CN115749231A - Climbing type operation platform for high-rise building construction - Google Patents

Climbing type operation platform for high-rise building construction Download PDF

Info

Publication number
CN115749231A
CN115749231A CN202211134116.5A CN202211134116A CN115749231A CN 115749231 A CN115749231 A CN 115749231A CN 202211134116 A CN202211134116 A CN 202211134116A CN 115749231 A CN115749231 A CN 115749231A
Authority
CN
China
Prior art keywords
plate
operation platform
building construction
rise building
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202211134116.5A
Other languages
Chinese (zh)
Inventor
徐雪健
邱艳敏
韩顺龙
葛亚兰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shengye Construction Project Management Co ltd
Original Assignee
Anhui Shengye Construction Project Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Shengye Construction Project Management Co ltd filed Critical Anhui Shengye Construction Project Management Co ltd
Priority to CN202211134116.5A priority Critical patent/CN115749231A/en
Publication of CN115749231A publication Critical patent/CN115749231A/en
Withdrawn legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The invention discloses a climbing type operation platform for high-rise building construction, which comprises parallel walls, wherein a platform frame structure is arranged on the side wall of the wall through a fixing mechanism, if the height of a device is required to be increased, a threaded column at the bottom of a frame-shaped supporting leg of a bottom device can be connected in a connecting sleeve on a connecting bottom plate of an upper device in a threaded manner, so that the heights of two layers of devices are increased, if the platform frame structure is required to be climbed, an electric hoist is arranged on the wall through a detachably-arranged hanging part, a hanging ring on a bottom connecting plate between left frame rods is hung through a hook at the bottom of a steel wire rope, the steel wire rope moves upwards, and a spring in a limiting structure pushes an arc-shaped clamping plate to be clamped in a clamping groove, so that the left frame rod can only move upwards under the action of the electric hoist, the self-climbing effect of the device is realized, and meanwhile, workers are protected by various protective plates during construction.

Description

Climbing type operation platform for high-rise building construction
Technical Field
The invention relates to the technical field of climbing type operating equipment, in particular to a climbing type operating platform for high-rise building construction.
Background
The building engineering is an engineering entity formed by the construction of various house buildings and auxiliary facilities thereof and the installation activities of lines, pipelines and equipment matched with the house buildings, when the high-rise building construction is carried out, a climbing type building construction operation platform is generally required, the building construction operation platform can replace a traditional scaffold, the labor intensity can be reduced, the work efficiency is improved, novel high-rise operation equipment can be repeatedly used, and the high-rise building construction equipment is widely recognized in high-altitude operations such as outer wall construction, curtain wall installation, heat preservation construction, maintenance and cleaning of high-rise multi-storey high buildings.
To this, the utility model discloses an outside formula construction operation platform that climbs of building is disclosed to the chinese utility model patent that the grant bulletin number is CN209163396U, including fixed chassis, all be provided with the support column on the outer wall in fixed chassis top four corners, and the quantity of support column is four, two all the welding has the enhancement horizontal pole, four on the outer wall of the relative one side of support column all the welding have operation platform on the outer wall on support column top, the intermediate position of operation platform top outer wall is opened there is the passageway, the inside grafting of passageway has the climbing ladder, and inside the climbing ladder was located the cavity that four support columns enclose, all opened on the outer wall of operation platform both sides and had the drawing groove. The utility model discloses be convenient for the workman to the device build, and improved the device's stability for operation platform's working area can carry out the regulation on the spot, has improved the device's flexibility, has accelerated the efficiency of workman's work, makes the frictional force of staff's during operation underfoot on the platform bigger, has played better guarantee to the operation of workman eminence.
The existing construction platform of the operation platform in the case is poor in stability, and the operation manual work does not have protective measures in the construction process, so that the safety is poor, the platform cannot climb upwards along with the height of a floor, the operation platform is inconvenient to use for a building with a high height, and the climbing type operation platform for high-rise building construction is provided for solving the problems.
Disclosure of Invention
The invention aims to provide a climbing operation platform for high-rise building construction, which solves the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a climbing operation platform for high-rise building construction comprises parallel walls, wherein one side wall of each wall is movably engaged with one side of a connecting bottom plate through a fixing mechanism, and the wall below is also movably engaged with a supporting bottom plate through the fixing mechanism;
the supporting bottom plate is connected with the bottom of the platform frame structure through bolts, the bottom of the supporting bottom plate is fixedly connected with a plurality of frame-shaped supporting legs, the bottoms of the frame-shaped supporting legs are rotatably connected with threaded columns, the connecting bottom plate is connected with the top of the platform frame structure through bolts, and a plurality of connecting sleeves are fixedly arranged on the connecting bottom plate;
the platform frame structure is slidably mounted on the side wall of the wall body through a limiting structure.
Preferably, the platform frame construction includes left hack lever and right hack lever of two sets of parallels, and sets up the connecting hole on the both ends wall of left hack lever and right hack lever, through a plurality of diaphragm activity joints between left side hack lever and the right hack lever, the below of left side hack lever and right hack lever is through a plurality of montant one and montant two that are parallel to each other of bolted connection, through the diagonal bracing piece rigid coupling between two adjacent montant one or the montant two, left hack lever and right hack lever that are located the below through bolted connection on the supporting baseplate, the backing plate is prevented falling through bolted connection in the diaphragm top, swing joint guard plate on the diaphragm of top.
Preferably, the inner walls of the first vertical rod and the second vertical rod are connected with a side guard plate through bolts, the transverse plate below the first vertical rod and the second vertical rod is movably connected with a reinforcing pedal, two groups of left frame rods or right frame rods on the same side are connected with an anti-falling cover through bolts, and the middle of the anti-falling cover is provided with a hollow part.
Preferably, the side wall of the wall body at the upper part is detachably provided with a hanging part, one side of the hanging part is fixedly connected with an electric hoist, a bottom connecting plate is fixedly arranged between left frame rods at one side of the wall body at the lower part, the bottom connecting plate is fixedly connected with a hanging ring, the bottom of a steel wire rope which is arranged in the electric hoist in a twisting way is movably sleeved with one end of a hook, and the hook is movably hung in the hook.
Preferably, the inside mounting groove of seting up of limit structure, and the inside slidable mounting push pedal of mounting groove, through spring swing joint between the diapire of a lateral wall of push pedal and mounting groove, another lateral wall rigid coupling one end of push pedal is convex arc cardboard.
Preferably, a clamping groove is formed in one side of the left frame rod, and the arc-shaped clamping plate is movably clamped in the clamping groove.
Preferably, the connecting holes are internally threaded with connecting bolts, and the sides of the falling-prevention cover are movably connected to the sides of the two groups of left frame rods and the right frame rods through the connecting bolts.
Compared with the prior art, the invention has the beneficial effects that:
the platform frame structure is connected through the fixing mechanism on one side of the wall body, meanwhile, the bottom of the wall body limits the left frame rod through the limiting mechanism, so that the limiting mechanism limits the whole device in a mounted mode, the device has higher stability, and the protection is performed on workers during construction through the protection plate, the side protection plate, the reinforcing pedal plate and the anti-falling cover, so that the safety of the device to the workers is guaranteed;
install the screw thread post in connecting sleeve, splice two devices and pile up, make the height of device rise, in order to deal with not building of co-altitude, simultaneously because electric block installs on the wall body through the piece of carrying of detachable installation, and carry out the carry to the link on the bottom-mounted connecting plate between the hack lever of left side through the couple of wire rope bottom, wire rope upward movement, with the hack lever of left side under limit structure's effect, shift up, thereby realize the self-climbing effect of device, the deduction and exemption is used for the manual work to carry out the work according to building height shift up device.
Drawings
FIG. 1 is a schematic view of the structure of the present invention;
FIG. 2 is a schematic view of a platform frame structure according to the present invention;
FIG. 3 is a schematic view of the installation structure of the drop-proof cover of the present invention;
FIG. 4 is a schematic view of a climbing structure according to the present invention;
fig. 5 is a schematic view of a limiting structure of the present invention.
In the figure: 1. a wall body; 11. a fixing mechanism; 2. connecting the bottom plate; 21. a connecting sleeve; 22. a connecting bolt; 3. a platform frame structure; 30. a left frame bar; 301. a right frame bar; 31. a transverse plate; 32. connecting holes; 33. a first vertical rod; 331. a card slot; 34. a second vertical rod; 35. an oblique supporting rod; 37. a falling-preventing base plate; 38. a support base plate; 39. a frame-shaped support leg; 391. a threaded post; 4. a protection plate; 41. a side guard plate; 42. reinforcing the pedal plate; 43. a falling prevention cover; 431. hollowing out; 5. a hanging member; 51. an electric hoist; 52. a wire rope; 53. a connecting plate is arranged at the bottom; 531. hanging a ring; 54. hooking; 6. a limiting structure; 61. mounting grooves; 62. a spring; 63. pushing a plate; 64. arc cardboard.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: a climbing operation platform for high-rise building construction comprises parallel wall bodies 1, wherein one side wall of each wall body 1 is movably engaged with one side of a connecting bottom plate 2 through a fixing mechanism 11, and the lower wall body 1 is also movably engaged with a supporting bottom plate 38 through the fixing mechanism 11;
the supporting bottom plate 38 is connected with the bottom of the platform frame structure 3 through bolts, the bottom of the supporting bottom plate 38 is fixedly connected with a plurality of frame-shaped supporting legs 39, the bottoms of the frame-shaped supporting legs 39 are rotatably connected with threaded columns 391, the connecting bottom plate 2 is connected with the top of the platform frame structure 3 through bolts, and a plurality of connecting sleeves 21 are fixedly arranged on the connecting bottom plate 2;
platform frame construction 3 passes through 6 slidable mounting of limit structure on the lateral wall of wall body 1, platform frame construction 3 includes left hack lever 30 and right hack lever 301 of two sets of parallels, and set up connecting hole 32 on the both ends wall of left hack lever 30 and right hack lever 301, through a plurality of diaphragm 31 activity joint between left hack lever 30 and the right hack lever 301, a plurality of montant 33 and the two 34 that are parallel to each other are passed through bolted connection in left hack lever 30 and right hack lever 301's below, pass through oblique bracing pole 35 rigid coupling between two adjacent montant 33 or the two 34 of montants.
The left frame rod 30 and the right frame rod 301 which are located below are connected through bolts on the supporting bottom plate 38, the base plate 37 is prevented from falling through bolts above the transverse plate 31, the protective plate 4 is movably connected to the transverse plate 31 above, the inner walls of the first vertical rod 33 and the second vertical rod 34 are connected through bolts to the side protection plate 41, the pedal 42 is movably connected to the transverse plate 31 below, the cover 43 is prevented from falling through bolts between the two groups of left frame rods 30 or the right frame rods 301 on the same side, and the hollow 431 is formed in the middle of the cover 43.
The side wall of the upper wall body 1 is detachably provided with a hanging part 5, one side of the hanging part 5 is fixedly connected with an electric hoist 51, and a bottom connecting plate 53 is fixedly arranged between the left frame rods 30 on one side of the lower wall body 1.
The bottom-mounted connecting plate 53 is fixedly connected with a hanging ring 531, one end of a hook 54 is movably sleeved at the bottom of a steel wire rope 52 which is arranged in the electric hoist 51 in a twisting manner, and the hook 54 is movably hung in the hook 54.
The inside mounting groove 61 that offers of limit structure 6, and the inside slidable mounting push pedal 63 of mounting groove 61, through spring 62 swing joint between the diapire of a lateral wall of push pedal 63 and mounting groove 61, another lateral wall rigid coupling one end of push pedal 63 is convex arc cardboard 64.
A clamping groove 331 is formed in one side of the left frame rod 30, and the arc-shaped clamping plate 64 is movably clamped in the clamping groove 331.
The connecting bolt 22 is arranged in the connecting hole 32, and the side edge of the anti-falling cover 43 is movably connected with the side edges of the two groups of left frame rods 30 and right frame rods 301 through the connecting bolt 22.
Limit structure 6 is similar to the door lock structure, spring 62 wherein promotes arc cardboard 64 joint in draw-in groove 331, because arc cardboard 64 is arc, thereby make left hack lever 30 can only shift up under electric block 51's effect, disassemble the device from the building top after the building is accomplished, fixed establishment 11 can adopt the dado among the prior art, the reinforcement etc. after moving on the device, shift up the fixed establishment 11 of bottom to the wall body 1 of top in, from newly making fixed establishment 11 and platform frame construction 3 mesh, realize that platform frame construction 3 is steady to be installed on the lateral wall of wall body 1, thereby the construction of the workman of being convenient for is used.
The working principle is as follows: when the device is normally used, the platform frame structure 3 is installed on the side wall of the wall body 1 through the fixing mechanism 11, if the height of the device needs to be increased, the threaded column 391 at the bottom of the bottom device frame-shaped supporting leg 39 can be connected in the connecting sleeve 21 on the upper device connecting bottom plate 2 in a threaded manner, so that the height of the two layers of devices is increased, if the platform frame structure 3 needs to be climbed, because the electric hoist 51 is installed on the wall body 1 through the detachably installed hanging part 8, and the hanging ring 531 on the bottom connecting plate 53 between the left frame rods 30 is hung through the hook 54 at the bottom of the steel wire rope 52, the steel wire rope 52 moves upwards, because the spring 62 in the limiting structure 6 pushes the arc-shaped clamping plate 64 to be clamped in the clamping groove 331, because the arc-shaped clamping plate 64 is arc-shaped, the left frame rod 30 can only move upwards under the action of the electric hoist 51, the self-climbing effect of the device is realized, meanwhile, the protection is performed on the construction of workers through the plates for protection, and the use safety of the workers is ensured.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. A climbing operation platform for high-rise building construction, comprising a parallel wall body (1), one side of a bottom plate (2) is movably engaged and connected on one side wall of the wall body (1) through a fixing mechanism (11), the wall body (1) below is also movably engaged and supported on the bottom plate (38) through the fixing mechanism (11), and the climbing operation platform is characterized in that:
the supporting bottom plate (38) is connected with the bottom of the platform frame structure (3) through bolts, the bottom of the supporting bottom plate (38) is fixedly connected with a plurality of frame-shaped supporting legs (39), the bottoms of the frame-shaped supporting legs (39) are rotatably connected with threaded columns (391), the connecting bottom plate (2) is connected with the top of the platform frame structure (3) through bolts, and a plurality of connecting sleeves (21) are fixedly arranged on the connecting bottom plate (2);
the platform frame structure (3) is slidably mounted on the side wall of the wall body (1) through a limiting structure (6).
2. A climbing operation platform for high-rise building construction according to claim 1, wherein: platform frame construction (3) include left hack lever (30) and right hack lever (301) of two sets of parallels, and offer connecting hole (32) on the both ends wall of left hack lever (30) and right hack lever (301), through a plurality of diaphragm (31) activity joint between left side hack lever (30) and right hack lever (301), a plurality of montant one (33) and montant two (34) that are parallel to each other are passed through bolted connection to the below of left side hack lever (30) and right hack lever (301), through diagonal bracing pole (35) rigid coupling between two adjacent montant one (33) or montant two (34).
3. A climbing operation platform for high-rise building construction according to claim 2, wherein: the supporting base plate (38) is connected with a left frame rod (30) and a right frame rod (301) which are located below through bolts, the transverse plate (31) is connected with an anti-falling base plate (37) through bolts, and the transverse plate (31) above the transverse plate (31) is movably connected with a protection plate (4).
4. A climbing operation platform for high-rise building construction according to claim 3, wherein: the inner walls of the first vertical rod (33) and the second vertical rod (34) are connected with a side protection plate (41) through bolts, the transverse plate (31) below is movably connected with a reinforcing pedal (42), two groups of left frame rods (30) or right frame rods (301) on the same side are connected with each other through bolts to form a falling-preventing cover (43), and the middle part of the falling-preventing cover (43) is provided with a hollow part (431).
5. A climbing operation platform for high-rise building construction according to claim 1, wherein: the hanging and carrying device is characterized in that a hanging and carrying piece (5) is detachably mounted on the side wall of the upper wall body (1), an electric hoist (51) is fixedly connected to one side of the hanging and carrying piece (5), and a bottom connecting plate (53) is fixedly mounted between the left frame rods (30) on one side of the lower wall body (1).
6. A climbing operation platform for high-rise building construction according to claim 5, wherein: the bottom-mounted connecting plate (53) is fixedly connected with a hanging ring (531), the bottom of a steel wire rope (52) which is arranged in an electric hoist (51) in a twisting mode is movably sleeved with one end of a hook (54), and the hook (54) is movably hung in the hook (54).
7. A climbing operation platform for high-rise building construction according to claim 1, wherein: mounting groove (61) is seted up to limit structure (6) inside, and inside slidable mounting push pedal (63) of mounting groove (61), through spring (62) swing joint between the diapire of a lateral wall of push pedal (63) and mounting groove (61), another lateral wall rigid coupling one end of push pedal (63) is convex arc cardboard (64).
8. A climbing operation platform for high-rise building construction according to claim 1, wherein: a clamping groove (331) is formed in one side of the left frame rod (30), and the arc-shaped clamping plate (64) is movably clamped in the clamping groove (331).
9. A climbing operation platform for high-rise building construction according to claim 1, wherein: the connecting holes (32) are internally threaded with connecting bolts (22), and the sides of the anti-falling cover (43) are movably connected to the sides of the two groups of left frame rods (30) and right frame rods (301) through the connecting bolts (22).
CN202211134116.5A 2022-09-19 2022-09-19 Climbing type operation platform for high-rise building construction Withdrawn CN115749231A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211134116.5A CN115749231A (en) 2022-09-19 2022-09-19 Climbing type operation platform for high-rise building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211134116.5A CN115749231A (en) 2022-09-19 2022-09-19 Climbing type operation platform for high-rise building construction

Publications (1)

Publication Number Publication Date
CN115749231A true CN115749231A (en) 2023-03-07

Family

ID=85350186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211134116.5A Withdrawn CN115749231A (en) 2022-09-19 2022-09-19 Climbing type operation platform for high-rise building construction

Country Status (1)

Country Link
CN (1) CN115749231A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117027344A (en) * 2023-07-28 2023-11-10 韩大建设有限公司 Construction platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117027344A (en) * 2023-07-28 2023-11-10 韩大建设有限公司 Construction platform

Similar Documents

Publication Publication Date Title
CN201506699U (en) Electric lifting bridge rack for construction
CN106284956B (en) A kind of scaffold and its construction method of automatic lifting
CN105986663B (en) Elevator tooling hoistable platform
CN219773544U (en) Scaffold for building engineering
CN115749231A (en) Climbing type operation platform for high-rise building construction
CN208056596U (en) A kind of Novel engineering exterior wall scaffold
CN205822747U (en) Architectural engineering scaffold
CN216276816U (en) Connecting assembly for hanging frame of building machine
CN102817464A (en) Construction device for painting anti-corrosion and fireproof paint of building
CN215167838U (en) Movable overhung suspension type operating platform
CN104278830A (en) Integral combined scaffold
CN220395120U (en) Overhanging type operation platform
CN209837631U (en) Multistage assembled lattice frame building structure
CN219280494U (en) Tower beam temporary consolidation supporting structure for bridge tower stability control
CN218346729U (en) scaffolding for construction
CN214246528U (en) Scaffold for building construction
CN216476221U (en) A construction scaffolding fixing mechanism
CN204435824U (en) Elevator frock lift platform
CN212388956U (en) Suspension operation platform for construction of building inclined structural column
CN205100533U (en) There is rail hanging flower basket
CN207863449U (en) Disk buckle type scaffold new type of safe cat ladder
CN209817424U (en) A mobile adjustable cantilevered operating platform suitable for super-long cantilevered structures
CN113404278A (en) Self-climbing type protection frame and climbing method thereof
CN216616769U (en) A mobile operating platform
CN216276815U (en) Connecting assembly for hanging frame of building machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20230307