CN115822233A - Construction process of overhanging scaffold - Google Patents

Construction process of overhanging scaffold Download PDF

Info

Publication number
CN115822233A
CN115822233A CN202211600247.8A CN202211600247A CN115822233A CN 115822233 A CN115822233 A CN 115822233A CN 202211600247 A CN202211600247 A CN 202211600247A CN 115822233 A CN115822233 A CN 115822233A
Authority
CN
China
Prior art keywords
cantilevered
scaffold
vertical
erection
scaffolding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211600247.8A
Other languages
Chinese (zh)
Inventor
王维军
李栋
朱朋刚
陈强
张冬瑞
焦亚
张钦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 20th Bureau Group Corp
Third Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Original Assignee
China Railway 20th Bureau Group Corp
Third Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 20th Bureau Group Corp, Third Engineering Co Ltd of China Railway 20th Bureau Group Co Ltd filed Critical China Railway 20th Bureau Group Corp
Priority to CN202211600247.8A priority Critical patent/CN115822233A/en
Publication of CN115822233A publication Critical patent/CN115822233A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The application discloses scaffold that encorbelments frame construction technology belongs to building engineering technical field. The cantilever I-shaped steel is installed on an embedded part embedded in the original construction process of a lower tower column; laying a first steel plate on the overhanging I-shaped steel to form a set-up foundation; and erecting the overhanging scaffold on the erection basis. It can be understood that, in the method, the scaffold is not set up from the ground, but the scaffold is set up from the construction height of the lower tower column, the overhanging I-shaped steel is installed on the embedded part embedded in the original construction process of the lower tower column, and the scaffold is set up on the basis of the overhanging I-shaped steel and the support of the steel plate, so that the setting material cost and the labor cost of the scaffold with the length of at least 16 meters are saved. In addition, the vertical rods, the longitudinal horizontal rods, the transverse horizontal rods and the cross braces are used in the method for erecting the vertical rods, the longitudinal horizontal rods, the transverse horizontal rods and the cross braces, so that the stability of the scaffold is enhanced, and the safety of the scaffold is improved.

Description

悬挑脚手架施工工艺Construction technology of cantilevered scaffolding

技术领域technical field

本申请涉及建筑施工技术领域,特别涉及一种悬挑脚手架施工工艺。The present application relates to the technical field of building construction, in particular to a construction technique of a cantilevered scaffold.

背景技术Background technique

在对下塔柱进行加固前,需要搭设脚手架,以供施工人员在下塔柱的施工高度进行加固施工,但由于主塔的下塔柱与地面呈倾斜状态,且下塔柱的施工高度在16米以上,若按目前的搭设方法来搭设脚手架,搭设成本较高。Before reinforcing the lower tower column, scaffolding needs to be set up for construction workers to carry out reinforcement construction at the construction height of the lower tower column, but because the lower tower column of the main tower is inclined to the ground, and the construction height of the lower tower column is 16 More than meters, if the scaffolding is erected according to the current erection method, the erection cost will be higher.

上述内容仅用于辅助理解本申请的技术方案,并不代表承认上述内容是现有技术。The above content is only used to assist in understanding the technical solution of the present application, and does not mean that the above content is admitted as prior art.

申请内容application content

本申请的主要目的是提供一种悬挑脚手架施工工艺,旨在解决现有技术中脚手架的搭设成本较高的技术问题。The main purpose of this application is to provide a construction technique for cantilevered scaffolding, aiming to solve the technical problem of high scaffolding erection cost in the prior art.

为实现上述目的,本申请提出的悬挑脚手架施工工艺,所述悬挑脚手架施工工艺包括以下步骤:In order to achieve the above object, the application proposes a cantilevered scaffolding construction process, the cantilevered scaffolding construction process includes the following steps:

在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢;Install cantilevered I-beams on the pre-embedded parts pre-buried in the original construction process of the lower tower column;

在所述悬挑工字钢上铺设第一钢板,形成搭设基础;Laying the first steel plate on the cantilevered I-beam to form the erection foundation;

在所述搭设基础上搭设所述悬挑脚手架。The cantilevered scaffold is erected on the erection basis.

可选地,所述在所述搭设基础上搭设所述悬挑脚手架的步骤,包括:Optionally, the step of erecting the cantilevered scaffold on the erection foundation includes:

在所述搭设基础上搭设立杆;erecting poles on said erecting foundation;

当所述立杆搭设完成后,搭设纵向水平杆,在所述纵向水平杆与所述立杆相交处用直角扣件固定;After the erection of the vertical rod is completed, a vertical horizontal rod is erected, and the intersection of the vertical horizontal rod and the vertical rod is fixed with a right-angle fastener;

当所述纵向水平杆搭设完成后,在所述纵向水平杆的下方搭设横向水平杆;After the erection of the longitudinal horizontal bar is completed, a horizontal horizontal bar is erected below the longitudinal horizontal bar;

当所述横向水平杆搭设完成后,在所述立杆的外侧搭设剪刀撑,在剪刀撑与外侧立杆的交接处采用旋转扣件连接。After the erection of the horizontal bar is completed, set up a scissors brace on the outside of the vertical bar, and use a rotary fastener to connect the scissors brace and the outer vertical bar at the junction.

可选地,所述在所述搭设基础上搭设立杆的步骤,包括:Optionally, the step of erecting poles on the erected foundation includes:

将所述立杆支承在所述悬挑工字钢正上方;Supporting the vertical rod directly above the cantilevered I-beam;

在所述悬挑工字钢上焊接U型钢筋,通过所述U型钢筋,将所述立杆与所述悬挑工字钢固定连接,以完成所述立杆的搭设。U-shaped steel bars are welded on the cantilevered I-beam, and the vertical bar is fixedly connected with the cantilevered I-shaped steel bar through the U-shaped steel bar to complete the erection of the vertical bar.

可选地,所述悬挑工字钢正上方的立杆由多根长度不同的钢管拼接而成。Optionally, the vertical pole directly above the cantilevered I-beam is spliced by a plurality of steel pipes of different lengths.

可选地,所述悬挑工字钢正上方的相邻立杆的多根钢管连接处在不同高度上。Optionally, the connections of multiple steel pipes of adjacent vertical poles directly above the cantilevered I-beam are at different heights.

可选地,所述相邻立杆的多根钢管连接处在不同高度上的高度差为至少50厘米。Optionally, the difference in height between the multiple steel pipes of the adjacent poles at different heights is at least 50 centimeters.

可选地,所述立杆的多根钢管的顶层连接处采用搭设连接,非顶层连接处采用对接扣件连接。Optionally, the top-layer connections of the plurality of steel pipes of the vertical rod are connected by bridging, and the non-top-layer connections are connected by butt fasteners.

可选地,所述悬挑工字钢在所述下塔柱的大小里程侧对称悬挑。Optionally, the cantilevered I-beam is symmetrically cantilevered on the large and small mileage sides of the lower tower column.

可选地,所述在所述搭设基础上搭设立杆的步骤之后,所述方法还包括:Optionally, after the step of erecting poles on the erected foundation, the method further includes:

在所述立杆底部向上至少20厘米处安装纵向扫地杆和横向扫地杆。A longitudinal sweeping rod and a horizontal sweeping rod are installed at least 20 centimeters upwards from the bottom of the pole.

可选地,所述在所述搭设基础上搭设所述悬挑脚手架的步骤之后,所述方法还包括:Optionally, after the step of erecting the cantilevered scaffold on the erection foundation, the method further includes:

将所述下塔柱的原施工过程中预埋的第二钢板作为连墙件;The second steel plate pre-embedded in the original construction process of the lower tower column is used as a connecting wall piece;

采用所述连墙件对所述悬挑脚手架进行加固;The cantilevered scaffold is reinforced by using the wall connecting piece;

在所述悬挑式脚手架的第一步和操作层上铺设脚手板,在所述悬挑式脚手架的非操作层铺设水平安全网。Lay the scaffold board on the first step and the operation layer of the cantilevered scaffold, and lay a horizontal safety net on the non-operational layer of the cantilevered scaffold.

本申请提出一种悬挑脚手架施工工艺,现有技术中由于主塔的下塔柱与地面呈倾斜状态,且下塔柱的施工高度在16米以上,若按目前的搭设方法来搭设脚手架,搭设成本较高,与之相比,本申请在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢;在所述悬挑工字钢上铺设第一钢板,形成搭设基础;在所述搭设基础上搭设所述悬挑脚手架。可以理解,本申请不从地面开始搭设脚手架,而是从下塔柱的施工高度处开始搭设脚手架,通过在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢,在悬挑工字钢和钢板的支撑下,以此为基础搭设脚手架,节省了至少16米以下的脚手架的搭设材料成本以及人工成本。The application proposes a construction technique for cantilevered scaffolding. In the prior art, since the lower column of the main tower is inclined to the ground, and the construction height of the lower column is more than 16 meters, if the scaffolding is erected according to the current erection method, The erection cost is relatively high. Compared with it, the application installs the cantilevered I-beam on the pre-embedded parts embedded in the original construction process of the lower tower column; the first steel plate is laid on the cantilevered I-beam to form the The foundation; erecting the cantilevered scaffold on the erecting foundation. It can be understood that this application does not start to build scaffolding from the ground, but starts to build scaffolding from the construction height of the lower tower column. Under the support of cantilevered I-beams and steel plates, scaffolding is built on this basis, saving at least the cost of materials and labor costs for scaffolding below 16 meters.

附图说明Description of drawings

此处的附图被并入说明书中并构成本说明书的一部分,示出了符合本申请的实施例,并与说明书一起用于解释本申请的原理。The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the application and together with the description serve to explain the principles of the application.

为了更清楚地说明本申请实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,对于本领域普通技术人员而言,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, for those of ordinary skill in the art, In other words, other drawings can also be obtained from these drawings without paying creative labor.

图1为本申请悬挑脚手架施工工艺第一实施例的流程示意图;Fig. 1 is the schematic flow sheet of the first embodiment of the cantilevered scaffolding construction technique of the present application;

图2为本申请悬挑脚手架施工工艺第二实施例的脚手架横桥向布置图;Fig. 2 is the horizontal layout of the scaffolding in the second embodiment of the cantilevered scaffolding construction process of the present application;

图3为本申请悬挑脚手架施工工艺第三实施例的脚手架顺桥向布置图;Fig. 3 is the layout diagram of the scaffold along the bridge direction of the third embodiment of the cantilevered scaffold construction process of the present application;

图4为本申请悬挑脚手架施工工艺第四实施例的流程示意图。Fig. 4 is a schematic flowchart of the fourth embodiment of the cantilevered scaffolding construction process of the present application.

本申请目的实现、功能特点及优点将结合实施例,参照附图做进一步说明。The realization of the purpose, functions and advantages of the present application will be further described in conjunction with the embodiments and with reference to the accompanying drawings.

具体实施方式Detailed ways

应当理解,此处所描述的具体实施例仅仅用以解释本申请,并不用于限定本申请。It should be understood that the specific embodiments described here are only used to explain the present application, and are not intended to limit the present application.

本申请实施例提供了一种悬挑脚手架施工工艺,参照图1,图1为本申请悬挑脚手架施工工艺第一实施例的流程示意图。The embodiment of the present application provides a cantilevered scaffolding construction process. Referring to FIG. 1 , FIG. 1 is a schematic flowchart of the first embodiment of the cantilevered scaffolding construction process of the present application.

在本实施例中,所述悬挑脚手架施工工艺包括以下步骤:In this embodiment, the cantilevered scaffolding construction process includes the following steps:

步骤S10:在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢;Step S10: installing cantilevered I-beams on the pre-embedded parts embedded in the original construction process of the lower tower column;

作为一种示例,由于主墩总高度23.057米,且原有施工平台已拆除,在对下塔柱进行加固前,需要重新搭设施工平台。As an example, since the total height of the main pier is 23.057 meters and the original construction platform has been dismantled, the construction platform needs to be rebuilt before the lower tower column is reinforced.

作为一种示例,主塔由上塔柱、中塔柱和下塔柱构成,如图2所示,下塔柱的施工部位为图中的黑色阴影部分。实际施工过程中,测得该部分高度处于下主塔离地面16米以上。且该下塔柱相对地面为倾斜状态。As an example, the main tower is composed of an upper tower column, a middle tower column and a lower tower column, as shown in Figure 2, the construction site of the lower tower column is the black shaded part in the figure. During the actual construction process, the measured height of this part is above 16 meters from the ground of the lower main tower. And the lower tower column is in an inclined state relative to the ground.

作为一种示例,在对下塔柱的横桥向进行施工前,需要在下塔柱的四周搭设脚手架,即在下塔柱的横桥向以及顺桥向分别搭设脚手架。具体地,如图3所示,对下塔柱的顺桥向进行施工时需要搭设的脚手架是从承台顶面开始搭设的,架体搭设至下横梁顶部,现场施工中测得整体高度为23.057米。即,顺桥向脚手架为落地式脚手架,本申请对此不进行详细阐述。As an example, before the construction is carried out on the cross-bridge direction of the lower tower column, scaffolding needs to be set up around the lower tower column, that is, scaffolding is respectively erected in the cross-bridge direction and along the bridge direction of the lower tower column. Specifically, as shown in Figure 3, the scaffolding that needs to be erected when constructing the lower tower column along the direction of the bridge is erected from the top surface of the cap, and the scaffold body is erected to the top of the lower beam. The overall height measured during the on-site construction is 23.057 meters. That is, the scaffolding along the bridge is a floor-standing scaffold, which is not described in detail in this application.

作为一种示例,由于横桥向的下塔柱在搭设脚手架时,现有技术中由于主塔的下塔柱与地面呈倾斜状态,且下塔柱的施工高度在16米以上,若按目前的搭设方法来搭设脚手架,搭设成本较高,即,从地面开始搭设脚手架会浪费大量材料成本,因此,横桥向搭设的脚手架为悬挑脚手架。As an example, when scaffolding is erected for the lower tower column in the direction of the transverse bridge, in the prior art, the lower tower column of the main tower is inclined to the ground, and the construction height of the lower tower column is more than 16 meters. The erection method is used to erect the scaffold, and the erection cost is relatively high, that is, a large amount of material cost will be wasted if the scaffold is erected from the ground. Therefore, the scaffold erected in the direction of the transverse bridge is a cantilevered scaffold.

作为一种示例,利用原主塔的下塔柱部分在施工过程中预埋的预埋件,在该预埋件上安装悬挑工字钢,具体地,在预埋件上焊接悬挑工字钢牛腿,再将悬挑工字钢固定至悬挑工字钢牛腿上,悬挑工字钢的一端悬挑,另一端固定在下塔柱结构上。As an example, use the embedded part embedded in the lower column part of the original main tower during the construction process, install the cantilevered I-beam on the embedded part, specifically, weld the cantilevered I-beam on the embedded part steel corbel, and then fix the cantilevered I-beam to the cantilevered I-beam corbel, one end of the cantilevered I-beam cantilevered, and the other end is fixed on the lower tower structure.

作为一种示例,该悬挑工字钢为I20B工字钢。As an example, the cantilevered I-beam is I20B I-beam.

在本实施例中,所述下塔柱有四个,所述悬挑工字钢在所述四个下塔柱的大小里程侧对称悬挑。In this embodiment, there are four lower tower columns, and the cantilevered I-beam is symmetrically cantilevered on the side of the four lower tower columns.

作为一种示例,参照图2,从顺桥向视角内的一对下主塔的大小里程侧的悬挑工字钢对称悬挑,可以是对称悬挑2.65米或2.67米等。As an example, referring to FIG. 2 , the cantilevered I-beam symmetrical cantilever on the large and small mileage sides of the pair of lower main towers in the viewing angle along the bridge can be 2.65 meters or 2.67 meters.

作为一种示例,参照图3,横桥向的两个下主塔的左右侧工字钢对称悬挑,可以是对称悬挑3米或3.2米等。As an example, referring to FIG. 3 , the left and right side I-beams of the two lower main towers in the direction of the transverse bridge are symmetrically overhanged, which can be 3 meters or 3.2 meters.

作为一种示例,对称悬挑能够减少下主塔的结构预应力损失。As an example, symmetrical overhangs can reduce structural prestress losses in the lower main tower.

步骤S20:在所述悬挑工字钢上铺设第一钢板,形成搭设基础;Step S20: laying a first steel plate on the cantilevered I-beam to form a foundation;

作为一种示例,在所述悬挑工字钢上铺设第一钢板,形成搭设基础,能够强力支撑脚手架的重量。As an example, the first steel plate is laid on the cantilevered I-beam to form a foundation, which can strongly support the weight of the scaffold.

作为一种示例,还可结合支栈桥与悬挑工字钢,在支栈桥与悬挑工字钢上铺设第一钢板,形成搭设基础。As an example, the trestle bridge and the cantilevered I-beam can also be combined, and the first steel plate is laid on the trestle bridge and the cantilevered I-beam to form the erection foundation.

作为一种示例,该第一钢板为花纹钢板,可以起到防滑的作用,提高施工安全性。As an example, the first steel plate is a checkered steel plate, which can play an anti-slip function and improve construction safety.

步骤S30:在所述搭设基础上搭设所述悬挑脚手架。Step S30: Erection of the cantilevered scaffold on the erection foundation.

作为一种示例,在所述四个下主塔的外围搭设悬挑脚手架,即,减少了从地面到该搭设基础的所有用料,节省了成本。As an example, a cantilevered scaffold is erected on the periphery of the four lower main towers, that is, all materials used from the ground to the erected foundation are reduced, and the cost is saved.

在本实施例中,所述在所述搭设基础上搭设所述悬挑脚手架的步骤,包括:In this embodiment, the step of erecting the cantilevered scaffold on the erection basis includes:

步骤S31:在所述搭设基础上搭设立杆;Step S31: setting up poles on the basis of erection;

作为一种示例,搭设立杆前,在所述悬挑工字钢的悬挑端拉钢丝绳,并在所述悬挑工字钢的固定端底部焊接钢筋桩,以保证搭设基础的稳定性。As an example, before erecting the pole, a steel wire rope is pulled at the cantilevered end of the cantilevered I-beam, and a reinforcement pile is welded at the bottom of the fixed end of the cantilevered I-beam, so as to ensure the stability of the erected foundation.

作为一种示例,立杆为脚手架搭设的第一步,搭设完立杆后,脚手架的框架部分确定。As an example, the pole is the first step in erecting the scaffold. After erecting the pole, the frame part of the scaffold is determined.

在本实施例中,所述在所述搭设基础上搭设立杆的步骤,包括:In this embodiment, the step of erecting poles on the erection basis includes:

步骤S310:将所述立杆支承在所述悬挑工字钢正上方;Step S310: supporting the vertical rod directly above the cantilevered I-beam;

作为一种示例,悬挑工字钢的横向间距与脚手架的立杆的横向间距相同,立杆直接支承在悬挑钢平台工字钢正上方,保证脚手架架体的稳定性。As an example, the horizontal spacing of the cantilevered I-beams is the same as that of the vertical poles of the scaffold, and the vertical poles are directly supported directly above the I-beams of the cantilevered steel platform to ensure the stability of the scaffolding frame.

步骤S320:在所述悬挑工字钢上焊接U型钢筋,通过所述U型钢筋,将所述立杆与所述悬挑工字钢固定连接,以完成所述立杆的搭设。Step S320: welding U-shaped steel bars on the cantilevered I-beam, and fixedly connecting the vertical pole with the cantilevered I-shaped steel bar through the U-shaped steel bar, so as to complete the erection of the vertical pole.

作为一种示例,脚手架的立杆与悬挑工字钢有可靠的定位连接措施,以确保脚手架架体的稳定。As an example, there are reliable positioning and connection measures between the scaffold pole and the cantilevered I-beam to ensure the stability of the scaffold body.

具体地,在悬挑工字钢上焊接一根U型钢筋,该U型钢筋长至少150-200毫米、直径为至少25毫米。Specifically, a U-shaped steel bar is welded on the cantilevered I-beam, and the length of the U-shaped steel bar is at least 150-200 mm and the diameter is at least 25 mm.

作为一种示例,立杆的外径相同,立杆间距不大于1.3米,横距不大于1.8米,内立杆距下塔柱墙身不大于0.8米(便于后期模板安装及加固,此处空挡可利用纵向水平杆搭设跳板补全空挡)。As an example, the outer diameter of the poles is the same, the distance between the poles is not more than 1.3 meters, the horizontal distance is not more than 1.8 meters, and the distance between the inner poles and the wall of the lower tower column is not more than 0.8 meters (to facilitate the later formwork installation and reinforcement, here The neutral gear can utilize the vertical horizontal bar to set up a springboard to complement the neutral gear).

在本实施例中,所述悬挑工字钢正上方的立杆由多根长度不同的钢管拼接而成。In this embodiment, the vertical pole directly above the cantilevered I-beam is spliced by a plurality of steel pipes with different lengths.

在本实施例中,所述悬挑工字钢正上方的相邻立杆的多根钢管连接处在不同高度上,保证脚手架整体稳定性,不易坍塌。In this embodiment, the connections of multiple steel pipes of the adjacent vertical poles directly above the cantilevered I-beam are at different heights, so as to ensure the overall stability of the scaffold and prevent it from collapsing.

在本实施例中,所述相邻立杆的多根钢管连接处在不同高度上的高度差为至少50厘米。In this embodiment, the difference in height between the multiple steel pipes of the adjacent poles at different heights is at least 50 centimeters.

在本实施例中,所述立杆的多根钢管的顶层连接处采用搭设连接,非顶层连接处采用对接扣件连接。In this embodiment, the top-layer connections of the plurality of steel pipes of the vertical rod are connected by lapping, and the non-top-layer connections are connected by butt fasteners.

作为一种示例,所述立杆的多根钢管的顶层连接处顶层可采用搭设连接外,其余接头需采用对接扣件连接,以加强脚手架架体的稳固性。As an example, the top layer of the joints of the plurality of steel pipes of the vertical rod can be connected by bridging, and the rest of the joints should be connected by butt fasteners to enhance the stability of the scaffolding frame.

作为一种示例,两根钢管的搭接连接长度至少1米,且采用至少2个旋转扣件固定。As an example, the overlapping connection length of two steel pipes is at least 1 meter, and at least 2 rotating fasteners are used to fix it.

步骤S32:当所述立杆搭设完成后,搭设纵向水平杆,在所述纵向水平杆与所述立杆相交处用直角扣件固定;Step S32: After the erection of the vertical pole is completed, erect a vertical horizontal pole, and fix it with a right-angle fastener at the intersection of the vertical horizontal pole and the vertical pole;

作为一种示例,立杆及纵向水平杆套在钢筋上,并同时在立杆下部搭设横纵向扫地杆。As an example, the vertical pole and the vertical horizontal pole are sleeved on the steel bar, and the horizontal and vertical sweeping poles are set up at the lower part of the vertical pole at the same time.

作为一种示例,若所述立杆底部不在同一水平高度,则将高处的纵向扫地杆低处延伸两跨,并与低跨立杆固定。As an example, if the bottoms of the vertical poles are not at the same level, extend the high vertical sweeping pole for two spans and fix it with the low-span vertical pole.

作为一种示例,纵向水平杆应水平设置,钢管的长度至少3米;纵向水平杆步高均为每1.8米一道。As an example, the vertical horizontal rods should be arranged horizontally, and the length of the steel pipes should be at least 3 meters; the step height of the vertical horizontal rods should be every 1.8 meters.

作为一种示例,纵向水平杆与立杆相交处采用直角扣件与立杆固定。As an example, the intersection of the vertical horizontal bar and the vertical bar is fixed with the vertical bar by using a right-angle fastener.

作为一种示例,沿下塔柱外围搭设的脚手架应采用闭合形式,脚手架的同一步纵向水平杆需为闭合状态,即,不同方向的纵向水平杆需在拐角处采用直角扣连接。As an example, the scaffolding erected along the periphery of the lower tower column should adopt a closed form, and the longitudinal horizontal bars of the same step of the scaffold should be in a closed state, that is, the longitudinal horizontal bars in different directions should be connected with right-angle buckles at the corners.

步骤S33:当所述纵向水平杆搭设完成后,在所述纵向水平杆的下方搭设横向水平杆;Step S33: After the erection of the longitudinal horizontal rod is completed, a horizontal horizontal rod is erected below the longitudinal horizontal rod;

作为一种示例,横向水平杆设在纵向水平杆的下方,立杆与纵向水平杆相交处需设置一根横向水平杆,且不可任意拆除。As an example, the horizontal horizontal bar is arranged below the longitudinal horizontal bar, and a horizontal horizontal bar needs to be provided at the intersection of the vertical bar and the longitudinal horizontal bar, and it cannot be dismantled arbitrarily.

在本实施例中,所述在所述搭设基础上搭设立杆的步骤之后,所述方法还包括:In this embodiment, after the step of erecting poles on the erected foundation, the method further includes:

步骤A1:在所述立杆底部向上至少20厘米处安装纵向扫地杆和横向扫地杆。Step A1: installing a vertical sweeping pole and a horizontal sweeping pole at least 20 cm above the bottom of the pole.

作为一种示例,设置扫地杆能有效地增大模板支架的整体刚度,使立杆受力趋于均匀,也就是说使立杆有效地共同工作,提高承载力,同时可以避免因局部支架刚度偏小、变形过大进而影响整个支架稳定性的现象。As an example, setting up sweeping poles can effectively increase the overall rigidity of the formwork support, so that the force on the poles tends to be uniform, that is to say, the poles can effectively work together to increase the bearing capacity, and at the same time, it can avoid the partial stiffness of the support. The phenomenon of small size and excessive deformation will affect the stability of the whole bracket.

作为一种示例,安装纵向扫地杆和横向扫地杆应符合下列要求:As an example, the installation of longitudinal sweeping poles and transverse sweeping poles should meet the following requirements:

在所述立杆底部向上至少20厘米处安装;installed at least 20 cm above the bottom of the pole;

用直角扣件将纵向扫地杆和横向扫地杆与立杆固定;Fix the vertical sweeping rod and horizontal sweeping rod to the vertical rod with right-angle fasteners;

当立杆底不在同一水平高度时,必须将高处的纵向扫地杆低处延伸两跨,并与低跨立杆固定。When the bottom of the pole is not at the same level, the high longitudinal sweeping pole must be extended for two spans and fixed with the low span pole.

步骤S34:当所述横向水平杆搭设完成后,在所述立杆的外侧搭设剪刀撑,在剪刀撑与外侧立杆的交接处采用旋转扣件连接。Step S34: After the erection of the horizontal bar is completed, a scissor brace is set up on the outside of the vertical bar, and a rotating fastener is used to connect the scissor brace and the outer vertical bar at the junction.

作为一种示例,剪刀撑的布置应均匀,剪刀撑钢管应拉线搭设,与外立杆交接处均用旋转扣件与立杆连接。As an example, the arrangement of the scissors braces should be uniform, the steel pipes of the scissors braces should be erected by pull wires, and the joints with the outer poles should be connected with the poles by rotating fasteners.

作为一种示例,剪刀撑设置在脚手架立杆外侧,杆件接头采用搭接连接,其搭接长度为1000毫米,由至少3个旋转扣件固定,固定间距为800毫米。As an example, the scissor braces are arranged on the outside of the scaffold poles, and the joints of the poles are connected by lap joints with a lap length of 1000 mm, fixed by at least 3 rotating fasteners with a fixed spacing of 800 mm.

作为一种示例,每幅剪刀撑跨越立杆应为4-6根,与纵向水平杆呈45度-60度夹角。As an example, there should be 4-6 vertical bars for each scissors brace, forming an angle of 45°-60° with the longitudinal horizontal bar.

作为一种示例,每道剪刀撑宽度为至少4跨,且不小于6米,剪刀撑沿脚手架由底至顶连续设置,其间距不大于20厘米。As an example, the width of each scissor brace is at least 4 spans and not less than 6 meters, and the scissor brace is continuously arranged from bottom to top along the scaffold, and the distance between them is not more than 20 cm.

在本实施例中,在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢;在所述悬挑工字钢上铺设第一钢板,形成搭设基础;在所述搭设基础上搭设所述悬挑脚手架。可以理解,本申请不从地面开始搭设脚手架,而是从下塔柱的施工高度处开始搭设脚手架,通过在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢,在悬挑工字钢和钢板的支撑下,以此为基础搭设脚手架,节省了至少16米以下的脚手架的搭设材料成本以及人工成本。且,在本申请中,使用上述立杆、纵向水平杆、横向水平杆、剪刀撑的搭设方法,使脚手架的稳固性增强,提高了脚手架的安全性。In this embodiment, a cantilevered I-beam is installed on the pre-embedded parts pre-buried in the original construction process of the lower tower column; the first steel plate is laid on the cantilevered I-beam to form the erection foundation; Set up the cantilevered scaffolding on the basis. It can be understood that this application does not start to build scaffolding from the ground, but starts to build scaffolding from the construction height of the lower tower column. Under the support of cantilevered I-beams and steel plates, scaffolding is built on this basis, saving at least the cost of materials and labor costs for scaffolding below 16 meters. Moreover, in the present application, the erection method of the above-mentioned vertical poles, longitudinal horizontal poles, horizontal horizontal poles, and scissors bracing is used to enhance the stability of the scaffolding and improve the safety of the scaffolding.

进一步地,本申请实施例在悬挑脚手架施工工艺的上述实施例的基础上,还提供了第二实施例。参照图4,图4为本申请悬挑脚手架施工工艺第二实施例的流程示意图。Further, the embodiment of the present application provides a second embodiment on the basis of the above embodiments of the cantilevered scaffolding construction technology. Referring to FIG. 4 , FIG. 4 is a schematic flowchart of the second embodiment of the cantilevered scaffolding construction process of the present application.

在本实施例中,所述在所述搭设基础上搭设所述悬挑脚手架的步骤之后,所述方法还包括:In this embodiment, after the step of erecting the cantilevered scaffold on the erection foundation, the method further includes:

步骤S40:将所述下塔柱的原施工过程中预埋的第二钢板作为连墙件;Step S40: using the second steel plate pre-embedded in the original construction process of the lower tower column as a connecting wall piece;

作为一种示例,将所述下塔柱的原施工过程中预埋的第二钢板作为连墙件。As an example, the second steel plate pre-embedded in the original construction process of the lower tower column is used as a connecting wall piece.

作为一种示例,用L钢筋与水平钢管焊接固定,脚手架上部连墙件的自由高度不大于2层。As an example, L steel bars and horizontal steel pipes are welded and fixed, and the free height of the upper wall parts of the scaffold is not greater than 2 floors.

作为一种示例,脚手架的最上部因会承受较大风力,拉撑连杆应加密设置,连墙杆应设在立杆与横向水平杆的连接处。As an example, since the uppermost part of the scaffold will bear a large wind force, the brace connecting rods should be densely arranged, and the wall rods should be arranged at the connection between the vertical rod and the horizontal horizontal rod.

步骤S50:采用所述连墙件对所述悬挑脚手架进行加固;Step S50: Reinforcing the cantilevered scaffold with the wall connecting piece;

作为一种示例,采用所述连墙件对所述悬挑脚手架进行加固,以使其不易脱离所述下塔柱的墙体,提高安全性。As an example, the cantilevered scaffolding is reinforced by using the wall connecting piece so that it is not easy to separate from the wall of the lower tower column, thereby improving safety.

步骤S60:在所述悬挑式脚手架的第一步和操作层上铺设脚手板,在所述悬挑式脚手架的非操作层铺设水平安全网。Step S60: laying scaffold boards on the first step and the operation layer of the cantilevered scaffold, and laying a horizontal safety net on the non-operational layer of the cantilevered scaffold.

脚手板的铺设要求:Scaffold laying requirements:

作为一种示例,每道悬挑式脚手架第一步及操作层需铺设脚手板,非操作层需铺设水平安全网。As an example, the first step and the operation layer of each cantilevered scaffold need to be laid with scaffolding boards, and the non-operation level needs to be laid with horizontal safety nets.

作为一种示例,脚手架里排立杆与下塔柱墙体之间均应铺设木板:板宽为至少200毫米,里外立杆应满铺脚手板,无探头板。As an example, planks should be laid between the inner poles of the scaffold and the wall of the lower tower column: the board width should be at least 200 mm, and the inner and outer poles should be fully covered with scaffolding boards, without probe boards.

作为一种示例,脚手板必须垂直墙面横向铺设,不留空位,不能满铺处需采取有效的防护措施,例如,增设水平安全网等。As an example, scaffolding boards must be laid vertically and horizontally on the wall without leaving any gaps, and effective protective measures must be taken where they cannot be fully paved, such as adding horizontal safety nets, etc.

作为一种示例,脚手板需用18铅丝双股并联绑扎,不少于4点,需绑扎牢固,交接处需平整,铺设时需选用完好无损的脚手板,发现有破损的要及时更换。As an example, the scaffold board needs to be tied with 18 lead wires in parallel, not less than 4 points.

水平安全网的铺设要求:从脚手架底部开始全部采用密目式安全网全封闭,密目网需设在外排立杆的里侧。密目网的绑扎需采用尼龙绳环形绑扎或用短绳每孔一绑。Requirements for the laying of horizontal safety nets: from the bottom of the scaffolding, all are fully enclosed with dense-mesh safety nets, and the dense-mesh nets must be set on the inner side of the outer row of vertical poles. The binding of the dense mesh should be bound with a nylon rope loop or with a short rope for each hole.

最后,在脚手架搭建完毕,且安全措施做好后,还需搭建人行斜道,人行斜道的设计:人行斜道的宽度为至少1.2米,坡度为1:3(高:长)。Finally, after the scaffolding is completed and the safety measures are taken, it is necessary to build a pedestrian ramp. The design of the pedestrian ramp: the width of the pedestrian ramp is at least 1.2 meters, and the slope is 1:3 (height: length).

作为一种示例,斜道拐弯平台宽度为至少1.5米。As an example, the ramp width is at least 1.5 metres.

作为一种示例,斜道两侧及拐弯平台外围,设置至少1.2米的防护栏杆及高至少180毫米的挡脚板。As an example, on both sides of the ramp and on the periphery of the turning platform, protective railings of at least 1.2 meters and toe guards with a height of at least 180 mm are provided.

作为一种示例,人行斜道的脚手板上钉防滑木条,其厚度为至少30毫米,间距为至少250毫米。As an example, the scaffolding of a pedestrian ramp is nailed with non-slip wooden strips with a thickness of at least 30 mm and a spacing of at least 250 mm.

在本实施例中,在脚手架假设完毕后,采用上述连墙件、脚手板、安全网等,加固脚手架,提高稳固性,提升安全性。In this embodiment, after the assumption of the scaffolding is completed, the above-mentioned wall parts, scaffolding boards, safety nets, etc. are used to reinforce the scaffolding to improve stability and safety.

需要说明的是,在本文中,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者系统不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者系统所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括该要素的过程、方法、物品或者系统中还存在另外的相同要素。It should be noted that, as used herein, the term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article or system comprising a set of elements includes not only those elements, It also includes other elements not expressly listed, or elements inherent in the process, method, article, or system. Without further limitations, an element defined by the phrase "comprising a..." does not preclude the presence of additional identical elements in the process, method, article or system comprising that element.

上述本申请实施例序号仅仅为了描述,不代表实施例的优劣。The serial numbers of the above embodiments of the present application are for description only, and do not represent the advantages and disadvantages of the embodiments.

以上仅为本申请的优选实施例,并非因此限制本申请的专利范围,凡是利用本申请说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本申请的专利保护范围内。The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. All equivalent structures or equivalent process transformations made by using the description of the application and the accompanying drawings are directly or indirectly used in other related technical fields. , are all included in the patent protection scope of the present application in the same way.

Claims (10)

1.一种悬挑脚手架施工工艺,其特征在于,所述悬挑脚手架施工工艺包括以下步骤:1. a kind of cantilevered scaffolding construction technique is characterized in that, described cantilevered scaffold construction technique comprises the following steps: 在下塔柱的原施工过程中预埋的预埋件上安装悬挑工字钢;Install cantilevered I-beams on the pre-embedded parts pre-buried in the original construction process of the lower tower column; 在所述悬挑工字钢上铺设第一钢板,形成搭设基础;Laying the first steel plate on the cantilevered I-beam to form the erection foundation; 在所述搭设基础上搭设所述悬挑脚手架。The cantilevered scaffold is erected on the erection basis. 2.如权利要求1所述的悬挑脚手架施工工艺,其特征在于,所述在所述搭设基础上搭设所述悬挑脚手架的步骤,包括:2. The cantilevered scaffold construction process as claimed in claim 1, wherein the step of erecting the cantilevered scaffold on the basis of the erection includes: 在所述搭设基础上搭设立杆;erecting poles on said erecting foundation; 当所述立杆搭设完成后,搭设纵向水平杆,在所述纵向水平杆与所述立杆相交处用直角扣件固定;After the erection of the vertical rod is completed, a vertical horizontal rod is erected, and the intersection of the vertical horizontal rod and the vertical rod is fixed with a right-angle fastener; 当所述纵向水平杆搭设完成后,在所述纵向水平杆的下方搭设横向水平杆;After the erection of the longitudinal horizontal bar is completed, a horizontal horizontal bar is erected below the longitudinal horizontal bar; 当所述横向水平杆搭设完成后,在所述立杆的外侧搭设剪刀撑,在剪刀撑与外侧立杆的交接处采用旋转扣件连接。After the erection of the horizontal bar is completed, set up a scissors brace on the outside of the vertical bar, and use a rotary fastener to connect the scissors brace and the outer vertical bar at the junction. 3.如权利要求2所述的悬挑脚手架施工工艺,其特征在于,所述在所述搭设基础上搭设立杆的步骤,包括:3. The construction technique of cantilevered scaffolding as claimed in claim 2, characterized in that, the step of erecting poles on the basis of the erection includes: 将所述立杆支承在所述悬挑工字钢正上方;Supporting the vertical rod directly above the cantilevered I-beam; 在所述悬挑工字钢上焊接U型钢筋,通过所述U型钢筋,将所述立杆与所述悬挑工字钢固定连接,以完成所述立杆的搭设。U-shaped steel bars are welded on the cantilevered I-beam, and the vertical bar is fixedly connected with the cantilevered I-shaped steel bar through the U-shaped steel bar to complete the erection of the vertical bar. 4.如权利要求3所述的悬挑脚手架施工工艺,其特征在于,所述悬挑工字钢正上方的立杆由多根长度不同的钢管拼接而成。4. The construction technique of cantilevered scaffolding according to claim 3, characterized in that, the vertical bar just above the cantilevered I-beam is spliced by a plurality of steel pipes with different lengths. 5.如权利要求4所述的悬挑脚手架施工工艺,其特征在于,所述悬挑工字钢正上方的相邻立杆的多根钢管连接处在不同高度上。5. The construction technique of cantilevered scaffolding according to claim 4, characterized in that, the connections of multiple steel pipes of adjacent vertical poles directly above the cantilevered I-beam are at different heights. 6.如权利要求5所述的悬挑脚手架施工工艺,其特征在于,所述相邻立杆的多根钢管连接处在不同高度上的高度差为至少50厘米。6 . The construction technique for cantilevered scaffolding according to claim 5 , wherein the difference in height between the multiple steel pipe connections of the adjacent vertical poles is at least 50 centimeters. 7.如权利要求4所述的悬挑脚手架施工工艺,其特征在于,所述立杆的多根钢管的顶层连接处采用搭设连接,非顶层连接处采用对接扣件连接。7. The construction technique of cantilevered scaffolding according to claim 4, characterized in that, the top-layer connections of the plurality of steel pipes of the vertical rods are connected by lapping, and the non-top-layer connections are connected by butt fasteners. 8.如权利要求1所述的悬挑脚手架施工工艺,其特征在于,所述悬挑工字钢在所述下塔柱的大小里程侧对称悬挑。8. The construction technique of cantilevered scaffolding according to claim 1, characterized in that, the cantilevered I-beam is cantilevered symmetrically on the large and small mileage sides of the lower tower column. 9.如权利要求3所述的悬挑脚手架施工工艺,其特征在于,所述在所述搭设基础上搭设立杆的步骤之后,所述方法还包括:9. The cantilevered scaffold construction process as claimed in claim 3, characterized in that, after the step of erecting poles on the basis of the erection, the method further comprises: 在所述立杆底部向上至少20厘米处安装纵向扫地杆和横向扫地杆。A longitudinal sweeping rod and a horizontal sweeping rod are installed at least 20 centimeters upwards from the bottom of the pole. 10.如权利要求3所述的悬挑脚手架施工工艺,其特征在于,所述在所述搭设基础上搭设所述悬挑脚手架的步骤之后,所述方法还包括:10. The construction technique of cantilevered scaffolding as claimed in claim 3, characterized in that, after the step of erecting said cantilevered scaffolding on said erecting basis, said method further comprises: 将所述下塔柱的原施工过程中预埋的第二钢板作为连墙件;The second steel plate pre-embedded in the original construction process of the lower tower column is used as a connecting wall piece; 采用所述连墙件对所述悬挑脚手架进行加固;The cantilevered scaffold is reinforced by using the wall connecting piece; 在所述悬挑式脚手架的第一步和操作层上铺设脚手板,在所述悬挑式脚手架的非操作层铺设水平安全网。Lay the scaffold board on the first step and the operation layer of the cantilevered scaffold, and lay a horizontal safety net on the non-operational layer of the cantilevered scaffold.
CN202211600247.8A 2022-12-12 2022-12-12 Construction process of overhanging scaffold Pending CN115822233A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211600247.8A CN115822233A (en) 2022-12-12 2022-12-12 Construction process of overhanging scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211600247.8A CN115822233A (en) 2022-12-12 2022-12-12 Construction process of overhanging scaffold

Publications (1)

Publication Number Publication Date
CN115822233A true CN115822233A (en) 2023-03-21

Family

ID=85547027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211600247.8A Pending CN115822233A (en) 2022-12-12 2022-12-12 Construction process of overhanging scaffold

Country Status (1)

Country Link
CN (1) CN115822233A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1749417A1 (en) * 1990-10-19 1992-07-23 Запорожский индустриальный институт Device for jointing reinforcing rods
CN203113226U (en) * 2012-12-31 2013-08-07 中建三局建设工程股份有限公司 Formwork support system with towering asymmetric concrete cantilever structure
CN203961258U (en) * 2014-05-23 2014-11-26 中天建设集团有限公司天津分公司 Builder's jack foot guard structure
CN109372260A (en) * 2018-11-16 2019-02-22 中国二十二冶集团有限公司 Chimney reinforces scaffold connection construction method
CN110670867A (en) * 2019-10-16 2020-01-10 陕西建工第三建设集团有限公司 Construction method of scaffold for improving outer vertical surface of existing building
CN115162697A (en) * 2022-06-23 2022-10-11 中建四局第三建设有限公司 I-shaped steel cantilever platform for special-shaped column construction and construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1749417A1 (en) * 1990-10-19 1992-07-23 Запорожский индустриальный институт Device for jointing reinforcing rods
CN203113226U (en) * 2012-12-31 2013-08-07 中建三局建设工程股份有限公司 Formwork support system with towering asymmetric concrete cantilever structure
CN203961258U (en) * 2014-05-23 2014-11-26 中天建设集团有限公司天津分公司 Builder's jack foot guard structure
CN109372260A (en) * 2018-11-16 2019-02-22 中国二十二冶集团有限公司 Chimney reinforces scaffold connection construction method
CN110670867A (en) * 2019-10-16 2020-01-10 陕西建工第三建设集团有限公司 Construction method of scaffold for improving outer vertical surface of existing building
CN115162697A (en) * 2022-06-23 2022-10-11 中建四局第三建设有限公司 I-shaped steel cantilever platform for special-shaped column construction and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄丽芬: "土木工程施工技术", 31 January 2022, 武汉:武汉理工大学出版社, pages: 120 - 121 *

Similar Documents

Publication Publication Date Title
CN105926448B (en) A kind of construction method of the Cable stayed Bridge Main Tower in the double rope faces of the only tower of curve
CN111593673A (en) Steel truss arch bridge and construction method
CN108265885B (en) Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column
CN107090975A (en) Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss
CN111779248B (en) High formwork system and construction method thereof
CN111424948A (en) Construction method and construction platform for cantilever structure layer of high-rise building
CN110409624A (en) A large-scale equipment installation and main structure reverse calculation and construction method
CN110593110A (en) Box girder cast-in-place support for curves and vertical and horizontal slopes and its construction method
CN212507296U (en) High formwork system
CN114319809A (en) Construction Method of Disk Buckle Scaffolding System for Superelevation Working Platform
CN116357069A (en) Construction method of hyperboloid roof structure
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN103061503B (en) A ring beam formwork
CN112031495A (en) Prefabricated cabin transformer substation assembled steel structure foundation and construction splicing method thereof
CN112412002B (en) A leaping formwork support system
CN212897482U (en) Construction platform for high-rise building overhanging structural layer
CN116696055B (en) Construction decoration method for cantilever structure of flat roof framework layer
CN116657875B (en) Cantilever steel structure construction platform with formwork system and construction method
CN115822233A (en) Construction process of overhanging scaffold
CN109024685B (en) Large-volume concrete bottom plate steel bar supporting system and construction method thereof
CN221740927U (en) A high pier body steel bar binding construction platform
CN118187078A (en) Supporting system for deep foundation pit reverse construction method working well main body
CN111593874A (en) Supporting system for overweight overhung suspended member of super high-rise residential conversion layer and construction method
CN116856544A (en) A circumferential inclined truss structure and its installation method
CN212270687U (en) Steel pipe support temporary pier for inclined main and auxiliary arch cross section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination