CN115637707A - Tunnel foundation pit supporting structure and construction method thereof - Google Patents
Tunnel foundation pit supporting structure and construction method thereof Download PDFInfo
- Publication number
- CN115637707A CN115637707A CN202211332911.5A CN202211332911A CN115637707A CN 115637707 A CN115637707 A CN 115637707A CN 202211332911 A CN202211332911 A CN 202211332911A CN 115637707 A CN115637707 A CN 115637707A
- Authority
- CN
- China
- Prior art keywords
- supporting
- support
- foundation pit
- plate
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
技术领域technical field
本发明属于基坑支护施工技术领域,具体涉及一种隧道基坑支护结构及其施工方法。The invention belongs to the technical field of foundation pit support construction, and in particular relates to a tunnel foundation pit support structure and a construction method thereof.
背景技术Background technique
随着我国城市轨道交通建设的蓬勃发展,明挖基坑工程数量逐渐增多,开挖深度逐渐加深,结构形式复杂多样。地铁车站多位于城市繁华区段,周边环境复杂,建筑物和各类管线密集,对基坑支护效果和变形控制的要求越来越高。With the vigorous development of my country's urban rail transit construction, the number of open-excavation foundation pit projects is gradually increasing, the excavation depth is gradually deepening, and the structural forms are complex and diverse. Most of the subway stations are located in the bustling areas of the city, the surrounding environment is complex, buildings and various pipelines are dense, and the requirements for the effect of foundation pit support and deformation control are getting higher and higher.
现有技术中,如公开号为CN109356168A的中国发明专利申请文献,公开了一种钢支撑活络头,包括底座、与底座活动连接的外筒组件,底座包括底板、安装在底板上的至少两个螺杆,螺杆上螺纹连接有螺母,外筒组件包括外筒、安装在外筒一端的限位板,限位板上设置有供螺杆穿过的开孔,螺母位于底板与限位板之间,通过旋转螺母,调节限位板与底板之间的距离。In the prior art, for example, the Chinese invention patent application document with the publication number CN109356168A discloses a steel supporting joint, including a base, an outer cylinder assembly movably connected with the base, the base includes a bottom plate, and at least two The screw is threaded with a nut. The outer cylinder assembly includes an outer cylinder and a limiting plate installed at one end of the outer cylinder. The limiting plate is provided with an opening for the screw to pass through. The nut is located between the bottom plate and the limiting plate. Rotate the nut to adjust the distance between the limiting plate and the bottom plate.
在上述现有技术中,通过螺杆、螺母对易产生轴力损失的活络端进行固定,在固定或释放过程中需要不断转动调节螺母,需要消耗较多的时间,不利于其快速的安装及拆除,影响施工进度。In the above-mentioned prior art, the active end, which is prone to loss of axial force, is fixed by screws and nuts, and the adjusting nut needs to be rotated continuously during the fixing or releasing process, which consumes a lot of time and is not conducive to its rapid installation and removal. , affecting the construction progress.
因此,需要设计一种不易产生轴力损失,同时便于快速安装及拆除的隧道基坑支护结构及其施工方法来解决目前所面临的技术问题。Therefore, it is necessary to design a tunnel foundation pit support structure and its construction method that are not prone to axial force loss and are easy to install and dismantle quickly to solve the current technical problems.
发明内容Contents of the invention
针对现有技术中所存在的不足,本发明提供了一种不易产生轴力损失,同时便于快速安装及拆除的隧道基坑支护结构及其施工方法。Aiming at the deficiencies in the prior art, the present invention provides a tunnel foundation pit support structure that is not prone to loss of axial force and is convenient for quick installation and dismantling, and a construction method thereof.
本发明的技术方案为:隧道基坑支护结构,包括支撑杆钢管,所述支撑钢管的两端可拆卸固定设置有连接钢管,所述连接钢管上与所述支撑钢管相背离的一端固定设置有支撑板,所述支撑板上与所述连接钢管相背离的一侧设置有用于放置千斤顶的托槽,所述托槽两侧的所述支撑板上对称设置有滑筒,所述滑筒的内部滑动设置有支撑脚,所述支撑脚的顶部开设有插口,所述插口的插装有支撑板,所述支撑板为直角梯形板体。The technical solution of the present invention is: the support structure of the tunnel foundation pit, including a support rod steel pipe, the two ends of the support steel pipe are detachably and fixedly provided with connecting steel pipes, and the end of the connecting steel pipe that is away from the supporting steel pipe is fixedly arranged There is a support plate, the side of the support plate that is away from the connecting steel pipe is provided with a bracket for placing a jack, and the support plates on both sides of the bracket are symmetrically provided with sliders, and the sliders There are support feet slidingly arranged inside the support feet, and sockets are opened on the top of the support feet, and a support plate is inserted into the socket, and the support plate is a right-angled trapezoidal plate body.
所述托槽的内部沿所述连接钢管的轴向设置有隔板,所述隔板垂直固定设置在所述托槽的内底部,所述隔板两侧的所述托槽内部均设置有千斤顶。The inside of the bracket is provided with a partition along the axial direction of the connecting steel pipe, and the partition is fixed vertically on the inner bottom of the bracket, and the inside of the bracket on both sides of the partition is provided with jack.
两个所述千斤顶的缸体前端分别固定设置有前端板,两个所述千斤顶的缸体后端均与一个后端板固定连接。The front ends of the cylinder bodies of the two jacks are respectively fixedly provided with front end plates, and the rear ends of the cylinder bodies of the two jacks are fixedly connected with a rear end plate.
所述前端板及所述后端板的顶部均开设有提拉孔。The tops of the front end plate and the rear end plate are provided with lifting holes.
所述隔板两侧的所述托槽内部设置有定位槽,所述定位槽的顶部开设有与所述千斤顶的缸体外侧相匹配的弧形槽。The brackets on both sides of the partition are provided with positioning grooves inside, and the top of the positioning grooves is provided with an arc-shaped groove matching the outside of the cylinder of the jack.
所述滑筒的内侧具有滑动腔,所述支撑脚具有与所述滑动腔相匹配的十字管,所述插口开设在所述十字管的顶部。The inner side of the sliding cylinder has a sliding cavity, the supporting foot has a cross tube matching the sliding cavity, and the socket is opened on the top of the cross tube.
所述十字管上与所述滑筒相背离的一端固定设置有支撑端板,所述支撑端板上与所述十字管相背离的一侧固定设置有垫板。A support end plate is fixedly provided on the end of the cross tube away from the sliding cylinder, and a backing plate is fixedly provided on the side of the support end plate away from the cross tube.
所述支撑板与所述连接钢管之间设置有加强板,所述加强板之间设置有侧板。A reinforcing plate is arranged between the supporting plate and the connecting steel pipe, and a side plate is arranged between the reinforcing plates.
所述支撑板的斜边上均匀开设有齿牙。Teeth are uniformly formed on the hypotenuse of the support plate.
隧道基坑支护的施工方法,包括以下步骤:The construction method of tunnel foundation pit support comprises the following steps:
采用如上任一项所述的隧道基坑支护结构;Adopt the tunnel foundation pit support structure as described in any one of the above;
当开挖出一道支撑的位置时,吊装隧道基坑支护结构就位,用倒链配合就位并微调,正位后对支撑脚端部与围檩间采用细石快硬砼填实找平,保证支撑脚端部接触紧密,控制千斤顶动作按设计要求施加预应力;When the position of a support is excavated, the supporting structure of the foundation pit of the hoisting tunnel is put in place, and it is put in place with an inverted chain and fine-tuned. , to ensure that the ends of the supporting feet are in close contact, and the action of the jack is controlled to apply prestress according to the design requirements;
预应力施加到设计要求后,将支撑板插入至插口内部进行支撑,保证紧密接触,防止预应力损失,然后回油松开千斤顶,完成隧道基坑支护结构支撑安装和预应力施加。After the prestress is applied to the design requirements, insert the support plate into the socket for support to ensure close contact and prevent the loss of prestress, and then return the oil to loosen the jack to complete the support installation and prestress application of the tunnel foundation pit support structure.
本发明的有益效果:Beneficial effects of the present invention:
(1)本发明中,当开挖出一道支撑的位置时,吊装隧道基坑支护结构就位,用倒链配合就位并微调,向托槽内部放置千斤顶,正位后对支撑脚端部与围檩间采用细石快硬砼填实找平,保证支撑脚端部接触紧密,控制千斤顶动作按设计要求施加预应力,预应力施加到设计要求后,将支撑板插入至插口内部进行支撑,保证紧密接触,防止预应力损失,然后回油松开千斤顶,完成隧道基坑支护结构支撑安装和预应力施加;(1) In the present invention, when the position of a support is excavated, the support structure of the tunnel foundation pit is hoisted in place, and the chain is used to fit in place and fine-tuned, and a jack is placed inside the bracket, and the support foot is aligned after being in the correct position. The gap between the head and the purlin is filled and leveled with fine stone quick-hardening concrete to ensure that the ends of the supporting feet are in close contact, and the action of the jack is controlled to apply prestress according to the design requirements. After the prestress is applied to the design requirements, insert the support plate into the socket for support , to ensure close contact and prevent the loss of prestress, and then return the oil to loosen the jack to complete the support installation and prestress application of the tunnel foundation pit support structure;
(2)支撑板的侧面两端分别通过两个支撑脚与围檩间支撑,提升支撑的可靠性,避免独立支撑时一个支撑板滑脱而造成轴力损失,保证支撑效果,并且支撑板便于快速安装及拆除,有利于提升施工进度。(2) The two ends of the side of the support plate are respectively supported by two support feet and the purlins to improve the reliability of the support, avoid the loss of axial force caused by a support plate slipping when independently supported, and ensure the support effect, and the support plate is convenient and fast Installation and dismantling are conducive to improving the construction progress.
附图说明Description of drawings
图1为本发明中隧道基坑支护结构的结构示意图。Fig. 1 is a structural schematic diagram of a tunnel foundation pit supporting structure in the present invention.
图2为本发明中隧道基坑支护结构的局部结构示意图之一。Fig. 2 is one of the local structural schematic diagrams of the tunnel foundation pit support structure in the present invention.
图3为本发明中隧道基坑支护结构的局部结构示意图之二。Fig. 3 is the second schematic diagram of the local structure of the tunnel foundation pit support structure in the present invention.
图4为本发明中隧道基坑支护结构的局部结构示意图之三。Fig. 4 is the third schematic diagram of the partial structure of the tunnel foundation pit support structure in the present invention.
图5为本发明中支撑板的局部结构示意图。Fig. 5 is a schematic diagram of a partial structure of a support plate in the present invention.
具体实施方式Detailed ways
现在将参照附图来详细描述本发明的各种示例性实施例。对示例性实施例的描述仅仅是说明性的,决不作为对本发明及其应用或使用的任何限制。本发明可以以许多不同的形式实现,不限于这里所述的实施例。提供这些实施例是为了使本发明透彻且完整,并且向本领域技术人员充分表达本发明的范围。应注意到:除非另外具体说明,否则在这些实施例中阐述的部件和步骤的相对布置、材料的组分、数字表达式和数值应被解释为仅仅是示例性的,而不是作为限制。Various exemplary embodiments of the present invention will now be described in detail with reference to the accompanying drawings. The description of the exemplary embodiments is illustrative only and in no way restrictive of the invention, its application or uses. The present invention can be implemented in many different forms and is not limited to the embodiments described here. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art. It should be noted that relative arrangements of parts and steps, compositions of materials, numerical expressions and numerical values set forth in these embodiments should be interpreted as illustrative only and not as limiting, unless specifically stated otherwise.
本发明中使用的“第一”、“第二”以及类似的词语并不表示任何顺序、数量或者重要性,而只是用来区分不同的部分。“包括”或者“包含”等类似的词语意指在该词前的要素涵盖在该词后列举的要素,并不排除也涵盖其他要素的可能。“上”、“下”、“左”、“右”等仅用于表示相对位置关系,当被描述对象的绝对位置改变后,则该相对位置关系也可能相应地改变。"First", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different parts. Words like "comprising" or "comprising" mean that the elements preceding the word cover the elements listed after the word, and do not exclude the possibility of also covering other elements. "Up", "Down", "Left", "Right" and so on are only used to indicate the relative positional relationship. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
如图1至5所示,隧道基坑支护结构,包括支撑杆钢管1,支撑钢管1的两端可拆卸固定设置有连接钢管2,连接钢管2上与支撑钢管1相背离的一端固定设置有支撑板3,支撑板3焊接固定在连接钢管2的端部,支撑板3上与连接钢管2相背离的一侧设置有用于放置千斤顶的托槽8,托槽8焊接固定在支撑板3的一侧中部,托槽8两侧的支撑板上对称设置有滑筒4,滑筒4的内部滑动设置有支撑脚5,支撑脚5的顶部开设有插口,插口51的插装有支撑板6,支撑板6为直角梯形板体;在本实施例中,当开挖出一道支撑的位置时,然后吊装隧道基坑支护结构就位,用倒链配合就位并微调,向托槽8内部放置千斤顶7,正位后对支撑脚5端部与围檩间采用细石快硬砼填实找平,保证支撑脚5端部接触紧密,控制千斤顶动作按设计要求施加预应力,预应力施加到设计要求后,将支撑板6插入至插口51内部进行支撑,保证紧密接触,防止预应力损失,然后回油松开千斤顶7,完成隧道基坑支护结构支撑安装和预应力施加;支撑板3的侧面两端分别通过两个支撑脚5与围檩间支撑,提升支撑的可靠性,避免独立支撑时一个支撑板6滑脱而造成轴力损失,保证支撑效果,并且支撑板6便于快速安装及拆除,有利于提升施工进度。As shown in Figures 1 to 5, the tunnel foundation pit support structure includes a support rod steel pipe 1, the two ends of the support steel pipe 1 are detachably fixed with a connecting
在一些实施例中,托槽8的内部沿连接钢管2的轴向设置有隔板81,隔板81垂直固定设置在托槽8的内底部,隔板81的底部焊接固定在托槽8的内底部,隔板81两侧的托槽8内部均设置有千斤顶7,通过隔板81将托槽8内部分隔出两个区域,方便与托槽8内部的两个千斤顶7进行定位,保证千斤顶7在使用过程中的稳定性。In some embodiments, the inside of the
在一些实施例中,两个千斤顶7的缸体前端分别固定设置有前端板72,前端板72通过螺栓装配固定在千斤顶7的缸体前端,两个千斤顶7的缸体后端均与一个后端板71固定连接,后端板71通过螺栓装配固定在千斤顶7的缸体后端,通过后端板71将两个千斤顶7连接成一体结构,能保持两个千斤顶7的顶伸力一致。In some embodiments, the front ends of the cylinder body of the two jacks 7 are respectively fixedly provided with
在一些实施例中,前端板72及后端板71的顶部均开设有提拉孔73,通过提拉孔73方便向托槽8内部放入千斤顶7,或从托槽8内部将千斤顶7取出。In some embodiments, the tops of the
在一些实施例中,隔板81两侧的托槽8内部设置有定位槽82,定位槽82的顶部开设有与千斤顶7的缸体外侧相匹配的弧形槽,通过定位槽82顶部的弧形槽能够对对千斤顶7缸体进行定位,进一步提升其稳定性。In some embodiments,
在一些实施例中,滑筒4的内侧具有滑动腔41,支撑脚5具有与滑动腔41相匹配的十字管52,插口51开设在十字管52的顶部,十字管52的四周分别与滑动腔41的内部四周相接触滑动连接。In some embodiments, the inner side of the sliding cylinder 4 has a sliding
在一些实施例中,十字管52上与滑筒4相背离的一端固定设置有支撑端板53,支撑端板53上与十字管52相背离的一侧固定设置有垫板54,支撑端板53焊接固定子啊十字管52的端部,垫板54采用橡胶板支撑,能够在支撑端板53与围檩间起到一定缓冲作用,同时能够增大支撑端板53与围檩间的摩擦力。In some embodiments, the end of the
在一些实施例中,支撑板3与连接钢管2之间设置有加强板31,加强板31为直角梯形板体,加强板31之间设置有侧板32,侧板32、加强板31、支撑板3及连接钢管2之间均通过焊接方式固定。In some embodiments, a reinforcing
在一些实施例中,如图5所示,支撑板6的斜边61上均匀开设有齿牙62,通过齿牙62能够避免支撑板6在插口51内部滑移,保证支撑的稳定性。In some embodiments, as shown in FIG. 5 ,
作为支撑钢管1与连接钢管2可拆卸固定连接的一种实施方式,支撑钢管1的两端均设置有法兰盘,连接钢管2上靠近支撑钢管1一端设置有法兰盘,支撑钢管1与连接钢管2通过法兰盘可拆卸固定连接。As an embodiment of the detachable and fixed connection between the supporting steel pipe 1 and the connecting
在一些实施例中,公开了一种隧道基坑支护的施工方法,包括以下步骤:In some embodiments, a construction method for tunnel foundation pit support is disclosed, comprising the following steps:
采用上述任一实施例中的隧道基坑支护结构;Adopt the tunnel foundation pit support structure in any of the above-mentioned embodiments;
当开挖出一道支撑的位置时,然后吊装隧道基坑支护结构就位,用倒链配合就位并微调,正位后对支撑脚端部与围檩间采用细石快硬砼填实找平,保证支撑脚端部接触紧密,控制千斤顶动作按设计要求施加预应力;When the position of a support is excavated, then the supporting structure of the tunnel foundation pit is hoisted in place, fitted with an inverted chain and fine-tuned. Leveling, to ensure that the ends of the supporting feet are in close contact, and to control the action of the jack to apply prestress according to the design requirements;
预应力施加到设计要求后,将支撑板插入至插口内部进行支撑,保证紧密接触,防止预应力损失,然后回油松开千斤顶,完成隧道基坑支护结构支撑安装和预应力施加。After the prestress is applied to the design requirements, insert the support plate into the socket for support to ensure close contact and prevent the loss of prestress, and then return the oil to loosen the jack to complete the support installation and prestress application of the tunnel foundation pit support structure.
加强对隧道基坑支护结构支撑预应力的观察,在第一次加预应力后12小时内观测预应力损失及墙体水平位移,并复加预应力至设计值。Strengthen the observation of the support prestress of the support structure of the tunnel foundation pit, observe the loss of prestress and the horizontal displacement of the wall within 12 hours after the first prestress is added, and add the prestress to the design value.
下一道隧道基坑支护结构的预应力施加后,上一道隧道基坑支护结构支撑的应力会减小。此时,根据监测单位数据对上一道隧道基坑支护结构支撑补加预应力,直至达到设计要求。After the prestress of the supporting structure of the foundation pit of the next tunnel is applied, the stress of the supporting structure of the supporting structure of the foundation pit of the previous tunnel will decrease. At this time, according to the data of the monitoring unit, prestress is added to the supporting structure of the foundation pit of the previous tunnel until the design requirements are met.
当昼夜温差过大导致隧道基坑支护结构支撑预应力损失时,立即在当天低温时段复加相应隧道基坑支护结构的预应力至设计值。When the large temperature difference between day and night leads to the loss of the supporting prestress of the tunnel foundation pit support structure, immediately increase the prestress of the corresponding tunnel foundation pit support structure to the design value during the low temperature period of the day.
至此,已经详细描述了本发明的各实施例。为了避免遮蔽本发明的构思,没有描述本领域所公知的一些细节。本领域技术人员根据上面的描述,完全可以明白如何实施这里公开的技术方案。So far, the embodiments of the present invention have been described in detail. Certain details well known in the art have not been described in order to avoid obscuring the inventive concept. Based on the above description, those skilled in the art can fully understand how to implement the technical solutions disclosed herein.
以上所述实施例仅表达了本发明的部分实施方式,其描述较为具体和详细,但并不能因此而理解为对发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only express some implementations of the present invention, and the descriptions thereof are more specific and detailed, but should not be construed as limiting the scope of the patent for the invention. It should be pointed out that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent for the present invention should be based on the appended claims.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211332911.5A CN115637707A (en) | 2022-10-28 | 2022-10-28 | Tunnel foundation pit supporting structure and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211332911.5A CN115637707A (en) | 2022-10-28 | 2022-10-28 | Tunnel foundation pit supporting structure and construction method thereof |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115637707A true CN115637707A (en) | 2023-01-24 |
Family
ID=84946177
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211332911.5A Pending CN115637707A (en) | 2022-10-28 | 2022-10-28 | Tunnel foundation pit supporting structure and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115637707A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116641397A (en) * | 2023-06-26 | 2023-08-25 | 华东建筑设计研究院有限公司 | Concrete axial force servo supporting system capable of actively controlling deformation |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10168881A (en) * | 1996-12-10 | 1998-06-23 | Nippon Steel Metal Prod Co Ltd | Support structure using sheet piles for earth retaining material |
| CN102720201A (en) * | 2012-07-02 | 2012-10-10 | 中建三局第二建设工程有限责任公司 | Support change construction building method implemented by using main structure of building |
| CN209636806U (en) * | 2018-12-11 | 2019-11-15 | 宏润建设集团股份有限公司 | A kind of steel support structure |
| CN211228518U (en) * | 2019-09-05 | 2020-08-11 | 中铁十六局集团北京轨道交通工程建设有限公司 | A steel tube support structure |
| CN114250788A (en) * | 2021-12-02 | 2022-03-29 | 江苏华东地质建设集团有限公司 | Assembly type square and rectangular tubular steel supporting beam system for foundation pit supporting |
-
2022
- 2022-10-28 CN CN202211332911.5A patent/CN115637707A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10168881A (en) * | 1996-12-10 | 1998-06-23 | Nippon Steel Metal Prod Co Ltd | Support structure using sheet piles for earth retaining material |
| CN102720201A (en) * | 2012-07-02 | 2012-10-10 | 中建三局第二建设工程有限责任公司 | Support change construction building method implemented by using main structure of building |
| CN209636806U (en) * | 2018-12-11 | 2019-11-15 | 宏润建设集团股份有限公司 | A kind of steel support structure |
| CN211228518U (en) * | 2019-09-05 | 2020-08-11 | 中铁十六局集团北京轨道交通工程建设有限公司 | A steel tube support structure |
| CN114250788A (en) * | 2021-12-02 | 2022-03-29 | 江苏华东地质建设集团有限公司 | Assembly type square and rectangular tubular steel supporting beam system for foundation pit supporting |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116641397A (en) * | 2023-06-26 | 2023-08-25 | 华东建筑设计研究院有限公司 | Concrete axial force servo supporting system capable of actively controlling deformation |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203296780U (en) | Supporting and protecting lining device used for preventing surrounding rock from large deformation in underground cavern construction | |
| CN105465481A (en) | Construction method for jacking structure of pipe jacking work well | |
| CN103032075B (en) | Construction method for building ground inlet and outlet type shield tunnel | |
| CN205479706U (en) | Push pipe work jing ding advances structure | |
| CN104234723A (en) | Self-propelled mobile template support trolley for open trench tunnel with rectangular cross section | |
| CN104314006B (en) | Towards the high-performance slide device of large-tonnage pushing tow engineering | |
| CN115637707A (en) | Tunnel foundation pit supporting structure and construction method thereof | |
| CN206036390U (en) | Pipeline rising -falling tone is put by paper -back edition | |
| CN115522950A (en) | A ring-cut steel blade foot device for pipe jacking construction in soft ground and silt environment | |
| CN110258514B (en) | A kind of steel guide wall for underground continuous wall and construction method thereof | |
| CN1260503C (en) | Construction technology of relay jacking for glass fiber reinforced plastics sand-inclusion pipe-jacking and apparatus of device thereof | |
| CN114856594A (en) | Reaction device and construction method for shield starting | |
| CN201865672U (en) | Support structure for soft tunnel surrounding rock | |
| CN108643167A (en) | The slotting shape steel rolled stock type TRD engineering methods wall and its construction method of one type anchor pole | |
| CN210459303U (en) | Inspection well repairing device | |
| CN211200406U (en) | Pipe groove support device | |
| CN218204314U (en) | Double-liquid cement grouting machine | |
| CN117846611A (en) | Servo-tough support structure and construction technology for shallow buried tunnel | |
| CN111577320A (en) | A kind of high safety civil engineering tunnel support | |
| CN207906578U (en) | A kind of quick positioning apparatus of pipeline | |
| CN209585109U (en) | The assembled piping lane of pile wall interaction | |
| CN204224990U (en) | Towards the high-performance slide device of large-tonnage pushing tow engineering | |
| CN210622813U (en) | An underground pressurized shield tunnel lining structure | |
| CN218716820U (en) | Segment support for subway tunnel construction | |
| CN107778029B (en) | Concrete curing method for buried pipe in structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |