Reservoir box culvert foundation excavation construction equipment
Technical Field
The invention belongs to the field of reservoir box culvert construction equipment, and particularly relates to reservoir box culvert foundation excavation construction equipment.
Background
In the construction process of the pumped storage reservoir, a box culvert is required to be paved, for example, the box culvert for drainage is paved at the bottom of a reservoir slag field, foundation excavation is required before the box culvert is paved, a groove is formed first, the box culvert is manufactured in a section-by-section cast-in-place mode in the groove, and then earth return landfill is carried out. The two side walls of the groove form inclined side slopes, which mainly prevent soil layer collapse from damaging workers and box culverts in cast-in-situ, and are convenient for workers and building materials to enter the groove during the box culvert cast-in-situ. The existing equipment for excavating the groove is an excavator, the excavator firstly excavates the groove with the square section along the advancing direction of the groove, the efficiency is higher, but when the side slope is excavated on the two vertical side walls of the groove, the action of the excavator bucket is difficult to continuously excavate along a slope, repeated fine adjustment and point-by-point excavation are required, the efficiency is very low, and the overall excavation efficiency of the groove is lower.
Disclosure of Invention
The invention aims to provide reservoir box culvert foundation excavation construction equipment. The invention has the advantage of improving the overall excavation efficiency of the groove.
The technical scheme includes that the reservoir box culvert foundation excavation construction equipment comprises a bottom plate, pressing plates are arranged on two sides of the bottom plate, a driving mechanism is arranged on each pressing plate, a through hole is formed in the front of each pressing plate, a plate chain type conveyor is arranged in each through hole, a frame of each conveyor is fixed with each pressing plate, a scraper plate is arranged on a plate chain of each conveyor, the outer side ends of the scraper plates are wavy, a plurality of scraper plates move to form a hooked digging surface, and the hooked digging surface is arranged on the inner side of each pressing plate.
In the aforementioned reservoir box culvert foundation excavation construction equipment, actuating mechanism includes the skeleton board of slope, and the upper end of skeleton board is articulated with the inside wall on clamp plate upper portion, is equipped with first hydro-cylinder between skeleton board and the clamp plate, and the lower extreme of two skeleton boards is articulated together.
In the aforementioned reservoir box culvert foundation excavation construction equipment, the bottom of bottom plate is equipped with a plurality of indent regions, is equipped with the gyro wheel in the indent region, is equipped with first pivot on the gyro wheel, and two lateral walls in indent region are passed respectively at the both ends of first pivot.
In the reservoir box culvert foundation excavation construction equipment, the front side of the pressing plate is provided with the guide plate with the front end inclined inwards.
In the reservoir box culvert foundation excavation construction equipment, two skeleton plates are hinged through a second rotating shaft, a plurality of bearings are arranged on the second rotating shaft, a second oil cylinder fixed with a bottom plate is arranged below the bearings, and the output end of the second oil cylinder is connected with the bearings.
In the reservoir box culvert foundation excavation construction equipment, the inner side of the pressing plate is provided with the vibrating motor.
In the reservoir box culvert foundation excavation construction equipment, a part of chain plates of the conveyor are provided with transverse raking plates, the rest of chain plates are provided with vertical cutting plates, and the height of each cutting plate is greater than that of each raking plate.
In the reservoir box culvert foundation excavation construction equipment, the chain plates provided with the raking plates and the chain plates provided with the cutting plates are distributed at intervals.
Compared with the prior art, the invention is matched with the excavator to excavate the foundation, firstly, the excavator is used for excavating the trench with the square section, when the construction is carried out on the two vertical side walls of the trench, the oil cylinder is used for driving the pressing plate to outwards rotate, in the process of rotating the pressing plate, the two conveyors are used for driving the raking plate to rotate, soil is raked out upwards, a flat side slope can be formed, the excavation efficiency is high, meanwhile, the pressing plate is used for compacting the side slope, the side slope is firm, collapse is not easy to happen, the side slope excavation angle can be smaller, the excavation engineering quantity is smaller, and the excavation efficiency is further improved. Therefore, the invention has the advantage of improving the overall excavation efficiency of the groove.
Drawings
Fig. 1 is a front view of the present invention.
Fig. 2 is a top view of the invention with the drive mechanism removed.
Fig. 3 is a left side view of the present invention.
Fig. 4 is a schematic view of fig. 1 at A-A.
Fig. 5 is a schematic front view of the conveyor.
Fig. 6 is a schematic view of the present invention compacting a side slope in a trench.
The drawing comprises a 1-bottom plate, a 2-pressing plate, a 3-through hole, a 4-conveyor, a 5-raking plate, a 6-skeleton plate, a 7-first oil cylinder, an 8-concave area, 9-rollers, 10-first rotating shafts, 11-guide plates, 12-second rotating shafts, 13-bearings, 14-second oil cylinders, 15-vibrating motors, 16-cutting plates, 17-first connecting plates and 18-second connecting plates.
Detailed Description
The invention is further illustrated by the following figures and examples, which are not intended to be limiting.
Examples. The utility model provides a reservoir box culvert foundation excavation construction equipment, as shown in fig. 1, including bottom plate 1, the both sides of bottom plate 1 all are equipped with clamp plate 2, are equipped with actuating mechanism on clamp plate 2, and the front portion of clamp plate 2 is equipped with through-hole 3, is equipped with plate chain conveyer 4 in the through-hole 3, and the frame of conveyer 4 is fixed with clamp plate 2, is equipped with on the plate chain of conveyer 4 and takes off flitch 5, takes off flitch 5's outside end (being the soil-removing end) and is the wave, and a plurality of take off flitch 5 movements form the hook and dig the face, and the hook digs the face in clamp plate 2's inboard.
The driving mechanism comprises an inclined framework plate 6, the framework plate 6 is formed by welding a plurality of square steel pipes, the upper end of the framework plate 6 is hinged with the inner side wall on the upper portion of the pressing plate 2, a plurality of first oil cylinders 7 which are arranged side by side are arranged between the framework plate 6 and the pressing plate 2, and the lower ends of the two framework plates 6 are hinged together.
The bottom of the bottom plate 1 is provided with a plurality of concave areas 8, rollers 9 are arranged in the concave areas 8, first rotating shafts 10 are arranged on the rollers 9, and two ends of each first rotating shaft 10 respectively penetrate through two side walls of the concave areas 8. The roller 9 facilitates the movement of the invention, the roller 9 is arranged in the concave area 8, the distance between the bottom plate 1 and the bottom surface of the groove can be reduced, the excavation depth of the side slope can be larger, and the excavation effect is improved.
The front side of the pressing plate 2 is provided with a guide plate 11 with the front end inclined inwards. The guide plate 11 is used for guiding the present invention when moving forward.
Two skeleton boards 6 are hinged through a second rotating shaft 12, a plurality of first connecting plates 17 are arranged on the second rotating shaft 12, the first connecting plates 17 are fixed with the bottom of one skeleton board 6, one side of each first connecting plate 17 is provided with a second connecting plate 18 fixed with the other skeleton board 6, the second rotating shaft 12 sequentially penetrates through all the first connecting plates 17 and all the second connecting plates 18, a plurality of bearings 13 are arranged on the second rotating shaft 12, a second oil cylinder 14 fixed with the bottom board 1 is arranged below the bearings 13, and the output end of each second oil cylinder 14 is connected with the bearings 13.
The inner side of the pressing plate 2 is provided with a vibration motor 15. The vibration motor 15 is used for further compacting the slope, the vibration motor 15 being turned on only when the pressing plate 2 compacts the slope.
A part of chain plates of the conveyor 4 are provided with transverse raking plates 5, and the rest of chain plates are provided with a plurality of vertical cutting plates 16, wherein the height of each cutting plate 16 is greater than that of each raking plate 5.
The chain plates provided with the raking plates 5 and the chain plates provided with the cutting plates 16 are arranged at intervals.
The working principle is that firstly, a trench with a square section is excavated by an excavator, then the trench is put into the trench for secondary construction, and the trench is pulled by the excavator or other power vehicles to move along the trench.
The second oil cylinder 14 and the first oil cylinder 7 extend, the pressing plate 2 is driven to outwards overturn through the skeleton plate 6, the conveyor 4 drives the scraping plate 5 and the cutting plate 16 to rotate, the cutting plate 16 cuts loose soil, the comb is simultaneously used for scraping out large stones in the soil in advance, the scraping plate 5 scrapes out the loose soil upwards, and when the second oil cylinder 14 and the first oil cylinder 7 extend to the maximum position, a section of side slope is formed. After the second oil cylinder 14 and the first oil cylinder 7 shrink, the whole device moves forwards for a certain distance, the second oil cylinder 14 and the first oil cylinder 7 stretch out again, a section of side slope is scraped again, meanwhile, the pressing plate 2 is in contact with the side slope scraped before, compaction is carried out, and the compaction force is further enhanced by the vibrating motor 15. Because the outer side end of the raking plate 5 is wavy, the side slope raked out by the raking plate 5 is wavy, and can be extruded more compactly when being extruded by the pressing plate 2.
In the process of continuous advancing, new slopes are continuously excavated, and the new slopes are compacted in the next advancing process.