CN115595986A - A foundation pit enclosure structure and construction method - Google Patents

A foundation pit enclosure structure and construction method Download PDF

Info

Publication number
CN115595986A
CN115595986A CN202211473678.2A CN202211473678A CN115595986A CN 115595986 A CN115595986 A CN 115595986A CN 202211473678 A CN202211473678 A CN 202211473678A CN 115595986 A CN115595986 A CN 115595986A
Authority
CN
China
Prior art keywords
foundation pit
support
transmission belt
force transmission
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211473678.2A
Other languages
Chinese (zh)
Other versions
CN115595986B (en
Inventor
於慧
秦志龙
谷朋
吴逸
陈静涛
韩旭
王贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202211473678.2A priority Critical patent/CN115595986B/en
Publication of CN115595986A publication Critical patent/CN115595986A/en
Application granted granted Critical
Publication of CN115595986B publication Critical patent/CN115595986B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a foundation pit support structure and a construction method, wherein the foundation pit support structure comprises a foundation pit, a plurality of fender posts are uniformly arranged at intervals around the foundation pit, the tops of the fender posts are fixedly connected through crown beams, a plurality of groups of supporting components are arranged in the foundation pit, the supporting components are supported on one side of the fender posts, and the supporting components are connected into a whole through connecting beams; the bottom of the supporting component penetrates through the reinforcement cushion component and is embedded and inserted in the deep part of the soil layer; a construction method of a foundation pit support structure comprises the steps of fender pile construction, first support construction, first subsoil excavation, second subsoil excavation and foundation pit backfilling. The structure is stable and reliable, the foundation pit excavation device is suitable for excavation of foundation pits of various specifications, particularly suitable for reduction of construction deformation of deeper foundation pits, part of the structure can be recycled, construction of the foundation pit enclosure structure and construction of the building structure in the pit are organically combined in the whole construction process, the whole foundation pit construction process is safe and orderly, and the construction period is short.

Description

一种基坑围护结构及施工方法A foundation pit enclosure structure and construction method

技术领域technical field

本发明涉及地下工程施工技术领域,具体涉及一种基坑围护结构及施工方法。The invention relates to the technical field of underground engineering construction, in particular to a foundation pit enclosure structure and a construction method.

背景技术Background technique

随着城市的不断发展与建设,基坑工程逐渐往深、大方向发展且施工环境越来越复杂。对于大面积的深基坑工程,工程实践中往往采用支撑或桩锚体系,支撑体系在基坑开挖面积较大时,由于支撑长细比过大,往往需要分坑施工,势必会对工期和经济性造成较大影响,同时内部支撑体系的设置对挖土也有较多限制影响;桩锚体系往往需要占用场地外侧空间,对周边环境影响较大,在城市施工中有诸多限制,因此这两种体系在工程应用中往往有一定的局限性。基坑工程一般是地下临时结构,如何在保证安全的基础上,综合考虑经济、工期等因素采取合理的围护支撑体系是基坑工程设计应该要思考的问题。With the continuous development and construction of the city, the foundation pit project is gradually developing in a deep and general direction, and the construction environment is becoming more and more complex. For large-area deep foundation pit projects, support or pile-anchor systems are often used in engineering practice. When the excavation area of the foundation pit is large, the support system often needs to be constructed in separate pits due to the large slenderness ratio of the support, which will inevitably affect the construction period. At the same time, the setting of the internal support system also has a lot of restrictions on excavation; the pile-anchor system often needs to occupy the space outside the site, which has a great impact on the surrounding environment. There are many restrictions in urban construction, so this The two systems often have certain limitations in engineering applications. Foundation pit engineering is generally an underground temporary structure. How to adopt a reasonable enclosure support system on the basis of ensuring safety and comprehensively considering factors such as economy and construction period is a problem that should be considered in the design of foundation pit engineering.

经检索发现,申请号为CN 106013172 B的中国专利,公开了一种双排桩与斜撑组合软土深基坑支护结构及施工方法,该专利通过在斜撑与基础筏板相接处设置底部支撑墩,将支撑力传至底板。该专利虽然采用斜撑,但斜撑未伸入土层深处,因此控制变形能力较差,同时该专利施工时坑边需留土后挖,底板需分两次施工,对工期影响较大,且如果坑边有号楼,基坑施工难度较大。After retrieval, it was found that the Chinese patent application number CN 106013172 B discloses a soft soil deep foundation pit support structure and construction method combined with double-row piles and diagonal braces. Set the bottom support pier to transfer the support force to the bottom plate. Although the patent uses diagonal braces, the diagonal braces do not penetrate deep into the soil layer, so the ability to control deformation is poor. At the same time, when the patent is constructed, the soil needs to be left behind and the bottom plate needs to be constructed twice, which has a great impact on the construction period. , and if there is a building beside the pit, the construction of the foundation pit will be more difficult.

申请号为CN 211922637 U的中国专利,公开了一种设置桩间斜撑的A字型双排桩基坑支护,该专利围护结构主要采用前排桩作为围护结构,后排桩作为支撑结构,前后排桩设置桩间斜撑,由于前排桩为单桩,围护结构稳定性和抗变形能力较差,往往适用于地下一层的较浅基坑,同时桩间斜撑仅撑至后排桩中心位置易造成后排桩折断等工程风险,且后排桩需穿越结构底板,对底板防水要求较高。The application number is the Chinese patent of CN 211922637 U, discloses a kind of A-shaped double-row pile foundation pit support with diagonal bracing between the piles, this patent enclosure structure mainly adopts the front row of piles as the enclosure structure, and the rear row of piles as the For the support structure, the front and rear rows of piles are set with diagonal braces between piles. Since the front row of piles is a single pile, the stability and deformation resistance of the enclosure structure are poor, so it is often suitable for shallow foundation pits on the ground floor. At the same time, the diagonal braces between piles are only Supporting to the center of the rear row of piles is likely to cause engineering risks such as breaking of the rear row of piles, and the rear row of piles needs to pass through the structural bottom plate, which requires high waterproofing of the bottom plate.

申请号为CN 114197483 A的中国专利,公开了一种基坑围护结构及其施工方法。该发明包括多个立柱、注浆斜撑管和连接斜撑管,通过在冠梁内开设插孔,插孔内活动连接有普通斜撑管,普通斜撑管与冠梁之间设有固定机构,注浆斜撑管与连接斜撑管之间设有调节机构,注浆斜撑管的顶部活动连接有转管,解决现有技术中采用的注浆斜撑管斜撑组合结构无法主动控制基坑变形,以及斜撑管固定连接不能收回难题,提高了结构使用成本的问题,但该发明没有解决注浆斜撑管与主体地下结构之间的相互关系等问题。The application number is the Chinese patent of CN 114197483 A, which discloses a foundation pit enclosure structure and a construction method thereof. The invention includes a plurality of upright columns, grouting slant pipes and connecting slant pipes. By setting jacks in the crown beam, ordinary slant pipes are movably connected in the sockets. Mechanism, there is an adjustment mechanism between the grouting slant pipe and the connecting slant pipe, and the top of the grouting slant pipe is movably connected with a rotating pipe, which solves the problem that the grouting slant pipe slant bracing combination structure used in the prior art cannot be actively The problem of controlling the deformation of the foundation pit and the inability to recover the fixed connection of the diagonal braces increases the cost of the structure. However, this invention does not solve the problems of the relationship between the grouted diagonal braces and the main underground structure.

综上所述,现有的类似基坑支护形式主要是采用双排桩+斜撑或者单排桩+斜撑两种组合,这两种围护形式均有一定的局限性:双排桩+斜撑组合中斜撑一般撑至底板上,坑边需留土后挖,底板需分两次施工,对工期影响较大,同时斜撑撑至底板,传力较差,基坑变形控制效果差,对基坑的开挖深度有一定的限制;单排桩+斜撑组合中,单排桩控制变形能力和稳定性较差,斜撑需要穿越底板,对底板防水要求较高,一般也是适用于较浅的基坑。To sum up, the existing support forms for similar foundation pits mainly use two combinations of double-row piles + diagonal braces or single-row piles + diagonal braces. These two types of enclosures have certain limitations: double-row piles +In the combination of diagonal braces, the diagonal braces are generally supported to the bottom plate, and the soil needs to be excavated after leaving the side of the pit. The bottom plate needs to be constructed twice, which has a great impact on the construction period. At the same time, the diagonal braces are braced to the bottom plate, so the force transmission is poor and the deformation of the foundation pit is controlled. The effect is poor, and there is a certain limit to the excavation depth of the foundation pit; in the combination of single-row piles and diagonal braces, the deformation control ability and stability of the single-row piles are poor, and the diagonal braces need to pass through the bottom plate, which requires high waterproofing of the bottom plate. It is also suitable for shallow foundation pits.

发明内容Contents of the invention

本发明目的是提供一种基坑围护结构及施工方法,该结构在基坑内固定连接成一个整体,并综合解决了基坑防水问题,围护过程稳定可靠,适用于各类规格的基坑开挖,尤其适用于减少较深基坑的施工变形,整个施工过程中,将基坑围护结构施工与坑内建筑结构施工有机结合,使整个基坑工程安全有序开展。The object of the present invention is to provide a foundation pit enclosure structure and construction method. The structure is fixedly connected into a whole in the foundation pit, and comprehensively solves the waterproof problem of the foundation pit. The enclosure process is stable and reliable, and is suitable for foundation pits of various specifications. Excavation is especially suitable for reducing the construction deformation of deep foundation pits. During the entire construction process, the construction of the foundation pit enclosure structure and the construction of the building structure in the pit are organically combined, so that the entire foundation pit project can be carried out safely and orderly.

为实现上述目的,本发明采取以下技术方案:To achieve the above object, the present invention takes the following technical solutions:

一种基坑围护结构,包括基坑,基坑四周均匀间隔设置有若干根围护桩,若干根围护桩顶部通过冠梁固定连接,基坑内设置有若干组支撑组件,支撑组件支撑在围护桩一侧,支撑组件间通过连接梁连接成一个整体;基坑底部四周设置有配筋垫层组件,支撑组件底部穿过配筋垫层组件、埋插在土层深处;An enclosure structure for a foundation pit, comprising a foundation pit, a number of enclosure piles are evenly spaced around the foundation pit, the tops of the several enclosure piles are fixedly connected by crown beams, and several groups of support components are arranged in the foundation pit, and the support assemblies are supported on On the side of the retaining pile, the supporting components are connected into a whole through the connecting beam; the reinforced cushion component is arranged around the bottom of the foundation pit, and the bottom of the supporting component passes through the reinforced cushion component and is buried deep in the soil layer;

支撑组件包括斜撑在冠梁与基坑底部间的第一支撑,第一支撑与围护桩对应设置,第一支撑与围护桩间还抵接、支撑有第二支撑;第一支撑包括斜撑管,斜撑管底部设置有浇筑头,斜撑管顶端锚接在冠梁处,斜撑管底部埋插在土层深处;第二支撑包括抵接在围护桩与第一支撑间的支撑横梁、顶端支撑在支撑横梁底部的钢立柱,钢立柱底端埋插在土层深处;The support assembly includes a first support between the crown beam and the bottom of the foundation pit. The first support is arranged correspondingly to the surrounding protection piles. Diagonal bracing pipe, the bottom of the diagonal bracing pipe is provided with a pouring head, the top of the diagonal bracing pipe is anchored at the crown beam, and the bottom of the diagonal bracing pipe is buried deep in the soil layer; The supporting beams in between, the steel columns whose tops are supported at the bottom of the supporting beams, and the bottom ends of the steel columns are buried deep in the soil layer;

配筋垫层组件包括配筋垫层和均匀间隔设置在配筋垫层底部的多根插筋,配筋垫层由双面双向配筋和混凝土浇筑而成,配筋垫层铺设在基坑底面周边、并通过插筋与基坑底部的土层插接。The reinforcement cushion component includes a reinforcement cushion and a plurality of inserted bars arranged at even intervals at the bottom of the reinforcement cushion. The reinforcement cushion is made of double-sided two-way reinforcement and concrete pouring, and the reinforcement cushion is laid on the bottom of the foundation pit The surrounding area and the soil layer at the bottom of the foundation pit are inserted through inserting reinforcement.

优选的,所述围护桩与基坑侧壁间设置有若干个竖向止水桩。Preferably, several vertical water stop piles are arranged between the surrounding protection piles and the side wall of the foundation pit.

优选的,所述斜撑管顶部周边设置有若干根锚筋,锚筋与冠梁内的钢筋结构绑扎为一体。Preferably, several anchor bars are arranged around the top of the diagonal brace, and the anchor bars are bound together with the steel bar structure in the crown beam.

优选的,所述支撑横梁一端通过双拼围檩与围护桩固定连接,支撑横梁另一端与斜撑管固定连接。Preferably, one end of the supporting beam is fixedly connected to the surrounding protection piles through double-split purlins, and the other end of the supporting beam is fixedly connected to the diagonal bracing pipe.

优选的,所述双拼围檩由工字钢、槽钢或钢板制成的四边形结构;所述支撑横梁由圆钢管或方钢管制成的杆状结构。Preferably, the double purlin is a quadrilateral structure made of I-beam, channel steel or steel plate; the supporting beam is a rod-shaped structure made of round steel pipe or square steel pipe.

优选的,所述连接梁由工字钢或槽钢制成,连接梁连接在相邻两个支撑横梁间。Preferably, the connecting beam is made of I-shaped steel or channel steel, and the connecting beam is connected between two adjacent supporting beams.

优选的,所述配筋垫层组件上侧设置有坑内建筑结构,坑内建筑结构包括底板,坑内建筑结构通过传力带与围护桩相连,所述斜撑管依次倾斜穿过坑内建筑结构和配筋垫层组件埋插在土层深处,斜撑管与底板中部相交位置处设置有止水钢板。Preferably, the upper side of the reinforced cushion assembly is provided with a building structure in the pit, the building structure in the pit includes a bottom plate, the building structure in the pit is connected with the surrounding piles through a force transmission belt, and the diagonal bracing pipe is inclined through the building structure in the pit and The reinforced cushion component is buried deep in the soil layer, and a water-stop steel plate is arranged at the intersection of the diagonal bracing pipe and the middle of the bottom plate.

优选的,所述传力带一端预埋浇筑在坑内建筑结构一侧,传力带另一端锚入围护桩中;传力带包括底板传力带和中楼板传力带,底板传力带主体设置在配筋垫层组件上部,底板传力带一端预埋浇筑在底板一端,底板传力带另一端锚入围护桩中;中楼板传力带钢筋一侧锚入中楼板、另一侧通过吊筋与围护桩主筋焊接;中楼板传力带布置于第一支撑间隙中、沿基坑周边等间距间隔布置。Preferably, one end of the force transmission belt is pre-buried and poured on one side of the building structure in the pit, and the other end of the force transmission belt is anchored in the surrounding protection pile; The main body is set on the upper part of the reinforced cushion assembly, one end of the power transmission belt of the bottom slab is pre-buried and poured on one end of the bottom slab, and the other end of the power transmission belt of the bottom slab is anchored into the surrounding protection pile; The side is welded to the main reinforcement of the surrounding protection pile through hanging ribs; the force transmission belt of the middle floor is arranged in the first support gap and arranged at equal intervals along the periphery of the foundation pit.

一种基坑围护结构的施工方法,包括以下步骤:A construction method for a foundation pit enclosure structure, comprising the following steps:

步骤一,围护桩施工,根据图纸测绘放样,在现场标注定位围护桩和竖向止水桩位置,并完成围护桩和竖向止水桩的施工;Step 1, the construction of the enclosure piles, according to the drawings, surveying and setting out, marking and positioning the locations of the enclosure piles and vertical water-stop piles on site, and completing the construction of the enclosure piles and vertical water-stop piles;

步骤二,第一支撑施工,将斜撑管静压至土层内指定深度后,先向斜撑管内灌入级配碎石,然后再向斜撑管内灌入纯水泥至斜撑管顶部,斜撑管顶部四周通过焊接均匀连接若干根锚筋,锚筋与冠梁内的钢筋结构绑扎并浇筑连接;Step 2, the first support construction, after statically pressing the diagonal support pipe to the specified depth in the soil layer, pour graded gravel into the diagonal support pipe first, and then pour pure cement into the diagonal support pipe to the top of the diagonal support pipe, A number of anchor bars are evenly connected by welding around the top of the diagonal brace pipe, and the anchor bars are bound and poured to the steel structure in the crown beam;

步骤三,第一皮土开挖,分层分块开挖土层至支撑横梁设计位置处,架设若干组第二支撑,通过连接梁将相邻第二支撑间固定连接,基坑内所有的第二支撑被连接成一个整体;Step 3: Excavate the first surface soil, excavate the soil layer by layer and block to the design position of the supporting beam, erect several groups of second supports, and connect the adjacent second supports through the connecting beams. All the first supports in the foundation pit The two supports are connected into a whole;

步骤四,第二皮土开挖,分层分块开挖至基坑底部,施工配筋垫层组件,随后施工底板以及底板传力带,底板中部与斜撑管的相交处设置止水钢板,待底板与底板传力带强度达到要求后,拆除连接梁与第二支撑;继续施工中楼板和中楼板传力带,待中楼板和中楼板传力带强度达到要求后,将斜撑管一端沿底板顶面平齐切除、另一端沿围护桩侧面平齐切除;Step 4: Excavate the second skin and soil, excavate layer by block to the bottom of the foundation pit, construct reinforcement cushion components, and then construct the bottom plate and bottom plate power transmission belt, and install water-stop steel plates at the intersection of the middle of the bottom plate and the diagonal bracing pipe , after the strength of the bottom slab and the force transmission belt of the bottom slab meets the requirements, remove the connecting beam and the second support; continue to construct the mid-floor and mid-floor force One end is cut flush along the top surface of the bottom plate, and the other end is cut flush along the side of the surrounding pile;

步骤五,基坑回填,施工坑内建筑结构至正负零,基坑回填。Step 5: backfill the foundation pit, fill the building structure in the construction pit to positive and negative zero, and backfill the foundation pit.

本发明中,该基坑围护结构由若干组支撑组件固定连接成一个整体,整个结构稳定可靠,提高了基坑围护的安全性,对施工环境要求低,适用于各类规格的基坑开挖,尤其适用于减少较深基坑的施工变形;In the present invention, the foundation pit enclosure structure is fixedly connected into a whole by several sets of support components, the whole structure is stable and reliable, improves the safety of the foundation pit enclosure, has low requirements on the construction environment, and is suitable for foundation pits of various specifications Excavation, especially suitable for reducing construction deformation of deep foundation pits;

第一支撑包括斜撑管,斜撑管不仅可以起到支撑的作用,在斜撑管就位后还作为灌注通道,从斜撑管顶部向斜撑管内灌注级配碎石和纯水泥,在斜撑管底部形成浇筑头,以增大第一支撑与土层间的接触面积,达到增加连接强度以及防止下陷的目的,相较于预制混凝土桩而言,经济性好且斜撑管部分可回收利用;The first support includes diagonal bracing tubes. The diagonal bracing tubes can not only play a supporting role, but also serve as a pouring channel after the diagonal bracing tubes are in place. Gradated gravel and pure cement are poured into the diagonal bracing tubes from the top of the diagonal bracing tubes. The pouring head is formed at the bottom of the diagonally braced pipe to increase the contact area between the first support and the soil layer, so as to increase the connection strength and prevent subsidence. Compared with prefabricated concrete piles, it is more economical and the diagonally braced pipe part can be recycle and re-use;

第二支撑设在第一支撑与围护桩间,增加了第一支撑的支撑强度,防止第一支撑发生变形,减少了基坑侧壁的变形,提高了整个基坑围护结构的安全性和可靠性;The second support is installed between the first support and the surrounding protection pile, which increases the supporting strength of the first support, prevents the deformation of the first support, reduces the deformation of the side wall of the foundation pit, and improves the safety of the entire foundation pit enclosure structure and reliability;

配筋垫层组件设置在基坑底部四周,可有效减少基坑开挖到底时底部变形;The reinforcement cushion components are arranged around the bottom of the foundation pit, which can effectively reduce the deformation of the bottom when the foundation pit is excavated to the bottom;

围护桩与基坑侧壁间设置若干个竖向止水桩,以起到防水和挡土的作用;A number of vertical water stop piles are set between the retaining pile and the side wall of the foundation pit to play the role of waterproof and soil retaining;

该基坑围护结构的施工方法与基坑开挖和坑内建筑结构的施工有机结合,基坑开挖不受限制、施工工序简单、施工周期短且经济性好。The construction method of the foundation pit enclosure structure is organically combined with the excavation of the foundation pit and the construction of the building structure in the pit, the excavation of the foundation pit is not restricted, the construction process is simple, the construction period is short and the economy is good.

附图说明Description of drawings

图1为本发明整体结构示意图;Fig. 1 is a schematic diagram of the overall structure of the present invention;

图2为本发明整体结构俯视图;Fig. 2 is a top view of the overall structure of the present invention;

图3为本发明支撑组件与连接梁间的焊接示意图;Fig. 3 is the welding schematic diagram between support assembly and connecting beam of the present invention;

图4为本发明斜撑管与冠梁间的连接示意图;Fig. 4 is the schematic diagram of the connection between the brace pipe and the crown beam of the present invention;

图5为本发明支撑横梁与斜撑管间的焊接示意图;Fig. 5 is a schematic diagram of welding between the supporting beam and the brace pipe of the present invention;

图6为本发明支撑横梁与钢立柱间的焊接示意图;Fig. 6 is the welding schematic diagram between support beam and steel column of the present invention;

图7为本发明整体结构上设置有坑内建筑结构的示意图;Fig. 7 is the schematic diagram that is provided with the building structure in the pit on the overall structure of the present invention;

图8为坑内建筑结构与围护桩间的连接示意图;Fig. 8 is a schematic diagram of the connection between the building structure in the pit and the retaining piles;

图9为止水钢板设置示意图;Figure 9 is a schematic diagram of the installation of water-stop steel plates;

图10为步骤一对应的施工示意图;Figure 10 is a construction schematic diagram corresponding to step 1;

图11为步骤二对应的施工示意图;Figure 11 is a construction schematic diagram corresponding to step 2;

图12为步骤三对应的施工示意图;Figure 12 is a construction schematic diagram corresponding to step three;

图13为步骤四对应的施工示意图之一;Figure 13 is one of the construction schematic diagrams corresponding to step four;

图14为步骤四对应的施工示意图之二;Figure 14 is the second construction schematic diagram corresponding to step four;

图15为步骤四对应的施工示意图之三;Figure 15 is the third construction schematic diagram corresponding to step four;

图16为步骤五对应的施工示意图。Figure 16 is a construction diagram corresponding to step five.

图中:1、围护桩;2、支撑组件;3、坑内建筑结构;4、配筋垫层组件;5、传力带;6、连接梁;10、冠梁;11、竖向止水桩;20、第一支撑;21、第二支撑;30、止水钢板;31、底板;40、配筋垫层;41、插筋;50、底板传力带;51、中楼板传力带;200、斜撑管;201、浇筑头;210、支撑横梁;211、钢立柱;212、双拼围檩。In the figure: 1. Surrounding piles; 2. Support components; 3. Building structure in the pit; 4. Reinforced cushion components; 5. Force transmission belt; 6. Connecting beams; 10. Crown beams; Pile; 20. First support; 21. Second support; 30. Waterproof steel plate; 31. Bottom plate; 40. Reinforcement cushion; 41. Inserting ribs; ; 200, diagonal bracing pipe; 201, pouring head; 210, supporting beam; 211, steel column;

具体实施方式detailed description

下面结合附图,对本发明做进一步说明:Below in conjunction with accompanying drawing, the present invention will be further described:

实施例一:Embodiment one:

如图1和图2所示的一种基坑围护结构,包括基坑,基坑四周均匀间隔设置有若干根围护桩1,若干根围护桩1顶部通过冠梁10固定连接,围护桩1为灌注桩,灌注桩的桩径、桩长、配筋通过计算确定。基坑内设置有若干组支撑组件2,支撑组件2支撑在围护桩1一侧,支撑组件2间通过连接梁6连接成一个整体,支撑组件2间相互作用会产生支撑力和拉力,防止单组支撑组件2发生倾倒,提高了支撑组件2的稳定性,增加了基坑围护支撑时的可靠性,如图3所示,支撑组件2与连接梁6间通过焊接连接,连接梁6连接在相邻两个支撑横梁210间,在具体实施时,连接梁6由工字钢或槽钢制成。基坑底部四周设置有配筋垫层组件4,支撑组件2底部穿过配筋垫层组件4、埋插在土层深处,配筋垫层组件4包括配筋垫层40和均匀间隔设置在配筋垫层40底部的多根插筋41,配筋垫层40由双面双向配筋和混凝土浇筑而成,配筋垫层40选用的混凝土不小于C30,内置C12@200双面双向配筋,插筋选用C12钢筋,长度为1500mm,插筋间隔为1m,插筋锚入配筋垫层内150mm深,配筋垫层40铺设在基坑底面周边、并通过插筋41与基坑底部的土层插接。A foundation pit enclosure structure as shown in Fig. 1 and Fig. 2 includes a foundation pit, and several surrounding protection piles 1 are evenly spaced around the foundation pit, and the tops of several surrounding protection piles 1 are fixedly connected by crown beams 10, and the surrounding The protection pile 1 is cast-in-situ pile, and the pile diameter, pile length and reinforcement of the cast-in-situ pile are determined by calculation. There are several groups of supporting components 2 arranged in the foundation pit. The supporting components 2 are supported on one side of the retaining pile 1. The supporting components 2 are connected into a whole through the connecting beam 6. The interaction between the supporting components will generate supporting force and pulling force, preventing a single The support assembly 2 is toppled, which improves the stability of the support assembly 2 and increases the reliability of foundation pit enclosure support. As shown in Figure 3, the support assembly 2 and the connecting beam 6 are connected by welding, and the connecting beam 6 is connected Between two adjacent supporting beams 210 , the connecting beam 6 is made of I-beam or channel steel during specific implementation. A reinforced cushion assembly 4 is arranged around the bottom of the foundation pit. The bottom of the support assembly 2 passes through the reinforced cushion assembly 4 and is buried deep in the soil layer. The reinforced cushion assembly 4 includes a reinforced cushion 40 and uniformly spaced Multiple inserted bars 41 at the bottom of the reinforcement cushion 40, the reinforcement cushion 40 is made of double-sided two-way reinforcement and concrete pouring, the concrete used for the reinforcement cushion 40 is not less than C30, and the built-in C12@200 double-sided two-way reinforcement C12 steel bars are used for the inserted bars, the length is 1500mm, and the interval between the inserted bars is 1m. The inserted bars are anchored into the reinforcement cushion 150mm deep. The bottom soil layer is plugged.

支撑组件2包括斜撑在冠梁10与基坑底部间的第一支撑20,第一支撑20与围护桩1对应设置,第一支撑20与围护桩1间的夹角大于35°,第一支撑20与围护桩1间还抵接、支撑有第二支撑21,第一支撑20包括斜撑管200,斜撑管20可选用圆钢管或方钢管,斜撑管200不仅可以起到支撑的作用,在斜撑管200就位后还作为灌注通道,从斜撑管200顶部向斜撑管200内灌注级配碎石和纯水泥,在斜撑管200底部形成浇筑头,以增大第一支撑与土层间的接触面积,达到增加连接强度以及防止下陷的目的,相较于预制混凝土桩而言,经济性好且斜撑管200部分可回收利用,斜撑管200顶端锚接在冠梁10处,在一个更优实施例中,如图所示4,斜撑管200顶部周边设置有若干根锚筋,锚筋与冠梁10内的钢筋结构绑扎为一体,因此在具体实施时,第一支撑20与冠梁10同时浇筑,斜撑管200底部埋插在土层深处;第二支撑21包括抵接在围护桩1与第一支撑20间的支撑横梁210、顶端支撑在支撑横梁210底部的钢立柱211,如图5和图6所示,支撑横梁210与斜撑管200间焊连接,支撑横梁210与钢立柱211间焊连接,焊缝厚度均不少于10mm,钢立柱211底端埋插在土层深处。The support assembly 2 includes a first support 20 diagonally braced between the crown beam 10 and the bottom of the foundation pit, the first support 20 is arranged corresponding to the surrounding protection pile 1, and the angle between the first support 20 and the surrounding protection pile 1 is greater than 35°, The first support 20 is in contact with the surrounding protection pile 1, and the second support 21 is supported. The first support 20 includes a slanting tube 200. The slanting tube 20 can be selected from a round steel tube or a square steel tube. To support the role of support, after the diagonal brace 200 is in place, it also serves as a pouring channel, pouring graded crushed stone and pure cement into the diagonal brace 200 from the top of the diagonal brace 200, forming a pouring head at the bottom of the diagonal brace 200, to Increase the contact area between the first support and the soil layer to achieve the purpose of increasing the connection strength and preventing subsidence. Compared with prefabricated concrete piles, it is more economical and part of the diagonal brace 200 can be recycled. The top of the diagonal brace 200 Anchored at the crown beam 10, in a more optimal embodiment, as shown in Figure 4, several anchor bars are arranged around the top of the diagonal brace 200, and the anchor bars are bound together with the steel structure in the crown beam 10, so In actual implementation, the first support 20 and the crown beam 10 are poured at the same time, and the bottom of the diagonal support pipe 200 is buried deep in the soil layer; the second support 21 includes a support beam abutted between the surrounding protection pile 1 and the first support 20 210. The top is supported on the steel column 211 at the bottom of the support beam 210, as shown in Figure 5 and Figure 6, the support beam 210 is welded to the diagonal brace pipe 200, and the support beam 210 is welded to the steel column 211, and the thickness of the weld is uniform Not less than 10mm, the bottom of the steel column 211 is buried deep in the soil layer.

实施例2Example 2

如图1和图2所示的一种基坑围护结构,围护桩1与基坑侧壁间设置有若干个竖向止水桩11,以起到防水和挡土的作用,竖向止水桩11为三轴搅拌桩,三轴搅拌桩套接一孔设置,桩底标高在基坑底部7m以下。A foundation pit enclosure structure as shown in Figure 1 and Figure 2, several vertical water stop piles 11 are arranged between the enclosure pile 1 and the side wall of the foundation pit to play the role of waterproof and soil retaining, vertical The water stop pile 11 is a three-axis stirring pile, and the three-axis stirring pile is sleeved with a hole, and the pile bottom elevation is below 7m at the bottom of the foundation pit.

在本例中,支撑横梁210一端通过双拼围檩212与围护桩1固定连接,支撑横梁210另一端通过焊接与斜撑管200固定连接,双拼围檩212由工字钢、槽钢、钢板或其它型钢制成的四边形结构,具体的,选用(尺寸为高度×宽度×腹板厚度×翼缘厚度)2H700×300×13×24的型钢,两根双拼制成,双拼围檩212一端预埋浇筑在围护桩1一侧,双拼围檩212另一端通过焊接与支撑横梁210固定连接,支撑横梁210由圆钢管或方钢管制成的杆状结构,具体的,支撑横梁210选用直径为609mm,壁厚16mm的圆钢管。In this example, one end of the supporting beam 210 is fixedly connected to the enclosure pile 1 through a double-folded purlin 212, and the other end of the supporting beam 210 is fixedly connected to the diagonal bracing pipe 200 by welding. , steel plate or other shaped steel made of quadrilateral structure, specifically, choose (dimensions: height×width×web thickness×flange thickness) 2H700×300×13×24 shaped steel, made of two double pieces, double piece around One end of the purlin 212 is pre-buried and poured on one side of the enclosure pile 1, and the other end of the double-split enclosure 212 is fixedly connected to the support beam 210 by welding. The support beam 210 is a rod-shaped structure made of a round steel pipe or a square steel pipe. Specifically, the support The beam 210 is a circular steel pipe with a diameter of 609 mm and a wall thickness of 16 mm.

如图7和图8所示,配筋垫层组件4上侧设置有坑内建筑结构3,坑内建筑结构3包括底板31,坑内建筑结构3通过传力带5与围护桩1相连,所述斜撑管200依次倾斜穿过坑内建筑结构3和配筋垫层组件4埋插在土层深处,斜撑管200与底板31中部相交位置处设置有止水钢板30,如图9所示,斜撑管200穿过止水钢板300,斜撑管200外壁与止水钢板300焊接为一体,传力带5一端预埋浇筑在坑内建筑结构3一侧,传力带5另一端锚入围护桩1中。传力带5包括底板传力带50和中楼板传力带51 ,底板传力带50主体设置在配筋垫层组件4上部,底板传力带50一端预埋浇筑在底板31一端,底板传力带50另一端锚入围护桩1中,中楼板传力带51与中楼板同时浇筑,中楼板传力带51钢筋一侧锚入中楼板、另一侧通过吊筋与围护桩1主筋焊接,中楼板传力带51布置于第一支撑20间隙中、沿基坑周边等间距间隔布置。As shown in Figures 7 and 8, the upper side of the reinforced cushion assembly 4 is provided with a building structure 3 in the pit, the building structure 3 in the pit includes a bottom plate 31, and the building structure 3 in the pit is connected to the enclosure pile 1 through a force transmission belt 5, the said The diagonal bracing pipe 200 passes through the building structure 3 and the reinforced cushion assembly 4 in the pit in turn and is buried deep in the soil layer. A water-stop steel plate 30 is provided at the intersection of the diagonal bracing pipe 200 and the middle of the bottom plate 31, as shown in FIG. 9 , the diagonal bracing pipe 200 passes through the water-stop steel plate 300, the outer wall of the diagonal bracing pipe 200 is welded with the water-stop steel plate 300, one end of the power transmission belt 5 is pre-buried and poured on the side of the building structure 3 in the pit, and the other end of the power transmission belt 5 is anchored Fence pile 1. The power transmission belt 5 includes a base plate power transmission belt 50 and a middle floor power transmission belt 51. The main body of the base plate power transmission belt 50 is arranged on the upper part of the reinforcement cushion assembly 4. One end of the bottom plate power transmission belt 50 is pre-buried and poured on one end of the bottom plate 31. The bottom plate transmission belt The other end of the force belt 50 is anchored into the surrounding protection pile 1, and the force transmission belt 51 of the middle floor is poured at the same time as the middle floor. The main reinforcement is welded, and the force transmission belt 51 of the middle floor is arranged in the gap of the first support 20 and arranged at equal intervals along the periphery of the foundation pit.

一种基坑围护结构的施工方法,包括以下步骤:A construction method for a foundation pit enclosure structure, comprising the following steps:

步骤一,围护桩1施工,如图10所示,根据图纸测绘放样,在现场标注定位围护桩1和竖向止水桩11位置,并完成围护桩1、冠梁10和竖向止水桩11的施工;Step 1, the construction of the enclosure pile 1, as shown in Figure 10, according to the drawings and surveying and setting out, mark and locate the location of the enclosure pile 1 and the vertical water stop pile 11 on site, and complete the enclosure pile 1, the crown beam 10 and the vertical Construction of water stop pile 11;

步骤二,第一支撑20施工,如图11所示,将斜撑管200静压至土层内指定深度后,先向斜撑管200内灌入级配碎石,然后再向斜撑管200内灌入纯水泥至斜撑管200顶部,斜撑管200顶部四周通过焊接均匀连接若干根锚筋,锚筋与冠梁10内的钢筋结构绑扎并浇筑连接;Step 2, construction of the first support 20, as shown in Figure 11, after the diagonal brace 200 is statically pressed to the specified depth in the soil layer, the graded gravel is poured into the diagonal brace 200 first, and then the diagonal brace 200 is poured into the diagonal brace 200 200 pours pure cement to the top of the brace pipe 200, the top of the brace pipe 200 is evenly connected with a number of anchor bars by welding, and the anchor bars are tied to the steel structure in the crown beam 10 and connected by pouring;

步骤三,第一皮土开挖,如图12所示,分层分块开挖土层至支撑横梁210设计位置处,架设若干组第二支撑21,通过连接梁6将相邻第二支撑21间固定连接,基坑内所有的第二支撑21被连接成一个整体,本例中,钢立柱211和连接梁6均选用规格为(尺寸为高度×宽度×腹板厚度×翼缘厚度)H400×400×13×21的工字钢;Step 3, excavation of the first skin soil, as shown in Figure 12, excavate the soil layer in layers and blocks to the design position of the support beam 210, erect several groups of second supports 21, and connect the adjacent second supports 21 through the connecting beam 6 21 are fixedly connected, and all the second supports 21 in the foundation pit are connected into a whole. In this example, the steel column 211 and the connecting beam 6 are all selected with a specification of (dimensions: height×width×web thickness×flange thickness) H400 ×400×13×21 I-beam;

步骤四,第二皮土开挖,如图13和图14所示,分层分块开挖至基坑底部,施工配筋垫层组件4,随后施工底板31以及底板传力带50,底板31中部与斜撑管200的相交处设置止水钢板30;待底板31与底板传力带50达到设计强度的80%后,拆除连接梁6与第二支撑21,继续施工中楼板和中楼板传力带51,待中楼板和中楼板传力带51达到设计强度的80%后,将斜撑管200一端沿底板31顶面平齐切除、另一端沿围护桩1侧面平齐切除;Step 4, excavation of the second leather soil, as shown in Figure 13 and Figure 14, excavated layer by block to the bottom of the foundation pit, construction of the reinforcement cushion component 4, and then the construction of the bottom plate 31 and the bottom plate force transmission belt 50, the bottom plate Set the waterproof steel plate 30 at the intersection of the middle part of 31 and the diagonal bracing pipe 200; after the bottom plate 31 and the bottom plate force transmission belt 50 reach 80% of the design strength, remove the connecting beam 6 and the second support 21, and continue the construction of the middle floor and the middle floor The force transmission belt 51, after the middle floor and the middle floor force transmission belt 51 reach 80% of the design strength, one end of the diagonal brace pipe 200 is cut off along the top surface of the bottom plate 31, and the other end is cut off along the side of the enclosure pile 1;

步骤五,基坑回填,如图16所示,施工坑内建筑结构3至正负零,进行基坑回填。Step five, foundation pit backfilling, as shown in Figure 16, the building structure 3 in the construction pit is filled to plus or minus zero, and the foundation pit is backfilled.

上述实施例只是对本发明构思和实现的若干说明,并非对其进行限制,在本发明构思下,未经实质变换的技术方案仍然在保护范围内。The above-mentioned embodiments are only some illustrations of the conception and realization of the present invention, and are not intended to limit it. Under the conception of the present invention, technical solutions without substantial changes are still within the scope of protection.

Claims (9)

1. The utility model provides a foundation pit retaining structure, includes the foundation pit, and the foundation pit is provided with a plurality of fender pile (1) at even interval all around, and a plurality of fender pile (1) tops are through guan liang (10) fixed connection, its characterized in that: a plurality of groups of supporting components (2) are arranged in the foundation pit, the supporting components (2) are supported on one side of the fender post (1), and the supporting components (2) are connected into a whole through connecting beams (6); the bottom of the foundation pit is provided with a reinforcement cushion component (4) around, and the bottom of the supporting component (2) penetrates through the reinforcement cushion component (4) and is embedded in the deep part of the soil layer;
the supporting component (2) comprises a first support (20) which is obliquely supported between the top beam (10) and the bottom of the foundation pit, the first support (20) is arranged corresponding to the fender post (1), and a second support (21) is abutted and supported between the first support (20) and the fender post (1); the first support (20) comprises an inclined supporting pipe (200), a pouring head (201) is arranged at the bottom of the inclined supporting pipe (200), the top end of the inclined supporting pipe (200) is anchored at the crown beam (10), and the bottom of the inclined supporting pipe (200) is embedded in the deep soil layer; the second support (21) comprises a support cross beam (210) abutted between the fender post (1) and the first support (20) and a steel upright post (211) with the top end supported at the bottom of the support cross beam (210), and the bottom end of the steel upright post (211) is embedded and inserted at the depth of a soil layer;
the reinforcement cushion assembly (4) comprises a reinforcement cushion layer (40) and a plurality of dowel bars (41) which are uniformly arranged at the bottom of the reinforcement cushion layer (40) at intervals, the reinforcement cushion layer (40) is formed by casting double-sided bidirectional reinforcement and concrete, and the reinforcement cushion layer (40) is laid on the periphery of the bottom surface of the foundation pit and is spliced with a soil layer at the bottom of the foundation pit through the dowel bars (41).
2. The foundation pit enclosure structure of claim 1, wherein: a plurality of vertical water stopping piles (11) are arranged between the fender post (1) and the side wall of the foundation pit.
3. A foundation pit enclosure structure according to claim 1 or 2, wherein: the periphery of the top of the inclined supporting pipe (200) is provided with a plurality of anchor bars, and the anchor bars are bound with the steel bar structure in the crown beam (10) into a whole.
4. A foundation pit enclosure structure according to claim 1 or 2, wherein: one end of the supporting cross beam (210) is fixedly connected with the fender post (1) through a double-splicing surrounding purlin (212), and the other end of the supporting cross beam (210) is fixedly connected with the inclined supporting pipe (200).
5. The foundation pit enclosure structure of claim 4, wherein: the double-spliced enclosing purlin (212) is of a quadrilateral structure made of I-shaped steel, channel steel or steel plates; the supporting beam (210) is of a rod-shaped structure made of round steel pipes or square steel pipes.
6. The foundation pit enclosure structure of claim 1, wherein: the connecting beam (6) is made of I-shaped steel or channel steel, and the connecting beam (6) is connected between two adjacent supporting cross beams (210).
7. A foundation pit enclosure structure according to any one of claims 1-6, wherein: the upper side of the reinforcement distribution cushion assembly (4) is provided with a built-in pit structure (3), the built-in pit structure (3) comprises a bottom plate (31), the built-in pit structure (3) is connected with the fender pile (1) through a force transmission belt (5), the inclined stay tubes (200) sequentially penetrate through the built-in pit structure (3) and the reinforcement distribution cushion assembly (4) in an inclined mode and are buried in deep soil layers, and water stop steel plates (30) are arranged at the intersecting positions of the inclined stay tubes (200) and the middle of the bottom plate (31).
8. A foundation pit enclosure structure according to claim 7, characterized in that: one end of the force transmission belt (5) is embedded and poured at one side of the in-pit building structure (3), and the other end of the force transmission belt (5) is anchored into the fender pile (1); the force transmission belt (5) comprises a bottom plate force transmission belt (50) and a middle floor plate force transmission belt (51), the main body of the bottom plate force transmission belt (50) is arranged at the upper part of the reinforced cushion layer component (4), one end of the bottom plate force transmission belt (50) is embedded and poured at one end of the bottom plate (31), and the other end of the bottom plate force transmission belt (50) is anchored into the enclosure pile (1); one side of a reinforcing steel bar of the middle floor slab force transmission belt (51) is anchored into the middle floor slab, and the other side of the reinforcing steel bar is welded with a main steel bar of the fender post (1) through a hanging steel bar; the middle floor slab force transmission belts (51) are arranged in the gap of the first support (20) and are arranged at equal intervals along the periphery of the foundation pit.
9. A construction method of a foundation pit support structure according to any one of claims 1-6, characterized by comprising the following steps:
firstly, constructing a fender pile (1), mapping and lofting according to a drawing, marking and positioning the positions of the fender pile (1) and a vertical water stop pile (11) on site, and completing construction of the fender pile (1), a crown beam (10) and the vertical water stop pile (10);
step two, constructing a first support (20), namely, after statically pressing the inclined supporting pipe (200) to a specified depth in a soil layer, firstly filling graded broken stones into the inclined supporting pipe (200), then filling pure cement into the inclined supporting pipe (200) to the top of the inclined supporting pipe (200), uniformly connecting a plurality of anchor bars around the top of the inclined supporting pipe (200) by welding, and binding and pouring the anchor bars with a steel bar structure in the crown beam (10);
thirdly, excavating first subsoil, excavating soil layers to the design position of a supporting beam (210) in a layered and partitioned manner, erecting a plurality of groups of second supports (21), fixedly connecting adjacent second supports (21) through connecting beams (6), and connecting all the second supports (21) in the foundation pit into a whole;
fourthly, excavating second soil, excavating to the bottom of the foundation pit in layers and blocks, constructing a reinforcement cushion layer assembly (4), then constructing a bottom plate (31) and a bottom plate force transmission belt (50), and arranging a water stop steel plate (30) at the intersection of the middle part of the bottom plate (31) and the inclined support pipe (200); after the strength of the bottom plate (31) and the bottom plate force transmission belt (50) meets the requirement, the connecting beam (6) and the second support (21) are dismantled, the middle floor plate and the middle floor plate force transmission belt (51) continue to be constructed, after the strength of the middle floor plate and the middle floor plate force transmission belt (51) meets the requirement, one end of the inclined supporting pipe (200) is cut off along the top surface of the bottom plate (31) in a flush manner, and the other end of the inclined supporting pipe is cut off along the side surface of the fender post (1) in a flush manner;
and fifthly, backfilling the foundation pit, wherein the building structure (3) in the construction pit is positive and negative, and backfilling the foundation pit.
CN202211473678.2A 2022-11-23 2022-11-23 A foundation pit retaining structure and construction method Active CN115595986B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211473678.2A CN115595986B (en) 2022-11-23 2022-11-23 A foundation pit retaining structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211473678.2A CN115595986B (en) 2022-11-23 2022-11-23 A foundation pit retaining structure and construction method

Publications (2)

Publication Number Publication Date
CN115595986A true CN115595986A (en) 2023-01-13
CN115595986B CN115595986B (en) 2025-06-24

Family

ID=84853641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211473678.2A Active CN115595986B (en) 2022-11-23 2022-11-23 A foundation pit retaining structure and construction method

Country Status (1)

Country Link
CN (1) CN115595986B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116104106A (en) * 2023-03-15 2023-05-12 苏州建筑工程监理有限公司 Manufacturing and using method of diagonal bracing supporting structure
CN116122306A (en) * 2023-03-18 2023-05-16 方远建设集团股份有限公司 A block-based enclosure and isolation method for foundation pit support and earthwork excavation
CN116950086A (en) * 2023-08-02 2023-10-27 江苏建院营造股份有限公司 Deep foundation pit supporting system with micro-deformation self-adjusting control function and construction method thereof
CN117026995A (en) * 2023-08-02 2023-11-10 中铁上海工程局集团有限公司 A recyclable diagonal brace compression steel pipe pile used for foundation pit support

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103882869A (en) * 2014-03-21 2014-06-25 郭永 Inclined supporting pile structure for foundation pit support and construction method thereof
CN205134327U (en) * 2015-11-10 2016-04-06 中天建设集团有限公司 Concrete diclinic props row -pile support system
CN106013172A (en) * 2016-07-01 2016-10-12 杭州江润科技有限公司 Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method
CN113818451A (en) * 2021-10-21 2021-12-21 城地建设集团有限公司 A diagonal double-row all-steel enclosure system
KR102364430B1 (en) * 2021-05-12 2022-02-16 이기환 Retaining wall having raker and construction method thereof
CN114197483A (en) * 2021-12-22 2022-03-18 上海建工四建集团有限公司 Foundation pit support structure and construction method thereof
CN114250784A (en) * 2020-09-25 2022-03-29 上海城地建设工程有限公司 Foundation pit enclosure system combining piles with inclined piles in support-first and excavation-later construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103882869A (en) * 2014-03-21 2014-06-25 郭永 Inclined supporting pile structure for foundation pit support and construction method thereof
CN205134327U (en) * 2015-11-10 2016-04-06 中天建设集团有限公司 Concrete diclinic props row -pile support system
CN106013172A (en) * 2016-07-01 2016-10-12 杭州江润科技有限公司 Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method
CN114250784A (en) * 2020-09-25 2022-03-29 上海城地建设工程有限公司 Foundation pit enclosure system combining piles with inclined piles in support-first and excavation-later construction method
KR102364430B1 (en) * 2021-05-12 2022-02-16 이기환 Retaining wall having raker and construction method thereof
CN113818451A (en) * 2021-10-21 2021-12-21 城地建设集团有限公司 A diagonal double-row all-steel enclosure system
CN114197483A (en) * 2021-12-22 2022-03-18 上海建工四建集团有限公司 Foundation pit support structure and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116104106A (en) * 2023-03-15 2023-05-12 苏州建筑工程监理有限公司 Manufacturing and using method of diagonal bracing supporting structure
CN116122306A (en) * 2023-03-18 2023-05-16 方远建设集团股份有限公司 A block-based enclosure and isolation method for foundation pit support and earthwork excavation
CN116950086A (en) * 2023-08-02 2023-10-27 江苏建院营造股份有限公司 Deep foundation pit supporting system with micro-deformation self-adjusting control function and construction method thereof
CN117026995A (en) * 2023-08-02 2023-11-10 中铁上海工程局集团有限公司 A recyclable diagonal brace compression steel pipe pile used for foundation pit support

Also Published As

Publication number Publication date
CN115595986B (en) 2025-06-24

Similar Documents

Publication Publication Date Title
CN115595986A (en) A foundation pit enclosure structure and construction method
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN101418569B (en) Optimized composite arch wall with combination of prefabricated arch, support and main structure
CN105155558A (en) Combined retaining structure and construction method thereof
CN102995659B (en) Method for constructing from central area to periphery of ultra-large type underground engineering
CN109750681B (en) Filling side slope frame micro-tensioning support anchor plate supporting structure and construction method thereof
CN102162258B (en) Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof
CN100510281C (en) Semi-inverted construction method for storage tanks with super large diameter and super buried depth
CN206034454U (en) Supporting construction
CN110387889B (en) A multi-arch foundation pit support method for long strip deep foundation pits
CN213952237U (en) Take a four corners supporting beam's underground structure
CN219410378U (en) Rock slope overhanging type road structure
CN108035360A (en) A kind of method for pattern foundation pit supporting structure
CN201991013U (en) High-piled tower footing structure of tower crane concrete-filled steel tube
CN218861543U (en) Combined foundation pit support structure
CN111485560A (en) Supporting structure of deep foundation pit under ultra-wide pipeline and construction method of deep foundation pit under ultra-wide pipeline
CN218622256U (en) Double-row pile and inclined pile combined type foundation pit support structure
CN111877358B (en) A support structure, building and construction method for a foundation pit with upper soil layer and lower soft rock
CN112144548B (en) Semi-embedded multifunctional frame supporting structure and construction method thereof
CN108005086A (en) A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure
CN110939139B (en) Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles
CN219732023U (en) A kind of enclosure pile and steel diagonal brace enclosure structure
CN106013174A (en) An oblique support method for foundation pit support and an oblique support structure
CN211395688U (en) Double row pile supporting construction
CN211973513U (en) A kind of foundation pit enclosure pile gap excavation treatment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant