CN115595895A - Method for installing reinforcement cage in continuous beam construction - Google Patents
Method for installing reinforcement cage in continuous beam construction Download PDFInfo
- Publication number
- CN115595895A CN115595895A CN202211338414.6A CN202211338414A CN115595895A CN 115595895 A CN115595895 A CN 115595895A CN 202211338414 A CN202211338414 A CN 202211338414A CN 115595895 A CN115595895 A CN 115595895A
- Authority
- CN
- China
- Prior art keywords
- reinforcement cage
- hoisting
- steel
- cage
- continuous beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种连续梁施工中钢筋笼的安装方法,其中:钢筋笼的安装采用悬臂浇筑走行一体机;悬臂浇筑走行一体机包括支撑骨架系统和走行系统,走行系统设置在支撑骨架系统的下部;悬臂浇筑走行一体机通过走行系统行走至已浇筑完成的连续梁节段的前端,将预制完成的钢筋笼由支撑骨架系统的后端吊运至前端,调整钢筋笼的角度、前后及左右方位与下一连续梁浇筑节段设计位置的角度、前后及左右方位相一致,然后下放钢筋笼至已拼装好的外侧模之间的设计位置处。本发明能通过采用悬臂浇筑走行一体机,将预制完成的钢筋笼吊运至下一连续梁浇筑节段设计位置的上方,然后再下放,能克服钢筋笼散拼作业存在的工期时间长、工程质量难以保证的问题。
The invention discloses a method for installing a reinforcement cage in continuous beam construction, wherein: the installation of the reinforcement cage adopts a cantilever pouring and traveling integrated machine; the cantilever pouring and traveling integrated machine includes a support frame system and a travel system, and the travel system is arranged on the support frame system The lower part: the cantilever pouring and walking integrated machine walks to the front end of the poured continuous beam segment through the walking system, lifts the prefabricated steel cage from the back end of the supporting frame system to the front end, and adjusts the angle, front and rear and left and right of the steel cage The orientation is consistent with the angle, front and rear and left and right orientations of the next continuous beam pouring segment design position, and then lower the reinforcement cage to the design position between the assembled outer molds. The present invention can hoist the prefabricated reinforcement cage to the top of the design position of the next continuous beam pouring segment by adopting the cantilever pouring and walking integrated machine, and then lower it down, which can overcome the long construction period and engineering problems of the scattered reinforcement cage operation. Difficult to guarantee the quality of the problem.
Description
技术领域technical field
本发明涉及连续梁浇筑施工技术领域,尤其是一种连续梁施工中钢筋笼的安装方法。The invention relates to the technical field of continuous beam pouring construction, in particular to a method for installing a reinforcement cage in continuous beam construction.
背景技术Background technique
目前我国建筑行业发展迅速,预应力混凝土连续梁具有很多应用优势,包括连续梁结构刚度大、变形小、动力性能好,且在相同条件下,它比普通钢筋混凝土构件截面小、重量轻、刚度大、抗裂性和耐久性好,能有效地控制结构的挠度(甚至无挠度),节约钢材40~50%,节约混凝土20~40%,特别在大跨度结构中应用更为经济,因此,目前预应力混凝土连续梁桥的应用越来越广泛,现已成为桥梁工程建造使用的核心桥型之一。At present, my country's construction industry is developing rapidly. Prestressed concrete continuous beams have many application advantages, including continuous beams with large structural rigidity, small deformation, and good dynamic performance. Large, crack-resistant and durable, can effectively control the deflection of the structure (even no deflection), save 40-50% of steel, save 20-40% of concrete, especially in long-span structures, it is more economical, therefore, At present, the application of prestressed concrete continuous girder bridge is more and more extensive, and it has become one of the core bridge types used in bridge engineering construction.
悬臂浇筑法是连续梁桥施工常用的方法,但其施工工艺复杂,还有许多施工技术问题函待解决,现有的连续梁悬臂浇注挂篮通常使用人工辅助操作越多,悬臂浇筑施工周期就越长,以钢筋笼施工为例,这一环节为在连续梁模板组拼完成之后,再进行现场散拼作业,每个连续梁节段的钢筋笼散拼作业占据的施工工期约为2~3天,约占用了20%的节段施工时间,工期时间长,且由于钢筋笼散拼作业往往需要依靠作业人员的经验,加上现场作业空间相对狭窄,工具有限,往往导致钢筋作业质量较差,进一步影响连续梁的工程质量;为克服钢筋笼存在的上述缺陷,钢筋笼可在工厂、或在施工现场地面位置处、或在已经浇注好的连续梁梁段上面进行预制,而如何将预制钢筋笼安全地吊运至连续梁模板中,成为亟待解决的问题。The cantilever pouring method is a commonly used method in the construction of continuous beam bridges, but its construction process is complicated, and there are still many construction technical problems to be solved. The existing continuous beam cantilever pouring hanging basket usually uses more manual auxiliary operations, and the construction period of cantilever pouring will be shorter. The longer it is, taking the construction of steel cages as an example, this link is to carry out on-site loose assembly after the continuous beam formwork assembly is completed. The construction period occupied by the steel cage loose assembly of each continuous beam segment is about 2~ 3 days, about 20% of the segmental construction time is taken up, the construction period is long, and because the reinforcement cage scattered work often needs to rely on the experience of the operators, and the site operation space is relatively narrow, and the tools are limited, which often leads to the quality of the reinforcement work. Poor, which further affects the engineering quality of continuous beams; in order to overcome the above-mentioned defects of steel cages, steel cages can be prefabricated in the factory, at the ground position of the construction site, or on the continuous beam section that has been poured, and how Safely lifting the prefabricated steel cage into the continuous beam formwork has become an urgent problem to be solved.
发明内容Contents of the invention
本发明公开了一种连续梁施工中钢筋笼的安装方法,能通过采用悬臂浇筑走行一体机,将预制完成的钢筋笼吊运至下一连续梁浇筑节段设计位置的上方,然后再下放,能克服钢筋笼散拼作业存在的上述问题。The invention discloses a method for installing a reinforcement cage in continuous beam construction. By adopting a cantilever pouring and traveling integrated machine, the prefabricated reinforcement cage can be hoisted to the upper part of the design position of the next continuous beam pouring segment, and then lowered. It can overcome the above-mentioned problems existing in the scattered reinforcement cage operation.
为实现上述目的,本发明的技术方案为:To achieve the above object, the technical solution of the present invention is:
一种连续梁施工中钢筋笼的安装方法,其中:钢筋笼的安装采用悬臂浇筑走行一体机;悬臂浇筑走行一体机包括支撑骨架系统和走行系统,走行系统设置在支撑骨架系统的下部,用于实现支撑骨架系统的移动;A method for installing a reinforcement cage in continuous beam construction, wherein: the reinforcement cage is installed using a cantilever pouring and traveling integrated machine; the cantilever pouring and traveling integrated machine includes a support frame system and a travel system, and the travel system is set at the lower part of the support frame system for Realize the movement of the supporting skeleton system;
悬臂浇筑走行一体机通过走行系统行走至已浇筑完成的连续梁节段的前端,将预制完成的钢筋笼由支撑骨架系统的后端吊运至前端,调整钢筋笼的角度、前后及左右方位与下一连续梁浇筑节段设计位置的角度、前后及左右方位相一致,然后下放钢筋笼至已拼装好的外侧模之间的设计位置处。The cantilever pouring and walking integrated machine walks to the front end of the poured continuous beam segment through the walking system, lifts the prefabricated steel cage from the back end of the supporting frame system to the front end, and adjusts the angle, front and rear and left and right orientations of the steel cage The angle of the design position of the next continuous beam pouring segment, the front and rear and left and right directions are consistent, and then the reinforcement cage is lowered to the design position between the assembled outer molds.
进一步的,预制完成的钢筋笼在吊运之前,放置于梁面上的横断面与安装横断面垂直,吊运到支撑骨架系统前侧时,旋转90°使钢筋笼的角度与安装角度一致。Further, before the prefabricated reinforcement cage is hoisted, the cross section placed on the beam surface is perpendicular to the installation cross section, and when hoisted to the front side of the supporting frame system, it is rotated 90° to make the angle of the reinforcement cage consistent with the installation angle.
进一步的,悬臂浇筑走行一体机还包括钢筋笼装配系统,其包括钢筋笼吊运轨道、吊重车和吊具机构,所述钢筋笼吊运轨道固定在支撑骨架系统上部,所述吊重车能沿着所述钢筋笼吊运轨道在支撑骨架系统的前端和后端之间前后移动,所述吊重车连接有吊具机构用于吊装钢筋笼;Further, the cantilever pouring and walking integrated machine also includes a steel cage assembly system, which includes a steel cage lifting track, a hoisting vehicle and a spreader mechanism, the steel cage lifting track is fixed on the upper part of the supporting frame system, and the lifting vehicle It can move back and forth between the front end and the rear end of the supporting frame system along the steel cage hoisting track, and the hoisting vehicle is connected with a spreader mechanism for hoisting the steel cage;
将预制完成的钢筋笼由支撑骨架系统的后端吊运至前端具体包括:吊具机构移动至支撑骨架系统的后端,吊起钢筋笼,将钢筋笼沿着所述钢筋笼吊运轨道移动至施工前端,吊具机构旋转及前后、左右移动,调整钢筋笼的角度、前后及左右方位与设计位置的角度、前后及左右方位相一致,下放钢筋笼,安装至连续梁模板中的设计位置。Hoisting the prefabricated reinforcement cage from the rear end of the support frame system to the front end specifically includes: moving the spreader mechanism to the rear end of the support frame system, lifting the reinforcement cage, and moving the reinforcement cage along the reinforcement cage lifting track To the front end of the construction, the spreader mechanism rotates and moves back and forth, left and right, adjust the angle, front and rear and left and right directions of the reinforcement cage to be consistent with the angle, front and rear and left and right directions of the design position, lower the reinforcement cage, and install it to the design position in the continuous beam formwork .
更进一步的,所述吊具机构包括旋转吊具,旋转的角度不小于90°。Furthermore, the spreader mechanism includes a rotating spreader, and the angle of rotation is not less than 90°.
更进一步的,所述吊具机构包括吊具承重梁、吊装件和旋转吊具,所述吊重车至少设置有两个,之间连接有吊具承重梁,所述吊具承重梁下面设置有吊装件,所述吊装件能沿着吊具承重梁横向移动,所述吊装件下面悬吊有旋转吊具,所述旋转吊具用于吊装及转动钢筋笼。Furthermore, the spreader mechanism includes a spreader load-bearing beam, a hoisting piece and a rotating spreader, and at least two of the hoisting vehicles are provided, and the spreader load-bearing beam is connected between them, and the lower part of the spreader load-bearing beam is arranged There is a hoisting piece, which can move laterally along the load-bearing beam of the sling, and a rotating sling is suspended below the sling, and the rotating sling is used for hoisting and rotating the reinforcement cage.
更进一步的,所述旋转吊具采用电动回转机构。Furthermore, the rotating sling adopts an electric slewing mechanism.
进一步的,支撑骨架系统,其包括立柱、下行走梁、上承重梁和横联系结构,两根立柱、一根下行走梁和一根上承重梁围成支撑桁架,两片支撑桁架通过横联系结构连接;Further, the support frame system includes columns, lower walking beams, upper load-bearing beams and a horizontal connection structure. Two columns, a lower walking beam and an upper load-bearing beam form a support truss, and the two support trusses pass through the horizontal connection structure. connect;
其中:所述上承重梁的中部与位于前侧的所述立柱上端连接,内侧设置有钢筋笼吊运轨道,所述立柱为可伸缩结构。Wherein: the middle part of the upper load-bearing beam is connected to the upper end of the column located at the front side, and a steel cage hoisting track is arranged on the inner side, and the column is a telescopic structure.
更进一步的,所述支撑骨架系统中,在所述立柱、所述下行走梁和所述上承重梁围成的支撑桁架中,设置有可拆卸的骨架斜撑和/或骨架纵梁连接于两根立柱之间;Furthermore, in the support frame system, in the support truss enclosed by the column, the lower walking beam and the upper load-bearing beam, there are detachable frame braces and/or frame longitudinal beams connected to between two uprights;
和/或and / or
所述上承重梁的前端和位于前侧的所述立柱之间也连接有可拆卸的骨架斜撑;A detachable frame brace is also connected between the front end of the upper load-bearing beam and the upright at the front side;
和/或and / or
所述下行走梁后端能连接下行走梁延长段,下行走梁延长段与位于后侧的所述立柱纸件连接有可拆卸的骨架斜撑。The rear end of the lower walking beam can be connected to the extended section of the lower walking beam, and the extended section of the lower walking beam is connected to the paper part of the column at the rear side with a detachable skeleton brace.
进一步的,所述支撑骨架系统的底部和已浇筑的连续梁节段之间设置有反压轮机构,所述反压轮机构包括滚轴压轮、保护框架、连接板、连接摇杆和螺旋接头,所述滚轴压轮的长度能匹配下压支撑骨架系统的底部,所述保护框架围护在所述滚轴压轮的上方和外侧,且通过轴承与所述滚轴压轮连接,所述连接板上部与所述保护框架连接,下端与所述连接摇杆的上端转动连接,所述连接摇杆的下端与所述螺旋接头可拆卸连接,所述螺旋接头由下端口向上开设有内螺纹用于固定所述预埋固定件中的预埋精轧钢;走行系统走行及吊装钢筋笼过程中采用反压轮机构保持所述支撑骨架系统的底部不向前倾斜。Further, an anti-pressure wheel mechanism is provided between the bottom of the supporting frame system and the poured continuous beam segment, and the anti-pressure wheel mechanism includes a roller pressure wheel, a protective frame, a connecting plate, a connecting rocker and a screw Joint, the length of the roller pinch can match the bottom of the pressing support frame system, the protective frame surrounds the upper and outer sides of the roller pinch, and is connected with the roller pinch through a bearing, The upper part of the connecting plate is connected with the protective frame, and the lower end is rotationally connected with the upper end of the connecting rocker, and the lower end of the connecting rocker is detachably connected with the screw joint, and the screw joint is upwardly opened by a lower port. The internal thread is used to fix the pre-embedded finish-rolled steel in the pre-embedded fixture; the anti-pressure wheel mechanism is used to keep the bottom of the support frame system from tilting forward during the running of the running system and the hoisting of the reinforcement cage.
更进一步的,所述走行系统包括走行轮组件,所述走行轮组件包括走行驱动电机、变速器、主动轮、从动轮和围护钢架,所述走行驱动电机设置在围护钢架上面,为所述变速器转动提供动力,所述变速器通过传动件带动主动轮转动,所述主动轮通过传动件带动从动轮转动,所述主动轮和所述从动轮设置于所述围护钢架内,并通过轴承与所述围护钢架连接,能匹配行走于走行轨道机构上面,所述围护钢架上面设置有围护钢板叉耳,所述支撑骨架系统的底部设置有走行梁叉耳,围护钢板叉耳和走行梁叉耳之间通过销轴连接。Further, the traveling system includes a traveling wheel assembly, the traveling wheel assembly includes a traveling drive motor, a transmission, a driving wheel, a driven wheel and an enclosure steel frame, and the travel drive motor is arranged on the enclosure steel frame for The transmission is rotated to provide power, the transmission drives the driving wheel to rotate through the transmission part, and the driving wheel drives the driven wheel to rotate through the transmission part, the driving wheel and the driven wheel are arranged in the enclosure steel frame, and The bearing is connected with the surrounding steel frame, and can be matched and walked on the running track mechanism. The surrounding steel frame is provided with the fork lug of the surrounding steel plate, and the bottom of the supporting frame system is provided with the fork lug of the traveling beam. The fork lug of the guard plate and the fork lug of the traveling beam are connected by a pin shaft.
以上所述的连续梁施工中钢筋笼的安装方法,具有以下优点:The installation method of the reinforcement cage in the continuous beam construction described above has the following advantages:
(1)通过采用本发明,可实现将统一预制完成的钢筋笼运输和吊装至外侧模中的设计位置,节约了钢筋笼散拼作业的时间,可有效缩减单个梁段施工时长,加快工程进度,提高施工质量。(1) By adopting the present invention, the uniformly prefabricated reinforced cage can be transported and hoisted to the design position in the outer formwork, which saves the time for loose assembly of the reinforced cage, effectively reduces the construction time of a single beam section, and speeds up the progress of the project , Improve the construction quality.
(2)由于钢筋笼的宽度需要匹配连续梁节段宽度,因此宽度较大,为缩减支撑骨架系统的宽度,本发明吊运前设置钢筋笼的方向为与安装方向垂直,待吊运至支撑骨架系统前端待安装时,通过旋转吊具旋转90°,再下放至连续梁模板中,如此可有效缩减支撑骨架系统的宽度,提高施工的安全性。(2) Since the width of the steel cage needs to match the width of the continuous beam section, the width is relatively large. In order to reduce the width of the supporting frame system, the direction of setting the steel cage before hoisting in the present invention is perpendicular to the installation direction, and it is to be hoisted to the support When the front end of the skeleton system is to be installed, it is rotated 90° by the rotating hoist, and then lowered into the continuous beam formwork, which can effectively reduce the width of the supporting skeleton system and improve the safety of construction.
(3)本发明还将立柱设置为可伸缩结构,如此可在将钢筋笼由支撑骨架系统后端吊运至前端时提升立柱高度,保证钢筋笼顺利通过,而在吊装钢筋笼的装置整体移动时,降低立柱高度,降低吊装钢筋笼的装置的重心,提高施工的安全性。(3) The present invention also sets the column as a telescopic structure, so that the height of the column can be raised when the steel cage is hoisted from the rear end of the supporting frame system to the front end, so as to ensure the smooth passage of the steel cage, and the overall movement of the device for hoisting the steel cage At the same time, the height of the column is reduced, the center of gravity of the device for hoisting the steel cage is lowered, and the safety of the construction is improved.
附图说明Description of drawings
图1是本发明涉及的悬臂浇筑一体机应用于连续梁节段施工的主视结构示意图。Fig. 1 is a front structural schematic diagram of a cantilever pouring integrated machine used in continuous beam segmental construction according to the present invention.
图2是本发明涉及的悬臂浇筑一体机另一结构形式应用于连续梁节段施工的主视结构示意图。Fig. 2 is a schematic front view of another structural form of the cantilever pouring integrated machine involved in the present invention applied to continuous beam segmental construction.
图3是钢筋笼装配系统的主视结构示意图。Fig. 3 is a front view structural schematic diagram of the reinforcement cage assembly system.
图4是图3的左视结构示意图(省略多点吊架结构部分)。Fig. 4 is a left view structural diagram of Fig. 3 (the multi-point hanger structure part is omitted).
图5是图2中多点吊架结构的左视结构示意图。Fig. 5 is a left view structural diagram of the multi-point hanger structure in Fig. 2 .
图6是图5中吊架纵梁、吊架横梁和连接吊耳的俯视结构示意图。Fig. 6 is a top structural schematic view of the hanger longitudinal beam, the hanger beam and the connecting lugs in Fig. 5 .
图7是反压轮机构的结构示意图。Fig. 7 is a structural schematic diagram of the anti-pressure wheel mechanism.
图8是图7的中截面左视结构示意图。Fig. 8 is a schematic structural diagram of the left view in the middle section of Fig. 7 .
图9是走行轮组件的结构示意图。Fig. 9 is a schematic structural view of the traveling wheel assembly.
图10是图9在主动轮部分的截面结构示意图。Fig. 10 is a schematic cross-sectional structural view of the driving wheel in Fig. 9 .
图11是图2中支点顶升支撑机构的放大结构示意图。Fig. 11 is an enlarged structural schematic diagram of the fulcrum lifting support mechanism in Fig. 2 .
图12是图11的截面结构示意图。FIG. 12 is a schematic cross-sectional structure diagram of FIG. 11 .
图中,连续梁1,走行轮组件2,驱动电机201,变速器202,主动轮203,从动轮204,围护钢板叉耳205,围护钢板206,支撑卡具207,下行走梁3,骨架斜撑4,多点吊架结构5,旋转架501,柔性悬吊单元502,吊架纵梁503,吊架横梁504,连接吊耳505,钢筋笼吊钩506,旋转吊具6,吊装件7,吊重车8,钢筋笼吊运轨道9,立柱10,上承重梁11,钢筋笼12,反压轮机构13,保护框架1301,滚轴压轮1302,连接板1303,连接摇杆1304,螺旋接头1305,锚固下销轴1306,锚固上销轴1307,吊具承重梁14,走行梁叉耳15,走行轨道16,预埋螺纹钢17,支点顶升支撑机构18,顶升分配梁1801,顶升千斤顶1802,顶升下垫板1803。In the figure, the continuous beam 1, the
具体实施方式detailed description
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述。显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the drawings in the embodiments of the present invention. Apparently, the described embodiments are only some of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.
在本发明的描述中 ,需要说明的是,术语“上”、“下”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be noted that the orientation or positional relationship indicated by the terms "upper", "lower", etc. is based on the orientation or positional relationship shown in the drawings, or the conventionally placed position when the product of the invention is used. Orientation or positional relationship is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as a limitation of the present invention.
在本申请中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。In this application, terms such as "installation", "connection", "connection" and "fixation" should be interpreted in a broad sense, for example, it can be a fixed connection or a detachable connection, unless otherwise clearly specified and limited. , or into one body; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediary. Those of ordinary skill in the art can understand the specific meanings of the above terms in this application according to specific situations.
一种连续梁施工中钢筋笼的安装方法,如图1和图2所示,其中:钢筋笼的安装采用悬臂浇筑走行一体机;悬臂浇筑走行一体机包括支撑骨架系统和走行系统,走行系统设置在支撑骨架系统的下部,用于实现支撑骨架系统的移动;支撑骨架系统用于支撑钢筋笼的吊运和安装。安装方法包括以下步骤:悬臂浇筑走行一体机通过走行系统行走至已浇筑完成的连续梁节段的前端,将预制完成的钢筋笼12由支撑骨架系统的后端吊运至前端,调整钢筋笼12的角度、前后及左右方位与下一连续梁浇筑节段设计位置的角度、前后及左右方位相一致,然后下放钢筋笼12至已拼装好的外侧模之间的设计位置处。A method for installing a reinforcement cage in continuous beam construction, as shown in Figures 1 and 2, wherein: the installation of the reinforcement cage adopts a cantilever pouring and traveling integrated machine; the cantilever pouring and traveling integrated machine includes a supporting frame system and a traveling system, and the traveling system is set The lower part of the supporting frame system is used to realize the movement of the supporting frame system; the supporting frame system is used to support the hoisting and installation of the steel cage. The installation method includes the following steps: the cantilever pouring and walking integrated machine walks to the front end of the poured continuous beam segment through the walking system, lifts the
以下对外侧模作出解释,用于浇筑连续梁的模板,包括外侧模、内模和底模,底模位于外模装置的底部,钢筋笼设置在外侧模之间,其中间有通道设置内模。对于钢筋笼12的预制,可以是在工厂预制,可以在施工现场地面预制完成,也可以是在连续梁梁面上集中加工。出于便于运输考虑,当施工1#连续梁节段时,钢筋笼12在施工现场地面预制完成,通过塔吊吊装至支撑骨架系统内或前端,当施工2#连续梁节段及后续节段施工时,在连续梁梁面上集中加工,当悬臂浇筑走行一体机通过走行系统行走至已浇筑完成的连续梁节段的前端时,通过平板运输车将钢筋笼12运输至悬臂浇筑走行一体机的后端,由支撑骨架系统的后端吊运至前端即可。The outer formwork is explained below. The formwork used for pouring continuous beams includes the outer formwork, inner formwork and bottom formwork. The bottom formwork is located at the bottom of the outer formwork device. The reinforcement cage is set between the outer formworks, and there is a channel in the middle to set the inner formwork. . The prefabrication of the
进一步的,由于钢筋笼12的宽度需要匹配连续梁节段宽度,因此宽度较大,为最大限度地缩减支撑骨架系统的宽度,预制完成的钢筋笼在吊运之前,放置于梁面上的横断面与安装横断面垂直,吊运到支撑骨架系统前侧时,则需要旋转90°使钢筋笼的角度与安装角度一致。Further, since the width of the
进一步的,悬臂浇筑走行一体机还包括钢筋笼装配系统,包括钢筋笼吊运轨道9、吊重车8和吊具机构,钢筋笼吊运轨道9固定在支撑骨架系统上部,吊重车8能沿着钢筋笼吊运轨道9在支撑骨架系统的前端和后端之间前后移动,吊重车8连接有吊具机构用于吊装钢筋笼12。由于设置有钢筋笼吊运轨道9,钢筋笼12即可以通过吊具机构吊起,然后利用吊重车8由支撑骨架系统的后端行走至前端,如此即可实现钢筋笼在支撑骨架系统的移动。针对于该钢筋笼装配系统,将预制完成的钢筋笼由支撑骨架系统的后端吊运至前端的方法具体包括:吊具机构移动至支撑骨架系统的后端,吊起钢筋笼12,将钢筋笼12沿着钢筋笼吊运轨道9移动至施工前端,吊具机构旋转及前后、左右移动,调整钢筋笼12的角度、前后及左右方位与设计位置的角度、前后及左右方位相一致,下放钢筋笼,安装至连续梁模板中的设计位置。Further, the cantilever pouring and walking integrated machine also includes a steel cage assembly system, including a steel
更进一步的,为实现钢筋笼12的旋转,吊具机构至少包括旋转吊具6,旋转的角度不小于90°。钢筋笼12通过旋转吊具6旋转90°,再下放至连续梁模板中,如此可有效缩减支撑骨架系统的宽度,提高施工的安全性。Furthermore, in order to realize the rotation of the
更进一步的,本实施例提供了一种更便于实现本发明目的吊具机构,结合图3和图4所示,吊具机构包括吊具承重梁14、吊装件7和旋转吊具6,吊重车8至少设置有两个,之间连接有吊具承重梁14,吊具承重梁14下面设置有吊装件7,吊装件7下面悬吊有旋转吊具6,旋转吊具6用于吊装及转动钢筋笼12,钢筋笼吊钩506上端与吊架纵梁503连接。对于吊重车8,在本实施例中,由于钢筋笼12重量较大,钢筋笼吊运轨道9可以设置有2条,每根上承重梁11内侧均设置有一条,吊重车8可以设置有4辆,位于同一轨道上的吊重车8之间连接有吊重车连接纵梁,吊重车连接纵梁通过横向的吊具承重梁14连接为一整体,吊具承重梁14与吊装件7连接,吊装件7能沿着吊具承重梁14横向移动,该结构可采用现有的桁吊吊机,或者类似于龙门吊中的吊装结构,或是采用葫芦吊,且有驱动结构驱动葫芦吊左右移动,作为吊装件7,必然的,还可以完成钢筋笼12下放和提升的功能。Furthermore, this embodiment provides a spreader mechanism that is more convenient to realize the purpose of the present invention. As shown in FIG. 3 and FIG. There are at least two
更进一步的,旋转吊具6采用电动回转机构。常见的电动回转机构,即通过电机带动蜗杆,蜗杆带动涡轮旋转,进而带动旋转体旋转的机构,电动回转机构为现有技术,此处不再详述。Furthermore, the rotary hoist 6 adopts an electric slewing mechanism. A common electric rotary mechanism is a mechanism in which the motor drives the worm, the worm drives the turbine to rotate, and then drives the rotating body to rotate. The electric rotary mechanism is a prior art, and will not be described in detail here.
优选的,支撑骨架系统,其包括立柱10、下行走梁3、上承重梁11和横联系结构,两根立柱10、一根下行走梁3和一根上承重梁11围成支撑桁架,具体的,立柱10平行竖直设置,上端与上承重梁11连接,下端与下行走梁3连接,上承重梁11部分节段和下行走梁3部分节段与立柱10围成支撑桁架,两片支撑桁架通过横联系结构连接,支撑桁架为方形,该横联系结构可以是连接在立柱10之间、和/或上承重梁11之间,和/或下行走梁3之间,只需要将两个支撑桁架固定成整体即可,由于支撑骨架系统前端吊装钢筋笼受到的压力更大,因此,优选的,在两根上承重梁11的前端上面连接有上前横梁,在两根位于前侧的立柱10下部前面也连接有下后横梁,以更好的保证支撑骨架系统前侧的稳定性。为保证支撑骨架系统的稳定性和支撑强度,在立柱10、下行走梁3和上承重梁11围成的支撑桁架中,设置有可拆卸的骨架斜撑4和/或骨架纵梁连接于两根立柱10之间,本实施例图中所示为一种优选的方式,立柱10的中部之间连接有骨架纵梁,骨架斜撑4连接于立柱10顶端和骨架纵梁的中部之间、以及立柱10底端和骨架纵梁的中部之间。为使钢筋笼12吊装下放时不被支撑骨架系统所遮挡,上承重梁11的中部与位于前侧的立柱10上端连接,即上承重梁11前端伸出位于前侧的立柱10之外,为保证上承重梁11的支撑强度和稳定性,在上承重梁11的前端和位于前侧的立柱10之间也可以连接有可拆卸的骨架斜撑4;为保证整个支撑骨架系统的平衡性,在下行走梁3后端还可以连接有下行走梁延长段,下行走梁延长段和下行走梁3之间可以通过螺栓锚固,即如图2所示的结构,下行走梁延长段与位于后侧的立柱10之间连接有可拆卸的骨架斜撑4。对于支撑骨架系统中的可拆卸连接的方式,均可采用螺栓连接,方便拆装。Preferably, the support frame system includes a
优选的,立柱10为可伸缩结构。钢筋笼12预制可以在连续梁梁段上面的固定位置完成,而整个吊装钢筋笼12的装置运行到下一浇筑节段还有一定的距离,在吊装钢筋笼12的装置依靠走行系统整体移动时,降低立柱10高度,降低悬臂浇筑走行一体机的重心,如此可提高施工的安全性,而在将钢筋笼12由支撑骨架系统后端吊运至前端时,提升立柱10高度,能保证钢筋笼12顺利通过,不受支撑骨架系统的阻挡。对于立柱10的可伸缩结构,可以是两根套管式结构,如包括上立柱节段和下立柱节段,上立柱节段的下端套在下立柱节段的上端外围,并通过螺栓固定,当需要调整立柱10的高度时,解除螺栓,将上立柱节段向上或向下移动,移动完成后在用螺栓固定即可,当然也可以采用其他便于伸缩的形式,柱状物体的伸缩结构为现有技术,此处不再详细叙述。当立柱10之间设置有骨架斜撑4时,为适应立柱10的不同高度,骨架斜撑4也设置为可拆卸式,骨架斜撑4与立柱10之间的连接采用螺栓连接,根据立柱10的高度,选择合适长度的骨架斜撑4进行替换即可,或者换一种形式,骨架斜撑4也可以采用可伸缩结构。对于本实施例图中所示的骨架斜撑4连接于立柱10顶端和骨架纵梁的中部之间、以及立柱10底端和骨架纵梁的中部之间的结构,且立柱10采用套管式,在调整立柱10高度时,骨架纵梁与上立柱节段连接,因此,骨架纵梁上面的骨架斜撑4长度不需要调整,只需要调整骨架纵梁下面的骨架斜撑4即可。针对于上述支撑骨架系统,本实施例提供了一种钢筋笼吊运轨道9的具体设置方式,上承重梁11内侧设置有钢筋笼吊运轨道9,本实施例中,上承重梁11采用截面为L型的箱型梁,结合图3所示,两根上承重梁11的L型箱型梁呈横向延伸的底部相对设置,为钢筋笼吊运轨道9提供支撑。如此可充分利用现有的支撑骨架系统。Preferably, the
进一步的,由于钢筋笼重量较大,悬臂走行一体机在吊运时前端会承受较大的重力,因而,为保证悬臂浇筑走行一体机整体不向前倾覆,在支撑骨架系统的底部和已浇筑的连续梁节段之间设置有反压轮机构,针对于本实施例的支撑骨架系统,是在下行走梁3和已浇筑的连续梁1节段之间设置有反压轮机构,如图7和图8所示,反压轮机构包括包括滚轴压轮1302、保护框架1301、连接板1303、连接摇杆1304和螺旋接头1305,滚轴压轮1302的长度能匹配下压下行走梁3,保护框架1301围护在滚轴压轮1302的上方和外侧,且通过轴承与滚轴压轮1302连接,连接板1303上部与保护框架1301连接,下端与连接摇杆1304的上端转动连接,连接摇杆1304的下端与螺旋接头1305可拆卸连接,螺旋接头1305由下端口向上开设有内螺纹用于固定预埋固定件中的预埋精轧钢。设置滚轴压轮1302下压下行走梁3,在吊装装置需要前移时,由于滚轴压轮1302可以转动,也能保证悬臂浇筑走行一体机在低摩擦阻力下高效前移作业。设置有保护框架1301,是为保护滚轴压轮1302不被雨水和灰尘损伤,保护框架1301可以是包括上封板和侧扣板,上封板的两侧分别与侧扣板连接,滚轴压轮1302位于上封板和侧扣板围成的空间中,且两端分别通过轴承与侧扣板连接,侧扣板为滚轴压轮1302的旋转提供支撑,且能协同上封板一定程度的遮挡雨水和灰尘,更优选的,保护框架1301还包括前侧板和后侧板,上封板、侧扣板、前侧板和后侧板从滚轴压轮1302的上方和侧方围住滚轴压轮1302,下方是需要留出滚轴压轮1302压住下行走梁3的空间,而具体的侧扣板,其截面优选设置为L型,两块侧扣板之间的最短间距大于待固定结构的宽度,且其底端与上封板之间的距离大于待固定结构的高度,如此可防止滚轴压轮1302滑落,同时保证轴承能更好的发挥支承作用。本实施例中,滚轴压轮1302为铸钢锻造的滚轴,保护框架1301采用钢板制成,滚轴压轮1302的转动面与上封板间设置有间隙,以保证轴承发挥支承作用,同时减少滚动摩擦阻力,同时,也保证滚轴压轮1302接触待固定结构的表面保持良好润滑覆盖面,减少接触阻力。对于连接板1303的连接方式,本实施例也提供一种优选的方式,连接板1303上部与保护框架1301连接,且设置有通孔容纳滚轴压轮1302穿过。结合以上所述的保护框架1301的结构,连接板1303上边缘与上封板的底面连接,上部前、后边缘分别与前侧板和后侧板连接,如此能更好的固定连接板1303。对于连接板1303与连接摇杆1304的上端转动连接的方式,本实施例中,连接板1303的下端设置有连接板1303销孔,连接摇杆1304的上端也设置有摇杆上销孔,连接板1303销孔和摇杆上销孔中穿设有锚固上销轴1307或上螺栓使连接板1303和连接摇杆1304连接在一起,采用此种转动连接的方式,可以在吊装装置前移的过程中,或者是吊装施工过程中有微小角度的前倾时,转动连接处也能适应性的调整一定的角度,保持连接摇杆1304的向下垂直度,选择使用锚固上销轴1307能更好的满足这一要求,而采用锚固上销轴1307时,锚固上销轴1307与连接板1303和连接摇杆1304通过轴承连接,如此能极大限度保证反压机构施加下压作用力时减少被拖拽的作用趋势。对于连接摇杆1304的下端与螺旋接头1305可拆卸连接的方式,连接摇杆1304的下端设置有摇杆下销孔,接头部分设置有接头销孔,摇杆下销孔和接头销孔中穿设有锚固下销轴1306或下螺栓使连接摇杆1304和接头部分固定连接在一起。对于接头部分,本实施例采用的具体结构,包括一块横向钢板和两块竖向钢板,横向钢板的下面与螺旋紧固部分的上端连接,上面连接有两块平行的竖向钢板,竖向钢板之间的间隙能匹配插入连接摇杆1304的下端,竖向钢板设置有接头销孔,与摇杆下销孔的位置相对应,如此能更好的稳定与连接摇杆1304连接,此处采用下螺栓更方便拆卸。采用以上所述的锚固机构5的技术方案,即使在吊装装置移动的过程中,也能实现对走行支撑机构6的锚固,使其不会向前倾覆,进一步使吊装装置不会向前倾覆。更优选的,连接板1303设置有两组,且相对所述保护框架1301的竖向中心线对称,连接板1303之间的间距大于走行支撑机构6的宽度。在本实施例中,连接板1303位于侧扣板的内侧,每组连接板1303优选是包括两块连接板1303单元,且中间设置有间隙,容纳连接摇杆1304的上端插入,从而能从连接摇杆1304两侧夹住连接摇杆1304,避免待固定结构碰撞损伤到连接摇杆1304,延长锚固装置的使用寿命,同时也能更好的保证连接的稳定性。对于锚固的过程,具体为:在浇筑连续梁1节段时,预埋螺母及预埋螺纹钢17在连续梁1节段中,且预埋螺纹钢17上端伸出连续梁1节段,在浇筑下一连续梁1节段时,悬臂浇筑走行一体机移动至预埋螺纹钢17上方,将滚轴压轮1302压在下行走梁3上面,解除螺旋接头1305和连接摇杆1304之间的连接,将螺旋接头1305拧紧至螺纹钢上端,连接摇杆1304转动下放,使摇杆下销孔和接头销孔位置对应,用锚固下销轴1306或下螺栓将连接摇杆1304和螺旋接头1305固定在一起,即完成悬臂浇筑走行一体机的整体锚固。当需要调整反压轮机构的锚固位置时,解除螺旋接头1305和连接摇杆1304之间的连接,旋出螺旋接头1305,反压轮机构和/或悬臂浇筑走行一体机调整至合适的位置即可。走行系统走行及吊装钢筋笼过程中采用反压轮机构可保持支撑骨架系统的底部不向前倾斜,在本实施例中,滚轴压轮的长度下压下行走梁3,可保持整个支撑骨架系统不向前倾斜。Further, due to the heavy weight of the steel cage, the front end of the cantilever walking integrated machine will bear greater gravity during hoisting. An anti-pressure wheel mechanism is arranged between the continuous beam segments. For the supporting frame system of this embodiment, an anti-pressure wheel mechanism is arranged between the
更进一步的,走行系统包括走行轮组件2,走行轮组件2可直接采用多个滚动轮,为降低整个吊装装置的高度,本实施例还提供了一种优选的结构,结合图9和图10所示,走行轮组件2包括走行驱动电机201、变速器202、主动轮203、从动轮204和围护钢架206,走行驱动电机201设置在围护钢架206上面,围护钢架206为走行驱动电机201提供支撑,走行驱动电机201为变速器202转动提供动力,变速器202通过传动件带动主动轮203转动,主动轮203通过传动件带动从动轮204转动,传动件可采用皮带或链轮,根据实际情况选择,变速器202可以选择是比主动轮203半径小的齿轮或链轮结构。主动轮203和从动轮204半径相同,设置于围护钢架206内,并通过轴承与围护钢架206连接,围护钢架206可设置为方形,与走行轨道机构3保持一定的间隙,其能为主动轮203和从动轮204提供保护,同时为与主动轮203和从动轮204的转轴连接的轴承提供支撑力,主动轮203和从动轮204能匹配行走于走行轨道机构3上面,围护钢架206与下行走梁3转动连接。每条轨道匹配一个主动轮203和一个从动轮204,两条轨道上即设置有平行的两个主动轮203和两个从动轮204,每个走行支撑机构6可根据需要选择走行轮组件4的数量,通过本优选的走行轮组件4的结构,可保证对走行支撑机构6以上结构的支撑力,保证移动的稳定性。由于走行支撑机构6上面可能为框架性结构,其在钢筋笼12下放时由于重力下压而会具有外倾的趋势,因此,在围护钢架206的外侧可设置有支撑卡具207,支撑卡具207上端与围护钢架206连接,下端延伸至轨道外侧,其具有向内伸出的卡位柱,卡在轨道的外侧面,对于本实施例采用工字钢制成的轨道,卡位柱卡在工字钢翼缘的下面。更优选的,围护钢架206上面设置有围护钢架叉耳205,下行走梁3下面设置有走行梁叉耳15,围护钢架叉耳205和走行梁叉耳15之间通过销轴连接。采用此种销轴连接的方式,可以在吊装装置前移的过程中,或者是吊装施工过程中有微小角度的前倾时,销轴连接处也能适应性的调整一定的角度,防止位于行走后端的走行轮组件脱离轨道。Furthermore, the running system includes a running
为保证悬臂浇筑走行一体机按既定路线行走,走行系统还包括走行轨道16,走行轨道16包括轨道1601、轨道连接梁和梁面支撑垫梁1602,其中,梁面支撑垫梁1602,其间隔平行设置,沿施工设备的移动方向铺设,轨道1601设置有两条,且互相平行,垂直设置在梁面支撑垫梁1602,轨道1601之间间隔连接有轨道连接梁,轨道连接梁将轨道1601连接成为一个整体,由于连续梁1梁面会存在凹凸不平的情况,铺设有梁面支撑垫梁1602,可以保持走行轨道16的平整性,走行轨道16则为走行轮组件2提供走行的轨道。本实施例中,一根下行走梁3下面匹配有四组走行轮组件2,每两组互相平行,以保持下走行梁3的平衡性,互相平行的两组走行轮组件2分别运行在同一走行轨道16的两条轨道1601上,而每个悬臂浇筑走行一体机有两根下行走梁3,也匹配两条走行轨道16。本实施例中,轨道1601采用双拼I40工字钢定位焊接而成,轨道连接梁采用槽钢制作,两端与轨道1601焊接,走行轨道16可多节组拼,走行轨道16前端和后端均设置有轨道连接件,将轨道连接件通过螺栓固定即可将走行轨道16组拼在一起。走行轨道16的前端优选安装有支挡块,防止走行轮组件2走行超过设计位置。In order to ensure that the cantilever pouring and walking integrated machine runs according to the predetermined route, the running system also includes a running
优选的,本实施例还设置有支点顶升支撑机构18,支点顶升支撑机构18包括顶升千斤顶1802,顶升千斤顶1802的固定端与支撑骨架系统的底面前端连接,在本实施例中是与下行走梁3的底面前端连接。由于悬臂浇筑走行一体机的前端吊装钢筋笼12,重量较大,因此悬臂浇筑走行一体机会呈现前倾的趋势,而通过顶升千斤顶1802可以向支撑骨架系统的前端施加向上的力,减缓悬臂浇筑走行一体机整体前倾的趋势。顶升千斤顶1802的固定端与支撑骨架系统6连接,在悬臂浇筑走行一体机停止前移时,顶升千斤顶1802的活塞伸长,以施加向上的力,在悬臂浇筑走行一体机移动时,顶升千斤顶1802的活塞缩短,不影响走行轮组件2的移动。更优选的,本实施例还提供了一种能稳定悬臂浇筑走行一体机前端的支点顶升支撑机构18,结合图11和图12所示,还包括顶升分配梁1801和顶升下垫板1803,顶升千斤顶1802至少设置有2个,固定端的上面与所述顶升分配梁1801连接,伸缩端的下面与顶升下垫板1803连接,即2个或2个以上的顶升千斤顶1802的顶面通过顶升分配梁1801来连接,底端通过顶升下垫板1803来连接,与支撑骨架系统的连接是通过底面顶升分配梁1801来实现的,顶升千斤顶1802向上顶升的力量通过顶升分配梁1801来均匀的传递至走行支撑机构6所述顶升,而顶升下垫板1803能匹配扣在走行轨道16的上面,结合图中所示,可以是顶升下垫板1803两侧有向下伸出的下垫板定位部,两块下垫板定位部之间的距离能匹配扣在走行轨道机构3的上面,如此可防止发生偏移,同时还能将走行轨道16的支撑力均匀传递至顶升千斤顶1802。支点顶升支撑机构18同时还具有保护走行轮组件2的作用,避免工作载荷全部集中在走行轮组件2部分处受力。Preferably, this embodiment is also provided with a fulcrum lifting
为保证吊装过程中钢筋笼不容易发生变形,本实施例对于钢筋笼的吊运,还采用了多点吊架结构5,旋转吊具6下面连接有多点吊架结构5,结合图3-5所示,多点吊架结构5包括吊架横梁504、吊架纵梁503、连接吊耳505、柔性悬吊单元502、旋转架501和钢筋笼吊钩506,吊架横梁504至少设置有两根,且通过多根吊架纵梁503连接,吊架横梁504上面设置有连接吊耳505,连接吊耳505相对吊架横梁504的纵向中心线至少对称设置有4个,且通过柔性悬吊单元502与旋转架501连接,旋转架501与旋转吊具6连接,钢筋笼吊钩506上端与吊架纵梁503连接,下端用于钩住钢筋笼12。旋转吊具6旋转,带动旋转架501旋转,旋转架501再带动吊架横梁504和吊架纵梁503旋转,进而带动钢筋笼12旋转。本实施例所示的连接吊耳505有14个,每根吊架横梁504连接有7个,其中,在吊架横梁504的中间有1个,相对吊架横梁504的纵向中心线,每侧设置有3个,呈对称设置,其中同一侧边的3个连接吊耳505通过钢链或钢筋各自连接于旋转架501对应一侧边的一端,中间的1个连接吊耳505通过钢链或钢筋连接于旋转架501对应一侧边的中间,钢链或钢筋即为柔性悬吊单元502。通过多点吊架结构5,可以避免吊装过程中出现钢筋笼12变型的问题,同时也解决吊装过程中钢筋笼12吊装受力不均匀的问题。In order to ensure that the steel cage is not easily deformed during the hoisting process, this embodiment also adopts a
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211338414.6A CN115595895B (en) | 2022-10-28 | 2022-10-28 | Method for installing reinforcement cage in continuous beam construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211338414.6A CN115595895B (en) | 2022-10-28 | 2022-10-28 | Method for installing reinforcement cage in continuous beam construction |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115595895A true CN115595895A (en) | 2023-01-13 |
| CN115595895B CN115595895B (en) | 2026-02-03 |
Family
ID=84851535
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211338414.6A Active CN115595895B (en) | 2022-10-28 | 2022-10-28 | Method for installing reinforcement cage in continuous beam construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115595895B (en) |
Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH1121820A (en) * | 1997-07-08 | 1999-01-26 | Kumagai Gumi Co Ltd | Reinforcing bar assembling method of overhang erection method and mobile work vehicle used therefor |
| CN201890265U (en) * | 2010-10-20 | 2011-07-06 | 秦皇岛天业通联重工股份有限公司 | Two-way travelling cement and asphalt mortar vehicle chassis |
| CN202830783U (en) * | 2011-11-30 | 2013-03-27 | 浙江省交通工程建设集团有限公司第二分公司 | Triangle basket running device |
| CN104195952A (en) * | 2014-08-20 | 2014-12-10 | 中铁四局集团第二工程有限公司 | Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge |
| CN205576748U (en) * | 2016-04-15 | 2016-09-14 | 中铁五局集团有限公司 | Hang basket self -balancing left -hand thread wheel structure |
| CN107447678A (en) * | 2017-09-27 | 2017-12-08 | 中国葛洲坝集团第五工程有限公司 | A kind of erection crane of the two-way positioning of energy |
| JP2018039587A (en) * | 2016-09-05 | 2018-03-15 | トヨタ紡織株式会社 | Carrier device |
| JP2018112024A (en) * | 2017-01-13 | 2018-07-19 | 鹿島建設株式会社 | Reinforcement cage relocation device |
| CN212077660U (en) * | 2020-04-16 | 2020-12-04 | 中交一公局第四工程有限公司 | Large-span wide width bridge girder rhombus hanging basket construction structure |
| CN112982182A (en) * | 2021-03-04 | 2021-06-18 | 保利长大工程有限公司 | Variable-curve cast-in-place beam bottom web plate reinforcing steel bar integral hoisting equipment and use method thereof |
| CN217460328U (en) * | 2022-06-16 | 2022-09-20 | 中铁二十三局集团第一工程有限公司 | Hanging basket walking device for bridge |
-
2022
- 2022-10-28 CN CN202211338414.6A patent/CN115595895B/en active Active
Patent Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH1121820A (en) * | 1997-07-08 | 1999-01-26 | Kumagai Gumi Co Ltd | Reinforcing bar assembling method of overhang erection method and mobile work vehicle used therefor |
| CN201890265U (en) * | 2010-10-20 | 2011-07-06 | 秦皇岛天业通联重工股份有限公司 | Two-way travelling cement and asphalt mortar vehicle chassis |
| CN202830783U (en) * | 2011-11-30 | 2013-03-27 | 浙江省交通工程建设集团有限公司第二分公司 | Triangle basket running device |
| CN104195952A (en) * | 2014-08-20 | 2014-12-10 | 中铁四局集团第二工程有限公司 | Steel box girder erection method applied to steel and concrete hybrid girder cable-stayed bridge |
| CN205576748U (en) * | 2016-04-15 | 2016-09-14 | 中铁五局集团有限公司 | Hang basket self -balancing left -hand thread wheel structure |
| JP2018039587A (en) * | 2016-09-05 | 2018-03-15 | トヨタ紡織株式会社 | Carrier device |
| JP2018112024A (en) * | 2017-01-13 | 2018-07-19 | 鹿島建設株式会社 | Reinforcement cage relocation device |
| CN107447678A (en) * | 2017-09-27 | 2017-12-08 | 中国葛洲坝集团第五工程有限公司 | A kind of erection crane of the two-way positioning of energy |
| CN212077660U (en) * | 2020-04-16 | 2020-12-04 | 中交一公局第四工程有限公司 | Large-span wide width bridge girder rhombus hanging basket construction structure |
| CN112982182A (en) * | 2021-03-04 | 2021-06-18 | 保利长大工程有限公司 | Variable-curve cast-in-place beam bottom web plate reinforcing steel bar integral hoisting equipment and use method thereof |
| CN217460328U (en) * | 2022-06-16 | 2022-09-20 | 中铁二十三局集团第一工程有限公司 | Hanging basket walking device for bridge |
Non-Patent Citations (1)
| Title |
|---|
| 丁如珍: "五河口斜拉桥主梁悬浇施工技术", 公路, no. 11, 25 November 2005 (2005-11-25), pages 45 - 50 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115595895B (en) | 2026-02-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN218708558U (en) | Device for hoisting reinforcement cage in cantilever casting segment construction | |
| CN115637658B (en) | Cantilever casting walking machine | |
| CN108560927A (en) | A kind of Lift-on/Lift-off System and its application method of reinforced concrete column | |
| CN218712236U (en) | External mold device applied to continuous beam construction | |
| CN107640706A (en) | A kind of crane gear and its construction method | |
| CN115613478B (en) | Continuous beam cantilever pouring method | |
| CN209835463U (en) | Prefabricated bridge deck hoisting equipment | |
| JP2006028881A (en) | Self-propelled PC slab erection machine and PC slab erection method | |
| CN107253675B (en) | A self-propelled tower crown crane | |
| CN114808747A (en) | Multifunctional bridge girder erection machine and bridge girder erection construction method | |
| CN115613477B (en) | Main girder cantilever trackless triangular hanging basket and construction method | |
| CN110407113B (en) | Construction method for installation and displacement of tower crane | |
| CN111502293A (en) | Method and system for hoisting single peripheral component of assembly type building | |
| CN112030777B (en) | A down-type mobile formwork support bracket spanning transfer construction method | |
| CN115749232A (en) | Building machine and building method thereof | |
| CN223255842U (en) | A mounted arch bridge main arch ring maintenance operation platform | |
| CN117886229B (en) | Multifunctional integrated rail type lifting mechanism | |
| CN111139742B (en) | Method for mounting and dismounting highway bridge girder erection machine | |
| JP4649562B2 (en) | Position adjustment method and apparatus for bridge girder connection | |
| CN115595895A (en) | Method for installing reinforcement cage in continuous beam construction | |
| CN203334186U (en) | A wheel type device for cable-stayed bridge floor press anchoring | |
| CN217781781U (en) | Self-walking operation platform for construction of cable-stayed bridge bottom | |
| CN117211524A (en) | Movable arm distributing machine elevator shaft climbing formwork integrated platform | |
| CN115897417A (en) | A formwork construction method and device in the process of cantilever pouring continuous beams | |
| CN218712237U (en) | Walking structure for continuous beam construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
