CN115749186A - Prefabricated wall dry-hanging installation structure and installation method - Google Patents
Prefabricated wall dry-hanging installation structure and installation method Download PDFInfo
- Publication number
- CN115749186A CN115749186A CN202211388106.4A CN202211388106A CN115749186A CN 115749186 A CN115749186 A CN 115749186A CN 202211388106 A CN202211388106 A CN 202211388106A CN 115749186 A CN115749186 A CN 115749186A
- Authority
- CN
- China
- Prior art keywords
- plug
- leveling
- installation structure
- board
- inner groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Finishing Walls (AREA)
Abstract
本发明公开一种装配式墙面干挂安装结构及其安装方法,所述安装结构包括基层调平结构和墙板安装结构,基层调平结构固定在建筑墙体上,包括数个调平件,所述墙板安装结构包括复合墙板、双侧插接固定件以及连接件,复合墙板的一端含有内凹槽,双侧插接固定件的一侧插接在所述内凹槽中,另一侧固定在调平件上,复合墙板不含有内凹槽的一端与连接件固定连接,连接件的另一端与双侧插接固定件形成插接固定结构,在复合墙板和建筑墙体之间形成管线集成空间。本发明运用调节性能优异且体积较小的调节件,使基层调平方便快捷,可使墙面管线系统置于基层调平结构之中,避免开槽铺设,且走线相对灵活。运用插接型连接件安装墙面板,连接结构稳定。
The invention discloses a prefabricated wall dry-hanging installation structure and an installation method thereof. The installation structure includes a base-level leveling structure and a wall panel installation structure. The base-level leveling structure is fixed on a building wall and includes several leveling pieces , the wall panel installation structure includes a composite wall panel, a double-sided plug-in fixing piece and a connector, one end of the composite wallboard contains an inner groove, and one side of the double-sided plug-in fixing piece is inserted into the inner groove , the other side is fixed on the leveling piece, one end of the composite wallboard without the inner groove is fixedly connected with the connector, and the other end of the connector forms a plug-in fixing structure with the double-sided plug-in fixture, and the composite wallboard and A pipeline integration space is formed between the building walls. The invention uses an adjusting member with excellent adjustment performance and small volume to make the leveling of the base layer convenient and quick, and can place the wall pipeline system in the leveling structure of the base layer, avoiding slotting and laying, and the wiring is relatively flexible. Use plug-in connectors to install wall panels, and the connection structure is stable.
Description
技术领域technical field
本发明属于建筑装饰技术领域,具体涉及一种装配式墙面干挂安装结构及其安装方法。The invention belongs to the technical field of architectural decoration, and in particular relates to a prefabricated wall dry-hanging installation structure and an installation method thereof.
背景技术Background technique
建筑装饰领域中,墙面装饰不仅可以起到美化空间的作用,使用不同材料也具备相应的功能性,可满足设计及用户日常使用需求。如瓷砖墙饰面兼具耐热、防水和易清洁的功能,常用于厨房、卫生间及其他特殊场景。因其突出的材料性能及装饰效果,被大范围推广及使用。In the field of architectural decoration, wall decoration can not only beautify the space, but also have corresponding functions using different materials, which can meet the needs of design and daily use of users. For example, tile wall finishes are heat-resistant, waterproof and easy to clean, and are often used in kitchens, bathrooms and other special scenes. Because of its outstanding material properties and decorative effects, it has been widely promoted and used.
但是,用传统湿贴或干挂方式对瓷砖进行墙面施工时会存在以下缺陷:1、传统湿贴法基层处理或铺贴不规范时,瓷砖可能发生空鼓脱落等现象,极大的影响瓷砖墙面效果和质量。2、湿法作业耗时长,且墙面质量过度依赖于施工人员技术水平。3、大尺寸瓷砖自重大、吸水率低,需采用高强度的粘结材料,干挂时对现场的施工环境要求较高。4、调平龙骨干挂瓷砖墙面板,由于龙骨调节有限,板后空间不足以容纳管线系统,需墙体开槽铺设,施工工序繁杂、后期不易对管线进行维修。However, the following defects will exist when using traditional wet paste or dry hanging methods to carry out wall construction on tiles: 1. When the base treatment or paving of the traditional wet paste method is not standardized, the tiles may be hollow and fall off, which will have a great impact Tile wall effect and quality. 2. Wet work takes a long time, and the quality of the wall is too dependent on the technical level of the construction personnel. 3. Large-sized ceramic tiles are heavy in weight and low in water absorption, so high-strength bonding materials are required, and the requirements for the construction environment on site are relatively high during dry-hanging. 4. Level the keel and hang the tile wall panel. Due to the limited keel adjustment, the space behind the panel is not enough to accommodate the pipeline system, and the wall needs to be slotted for laying. The construction process is complicated and it is difficult to maintain the pipeline in the later stage.
发明内容Contents of the invention
针对上述问题情况,本发明提供一种装配式墙面干挂安装结构及其安装方法,用于提高瓷砖墙面质量、安装效率以及增加墙面集成度。In view of the above problems and situations, the present invention provides a prefabricated wall dry-hanging installation structure and an installation method thereof, which are used to improve the quality of tile walls, installation efficiency and increase the degree of wall integration.
为了实现上述目的,本发明采取的技术方案为:In order to achieve the above object, the technical scheme that the present invention takes is:
一种装配式墙面干挂安装结构,包括基层调平结构和墙板安装结构,所述基层调平结构固定在建筑墙体上,包括数个调平件组成,所述墙板安装结构包括复合墙板、双侧插接固定件以及连接件,所述复合墙板的一端含有内凹槽,双侧插接固定件的一侧插接在所述内凹槽中,另一侧固定在调平件上,所述复合墙板不含有内凹槽的一端与连接件固定连接,连接件的另一端与双侧插接固定件形成插接固定结构,在复合墙板和建筑墙体之间形成管线集成空间,用于布置管线集成系统。A prefabricated wall dry-hanging installation structure, including a base-level leveling structure and a wallboard installation structure, the base-level leveling structure is fixed on a building wall, and consists of several leveling parts, and the wallboard installation structure includes Composite wall panels, double-sided plug-in fixing parts and connectors, one end of the composite wall board has an inner groove, one side of the double-sided plug-in fixing parts is plugged into the inner groove, and the other side is fixed in the inner groove. On the leveling piece, one end of the composite wallboard that does not contain an inner groove is fixedly connected to the connector, and the other end of the connector forms a plug-in fixing structure with the double-sided plug-in fasteners, between the composite wallboard and the building wall A pipeline integration space is formed between them, which is used to arrange the pipeline integration system.
作为进一步的技术方案,所述调平件包括底座、调节筒以及伸缩杆,所述底座和调节筒为一体结构,底座的两侧设置有螺纹孔,用于固定连接建筑墙体,调节筒内设置有内螺纹,伸缩杆设置在调节筒内侧并具有与所述内螺纹配合的外螺纹。As a further technical solution, the leveling member includes a base, an adjustment cylinder, and a telescopic rod. The base and the adjustment cylinder are integrally structured. Threaded holes are provided on both sides of the base for fixed connection with the building wall. An internal thread is provided, and the telescopic rod is arranged inside the adjusting cylinder and has an external thread matched with the internal thread.
作为进一步的技术方案,数个调平件设置在建筑墙体上,调平件的前端位于同一垂直平面上,对基层调平。As a further technical solution, several leveling parts are arranged on the building wall, and the front ends of the leveling parts are located on the same vertical plane to level the base.
作为进一步的技术方案,所述双侧插接固定件包括相互配合一体设置的第一插接板、第一侧板、第一肋板、第二侧板、第二肋板以及第一连接板,所述第一插接板、第一侧板以及第一肋板构成容纳复合墙板端部的第一容腔,第一插接板插接与复合墙板的内凹槽中;第一肋板、第二侧板以及第二肋板构成容纳连接件的第二容腔;第一连接板连接在第二肋板上。As a further technical solution, the double-sided plug-in fixing member includes a first plug-in board, a first side board, a first rib board, a second side board, a second rib board and a first connecting board that are integrated with each other. , the first plug-in board, the first side board and the first rib form a first cavity for accommodating the end of the composite wallboard, and the first plug-in board is plugged into the inner groove of the composite wallboard; the first The rib plate, the second side plate and the second rib plate form a second cavity for accommodating the connecting piece; the first connecting plate is connected to the second rib plate.
作为进一步的技术方案,在第二肋板的端部还设置有凸起部,在第一连接板上设置有螺纹孔,所述第一连接板通过螺钉固定在调平件的伸缩杆的上端部。As a further technical solution, a raised portion is provided at the end of the second rib, and a threaded hole is provided on the first connecting plate, and the first connecting plate is fixed to the upper end of the telescopic rod of the leveling member by screws department.
作为进一步的技术方案,所述连接件包括第二插接板、第二连接板以及第二插接板和第二连接板之间的弯曲部。As a further technical solution, the connecting piece includes a second socket board, a second connection board, and a bent portion between the second socket board and the second connection board.
作为进一步的技术方案,所述第二插接板插接于第二容腔中,第二连接板上设置有螺纹孔,第二连接板通过螺钉固定在复合墙板不含有内凹槽的一端,所述弯曲部与所述凸起部相对应设置。As a further technical solution, the second plug-in board is plugged into the second cavity, the second connecting board is provided with threaded holes, and the second connecting board is fixed on the end of the composite wallboard without the inner groove by screws , the curved portion is arranged corresponding to the raised portion.
作为进一步的技术方案,所述复合墙板由瓷砖和蜂窝芯复合而成,蜂窝芯的两侧设置有钢板,所述复合墙板的一端设置有用于双侧插接固定件进行插接的内凹槽。As a further technical solution, the composite wallboard is composed of ceramic tiles and honeycomb cores, steel plates are provided on both sides of the honeycomb core, and inner sockets are provided at one end of the composite wallboard for inserting fixed parts on both sides. groove.
作为进一步的技术方案,所述第二容腔的尺寸与第二插接板的尺寸相匹配;所述第一容腔的尺寸与复合墙板具有内凹槽一端的蜂窝芯的尺寸相匹配。As a further technical solution, the size of the second cavity matches the size of the second plug-in board; the size of the first cavity matches the size of the honeycomb core at the end of the composite wallboard having an inner groove.
本发明还提出了上述装配式墙面干挂安装结构的安装方法,包括如下步骤:The present invention also proposes an installation method of the above-mentioned prefabricated wall surface dry-hanging installation structure, including the following steps:
先根据设计节点图,逐个布置调平件,通过底座两侧预留的螺纹孔用螺钉固定在建筑墙体上;依次旋转调平件的伸缩杆,使其前端位于同一垂直平面上,调平基层;再用双侧插接固定件的第一插接板与复合墙板带有内凹槽端插接,并将第一连接板与调平件的上端部螺钉连接固定;复合墙板不含有内凹槽的一端后方螺钉连接连接件的第二连接板,连接件的第二插接板再与双侧插接的固定件第二容腔连接;重复上述安装步骤,完成装配式墙面干挂安装结构的安装。First, arrange the leveling parts one by one according to the design node diagram, and fix them on the building wall with screws through the threaded holes reserved on both sides of the base; rotate the telescopic rods of the leveling parts in turn so that the front ends are on the same vertical plane, and level the The base layer; then use the first plug-in board of the double-sided plug-in fixture to plug in the end of the composite wallboard with an inner groove, and connect and fix the first connecting board with the upper end of the leveling piece with screws; the composite wallboard does not One end containing the inner groove is screwed to the second connection plate of the connector, and the second plug-in plate of the connector is connected to the second cavity of the fixed part inserted on both sides; repeat the above installation steps to complete the prefabricated wall Installation of dry hanging installation structure.
与现有技术相比,本发明技术方案具有如下有益效果:Compared with the prior art, the technical solution of the present invention has the following beneficial effects:
装配式墙面干挂安装结构,运用了调节性能优异且体积较小的调节件,使基层调平方便快捷,可使墙面管线系统置于基层调平结构之中,避免开槽铺设,且走线相对灵活。The prefabricated wall dry-hanging installation structure uses adjusting parts with excellent adjustment performance and small volume, which makes the leveling of the base layer convenient and quick, and allows the wall pipeline system to be placed in the leveling structure of the base layer, avoiding slotting and laying, and The wiring is relatively flexible.
运用插接型连接件安装墙面板,连接结构稳定。安装时利用固定件与连接件长度差,会自动留出伸缩缝,使瓷砖墙面效果好。使用插接和螺接方式安装,方便快捷,且无胶安装,便于板材二次利用。Use plug-in connectors to install wall panels, and the connection structure is stable. When installing, use the length difference between the fixing part and the connecting part to automatically leave expansion joints, so that the effect of the tile wall is good. It is convenient and quick to install by plugging and screwing, and it is installed without glue, which is convenient for the secondary use of the board.
墙面板安装组件都可经过深化后在工厂阶段进行预制生产,降低了材料损耗率,并减少了现场与其他工种的交叉作业时间,组件运输到场后可快速精确组装,保证现场墙面板安装顺利完工。The wall panel installation components can be prefabricated at the factory stage after deepening, which reduces the material loss rate and reduces the cross-working time between the site and other types of work. After the components are transported to the site, they can be assembled quickly and accurately to ensure the smooth completion of the site wall panel installation. .
附图说明Description of drawings
图1为本发明的装配式墙面干挂安装结构平面示意图;Fig. 1 is a schematic plan view of the installation structure of the prefabricated wall surface dry hanging of the present invention;
图2为本发明的装配式墙面干挂安装结构立体示意图;Fig. 2 is the three-dimensional schematic view of the installation structure of the prefabricated wall surface dry hanging of the present invention;
图3为本发明的调平件结构示意图;Fig. 3 is a structural schematic diagram of a leveling member of the present invention;
图4为本发明的双侧插接固定件结构示意图;Fig. 4 is a schematic structural diagram of a double-sided plug-in fixture of the present invention;
图5为本发明的连接件结构示意图;Fig. 5 is a structural schematic diagram of a connector of the present invention;
图中:1、建筑墙体;2、调平件;21、底座;22、调节筒;23、伸缩杆;3、复合墙板;31、内凹槽;32、瓷砖;33、蜂窝芯;34、钢板;4、双侧插接固定件;41、第一插接板;42、第一侧板;43、第一肋板;44、第二侧板;45、第二肋板;46、第一连接板;47、第一容腔;48、第二容腔;49、凸起部;5、连接件;51、第二插接板;52、第二连接板;53、弯曲部;6、管线集成空间。In the figure: 1. Building wall; 2. Leveling parts; 21. Base; 22. Adjusting cylinder; 23. Telescopic rod; 3. Composite wallboard; 31. Inner groove; 32. Ceramic tile; 33. Honeycomb core; 34. Steel plate; 4. Double-sided plug-in fixing piece; 41. First plug-in board; 42. First side plate; 43. First rib plate; 44. Second side plate; 45. Second rib plate; 46 , the first connecting plate; 47, the first cavity; 48, the second cavity; 49, the raised part; 5, the connector; 51, the second plug-in plate; 52, the second connecting plate; ; 6. Pipeline integration space.
具体实施方式Detailed ways
下面通过实施例对本发明的技术方案进行清楚、完整地描述,显然所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solution of the present invention will be described clearly and completely through the following examples. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
如图1-5所示,一种装配式墙面干挂安装结构,包括基层调平结构和墙板安装结构以及两者之间的管线集成空间,具体为:As shown in Figure 1-5, a prefabricated wall dry-hanging installation structure includes the base leveling structure, the wall panel installation structure and the pipeline integration space between the two, specifically:
基层调平结构:由建筑墙体1上分布的调平件2组成的基层调平结构,调平件2包括底座21、调节筒22及伸缩杆23。调节筒22与底座21一体,通过两侧预留孔与建筑墙体1螺接,伸缩杆23位于调节筒22内侧,调节筒22内设置有内螺纹,伸缩杆23外设置有外螺纹,两者螺纹相连。可通过调节伸缩杆23的相对螺距,使置于建筑墙体1局部的多个调平件2前端位于同一垂直平面上,对基层调平。Base leveling structure: a base leveling structure composed of leveling
管线集成空间6:用于布置管线集成系统,管线集成系统可置于基层调平结构之中,位于复合墙板3与建筑墙体1之间。基层调平结构可配合设计调整调平件2高度,以容纳管线系统铺设,满足所需空间要求,使走线相对灵活,且无需开槽铺设。Pipeline integration space 6: for arranging the pipeline integration system, which can be placed in the base leveling structure, between the
墙板安装结构:由双侧插接固定件4、连接件5及复合墙板3组成墙面安装结构。双侧插接固定件4两侧的插接口分别与含内凹槽31的复合墙板3一端插接,及与螺接了连接件5的复合墙板3一侧连接并主动留出瓷砖伸缩缝,双侧插接固定件4其底面置于调平件2上,并螺接固定。Wall panel installation structure: The wall installation structure is composed of double-sided plug-in
具体的,本发明的所述双侧插接固定件4的机构,包括相互配合一体设置的第一插接板41、第一侧板42、第一肋板43、第二侧板44、第二肋板45以及第一连接板46,所述第一插接板41、第一侧板42以及第一肋板43构成容纳复合墙板3端部的第一容腔47,第一插接板41插接与复合墙板3的内凹槽31中;第一肋板43、第二侧板44以及第二肋板45构成容纳连接件5的第二容腔48;第一连接板46连接在第二肋板45上。在第二肋板45的端部还设置有凸起部49,在第一连接板46上设置有螺纹孔,所述第一连接板46通过螺钉固定在调平件2的伸缩杆23的上端部。Specifically, the mechanism of the double-sided inserting
所述连接件5包括第二插接板51、第二连接板52以及第二插接板51和第二连接板52之间的弯曲部53。所述第二插接板51插接于第二容腔48中,第二连接板52上设置有螺纹孔,第二连接板52通过螺钉固定在复合墙板3不含有内凹槽31的一端,所述弯曲部53与所述凸起部49相对应设置。通过弯曲部53与凸起部49的相配合,进一步增加了装配时的牢固性。The connecting
所述复合墙板3由瓷砖32和蜂窝芯33复合而成,蜂窝芯33的两侧设置有钢板34,所述复合墙板3的一端设置有用于双侧插接固定件4进行插接的内凹槽31。复合墙板的各部分连接工艺属于现有技术,可采用现有的工艺或特殊的胶水实现复合。The
在连接时,双侧插接固定件4的一侧插接在所述内凹槽31中,另一侧固定在调平件2上,所述复合墙板3不含有内凹槽31的一端与连接件5固定连接,连接件5的另一端与双侧插接固定件4形成插接固定结构。When connecting, one side of the double-sided plug-in
为了增加装配安装时的匹配性和牢固性,所述第二容腔48的尺寸与第二插接板51的尺寸相匹配;第一容腔47的尺寸与复合墙板3具有内凹槽31一端的蜂窝芯33的尺寸相匹配。In order to increase the compatibility and firmness during assembly and installation, the size of the second cavity 48 matches the size of the
本发明的装配式墙面干挂结构的安装方法为:先根据设计节点图,逐个布置调平件2,通过底座21两侧预留的螺纹孔用螺钉固定在建筑墙体1上;依次旋转调平件2的伸缩杆23,使其前端位于同一垂直平面上,调平基层;再用双侧插接固定件4的第一插接板41与复合墙板3带有内凹槽31端插接,并将第一连接板46与调平件2的上端部螺钉连接固定;复合墙板3不含有内凹槽31的一端后方螺钉连接连接件5的第二连接板52,连接件5的第二插接板51再与双侧插接固定件4的第二容腔48连接;重复上述安装步骤,完成装配式墙面干挂安装结构的安装。The installation method of the prefabricated wall surface dry-hanging structure of the present invention is as follows: first, arrange the leveling
综上,本发明的装配式墙面干挂安装结构,运用了调节性能优异且体积较小的调节件,使基层调平方便快捷,可使墙面管线系统置于基层调平结构之中,避免开槽铺设,且走线相对灵活。To sum up, the prefabricated wall dry-hanging installation structure of the present invention uses an adjusting member with excellent adjustment performance and small volume, which makes the leveling of the base layer convenient and quick, and allows the wall pipeline system to be placed in the leveling structure of the base layer. Avoid laying slots, and the wiring is relatively flexible.
运用插接型连接件安装墙面板,连接结构稳定。安装时利用两侧插接固定件与连接件长度差(连接件插接部分的长度略大于两侧插接固定件插接部分的长度),会自动留出伸缩缝,使瓷砖墙面效果好。使用插接和螺接方式安装,方便快捷,且无胶安装,便于板材二次利用。Use plug-in connectors to install wall panels, and the connection structure is stable. When installing, use the length difference between the plug-in fixing parts on both sides and the connecting parts (the length of the plug-in part of the connecting part is slightly longer than the length of the plug-in parts of the plug-in fixing parts on both sides), and the expansion joints will be automatically reserved, so that the effect of the tile wall is good. . It is convenient and quick to install by plugging and screwing, and it is installed without glue, which is convenient for the secondary use of the board.
墙面板安装组件都可经过深化后在工厂阶段进行预制生产,降低了材料损耗率,并减少了现场与其他工种的交叉作业时间,组件运输到场后可快速精确组装,保证现场墙面板安装顺利完工。The wall panel installation components can be prefabricated at the factory stage after deepening, which reduces the material loss rate and reduces the cross-working time between the site and other types of work. After the components are transported to the site, they can be assembled quickly and accurately to ensure the smooth completion of the site wall panel installation. .
以上所述,仅为本发明的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到变化或替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应以所述权利要求的保护范围为准。The above is only a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Anyone skilled in the art can easily think of changes or substitutions within the technical scope disclosed in the present invention. Should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be determined by the protection scope of the claims.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211388106.4A CN115749186B (en) | 2022-11-08 | 2022-11-08 | Dry hanging installation structure of assembled wall surface and installation method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211388106.4A CN115749186B (en) | 2022-11-08 | 2022-11-08 | Dry hanging installation structure of assembled wall surface and installation method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115749186A true CN115749186A (en) | 2023-03-07 |
| CN115749186B CN115749186B (en) | 2025-07-08 |
Family
ID=85357256
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211388106.4A Active CN115749186B (en) | 2022-11-08 | 2022-11-08 | Dry hanging installation structure of assembled wall surface and installation method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115749186B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116065777A (en) * | 2023-03-09 | 2023-05-05 | 浙江亚厦装饰股份有限公司 | A wall decoration panel installation structure and installation method thereof |
| CN117027303A (en) * | 2023-07-21 | 2023-11-10 | 浙江亚厦装饰股份有限公司 | Assembled wall door side plate system and installation method thereof |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN209975934U (en) * | 2019-03-04 | 2020-01-21 | 浙江亚厦装饰股份有限公司 | Flat fast-assembling wallboard straight angle mounting structure of fine setting |
| CN112554482A (en) * | 2020-12-14 | 2021-03-26 | 浙江亚厦装饰股份有限公司 | Assembly type wallboard mounting structure convenient to detach and replace and using method |
| CN112663886A (en) * | 2020-12-25 | 2021-04-16 | 浙江亚厦装饰股份有限公司 | Hanging composite wallboard installation system and installation method thereof |
| CN113356495A (en) * | 2021-07-14 | 2021-09-07 | 浙江亚厦装饰股份有限公司 | Wallboard mounting structure for wallboard butt joint and mounting method thereof |
| CN113931396A (en) * | 2021-11-22 | 2022-01-14 | 金螳螂精装科技(苏州)有限公司 | Wall mounting structure is maked somebody a mere figurehead to ready-package that wallboard reutilization can |
| CN219033884U (en) * | 2022-11-08 | 2023-05-16 | 浙江亚厦装饰股份有限公司 | Mounting structure is hung futilely to assembled wall |
-
2022
- 2022-11-08 CN CN202211388106.4A patent/CN115749186B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN209975934U (en) * | 2019-03-04 | 2020-01-21 | 浙江亚厦装饰股份有限公司 | Flat fast-assembling wallboard straight angle mounting structure of fine setting |
| CN112554482A (en) * | 2020-12-14 | 2021-03-26 | 浙江亚厦装饰股份有限公司 | Assembly type wallboard mounting structure convenient to detach and replace and using method |
| CN112663886A (en) * | 2020-12-25 | 2021-04-16 | 浙江亚厦装饰股份有限公司 | Hanging composite wallboard installation system and installation method thereof |
| CN113356495A (en) * | 2021-07-14 | 2021-09-07 | 浙江亚厦装饰股份有限公司 | Wallboard mounting structure for wallboard butt joint and mounting method thereof |
| CN113931396A (en) * | 2021-11-22 | 2022-01-14 | 金螳螂精装科技(苏州)有限公司 | Wall mounting structure is maked somebody a mere figurehead to ready-package that wallboard reutilization can |
| CN219033884U (en) * | 2022-11-08 | 2023-05-16 | 浙江亚厦装饰股份有限公司 | Mounting structure is hung futilely to assembled wall |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116065777A (en) * | 2023-03-09 | 2023-05-05 | 浙江亚厦装饰股份有限公司 | A wall decoration panel installation structure and installation method thereof |
| CN117027303A (en) * | 2023-07-21 | 2023-11-10 | 浙江亚厦装饰股份有限公司 | Assembled wall door side plate system and installation method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115749186B (en) | 2025-07-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN219033884U (en) | Mounting structure is hung futilely to assembled wall | |
| CN111485694A (en) | Prefabricated wall structure | |
| CN115749186B (en) | Dry hanging installation structure of assembled wall surface and installation method thereof | |
| CN102425262B (en) | ceiling structure | |
| CN207700595U (en) | A kind of assembled shingle nail hanging structure of shingle nail notching construction | |
| CN205314448U (en) | Side fascia anchor assembly | |
| CN112443094B (en) | Wall internal corner ceramic tile mounting structure and mounting method | |
| CN112663886B (en) | Hanging composite wallboard mounting system and mounting method thereof | |
| CN114991408A (en) | A wall panel flat connection structure and installation method thereof | |
| CN221856068U (en) | A PSC ceramic tile composite board installation and fixing structure | |
| CN103382748B (en) | A kind of Terracotta panel curtain wall installation structure | |
| CN112227641A (en) | Toilet large-plate ground system and installation method thereof | |
| CN214498157U (en) | Wall body reentrant corner ceramic tile mounting structure | |
| CN218492941U (en) | Prefabricated wall panel installation structure at the male corner position | |
| CN218061140U (en) | A waterproof ceramsite wallboard | |
| CN213682965U (en) | Assembled combination sound insulation wallboard | |
| CN110565845A (en) | But fast assembly's multipurpose keel structure | |
| CN206667553U (en) | A kind of hanging molding decorative furred ceiling of polyhedron | |
| CN216920996U (en) | Assembly type wall body structure based on pipeline separation | |
| CN213682549U (en) | A pre-installation structure for prefabricated wall panels | |
| CN114991414A (en) | A kind of prefabricated kitchen wall structure and installation method | |
| CN210134614U (en) | Horizontal assembled structure of mating formation of ground finish material | |
| CN209744310U (en) | A finished lamp trough | |
| CN220167224U (en) | Energy-saving heat-preserving wall | |
| CN219548088U (en) | Fast-assembling formula double-sided composite wall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |