CN115749793A - A construction method for the connecting passage of a cascading tunnel - Google Patents

A construction method for the connecting passage of a cascading tunnel Download PDF

Info

Publication number
CN115749793A
CN115749793A CN202211199439.2A CN202211199439A CN115749793A CN 115749793 A CN115749793 A CN 115749793A CN 202211199439 A CN202211199439 A CN 202211199439A CN 115749793 A CN115749793 A CN 115749793A
Authority
CN
China
Prior art keywords
tunnel
communication channel
lining
channel
cascading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202211199439.2A
Other languages
Chinese (zh)
Inventor
丁万涛
郭文静
王庆礼
李振宇
张存
刘宇婷
李海洋
王忠岭
张萌萌
黄兴行
文毅然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Metro Group Co ltd
Shandong University
China Railway Liuyuan Group Co Ltd
Original Assignee
Harbin Metro Group Co ltd
Shandong University
China Railway Liuyuan Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Metro Group Co ltd, Shandong University, China Railway Liuyuan Group Co Ltd filed Critical Harbin Metro Group Co ltd
Priority to CN202211199439.2A priority Critical patent/CN115749793A/en
Publication of CN115749793A publication Critical patent/CN115749793A/en
Withdrawn legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种叠落隧道联络通道施工方法,属于地下工程施工技术领域,包括以下步骤:盾构推进至拟建上/下层联络通道时,对应拼装衬砌环管片;采用地面垂直冷冻+洞内冷冻法加固下层联络通道周围土体;下层隧道开挖下层联络通道,并施工初支结构和二衬结构;冷冻上层联络通道周围土体,上层隧道开挖上层联络通道,并施工初支结构和二衬结构;施工内部结构,主体结构达到强度后解除冷冻。该方法可解决叠落型联络施工期扰动大、开挖面不稳的难题,有利于保障工程安全。

Figure 202211199439

The invention discloses a method for constructing a communication channel of a stacked tunnel, which belongs to the technical field of underground engineering construction and comprises the following steps: when a shield tunnel is advanced to the upper/lower communication channel to be built, correspondingly assembling lining ring segments; adopting vertical freezing on the ground + Reinforce the soil around the lower communication channel by the freezing method in the cave; excavate the lower communication channel in the lower tunnel, and construct the primary support structure and the secondary lining structure; freeze the soil around the upper communication channel, excavate the upper communication channel in the upper tunnel, and construct the primary support Structure and secondary lining structure; construct the internal structure, and thaw after the main structure reaches strength. This method can solve the problems of large disturbance and unstable excavation surface during the construction period of the cascading connection, which is beneficial to ensure the safety of the project.

Figure 202211199439

Description

一种叠落隧道联络通道施工方法A construction method for the connecting passage of a cascading tunnel

技术领域technical field

本发明属于地下工程施工技术领域,具体涉及一种叠落隧道联络通道施工方法。The invention belongs to the technical field of underground engineering construction, and in particular relates to a construction method for a connecting channel of a cascading tunnel.

背景技术Background technique

这里的陈述仅提供与本发明相关的背景技术,而不必然地构成现有技术。The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.

随着经济的发展和对交通基础设施需求的增大,地铁隧道建设迅猛发展,地下交通路网越来越庞大,地铁隧道建设不可避免地会出现叠落区间,而联络通道作为地铁运营期间应急安全保障体系(安全紧急疏散、排水、防火等)的重要组成部分,是地铁建设过程中的一个重大风险源。尤其对于正叠落隧道,其联络通道整体体积较大,开挖周期长,上、下层横通道距离较近,上、下层通道施工对土体的扰动大且相互影响,且当联络通道兼泵房底部位于黏土或中砂土层(含有承压水)时,施工过程中极易发生拱顶塌陷、掌子面失稳等重大工程事故。With the development of the economy and the increase in the demand for transportation infrastructure, the construction of subway tunnels is developing rapidly, and the underground traffic network is becoming larger and larger. The construction of subway tunnels will inevitably have overlapping sections, and the communication channel is used as an emergency during the operation of the subway. An important part of the safety guarantee system (safety and emergency evacuation, drainage, fire prevention, etc.), is a major risk source in the process of subway construction. Especially for stacking tunnels, the overall volume of the connecting passage is large, the excavation period is long, the distance between the upper and lower horizontal passages is relatively close, the disturbance of the upper and lower passages to the soil is large and they affect each other, and when the connecting passage and the pump When the bottom of the building is located in clay or medium sandy soil (containing confined water), major engineering accidents such as vault collapse and face instability are prone to occur during construction.

发明内容Contents of the invention

针对现有技术存在的不足,本发明的目的是提供一种叠落隧道联络通道施工方法,该方法可解决叠落型联络施工期扰动大、开挖面不稳的难题,有利于保障工程安全。Aiming at the deficiencies in the prior art, the purpose of the present invention is to provide a construction method for the cascading tunnel connection channel, which can solve the problems of large disturbance and unstable excavation surface during the construction period of the cascading tunnel, and is conducive to ensuring the safety of the project .

为了实现上述目的,本发明是通过如下的技术方案来实现:In order to achieve the above object, the present invention is achieved through the following technical solutions:

第一方面,本发明提供了一种叠落隧道联络通道施工方法,包括以下步骤:In a first aspect, the present invention provides a construction method for a cascading tunnel communication channel, comprising the following steps:

盾构推进至拟建上/下层联络通道时,对应拼装衬砌环管片;When the shield is advanced to the proposed upper/lower layer communication channel, the lining ring segment should be assembled correspondingly;

采用地面垂直冷冻+洞内冷冻法加固下层联络通道周围土体;Use ground vertical freezing + in-hole freezing method to strengthen the soil around the lower communication channel;

下层隧道开挖下层联络通道,并施工初支结构和二衬结构;Excavate the lower connecting channel for the lower tunnel, and construct the primary support structure and the secondary lining structure;

冷冻上层联络通道周围土体,上层隧道开挖上层联络通道,并施工初支结构和二衬结构;Freeze the soil around the upper communication passage, excavate the upper communication passage for the upper tunnel, and construct the primary support structure and the secondary lining structure;

施工内部结构,主体结构达到强度后解除冷冻。The internal structure is constructed, and the main structure reaches its strength and then thawed out.

作为进一步的技术方案,下层联络通道周围土体加固时,从下线注浆口及地面打设循环管路冷冻加固下层联络通道周围土体,洞内加固借助预留孔洞进行冷冻。As a further technical solution, when the soil around the lower communication channel is reinforced, a circulating pipeline is drilled from the downline grouting port and the ground to freeze and reinforce the soil around the lower communication channel, and the reinforcement in the hole is frozen by means of reserved holes.

作为进一步的技术方案,加固时,在隧道冻结帷幕封闭区域内均布多个卸压孔,在卸压孔上安装压力表,实时监测冻结帷幕内的压力变化情况,判断冻结帷幕的形成,释放冻胀压力。As a further technical solution, during reinforcement, multiple pressure relief holes are evenly distributed in the closed area of the tunnel freezing curtain, and pressure gauges are installed on the pressure relief holes to monitor the pressure changes in the freezing curtain in real time, judge the formation of the freezing curtain, and release frost heave pressure.

作为进一步的技术方案,冷冻加固前,在上下层隧道衬砌环不开口部位安装临时支撑、支承板。As a further technical solution, before freezing and strengthening, install temporary supports and bearing plates on the openings of the upper and lower tunnel lining rings.

作为进一步的技术方案,下层隧道的施工过程为:As a further technical solution, the construction process of the lower tunnel is as follows:

加固土体达到开挖要求后,拆除下层隧道衬砌环管片中开口部分,从下层隧道内采用台阶法开挖下层联络通道上部洞室,施工初支结构,开挖下部洞室,施做初支结构,初支封闭后,由下向上施工下层联络通道防水层、二衬结构,预留与竖直段二衬连接的钢筋接头;After the reinforced soil meets the excavation requirements, the opening part of the lower tunnel lining ring segment is removed, and the upper cavern of the lower connecting passage is excavated from the lower tunnel by the step method, the initial support structure is constructed, the lower cavern is excavated, and the initial tunnel is constructed. For the support structure, after the initial support is closed, the waterproof layer and the second lining structure of the lower communication channel shall be constructed from bottom to top, and the steel bar joints connected with the second lining of the vertical section shall be reserved;

在下层联络通道二衬达到设计强度后,向下破除泵房处初支,开挖泵房,泵房初支封闭后,由下向上施工泵房防水、二衬,下层联络通道竖直段防水、侧缝,预留与上部侧墙相接的钢筋接驳器。After the second lining of the lower communication channel reaches the design strength, remove the initial support at the pump room downwards and excavate the pump room. After the initial support of the pump room is closed, waterproof the pump room and the second lining from bottom to top, and waterproof the vertical section of the lower communication channel. , Side seam, reserve a steel bar connector connected to the upper side wall.

作为进一步的技术方案,泵房及下层联络通道竖直段二衬达到强度后,减少部分冷冻管,使竖直段顶部处于冷冻体中,同时冷冻上层联络通道周围土体。As a further technical solution, after the pump house and the second lining of the vertical section of the lower communication channel reach strength, part of the freezing pipes are reduced so that the top of the vertical section is in the frozen body, and the soil around the upper communication channel is frozen at the same time.

作为进一步的技术方案,拼装完衬砌环管片后,从地面打设新风井钢管至竖直段通道顶板底标高位置。As a further technical solution, after the lining segment is assembled, the fresh air shaft steel pipe is drilled from the ground to the elevation of the roof bottom of the vertical passageway.

作为进一步的技术方案,上层隧道的施工过程为:As a further technical solution, the construction process of the upper tunnel is as follows:

从上层隧道内采用台阶法开挖上层联络通道上部洞室,施工初支结构,开挖下部洞室,施做初支,初支封闭后,由下向上施工上层联络通道防水、二衬结构,预留与竖直段二衬连接的钢筋接头;上层联络通道二衬达到设计强度后,向下破除初支,开挖剩余竖直段通道,竖直段通道初支与两端连接封闭后,由下向上施工竖直段通道防水、侧墙、顶板,顶板与新风井钢管连接,顶板钢筋与新风井钢管焊接,连接外混凝土浇筑密实,侧墙底部预留钢筋接驳器。Excavate the upper cavern of the upper communication passage from the upper tunnel by step method, construct the primary support structure, excavate the lower chamber, and make the initial support. After the initial support is closed, construct the waterproof and secondary lining structure of the upper communication passage from bottom to top. Reserve the steel bar joints connected with the second lining of the vertical section; after the second lining of the upper communication channel reaches the design strength, remove the initial support downwards, excavate the remaining vertical section channels, and after the initial support of the vertical section channel is connected to both ends and closed, Waterproofing, side walls, and roof of the vertical section shall be constructed from bottom to top. The roof shall be connected to the steel pipe of the fresh air shaft, the steel bars of the roof shall be welded to the steel pipe of the fresh air shaft, the concrete shall be poured densely outside the connection, and a steel bar connector shall be reserved at the bottom of the side wall.

作为进一步的技术方案,完成后破除坚直段底板格栅,向下开挖坚直段最后一部分,施做初期支护,全部挖通后,由下至上施工防水及侧墙,使上层联络通道、下层联络通道、竖直段通道的二衬连接成整体。As a further technical solution, after the completion, the floor grille of the straight section will be removed, and the last part of the straight section will be excavated downwards for initial support. The second liner of the lower layer communication passage and the vertical section passage are connected as a whole.

作为进一步的技术方案,当解除冷冻引起融沉时,利用预埋注浆管及管片注浆孔进行融沉注浆填充,采用单液浆注浆,采用由下而上、少量多次的注浆方法,通道拱顶变形稳定后,停止融沉注浆,注浆结束后,用双液浆进行封孔。As a further technical solution, when thawing is caused by thawing, use pre-embedded grouting pipes and segment grouting holes for thawing grouting filling, use single-liquid grouting, and use bottom-up, small and multiple grouting In the grouting method, after the deformation of the channel vault is stable, the melt-settling grouting is stopped, and after the grouting is completed, the holes are sealed with double-liquid grout.

上述本发明的有益效果如下:The above-mentioned beneficial effects of the present invention are as follows:

本发明的施工方法,采用地面垂直冷冻、洞内冷冻加固上下层联络通道的周围土体,安全性好,可有效的隔绝地下水;适应面广,适用于任何含一定水量的松散岩土层,在复杂水文地质如软土、含水不稳定土层、流砂、高水压及高地压地层条件下冻结技术有效、可行;灵活性好,可以人为地控制冻结体的形状和扩展范围,必要时可以绕过地下障碍物进行冻结;可控性较好,冻结加固土体均匀、完整;经济上较合理。The construction method of the present invention adopts vertical freezing on the ground and freezing in the cave to strengthen the surrounding soil of the upper and lower communication passages, which has good safety and can effectively isolate groundwater; it has a wide range of applications and is suitable for any loose rock and soil layer with a certain amount of water. The freezing technology is effective and feasible under the conditions of complex hydrogeology such as soft soil, water-containing unstable soil layer, quicksand, high water pressure and high ground pressure formation; it has good flexibility and can artificially control the shape and expansion range of the frozen body, and can be used when necessary Freezing bypasses underground obstacles; the controllability is good, and the frozen and reinforced soil is uniform and complete; it is economically reasonable.

本发明的施工方法,由于叠落隧道联络通道体积大,施工工期长,采用上、下层联络通道分段冷冻法,可有效减小上、下层通道施工对土体的扰动且降低相互干扰的风险。The construction method of the present invention, due to the large volume of the connecting channel of the stacked tunnel and the long construction period, adopts the segmental freezing method of the upper and lower layer connecting channels, which can effectively reduce the disturbance of the upper and lower layer channel construction to the soil and reduce the risk of mutual interference .

本发明的施工方法,利用台阶法开挖横道,可减少对围岩的扰动,显著降低叠落区间联络通道施工过程中拱顶塌陷、掌子面失稳的风险。The construction method of the present invention uses the step method to excavate the transverse passage, which can reduce the disturbance to the surrounding rock, and significantly reduce the risk of vault collapse and tunnel face instability during the construction process of the connecting passage in the cascading section.

本发明的施工方法,形成的叠落隧道联络通道结构,既能保证联络通道满足灾难工况时人员的紧急疏散要求,又能保证泵房设置于正线区间轨道的最低点并将道床积水正常排流至泵房内部。According to the construction method of the present invention, the structure of the cascading tunnel communication channel formed can not only ensure that the communication channel meets the emergency evacuation requirements of personnel in disaster conditions, but also ensure that the pump room is set at the lowest point of the track in the main line section and the ballast bed will accumulate water. Drain normally to the interior of the pump room.

附图说明Description of drawings

构成本发明的一部分的说明书附图用来提供对本发明的进一步理解,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定。The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention, and the schematic embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations to the present invention.

图1是本发明叠落隧道联络通道施工方法的流程图;Fig. 1 is the flow chart of the construction method of the cascading tunnel connecting passage of the present invention;

图2是本发明步骤1中衬砌环管片位置关系示意图;Fig. 2 is a schematic diagram of the positional relationship of lining ring segments in step 1 of the present invention;

图3是本发明步骤2中地面、新风井钢管、通道竖直段顶板位置关系示意图;Fig. 3 is a schematic diagram of the positional relationship between the ground, the fresh air well steel pipe, and the vertical section roof of the channel in step 2 of the present invention;

图4是本发明步骤3中下层、上层隧道开口环中临时支撑及支承板的施工示意图;Fig. 4 is the construction schematic diagram of the temporary support and support plate in the lower and upper tunnel opening rings in step 3 of the present invention;

图5是本发明步骤4中下层联络通道周围土体冷冻加固的施工示意图;Fig. 5 is the construction schematic diagram of the frozen reinforcement of the soil around the lower communication channel in step 4 of the present invention;

图6-1是本发明步骤5中从下层隧道内采用台阶法开挖下层联络通道的施工示意图;Fig. 6-1 is the construction schematic diagram of adopting the step method to excavate the lower layer communication channel from the lower layer tunnel in step 5 of the present invention;

图6-2是本发明步骤5及步骤8中横通道的施工示意图;Fig. 6-2 is the construction schematic diagram of cross channel in step 5 and step 8 of the present invention;

图7是本发明步骤6中泵房及下层通道竖直段的施工示意图;Fig. 7 is the construction schematic diagram of pump house and the vertical section of lower passage in step 6 of the present invention;

图8是本发明步骤7中上层联络通道周围土体冷冻加固的施工示意图;Fig. 8 is the construction schematic diagram of frozen reinforcement of the soil around the upper layer communication channel in step 7 of the present invention;

图9是本发明步骤8中从上层隧道内采用台阶法开挖上层联络通道的施工示意图;Fig. 9 is a construction schematic diagram of excavating an upper-level connecting channel from the upper-level tunnel in step 8 of the present invention by adopting the step method;

图10是本发明步骤9中剩余竖直段通道的施工示意图;Fig. 10 is the construction schematic diagram of remaining vertical section channel in step 9 of the present invention;

图11是本发明步骤中10中加压送风机房、楼梯等内部结构的施工示意图;Fig. 11 is the construction schematic diagram of internal structures such as pressurized blower room, stair among 10 in the step of the present invention;

图中:为显示各部位位置而夸大了互相间间距或尺寸,示意图仅作示意使用;In the figure: The distance or size between each part is exaggerated to show the position of each part, and the schematic diagram is for illustration only;

其中,1-衬砌环管片;2-新风井钢管;3-临时支撑;4-支承板;5-下层联络通道周围土体;6-下层隧道;7-下层联络通道;8-上部洞室;9-初支结构;10-下部洞室;11-初支;12-防水层;13-二衬结构;14-泵房;15-上层联络通道周围土体;16-上层隧道;17-上层联络通道;18-竖直段通道;19-加压送风机房;20-盖板;21-楼梯。Among them, 1-lining ring segment; 2-new air shaft steel pipe; 3-temporary support; 4-support plate; 5-soil around the lower communication channel; 6-lower tunnel; 7-lower communication channel; 8-upper cavern ;9-primary support structure; 10-lower cavern; 11-primary support; 12-waterproof layer; 13-second lining structure; 14-pump room; Upper communication channel; 18-vertical section channel; 19-pressurized blower room; 20-cover plate; 21-stairs.

具体实施方式Detailed ways

应该指出,以下详细说明都是例示性的,旨在对本发明提供进一步的说明。除非另有指明,本发明使用的所有技术和科学术语具有与本发明所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is exemplary and intended to provide further explanation of the present invention. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

本发明的一种典型的实施方式中,如图1所示,提出一种叠落隧道联络通道施工方法,包括以下步骤:In a typical implementation of the present invention, as shown in Figure 1, a construction method for a cascading tunnel connecting passage is proposed, comprising the following steps:

步骤1:盾构推进至拟建上/下层联络通道时,一一对应拼装衬砌环管片1,衬砌环管片1侧部带有开口,可拆卸,由该衬砌环管片处挖上/下层联络通道;Step 1: When the shield is advanced to the proposed upper/lower communication channel, the lining segment 1 is assembled one by one. The side of the lining segment 1 has an opening, which can be disassembled, and is dug from the lining segment. The lower communication channel;

步骤2:从地面打设新风井钢管2至竖直段通道的顶板底标高位置,待后期与竖直段通道的顶板连接;新风井钢管在联络通道上方,距隧道有一定距离;Step 2: Drill fresh air shaft steel pipe 2 from the ground to the elevation of the roof bottom of the vertical passage, and connect it to the roof of the vertical passage in the later stage; the fresh air shaft steel pipe is above the connecting passage and has a certain distance from the tunnel;

步骤3:在下层、上层隧道衬砌环中不开口部位安装临时支撑3、支承板4等,以控制施工时衬砌环变形;Step 3: Install temporary support 3, support plate 4, etc. in the openings of the lower and upper tunnel lining rings to control the deformation of the lining ring during construction;

步骤4:采用地面垂直冷冻+洞内冷冻法加固,从下线注浆口及地面打设循环管路冷冻加固下层联络通道周围土体5,在左线、右线冻结帷幕封闭区域内均布多个卸压孔,在卸压孔上安装压力表,实时监测冻结帷幕内的压力变化情况,通过每日观测,及时判断冻结帷幕的形成,并可直接释放冻胀压力;Step 4: Use ground vertical freezing + in-hole freezing method for reinforcement, set up circulating pipelines from the downline grouting port and the ground to freeze and reinforce the soil 5 around the lower communication channel, and distribute them evenly in the closed area of the left and right freezing curtains Multiple pressure relief holes, install pressure gauges on the pressure relief holes, monitor the pressure changes in the freezing curtain in real time, judge the formation of the freezing curtain in time through daily observation, and directly release the frost heave pressure;

步骤5:加固土体达到开挖要求后,拆除下层隧道衬砌环管片的开口部分,从下层隧道6内采用台阶法开挖下层联络通道7上部洞室8,施工初支结构9,开挖下部洞室10,施做初支结构11,初支封闭后,由下向上施工下层联络通道防水层12、二衬结构13,预留与竖直段通道18二衬连接的钢筋接头;Step 5: After the reinforced soil meets the excavation requirements, remove the opening part of the lower tunnel lining ring segment, excavate the lower connecting channel 7 and the upper chamber 8 from the lower tunnel 6 using the step method, construct the initial support structure 9, and excavate In the lower cavern 10, the initial support structure 11 is constructed. After the initial support is closed, the waterproof layer 12 and the second lining structure 13 of the lower communication channel are constructed from bottom to top, and the steel bar joints connected with the second lining of the vertical channel 18 are reserved;

步骤6,下层联络通道二衬达到设计强度后,向下破除泵房14处初支,开挖泵房,泵房初支封闭后,由下向上施工泵房防水、二衬,下层联络通道竖直段防水、侧缝,预留与上部侧墙相接的钢筋接驳器;Step 6: After the second lining of the lower communication channel reaches the design strength, remove the 14 primary supports of the pump room downwards, excavate the pump room, and after the initial support of the pump room is closed, construct the waterproofing and second lining of the pump room from bottom to top, and the lower communication channel vertically Straight section waterproofing, side seam, rebar connector connected with the upper side wall is reserved;

步骤7,泵房及下层联络通道竖直段二衬达到强度后,减少部分冷冻管,但竖直段仅靠初支封闭,仍需确保竖直段通道顶部处于冷冻体中,同时冷冻上层联络通道周围土体15,采用与下层联络通道周围土体冷冻相同的方法进行;Step 7: After the second lining of the vertical section of the pump room and the lower communication channel has reached its strength, reduce part of the frozen pipes, but the vertical section is only closed by the primary branch, and it is still necessary to ensure that the top of the vertical section is in the frozen body, and at the same time freeze the upper communication The soil body 15 around the channel adopts the same method as the freezing of the soil around the lower communication channel;

步骤8,加固土体达到开挖要求后,从上层隧道16内采用台阶法开挖上层联络通道17上部洞室,施工初支结构,开挖下部洞室,施做初支,初支封闭后,由下向上施工上层联络通道防水、二衬结构,预留与竖直段通道18二衬连接的钢筋接头;Step 8: After the reinforced soil meets the excavation requirements, excavate the upper cavern of the upper communication channel 17 from the upper tunnel 16 using the step method, construct the initial support structure, excavate the lower cavern, apply the initial support, and after the initial support is closed , from the bottom up to construct the waterproof and secondary lining structure of the upper communication channel, and reserve the steel bar joints connected with the secondary lining of the channel 18 in the vertical section;

步骤9,上层联络通道二衬达到设计强度后,方可向下破除初支,开挖剩余竖直段通道18,竖直段通道初支与两端连接封闭后,由下向上施工竖直段通道防水、侧墙、顶板,顶板与新风井钢管连接,顶板钢筋与新风井钢管焊接,连接外混凝土浇筑密实,侧墙底部预留钢筋接驳器。完成后破除坚直段底板格栅,向下开挖坚直段最后一部分,施做初期支护,全部挖通后,由下至上施工防水及侧墙,使上层联络通道、下层联络通道、竖直段通道的二衬连接成整体;Step 9: After the second lining of the upper communication channel reaches the design strength, the initial support can be removed downwards, and the remaining vertical section channel 18 is excavated. After the initial support of the vertical section channel is connected and closed with both ends, the vertical section is constructed from bottom to top Waterproofing of the channel, side walls, roof, the roof is connected to the steel pipe of the new air shaft, the steel bars of the roof are welded to the steel pipe of the new air shaft, the concrete outside the connection is poured densely, and the steel bar connector is reserved at the bottom of the side wall. After the completion, remove the floor grille of the straight section, excavate the last part of the straight section downwards, and apply initial support. The two linings of the straight channel are connected as a whole;

步骤10,施工加压送风机房19、盖板20、楼梯21、扶手等内部结构,主体结构达到强度后即可逐渐解除冷冻。Step 10, construct internal structures such as pressurized blower room 19, cover plate 20, stairs 21, handrails, etc., and gradually defreeze after the main structure reaches strength.

临时支撑3、支承板4在施工完成后需要拆除,须以隧道监控测量的结果为指导,即在隧道及联络通道整体结构受力状态趋于稳定后,方可拆除。Temporary support 3 and support plate 4 need to be removed after the construction is completed, and must be guided by the results of tunnel monitoring and measurement, that is, they can be removed only after the stress state of the overall structure of the tunnel and connecting passage tends to be stable.

其中,步骤3种衬砌环为左、右线各6环。Wherein, step 3 kinds of lining rings are 6 rings respectively for the left line and the right line.

其中,步骤4中,洞内加固借助预留孔洞进行冷冻,能够方便加固夹层土体,保证加固范围与安全,冻土帷幕有效冻结厚度初支外侧部位小于3m,开挖范围内也应适当进行冻结加固以保证开挖面的稳定,冻土抗压强度设计值不小于4Mpa,抗折强度设计值不小于1.8Mpa,抗剪强度设计值不小于1.5Mpa。Among them, in step 4, the reinforcement in the hole is frozen by means of reserved holes, which can facilitate the reinforcement of the interlayer soil and ensure the reinforcement range and safety. The effective freezing thickness of the frozen soil curtain outside the initial support is less than 3m, and it should also be properly carried out within the excavation range. Freeze reinforcement to ensure the stability of the excavation surface. The design value of the compressive strength of frozen soil is not less than 4Mpa, the design value of the flexural strength is not less than 1.8Mpa, and the design value of the shear strength is not less than 1.5Mpa.

步骤4中,卸压管选用

Figure BDA0003871884040000081
无缝钢管;管前端开口进入土体段钻孔呈梅花状,以确保冻结帷幕内的压力有效传递。In step 4, the pressure relief pipe is selected
Figure BDA0003871884040000081
Seamless steel pipe; the opening of the front end of the pipe enters the soil section and the drilling is in the shape of a plum blossom to ensure the effective transmission of pressure in the freezing curtain.

其中,步骤5及步骤8中,加固土体达到开挖要求后,采用台阶法开挖联络通道,通道上台阶开挖采用环形开挖预留核心土,台阶长度为3~5m,并根据施工实际情况调整,通道开挖循环进尺为0.5m。Among them, in step 5 and step 8, after the reinforced soil meets the excavation requirements, the connecting channel is excavated by the step method, and the core soil is reserved by circular excavation for the step excavation on the channel. The actual situation is adjusted, and the excavation cycle footage of the channel is 0.5m.

其中,步骤10中,解除冷冻时,冻土层自然融沉过程中,由于土体孔隙率变大含水量增加,物理力学参数和变形参数变差,结构和地层容易产生过大变形,必要时可采用强制融沉注浆措施,以控制结构和地层变形,减少对周围环境及两侧盾构区间的不利影响。Among them, in step 10, when thawing, during the natural thawing and settlement process of the permafrost layer, due to the increase of soil porosity and water content, the physical and mechanical parameters and deformation parameters become worse, and the structure and formation are prone to excessive deformation. Forced melt-settling grouting measures can be adopted to control structural and stratum deformation and reduce adverse effects on the surrounding environment and shield sections on both sides.

融沉时,注浆管选用

Figure BDA0003871884040000091
的焊接管,顶端接带螺纹的管箍,并用丝堵封闭。当停止地层冻结时将引起融沉,就可利用预埋注浆管及管片注浆孔等进行注浆填充。在隧道底部和喇叭口处可利用管片注浆孔,必要时再利用钻机开孔布设注浆孔,进行注浆。When melting and settling, the grouting pipe is selected
Figure BDA0003871884040000091
The welded pipe is connected with a threaded pipe collar at the top and closed with a plug. When the freezing of the ground will cause thawing, the pre-embedded grouting pipe and segment grouting holes can be used for grouting filling. Segment grouting holes can be used at the bottom of the tunnel and at the bell mouth, and if necessary, the drilling rig can be used to lay out the grouting holes for grouting.

融沉注浆的具体措施如下:The specific measures for melt-settling grouting are as follows:

(1)浆材料及参数。浆液为单液浆,水泥浆的配比宜为水:水泥=1:1,单孔注浆量为1m3,注浆压力不超过2倍的静水压力。(1) Slurry material and parameters. The grout is single liquid grout, and the ratio of cement grout should be water:cement = 1:1, the grouting amount for a single hole is 1m 3 , and the grouting pressure should not exceed 2 times the hydrostatic pressure.

(2)注浆孔设置。利用结构施工时预埋的注浆孔,用冲击钻进行冲孔,必要时可用开孔机开孔,钻透冻结壁进行注浆。(2) Grouting hole setting. Utilize the pre-buried grouting holes during structure construction, punch holes with a percussion drill, and drill holes with a hole drilling machine if necessary, and drill through the frozen wall for grouting.

(3)注浆方法。采用由下而上、少量多次的注浆方法,具体做法是:由通道底板、侧墙、拱顶进行注浆。注浆结束后,用双液浆进行封孔。(3) Grouting method. The method of grouting from bottom to top, small amount and multiple times is adopted, and the specific method is: grouting from the bottom plate of the channel, side walls and vault. After grouting, seal the holes with double-fluid grout.

(4)注浆施工过程的监测。控制通道的拱顶沉降变形是注浆的目的,因此,自然解冻过程中,要加强通道拱顶变形监测,监测数据是注浆参数调整的依据。(4) Monitoring of grouting construction process. The purpose of grouting is to control the settlement and deformation of the arch of the channel. Therefore, during the natural thawing process, it is necessary to strengthen the monitoring of the deformation of the vault of the channel. The monitoring data is the basis for adjusting the grouting parameters.

(5)融沉注浆结束标志。融沉注浆的结束是以通道拱顶变形稳定为依据,若冻结壁全部融化,且实测通道拱顶沉降持续一个月,每半个月不大于0.5mm,可停止融沉注浆。(5) The sign of the end of melting and sinking grouting. The end of the melt-settling grouting is based on the stable deformation of the channel vault. If the frozen wall is completely melted and the settlement of the channel vault lasts for one month, and the settlement of the channel vault is not greater than 0.5mm every half month, the melt-settling grouting can be stopped.

以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and changes. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1.一种叠落隧道联络通道施工方法,其特征是,包括以下步骤:1. A method of construction of a cascading tunnel connecting passage, is characterized in that, comprises the following steps: 盾构推进至拟建上/下层联络通道时,对应拼装衬砌环管片;When the shield is advanced to the proposed upper/lower layer communication channel, the lining ring segment should be assembled correspondingly; 采用地面垂直冷冻+洞内冷冻法加固下层联络通道周围土体;Use ground vertical freezing + in-hole freezing method to strengthen the soil around the lower communication channel; 下层隧道开挖下层联络通道,并施工初支结构和二衬结构;Excavate the lower connecting channel for the lower tunnel, and construct the primary support structure and the secondary lining structure; 冷冻上层联络通道周围土体,上层隧道开挖上层联络通道,并施工初支结构和二衬结构;Freeze the soil around the upper communication passage, excavate the upper communication passage for the upper tunnel, and construct the primary support structure and the secondary lining structure; 施工内部结构,主体结构达到强度后解除冷冻。The internal structure is constructed, and the main structure reaches its strength and then thawed out. 2.如权利要求1所述的叠落隧道联络通道施工方法,其特征是,下层联络通道周围土体加固时,从下线注浆口及地面打设循环管路冷冻加固下层联络通道周围土体,洞内加固借助预留孔洞进行冷冻。2. The construction method of the cascading tunnel communication channel as claimed in claim 1, characterized in that, when the soil around the lower layer communication channel is reinforced, a circulating pipeline is set up from the downline grouting port and the ground to freeze and reinforce the soil around the lower layer communication channel Body, the reinforcement in the hole is frozen by means of reserved holes. 3.如权利要求2所述的叠落隧道联络通道施工方法,其特征是,加固时,在隧道冻结帷幕封闭区域内均布多个卸压孔,在卸压孔上安装压力表,实时监测冻结帷幕内的压力变化情况,判断冻结帷幕的形成,释放冻胀压力。3. The construction method of the cascading tunnel communication channel as claimed in claim 2, wherein during reinforcement, a plurality of pressure relief holes are evenly distributed in the closed area of the tunnel freezing curtain, and pressure gauges are installed on the pressure relief holes for real-time monitoring. Freeze the pressure changes in the curtain, judge the formation of the freeze curtain, and release the frost heave pressure. 4.如权利要求1所述的叠落隧道联络通道施工方法,其特征是,冷冻加固前,在上下层隧道衬砌环不开口部位安装临时支撑、支承板。4. The construction method of the connecting channel of the cascading tunnel according to claim 1, characterized in that, before freezing and strengthening, temporary supports and support plates are installed on the openings of the upper and lower tunnel lining rings. 5.如权利要求1所述的叠落隧道联络通道施工方法,其特征是,下层隧道的施工过程为:5. The construction method of the cascading tunnel connecting passage as claimed in claim 1, wherein the construction process of the lower tunnel is: 加固土体达到开挖要求后,拆除下层隧道衬砌环管片中开口部分,从下层隧道内采用台阶法开挖下层联络通道上部洞室,施工初支结构,开挖下部洞室,施做初支结构,初支封闭后,由下向上施工下层联络通道防水层、二衬结构,预留与竖直段二衬连接的钢筋接头;After the reinforced soil meets the excavation requirements, the opening part of the lower tunnel lining ring segment is removed, and the upper cavern of the lower connecting passage is excavated from the lower tunnel by the step method, the initial support structure is constructed, the lower cavern is excavated, and the initial tunnel is constructed. For the support structure, after the initial support is closed, the waterproof layer and the second lining structure of the lower communication channel shall be constructed from bottom to top, and the steel bar joints connected with the second lining of the vertical section shall be reserved; 在下层联络通道二衬达到设计强度后,向下破除泵房处初支,开挖泵房,泵房初支封闭后,由下向上施工泵房防水、二衬,下层联络通道竖直段防水、侧缝,预留与上部侧墙相接的钢筋接驳器。After the second lining of the lower communication channel reaches the design strength, remove the initial support at the pump room downwards and excavate the pump room. After the initial support of the pump room is closed, waterproof the pump room and the second lining from bottom to top, and waterproof the vertical section of the lower communication channel. , Side seam, reserve a steel bar connector connected to the upper side wall. 6.如权利要求5所述的叠落隧道联络通道施工方法,其特征是,泵房及下层联络通道竖直段二衬达到强度后,减少部分冷冻管,使竖直段顶部处于冷冻体中,同时冷冻上层联络通道周围土体。6. The construction method of the cascading tunnel communication channel as claimed in claim 5, characterized in that, after the pump room and the second lining of the vertical section of the lower communication channel reach the strength, part of the frozen pipes are reduced so that the top of the vertical section is in the frozen body , and freeze the soil around the upper communication channel at the same time. 7.如权利要求1所述的叠落隧道联络通道施工方法,其特征是,拼装完衬砌环管片后,从地面打设新风井钢管至竖直段通道顶板底标高位置。7. The construction method of the connecting channel of the cascading tunnel according to claim 1, characterized in that, after assembling the lining ring segment, the fresh air shaft steel pipe is drilled from the ground to the elevation of the roof bottom of the vertical section channel. 8.如权利要求7所述的叠落隧道联络通道施工方法,其特征是,上层隧道的施工过程为:8. The construction method of the cascading tunnel connecting passage as claimed in claim 7, wherein the construction process of the upper tunnel is: 从上层隧道内采用台阶法开挖上层联络通道上部洞室,施工初支结构,开挖下部洞室,施做初支,初支封闭后,由下向上施工上层联络通道防水、二衬结构,预留与竖直段二衬连接的钢筋接头;上层联络通道二衬达到设计强度后,向下破除初支,开挖剩余竖直段通道,竖直段通道初支与两端连接封闭后,由下向上施工竖直段通道防水、侧墙、顶板,顶板与新风井钢管连接,顶板钢筋与新风井钢管焊接,连接外混凝土浇筑密实,侧墙底部预留钢筋接驳器。Excavate the upper cavern of the upper communication passage from the upper tunnel by step method, construct the primary support structure, excavate the lower cavern, and make the initial support. After the initial support is closed, construct the waterproof and secondary lining structure of the upper communication passage from bottom to top. Reserve the steel bar joints connected with the second lining of the vertical section; after the second lining of the upper communication channel reaches the design strength, remove the initial support downwards, excavate the remaining vertical section channels, and after the initial support of the vertical section channel is connected to both ends and closed, Waterproofing, side walls, and roof of the vertical section shall be constructed from bottom to top. The roof shall be connected to the steel pipe of the fresh air shaft, the steel bars of the roof shall be welded to the steel pipe of the fresh air shaft, the concrete shall be poured densely outside the connection, and a steel bar connector shall be reserved at the bottom of the side wall. 9.如权利要求8所述的叠落隧道联络通道施工方法,其特征是,完成后破除坚直段底板格栅,向下开挖坚直段最后一部分,施做初期支护,全部挖通后,由下至上施工防水及侧墙,使上层联络通道、下层联络通道、竖直段通道的二衬连接成整体。9. The construction method for the connecting channel of the cascading tunnel as claimed in claim 8, characterized in that, after the completion, the floor grid of the straight section is removed, the last part of the straight section is excavated downwards, initial support is applied, and all of them are dug through. Finally, waterproofing and side walls are constructed from bottom to top, so that the upper layer communication channel, the lower layer communication channel, and the second lining of the vertical section channel are connected as a whole. 10.如权利要求1所述的叠落隧道联络通道施工方法,其特征是,当解除冷冻引起融沉时,利用预埋注浆管及管片注浆孔进行融沉注浆填充,采用单液浆注浆,采用由下而上、少量多次的注浆方法,通道拱顶变形稳定后,停止融沉注浆,注浆结束后,用双液浆进行封孔。10. The construction method of the cascading tunnel communication channel as claimed in claim 1, characterized in that, when thawing causes thawing, pre-embedded grouting pipes and segment grouting holes are used for thawing and grouting filling, and a single Slurry grouting adopts the grouting method from bottom to top, small amount and multiple times. After the deformation of the channel vault is stable, stop the melt-settling grouting. After the grouting is completed, use double-slurry grout to seal the hole.
CN202211199439.2A 2022-09-29 2022-09-29 A construction method for the connecting passage of a cascading tunnel Withdrawn CN115749793A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211199439.2A CN115749793A (en) 2022-09-29 2022-09-29 A construction method for the connecting passage of a cascading tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211199439.2A CN115749793A (en) 2022-09-29 2022-09-29 A construction method for the connecting passage of a cascading tunnel

Publications (1)

Publication Number Publication Date
CN115749793A true CN115749793A (en) 2023-03-07

Family

ID=85350635

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211199439.2A Withdrawn CN115749793A (en) 2022-09-29 2022-09-29 A construction method for the connecting passage of a cascading tunnel

Country Status (1)

Country Link
CN (1) CN115749793A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116838351A (en) * 2023-07-21 2023-10-03 上海市基础工程集团有限公司 Construction method for constructing externally-hung connecting channel in shield overlapping tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116838351A (en) * 2023-07-21 2023-10-03 上海市基础工程集团有限公司 Construction method for constructing externally-hung connecting channel in shield overlapping tunnel

Similar Documents

Publication Publication Date Title
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN210013697U (en) Construction structure of near-penetrating building of underground excavation section of subway station entrance and exit
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN109736827B (en) Excavation method of high-pressure gas expansion-induced cracking in the connection channel of urban subway hard rock strata
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN215169989U (en) Freezing system for reinforcing 60-meter-grade ultra-long distance communication channel by freezing method
CN114542086A (en) A construction method for long-span undercut tunnels affected by groundwater
CN112049115A (en) Anti-seepage treatment method for deep foundation pit excavation of water-rich silt stratum
CN105065009B (en) A method for expanding shield construction subway station
CN111395391B (en) Construction method for multi-hole rectangular jacking pipe and light and dark excavation joint pipe gallery joint
CN112727466A (en) Construction method for support-free prefabricated assembled type shield tunnel air shaft structure
CN111322089A (en) Vault prefabricated assembled tunnel and construction method
CN116398165A (en) A new tunnel under zero distance passing through an existing station and its construction method
CN104963341B (en) A kind of manifold type earth source heat pump mixing backfilling process and backfill material
CN115749793A (en) A construction method for the connecting passage of a cascading tunnel
CN116397694A (en) Arch protection structure and construction method of excavation and cover-excavation of tunnel under partial pressure in shallow buried section
CN113186977B (en) A reverse sequence construction method for underground comprehensive utility gallery
CN111472803B (en) Tunnel structure suitable for upper soft and lower hard composite stratum and construction method
CN110735641B (en) The construction method of the transfer channel under the pipeline
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN209523759U (en) A super shallow buried tunnel structure
CN111561322A (en) Construction structure and construction method of large-section tunnel with water-rich and weak surrounding rock
CN114277700B (en) Construction method of open cut tunnel of high and large karst cave in hidden river section
CN112359819B (en) Wall structure construction method for increasing depth of old diaphragm wall
CN217462171U (en) Large-span cross-sectional undercut tunnel stagnant water reinforced structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20230307