CN115573503A - A method of installing a prefabricated suspended ceiling - Google Patents

A method of installing a prefabricated suspended ceiling Download PDF

Info

Publication number
CN115573503A
CN115573503A CN202210984301.7A CN202210984301A CN115573503A CN 115573503 A CN115573503 A CN 115573503A CN 202210984301 A CN202210984301 A CN 202210984301A CN 115573503 A CN115573503 A CN 115573503A
Authority
CN
China
Prior art keywords
keel
semi
installing
gypsum board
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210984301.7A
Other languages
Chinese (zh)
Inventor
彭伟
孙文
陆志强
史法亮
马艳婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Laizhuang Speed Matching Technology Co ltd
Original Assignee
Suzhou Laizhuang Speed Matching Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Laizhuang Speed Matching Technology Co ltd filed Critical Suzhou Laizhuang Speed Matching Technology Co ltd
Priority to CN202210984301.7A priority Critical patent/CN115573503A/en
Publication of CN115573503A publication Critical patent/CN115573503A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/04Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • E04B9/10Connections between parallel members of the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/22Connection of slabs, panels, sheets or the like to the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention discloses an installation method of an assembled ceiling, belonging to the technical field of ceilings and comprising the following steps: s1: processing the gypsum board in the back field in batches according to the typesetting drawing, and fixing the gypsum board by using auxiliary keels and screws; s2: installing the hanging ribs and the main keels according to the typesetting drawing; s3: after the auxiliary keel and the gypsum board are fixed by screws, performing batch nail hole treatment, putty scraping, polishing and first latex paint treatment on a back operation table to form a semi-finished veneer; s4: the semi-finished veneer and the main keel are fixed and leveled through fasteners; s5: and (4) after all the semi-finished decorative panels are installed, processing the seams by using a seam material, and finishing the subsequent emulsion paint decorative surface after the processing. According to the invention, through the steps of batch putty batching, polishing and emulsion paint making on the back site, the auxiliary keel and the gypsum board emulsion paint veneer can be assembled and installed after the on-site hanging ribs and the main keel are installed, the structure does not need to be dried naturally, the construction period is greatly shortened, and the whole structure is simple and easy to install.

Description

一种装配式吊顶的安装方法A method of installing a prefabricated suspended ceiling

技术领域technical field

本发明属于吊顶技术领域,尤其涉及一种装配式吊顶的安装方法。The invention belongs to the technical field of suspended ceilings, in particular to a method for installing a fabricated suspended ceiling.

背景技术Background technique

现有传统石膏板吊顶技术中,因为空间小,工序多,造成石膏板吊顶经常小空间交叉施工,且批腻子工序受天气影响较大,导致石膏板吊顶总工期受影响。传统石膏板吊顶技术中通常是先确定标高,然后制作边龙骨、吊筋、主龙骨、副龙骨、封石膏板、批腻子、打磨、乳胶漆。每一道施工工序必须按部就班,且会受到天气影响导致腻子自然风干时间有所延迟,间接耽误工期。In the existing traditional gypsum board ceiling technology, due to the small space and many processes, the gypsum board ceiling is often cross-constructed in a small space, and the putty process is greatly affected by the weather, which affects the total construction period of the gypsum board ceiling. In the traditional gypsum board ceiling technology, the elevation is usually determined first, and then the side keel, hanging rib, main keel, auxiliary keel, sealing gypsum board, putty, grinding, and latex paint are made. Every construction process must be done step by step, and the natural air-drying time of the putty will be delayed due to the influence of the weather, which indirectly delays the construction period.

发明内容Contents of the invention

本发明的目的在于:为了解决现有传统石膏板吊顶安装过程中,安装的每一道施工工序必须按部就班,且会受到天气影响导致腻子自然风干时间有所延迟,间接耽误工期而提出的一种装配式吊顶的安装方法。The purpose of the present invention is: in order to solve the existing traditional gypsum board ceiling installation process, each installation process must be done step by step, and the natural air drying time of the putty will be delayed due to the influence of the weather, which indirectly delays the construction period. How to install a suspended ceiling.

为了实现上述目的,本发明采用了如下技术方案:一种装配式吊顶的安装方法,包括以下步骤:In order to achieve the above object, the present invention adopts the following technical solution: a method for installing a prefabricated suspended ceiling, comprising the following steps:

S1:后场批量化按排版图加工好石膏板尺寸,并用副龙骨用螺丝固定;S1: The size of the gypsum board is processed in batches according to the layout drawing in the back field, and the auxiliary keel is fixed with screws;

S2:根据排版图安装吊筋及主龙骨;S2: Install hanging bars and main keels according to the layout drawing;

S3:所述副龙骨与所述石膏板用螺丝固定完成后,后场操作台批量钉眼处理、腻子刮平、打磨、第一遍乳胶漆形成半成品饰面板;S3: After the auxiliary keel and the gypsum board are fixed with screws, batches of nail holes are processed on the backyard console, the putty is smoothed, polished, and the first pass of latex paint is used to form a semi-finished decorative panel;

S4:半成品饰面板与所述主龙骨通过扣件固定、调平;S4: The semi-finished decorative panel and the main keel are fixed and leveled by fasteners;

S5:安装所有所述半成品饰面板后使用接缝材料对接缝进行处理,处理后完成后续乳胶漆饰面工作。S5: After installing all the semi-finished decorative panels, use the joint material to process the joints, and complete the subsequent latex paint finishing work after the treatment.

作为上述技术方案的进一步描述:As a further description of the above technical solution:

所述吊筋为全牙丝杆,所述吊筋通过锚固定连接在原建筑钢筋混凝土楼板。The hanging bar is a full-thread screw rod, and the hanging bar is fixedly connected to the reinforced concrete floor of the original building through anchors.

作为上述技术方案的进一步描述:As a further description of the above technical solution:

所述副龙骨上设置有卡接槽,所述扣件固定连接在所述主龙骨上,所述扣件对应卡接在所述卡接槽内。The auxiliary keel is provided with a clamping groove, the fastener is fixedly connected to the main keel, and the fastener is correspondingly clamped in the clamping groove.

作为上述技术方案的进一步描述:As a further description of the above technical solution:

所述接缝材料为接缝王。The seam material is Seam King.

作为上述技术方案的进一步描述:As a further description of the above technical solution:

所述扣件上设置有固定孔,螺钉穿过所述固定孔固定连接在所述主龙骨上。The fastener is provided with a fixing hole, and the screw passes through the fixing hole and is fixedly connected to the main keel.

作为上述技术方案的进一步描述:As a further description of the above technical solution:

所述扣件上设置有扇形调平块,所述扇形调平块对应卡接在所述卡接槽内。The fastener is provided with a fan-shaped leveling block, and the fan-shaped leveling block is correspondingly snapped into the snap-in groove.

综上所述,由于采用了上述技术方案,本发明的有益效果是:In summary, owing to adopting above-mentioned technical scheme, the beneficial effect of the present invention is:

1、本发明中,通过在后场批量化批腻子、打磨、做乳胶漆形成半成品饰面板,现场吊筋及主龙骨安装完成后即可装配式安装副龙骨及石膏板乳胶漆饰面板,主龙骨上设置有扣件,通过将扣件对应卡接在副龙骨的卡接槽内,安装完成后对饰面板接缝处进行勾缝处理,此结构的设计,无需等自然风干,大大缩短工期,且整体结构简单,易安装。1. In the present invention, semi-finished decorative panels are formed by batching putty, grinding, and latex paint in the back field. After the hanging ribs and main keel are installed on site, the auxiliary keel and gypsum board latex paint decorative panel can be assembled in an assembled manner. There are fasteners on the keel, and the fasteners are correspondingly connected to the clamping grooves of the auxiliary keel. After the installation is completed, the joints of the veneer panels are jointed. The design of this structure does not need to wait for natural air drying, which greatly shortens the construction period. , and the overall structure is simple and easy to install.

2、本发明中,通过将扣件上设置扇形调平块,扇形调平块对应卡接在卡接槽,扇形调节块的顶端内侧壁抵接在卡接槽内侧壁上,可以对副龙骨的安装进行调平,从而保证石膏板安装的平整度,提高安装的外观效果。2. In the present invention, by setting the fan-shaped leveling block on the fastener, the fan-shaped leveling block is correspondingly clamped in the clamping groove, and the inner side wall of the top of the fan-shaped adjusting block is abutted against the inner wall of the clamping groove, so that the auxiliary keel can be adjusted. The installation is leveled to ensure the flatness of the gypsum board installation and improve the appearance of the installation.

附图说明Description of drawings

为了更清楚地说明本发明实施例的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,应当理解,以下附图仅示出了本发明的某些实施例,因此不应被看作是对范围的限定,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他相关的附图。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention, and thus It should be regarded as a limitation on the scope, and those skilled in the art can also obtain other related drawings based on these drawings without creative work.

图1为一种装配式吊顶的安装方法的安装结构示意图。Fig. 1 is a schematic diagram of an installation structure of an installation method of a fabricated suspended ceiling.

图例说明:illustration:

1-石膏板;2-副龙骨;3-吊筋;4-主龙骨;5-扣件;6-接缝材料;7-锚栓;8-原建筑钢筋混凝土楼板;9-卡接槽;10-固定孔;11-扇形调平块。1-gypsum board; 2-auxiliary keel; 3-hanging bar; 4-main keel; 5-fastener; 6-joint material; 7-anchor bolt; 8-reinforced concrete floor of the original building; 10-fixing hole; 11-sector leveling block.

具体实施方式detailed description

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.

为使本发明实施例的目的、技术方案和优点更加清楚,下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。通常在此处附图中描述和示出的本发明实施例的组件可以以各种不同的配置来布置和设计。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments It is a part of embodiments of the present invention, but not all embodiments. The components of the embodiments of the invention generally described and illustrated in the figures herein may be arranged and designed in a variety of different configurations.

因此,以下对在附图中提供的本发明的实施例的详细描述并非旨在限制要求保护的本发明的范围,而是仅仅表示本发明的选定实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。Accordingly, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.

应注意到:相似的标号和字母在下面的附图中表示类似项,因此,一旦某一项在一个附图中被定义,则在随后的附图中不需要对其进行进一步定义和解释。It should be noted that like numerals and letters denote similar items in the following figures, therefore, once an item is defined in one figure, it does not require further definition and explanation in subsequent figures.

在本发明实施例的描述中,需要说明的是,术语“上”、“内”等指示的方位或位置关系为基于附图所示的方位或位置关系,或者是该发明产品使用时惯常摆放的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the embodiments of the present invention, it should be noted that the orientation or positional relationship indicated by the terms "upper", "inner" and the like are based on the orientation or positional relationship shown in the drawings, or the usual orientation when the product of the invention is used. The orientation or positional relationship is only for the convenience of describing the present invention and simplifies the description, but does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be construed as limiting the scope of the present invention. limit.

在本发明的描述中,还需要说明的是,除非另有明确的规定和限定,术语“设置”、“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should also be noted that, unless otherwise clearly specified and limited, the terms "installation", "installation", "connection" and "connection" should be understood in a broad sense, for example, it may be a fixed connection, It can also be detachably connected or integrally connected; it can be directly connected or indirectly connected through an intermediary, and it can be internal communication between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.

请参阅图1,本发明提供一种技术方案:一种装配式吊顶的安装方法,包括以下步骤:Please refer to Fig. 1, the present invention provides a technical solution: a method for installing a prefabricated suspended ceiling, comprising the following steps:

S1:后场批量化按排版图加工好石膏板1尺寸,并用副龙骨2用螺丝固定;S1: The size of gypsum board 1 is processed in batches in the back field according to the layout drawing, and the auxiliary keel 2 is fixed with screws;

S2:根据排版图安装吊筋3及主龙骨4;S2: Install hanging bars 3 and main keel 4 according to the layout drawing;

S3:所述副龙骨2与所述石膏板1用螺丝固定完成后,后场操作台批量钉眼处理、腻子刮平、打磨、第一遍乳胶漆形成半成品饰面板;S3: After the auxiliary keel 2 and the gypsum board 1 are fixed with screws, the backfield operation table batches nail holes, putty scraping, grinding, and the first pass of latex paint to form a semi-finished decorative panel;

S4:半成品饰面板与所述主龙骨4通过扣件5固定、调平;S4: The semi-finished decorative panel and the main keel 4 are fixed and leveled through the fastener 5;

S5:安装所有所述半成品饰面板后使用接缝材料6对接缝进行处理,处理后完成后续乳胶漆饰面工作。S5: After installing all the semi-finished decorative panels, use the joint material 6 to process the joints, and complete the subsequent latex paint finishing work after the treatment.

所述吊筋3为全牙丝杆,所述吊筋3通过锚栓7固定连接在原建筑钢筋混凝土楼板8。The hanging bar 3 is a full-thread screw rod, and the hanging bar 3 is fixedly connected to the reinforced concrete floor 8 of the original building through an anchor bolt 7 .

所述副龙骨2上设置有卡接槽9,所述扣件5固定连接在所述主龙骨4上,所述扣件5对应卡接在所述卡接槽9内。The secondary keel 2 is provided with a clamping groove 9 , the fastener 5 is fixedly connected to the main keel 4 , and the fastener 5 is correspondingly clamped in the clamping groove 9 .

所述接缝材料6为接缝王。The seam material 6 is a seam king.

所述扣件5上设置有固定孔10,螺钉穿过所述固定孔10固定连接在所述主龙骨4上。提高扣件与主龙骨之间连接的稳固性。The fastener 5 is provided with a fixing hole 10 through which a screw is fixedly connected to the main keel 4 . Improve the stability of the connection between the fastener and the main keel.

所述扣件5上设置有扇形调平块11,所述扇形调平块11对应卡接在所述卡接槽9内。通过将扣件上设置扇形调平块,扇形调平块对应卡接在卡接槽,扇形调节块的顶端内侧壁抵接在卡接槽内侧壁上,可以对副龙骨的安装进行调平,从而保证石膏板安装的平整度,提高安装的外观效果。The fastener 5 is provided with a sector-shaped leveling block 11 , and the sector-shaped leveling block 11 is correspondingly engaged in the engagement slot 9 . By setting the fan-shaped leveling block on the fastener, the fan-shaped leveling block is correspondingly connected to the snap-in slot, and the top inner wall of the fan-shaped adjustment block is abutted against the inner wall of the snap-in slot, so that the installation of the auxiliary keel can be leveled. Thereby ensuring the flatness of the gypsum board installation and improving the appearance effect of the installation.

工作原理:通过在后场批量化批腻子、打磨、做乳胶漆形成半成品饰面板,现场吊筋及主龙骨安装完成后即可装配式安装副龙骨及石膏板乳胶漆饰面板,主龙骨上设置有扣件,通过将扣件对应卡接在副龙骨的卡接槽内,安装完成后对饰面板接缝处进行勾缝处理,此结构的设计,无需等自然风干,大大缩短工期,且整体结构简单,易安装。Working principle: The semi-finished decorative panels are formed by batching putty, grinding, and latex paint in the back field. After the installation of the hanging bars and the main keel on site, the auxiliary keel and the gypsum board latex paint decorative panel can be assembled. Set on the main keel There are fasteners, and the fasteners are correspondingly clamped in the clamping groove of the auxiliary keel. After the installation is completed, the seams of the veneer are jointed. The design of this structure does not need to wait for natural air drying, which greatly shortens the construction period, and the overall Simple structure and easy installation.

以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, any person familiar with the technical field within the technical scope disclosed in the present invention, according to the technical solution of the present invention Any equivalent replacement or change of the inventive concepts thereof shall fall within the protection scope of the present invention.

Claims (6)

1. A method of installing an assembled ceiling comprising the steps of:
s1: the gypsum boards (1) are processed into sizes according to typesetting drawings in a back field in batch, and are fixed by screws through auxiliary keels (2);
s2: installing the hanging ribs (3) and the main keels (4) according to the typesetting drawing;
s3: after the auxiliary keel (2) and the gypsum board (1) are fixed through screws, a back field operation table is subjected to batch nail-hole processing, putty is flattened, polishing and first-pass emulsion paint to form a semi-finished veneer;
s4: the semi-finished veneer and the main keel (4) are fixed and leveled through a fastener (5);
s5: and (3) after all the semi-finished decorative panels are installed, processing the seams by using a seam material (6), and finishing the subsequent latex paint decorative surface after processing.
2. The installation method of the fabricated suspended ceiling according to claim 1, wherein the hanging bar (3) is a full-tooth screw rod, and the hanging bar (3) is fixedly connected to the original reinforced concrete floor (8) through an anchor bolt (7).
3. The mounting method of the assembled suspended ceiling according to claim 2, wherein the auxiliary keel (2) is provided with a clamping groove (9), the fastener (5) is fixedly connected to the main keel (4), and the fastener (5) is correspondingly clamped in the clamping groove (9).
4. A method of installing a fabricated ceiling according to claim 1, wherein the jointing material (6) is a jointing king.
5. A method for installing a fabricated suspended ceiling according to claim 3, wherein the fastening member (5) is provided with a fixing hole (10), and a screw is fixedly connected to the main keel (4) through the fixing hole (10).
6. The mounting method of the assembled suspended ceiling according to claim 5, wherein the fastener (5) is provided with a fan-shaped leveling block (11), and the fan-shaped leveling block (11) is correspondingly clamped in the clamping groove (9).
CN202210984301.7A 2022-08-16 2022-08-16 A method of installing a prefabricated suspended ceiling Pending CN115573503A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210984301.7A CN115573503A (en) 2022-08-16 2022-08-16 A method of installing a prefabricated suspended ceiling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210984301.7A CN115573503A (en) 2022-08-16 2022-08-16 A method of installing a prefabricated suspended ceiling

Publications (1)

Publication Number Publication Date
CN115573503A true CN115573503A (en) 2023-01-06

Family

ID=84579382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210984301.7A Pending CN115573503A (en) 2022-08-16 2022-08-16 A method of installing a prefabricated suspended ceiling

Country Status (1)

Country Link
CN (1) CN115573503A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019015107A1 (en) * 2017-07-19 2019-01-24 江苏东保装饰集团有限公司 Large area mineral wool board ceiling structure
CN109537793A (en) * 2018-12-06 2019-03-29 河南三阳建材科技有限公司 It is easily installed the ceiling structure and its installation method of leveling
CN109930735A (en) * 2019-04-25 2019-06-25 江苏宅创建筑科技有限公司 A kind of adjustable bulk board furred ceiling of assembled
CN210049468U (en) * 2019-03-25 2020-02-11 丰屋科技(深圳)有限公司 Fast-assembling wall body smallpox binding off component and furred ceiling structure
WO2020143222A1 (en) * 2019-01-10 2020-07-16 深圳瑞和建筑装饰股份有限公司 Fabricated suspended ceiling structure and installation method therefor
CN211172657U (en) * 2019-10-22 2020-08-04 广东乾兴建设工程有限公司 Suspended ceiling connecting structure
CN113431244A (en) * 2021-06-21 2021-09-24 北新集团建材股份有限公司 Adjustable ceiling mounting assembly, ceiling structure and mounting method of ceiling structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019015107A1 (en) * 2017-07-19 2019-01-24 江苏东保装饰集团有限公司 Large area mineral wool board ceiling structure
CN109537793A (en) * 2018-12-06 2019-03-29 河南三阳建材科技有限公司 It is easily installed the ceiling structure and its installation method of leveling
WO2020143222A1 (en) * 2019-01-10 2020-07-16 深圳瑞和建筑装饰股份有限公司 Fabricated suspended ceiling structure and installation method therefor
CN210049468U (en) * 2019-03-25 2020-02-11 丰屋科技(深圳)有限公司 Fast-assembling wall body smallpox binding off component and furred ceiling structure
CN109930735A (en) * 2019-04-25 2019-06-25 江苏宅创建筑科技有限公司 A kind of adjustable bulk board furred ceiling of assembled
CN211172657U (en) * 2019-10-22 2020-08-04 广东乾兴建设工程有限公司 Suspended ceiling connecting structure
CN113431244A (en) * 2021-06-21 2021-09-24 北新集团建材股份有限公司 Adjustable ceiling mounting assembly, ceiling structure and mounting method of ceiling structure

Similar Documents

Publication Publication Date Title
CN105569251B (en) Device for split-level ceiling and installation method
CN107044179B (en) Decorative panel and template integrated heat-preservation decorative composite wall and construction method thereof
CN108316593A (en) Wallboard cladding system and construction method
CN104763123A (en) Unit assembling type installation method of irregular arc-shaped GRG decoration board
CN110219371A (en) Assembled furred ceiling and metope Demountable
CN110424661A (en) Construction method for dry-hanging granite slab
CN108952075A (en) Assembled floor leveling structure and installation method
CN109610766A (en) Wall assembly and installation method
CN115573503A (en) A method of installing a prefabricated suspended ceiling
CN210239046U (en) Air conditioner flat device for floor frame
US20100192494A1 (en) Elongate abutment member of plaster
CN109372176B (en) Suspended ceiling and suspended ceiling mounting method
CN111962804A (en) Method for paving floor tiles and application thereof
CN216196255U (en) Assembled decorative wallboard structure
CN204663001U (en) Regulating structure for wallboard
CN220014155U (en) Unit curtain wall large ribbon aluminum plastic panel system
CN206070818U (en) A kind of cladding connector of curtain wall
KR101302552B1 (en) External panel fixing bracket
CN112443094A (en) Wall internal corner ceramic tile installation structure and installation method
CN219100598U (en) Socket-joint opposite-buckling type assembled overhead ground system
CN107119841B (en) Top surface veneer installation joint structure
CN205530878U (en) Device for connecting be used for stone cladding process
CN214498157U (en) Wall body reentrant corner ceramic tile mounting structure
WO2020180276A1 (en) Facade cladding system
CN111335536A (en) A kind of prefabricated shape ceiling connector and installation method

Legal Events