface of the Larsen steel sheet pile. When setting the length of the side bar 44, ensure that its length is at least half Insert below the ground.

侧杆44的底端固定设置有多根竖直的助插轴441,施工时,由于侧杆44与插杆43分设于拉森钢板桩挂耳3连接处相对位置的空隙,因此挂耳3在对接后能够得到较为紧密的涨紧,进一步提高了挂耳3连接的稳定性。The bottom end of the side rod 44 is fixedly provided with a plurality of vertical auxiliary shafts 441. During construction, since the side rod 44 and the insertion rod 43 are respectively arranged in the gap at the relative position of the connection of the Larsen steel sheet pile hanging ear 3, the hanging ear 3 Relatively tight tension can be obtained after docking, which further improves the stability of the connection of the hanging lug 3 .

结合图3和图4,端板41下表面的中心位置处开设有安装槽6,安装槽6内卡设有连接条5,连接条5的下表面与端板41下表面平齐,且连接条5横跨两组嵌板42以及嵌槽411。挂耳3上表面对应位置处开设有横跨自身的连接槽口31,在安装好锁紧组件4后,挂耳3插入嵌槽411内,并且连接条5卡入连接槽口31,从而使得两组挂耳3能够被进一步限制,从而提高连接的稳定性。3 and 4, an installation groove 6 is provided at the center of the lower surface of the end plate 41, and a connecting strip 5 is clamped in the installation groove 6. The lower surface of the connecting strip 5 is flush with the lower surface of the end plate 41, and connected The bar 5 spans the two sets of panels 42 and the slot 411 . The corresponding position on the upper surface of the hanging ear 3 is provided with a connecting notch 31 across itself. After the locking assembly 4 is installed, the hanging ear 3 is inserted into the slot 411, and the connecting strip 5 is snapped into the connecting notch 31, so that The two sets of hanging lugs 3 can be further restricted, thereby improving the stability of the connection.

本实施例还公开一种改进后的拉森钢板桩的施工方法,包括如下步骤:This embodiment also discloses an improved Larsen steel sheet pile construction method, including the following steps:

S1、将首个拉森钢板桩按照既定位置打入地面,并预留自身高度的二分之一高出地面以上部分;S1. Drive the first Larsen steel sheet pile into the ground according to the predetermined position, and reserve half of its height above the ground;

S2、将新的拉森钢板桩的挂耳3对准已打入地面部分拉森钢板桩的挂耳3,并继续将新的拉森钢板桩打入地面以下部分,保持两组拉森钢板桩高度平齐;S2. Align the lug 3 of the new Larsen steel sheet pile with the lug 3 of the Larsen steel sheet pile that has been driven into the ground, and continue to drive the new Larsen steel sheet pile into the part below the ground, keeping two sets of Larsen steel sheets Pile height is even;

S3、调整两组拉森钢板桩的挂耳3处连接位置,利用锁紧组件4将相邻的挂耳3进行连接;具体为将插杆43插入两组挂耳3对接的中心位置处,并将插杆43的底端插入地面以下,同时侧杆44插入两组挂耳3间非中间部分的空隙,侧杆44底部的助插轴441插入地面以下,且侧杆44自身也部分插入地面以下,最终直至挂耳3嵌设于嵌板42之间、连接条5插入连接槽口31、且端板41底面与挂耳3上端面抵接;S3. Adjust the connection position of the 3 hanging lugs of the two sets of Larsen steel sheet piles, and use the locking assembly 4 to connect the adjacent hanging lugs 3; specifically, insert the insertion rod 43 into the central position where the two sets of hanging lugs 3 are docked, And insert the bottom end of the insertion rod 43 below the ground, and at the same time, insert the side rod 44 into the gap between the two groups of hanging ears 3, and insert the auxiliary shaft 441 at the bottom of the side rod 44 below the ground, and the side rod 44 itself is also partially inserted Below the ground, until the hanging lug 3 is embedded between the panels 42, the connecting strip 5 is inserted into the connecting notch 31, and the bottom surface of the end plate 41 abuts against the upper end surface of the hanging lug 3;

S4、重复步骤S2和步骤S3,继续完成所有拉森钢板桩的安装工作。S4. Steps S2 and S3 are repeated to continue to complete the installation of all Larsen steel sheet piles.

综上可知,本申请中,在拉森钢板桩相邻的挂耳3连接处,能够利用锁紧组件4多方位涨紧锁定,插杆43与侧杆44相互配合,使得挂耳3连接处的缝隙能够被填充定位,确保挂耳3带动整个拉森钢板桩保持竖直,同时再次通过嵌板42对挂耳3顶端的嵌合、配合着连接条5与连接槽口31的卡合,使得挂耳3进一步保证稳定,因此相较于现有技术,本申请具有提高挂耳3连接处稳定性以及连接精度的优点。To sum up, in this application, at the joints of the adjacent lugs 3 of the Larsen steel sheet piles, the locking assembly 4 can be used to tighten and lock in multiple directions, and the insertion rod 43 and the side rod 44 cooperate with each other, so that the joints of the lugs 3 The gap can be filled and positioned to ensure that the hanging lug 3 drives the entire Larsen steel sheet pile to remain vertical. At the same time, through the fitting of the panel 42 on the top of the hanging lug 3 and the engagement of the connecting strip 5 and the connecting notch 31, The hanging lug 3 is further ensured to be stable. Therefore, compared with the prior art, the present application has the advantage of improving the stability and connection accuracy of the connection of the hanging lug 3 .

本具体实施例仅仅是对本申请的解释,其并不是对本申请的限制,本领域技术人员在阅读完本说明书后可以根据需要对本实施例做出没有创造性贡献的修改,但只要在本申请的权利要求范围内都受到专利法的保护。This specific embodiment is only an explanation of this application, and it is not a limitation of this application. Those skilled in the art can make modifications to this embodiment without creative contribution according to needs after reading this specification, but as long as the rights of this application All claims are protected by patent law.

Claims (9)

1. The utility model provides a Larsen steel sheet pile after improvement, includes pile plate (1), connects in curb plate (2) of pile plate (1) both sides and is fixed in hangers (3) at curb plate (2) both ends, its characterized in that: adjacent hangers (3) junction is provided with locking Assembly (4), locking Assembly (4) include end plate (41), and the lower fixed surface of end plate (41) is provided with two sets of panels (42), and every group panel (42) is two, and two panels (42) of every group are just right each other, and are the heliciform setting, in order to be used for inlaying hangers (3) and locate between two panels (42), the fixed inserted bar (43) that are provided with the ellipse form of bottom central point department of putting of end plate (41), inserted bar (43) are used for inserting the central point who establishes two sets of hangers (3) butt joint put and with the central lateral wall butt of hangers (3).
2. The improved Larsen steel sheet pile as claimed in claim 1, wherein: side rods (44) fixed with the bottom surface of the end plate (41) are arranged on two opposite sides of the inserted rod (43), and two sides of each side rod (44) are in arc shapes matched with opposite side walls of two groups of different panels (42).
3. The improved Larsen steel sheet pile as claimed in claim 2, wherein: the bottom end of the side rod (44) is fixedly provided with a plurality of vertically arranged insertion assisting shafts (441), and the distance from the top of the side rod (44) to the bottom of the insertion assisting shafts (441) is smaller than the height of the side plate (2).
4. The improved Larsen steel sheet pile as claimed in claim 1, wherein: the bottom of the inserted bar (43) is provided with a soil containing groove (431) which vertically penetrates upwards.
5. The improved Larsen steel sheet pile as claimed in claim 1, wherein: the end plate (41) is provided with a caulking groove (411) in the area between the two panels (42) in the same group, and the caulking groove (411) is used for being embedded with the end part of the hanging lug (3).
6. The improved Larsen steel sheet pile as claimed in claim 1, wherein: the top end position department of two sets of hangers (3) central section sets up level just to connecting notch (31), and horizontal cutting has connecting strip (5) in connecting notch (31), and the bottom central point department of end plate (41) sets up and supplies connecting strip (5) to inlay mounting groove (6) of establishing.
7. The improved Larsen steel sheet pile as claimed in claim 1, wherein: the side plate (2) is fixedly provided with a semicircular arc plate at the connecting position of the side plate and the hanging lug (3), and one side of the semicircular arc plate, which is away from the surface of the side plate (2), is in a shape of a convex arc.
8. An improved Larsen steel sheet pile as claimed in claim 1, wherein: the length of the inserted bar (43) is greater than the height of the side plate (2).
9. An improved larsen steel sheet pile according to any one of claims 1 to 8, wherein: the construction method comprises the following steps:
s1, driving a first Larsen steel sheet pile into the ground according to a set position, and reserving a part of the first Larsen steel sheet pile, which is half of the height of the first Larsen steel sheet pile, above the ground;
s2, aligning the hangers (3) of the new Larsen steel sheet pile with the hangers (3) of the Larsen steel sheet pile which is driven into the ground, continuously driving the new Larsen steel sheet pile into the part below the ground, and keeping the two groups of Larsen steel sheet piles at the same height;
s3, adjusting the connection positions of the hangers (3) of the two groups of Larsen steel sheet piles, and connecting the adjacent hangers (3) by using a locking assembly (4); inserting an inserting rod (43) into the butt joint center position of two groups of hanging lugs (3), inserting the bottom end of the inserting rod (43) into the ground until the hanging lugs (3) are embedded between the panels (42), inserting the connecting strip (5) into the connecting notch (31), and abutting the bottom surface of the end plate (41) against the upper end surface of the hanging lugs (3);
and S4, repeating the step S2 and the step S3, and continuously completing the installation work of all Larsen steel sheet piles.
CN202211643404.3A 2022-12-20 2022-12-20 An improved Larsen steel sheet pile and its construction method Active CN115852936B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211643404.3A CN115852936B (en) 2022-12-20 2022-12-20 An improved Larsen steel sheet pile and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211643404.3A CN115852936B (en) 2022-12-20 2022-12-20 An improved Larsen steel sheet pile and its construction method

Publications (2)

Publication Number Publication Date
CN115852936A true CN115852936A (en) 2023-03-28
CN115852936B CN115852936B (en) 2025-04-11

Family

ID=85674596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211643404.3A Active CN115852936B (en) 2022-12-20 2022-12-20 An improved Larsen steel sheet pile and its construction method

Country Status (1)

Country Link
CN (1) CN115852936B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201933484U (en) * 2010-11-22 2011-08-17 大连冶金工具厂有限公司 Compound steel sheet pile
CN109339031A (en) * 2018-11-20 2019-02-15 南昌工程学院 A kind of anti-seepage device for underground concrete diaphragm wall joint
CN216515529U (en) * 2021-11-30 2022-05-13 湖北顺意通建设有限公司 Larsen steel sheet pile with sealing structure for municipal construction
CN114837194A (en) * 2022-05-15 2022-08-02 中冶建工集团有限公司 Construction method for improving stability of PC (polycarbonate) composite pile
CN217267395U (en) * 2022-05-10 2022-08-23 中煤江南建设发展集团有限公司 Make things convenient for assembly quality of steel-pipe pile and combination of Larsen steel sheet pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201933484U (en) * 2010-11-22 2011-08-17 大连冶金工具厂有限公司 Compound steel sheet pile
CN109339031A (en) * 2018-11-20 2019-02-15 南昌工程学院 A kind of anti-seepage device for underground concrete diaphragm wall joint
CN216515529U (en) * 2021-11-30 2022-05-13 湖北顺意通建设有限公司 Larsen steel sheet pile with sealing structure for municipal construction
CN217267395U (en) * 2022-05-10 2022-08-23 中煤江南建设发展集团有限公司 Make things convenient for assembly quality of steel-pipe pile and combination of Larsen steel sheet pile
CN114837194A (en) * 2022-05-15 2022-08-02 中冶建工集团有限公司 Construction method for improving stability of PC (polycarbonate) composite pile

Also Published As

Publication number Publication date
CN115852936B (en) 2025-04-11

Similar Documents

Publication Publication Date Title
CN209260723U (en) A foundation pit enclosure structure
CN211523614U (en) Connection structure of assembled shear force wall
CN108331216A (en) A kind of installation method of large size carving stone curtain wall
CN214614154U (en) A prefabricated caisson for building underground sewage pools
CN111305644A (en) Assembled light steel structure enclosing wall and construction method
CN203939029U (en) Gantry type supporting and protection structure when excavate the same period wall both sides, soil strip hole
CN212154367U (en) Assembled light steel structure fence
CN115852936B (en) An improved Larsen steel sheet pile and its construction method
CN218779701U (en) Can assemble spb wallboard for building
CN115748664B (en) Two-wall-in-one prefabricated underground continuous wall structure and construction method thereof
CN107190869B (en) Plugging piece for plugging during prefabricated double-T plate assembly and construction method thereof
CN212772422U (en) Cofferdam structure
CN108643208A (en) Sandwiched with steel plates concrete combined board cofferdam and assembling method
CN114809103A (en) Prefabricated section of jurisdiction enclosed construction of assembled
CN210140822U (en) Pile inserting for construction equipment
KR20190142492A (en) PHC pile to facilitate soil guard and construction method of soil guard structure using the same
CN219343434U (en) Prefabricated escape canal interface reinforcing assembly and PE escape canal package assembly
CN220013632U (en) Connecting device of Larson steel sheet pile
CN108468339B (en) A skeleton-type foundation pit support and basement exterior wall assembly structure and construction method thereof
CN106320611B (en) steel bar splicing method
CN217782456U (en) Embedded-locked brick wall
CN219825297U (en) Earth and stone square support structure
CN217630445U (en) Combined spliced steel structure
CN218757634U (en) Design stagnant water steel sheet dog-ear connects
CN220377249U (en) A groutable steel sheet pile that is easy to dismantle and use

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
TA01 Transfer of patent application right

Effective date of registration: 20230404

Address after: No.114, Jiaodaokou South Street, Dongcheng District, Beijing

Applicant after: CCCC Construction Group Co.,Ltd.

Applicant after: THE SIXTH ENGINEERING CO., LTD. OF CCCC FOURTH HIGHWAY ENGINEERING Co.,Ltd.

Address before: 301700 Building 1, Xinkai Square, Venture Headquarters Base, Fuyuan Road North, Wuqing Development Zone, Wuqing District, Tianjin City

Applicant before: THE SIXTH ENGINEERING CO., LTD. OF CCCC FOURTH HIGHWAY ENGINEERING Co.,Ltd.

TA01 Transfer of patent application right
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20250512

Address after: Room 1201, No. 12 Jinlan Road, Jiangning District, Nanjing City, Jiangsu Province, 211100

Patentee after: China Communications Construction Group First Engineering Co.,Ltd.

Country or region after: China

Address before: No.114, Jiaodaokou South Street, Dongcheng District, Beijing

Patentee before: CCCC Construction Group Co.,Ltd.

Country or region before: China

Patentee before: THE SIXTH ENGINEERING CO., LTD. OF CCCC FOURTH HIGHWAY ENGINEERING Co.,Ltd.

TR01 Transfer of patent right