CN115653095A - Method for quickly building assembled frame structure - Google Patents

Method for quickly building assembled frame structure Download PDF

Info

Publication number
CN115653095A
CN115653095A CN202211431812.2A CN202211431812A CN115653095A CN 115653095 A CN115653095 A CN 115653095A CN 202211431812 A CN202211431812 A CN 202211431812A CN 115653095 A CN115653095 A CN 115653095A
Authority
CN
China
Prior art keywords
prefabricated
frame structure
steel bar
steel
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211431812.2A
Other languages
Chinese (zh)
Inventor
彭光磊
李腾
施红兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN202211431812.2A priority Critical patent/CN115653095A/en
Publication of CN115653095A publication Critical patent/CN115653095A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a rapid construction method of an assembled frame structure, which comprises the following steps: step 1: the integrated construction and the component prefabrication of the foundation bearing platform: the prefabricated parts comprise prefabricated main beams and prefabricated secondary beams; the integrated construction of the foundation bearing platform sequentially comprises bearing platform steel bar installation, pre-buried galvanized corrugated pipes, concrete pouring and galvanized corrugated pipe plugging; step 2: the vertical structure steel bars and the template are assembled and installed: sequentially processing a steel bar, binding a steel bar cage, hoisting the steel bar cage and fixing the steel bar cage and a template; and step 3: hoisting the template and the prefabricated part in sequence by using hoisting equipment and installing; and 4, step 4: taking the prefabricated part as a stress fulcrum, arranging a detachable conversion member, a temporary consolidation steel truss and the prefabricated part to cooperatively bear force to form a floor bearing plate structure without vertical support; and 5: and (5) constructing cast-in-place layer steel bars and pouring concrete. The invention reduces the field construction workload, improves the construction efficiency and shortens the construction period.

Description

一种装配式框架结构快速建造方法A rapid construction method of prefabricated frame structure

技术领域technical field

本发明涉及建筑施工领域,尤其涉及一种装配式框架结构快速建造方法。The invention relates to the field of building construction, in particular to a rapid construction method of an assembled frame structure.

背景技术Background technique

目前建筑行业的设计与施工仍以混凝土现浇施工为主,相对于其他行业存在着工业化程度严重不足、行业生产效率低下、建设工程质量较为粗糙、建筑材料损耗率较多及对周边造成环境污染等诸多问题。此外,随着钢产量及技术日益增强,以及人力成本的不断增加,装配式建筑的建造优势越发突出,而结合了装配式建筑和钢结构的优点的装配式钢结构住宅,成为了住宅建筑发展的重要趋势。At present, the design and construction of the construction industry are still dominated by concrete cast-in-place construction. Compared with other industries, there are serious shortages of industrialization, low production efficiency, relatively rough construction quality, high loss rate of building materials, and environmental pollution to the surrounding area. and many other issues. In addition, with the increasing steel production and technology, as well as the continuous increase in labor costs, the construction advantages of prefabricated buildings have become more prominent, and prefabricated steel structure residences that combine the advantages of prefabricated buildings and steel structures have become the development of residential buildings. important trends.

但目前行业内装配式混凝土结构建造方式相较传统现浇结构在本质上并无区别,多采用全支撑体系、原位现场钢筋施工、塔吊与汽车吊进行垂直运输,而预制装配式结构在建筑工业化方面的优点并不能充分发挥。因此,如何提供一种能够减少现场施工作业量,提高施工效率,缩短建造周期的装配式框架结构快速建造方法是本领域技术人员亟待解决的一个技术问题。However, compared with traditional cast-in-place structures, the construction methods of prefabricated concrete structures in the industry are essentially the same. Full support systems, in-situ on-site steel reinforcement construction, vertical transportation by tower cranes and truck cranes are mostly used, while prefabricated structures are used in construction. The advantages of industrialization cannot be fully utilized. Therefore, how to provide a rapid construction method of a prefabricated frame structure that can reduce on-site construction workload, improve construction efficiency, and shorten construction period is a technical problem to be solved urgently by those skilled in the art.

发明内容Contents of the invention

本发明提供一种装配式框架结构快速建造方法,以解决上述技术问题。The invention provides a rapid construction method of an assembled frame structure to solve the above technical problems.

为解决上述技术问题,本发明提供一种装配式框架结构快速建造方法,包括如下步骤:In order to solve the above technical problems, the present invention provides a rapid construction method of a prefabricated frame structure, comprising the following steps:

步骤1:基础承台的一体化施工及构件预制:预制构件包括预制主梁和预制次梁;所述基础承台的一体化施工依次包括承台钢筋安装、预埋镀锌波纹管、混凝土浇筑以及镀锌波纹管封堵;Step 1: Integrated construction of the foundation cap and component prefabrication: prefabricated components include prefabricated main beams and prefabricated secondary beams; the integrated construction of the foundation cap includes the installation of cap steel bars, pre-embedded galvanized corrugated pipes, and concrete pouring in sequence And galvanized bellows sealing;

步骤2:竖向结构钢筋与模板组合安装:依次包括钢筋加工、绑扎钢筋笼、钢筋笼吊装以及钢筋笼与模板固定;Step 2: Combined installation of vertical structural steel bars and formwork: including steel bar processing, binding of steel cages, hoisting of steel cages, and fixing of steel cages and formwork in sequence;

步骤3:采用吊运设备依次吊运所述模板以及所述预制构件并安装;Step 3: using lifting equipment to lift and install the formwork and the prefabricated components in sequence;

步骤4:以所述预制构件为受力支点,设置可拆卸转换构件、临时固结钢桁架与所述预制构件协同受力,组成无竖向支撑的楼承板结构;Step 4: Using the prefabricated component as the fulcrum of force, set the detachable conversion component, temporarily consolidated steel truss and the prefabricated component to cooperate with the force to form a floor deck structure without vertical support;

步骤5:现浇层钢筋施工、混凝土浇筑。Step 5: Construction of cast-in-place layer reinforcement and concrete pouring.

较佳地,步骤1中,所述构件预制包括采用BIM进行三维建模,利用三维建模对结构节点、构件拆分、管线布置、预应力设置进行优化。Preferably, in step 1, the component prefabrication includes three-dimensional modeling using BIM, and using three-dimensional modeling to optimize structural nodes, component splitting, pipeline layout, and prestress settings.

较佳地,步骤1中,基础承台的混凝土浇筑时,振动棒与预埋的所述镀锌波纹管之间留有缝隙。Preferably, in step 1, when the concrete of the foundation cap is poured, there is a gap between the vibrating rod and the pre-embedded galvanized bellows.

较佳地,步骤2中,竖向结构的钢筋笼中部预留有用于让泵送管落到柱脚处的孔洞。Preferably, in step 2, a hole is reserved in the middle of the reinforcement cage of the vertical structure for allowing the pumping pipe to drop to the foot of the column.

较佳地,所述孔洞的边长尺寸为150mm±20mm。Preferably, the side length of the hole is 150mm±20mm.

较佳地,步骤3中,所述吊运设备采用履带吊为主、汽车吊辅助的吊运机械组合。Preferably, in step 3, the hoisting equipment adopts a combination of hoisting machinery consisting mainly of crawler cranes and assisted by truck cranes.

较佳地,步骤3中,吊运所述模板时,先采用主臂将所述模板水平吊离地面,再采用副臂垂直吊至柱脚处。Preferably, in step 3, when hoisting the formwork, the formwork is first hoisted horizontally from the ground with the main arm, and then vertically hoisted to the foot of the column with the auxiliary arm.

较佳地,步骤3中,所述模板安装下落时,由4人分站四方用钢丝绳调整位置,由2人扶柱脚钢筋落入所述镀锌波纹管中心位置。Preferably, in step 3, when the formwork is installed and dropped, 4 people stand in four directions to adjust the position with steel wire ropes, and 2 people support the column foot steel bar to fall into the center position of the galvanized bellows.

较佳地,步骤3中,对所述钢丝绳进行斜拉调整所述模板的垂直度。Preferably, in step 3, the verticality of the formwork is adjusted by diagonally pulling the steel wire rope.

较佳地,步骤3中,在所述模板的底部设置50mm厚可调整接缝,并采用木楔子调整所述模板的标高。Preferably, in step 3, an adjustable joint with a thickness of 50 mm is provided at the bottom of the template, and wooden wedges are used to adjust the elevation of the template.

与现有技术相比,本发明提供的装配式框架结构快速建造方法具有如下优点:Compared with the prior art, the rapid construction method of the fabricated frame structure provided by the present invention has the following advantages:

1、本发明通过采用基础承台的一体化施工、竖向结构钢筋与模板组合一体化安装、无支撑预制结构体系施工、吊装设备及机械布置、预制结构BIM深化与构件加工联动协同达到对框架结构的快速施工效果,从而达到快速施工的目的;1. In the present invention, the integrated construction of the foundation cap, the integrated installation of the combination of vertical structural reinforcement and formwork, the construction of the unsupported prefabricated structure system, the hoisting equipment and mechanical layout, the BIM deepening of the prefabricated structure and the linkage and coordination of the component processing achieve a complete understanding of the frame. The rapid construction effect of the structure, so as to achieve the purpose of rapid construction;

2、本发明减少了现场施工作业量,提高了施工效率,缩短了建造周期,并对建筑资源进行了更加合理化的分配。2. The present invention reduces the amount of on-site construction work, improves construction efficiency, shortens the construction period, and more rationally allocates construction resources.

附图说明Description of drawings

图1为本发明一具体实施方式中装配式框架结构快速建造方法的实施流程图;Fig. 1 is the implementation flowchart of the fast construction method of prefabricated frame structure in a specific embodiment of the present invention;

图2为本发明一具体实施方式中装配式框架结构快速建造方法的实施示意图。Fig. 2 is a schematic diagram of the implementation of the rapid construction method of the prefabricated frame structure in a specific embodiment of the present invention.

图中:01-地坪、10-基础承台、11-镀锌波纹管、20-模板、21-钢筋笼、22-柱顶梁垫、31-预制主梁、32-预制次梁。In the figure: 01-floor, 10-foundation cap, 11-galvanized corrugated pipe, 20-formwork, 21-reinforcement cage, 22-column top beam pad, 31-prefabricated main beam, 32-prefabricated secondary beam.

具体实施方式Detailed ways

为了更详尽的表述上述发明的技术方案,以下列举出具体的实施例来证明技术效果;需要强调的是,这些实施例用于说明本发明而不限于限制本发明的范围。In order to describe the technical solution of the above invention in more detail, specific examples are listed below to demonstrate the technical effect; it should be emphasized that these examples are used to illustrate the present invention and not limit the scope of the present invention.

本发明提供的装配式框架结构快速建造方法,如图1和图2所示,包括如下步骤:The rapid construction method of the assembled frame structure provided by the present invention, as shown in Figure 1 and Figure 2, includes the following steps:

步骤1:基础承台10的一体化施工及构件预制:预制构件包括预制主梁31和预制次梁32,在一些实施例中,预制过程可以包括采用BIM进行三维建模,具体可以采用Revit进行三维建模,利用三维建模对结构节点、构件拆分、管线布置、预应力设置进行优化,确定构件划分和预留口洞位置、预应力孔道留设情况并进行补强设计,根据设计结果进行构件拆分,并交由厂家加工。Step 1: Integrated construction of the foundation cap 10 and component prefabrication: the prefabricated components include the prefabricated main girder 31 and the prefabricated secondary beam 32. In some embodiments, the prefabricated process may include BIM for 3D modeling, specifically Revit 3D modeling, using 3D modeling to optimize structural nodes, component splitting, pipeline layout, and prestressing settings, determine component division, reserved opening positions, prestressed tunnels, and carry out reinforcement design. According to the design results The components are disassembled and handed over to the manufacturer for processing.

所述基础承台10的一体化施工依次包括承台钢筋安装、预埋镀锌波纹管11、混凝土浇筑以及镀锌波纹管11封堵。具体地,在地坪01上安装承台钢筋前,必须对桩基进行全数的小应变检查和轴线、标高复核;预埋镀锌波纹管11固定必须牢固;混凝土浇筑时,振动棒与预埋的所述镀锌波纹管11之间应当留有缝隙,禁止振动棒触碰镀锌波纹管11,防止镀锌波纹管11出现位移或损伤;镀锌波纹管11底部须封堵,混凝土浆料不得进入镀锌波纹管11内,顶口也应临时封堵。The integrated construction of the foundation cap 10 sequentially includes the installation of cap steel bars, pre-embedded galvanized bellows 11, concrete pouring and galvanized bellows 11 sealing. Specifically, before installing the cap reinforcement on the floor 01, it is necessary to carry out all small strain inspections and re-checks on the axis and elevation of the pile foundation; the pre-embedded galvanized bellows 11 must be firmly fixed; There should be gaps between the galvanized corrugated pipes 11, and the vibrating rod is prohibited from touching the galvanized corrugated pipes 11 to prevent displacement or damage of the galvanized corrugated pipes 11; the bottom of the galvanized corrugated pipes 11 must be blocked, and the concrete slurry Do not enter the galvanized bellows 11, and the top port should be temporarily blocked.

步骤2:竖向结构钢筋与模板20组合安装:依次包括钢筋加工、绑扎钢筋笼21、钢筋笼21吊装以及钢筋笼21与模板20固定。具体地,钢筋加工的形状、尺寸应与钢柱模具体尺寸配套,深化图应根据成品柱模尺寸来深化;绑扎过程中柱筋根部需做上定位夹,确保钢筋位置与预埋镀锌波纹管11空位一致,钢筋笼21中间必须预留足够大的孔洞(未图示)让泵送管落到柱脚;钢筋笼21的吊装点必须固定牢固,防止吊装过程中脱落造成安全事故;钢筋笼21与模板20固定点的设置必须固定牢固,防止模板20竖直后钢筋笼21滑落;柱帽钢筋必须严格根据钢模斜度放样。Step 2: Combined installation of vertical structural steel bars and formwork 20: including steel bar processing, binding of steel bar cages 21, hoisting of steel bar cages 21, and fixing of steel bar cages 21 and formwork 20 in sequence. Specifically, the shape and size of steel bar processing should match the size of the steel column mold body, and the deepening drawing should be deepened according to the size of the finished column mold; during the binding process, the root of the column bar needs to be equipped with a positioning clip to ensure that the position of the steel bar is consistent with the pre-embedded galvanized corrugation. The vacancy of the tube 11 is consistent, and a large enough hole (not shown) must be reserved in the middle of the steel cage 21 to allow the pumping pipe to fall to the column foot; the hoisting point of the steel cage 21 must be fixed firmly to prevent safety accidents caused by falling off during the hoisting process; The fixed points of the cage 21 and the formwork 20 must be fixed firmly to prevent the reinforcement cage 21 from slipping after the formwork 20 is vertical;

钢筋笼21吊装前需对钢筋笼21的截面尺寸、长度进行全数检查,重点检查柱帽截面尺寸和定位器、固定件的位置是否准确且牢固;钢筋笼21起吊离开操作架时,如柱帽(表面)未达到水平,必须调整水平后再吊入A片模具(放钢筋笼21的模具)就位处,便于钢筋笼21校正和定位;钢筋笼21就位时,应进行保护层厚度的检查,符合设计要求后方可定位固定。Before hoisting the steel cage 21, it is necessary to check the cross-sectional size and length of the steel cage 21 in full, focusing on checking whether the cross-sectional size of the column cap and the positions of the locators and fixing parts are accurate and firm; (surface) has not reached the level, must adjust the level and then hoist it into the A piece mold (the mold for placing the reinforcement cage 21) in place, so as to facilitate the correction and positioning of the reinforcement cage 21; when the reinforcement cage 21 is in place, the thickness of the protective layer should be adjusted After checking, it can be positioned and fixed after meeting the design requirements.

步骤3:采用吊运设备依次吊运所述模板20以及所述预制构件并安装。在一些实施例中,吊运所述模板20时,先采用主臂将所述模板20水平吊离地面,再采用副臂垂直吊至柱脚处;所述模板20安装下落时,由4人分站四方用钢丝绳调整所述模板20的大致位置,由2人扶柱脚钢筋对准镀锌波纹管11中心,缓慢下降就位,尽量使柱脚钢筋落入所述镀锌波纹管11中心位置;对四根所述钢丝绳进行斜拉以调整所述模板20的垂直度;在所述模板20的底部设置50mm厚可调整接缝,并采用木楔子调整所述模板20的标高。将所述预制构件安装于所述模板20前,还需先设置柱顶梁垫22,以增加承压面积。Step 3: using lifting equipment to lift and install the template 20 and the prefabricated components in sequence. In some embodiments, when lifting the formwork 20, the main arm is used to hoist the formwork 20 horizontally from the ground, and then the auxiliary arm is used to vertically lift the formwork 20 to the foot of the column; when the formwork 20 is installed and dropped, four people Sub-station Quartet adjusts the general position of the template 20 with a steel wire rope, aligns the steel bar at the foot of the column with the center of the galvanized corrugated pipe 11 by two people, and slowly lowers it into place, so that the steel bar at the foot of the column falls into the center of the galvanized bellows 11 as much as possible position; the four steel wire ropes are obliquely pulled to adjust the verticality of the formwork 20; a 50mm thick adjustable joint is set at the bottom of the formwork 20, and wooden wedges are used to adjust the elevation of the formwork 20. Before the prefabricated components are installed on the formwork 20 , it is necessary to set the column top beam pad 22 to increase the bearing area.

步骤4:以所述预制构件(预制主梁31和预制次梁32)为受力支点,设置可拆卸转换构件、临时固结钢桁架与所述预制构件协同受力,组成无竖向支撑的楼承板结构。这样,无需在现场设置竖向支撑,从而提高了现场施工的灵活度。Step 4: Taking the prefabricated components (prefabricated main girder 31 and prefabricated secondary girder 32) as the force fulcrum, set detachable conversion components, temporary consolidation steel trusses and the prefabricated components to cooperate with the force to form a vertically supported Floor deck structure. In this way, there is no need to set up vertical supports on site, thereby improving the flexibility of site construction.

步骤5:现浇层钢筋施工、混凝土浇筑。具体地,若混凝土浇筑高度比较高,则必须根据柱截面、钢筋间距、浇筑等因素设计合理的配合比,确保混凝土浇筑的成型质量,混凝土绝对不能离析;钢筋笼21在设计时在中心位置预留边长尺寸为150mm±20mm的孔洞(混凝土浇筑导管下落区域),用导管把混凝土送至柱底部,保证混凝土自由下落高度不超过1.5米;还可以在浇筑混凝土前注入50mm厚同强度砂浆,以保证柱底部的外观质量。Step 5: Construction of cast-in-place layer reinforcement and concrete pouring. Specifically, if the concrete pouring height is relatively high, a reasonable mix ratio must be designed according to factors such as column section, steel bar spacing, pouring, etc., to ensure the quality of the concrete pouring, and the concrete must not segregate; Leave a hole with a side length of 150mm±20mm (the drop area of the concrete pouring conduit), and use the conduit to send the concrete to the bottom of the column to ensure that the free fall height of the concrete does not exceed 1.5 meters; you can also inject 50mm thick mortar of the same strength before pouring the concrete. To ensure the appearance quality of the bottom of the column.

在一些实施例中,步骤3中,所述吊运设备采用履带吊为主、汽车吊辅助的吊运机械组合,并结合预制道板作为可移动周转堆场,相较传统的塔吊吊运与固定堆场形式,极大的提高了吊运能力及现场的机动性,加之框架结构构件重量较重,继而更加具有经济性。In some embodiments, in step 3, the hoisting equipment adopts a combination of hoisting machinery with crawler cranes as the main part and truck cranes as the auxiliary, combined with prefabricated slabs as a movable turnover yard, compared with traditional tower cranes and The fixed storage yard form greatly improves the lifting capacity and site mobility, and the weight of the frame structural members is heavier, which makes it more economical.

另外,还可以通过对永临结合水平通道、设备运输路线以及构件布置区域的精细化地面场布,将永久道路与设备基础、构件布置区域硬化相结合,并结合构件连接、拼装及固定形式及要求对场地进行精细化设计。In addition, it is also possible to combine the permanent road with the equipment foundation and the hardening of the component layout area through the refined ground layout of the Yonglin combined horizontal passage, equipment transportation route and component layout area, and combine component connection, assembly and fixing forms and A detailed design of the site is required.

综上所述,本发明提供的装配式框架结构快速建造方法,包括如下步骤:步骤1:基础承台10的一体化施工及构件预制:预制构件包括预制主梁31和预制次梁32;所述基础承台10的一体化施工依次包括承台钢筋安装、预埋镀锌波纹管11、混凝土浇筑以及镀锌波纹管11封堵;步骤2:竖向结构钢筋与模板20组合安装:依次包括钢筋加工、绑扎钢筋笼21、钢筋笼21吊装以及钢筋笼21与模板20固定;步骤3:采用吊运设备依次吊运所述模板20以及所述预制构件并安装;步骤4:以所述预制构件为受力支点,设置可拆卸转换构件、临时固结钢桁架与所述预制构件协同受力,组成无竖向支撑的楼承板结构;步骤5:现浇层钢筋施工、混凝土浇筑。本发明通过采用基础承台10的一体化施工准备、竖向结构钢筋与模板20组合一体化安装技术、无支撑预制结构体系施工技术、全移动机械垂直与水平运输施工技术吊运设备及机械布置、预制结构BIM深化与构件加工联动、无支撑组合楼板施工、场地水平通道永临结合与精细化地面布置等手段,达到对框架结构的快速施工效果,从而达到快速施工的目的。本发明减少了现场施工作业量,提高了施工效率,缩短了建造周期,并对建筑资源进行了更加合理化的分配。In summary, the rapid construction method of the prefabricated frame structure provided by the present invention includes the following steps: Step 1: Integrated construction of the foundation cap 10 and component prefabrication: the prefabricated components include the prefabricated main beam 31 and the prefabricated secondary beam 32; The integrated construction of the foundation cap 10 includes the installation of cap steel bars, pre-embedded galvanized corrugated pipes 11, concrete pouring and galvanized corrugated pipes 11 sealing; Steel bar processing, binding steel cage 21, hoisting of steel cage 21 and fixing of steel cage 21 and formwork 20; step 3: using lifting equipment to lift and install the formwork 20 and the prefabricated components in sequence; step 4: using the prefabricated The component is the force-bearing fulcrum, and the detachable conversion component, the temporarily consolidated steel truss and the prefabricated component are set to cooperate with the force to form a floor deck structure without vertical support; Step 5: Construction of cast-in-place layer reinforcement and concrete pouring. The present invention adopts the integrated construction preparation of the foundation cap 10, the combination and integrated installation technology of vertical structural steel bars and formwork 20, the construction technology of unsupported prefabricated structure system, the vertical and horizontal transportation construction technology of all mobile machinery, lifting equipment and mechanical layout , Prefabricated structure BIM deepening and component processing linkage, unsupported composite floor construction, site horizontal passage permanent combination and refined ground layout, etc., to achieve the rapid construction effect of the frame structure, so as to achieve the purpose of rapid construction. The invention reduces the amount of on-site construction work, improves construction efficiency, shortens the construction period, and more rationally allocates construction resources.

显然,本领域的技术人员可以对发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包括这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the invention without departing from the spirit and scope of the invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and equivalent technologies thereof, the present invention also intends to include these modifications and variations.

Claims (10)

1. A rapid construction method of an assembled frame structure is characterized by comprising the following steps:
step 1: the integrated construction and the component prefabrication of the foundation bearing platform: the prefabricated parts comprise prefabricated main beams and prefabricated secondary beams; the integrated construction of the foundation bearing platform sequentially comprises bearing platform steel bar installation, pre-buried galvanized corrugated pipes, concrete pouring and galvanized corrugated pipe plugging;
and 2, step: the vertical structural steel bars and the templates are assembled and installed: sequentially processing a steel bar, binding a steel bar cage, hoisting the steel bar cage and fixing the steel bar cage and a template;
and step 3: hoisting the template and the prefabricated part in sequence by using hoisting equipment and installing;
and 4, step 4: taking the prefabricated part as a stress fulcrum, arranging a detachable conversion member, a temporary consolidation steel truss and the prefabricated part to cooperatively bear force to form a floor bearing plate structure without vertical support;
and 5: and (5) constructing cast-in-place layer steel bars and pouring concrete.
2. The rapid construction method of an assembled frame structure according to claim 1, wherein in step 1, the prefabrication of the members comprises three-dimensional modeling by means of BIM, and the three-dimensional modeling is used for optimizing structure nodes, member disassembly, pipeline arrangement and prestress setting.
3. The rapid construction method of an assembled frame structure according to claim 1, wherein in the step 1, a gap is left between the vibrating rod and the pre-buried galvanized corrugated pipe when concrete of the foundation cap is poured.
4. The rapid construction method of an assembled frame structure according to claim 1, wherein in the step 2, a hole for allowing the pumping pipe to fall to the column base is reserved in the middle of the reinforcement cage of the vertical structure.
5. The rapid building method of an assembled frame structure according to claim 4, wherein the size of the side length of the hole is 150mm ± 20mm.
6. A rapid construction method of an assembled frame structure according to claim 1, wherein in step 3, the hoisting equipment adopts a combination of a crawler crane as a main hoisting machine and a truck crane as an auxiliary hoisting machine.
7. A rapid construction method of an assembled frame structure according to claim 1, wherein in the step 3, when the template is hoisted, the template is hoisted horizontally away from the ground by using the main arm, and then is hoisted vertically to the column foot by using the auxiliary arm.
8. The rapid construction method of an assembled frame structure according to claim 7, wherein in the step 3, when the formwork is installed and falls down, the position of the formwork is adjusted by using a steel wire rope at four directions of the 4-person substation, and the steel bar of the 2-person support foot falls into the center of the galvanized corrugated pipe.
9. A rapid construction method of an assembly type frame structure according to claim 8, wherein in the step 3, the steel wire ropes are obliquely pulled to adjust the verticality of the formwork.
10. A rapid construction method of an assembled frame structure according to claim 9, wherein in step 3, adjustable joints with a thickness of 50mm are provided at the bottom of the formworks, and the elevation of the formworks is adjusted using wooden wedges.
CN202211431812.2A 2022-11-16 2022-11-16 Method for quickly building assembled frame structure Pending CN115653095A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211431812.2A CN115653095A (en) 2022-11-16 2022-11-16 Method for quickly building assembled frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211431812.2A CN115653095A (en) 2022-11-16 2022-11-16 Method for quickly building assembled frame structure

Publications (1)

Publication Number Publication Date
CN115653095A true CN115653095A (en) 2023-01-31

Family

ID=85021977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211431812.2A Pending CN115653095A (en) 2022-11-16 2022-11-16 Method for quickly building assembled frame structure

Country Status (1)

Country Link
CN (1) CN115653095A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119162971A (en) * 2024-11-12 2024-12-20 中国水利水电第五工程局有限公司 A kind of assembled modular component and construction method of flow hole of pressure regulating well
CN119711702A (en) * 2025-02-08 2025-03-28 中建八局第三建设有限公司 Reverse construction method for flat floor structure
CN119830575A (en) * 2024-12-24 2025-04-15 苏州智本信息科技有限公司 Industrial intelligent batching method and system based on building materials

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014032558A1 (en) * 2012-08-28 2014-03-06 Chu Mingjin Assembled and integrated shear wall building structure and construction method
CN104234428A (en) * 2014-09-25 2014-12-24 管金平 Construction technology for columns, beams and plates of assembled monolithic structure of building
CN108301546A (en) * 2018-03-03 2018-07-20 北京工业大学 A kind of big module overlapping contignation of the assembled with plane girder temporary support
CN113338537A (en) * 2021-05-26 2021-09-03 中国五冶集团有限公司 Construction method of ultrahigh large-section concrete frame column

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014032558A1 (en) * 2012-08-28 2014-03-06 Chu Mingjin Assembled and integrated shear wall building structure and construction method
CN104234428A (en) * 2014-09-25 2014-12-24 管金平 Construction technology for columns, beams and plates of assembled monolithic structure of building
CN108301546A (en) * 2018-03-03 2018-07-20 北京工业大学 A kind of big module overlapping contignation of the assembled with plane girder temporary support
CN113338537A (en) * 2021-05-26 2021-09-03 中国五冶集团有限公司 Construction method of ultrahigh large-section concrete frame column

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN119162971A (en) * 2024-11-12 2024-12-20 中国水利水电第五工程局有限公司 A kind of assembled modular component and construction method of flow hole of pressure regulating well
CN119830575A (en) * 2024-12-24 2025-04-15 苏州智本信息科技有限公司 Industrial intelligent batching method and system based on building materials
CN119711702A (en) * 2025-02-08 2025-03-28 中建八局第三建设有限公司 Reverse construction method for flat floor structure

Similar Documents

Publication Publication Date Title
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN103924505B (en) Use prefabricated steel-concrete combination T beam and the construction method of Wavelike steel webplate
CN115653095A (en) Method for quickly building assembled frame structure
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN111945891A (en) Ring truss high-altitude in-situ splicing construction method
CN103758348B (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN102587286A (en) Simply supported-continuous construction method for bridge superstructure
CN110409318B (en) A method for assembling and erecting large-span simply supported steel-concrete beams
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN105714683A (en) Installation and dismantling method of high bent cast-in-situ aqueduct suspension type bailey frames
CN107700648A (en) Prefabricated component and cast-in-place post assembled integral concrete frame structure construction
CN114808759A (en) Cantilever concrete formwork support structure of steel-concrete composite beam bridge and cantilever concrete construction method
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN116771116B (en) Construction method of reverse construction equipment system for suspended structures
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN111186780B (en) Ballast-type foundation and construction method of boom-type tower crane base frame
CN102777044A (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN104963295A (en) Support frame for non-ground internal-force balanced cast-in-place beam and construction method thereof
CN112324131A (en) A dual-purpose large-span stiff beam construction structure and its construction method
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN113802726A (en) Edge member of superimposed integral prefabricated shear wall and installation method
CN100424298C (en) Construction method of making laminated floor slab with upper support frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination