CN115647263B - A forging process for R-pin ball and socket hardware - Google Patents

A forging process for R-pin ball and socket hardware Download PDF

Info

Publication number
CN115647263B
CN115647263B CN202211334847.4A CN202211334847A CN115647263B CN 115647263 B CN115647263 B CN 115647263B CN 202211334847 A CN202211334847 A CN 202211334847A CN 115647263 B CN115647263 B CN 115647263B
Authority
CN
China
Prior art keywords
ball socket
forging
die
punch
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211334847.4A
Other languages
Chinese (zh)
Other versions
CN115647263A (en
Inventor
征大生
黄小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rugao Dasheng Line Material Co ltd
Original Assignee
Rugao Dasheng Line Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rugao Dasheng Line Material Co ltd filed Critical Rugao Dasheng Line Material Co ltd
Priority to CN202211334847.4A priority Critical patent/CN115647263B/en
Publication of CN115647263A publication Critical patent/CN115647263A/en
Application granted granted Critical
Publication of CN115647263B publication Critical patent/CN115647263B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forging (AREA)

Abstract

本发明涉及一种R销球窝金具锻造成型工艺,具体步骤包括准备原料、一次锻造成型、二次锻造成型、截取、三次锻造成型以及成品,整个锻造过程中不会出现锻造模具内部被挤压变形或塌陷的情况,避免因锻造模具损坏而替换锻造模具的费时费力的情况,且第二加工部上的半圆形突起,用于确定半成品球窝金具总长,便于后续将待加工件前后定位置于球窝部成型腔与压接部卡接槽内,保证成型时半成品球窝金具的外形冲型度与致密度,而将半圆形突起与第二圆柱本体之间的连接采用圆弧过渡,可避免在三次锻造成型过程中半圆形突起与第二圆柱本体之间产生包扎、折叠(折缝),最终提升生产效率,进而提升工厂的生产效益。

The invention relates to a forging process for an R-pin ball socket hardware. The specific steps include preparing raw materials, primary forging, secondary forging, cutting, tertiary forging and finished products. During the entire forging process, the inside of the forging die will not be squeezed, deformed or collapsed, thereby avoiding the time-consuming and labor-intensive situation of replacing the forging die due to damage to the forging die. The semicircular protrusion on the second processing part is used to determine the total length of the semi-finished ball socket hardware, which is convenient for subsequent front and rear positioning of the workpiece to be processed in the ball socket forming cavity and the crimping part clamping groove, thereby ensuring the shape punching degree and density of the semi-finished ball socket hardware during forming. The connection between the semicircular protrusion and the second cylindrical body adopts an arc transition, thereby avoiding the generation of bandaging and folding (crease) between the semicircular protrusion and the second cylindrical body during the three-stage forging process, thereby ultimately improving the production efficiency and further improving the production benefits of the factory.

Description

R pin ball socket fitting forging forming process
Technical Field
The invention relates to the technical field of hardware forging, in particular to a forging forming process of an R-pin ball socket hardware.
Background
The ball socket fitting is used as an important connecting part in the power transmission system, and the electric power fitting ball socket type connecting part is generally used for being matched with a ball head type fitting, so that the quality requirement is very high.
When the ball socket fitting is produced, the semi-finished ball socket fitting is generally forged first, then the semi-finished ball socket fitting is subjected to subsequent finish machining, the structure of the semi-finished ball socket fitting is shown in fig. 1, the semi-finished ball socket fitting mainly comprises a compression joint part b and a ball socket part a, the ball socket part a is provided with a spherical inner cavity 1 for accommodating the end ball head section of the insulator ball head fitting, and the side surface of the ball socket part is provided with a lateral opening, namely a lateral groove 2, for allowing the ball head fitting to enter the spherical inner cavity.
In the existing ball socket fitting forging process, a blank is formed by adopting a round steel bar to be directly heated and then through a forging die, and the blank is provided with a large cylinder and a small cylinder, wherein the large cylinder is used for processing a ball socket part, and the small cylinder is used for processing a fitting crimping part. In the technical mode, the ball socket part is of a solid structure, the ball socket structure is formed by metal processing milling grooves and milling ball sockets, the processing amount is large, the metal materials are wasted, and the cost is high.
In addition, during forging, a general forging piece adopts a lower ejection discharging mode, namely, a material ejection hole is formed in the center of a mold core of a lower mold, and a hardware fitting is ejected out through a lower ejector rod in the material ejection hole, but in a practical forging process, the hardware fitting is attached to an upper punch and leaves a lower mold cavity along with the upper punch, and manual demolding is still needed.
The prior patent CN 202111139774.9 provides a forging process of an R pin ball socket fitting and a forging die thereof, wherein straight round steel is adopted as a raw material, and is heated and then forged into a semi-finished ball socket fitting in the forging die, one end of the semi-finished ball socket fitting is a large-diameter cylinder, the other end of the semi-finished ball socket fitting is a small-diameter cylinder, a side slot extending from the end face to one side wall is formed in the large-diameter cylinder, and the semi-finished ball socket fitting is subjected to metal processing to form the R pin ball socket fitting. The invention has the advantages that the milling quantity of the metal working and the consumption of materials can be reduced and the production efficiency can be improved by forging the semi-finished product of the ball socket fitting with the side slot.
However, the above patent still has the defects that in the actual batch processing process, the ball socket forming convex block at the bottom end of the cylindrical cavity of the mold core is easy to be extruded and deformed or collapse, and the forged forming part is not in line with the requirement, so that the forging process is required to be stopped frequently and the mold core is replaced, the operation is tedious, time and labor are wasted, the problem of low production efficiency is caused, and the production benefit of factories is reduced.
Disclosure of Invention
The invention aims to solve the technical problems that the R pin ball socket fitting forging forming process is provided, and the problems that the die core internal structure is easy to collapse, the die core needs to be replaced frequently, the operation is complicated, the production efficiency is low and the production benefit of factories is reduced in the prior art are solved.
In order to solve the technical problems, the technical scheme of the invention is that the R pin ball socket fitting forging forming process is characterized by comprising the following steps:
t1, preparing raw materials, namely adopting straight round steel as a raw material;
T2, one-time forging forming, namely mounting the straight round steel in a first forging die, forging the middle and upper parts of the straight round steel by using the first forging die, so that a first processing part with the height of n+ (1-2) and the outer diameter of R- (4-9) is formed at the top of the straight round steel, a first crimping part with the outer diameter of r+/-0.4 is formed at the middle part of the straight round steel, and the first processing part and the first crimping part are coaxially arranged;
The first processing part comprises a first cylindrical body, an S-shaped arc transition is formed between the first cylindrical body and the first compression joint part, and one side periphery of the first cylindrical body far away from the first compression joint part is provided with a chamfer;
Taking out the first machined part from the first forging die, installing the first machined part in a second forging die, forging the first machined part and the first crimping part by using the second forging die to form a second machined part, forming a second machined part with the height of n+/-0.5 and the outer diameter of R+/-0.5 on the first machined part, forming a second crimping part with the outer diameter of r+/-0.2 on the first crimping part, and coaxially arranging the second machined part and the second crimping part;
The second processing part comprises a second cylindrical body and a semicircular protrusion which are coaxially arranged up and down, the semicircular protrusion is arranged at the center of the top of the second cylindrical body, and the semicircular protrusion and the second cylindrical body are in arc transition;
T4, cutting, namely taking out the second machined part from the second forging die, and completely cutting off the second machined part and the second crimping part from the straight round steel to form a to-be-machined part;
T5, three times of forging forming, namely mounting a to-be-machined part in a third forging die, forging a second machining part of the to-be-machined part by utilizing the third forging die, extruding the second machining part into a sphere, extruding a spherical inner cavity and a lateral groove which are communicated with each other to form a semi-finished ball socket part, wherein the height of the semi-finished ball socket part is n+/-0.2, the outer diameter of the semi-finished ball socket part is R+/-0.2, and the semi-finished ball socket part and the second crimping part coaxially form a semi-finished ball socket fitting at the moment, and the forging of the semi-finished ball socket fitting is completed;
And T6, taking out the semi-finished ball socket fitting, and performing metal processing to form the R-pin ball socket fitting, wherein the height of a ball socket part of the R-pin ball socket fitting is n, the outer diameter of the ball socket part is R, and the radius of the compression joint part is R.
Further, the first forging die comprises a first upper die and a first lower die which are arranged up and down, the first lower die is provided with a first inner cavity which is vertically and penetratingly arranged, and the first upper die comprises a first punch;
the first inner cavity comprises an upper circular tube groove, a middle circular tube groove and a lower circular tube groove which are coaxially and communicated, wherein the inner diameter of the upper circular tube groove is larger than that of the middle circular tube groove, an S-shaped arc transition is formed between the upper circular tube groove and the middle circular tube groove, the inner diameter of the middle circular tube groove is larger than that of the lower circular tube groove, and the length of the middle circular tube groove is larger than that of a crimping part of the semi-finished ball socket fitting;
The first punch is vertically downwards arranged and comprises a first punch body, a first punch part is arranged in the center of the bottom of the first punch body, the first punch part is a circular truncated cone-shaped groove, and the upper bottom of the circular truncated cone-shaped groove is smaller than the lower bottom of the circular truncated cone-shaped groove;
The second forging die comprises a second upper die and a second lower die, the second lower die has the same structure as the first lower die, the second upper die comprises a second punch, the second punch is also vertically and downwards arranged and comprises a second punch body, a second punch part is arranged in the center of the bottom of the second punch body, and the length of the second punch is longer than that of the first punch;
the third forging die comprises a third upper die and a third lower die which are arranged up and down, the third lower die is provided with a third inner cavity, the third upper die comprises a third punch head, the third punch head comprises a third punch head body, a third punching part is arranged at the bottom of the third punch head body, and the third punching part comprises a spherical inner cavity punching part and a lateral groove punching part.
Further, the inner diameter of the lower circular tube groove is consistent with the outer diameter of the straight circular steel, the inner diameter of the middle circular tube groove is not smaller than the outer diameter of the first compression joint part, the outer diameter of the first compression joint part is larger than the outer diameter of the straight circular steel, the inclination angle of the chamfer is consistent with the inclination of the circular truncated cone-shaped groove, and the lower bottom of the circular truncated cone-shaped groove is larger than the outer diameter of the first cylindrical body;
The external diameter of second crimping portion is not greater than the internal diameter of middle part circular tube groove, the external diameter of second cylinder body is not greater than the internal diameter of upper portion circular tube groove, still is equipped with semicircular projection in the middle part of one side that this second cylinder body kept away from second crimping portion, and this semicircular projection and second cylinder body circular arc transition.
Further, the second lower die comprises two symmetrically arranged lower modules, a half cavity is formed in the inner side of each lower module, the two lower modules are folded, and the half cavities of the two lower modules are folded to form the third inner cavity;
The third inner cavity comprises a ball socket part forming cavity and a crimping part clamping groove, and the crimping part clamping groove just accommodates the crimping part of the semi-finished ball socket fitting;
The ball socket part forming cavity is communicated with the clamping groove of the compression joint part and is horizontally arranged in the middle of the second lower die, the length of the ball socket part forming cavity is equal to that of the ball socket part of the semi-finished ball socket fitting, and the total length of the ball socket part forming cavity and the clamping groove of the compression joint part is the total length of the semi-finished ball socket fitting.
Further, an inlet and outlet groove is further formed in the second lower die, the inlet and outlet channel is vertically arranged on the second lower die and located above the ball socket portion forming cavity, and the inlet and outlet channel is communicated with the third inner cavity and used for accommodating the third punch to vertically enter and exit the ball socket portion forming cavity.
Further, a workpiece clamping groove which is vertically arranged is further formed in the second lower die, an opening of the workpiece clamping groove is upwards arranged, the workpiece clamping groove is communicated with the outer side of the clamping groove of the pressing part, a gap is reserved between the bottom end of the clamping groove of the pressing part and the bottom of the clamping groove of the workpiece clamping groove, the clamp can extend into the inner part of the third inner cavity from the workpiece clamping groove in the actual forging process conveniently to firmly clamp the semi-finished ball socket fitting, or the workpiece to be machined is firmly clamped between the two half cavities, the subsequent two lower modules can be folded conveniently, and the workpiece to be machined can be accurately placed between the two half cavities, so that the workpiece to be machined can be accurately placed in the third inner cavity.
Further, the outer diameters of the first punch and the second punch are not larger than the inner diameter of the upper circular tube groove.
The invention has the advantages that:
in the invention, the first forging forming die and the second forging forming die are utilized to forge and form the semi-finished ball socket fitting for many times, the situation that the inside of the forging die is extruded and deformed or collapses cannot occur in the whole forging process, the time and labor waste caused by the damage of the forging die are avoided, the semicircular protrusions on the second processing part are used for determining the total length of the semi-finished ball socket fitting, the to-be-machined part is conveniently positioned in the clamping grooves of the ball socket part forming cavity and the compression joint part in the follow-up mode, the shape punching degree and the compactness of the semi-finished ball socket fitting during forming are ensured, the connection between the semicircular protrusions and the second cylindrical body adopts arc transition, the binding and folding (crease) between the semicircular protrusions and the second cylindrical body in the three-time forging forming process can be avoided, the production efficiency is finally improved, and the production benefit of factories is further improved.
Drawings
The invention will be described in further detail with reference to the drawings and the detailed description.
Fig. 1 is a perspective view of the R pin ball socket fitting of the present invention.
FIG. 2 is a cross-sectional view of a first forging die portion of the present invention.
Fig. 3 is a cross-sectional view showing the structure of the first forging die of the present invention when the dies are closed.
Fig. 4 is a cross-sectional view showing the structure of the second forging die of the present invention when the dies are closed.
FIG. 5 is a first view of the construction of a third forging die portion of the present invention.
FIG. 6 is a diagram of a second forging die part configuration in accordance with the present invention.
FIG. 7 is a third forging die part configuration diagram of the present invention.
FIG. 8 is a top view of a third forging die part structure of the present invention.
FIG. 9 is a U-U cross-sectional view of the present invention.
Detailed Description
The forging forming die adopted by the R pin ball socket fitting forging forming process comprises a first forging die 4, a second forging die 5 and a third forging die 6. As shown in fig. 2 to 3, the first forging die 4 includes a first upper cylinder and a first upper die and a first lower die disposed up and down.
The first lower die comprises a first lower die holder 44 and a first lower die block 42 mounted on the first lower die holder 44, wherein a first inner cavity 43 vertically penetrating the first lower die block 42 is arranged on the first lower die block.
The first upper die comprises a first punch 41, the first punch 41 is vertically downwards arranged and comprises a first punch 41 body, a first punch part is arranged in the center of the bottom of the first punch 41 body and is a circular truncated cone-shaped groove, and the upper bottom of the circular truncated cone-shaped groove is smaller than the lower bottom of the circular truncated cone-shaped groove.
The first inner cavity 43 comprises an upper circular tube groove 431, a middle circular tube groove 432 and a lower circular tube groove 433 which are coaxially and communicated, the inner diameter of the upper circular tube groove 431 is larger than that of the middle circular tube groove 432, an S-shaped arc transition is formed between the upper circular tube groove 431 and the middle circular tube groove 432, the inner diameter of the middle circular tube groove 432 is larger than that of the lower circular tube groove 433, and meanwhile, the length of the middle circular tube groove 432 is larger than that of a crimping part b of the semi-finished ball socket fitting.
A feeding channel is also formed on the first lower die holder 44, and the feeding channel is coaxially disposed with the first inner cavity 43, and has a diameter larger than that of the lower circular tube slot.
The inner diameter of the lower circular tube groove 433 is consistent with the outer diameter of the straight circular steel 3, the inner diameter of the middle circular tube groove 432 is not smaller than the outer diameter of the first press-connection part 9, the outer diameter of the first press-connection part 9 is larger than the outer diameter of the straight circular steel 3, the inclination angle of the chamfer is consistent with the inclination of the circular truncated cone-shaped groove, and the lower bottom of the circular truncated cone-shaped groove is larger than the outer diameter of the first cylindrical body.
The first upper oil cylinder is arranged above the first upper die, the output end of the first upper oil cylinder is connected with the first upper die, and the first upper oil cylinder drives the first upper die to lift and lower, so that the die assembly and the die stripping of the first upper die and the lower die are realized, and the forging and pressing of the first machined part are realized.
The outer diameter of the second press-connection part 10 is not greater than the inner diameter of the middle circular tube groove 432, the outer diameter of the second cylindrical body 81 is not greater than the inner diameter of the upper circular tube groove 431, a semicircular protrusion 82 is further arranged in the middle of one side of the second cylindrical body 81 away from the second press-connection part 10, and the semicircular protrusion 82 and the second cylindrical body 81 are in arc transition.
As shown in fig. 4, the second forging die 5 includes a second upper cylinder, a second upper die, and a second lower die 52.
The second lower die 52 has the same structure as the first lower die, and comprises a second lower die 52 seat and a second lower die 52 block arranged on the second lower die 52 seat, wherein a second inner cavity is vertically arranged on the second lower die 52 block in a penetrating way, and the second inner cavity has the same structure as the first inner cavity 43.
The second upper die comprises a second punch 51, the second punch 51 is also vertically arranged downwards and comprises a second punch 51 body, a second punch part is arranged at the bottom center of the second punch 51 body, and the length of the second punch 51 is longer than that of the first punch 41.
The outer diameter of the first punch and the outer diameter of the second punch are not larger than the inner diameter of the upper circular tube groove 431.
The second upper oil cylinder is arranged above the second upper die, the output end of the second upper oil cylinder is connected with the second upper die, and the second upper oil cylinder drives the second upper die to lift and lower, so that the die assembly and the die stripping of the second upper die and the second lower die are realized, and the forging and pressing of a second machined part are realized.
As shown in fig. 5 to 9, the third forging die 6 includes a third upper cylinder, a first side cylinder, a second side cylinder, and third upper and lower dies disposed up and down.
The third lower die comprises a second inner cavity, the third lower die comprises two lower modules 66 which are symmetrical and are arranged on a third lower die holder in a sliding mode, two sliding grooves which are symmetrically arranged are formed in the third lower die holder, a sliding block is arranged in each sliding groove, the two lower modules 66 are respectively arranged on the two sliding blocks, a half of cavity 614 is formed in the inner side of each lower module 66, a first side oil cylinder and a second side oil cylinder are respectively arranged on the outer sides of the two lower modules 66, the output ends of the first side oil cylinder and the second side oil cylinder are respectively connected with the outer sides of the two lower modules 66, the two lower modules 66 are driven to be close to or far away from each other through the first side oil cylinder and the second side oil cylinder, folding and separating of the two lower modules 66 are achieved, and the half of cavities 614 of the two lower modules 66 are folded to form the second inner cavity.
The third upper die comprises a third punch 61, the third punch 61 comprises a third punch body, and a third punch part is arranged at the bottom of the third punch body and comprises a spherical inner cavity punch segment 611 and a lateral groove punch segment 612.
The second cavity comprises a ball socket part forming cavity 62 and a press joint part clamping groove 63, and the press joint part clamping groove 63 just accommodates a press joint part b of the semi-finished ball socket fitting.
The ball socket portion forming cavity 62 is communicated with the press-connection portion clamping groove 63 and is horizontally arranged in the middle of the third lower die, the length of the ball socket portion forming cavity 62 is equal to that of the ball socket portion a of the semi-finished ball socket fitting, and the total length of the ball socket portion forming cavity 62 and the press-connection portion clamping groove 63 is the total length of the semi-finished ball socket fitting.
The third lower die is further provided with an inlet and outlet groove 64, and the inlet and outlet channel is vertically arranged above the ball socket part forming cavity 62 on the third lower die and is communicated with the second inner cavity for accommodating the third punch 61 to vertically enter and exit the ball socket part forming cavity 62.
The third lower die is further provided with a vertically arranged workpiece clamping groove 65, an opening of the workpiece clamping groove 65 is upwards arranged, the workpiece clamping groove 65 is communicated with the outer side of the crimping part clamping groove 63, a gap is reserved between the bottom end of the crimping part clamping groove 63 and the bottom of the workpiece clamping groove 65, the second-state ball socket fitting is clamped by an adaptive clamp in the actual forging process conveniently, the second-state ball socket fitting is arranged between the two half cavities 614, or the clamp stretches into the second cavity from the workpiece clamping groove 65 to firmly clamp the semi-finished ball socket fitting, and the semi-finished ball socket fitting is taken out.
The third upper oil cylinder is arranged above the third upper die, the output end of the third upper oil cylinder is connected with the third upper die, and the third upper oil cylinder drives the third upper die to lift and lower, so that the die assembly and the die stripping of the third upper die and the third lower die are realized, and the forging and pressing of the first semi-finished ball socket fitting are realized.
A forging forming process of an R pin ball socket fitting specifically comprises the following steps:
And T1, preparing raw materials, namely adopting straight round steel as a raw material.
And T2, one-step forging forming, namely extending the straight round steel 3 into the first inner cavity 43 from the bottom of the first forging die through a feeding channel, enabling the top end of the straight round steel 3 to be flush with the top end of the upper round pipe groove 431, driving the first upper die 41 to descend through the first upper oil cylinder, and accordingly achieving die assembly of the first upper die and the lower die, and forging and pressing the middle upper portion of the straight round steel 3 to form a first machined part.
At this time, a first processing portion 7 having a height of n+2 and an outer diameter of r+9 is formed on the top of the straight round steel, a first crimping portion 9 having an outer diameter of r±0.4 is formed on the middle of the straight round steel, and the first processing portion 7 and the first crimping portion 9 are coaxially disposed.
The first processing portion 7 includes a first cylindrical body, an S-shaped arc transition is formed between the first cylindrical body and the first crimping portion, and a side peripheral portion of the first cylindrical body away from the first crimping portion 9 is chamfered.
And T3, secondary forging forming, namely driving the first upper die 41 to ascend through the first upper oil cylinder until demoulding of the first upper die and the lower die is realized, taking out the first machined part from the first forging die 4, and installing the first machined part in the second inner cavity of the second forging die 5, wherein the installation position of the first machined part in the second inner cavity is the same as the installation position of the first machined part in the first inner cavity.
The second upper die 51 is driven to descend by the second upper cylinder, so that the second upper and lower dies are clamped, and the first processing portion 7 and the first press-contact portion 9 of the first workpiece are forged and pressed to form a second workpiece.
The first processing part 7 is forged and pressed by the second forging die 5 to form a second processing part 8 with the height of n+0.5 and the outer diameter of R+/-1, the first press-connection part 9 is forged and pressed by the second forging die 5 to form a second press-connection part 10 with the outer diameter of r+/-0.2, and the second processing part 8 and the second press-connection part 10 are coaxially arranged.
The second processing portion 8 includes a second cylindrical body 81 and a semicircular protrusion 82 coaxially disposed up and down, the semicircular protrusion 82 is disposed at the top center of the second cylindrical body 81, and an arc transition is formed between the semicircular protrusion 82 and the second cylindrical body 81.
And T4, cutting, namely taking out the second machined part from the second forging die 5, and completely cutting off the straight round steel by the second machined part 8 and the second press joint part 10 with the length of L+/-0.2 to form the machined part.
And T5, three times of forging forming, namely placing a to-be-machined part between two half cavities of the third forging die 6, driving the two lower modules 66 to be close to each other through the first side oil cylinder and the second side oil cylinder respectively, and closing the two lower modules 66 to enable the two half cavities 614 to be closed to form a second inner cavity, and completely placing the front and rear positions of the to-be-machined part in the second inner cavity by utilizing semicircular protrusions.
The third upper oil cylinder drives the third upper die to descend, so that the die assembly of the third upper die and the die assembly of the third lower die are realized, the second processing part of the workpiece to be processed is forged and pressed, the spherical inner cavity and the lateral groove which are arranged in an extrusion and communication mode on the second processing part are utilized, meanwhile, the second processing part is extruded into a sphere, a semi-finished ball socket part is formed, the height of the semi-finished ball socket part is n+/-0.2, the outer diameter of the semi-finished ball socket part is R+/-0.2, the semi-finished ball socket part and the second crimping part at the moment are coaxial to form the semi-finished ball socket fitting, and the semi-finished ball socket fitting is forged.
And T6, driving the third upper die to ascend through the third upper oil cylinder, so as to realize demoulding of the third upper die and the third lower die, enabling an adaptive clamp to extend into the second inner cavity from the workpiece clamping groove 65 to firmly clamp the semi-finished ball socket fitting, driving the two lower modules 66 to be away from each other through the first side oil cylinder and the second side oil cylinder respectively, realizing separation of the two lower modules 66, taking out the clamp and the semi-finished ball socket fitting, and metalworking the semi-finished ball socket fitting to form an R pin ball socket fitting, wherein the height of a ball socket part of the R pin ball socket fitting is n, the outer diameter of the ball socket part is R, the radius of a crimping part is R, and the length of the crimping part b is L.
In the invention, the first forging forming die and the second forging forming die are utilized to forge and form the semi-finished ball socket fitting for many times, the situation that the inside of the forging die is extruded and deformed or collapses cannot occur in the whole forging process, the time and labor waste caused by the damage of the forging die are avoided, the semicircular protrusions 82 on the second processing part 8 are used for determining the total length of the semi-finished ball socket fitting, the ball socket fitting in the second state is positioned in the ball socket part forming cavity 62 and the clamping groove 63 in the front and back conveniently, the shape punching degree and the compactness of the semi-finished ball socket fitting in the forming process are ensured, the connection between the semicircular protrusions 82 and the second cylindrical body 81 adopts arc transition, the binding and folding (crease) between the semicircular protrusions 82 and the second cylindrical body 81 in the three-time forging forming process can be avoided, the production efficiency is finally improved, and the production benefit of a factory is further improved.
It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present invention, and various changes and modifications may be made without departing from the spirit and scope of the invention, which is defined in the appended claims. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (7)

1.一种R销球窝金具锻造成型工艺,其特征在于:具体包括以下步骤:1. A forging process for an R-pin ball and socket hardware, characterized in that it specifically comprises the following steps: T1:准备原料:采用直圆钢为原材料;T1: Prepare raw materials: use straight round steel as raw material; T2:一次锻造成型:将直圆钢安装在第一锻造模具中,利用第一锻造模具对直圆钢的中上部进行锻压,形成第一加工件,且第一加工件上位于直圆钢的顶部形成高度为n+(1~2)、外径为R-(4~9)的第一加工部、位于直圆钢的中部形成外径为r±0.4的第一压接部,且第一加工部与第一压接部同轴设置;T2: One-step forging: Install the straight round steel in the first forging die, and use the first forging die to forge the middle and upper part of the straight round steel to form a first processed part, and a first processed part with a height of n+(1~2) and an outer diameter of R-(4~9) is formed at the top of the straight round steel, and a first crimping part with an outer diameter of r±0.4 is formed at the middle of the straight round steel, and the first processed part and the first crimping part are coaxially arranged; 所述第一加工部包括第一圆柱本体,所述第一圆柱本体与第一压接部之间为S形圆弧过渡,且该第一圆柱本体远离第一压接部的一侧周部设为倒角;The first processed portion comprises a first cylindrical body, an S-shaped arc transition is formed between the first cylindrical body and the first crimping portion, and a circumference of one side of the first cylindrical body away from the first crimping portion is chamfered; T3:二次锻造成型:将第一加工件从第一锻造模具中取出,并安装在第二锻造模具中,利用第二锻造模具对第一加工件的第一加工部与第一压接部进行锻压,形成第二加工件,使得第一加工部形成高度为n±0.5、外径为R±0.5的第二加工部,使得第一压接部形成外径为r±0.2的第二压接部,且第二加工部与第二压接部同轴设置;T3: Secondary forging: The first workpiece is taken out from the first forging die and installed in the second forging die. The first processing part and the first crimping part of the first workpiece are forged by the second forging die to form a second workpiece, so that the first processing part forms a second processing part with a height of n±0.5 and an outer diameter of R±0.5, and the first crimping part forms a second crimping part with an outer diameter of r±0.2, and the second processing part and the second crimping part are coaxially arranged; 所述第二加工部包括上下同轴设置的第二圆柱本体与半圆形突起,所述半圆形突起设置在该第二圆柱本体的顶部中央,且该半圆形突起与第二圆柱本体之间为圆弧过渡;The second processing part comprises a second cylindrical body and a semicircular protrusion which are coaxially arranged up and down, wherein the semicircular protrusion is arranged at the top center of the second cylindrical body, and there is an arc transition between the semicircular protrusion and the second cylindrical body; T4:截取:将第二加工件从第二锻造模具中取出,将第二加工部与第二压接部完全截取脱离直圆钢,形成待加工件;T4: Cutting: taking the second workpiece out of the second forging die, and completely cutting the second processing portion and the second crimping portion off the straight round steel to form a workpiece to be processed; T5:三次锻造成型:将待加工件安装在第三锻造模具中,利用第三锻造模具对待加工件的第二加工部进行锻压,将第二加工部挤压成球状,同时挤出连通设置的球形内腔与侧向槽,形成半成品球窝部,且该半成品球窝部的高度为n±0.2、外径为R±0.2,此时的半成品球窝部与第二压接部同轴组成半成品球窝金具,且半成品球窝金具锻造完成;T5: Three-step forging: The workpiece to be processed is installed in the third forging die, and the second processing part of the workpiece to be processed is forged by the third forging die, and the second processing part is squeezed into a spherical shape, and the spherical inner cavity and the lateral groove that are connected are squeezed out to form a semi-finished ball socket part, and the height of the semi-finished ball socket part is n±0.2 and the outer diameter is R±0.2. At this time, the semi-finished ball socket part and the second crimping part are coaxial to form a semi-finished ball socket hardware, and the forging of the semi-finished ball socket hardware is completed; T6:成品:将半成品球窝金具取出,经过金加工形成R销球窝金具,且R销球窝金具的球窝部的高度为n、球窝部的外径为R、压接部的半径为r。T6: Finished product: The semi-finished ball and socket fitting is taken out and processed into an R-pin ball and socket fitting, wherein the height of the ball socket of the R-pin ball and socket fitting is n, the outer diameter of the ball socket is R, and the radius of the crimping portion is r. 2.根据权利要求1所述的一种R销球窝金具锻造成型工艺,其特征在于:2. The R-pin ball and socket hardware forging process according to claim 1 is characterized in that: 所述第一锻造模具包括上下设置的第一上模以及第一下模,所述第一下模具有一垂直贯穿设置的第一内腔,所述第一上模包括第一冲头;The first forging die comprises a first upper die and a first lower die arranged up and down, the first lower die has a first inner cavity arranged vertically through, and the first upper die comprises a first punch; 所述第一内腔包括同轴并连通设置的上部圆管槽、中部圆管槽以及下部圆管槽,所述上部圆管槽的内径大于中部圆管槽的内径,且上部圆管槽与中部圆管槽之间为S形圆弧过渡,所述中部圆管槽的内径大于下部圆管槽的内径,且中部圆管槽的长度大于半成品球窝金具的压接部的长度;The first inner cavity comprises an upper circular tube groove, a middle circular tube groove and a lower circular tube groove which are coaxially and connected to each other, the inner diameter of the upper circular tube groove is larger than the inner diameter of the middle circular tube groove, and an S-shaped arc transition is formed between the upper circular tube groove and the middle circular tube groove, the inner diameter of the middle circular tube groove is larger than the inner diameter of the lower circular tube groove, and the length of the middle circular tube groove is larger than the length of the crimping portion of the semi-finished ball and socket hardware; 所述第一冲头垂直向下设置,包括第一冲头本体,在所述第一冲头本体的底部中央设有第一冲部,所述第一冲部为一圆台形凹槽,且该圆台形凹槽的上底小于其下底;The first punch is vertically arranged downward, and comprises a first punch body, a first punch portion is arranged at the center of the bottom of the first punch body, the first punch portion is a truncated cone-shaped groove, and the upper bottom of the truncated cone-shaped groove is smaller than the lower bottom thereof; 所述第二锻造模具包括第二上模以及第二下模,第二下模与第一下模结构相同,所述第二上模包括第二冲头,所述第二冲头也是垂直向下设置,包括第二冲头本体,在所述第二冲头本体的底部中央设有第二冲部,且第二冲头的长度大于第一冲头;The second forging die comprises a second upper die and a second lower die, the second lower die has the same structure as the first lower die, the second upper die comprises a second punch, the second punch is also vertically downwardly arranged, comprises a second punch body, a second punch portion is arranged at the bottom center of the second punch body, and the length of the second punch is greater than that of the first punch; 所述第三锻造模具包括上下设置的第三上模和第三下模,所述第三下模具有第三内腔,所述第三上模包括第三冲头,所述第三冲头包括第三冲头本体,且第三冲头本体的底部设有第三冲部,所述第三冲部包括球形内腔冲部以及侧向槽冲部。The third forging die includes a third upper die and a third lower die which are arranged up and down, the third lower die has a third inner cavity, the third upper die includes a third punch, the third punch includes a third punch body, and a third punch portion is provided at the bottom of the third punch body, and the third punch portion includes a spherical inner cavity punch portion and a lateral groove punch portion. 3.根据权利要求1或2所述的一种R销球窝金具锻造成型工艺,其特征在于:所述下部圆管槽的内径与直圆钢的外径一致,中部圆管槽的内径不小于第一压接部的外径,所述第一压接部的外径大于直圆钢的外径,该倒角的倾斜角度与该圆台形凹槽的倾斜度一致,且所述圆台形凹槽的下底大于该第一圆柱本体外径;3. A forging process for an R-pin ball socket hardware according to claim 1 or 2, characterized in that: the inner diameter of the lower circular tube groove is consistent with the outer diameter of the straight round steel, the inner diameter of the middle circular tube groove is not less than the outer diameter of the first crimping portion, the outer diameter of the first crimping portion is larger than the outer diameter of the straight round steel, the inclination angle of the chamfer is consistent with the inclination of the truncated cone groove, and the lower bottom of the truncated cone groove is larger than the outer diameter of the first cylindrical body; 所述第二压接部的外径不大于中部圆管槽的内径,所述第二圆柱本体的外径不大于所述上部圆管槽的内径,在该第二圆柱本体远离第二压接部的一侧中部还设有半圆形突起,且该半圆形突起与第二圆柱本体圆弧过渡。The outer diameter of the second crimping portion is not larger than the inner diameter of the middle circular tube groove, and the outer diameter of the second cylindrical body is not larger than the inner diameter of the upper circular tube groove. A semicircular protrusion is also provided in the middle of one side of the second cylindrical body away from the second crimping portion, and the semicircular protrusion transitions to the arc of the second cylindrical body. 4.根据权利要求2所述的一种R销球窝金具锻造成型工艺,其特征在于:所述第二下模包括两个对称设置的下模块,每个下模块的内侧均设有一半腔室,将两个下模块合拢,两个下模块的半腔室合拢形成所述第三内腔;4. A forging process for an R-pin ball and socket hardware according to claim 2, characterized in that: the second lower die comprises two symmetrically arranged lower modules, each lower module has a half chamber on its inner side, and the two lower modules are closed together, and the half chambers of the two lower modules are closed together to form the third inner cavity; 第三内腔包括一球窝部成型腔和压接部卡接槽,所述压接部卡接槽内刚好容纳所述半成品球窝金具的压接部;The third inner cavity includes a ball socket forming cavity and a crimping portion clamping groove, wherein the crimping portion of the semi-finished ball socket fitting is just accommodated in the crimping portion of the semi-finished ball socket fitting; 所述球窝部成型腔与压接部卡接槽连通并水平设置在第二下模的中部,且球窝部成型腔的长度等于半成品球窝金具的球窝部的长度,所述球窝部成型腔与压接部卡接槽的总长为半成品球窝金具的总长。The ball socket forming cavity is connected to the crimping part snap-in groove and is horizontally arranged in the middle of the second lower mold, and the length of the ball socket forming cavity is equal to the length of the ball socket of the semi-finished ball socket hardware. The total length of the ball socket forming cavity and the crimping part snap-in groove is the total length of the semi-finished ball socket hardware. 5.根据权利要求4所述的一种R销球窝金具锻造成型工艺,其特征在于:所述第二下模上还开设有一进出槽,所述进出通道垂直设置在第二下模上位于所述球窝部成型腔的上方,且该进出通道与第三内腔连通设置,用于容纳所述第三冲头垂直进出所述球窝部成型腔。5. An R-pin ball socket hardware forging process according to claim 4 is characterized in that: an entry and exit groove is also provided on the second lower die, and the entry and exit channel is vertically arranged on the second lower die above the ball socket forming cavity, and the entry and exit channel is connected to the third inner cavity to accommodate the third punch to vertically enter and exit the ball socket forming cavity. 6.根据权利要求4所述的一种R销球窝金具锻造成型工艺,其特征在于:所述第二下模上还开设有一垂直设置的工件夹装槽,所述工件夹装槽的开口向上设置,且该工件夹装槽连通设置在所述压接部卡接槽的外侧,且所述压接部卡接槽底端与工件夹装槽槽底之间留有间隙。6. An R-pin ball socket hardware forging process according to claim 4 is characterized in that: a vertically arranged workpiece clamping groove is also provided on the second lower die, the opening of the workpiece clamping groove is arranged upward, and the workpiece clamping groove is connected to the outer side of the crimping part clamping groove, and a gap is left between the bottom end of the crimping part clamping groove and the bottom of the workpiece clamping groove. 7.根据权利要求2所述的一种R销球窝金具锻造成型工艺,其特征在于:所述第一、二冲头的外径均不大于所述上部圆管槽的内径。7. A forging process for an R-pin ball socket hardware according to claim 2, characterized in that the outer diameters of the first and second punches are not larger than the inner diameter of the upper circular tube groove.
CN202211334847.4A 2022-10-28 2022-10-28 A forging process for R-pin ball and socket hardware Active CN115647263B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211334847.4A CN115647263B (en) 2022-10-28 2022-10-28 A forging process for R-pin ball and socket hardware

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211334847.4A CN115647263B (en) 2022-10-28 2022-10-28 A forging process for R-pin ball and socket hardware

Publications (2)

Publication Number Publication Date
CN115647263A CN115647263A (en) 2023-01-31
CN115647263B true CN115647263B (en) 2025-05-13

Family

ID=84993315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211334847.4A Active CN115647263B (en) 2022-10-28 2022-10-28 A forging process for R-pin ball and socket hardware

Country Status (1)

Country Link
CN (1) CN115647263B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118180303A (en) * 2023-12-28 2024-06-14 如皋市林达线路金具有限公司 A processing technology for connecting hardware for railway transmission line

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112517816A (en) * 2020-10-16 2021-03-19 中北大学 Bidirectional intermittent differential upsetting composite extrusion forming method for outer longitudinal rib cylindrical part
CN215279713U (en) * 2021-04-15 2021-12-24 沈阳和世泰通用钛业有限公司 Forging forming die

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002153939A (en) * 2000-11-22 2002-05-28 Somic Ishikawa Inc Joint device and method of manufacturing arm thereof
CN102989947B (en) * 2012-10-22 2015-05-06 如皋市大生线路器材有限公司 Compound insulator ball socket armor clamp forging and molding process
CN106040938A (en) * 2016-06-02 2016-10-26 溧阳市金昆锻压有限公司 Combined die for forging gear shaft through moulding bed and forging technology
KR102036582B1 (en) * 2018-01-29 2019-10-25 주식회사 세림티앤디 Integrated cold forging method and apparatus therefor for weight of monolithic eccentric yoke for steering
CN114029440A (en) * 2021-09-28 2022-02-11 如皋市大生线路器材有限公司 Forging process and forging die for R pin ball socket fitting

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112517816A (en) * 2020-10-16 2021-03-19 中北大学 Bidirectional intermittent differential upsetting composite extrusion forming method for outer longitudinal rib cylindrical part
CN215279713U (en) * 2021-04-15 2021-12-24 沈阳和世泰通用钛业有限公司 Forging forming die

Also Published As

Publication number Publication date
CN115647263A (en) 2023-01-31

Similar Documents

Publication Publication Date Title
CN101947567B (en) Processing technique of flat-head hexagon bolt for cold extrusion shaping cart
CN105880308A (en) Two-time extruding die of moving contact and secondary-extruding die thereof
CN111889531B (en) Positive and negative extrusion forming die and forming method for curved bus type shell
CN201815555U (en) Machining equipment for flat-head hexagon bolt of cold-extrusion forming vehicle
CN113369330B (en) Extrusion forming process for cylindrical component
CN115647263A (en) Forging forming process for R pin ball socket hardware
CN119657679A (en) Reverse extrusion forming die for cylindrical component and reverse extrusion forming method thereof
CN114029440A (en) Forging process and forging die for R pin ball socket fitting
CN111842524A (en) Extrusion forming die and method for parts with grooves
CN114273591B (en) A W-pin ball socket hardware forging die and a process for manufacturing hardware using the die
CN217492565U (en) Cold forging device of automobile tail door connecting piece
CN206104697U (en) Welding electrode cap stamping die for manufacturing
CN214161117U (en) Mould of blade circle on area material
CN105234325A (en) Forging process for welding neck flange
KR100986238B1 (en) Manufacturing method of pipe electrode for power plug
CN114406103A (en) Profiling die structure
CN110076269B (en) Die device for processing shoe last positioning pin and processing method thereof
CN220278194U (en) Cold upsetting extrusion processing die for thin-wall pipe fitting
CN114733973A (en) Processing technology and processing die for automobile armrest frame
CN113695442A (en) Method and apparatus for forming rounded corners of box-shaped member
CN219520375U (en) Electric power fitting wire clamp series die forging die
CN223789387U (en) Bushing forming apparatus and bushing forming system
CN206373269U (en) Integrated rivet processing device
CN204912475U (en) Pommelled horse type plinth cold -punching mould
CN113369326A (en) Open inner type progressive extrusion forming die based on current auxiliary heating

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant