CN115822271A - Construction method of oblique wall with large angle - Google Patents
Construction method of oblique wall with large angle Download PDFInfo
- Publication number
- CN115822271A CN115822271A CN202211452490.XA CN202211452490A CN115822271A CN 115822271 A CN115822271 A CN 115822271A CN 202211452490 A CN202211452490 A CN 202211452490A CN 115822271 A CN115822271 A CN 115822271A
- Authority
- CN
- China
- Prior art keywords
- wall
- construction
- building
- masonry
- template
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工技术领域,具体是大角度斜砌墙施工工法。The invention relates to the technical field of building construction, in particular to a large-angle oblique wall construction method.
背景技术Background technique
建筑施工是指工程建设实施阶段的生产活动,是各类建筑物的建造过程,也可以说是把设计图纸上的各种线条,在指定的地点,变成实物的过程,它包括基础工程施工、主体结构施工、屋面工程施工、装饰工程施工等,施工作业的场所称为"建筑施工现场"或叫"施工现场"。Building construction refers to the production activities in the implementation stage of engineering construction. It is the construction process of various buildings. It can also be said to be the process of turning various lines on the design drawings into physical objects at designated locations. It includes basic engineering construction. , main structure construction, roofing engineering construction, decoration engineering construction, etc., the place of construction work is called "building construction site" or "construction site".
近年来,随着建筑业的飞速发展,各地的标志性建筑越来越多,为了满足建筑物独特的建筑造型,异形柱越来越多的被应用到大型公共建筑中,虽然现有的大角度斜砌墙施工方式存在,但是现有技术的施工效率较低,施工难度较大,而且大角度斜墙砌筑与普通墙体相比,自重偏心距大,自身抗倾覆能力差,容易产生墙体开裂、平整度差、砂浆饱满度不足等质量问题,无法满足后续抹灰及防水等施工工序要求。In recent years, with the rapid development of the construction industry, there are more and more landmark buildings everywhere. In order to meet the unique architectural shape of the buildings, more and more special-shaped columns are applied to large public buildings. Although the existing large Angle oblique wall construction methods exist, but the construction efficiency of the existing technology is low, and the construction difficulty is relatively large. Compared with ordinary walls, large-angle oblique wall masonry has a large self-weight eccentricity, poor anti-overturning ability, and is prone to accidents. Quality problems such as wall cracking, poor flatness, and insufficient mortar fullness cannot meet the requirements of subsequent construction procedures such as plastering and waterproofing.
因此,本领域技术人员提供了大角度斜砌墙施工工法,以解决上述背景技术中提出的问题。Therefore, those skilled in the art provide a large-angle oblique wall construction method to solve the problems raised in the above-mentioned background technology.
发明内容Contents of the invention
本发明的目的在于提供大角度斜砌墙施工工法,以解决上述背景技术中提出的问题。The object of the present invention is to provide a large-angle oblique wall construction method to solve the problems raised in the above-mentioned background technology.
为实现上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:
大角度斜砌墙施工工法,所述施工工法包括以下步骤:A large-angle oblique wall construction method, the construction method includes the following steps:
模架体系施工策划;架体采用钢管脚手架,立杆横杆规格为φ48.3mm×3.5mm,支撑顶板外径为36mm,主龙骨采用钢管,次龙骨采用40×90mm方木(过刨),模板采用双面覆膜木胶合板模板规格为:1830*915*15mm;Construction planning of the formwork system; the frame body adopts steel pipe scaffolding, the vertical rod and cross bar are φ48.3mm×3.5mm, the outer diameter of the supporting roof is 36mm, the main keel is made of steel pipe, and the secondary keel is made of 40×90mm square wood (planed). The formwork adopts double-sided laminated wood plywood formwork specifications: 1830*915*15mm;
砌体排版深化设计;根据砌体排版,深化构造柱间距及腰梁位置,绘制砌体排版平面布置图及施工大样图,最后出具总材料用量清单;Masonry typesetting deepening design; according to the masonry typesetting, deepen the structural column spacing and waist beam position, draw the masonry typesetting layout plan and large construction sample diagram, and finally issue a list of total material consumption;
测量放线、定位;根据施工图纸,使用经纬仪测出斜墙上下边线及倾斜墙体线,以准确搭设墙体模板;Measure the setting out and positioning; according to the construction drawings, use the theodolite to measure the upper and lower lines of the inclined wall and the inclined wall line, so as to accurately erect the wall formwork;
搭设双侧脚手架;由于需搭设模架,无法从建筑内侧倒运建筑材料,外侧墙体普遍较高,根据现场施工条件采用移动式剪叉升降机倒运加气块及砂浆等材料,除需要额外搭设支架外,本工法斜墙砌筑与普通砌墙方法基本相同,但须特别注意砂浆稠度以保证墙体砂浆饱满度。为控制斜墙后期变形与裂缝产生,墙体锚拉筋每250mm高设置两根HRB400/6钢筋;Set up double-sided scaffolding; due to the need to set up formwork, it is impossible to transport building materials from the inside of the building, and the outer walls are generally high. According to the construction conditions on site, a mobile scissor lift is used to transport materials such as aerated blocks and mortar, except that additional supports are required. In addition, the construction method of inclined wall masonry is basically the same as that of ordinary wall masonry, but special attention must be paid to the consistency of the mortar to ensure the fullness of the wall mortar. In order to control the late deformation and cracks of the inclined wall, two HRB400/6 steel bars are installed for every 250mm height of the anchor bars of the wall;
模板支设(圈梁钢筋绑扎及模板支设,双面胶带粘贴;圈梁及构造柱模板支设);根据放出的墙体倾斜线及控制线,按照支架方案搭设内侧支架模板,架体搭设立杆间距≤900,水平杆间距≤1250,为保证模板侧向刚度同步搭设三道斜撑,斜撑间距≤900,并每隔三道斜撑使用膨胀螺固定,并按照施工进度同步搭设外侧脚手架,以便于施工;Formwork support (ring beam reinforcement binding and formwork support, double-sided tape pasting; ring beam and structural column formwork support); according to the released wall inclination line and control line, set up the inner support formwork according to the support plan, and the frame body Set up a pole spacing of ≤900 and a horizontal pole spacing of ≤1250. In order to ensure the lateral rigidity of the formwork, three diagonal braces are erected synchronously. The spacing of the diagonal braces is ≤900, and every third diagonal brace is fixed with expansion screws, and the outer side is erected synchronously according to the construction progress. Scaffolding to facilitate construction;
钻孔植筋(构造柱钢筋绑扎,圈梁钢筋绑扎);为保证斜墙整体合格率,砌体锚拉筋为每250mm高设置两根HRB400/6钢筋,斜墙构造柱间距≤2.0m,柱截面为墙宽*200,纵筋两根HRB400/12,箍筋为CRB600H/6@200圈梁宽度同墙厚,高度为200mm,纵筋为上、下各2根HRB400/12,箍筋为CRB600H/8@200。砌体植筋在原框柱上,植筋深度90mm,构造柱钢筋植筋深度为390mm;Drilling and planting reinforcement (binding of structural column reinforcement and ring beam reinforcement); in order to ensure the overall qualification rate of the inclined wall, two HRB400/6 reinforcement bars are set for every 250mm height of the masonry anchor reinforcement, and the spacing between the structural columns of the inclined wall is ≤2.0m. Column section is wall width*200, two longitudinal reinforcements HRB400/12, stirrups are CRB600H/6@200 ring beam width same as wall thickness, height is 200mm, longitudinal reinforcements are upper and lower two HRB400/12, stirrups For CRB600H/8@200. The masonry bar is planted on the original frame column, the planting bar depth is 90mm, and the structural column steel bar planting depth is 390mm;
圈梁以下砌体砌筑;砌块砌筑前一天应进行浇水湿润,冲去浮尘,清除砌块表面的杂物后方可吊、运就位。砌筑就位应先远后近、先下后上、先外后内;每层开始时,应从转角处或定位砌块处开始;应砌一皮、校正一皮,皮皮拉线控制砌体标高和墙面平整度。为保证砌块不产生侧向位移,一次砌筑高度不得超过1500mm,间隔三天再砌筑上部砌体;The masonry below the ring beam is built; the block should be watered and moistened one day before the block is built, the floating dust should be washed away, and the sundries on the surface of the block should be removed before being hoisted and transported in place. When the masonry is in place, it should be far away and then close, first down and then up, first outside and then inside; when each layer starts, it should start from the corner or the positioning block; one skin should be built, one skin should be corrected, and the skin should be pulled to control the masonry Level and wall flatness. In order to ensure that the blocks do not have lateral displacement, the height of one masonry shall not exceed 1500mm, and the upper masonry shall be built at intervals of three days;
圈梁及圈梁下构造柱浇筑(圈梁及构造柱浇筑,);构造柱、圈梁模板用对拉螺杆固定,对拉螺杆间距500mm,并在模板内下侧于墙体接触部位贴密封胶条构造柱的浇筑应采取上下两层分步浇筑的方法,并采取可靠的振捣措施保证振捣密实,避免跑模漏浆;Pouring of the ring beam and the structural column under the ring beam (pouring of the ring beam and the structural column); the structural column and the ring beam formwork are fixed with tensioning screws with a distance of 500mm between the tensioning screws, and the inner and lower sides of the formwork are sealed at the contact part of the wall The pouring of the rubber strip structure column should adopt the method of pouring the upper and lower layers step by step, and take reliable vibration measures to ensure the compactness of the vibration and avoid the leakage of the mold;
圈梁以上砌体砌筑;上部墙体砌筑与圈梁以下一致,待上下墙体全部砌筑完成后,养护满14天,在斜墙的底部、顶部全部采用C25细石微膨胀素混凝土找平;Masonry above the ring beam; the upper wall is the same as that below the ring beam. After the upper and lower walls are completely built, after 14 days of curing, the bottom and top of the inclined wall are all made of C25 fine stone micro-expansion concrete leveling;
拆除模板(墙顶施工,待填充墙砌筑完并应至少间隔14天后施工);为保证拆模后墙体不产生裂缝,经现场试验确定,参照《混凝土结构工程施工质量验收规范》中板(>2m、≤8m)的拆模条件,现场留置砂浆及混凝土同条件试块,混凝土结构及砂浆强度达到设计强度75%以上方可进行拆模作业,模板及架体拆除后用于下一道墙体施工;Remove the formwork (construction on the top of the wall, after the filling wall is completed and should be constructed at least 14 days later); in order to ensure that there will be no cracks in the wall after the formwork is removed, it is determined by field tests, referring to the "Construction Quality Acceptance Specification for Concrete Structure Engineering" (>2m, ≤8m) formwork demolition conditions, mortar and concrete test blocks with the same conditions shall be left on site, and the concrete structure and mortar strength shall reach more than 75% of the design strength before the formwork demolition operation can be carried out. After the formwork and frame are removed, they will be used for the next step wall construction;
拆除架体并修补孔洞;拆除模板后形成脚手架孔洞,采用C25细石微膨胀素混凝土进行封堵,待拆模后剔除表面凸出多余混凝土,并采用M25预拌水泥砂浆抹平,后期洞口周围300mm范围内附加1.5厚聚合物水泥防水涂料Ⅱ型一道。Remove the frame body and repair the hole; after removing the formwork, the scaffold hole is formed, and it is sealed with C25 fine stone micro-expansion concrete. Add a 1.5-thick polymer cement waterproof coating type II within the range of 300mm.
优选的:所述架体采用钢管脚手架,立杆横杆规格为φ48.3mm×3.5mm,支撑顶板外径为36mm,主龙骨采用钢管,次龙骨采用40×90mm方木(过刨),模板采用双面覆膜木胶合板模板规格为:1830*915*15mm。Preferably: the frame body adopts steel pipe scaffolding, the specification of the vertical rod and cross bar is φ48.3mm×3.5mm, the outer diameter of the supporting top plate is 36mm, the main keel is made of steel pipe, the secondary keel is made of 40×90mm square wood (planed), and the formwork The specification of double-sided laminated wood plywood formwork is: 1830*915*15mm.
优选的:所述为保证后期墙面不产生开裂等质量事故,斜墙内外两面均采用钢丝网砂浆面层加强。砂浆厚度为20mm,采用M20预拌水泥砂浆,内敷16号钢丝网20mm*20mm。Preferably: in order to ensure that there will be no quality accidents such as cracks on the wall surface in the later stage, the inner and outer sides of the inclined wall are reinforced with steel wire mesh mortar surface. The thickness of the mortar is 20mm, and M20 ready-mixed cement mortar is used, and 16-gauge steel wire mesh 20mm*20mm is applied inside.
与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:
1.有效解决斜墙角度与墙体变形量等施工质量的问题,同时也有效解决了斜墙施工难度大的难题,相比传统的施工方法,提高了施工效率,质量也更为可靠;1. Effectively solve the problems of construction quality such as the angle of the inclined wall and the amount of deformation of the wall, and also effectively solve the problem of difficult construction of the inclined wall. Compared with the traditional construction method, the construction efficiency is improved and the quality is more reliable;
2.模架体系需要提前进行深化排布、受力计算,使支模体系安全可靠,受力稳定。搭设尺寸规范化、标准化,避免操作工人随意搭设,出现不稳定得节点;2. The formwork system needs to be in-depth arrangement and force calculation in advance to make the formwork system safe and reliable, and the force is stable. Standardize and standardize the size of the erection, to avoid the random erection of the operators and the occurrence of unstable nodes;
3.本工法适用性和可操作性强,安全可靠度高,施工便捷,操作简单工人易接受,重要的是消除了施工过程中的安全隐患,实施效果好,多适用于博物馆建筑、剧院建筑、体育场馆等公共建筑中角度大于8°的大倾斜墙体的施工。3. This construction method has strong applicability and operability, high safety and reliability, convenient construction, simple operation and easy acceptance by workers. The most important thing is to eliminate potential safety hazards in the construction process, and the implementation effect is good. It is mostly suitable for museum buildings and theater buildings. Construction of large inclined walls with an angle greater than 8° in public buildings such as stadiums and stadiums.
附图说明Description of drawings
图1为大角度斜砌墙施工工法的施工流程图。Figure 1 is a construction flow chart of the large-angle oblique wall construction method.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
请参阅图1,本发明实施例中,大角度斜砌墙施工工法,所述施工工法包括以下步骤:Please refer to Fig. 1, in the embodiment of the present invention, the large-angle oblique wall construction method, the construction method includes the following steps:
模架体系施工策划;架体采用钢管脚手架,立杆横杆规格为φ48.3mm×3.5mm,支撑顶板外径为36mm,主龙骨采用钢管,次龙骨采用40×90mm方木(过刨),模板采用双面覆膜木胶合板模板规格为:1830*915*15mm;Construction planning of the formwork system; the frame body adopts steel pipe scaffolding, the vertical rod and cross bar are φ48.3mm×3.5mm, the outer diameter of the supporting roof is 36mm, the main keel is made of steel pipe, and the secondary keel is made of 40×90mm square wood (planed). The formwork adopts double-sided laminated wood plywood formwork specifications: 1830*915*15mm;
砌体排版深化设计;根据砌体排版,深化构造柱间距及腰梁位置,绘制砌体排版平面布置图及施工大样图,最后出具总材料用量清单;Masonry typesetting deepening design; according to the masonry typesetting, deepen the structural column spacing and waist beam position, draw the masonry typesetting layout plan and large construction sample diagram, and finally issue a list of total material consumption;
测量放线、定位;根据施工图纸,使用经纬仪测出斜墙上下边线及倾斜墙体线,以准确搭设墙体模板;Measure the setting out and positioning; according to the construction drawings, use the theodolite to measure the upper and lower lines of the inclined wall and the inclined wall line, so as to accurately erect the wall formwork;
搭设双侧脚手架;由于需搭设模架,无法从建筑内侧倒运建筑材料,外侧墙体普遍较高,根据现场施工条件采用移动式剪叉升降机倒运加气块及砂浆等材料,除需要额外搭设支架外,本工法斜墙砌筑与普通砌墙方法基本相同,但须特别注意砂浆稠度以保证墙体砂浆饱满度。为控制斜墙后期变形与裂缝产生,墙体锚拉筋每250mm高设置两根HRB400/6钢筋;Set up double-sided scaffolding; due to the need to set up formwork, it is impossible to transport building materials from the inside of the building, and the outer walls are generally high. According to the construction conditions on site, a mobile scissor lift is used to transport materials such as aerated blocks and mortar, except that additional supports are required. In addition, the construction method of inclined wall masonry is basically the same as that of ordinary wall masonry, but special attention must be paid to the consistency of the mortar to ensure the fullness of the wall mortar. In order to control the late deformation and cracks of the inclined wall, two HRB400/6 steel bars are installed for every 250mm height of the anchor bars of the wall;
模板支设(圈梁钢筋绑扎及模板支设,双面胶带粘贴;圈梁及构造柱模板支设);根据放出的墙体倾斜线及控制线,按照支架方案搭设内侧支架模板,架体搭设立杆间距≤900,水平杆间距≤1250,为保证模板侧向刚度同步搭设三道斜撑,斜撑间距≤900,并每隔三道斜撑使用膨胀螺固定,并按照施工进度同步搭设外侧脚手架,以便于施工;Formwork support (ring beam reinforcement binding and formwork support, double-sided tape pasting; ring beam and structural column formwork support); according to the released wall slope line and control line, the inner support formwork is erected according to the support plan, and the frame body is erected. Set up a pole spacing of ≤900 and a horizontal pole spacing of ≤1250. In order to ensure the lateral stiffness of the formwork, three diagonal braces are erected synchronously. The spacing of the diagonal braces is ≤900, and every third diagonal brace is fixed with expansion screws, and the outer side is erected synchronously according to the construction progress. Scaffolding to facilitate construction;
钻孔植筋(构造柱钢筋绑扎,圈梁钢筋绑扎);为保证斜墙整体合格率,砌体锚拉筋为每250mm高设置两根HRB400/6钢筋,斜墙构造柱间距≤2.0m,柱截面为墙宽*200,纵筋两根HRB400/12,箍筋为CRB600H/6@200圈梁宽度同墙厚,高度为200mm,纵筋为上、下各2根HRB400/12,箍筋为CRB600H/8@200。砌体植筋在原框柱上,植筋深度90mm,构造柱钢筋植筋深度为390mm;Drilling and planting reinforcement (binding of structural column reinforcement and ring beam reinforcement); in order to ensure the overall qualification rate of the inclined wall, two HRB400/6 reinforcement bars are set for every 250mm height of the masonry anchor reinforcement, and the spacing between the structural columns of the inclined wall is ≤2.0m. Column section is wall width*200, two longitudinal reinforcements HRB400/12, stirrups are CRB600H/6@200 ring beam width same as wall thickness, height is 200mm, longitudinal reinforcements are upper and lower two HRB400/12, stirrups For CRB600H/8@200. The masonry bar is planted on the original frame column, the planting bar depth is 90mm, and the structural column steel bar planting depth is 390mm;
圈梁以下砌体砌筑;砌块砌筑前一天应进行浇水湿润,冲去浮尘,清除砌块表面的杂物后方可吊、运就位。砌筑就位应先远后近、先下后上、先外后内;每层开始时,应从转角处或定位砌块处开始;应砌一皮、校正一皮,皮皮拉线控制砌体标高和墙面平整度。为保证砌块不产生侧向位移,一次砌筑高度不得超过1500mm,间隔三天再砌筑上部砌体;Masonry below the ring beam; the block should be watered and moistened the day before the masonry is built, the floating dust should be washed away, and the sundries on the surface of the block should be removed before being hoisted and transported in place. The masonry should be placed far and then close, first down and then up, first outside and then inside; at the beginning of each layer, it should start from the corner or the positioning block; one skin should be built, one skin should be corrected, and the skin should be pulled to control the masonry Level and wall flatness. In order to ensure that the blocks do not have lateral displacement, the height of one masonry shall not exceed 1500mm, and the upper masonry shall be built at intervals of three days;
圈梁及圈梁下构造柱浇筑(圈梁及构造柱浇筑,);构造柱、圈梁模板用对拉螺杆固定,对拉螺杆间距500mm,并在模板内下侧于墙体接触部位贴密封胶条构造柱的浇筑应采取上下两层分步浇筑的方法,并采取可靠的振捣措施保证振捣密实,避免跑模漏浆;Pouring of the ring beam and the structural column under the ring beam (pouring of the ring beam and the structural column); the structural column and the ring beam formwork are fixed with tensioning screws with a distance of 500mm between the tensioning screws, and the inner and lower sides of the formwork are sealed at the contact part of the wall The pouring of the rubber strip structure column should adopt the method of pouring the upper and lower layers step by step, and take reliable vibration measures to ensure the compactness of the vibration and avoid the leakage of the mold;
圈梁以上砌体砌筑;上部墙体砌筑与圈梁以下一致,待上下墙体全部砌筑完成后,养护满14天,在斜墙的底部、顶部全部采用C25细石微膨胀素混凝土找平;Masonry above the ring beam; the upper wall is the same as that below the ring beam. After the upper and lower walls are completely built, after 14 days of curing, the bottom and top of the inclined wall are all made of C25 fine stone micro-expansion concrete leveling;
拆除模板(墙顶施工,待填充墙砌筑完并应至少间隔14天后施工);为保证拆模后墙体不产生裂缝,经现场试验确定,参照《混凝土结构工程施工质量验收规范》中板(>2m、≤8m)的拆模条件,现场留置砂浆及混凝土同条件试块,混凝土结构及砂浆强度达到设计强度75%以上方可进行拆模作业,模板及架体拆除后用于下一道墙体施工;Remove the formwork (construction on the top of the wall, after the filling wall is completed and should be constructed at least 14 days later); in order to ensure that there will be no cracks in the wall after the formwork is removed, it is determined by field tests, referring to the "Construction Quality Acceptance Specification for Concrete Structure Engineering" (>2m, ≤8m) formwork demolition conditions, mortar and concrete test blocks with the same conditions shall be left on site, and the concrete structure and mortar strength shall reach more than 75% of the design strength before the formwork demolition operation can be carried out. After the formwork and frame are removed, they will be used for the next step wall construction;
拆除架体并修补孔洞;拆除模板后形成脚手架孔洞,采用C25细石微膨胀素混凝土进行封堵,待拆模后剔除表面凸出多余混凝土,并采用M25预拌水泥砂浆抹平,后期洞口周围300mm范围内附加1.5厚聚合物水泥防水涂料Ⅱ型一道。Remove the frame body and repair the hole; after removing the formwork, the scaffold hole is formed, and it is sealed with C25 fine stone micro-expansion concrete. Add a 1.5-thick polymer cement waterproof coating type II within the range of 300mm.
所述架体采用钢管脚手架,立杆横杆规格为φ48.3mm×3.5mm,支撑顶板外径为36mm,主龙骨采用钢管,次龙骨采用40×90mm方木(过刨),模板采用双面覆膜木胶合板模板规格为:1830*915*15mm。The frame body adopts steel pipe scaffolding, the specification of the vertical rod and cross bar is φ48.3mm×3.5mm, the outer diameter of the supporting top plate is 36mm, the main keel is made of steel pipe, the secondary keel is made of 40×90mm square wood (planed), and the formwork is double-sided The specifications of the laminated wood plywood formwork are: 1830*915*15mm.
所述为保证后期墙面不产生开裂等质量事故,斜墙内外两面均采用钢丝网砂浆面层加强。砂浆厚度为20mm,采用M20预拌水泥砂浆,内敷16号钢丝网20mm*20mm。In order to ensure that there will be no quality accidents such as cracks on the wall in the later stage, the inner and outer sides of the inclined wall are reinforced with steel mesh mortar surface. The thickness of the mortar is 20mm, and M20 ready-mixed cement mortar is used, and 16-gauge steel wire mesh 20mm*20mm is applied inside.
对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其他的具体形式实现本发明。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。It will be apparent to those skilled in the art that the invention is not limited to the details of the above-described exemplary embodiments, but that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Accordingly, the embodiments should be regarded in all points of view as exemplary and not restrictive, the scope of the invention being defined by the appended claims rather than the foregoing description, and it is therefore intended that the scope of the invention be defined by the appended claims rather than by the foregoing description. All changes within the meaning and range of equivalents of the elements are embraced in the present invention. Any reference sign in a claim should not be construed as limiting the claim concerned.
此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。In addition, it should be understood that although this specification is described according to implementation modes, not each implementation mode only contains an independent technical solution, and this description in the specification is only for clarity, and those skilled in the art should take the specification as a whole , the technical solutions in the various embodiments can also be properly combined to form other implementations that can be understood by those skilled in the art.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211452490.XA CN115822271A (en) | 2022-11-21 | 2022-11-21 | Construction method of oblique wall with large angle |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211452490.XA CN115822271A (en) | 2022-11-21 | 2022-11-21 | Construction method of oblique wall with large angle |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115822271A true CN115822271A (en) | 2023-03-21 |
Family
ID=85529480
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211452490.XA Pending CN115822271A (en) | 2022-11-21 | 2022-11-21 | Construction method of oblique wall with large angle |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115822271A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117738355A (en) * | 2023-12-19 | 2024-03-22 | 中国五冶集团有限公司 | A masonry method and structure of non-parallel steel inclined columns for partition walls |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20010019548A (en) * | 1999-08-27 | 2001-03-15 | 이창남 | The SEN Retaining Wall |
| CN112411882A (en) * | 2020-11-27 | 2021-02-26 | 上海宝冶集团有限公司 | Method for building ultrahigh and oversized space inclined cylindrical column |
| CN113530267A (en) * | 2021-08-13 | 2021-10-22 | 上海宝冶集团有限公司 | A masonry method suitable for inclined walls |
| CN216476421U (en) * | 2021-11-23 | 2022-05-10 | 上海飞玲建筑装饰工程有限公司 | A platform of unloading for construction |
-
2022
- 2022-11-21 CN CN202211452490.XA patent/CN115822271A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20010019548A (en) * | 1999-08-27 | 2001-03-15 | 이창남 | The SEN Retaining Wall |
| CN112411882A (en) * | 2020-11-27 | 2021-02-26 | 上海宝冶集团有限公司 | Method for building ultrahigh and oversized space inclined cylindrical column |
| CN113530267A (en) * | 2021-08-13 | 2021-10-22 | 上海宝冶集团有限公司 | A masonry method suitable for inclined walls |
| CN216476421U (en) * | 2021-11-23 | 2022-05-10 | 上海飞玲建筑装饰工程有限公司 | A platform of unloading for construction |
Non-Patent Citations (1)
| Title |
|---|
| 郑义;: "斜墙砌筑技术探讨", 福建建筑, no. 01, 1 January 2009 (2009-01-01), pages 64 - 65 * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117738355A (en) * | 2023-12-19 | 2024-03-22 | 中国五冶集团有限公司 | A masonry method and structure of non-parallel steel inclined columns for partition walls |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101603372B (en) | Method for reinforcing integral replacement concrete for high-rise building steel bar concrete column | |
| CN104631512B (en) | Hang modulus method after-pouring band beam-slab construction method | |
| CN106988525A (en) | A kind of skyscraper aluminum alloy mould plate construction method | |
| CN108005387B (en) | Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall | |
| CN110145124A (en) | A reinforcement tool and its construction method for controlling the quality of horizontal stubble of shear walls | |
| CN108677962A (en) | A kind of subway comes in and goes out line segment foundation pit fixing of the forming frame and method for dismounting | |
| CN117306861A (en) | Construction method of prefabricated canopy at tunnel entrance based on BIM technology | |
| CN115822271A (en) | Construction method of oblique wall with large angle | |
| CN106285721B (en) | A kind of railway culvert method of construction based on sliding mode system | |
| CN216787893U (en) | Prefabricated shear wall positioner | |
| CN115839184A (en) | Ancient building wall dismantling and building repairing method | |
| CN106930391B (en) | Cast-in-place drainage channel structure of top plate for formwork-free construction and construction method | |
| CN210002862U (en) | A single-sided formwork system adjacent to the existing basement exterior wall | |
| CN206070570U (en) | A kind of building structure | |
| CN110847598A (en) | A kind of thin-walled hollow pier diaphragm bottom formwork and construction method | |
| CN116971798A (en) | Arch tunnel structure and arch tunnel construction method | |
| CN219992537U (en) | A construction device for removing and temporarily replacing supporting piles, anchor cables and waist beams | |
| CN115627778A (en) | A combined construction method of cover-excavation and reverse-work subway station waist beams and structural side walls | |
| CN115404911B (en) | Reverse construction method of underground structure | |
| CN213683130U (en) | Bowl buckle type full-hall support capable of being constructed quickly in underground structure | |
| CN221856176U (en) | Steel-wood mixed template reinforcing system of shear wall at expansion joint | |
| CN115652999B (en) | A construction method and structural system for a crane beam structure on the rock wall of an underground powerhouse | |
| CN223151330U (en) | Building prefabricated component system and assembled building | |
| CN217106297U (en) | Node structure of reinforcing construction unloading device | |
| CN118835648A (en) | Construction method for waterproof basement exterior wall and formwork reinforcement at limited space |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20230321 |
|
| WD01 | Invention patent application deemed withdrawn after publication |