CN115726285A - Method for simply erecting multi-connected multi-span steel truss bridge in sequence - Google Patents
Method for simply erecting multi-connected multi-span steel truss bridge in sequence Download PDFInfo
- Publication number
- CN115726285A CN115726285A CN202211569807.8A CN202211569807A CN115726285A CN 115726285 A CN115726285 A CN 115726285A CN 202211569807 A CN202211569807 A CN 202211569807A CN 115726285 A CN115726285 A CN 115726285A
- Authority
- CN
- China
- Prior art keywords
- steel truss
- truss girder
- bridge
- complete
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 89
- 239000010959 steel Substances 0.000 title claims abstract description 89
- 238000000034 method Methods 0.000 title claims abstract description 30
- 238000010276 construction Methods 0.000 claims abstract description 24
- 238000009434 installation Methods 0.000 claims abstract description 20
- 238000005520 cutting process Methods 0.000 claims abstract description 11
- 238000006243 chemical reaction Methods 0.000 claims abstract description 4
- 238000004364 calculation method Methods 0.000 claims description 3
- 238000011144 upstream manufacturing Methods 0.000 claims description 3
- 239000011248 coating agent Substances 0.000 claims description 2
- 238000000576 coating method Methods 0.000 claims description 2
- 238000004519 manufacturing process Methods 0.000 claims description 2
- 238000005498 polishing Methods 0.000 claims 1
- 239000000463 material Substances 0.000 abstract description 6
- 239000003973 paint Substances 0.000 abstract 1
- 239000002131 composite material Substances 0.000 description 5
- 238000010586 diagram Methods 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000013461 design Methods 0.000 description 3
- 238000007667 floating Methods 0.000 description 3
- 238000010422 painting Methods 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000003754 machining Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
一种多联多跨钢桁梁桥先连续后简支架设方法,包括以下步骤:①在工厂内预制钢桁梁单元;②首架联起架段第一桥墩和第二桥墩之间架设多组临时拼装支架;③履带吊站位于已有栈桥上,在拼装支架及临时支墩上拼装起始段钢桁梁,完成第一跨钢桁梁拼装;④利用桥面吊机安装起吊范围内钢桁梁杆件完成该联钢桁梁安装;⑤桥面吊机前移至相邻联钢桁梁上,继续安装该联钢桁梁至相邻桥墩,完成整垮安装;利用半自动切割机切割联与联交界处的组合杆件,打磨、涂装,完成相邻两联钢桁梁安装由连续至简支的受力体系转换;⑥重复第四步~第五步,按照两联连做的方法,完成剩余联钢梁的施工。本发明施工周期短、节省人工和材料成本、安全高效。
A multi-connection and multi-span steel truss girder bridge construction method first continuous and then simply supported, comprising the following steps: ① prefabricating steel truss girder units in a factory; ② erecting multiple Set up temporary assembly brackets; ③The crawler crane station is located on the existing trestle, assemble the steel truss beams at the initial section on the assembly brackets and temporary piers, and complete the assembly of the first span steel truss girders; ④Use the bridge deck crane to install within the hoisting range Steel truss members complete the installation of the joint steel truss girder; ⑤The bridge deck crane moves forward to the adjacent steel truss girder, and continues to install the joint steel truss girder to the adjacent pier to complete the whole collapse installation; use the semi-automatic cutting machine Cut the combined rods at the junction of the joints, grind and paint, and complete the conversion of the stress system of the installation of two adjacent steel truss beams from continuous to simply supported; ⑥Repeat steps The method of doing is to complete the construction of the remaining joint steel beams. The invention has a short construction period, saves labor and material costs, and is safe and efficient.
Description
技术领域technical field
本发明涉及公路桥梁施工技术领域,尤其是涉及一种多联多跨钢桁梁桥先连续后简支架设方法。The invention relates to the technical field of highway bridge construction, in particular to a multi-connection and multi-span steel truss girder bridge erection method which is continuous first and then simply supported.
背景技术Background technique
随着我国城市建设的高速发展和钢结构桥梁疲、焊接、振动及桥梁上下结构设计、制造、施工等方技术的日益成熟与发展,钢结构桥梁已广泛应用铁路、公路、公轨两用桥及人行天桥等大跨度桥梁领域,是目前国家大力推广的结构类型。With the rapid development of urban construction in my country and the increasing maturity and development of steel structure bridge fatigue, welding, vibration, and bridge upper and lower structure design, manufacturing, and construction technologies, steel structure bridges have been widely used in railways, highways, and public rail dual-purpose bridges. The field of long-span bridges such as pedestrian bridges and pedestrian bridges is a structure type that the country is vigorously promoting at present.
传统钢桁梁多采用大型浮吊整孔吊装、悬臂安装及顶推施工等方式架设。浮吊整孔吊装多适用于深水及大型设备可以进出的区域;悬臂拼装多适用于多跨连续标准断面钢桁梁;顶推施工多适用于直线标准断面钢桁梁。对于简支钢桁梁传统方法多采用搭设双侧栈桥安装跨墩龙门吊或采用大型浮吊整体吊装等方法,上述方法材料投入大、工期长,对于浅水区域等大型设备无法进入区域不能适用。传统的悬臂拼装架设方法对于单联多跨连续钢桁梁较适用,但对于多联施工时,每一联起始段只能采用支架法架设起始段钢桁梁,增加工期和材料成本,无法形成连续作业,整体施工效率低。Traditional steel truss girders are mostly erected by means of large-scale floating crane hoisting, cantilever installation and jacking construction. Floating crane hoisting is mostly suitable for deep water and areas where large equipment can enter and exit; cantilever assembly is mostly suitable for multi-span continuous standard section steel truss beams; jacking construction is mostly suitable for straight line standard section steel truss beams. For simply supported steel truss girders, the traditional method usually adopts methods such as erecting double-sided trestle bridges and installing cross-pier gantry cranes or using large-scale floating cranes for overall hoisting. The above-mentioned methods require large material investment and long construction periods, and are not suitable for areas where large equipment cannot enter such as shallow water areas. The traditional cantilever assembly erection method is more suitable for single-joint multi-span continuous steel truss girders, but for multi-joint construction, the initial section of each joint can only be erected by the bracket method, which increases the construction period and material costs. Continuous operation cannot be formed, and the overall construction efficiency is low.
因此有必要提供一种钢桁梁桥先连续后简支架设方法解决以上问题。Therefore, it is necessary to provide a steel truss girder bridge that is first continuous and then simply supported to solve the above problems.
发明内容Contents of the invention
本发明需要解决的技术问题是提供一种施工周期短、节省人工和材料成本、安全高效的多联钢桁梁桥先连续后简支架设方法。The technical problem to be solved by the present invention is to provide a method for constructing a multi-connected steel truss girder bridge that is continuous first and then simply supported, with a short construction period, saving labor and material costs, and being safe and efficient.
为解决以上问题,本发明的技术方案是:一种多联多跨钢桁梁桥先连续后简支架设方法,架设N联钢桁梁,N为大于或等于2的整数,每联钢桁梁有若干个桥墩,其特征在于,该方法包括以下步骤:In order to solve the above problems, the technical solution of the present invention is: a multi-connection multi-span steel truss girder bridge is first continuous and then simply supported, erecting N-connection steel truss girders, where N is an integer greater than or equal to 2, and each connection of steel truss The beam has several piers, characterized in that the method comprises the steps of:
①在工厂内预制钢桁梁单元,包括联与联交界处的组合杆件,然后运输至现场便于安装的位置;① Steel truss units are prefabricated in the factory, including the combined members at the junction of joints and joints, and then transported to the site for easy installation;
②首架联起架段第一桥墩和第二桥墩之间架设多组临时拼装支架,并在第二桥墩后每相邻两个桥墩之间的跨中位置架设一组临时支墩;②Multiple sets of temporary assembly supports shall be erected between the first pier and the second pier of the first joint erection section, and a set of temporary support pier shall be erected at the mid-span position between every two adjacent pier after the second pier;
③履带吊站位于已有栈桥上,在拼装支架及临时支墩上拼装起始段钢桁梁,完成第一跨钢桁梁拼装,并在第一跨钢桁梁上拼装两台桥面吊机;③The crawler crane station is located on the existing trestle bridge, assemble the steel truss girder of the initial section on the assembly bracket and temporary pier, complete the assembly of the steel truss girder of the first span, and assemble two bridge deck cranes on the steel truss girder of the first span machine;
④利用桥面吊机安装起吊范围内钢桁梁杆件,通过悬臂拼装的方式完成该联钢桁梁安装,其中包括联与联交界处组合杆件的安装,钢桁梁均放置在临时支座上,且抄垫预设高度;④ Use the bridge deck crane to install the steel truss members within the lifting range, and complete the installation of the joint steel truss girders by cantilever assembly, including the installation of the combined members at the junction of the joints and the joints. The steel truss girders are placed on temporary supports On the seat, and the preset height of the pad;
⑤桥面吊机前移至相邻联钢桁梁上,继续安装该联钢桁梁至相邻桥墩,完成整垮安装;利用半自动切割机切割联与联交界处的组合杆件,打磨、涂装,完成相邻两联钢桁梁安装由连续至简支的受力体系转换;⑤ The bridge deck crane moves forward to the adjacent steel truss girder, and continues to install the steel truss girder to the adjacent pier to complete the whole collapse installation; use a semi-automatic cutting machine to cut the combined rods at the junction of the joint and the joint, grind, Coating, to complete the conversion of the load-bearing system from continuous to simply supported in the installation of two adjacent steel truss girders;
⑥重复第四步~第五步,按照两联连做的方法,完成剩余联钢梁的施工。⑥Repeat the fourth to fifth steps, and complete the construction of the remaining joint steel beams according to the method of doing two joints.
优选的,所述联与联交界处的组合杆件由伸缩缝处两侧的上弦杆和下弦杆分别做成组合杆件。Preferably, the composite rod at the junction of the joint and the joint is made of the upper chord and the lower chord on both sides of the expansion joint to form a composite rod respectively.
优选的,所述起始段拼装支架为单排管桩,起始段两桥墩之间拼装支架为3~4组,每组受力点均在下弦杆节点处。Preferably, the assembled support in the initial section is a single row of pipe piles, and there are 3 to 4 sets of assembled supports between the two piers in the initial section, and the stress points of each set are at the node of the lower chord.
优选的,所述钢桁梁抄垫的预设高度为200~500mm。Preferably, the preset height of the steel truss pad is 200-500mm.
优选的,所述相邻两桥墩之间的临时支墩横向距离为上下游主桁弦件之间的中心距离,且该所述临时支墩采用8根钢管和连接系组成,钢管及连接系选型需经过计算取得。Preferably, the lateral distance of the temporary pier between two adjacent piers is the center distance between the upstream and downstream main chords, and the temporary pier is composed of 8 steel pipes and connecting systems, the steel pipes and connecting systems The selection needs to be obtained through calculation.
优选的,所述桥面吊机为单臂架全回转式旋转吊机,28m时最大起重为50吨,旋转角度360°。Preferably, the bridge deck crane is a single-arm full-slewing rotary crane with a maximum lifting capacity of 50 tons at a height of 28m and a rotation angle of 360°.
本发明的有益效果是:本发明适用于深水、浅水等多种外部环境施工,能够解决传统悬臂拼装跨联施工无法形成连续作业问题,减少了搭设各联起始段拼装支架、大型机械设备等材料投入,仅需搭设一组临时墩,缩短了施工周期,节约了成本,极大的提高了施工速度,且安全可靠性好。The beneficial effects of the present invention are: the present invention is suitable for construction in various external environments such as deep water and shallow water, can solve the problem that the traditional cantilever assembly cross-connection construction cannot form continuous operations, and reduces the need for erecting the initial section assembly brackets of each connection, large-scale mechanical equipment, etc. With the input of materials, only a set of temporary piers needs to be built, which shortens the construction period, saves costs, greatly improves the construction speed, and has good safety and reliability.
附图说明Description of drawings
图1为步骤3施工结构示意图;Fig. 1 is the schematic diagram of construction structure of
图2为步骤4施工结构示意图;Fig. 2 is the schematic diagram of construction structure of
图3为步骤5施工结构示意图;Fig. 3 is the schematic diagram of construction structure of
图4为图2中A的放大示意图;Fig. 4 is the enlarged schematic view of A in Fig. 2;
图5为图3中B的放大示意图;Fig. 5 is the enlarged schematic diagram of B in Fig. 3;
图6为本发明的桥面吊机起重曲线示意图;Fig. 6 is a schematic diagram of the lifting curve of the bridge deck crane of the present invention;
图中:1-桥面吊机;2-钢桁梁;21-前一联上弦杆;22-后一联下弦杆;23-前一联下弦杆;24-后一联下弦杆;25-上弦杆组合杆件;26-下弦杆组合杆件;3-拼装支架;4-临时支墩;5-桥墩;51-第一桥墩;52-第二桥墩;53-第三桥墩;54-第四桥墩;In the figure: 1-deck crane; 2-steel truss girder; 21-the first upper chord; 22-the last lower chord; 23-the first lower chord; 24-the last lower chord; 25- Upper chord composite member; 26-lower chord composite member; 3-assembled bracket; 4-temporary support pier; 5-bridge pier; 51-first bridge pier; 52-second bridge pier; four piers;
具体实施方式Detailed ways
以下面结合附图和具体实例对本发明的施工方法做进一步的详细描述,但本发明不局限于以下实施例。The construction method of the present invention will be further described in detail below in conjunction with the accompanying drawings and specific examples, but the present invention is not limited to the following examples.
如图1-6所示,一种钢桁梁桥先连续后简支架设方法,架设N联钢桁梁,N为大于或等于2的整数,每联钢桁梁有若干个桥墩。本实施方式中,以N取2为例进行说明,每联均为多跨连续钢桁梁,包括若干个桥墩,每跨包含7个节间钢桁梁。本发明包括以下步骤:As shown in Figure 1-6, a steel truss girder bridge is first continuous and then simply supported. N steel truss girders are erected, N is an integer greater than or equal to 2, and each steel truss girder has several piers. In this embodiment, take N as 2 as an example for illustration, each link is a multi-span continuous steel truss girder, including several piers, and each span includes 7 internode steel truss girders. The present invention comprises the following steps:
①在工厂内预制钢桁梁2单元,包括联与联交界处的组合杆件25、26,然后运输至现场便于安装的位置;① Steel
本实施方式中,所述联与联交界处的组合杆件25由伸缩缝处两侧的上弦杆21和22组成,所述联与联交界处的组合杆件26由伸缩缝处两侧的下弦杆23和24组成,组合杆件25、26的实腹式钢板均在厂内一次切割下料、组装、焊接完成,上弦杆21和22之间和下弦杆23和24的有效组合长度根据伸缩缝尺寸取得,采用数控火焰切割机、等离子切割机和机加工来保证零件尺寸,且内侧采用圆弧过渡,以消除应力集中。In this embodiment, the combined
②首架联起架段第一桥墩51和第二桥墩52之间架设多组临时拼装支架3,并在第二桥墩51后每相邻两个桥墩5之间的跨中位置架设一组临时支墩4;② Multiple sets of
本实施方式中,所述起始段拼装支架3为单排管桩,起始段两桥墩51和52之间拼装支架3为3~4组,每组受力点均在下弦杆节点处。In this embodiment, the assembled
本实施方式中,所述相邻两桥墩之间的临时支墩4横向距离为上下游主桁弦件之间的中心距离,且该所述临时支墩4采用8跟钢管和连接系组成,钢管及连接系选型需经过计算取得。In this embodiment, the lateral distance of the
③履带吊站位于已有栈桥上,在拼装支架3及临时支墩4上拼装起始段钢桁梁2,完成第一跨钢桁梁2拼装,并在第一跨钢桁梁上拼装两台桥面吊机1;③The crawler crane station is located on the existing trestle, assemble the
本实施方式中,拼装第一桥墩51和第二桥墩52之间起始段钢桁梁2的具体步骤为:下弦杆→下层铁路桥面系→腹杆→上弦杆→上层公路桥面系In this embodiment, the specific steps for assembling the
④利用桥面吊机1安装起吊范围内钢桁梁2杆件,通过悬臂拼装的方式完成该联钢桁梁2安装,其中包括联与联交界处组合杆件25、26的安装,钢桁梁均放置在临时支座上,且抄垫预设高度;④Use the
本实施方式中,起吊前事先核实杆件重力是否在桥面吊机1相应吊距的额定起重力以内,试吊后无意外再提升;拼装悬臂拼装段第二桥墩52和第三桥墩53之间钢桁梁2的具体步骤为:下弦杆→腹杆→上弦杆→下层铁路桥面系→上层公路桥面系In this embodiment, before lifting, check in advance whether the gravity of the bar is within the rated lifting force of the corresponding lifting distance of the
本实施方式中,所述钢桁梁2抄垫的预设高度为200~500mm,预设高度应满足半自动切割机的工作要求。In this embodiment, the preset height of the
⑤桥面吊机1前移至相邻联钢桁梁上,继续安装该联钢桁梁2至相邻桥墩54,完成整垮安装;利用半自动切割机切割联与联交界处的组合杆件25、26,打磨、涂装,完成相邻两联钢桁梁安装由连续至简支的受力体系转换;⑤ The
本实施方式中,可将半自动切割机轨道吸附在钢桁梁2上,在气温较低且相对稳定时间沿切割线将组合杆件25、26整体切割分离,按照原设计文件要求对切割部位进行打磨、涂装和防腐处理。In this embodiment, the track of the semi-automatic cutting machine can be adsorbed on the
⑥重复第四步~第五步,按照两联连做的方法,即先将剩余联伸缩缝处两侧的上弦杆21和22、下弦杆23和24,在工厂内加工成组合杆件25、26,按照悬臂拼装的方法架设完成相邻联首跨,接着切割组合杆件25、26,完成由连续至简支的受力体系转换,最后通过千斤顶将钢桁梁2整体回落至设计标高,调整纵横平面位置,安装永久支座,完成剩余联钢桁梁的安装。⑥Repeat steps 4 to 5, and follow the method of two joints, that is, first process the
以上步骤中所述桥面吊机1为单臂架全回转式旋转吊机,如图6所示,28m时最大起重为50吨,旋转角度360°。The
相较于现有技术,本发明的钢桁梁先连续后简支架设方法,消除了钢桁梁2悬臂架设中跨联无法连续作业,需搭设大量拼装支架3的问题,仅需搭设一组临时墩,大幅降低了辅助措施材料和机械设备的投入,节约成本,提高施工效率。Compared with the prior art, the erection method of the steel truss girder in the present invention is continuous first and then simply supported, which eliminates the problem that the
以上结合附图对本发明进行了示例性描述,显然本发明具体实现并不受上述方式的限制,只要采用了本发明的方法构思和技术方案进行的各种改进,或未经改进直接应用于其他场合的,均在本发明的保护范围之内。The present invention has been exemplarily described above in conjunction with the accompanying drawings. Obviously, the specific implementation of the present invention is not limited by the above-mentioned manner, as long as various improvements of the method concept and technical solutions of the present invention are adopted, or directly applied to other methods without improvement. Occasions, all within the protection scope of the present invention.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211569807.8A CN115726285A (en) | 2022-12-08 | 2022-12-08 | Method for simply erecting multi-connected multi-span steel truss bridge in sequence |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211569807.8A CN115726285A (en) | 2022-12-08 | 2022-12-08 | Method for simply erecting multi-connected multi-span steel truss bridge in sequence |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115726285A true CN115726285A (en) | 2023-03-03 |
Family
ID=85300585
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211569807.8A Pending CN115726285A (en) | 2022-12-08 | 2022-12-08 | Method for simply erecting multi-connected multi-span steel truss bridge in sequence |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115726285A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116357086A (en) * | 2023-04-14 | 2023-06-30 | 中建八局第三建设有限公司 | A construction method for a large-span steel truss basin-type support |
| CN116892172A (en) * | 2023-06-26 | 2023-10-17 | 中铁山桥集团有限公司 | A method for erecting segments of a multi-span continuous steel truss bridge co-constructed by public rail |
| CN117385767A (en) * | 2023-11-14 | 2024-01-12 | 中国建筑第六工程局有限公司 | A construction method for a long-line multi-link steel truss bridge |
-
2022
- 2022-12-08 CN CN202211569807.8A patent/CN115726285A/en active Pending
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116357086A (en) * | 2023-04-14 | 2023-06-30 | 中建八局第三建设有限公司 | A construction method for a large-span steel truss basin-type support |
| CN116892172A (en) * | 2023-06-26 | 2023-10-17 | 中铁山桥集团有限公司 | A method for erecting segments of a multi-span continuous steel truss bridge co-constructed by public rail |
| CN117385767A (en) * | 2023-11-14 | 2024-01-12 | 中国建筑第六工程局有限公司 | A construction method for a long-line multi-link steel truss bridge |
| CN117385767B (en) * | 2023-11-14 | 2026-02-24 | 中国建筑第六工程局有限公司 | Construction method of long-line multi-connection steel truss bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN115726285A (en) | Method for simply erecting multi-connected multi-span steel truss bridge in sequence | |
| CN114214920B (en) | Large-span double-layer steel truss arch bridge and its construction method | |
| CN102108676B (en) | Arch bridge construction method for combined beam-steel arch combined system | |
| CN216640288U (en) | Tower-passing sliding platform for steel box girder of cable-stayed bridge | |
| CN106149576B (en) | On removed and construction method of installation across both wired bridge whole groups | |
| CN110847062A (en) | Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory | |
| CN110373988A (en) | The big segment steel truss girder and manufacturing technology of a kind of band pair purlin | |
| CN102352604A (en) | Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof | |
| CN115012318B (en) | A construction method for reverse installation of a double-deck steel truss arch bridge | |
| CN111962372A (en) | Road-rail combined construction steel web member double-combination continuous truss girder and construction method thereof | |
| CN216891927U (en) | Large-span double-layer combined construction steel truss arch bridge | |
| CN114263114A (en) | Construction system and construction method of large-section steel box girder | |
| CN110184903B (en) | A truss-type prefabricated pipe column assembled bridge pier | |
| CN116892172B (en) | Method for erecting sections of public rail co-construction multi-span continuous steel truss bridge | |
| CN209652741U (en) | A long-span viaduct across railway stations | |
| CN213571497U (en) | Large-span truss-type railway temporary beam structure | |
| CN212335738U (en) | Double-combination continuous truss girder of combined steel web member for highway and railway construction | |
| CN112095798B (en) | Super high-rise double-layer super large cantilever steel structure | |
| CN115467237B (en) | Construction method of "machine-to-beam" steel structure bridge | |
| CN217678547U (en) | Large-span steel trestle structure | |
| CN215164781U (en) | Cast-in-place roof beam construction support of river or road bridge strides | |
| CN215925697U (en) | Truss type mobile platform for welding construction of steel beam sections | |
| CN212077591U (en) | Component hoisting walking foundation under complex environment of large railway station house | |
| CN215629403U (en) | Supporting system for temporary via hole of bridge girder erection machine | |
| CN109252455B (en) | Cantilever assembling construction method of multi-main-truss steel truss girder structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |
