CN115627778A - Combined construction method for waist rail and structural side wall of cover-excavation top-down subway station - Google Patents

Combined construction method for waist rail and structural side wall of cover-excavation top-down subway station Download PDF

Info

Publication number
CN115627778A
CN115627778A CN202211402072.XA CN202211402072A CN115627778A CN 115627778 A CN115627778 A CN 115627778A CN 202211402072 A CN202211402072 A CN 202211402072A CN 115627778 A CN115627778 A CN 115627778A
Authority
CN
China
Prior art keywords
wall
reinforcement
waist beam
side wall
structural side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211402072.XA
Other languages
Chinese (zh)
Inventor
王蒙
贾建伟
张泽鑫
孙鹏
付杨坤
朱盼盼
王勋
张彦栋
任富芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN202211402072.XA priority Critical patent/CN115627778A/en
Publication of CN115627778A publication Critical patent/CN115627778A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/02—Foundation pits
    • E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00—Independent underground or underwater structures; Retaining walls
    • E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18—Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明公开了一种盖挖逆作地铁车站腰梁、结构侧墙合建施工方法,步骤如下:1)在围护结构中,预埋腰梁抗剪钢筋的锚固段;2)在基坑开挖至腰梁设计标高时,施作垫层、施工合建部分,合建部分的主体是腰梁,腰梁的宽度与结构侧墙的厚度相同,在腰梁的上方和下方均设有引墙,合建部分的钢筋包括腰梁钢筋和结构侧墙钢筋,其中结构侧墙钢筋贯穿整个合建部分,设有曝露的接驳器;腰梁钢筋满足结构侧墙厚度要求、满足腰梁受力要求;最后采用与结构侧墙混凝土标号相同的混凝土浇筑合建部分;3)进行后续基坑土方开挖,至底板设计标高后施工底板以及后续侧墙。本发明可以不用拆除腰梁,简化施工流程、减少工作量,缩短施工工期,降低施工成本。

Figure 202211402072

The invention discloses a construction method for combined construction of a waist beam and a structural side wall of a subway station by cover-excavation, the steps are as follows: 1) in the enclosure structure, the anchorage section of the shear reinforcement of the waist beam is pre-embedded; 2) in the foundation pit When the excavation reaches the design elevation of the waist beam, the cushion layer and the joint construction part shall be constructed. The main body of the joint construction part is the waist beam. The width of the waist beam is the same as the thickness of the side wall of the structure. Leading wall, the reinforcement of the joint construction part includes waist beam reinforcement and structural side wall reinforcement, in which the structural side wall reinforcement runs through the entire joint construction part, with exposed connectors; the waist beam reinforcement meets the thickness requirements of the structural side wall and the load of the waist beam Requirements; Finally, use the same concrete grade as the structural side wall concrete to pour the combined construction part; 3) Carry out subsequent foundation pit earthwork excavation, and construct the bottom slab and subsequent side walls after reaching the design elevation of the bottom slab. The invention does not need to dismantle the waist beam, simplifies the construction process, reduces the workload, shortens the construction period and reduces the construction cost.

Figure 202211402072

Description

一种盖挖逆作地铁车站腰梁、结构侧墙合建施工方法A combined construction method of cover-excavation and reverse-work subway station waist beams and structural side walls

技术领域technical field

本发明涉及盖挖逆作地铁车站的施工方法,特别是一种盖挖逆作地铁车站腰梁、结构侧墙合建施工方法。The invention relates to a construction method for cover-dig and upside-down construction of a subway station, in particular to a combined construction method for cover-dig upside down construction of a waist beam and structural side walls of a subway station.

背景技术Background technique

深基坑工程中,混凝土支撑腰梁具有很好的强度、刚度、稳定性,且施工做法简单,在许多基坑支护体系中得到广泛的应用。但腰梁的设置经常与结构侧墙在空间位置冲突。盖挖逆作法设计工艺中需等待底板结构达到强度后,进行支撑腰梁的拆除工作,方可施工结构侧墙。考虑到腰梁及支撑安装、浇筑、后续拆除工程量大,涉及到底部支撑平台搭设、机械安装、结构切割移除、支撑平台拆除等多道工序,拆除施工占结构施工关键线路时间较长。同时,混凝土腰梁下为侧墙引墙以及下部侧墙预留钢筋,用于腰梁拆除的支撑架安装困难。结合施工工期紧迫,拆除施工制约地铁车站整体施工进度。因此需要设计一种可以不用拆除腰梁的施工方法。In deep foundation pit engineering, the concrete support waist beam has good strength, stiffness and stability, and the construction method is simple, so it is widely used in many foundation pit support systems. However, the setting of the waist beam often conflicts with the spatial position of the structural side wall. In the design process of the cover-excavation method, it is necessary to wait for the base plate structure to reach its strength before removing the supporting waist beams before constructing the structural side walls. Considering that the installation, pouring, and subsequent demolition of the lumbar beams and supports is a large amount of work, involving multiple processes such as the erection of the bottom support platform, mechanical installation, structural cutting and removal, and support platform removal, the demolition construction takes up a long time for the key line of structural construction. At the same time, steel bars are reserved under the concrete waist beam for the lead wall of the side wall and the lower side wall, and it is difficult to install the supporting frame for the removal of the waist beam. Combined with the tight construction period, the demolition construction restricts the overall construction progress of the subway station. Therefore need to design a kind of construction method that can not dismantle waist beam.

发明内容Contents of the invention

本发明为解决公知技术中存在的技术问题而提供一种盖挖逆作地铁车站腰梁、结构侧墙合建方法,可以不用拆除腰梁,简化施工流程、减少工作量,缩短施工工期,降低施工成本。In order to solve the technical problems existing in the known technology, the present invention provides a combined construction method of the waist beam and structural side wall of the subway station by cover and excavation, which can simplify the construction process, reduce the workload, shorten the construction period, and reduce the Construction costs.

本发明为解决公知技术中存在的技术问题所采取的技术方案是:一种盖挖逆作地铁车站腰梁、结构侧墙合建施工方法,采用以下步骤:The technical solution adopted by the present invention to solve the technical problems existing in the known technology is: a construction method for combined construction of waist beams and structural side walls of a subway station with cover and excavation, and adopts the following steps:

1)在车站围护结构施工中,预埋腰梁抗剪钢筋的锚固段,锚固段设有抗剪钢筋接驳器;1) In the construction of the station enclosure structure, the anchorage section of the waist beam shear reinforcement is pre-embedded, and the anchorage section is provided with a shear reinforcement connector;

2)在基坑开挖至腰梁设计标高时,施作垫层、剔凿出预埋的抗剪钢筋接驳器、施工合建部分,所述合建部分的主体是腰梁,所述腰梁的宽度与结构侧墙的厚度相同,在所述腰梁的上方设有上引墙,下方设有下引墙,在施工合建部分之前施工合建部分的外侧防水层,然后绑扎合建部分的钢筋,包括腰梁钢筋和结构侧墙钢筋,其中结构侧墙钢筋贯穿整个合建部分,设有曝露于所述上引墙之上的接驳器Ⅰ以及曝露于下引墙之下的接驳器Ⅱ,在结构侧墙钢筋上固定有曝露于所述上引墙之上的钢板止水带;腰梁钢筋满足结构侧墙厚度要求、满足腰梁受力要求,腰梁钢筋中的抗剪钢筋是由围护结构中预留的锚固段接长至腰梁内的,在每根接长抗剪钢筋的连接部位涂有环形遇水膨胀止水胶;最后采用与结构侧墙混凝土标号相同的混凝土浇筑合建部分;2) When the foundation pit is excavated to the design elevation of the waist beam, the cushion layer is applied, the pre-buried shear steel bar connector is excavated, and the joint construction part is constructed. The main body of the joint construction part is the waist beam. The width of the waist beam is the same as the thickness of the side wall of the structure. An upper lead-in wall is set above the waist beam and a lower lead-in wall is set below. Before the construction of the joint construction part, the outer waterproof layer of the joint construction part is constructed and then bound Reinforcement of the construction part, including waist beam reinforcement and structural side wall reinforcement, wherein the structural side wall reinforcement runs through the entire joint construction part, and is provided with a connector I exposed on the upper leading wall and exposed under the lower leading wall The connector II of the structural side wall is fixed with a steel plate waterstop exposed on the upper leading wall; the waist beam reinforcement meets the thickness requirements of the structural side wall and the force requirements of the waist beam, and the resistance of the waist beam reinforcement The shear reinforcement is extended to the waist beam by the anchorage section reserved in the enclosure structure, and the joint of each extended shear reinforcement is coated with a ring-shaped water-swellable waterproof glue; finally, the concrete label of the structural side wall is used The same concrete pouring composite part;

3)在合建部分施工完成后,进行后续基坑土方开挖,至底板设计标高后施工底板以及后续侧墙,其中后续侧墙包括下部墙体和上部墙体,首先逆作下部墙体,然后顺作上部墙体,在逆作下部墙体之前,在围护结构表面施工与合建部分的外侧防水层衔接的下部墙体的外侧防水层;在合建部分底部固定遇水膨胀止水胶条;然后绑扎下部墙体钢筋,下部墙体钢筋的主筋与接驳器Ⅱ连接,在下部墙体的钢筋结构中固定注浆导管Ⅱ,所述注浆导管Ⅱ的出口位于所述下引墙与所述下部墙体的接缝处,最后浇筑下墙体混凝土;在顺作上部墙体之前,在围护结构表面施工与合建部分的外侧防水层衔接的上部墙体的外侧防水层;然后绑扎上部墙体钢筋,上部墙体钢筋的主筋与接驳器Ⅰ连接,在上部墙体的钢筋结构中固定注浆导管Ⅰ,所述注浆导管Ⅰ的出口位于所述上引墙与所述上部墙体的接缝处,最后浇筑上部墙体混凝土;至此已经完成了结构侧墙的施工。3) After the construction of the joint construction part is completed, the follow-up excavation of the foundation pit shall be carried out, and the bottom slab and subsequent side walls shall be constructed after reaching the design level of the bottom slab. The subsequent side walls include the lower wall and the upper wall. Then make the upper wall along the way, and before reverse the lower wall, construct the outer waterproof layer of the lower wall connected with the outer waterproof layer of the joint construction part on the surface of the enclosure structure; fix the water-swelling waterstop at the bottom of the joint construction part Glue strips; then bind the lower wall reinforcement, the main reinforcement of the lower wall reinforcement is connected to the connector II, and the grouting conduit II is fixed in the reinforcement structure of the lower wall, and the outlet of the grouting conduit II is located in the lower lead At the joint between the wall and the lower wall, the lower wall concrete is poured at last; before the upper wall is built, the outer waterproof layer of the upper wall connected with the outer waterproof layer of the joint construction part is constructed on the surface of the enclosure structure Then bind the upper wall reinforcement, the main reinforcement of the upper wall reinforcement is connected with the connector I, and the grouting conduit I is fixed in the reinforcement structure of the upper wall, and the outlet of the grouting conduit I is located between the upper lead wall and the At the joints of the upper wall, the upper wall concrete is finally poured; so far, the construction of the structural side wall has been completed.

所述步骤2),合建部分的外侧防水层,剔凿部位是采用水泥基渗透结晶性防水涂料涂刷而成的水泥基渗透结晶防水涂层,其余部位铺设防水卷材,所述步骤3),下部墙体的外侧防水层和上部墙体的外侧防水层均采用防水卷材铺设,在与合建部分外侧的防水层的衔接处设置防水卷材加强层。The step 2), the outer waterproof layer of the joint construction part, the chiseled part is a cement-based osmotic crystalline waterproof coating painted with cement-based osmotic crystalline waterproof coating, and the rest of the parts are laid with waterproof coiled materials, and the step 3 ), the outer waterproof layer of the lower wall and the outer waterproof layer of the upper wall are laid with waterproof membranes, and a waterproof membrane reinforcement layer is set at the connection with the outer waterproof layer of the joint construction part.

本发明具有的优点和积极效果是:通过调整临时支护结构腰梁的施工方案,将腰梁的宽度调整为同部位结构侧墙厚度,将腰梁的混凝土调整为同部位结构侧墙混凝土,增强腰梁横向受力钢筋,在腰梁内设置结构侧墙预留钢筋,并使腰梁内所有钢筋均满足钢筋保护层厚度要求,使合建结构内的腰梁同时满足临时结构腰梁水平支护设计要求和永久结构侧墙的竖向承载设计要求,使临时腰梁与永久结构侧墙合二为一。同时为了施工方便,在腰梁上下设置引墙,上、下引墙按照结构侧墙的设计方案进行配筋和混凝土浇筑。本发明可以省去后期腰梁拆除、结构侧墙施工的施工步骤,简化施工流程,能够大幅减少作业人员工作量,加快整体施工进度,显著缩短施工工期,节约施工成本。The advantages and positive effects of the present invention are: by adjusting the construction plan of the temporary support structure waist beam, the width of the waist beam is adjusted to the thickness of the side wall of the structure at the same position, and the concrete of the waist beam is adjusted to the concrete of the side wall of the structure at the same position, Reinforcing the lateral stress reinforcement of the waist beam, setting the reserved steel bars for the structural side walls in the waist beam, and making all the reinforcement in the waist beam meet the thickness requirements of the reinforcement cover, so that the waist beam in the combined structure can meet the level of the temporary structure waist beam at the same time The design requirements of the support and the vertical bearing design requirements of the side walls of the permanent structure make the temporary waist beam and the side wall of the permanent structure into one. At the same time, for the convenience of construction, guide walls are set above and below the waist beam, and the upper and lower guide walls are reinforced and concreted according to the design scheme of the structural side walls. The present invention can save the construction steps of dismantling the waist beams and constructing the structural side walls in the later stage, simplifies the construction process, can greatly reduce the workload of operators, speed up the overall construction progress, significantly shorten the construction period, and save construction costs.

附图说明Description of drawings

图1为本发明中腰梁内的钢筋结构示意图;Fig. 1 is the reinforcing bar structure schematic diagram in the waist beam of the present invention;

图2为本发明中的防水结构示意图。Fig. 2 is a schematic diagram of the waterproof structure in the present invention.

图中:1、钢板止水带;2-1、接驳器Ⅰ;2-2、接驳器Ⅱ;3、上引墙;4、结构侧墙预留钢筋;5、腰梁;6、下引墙;7、围护结构;8、上部墙体的外侧防水层;9、注浆导管Ⅰ;10、抗剪钢筋;11、注浆导管Ⅱ;12、遇水膨胀止水胶条;13、下部墙体的外侧防水层;14、水泥基渗透结晶防水涂层;15-1、15-2、防水卷材加强层。In the figure: 1. Steel plate waterstop; 2-1. Connector Ⅰ; 2-2. Connector Ⅱ; 3. Leading wall; 4. Rebar reserved for structural side walls; 5. Waist beam; 6. 7. Enclosure structure; 8. Outer waterproof layer of the upper wall; 9. Grouting duct Ⅰ; 10. Shear steel bar; 11. Grouting duct Ⅱ; 12. Water-swelling waterproof strip; 13. The outer waterproof layer of the lower wall; 14. The cement-based permeable crystalline waterproof coating; 15-1, 15-2, the reinforced layer of waterproof coiled material.

具体实施方式Detailed ways

为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:

请参阅图1和图2,一种盖挖逆作地铁车站腰梁、结构侧墙合建方法,采用以下步骤:Please refer to Figure 1 and Figure 2, a method of combined construction of waist beams and structural side walls of a subway station with cover-excavation, the following steps are adopted:

1)在车站围护结构7施工中,预埋腰梁抗剪钢筋10的锚固段,锚固段设有抗剪钢筋接驳器。在本实施例中,围护结构7采用地连墙。1) During the construction of the station enclosure structure 7, the anchorage section of the waist beam shear reinforcement 10 is pre-embedded, and the anchorage section is provided with a shear reinforcement connector. In this embodiment, the enclosure structure 7 adopts ground connection walls.

2)在基坑开挖至腰梁设计标高时,施作垫层、剔凿出预埋的抗剪钢筋接驳器、施工合建部分,所述合建部分的主体是腰梁5,所述腰梁5的宽度与结构侧墙的厚度相同,在所述腰梁的上方设有上引墙3,下方设有下引墙6,在施工合建部分之前施工合建部分的外侧防水层,然后绑扎合建部分的钢筋,包括腰梁钢筋和结构侧墙钢筋4(图中仅示出了主筋),其中结构侧墙钢筋4贯穿整个合建部分,设有曝露于所述上引墙之上的接驳器Ⅰ2-1以及曝露于下引墙之下的接驳器Ⅱ2-2,在结构侧墙钢筋上固定有曝露于所述上引墙3之上的钢板止水带1;腰梁钢筋需要满足结构侧墙厚度要求、满足腰梁设计受力要求,腰梁钢筋中的抗剪钢筋10是由围护结构中预留的锚固段接长至腰梁内的,在每根接长抗剪钢筋的连接部位涂有环形遇水膨胀止水胶;最后采用与结构侧墙混凝土标号相同的混凝土浇筑合建部分。2) When the foundation pit is excavated to the design elevation of the waist beam, the cushion layer is applied, the pre-buried shear steel bar connector is chiseled out, and the joint construction part is constructed. The main body of the joint construction part is the waist beam 5, so The width of the waist beam 5 is the same as the thickness of the structural side wall, an upper lead wall 3 is provided above the waist beam, and a lower lead wall 6 is arranged below, and the outer waterproof layer of the joint construction part is constructed before the construction of the joint construction part , and then bind the steel bars of the joint construction part, including waist beam steel bars and structural side wall steel bars 4 (only the main bars are shown in the figure), wherein the structural side wall steel bars 4 run through the entire joint construction part, and are provided with The upper connector I2-1 and the connector II2-2 exposed under the lower lead wall are fixed with a steel plate waterstop 1 exposed on the upper lead wall 3 on the reinforcement of the structural side wall; The waist beam reinforcement needs to meet the thickness requirements of the structural side wall and the design force requirements of the waist beam. The shear reinforcement 10 in the waist beam reinforcement is connected to the waist beam by the anchorage section reserved in the enclosure structure. The connection part of the extended shear steel bar is coated with a ring-shaped water-swellable waterproof glue; finally, the concrete with the same label as the structural side wall concrete is used to pour the composite part.

3)在合建部分施工完成后,进行后续基坑土方开挖,至底板设计标高后施工底板以及后续侧墙,其中后续侧墙包括下部墙体(图中未示出)和上部墙体(图中未示出),首先逆作下部墙体,然后顺作上部墙体,在逆作下部墙体之前,在围护结构表面施工与合建部分的外侧防水层衔接的下部墙体的外侧防水层13;在合建部分底部固定遇水膨胀止水胶条12;然后绑扎下部墙体钢筋,下部墙体钢筋的主筋与接驳器Ⅱ2-2连接,在下部墙体的钢筋结构中固定注浆导管Ⅱ11,所述注浆导管Ⅱ11的出口位于所述下引墙6与所述下部墙体的接缝处,用于补浆防渗。最后浇筑下墙体混凝土;在顺作上部墙体之前,在围护结构表面施工与合建部分外侧防水层衔接的上部墙体外侧防水层8;然后绑扎上部墙体钢筋,上部墙体钢筋的主筋与接驳器Ⅰ2-1连接,在上部墙体的钢筋结构中固定注浆导管Ⅰ9,所述注浆导管Ⅰ9的出口位于所述上引墙3与所述上部墙体的接缝处,用于补浆防渗。最后浇筑上部墙体混凝土;至此已经完成了结构侧墙的施工。3) After the construction of the joint construction part is completed, the subsequent excavation of foundation pit earthwork is carried out, and the bottom slab and subsequent side walls are constructed after reaching the design level of the bottom slab, wherein the subsequent side walls include the lower wall (not shown in the figure) and the upper wall ( not shown in the figure), first make the lower wall in reverse, and then make the upper wall along the way. Before the lower wall is reversed, construct the outer side of the lower wall connected with the outer waterproof layer of the joint construction part on the surface of the enclosure structure Waterproof layer 13; fix the water-swellable waterproof strip 12 at the bottom of the joint construction part; then tie the lower wall reinforcement, the main reinforcement of the lower wall reinforcement is connected with the connector Ⅱ2-2, and fixed in the reinforcement structure of the lower wall The grouting conduit II11, the outlet of the grouting conduit II11 is located at the joint between the downfall wall 6 and the lower wall, and is used for grouting and anti-seepage. Finally, the lower wall concrete is poured; before the upper wall is built, the outer waterproof layer 8 of the upper wall connected with the outer waterproof layer of the joint construction part is constructed on the surface of the enclosure structure; then the upper wall reinforcement is bound, and the upper wall reinforcement The main reinforcement is connected to the connector I2-1, and the grouting conduit I9 is fixed in the steel structure of the upper wall, and the outlet of the grouting conduit I9 is located at the joint between the upper leading wall 3 and the upper wall, Used for grouting and anti-seepage. Finally, the upper wall concrete is poured; the construction of the structural side walls has now been completed.

在本实施例中,所述步骤2),合建部分外侧防水层,剔凿部位是采用水泥基渗透结晶性防水涂料涂刷而成的水泥基渗透结晶防水涂层14,其余部位铺设防水卷材,所述步骤3),下部墙体外侧的防水层13和上部墙体外侧的防水层均采用防水卷材铺设,在与合建部分的外侧防水层衔接处设置防水卷材加强层15-1和15-2。In the present embodiment, in the step 2), part of the outer waterproof layer is jointly built, and the chiseled part is a cement-based permeable crystalline waterproof coating 14 that is painted with cement-based permeable crystalline waterproof paint, and the rest of the parts are laid with waterproof rolls material, step 3), the waterproof layer 13 on the outside of the lower wall and the waterproof layer on the outside of the upper wall are laid with waterproof rolls, and a waterproof roll reinforcement layer 15- 1 and 15-2.

上述合建施工方法通过调整腰梁结构截面尺寸,将腰梁宽度调整为结构侧墙厚度;调整腰梁配筋使其仍能满足腰梁的设计受力要求;调整腰梁混凝土使其与结构侧墙混凝土标号相同,进而使腰梁在保证腰梁临时结构设计和使用功能的前提下,同时能满足结构侧墙永久结构的设计要求,合二为一的施工方法使得腰梁兼做此处的结构侧墙,省去了后期腰梁拆除、该处结构侧墙施工的工作量,能够显著缩短施工工期。The above combined construction method adjusts the width of the waist beam to the thickness of the side wall of the structure by adjusting the section size of the waist beam structure; adjusts the reinforcement of the waist beam so that it can still meet the design force requirements of the waist beam; The concrete grades of the side walls are the same, so that the waist beam can meet the design requirements of the permanent structure of the side wall of the structure under the premise of ensuring the temporary structure design and use functions of the waist beam. The structural side wall saves the workload of dismantling the waist beam and constructing the structural side wall in the later stage, which can significantly shorten the construction period.

关于腰梁施工的详细说明:Detailed instructions on waist beam construction:

一般工况下,腰梁截面尺寸1.4×1.2m,宽度远超结构侧墙的厚度1.1m,因此在合建施工时需要进行调整,将腰梁截面尺寸调整为1.1×1.2m,与结构侧墙厚度相同。Under normal working conditions, the cross-sectional size of the waist beam is 1.4×1.2m, and its width far exceeds the thickness of the side wall of the structure by 1.1m. The walls are the same thickness.

在进行腰梁配筋设计时,按照基坑支护最不利工况(支撑间距9m)对腰梁进行纯弯、抗剪配筋计算,需要增强其横向受力钢筋。In the design of waist beam reinforcement, according to the most unfavorable working condition of foundation pit support (support spacing 9m), the calculation of pure bending and shear reinforcement of waist beam needs to be strengthened.

由于腰梁兼做侧墙,后期不进行拆除,腰梁内需预留侧墙钢筋,腰梁混凝土需调整为与结构侧墙混凝土标号相同,采用浇筑结构侧墙的混凝土C35P10浇筑腰梁。Since the waist beam is also used as the side wall, it will not be demolished in the later stage. The side wall reinforcement needs to be reserved in the waist beam, and the waist beam concrete needs to be adjusted to the same label as the structural side wall concrete. The waist beam is poured with concrete C35P10 for the structural side wall.

为了后续结构侧墙施工方便,在腰梁上下均设置高度大于300mm的引墙,在引墙内预留侧墙钢筋,长度超出引墙高度,钢筋端部设置接驳器,用于后续连接。接驳器均为1级。具体侧墙钢筋预留做法请参见图1。In order to facilitate the construction of the side wall of the subsequent structure, lead walls with a height greater than 300mm are set above and below the waist beam, and side wall reinforcement is reserved in the lead wall, the length of which exceeds the height of the lead wall, and a connector is provided at the end of the steel bar for subsequent connection. The connectors are all class 1. Please refer to Figure 1 for the specific method of reserving side wall reinforcement.

上述配筋均需满足钢筋保护层厚度要求。The above-mentioned reinforcements must meet the requirements for the thickness of the reinforcement cover.

尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围的情况下,还可以做出很多形式,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention.

Claims (2)

1.一种盖挖逆作地铁车站腰梁、结构侧墙合建施工方法,其特征在于,采用以下步骤:1. A kind of cover excavation reverse works subway station waist beam, structure side wall and builds construction method together, it is characterized in that, adopts the following steps: 1)在车站围护结构施工中,预埋腰梁抗剪钢筋的锚固段,锚固段设有抗剪钢筋接驳器;1) In the construction of the station enclosure structure, the anchorage section of the waist beam shear reinforcement is pre-embedded, and the anchorage section is provided with a shear reinforcement connector; 2)在基坑开挖至腰梁设计标高时,施作垫层、剔凿出预埋的抗剪钢筋接驳器、施工合建部分,所述合建部分的主体是腰梁,所述腰梁的宽度与结构侧墙的厚度相同,2) When the foundation pit is excavated to the design elevation of the waist beam, the cushion layer is applied, the pre-buried shear steel bar connector is excavated, and the joint construction part is constructed. The main body of the joint construction part is the waist beam. The width of the girder is the same as the thickness of the structural side walls, 在所述腰梁的上方设有上引墙,下方设有下引墙,An upward leading wall is provided above the waist beam, and a downward leading wall is provided below, 在施工合建部分之前施工合建部分的外侧防水层,Construct the outer waterproof layer of the joint construction part before constructing the joint construction part, 然后绑扎合建部分的钢筋,包括腰梁钢筋和结构侧墙钢筋,其中结构侧墙钢筋贯穿整个合建部分,设有曝露于所述上引墙之上的接驳器Ⅰ以及曝露于下引墙之下的接驳器Ⅱ,在结构侧墙钢筋上固定有曝露于所述上引墙之上的钢板止水带;腰梁钢筋满足结构侧墙厚度要求、满足腰梁受力要求,腰梁钢筋中的抗剪钢筋是由围护结构中预留的锚固段接长至腰梁内的,在每根接长抗剪钢筋的连接部位涂有环形遇水膨胀止水胶;Then bind the steel bars of the joint construction part, including waist beam steel bars and structural side wall steel bars, wherein the structural side wall steel bars run through the entire joint construction part, and are provided with a connector I exposed on the upper lead-in wall and exposed on the lower lead-in wall. The connector II under the wall is fixed with a steel plate waterstop exposed on the upper lead-in wall on the steel bar of the structural side wall; the steel bar of the waist beam meets the thickness requirements of the structural side wall and the force requirement of the waist beam, and the steel bar of the waist beam The shearing reinforcement in the enclosure is extended to the waist beam by the anchorage section reserved in the enclosure structure, and the joint of each lengthening shearing reinforcement is coated with a ring-shaped water-expanding waterproof glue; 最后采用与结构侧墙混凝土标号相同的混凝土浇筑合建部分;Finally, use the same concrete label as the structural side wall concrete to pour the composite part; 3)在合建部分施工完成后,进行后续基坑土方开挖,至底板设计标高后施工底板以及后续侧墙,其中后续侧墙包括下部墙体和上部墙体,首先逆作下部墙体,然后顺作上部墙体,3) After the construction of the joint construction part is completed, the follow-up excavation of the foundation pit shall be carried out, and the bottom slab and subsequent side walls shall be constructed after reaching the design level of the bottom slab. The subsequent side walls include the lower wall and the upper wall. Then make the upper wall along the way, 在逆作下部墙体之前,在围护结构表面施工与合建部分的外侧防水层衔接的下部墙体的外侧防水层;在合建部分底部固定遇水膨胀止水胶条;然后绑扎下部墙体钢筋,下部墙体钢筋的主筋与接驳器Ⅱ连接,在下部墙体的钢筋结构中固定注浆导管Ⅱ,所述注浆导管Ⅱ的出口位于所述下引墙与所述下部墙体的接缝处,最后浇筑下墙体混凝土;Before the reverse construction of the lower wall, the outer waterproof layer of the lower wall connected with the outer waterproof layer of the joint construction part shall be constructed on the surface of the enclosure structure; the water-swellable waterproof strip shall be fixed at the bottom of the joint construction part; then the lower wall shall be bound body reinforcement, the main reinforcement of the lower wall reinforcement is connected to the connector II, and the grouting conduit II is fixed in the reinforcement structure of the lower wall, and the outlet of the grouting conduit II is located between the lower lead wall and the lower wall At the joints, the concrete of the lower wall is finally poured; 在顺作上部墙体之前,在围护结构表面施工与合建部分的外侧防水层衔接的上部墙体的外侧防水层;然后绑扎上部墙体钢筋,上部墙体钢筋的主筋与接驳器Ⅰ连接,在上部墙体的钢筋结构中固定注浆导管Ⅰ,所述注浆导管Ⅰ的出口位于所述上引墙与所述上部墙体的接缝处,最后浇筑上部墙体混凝土;至此已经完成了结构侧墙的施工。Before constructing the upper wall, construct the outer waterproof layer of the upper wall connected to the outer waterproof layer of the joint construction part on the surface of the enclosure structure; then bind the upper wall reinforcement, the main reinforcement of the upper wall reinforcement and the connector I Connect, fix the grouting conduit I in the steel bar structure of the upper wall, the outlet of the grouting conduit I is located at the joint between the upper lead wall and the upper wall, and finally pour the upper wall concrete; so far The construction of the structural side walls is completed. 2.根据权利要求1所述的盖挖逆作地铁车站腰梁、结构侧墙合建施工方法,其特征在于,所述步骤2),合建部分的外侧防水层,剔凿部位是采用水泥基渗透结晶性防水涂料涂刷而成的水泥基渗透结晶防水涂层,其余部位铺设防水卷材,所述步骤3),下部墙体的外侧防水层和上部墙体的外侧防水层均采用防水卷材铺设,在与合建部分外侧的防水层的衔接处设置防水卷材加强层。2. cover excavation according to claim 1 and reverse works subway station lumbar beam, structural side wall joint construction construction method, it is characterized in that, described step 2), the outer waterproof layer of joint construction part, pick chisel position is to adopt cement The cement-based permeable crystalline waterproof coating formed by painting the base permeable crystalline waterproof coating, and the rest of the parts are laid with waterproof membranes. In the step 3), the outer waterproof layer of the lower wall and the outer waterproof layer of the upper wall are all made of waterproof For the laying of the coiled material, a waterproof coiled material reinforcement layer is set at the connection with the waterproof layer on the outside of the joint construction part.
CN202211402072.XA 2022-11-09 2022-11-09 Combined construction method for waist rail and structural side wall of cover-excavation top-down subway station Pending CN115627778A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211402072.XA CN115627778A (en) 2022-11-09 2022-11-09 Combined construction method for waist rail and structural side wall of cover-excavation top-down subway station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211402072.XA CN115627778A (en) 2022-11-09 2022-11-09 Combined construction method for waist rail and structural side wall of cover-excavation top-down subway station

Publications (1)

Publication Number Publication Date
CN115627778A true CN115627778A (en) 2023-01-20

Family

ID=84907946

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211402072.XA Pending CN115627778A (en) 2022-11-09 2022-11-09 Combined construction method for waist rail and structural side wall of cover-excavation top-down subway station

Country Status (1)

Country Link
CN (1) CN115627778A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116950134A (en) * 2023-07-10 2023-10-27 中建八局第一建设有限公司 Waterproof device for permanent waist beam of deep foundation pit and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691301A (en) * 2012-06-21 2012-09-26 中国建筑第八工程局有限公司 Synchronous construction method for envelope enclosure supporting breast beam and main structure wall
CN106013256A (en) * 2016-06-22 2016-10-12 中铁第四勘察设计院集团有限公司 Tenon type connector water-proof structure for side wall of concrete waist beam embedded structure
CN214245851U (en) * 2020-12-07 2021-09-21 中国建筑第八工程局有限公司 Deep foundation pit rear-dismantling support waist beam waterproof structure
CN115059091A (en) * 2022-07-06 2022-09-16 中国建筑第六工程局有限公司 Waist beam and side wall integrated structure for foundation pit construction and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691301A (en) * 2012-06-21 2012-09-26 中国建筑第八工程局有限公司 Synchronous construction method for envelope enclosure supporting breast beam and main structure wall
CN106013256A (en) * 2016-06-22 2016-10-12 中铁第四勘察设计院集团有限公司 Tenon type connector water-proof structure for side wall of concrete waist beam embedded structure
CN214245851U (en) * 2020-12-07 2021-09-21 中国建筑第八工程局有限公司 Deep foundation pit rear-dismantling support waist beam waterproof structure
CN115059091A (en) * 2022-07-06 2022-09-16 中国建筑第六工程局有限公司 Waist beam and side wall integrated structure for foundation pit construction and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116950134A (en) * 2023-07-10 2023-10-27 中建八局第一建设有限公司 Waterproof device for permanent waist beam of deep foundation pit and construction method

Similar Documents

Publication Publication Date Title
CN106320377B (en) A construction method for deep foundation pit cover and excavation in water-rich soft soil area
CN112922208A (en) Construction method of steel bar truss floor support plate
CN106555453A (en) A kind of prefabricated overlapped hollow plate of prestressing force and its construction method
CN111733873A (en) Construction method of assembled subway station
CN114673169A (en) A combined construction method of multi-layer large-span deep foundation pit covering and excavation in urban core area
CN103806647A (en) Assembly and disassembly process for large-span concrete bidirectional dense rib beam formwork case
CN205348391U (en) Take prefabricated beam column rebar mechanical connection node of lag
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN110359671B (en) Construction method of assembled rail top air duct
WO2026060993A1 (en) Construction method for non-reserved rail transit interface of operating subway station
CN114809070A (en) Open-cut tunnel assembly integral structure and construction method thereof
CN103758343A (en) Hanging type construction method and hanging device for reinforced concrete floor
CN211172070U (en) Assembled type suspended wall retaining wall structure of reinforced concrete member
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN205296197U (en) Prefabricated cushion cap of anticorrosive industry factory building concrete rim of a cup formula
CN116856550A (en) Newly-built reverse construction method for lifting steel slideway of reinforced concrete frame structure on ground
CN115853287A (en) Forward and reverse combined construction method for large-span roof building in narrow site
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN110847466A (en) Splicing and reinforcing construction method for prefabricated laminated slab
CN212506301U (en) Support system in combination assembled forever
CN114635503A (en) Fair-faced concrete wall flexibly connected with concrete frame column and construction method
CN114458042A (en) Construction method for newly building plate above existing subway station rail-mounted area
CN119824948A (en) Basement exterior wall construction method in ultra-narrow foundation trench environment
CN111877626A (en) Overhead laminated slab construction structure and construction method
CN108487072B (en) Across Business Line railway cast-in-place frame bridge rapid constructing method in one kind

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20230120