CN115559340A - Steel-concrete combined assembly type main transformer foundation and construction method thereof - Google Patents
Steel-concrete combined assembly type main transformer foundation and construction method thereof Download PDFInfo
- Publication number
- CN115559340A CN115559340A CN202211332513.3A CN202211332513A CN115559340A CN 115559340 A CN115559340 A CN 115559340A CN 202211332513 A CN202211332513 A CN 202211332513A CN 115559340 A CN115559340 A CN 115559340A
- Authority
- CN
- China
- Prior art keywords
- raft
- steel
- concrete
- combined
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/01—Flat foundations
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
- E04B1/4157—Longitudinally-externally threaded elements extending from the concrete or masonry, e.g. anchoring bolt with embedded head
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Foundations (AREA)
Abstract
本发明涉及一种钢混组合装配式主变压器基础及其施工方法,包括混凝土垫层、组合筏板和组合支墩,复数个组合筏板呈矩阵分布在混凝土垫层上;组合支墩的数量为组合筏板数量的一半,每个组合支墩分别与两个相邻的组合筏板相对应,组合支墩位于组合筏板的上方,组合筏板相互之间、组合筏板与组合支墩之间均通过螺栓连接形成一个整体。组合筏板采用分体式工厂预制,体积较小,减小运输成本、提升运输的效率;同时模块化安装,灵活适用于不同主变设备的需要,施工安装灵活,解决了浇筑引起的现场湿作业工作量大的问题,一定程度上缓解了施工所带来的环境污染问题,减少施工工序,提升了现场作业的效率和施工质量,大大减少人工成本。
The invention relates to a steel-concrete combined assembly type main transformer foundation and a construction method thereof, comprising a concrete cushion, a combined raft and a combined buttress, and a plurality of combined rafts are distributed on the concrete cushion in a matrix; the number of combined buttresses It is half of the number of combined rafts. Each combined support pier corresponds to two adjacent combined rafts. The combined support pier is located above the combined raft. All are connected by bolts to form a whole. The combined raft is prefabricated in a split factory, which is small in size, reduces transportation costs, and improves transportation efficiency; at the same time, modular installation is flexible to meet the needs of different main transformer equipment, flexible construction and installation, and solves the on-site wet work caused by pouring The problem of heavy workload alleviates the problem of environmental pollution caused by construction to a certain extent, reduces construction procedures, improves the efficiency and construction quality of on-site operations, and greatly reduces labor costs.
Description
技术领域:Technical field:
本发明涉及一种钢混组合装配式主变压器基础及其施工方法。The invention relates to a steel-concrete combined assembly type main transformer foundation and a construction method thereof.
背景技术:Background technique:
装配式技术具有施工周期短、减少环境污染、节约人力成本等优点。随着新型电力系统的加快构建,模块化装配式技术目前在电力行业已经得到了多方面的应用,目前应用领域主要集中在小型预制构件基础、电缆沟等,主变压器等大型设备的基础仍然采用传统混凝土浇筑形式。Prefabricated technology has the advantages of short construction period, reduced environmental pollution, and labor cost savings. With the accelerated construction of new power systems, modular assembly technology has been applied in many aspects in the power industry. At present, the application fields are mainly concentrated in small prefabricated component foundations, cable trenches, etc., and the foundations of large equipment such as main transformers are still used. Traditional form of concrete pouring.
主变压器基础传统的施工方式存在诸多缺点,例如存在大量的湿作业,造成一定程度上的环境破坏和资源浪费,工程质量控制的难度较高;同时混凝土的养护时间长,特别是在天气寒冷、潮湿多雨的地区,冬歇期、雨季的停工时间长,将会进一步延长变电站的建设周期和增加人工成本。基础传统的混凝土浇筑施工在结束后基础支墩的尺寸无法调整,但是随着用电负荷的不断增加,更换主变增容的情况越来越多,导致前期的设计方案与后期调整的方案(实际到货主变压器设备)不符,往往需要将原有的基础拆除重建,增加了工程的投资和资源的浪费。The traditional construction method of the main transformer foundation has many disadvantages. For example, there are a lot of wet operations, which cause a certain degree of environmental damage and waste of resources, and the difficulty of project quality control is relatively high. At the same time, the curing time of concrete is long, especially in cold weather. In humid and rainy areas, the winter break and the rainy season have a long shutdown time, which will further prolong the construction period of the substation and increase labor costs. The size of the foundation pier cannot be adjusted after the traditional concrete pouring construction of the foundation is completed. However, as the power load continues to increase, there are more and more cases of replacing the main transformer to increase the capacity, which leads to the early design plan and the later adjustment plan ( The actual arrival of the main transformer equipment) does not match, and the original foundation often needs to be demolished and rebuilt, which increases the project investment and waste of resources.
目前装配式主变压器基础也已经有了一定的研究成果,现有相关技术方案具备以下特点:例如中国专利CN201920125732.1提出了一种半标准配送可调式通用主变基础,该构造利用整板+预制成品梁或支墩的方案,其存在着由于整板的体积、重量较大,运输的成本较高的问题。中国专利又如CN202021215093.7提出了一种提高整体性易装配的高电压榫卯结构主变基础,筏板由三块构件形成的咬合面利用粘合剂粘结固定,同时榫头与构件在工厂中已经预制连接完成,存在着筏板钢筋受力不连续、占用运输空间较大等问题。At present, the prefabricated main transformer foundation has also had certain research results, and the existing related technical solutions have the following characteristics: For example, Chinese patent CN201920125732.1 proposes a semi-standard distribution adjustable general-purpose main transformer foundation, which uses the whole board + The solution of the prefabricated beam or pier has the problem of high transportation cost due to the large volume and weight of the whole board. Another Chinese patent, CN202021215093.7, proposes a high-voltage mortise and tenon structure main transformer foundation that improves integrity and is easy to assemble. The prefabricated connection has been completed, but there are problems such as discontinuous stress on the reinforcement of the raft and large transportation space.
发明内容:Invention content:
本发明针对上述现有技术存在的问题做出改进,即本发明所要解决的技术问题是提供一种钢混组合装配式主变压器基础及其施工方法,设计合理,提高运输和施工的便利性。The present invention makes improvements to the problems existing in the above-mentioned prior art, that is, the technical problem to be solved by the present invention is to provide a steel-concrete assembled main transformer foundation and its construction method, which has a reasonable design and improves the convenience of transportation and construction.
为了实现上述目的,本发明采用的技术方案是:一种钢混组合装配式主变压器基础,包括混凝土垫层,还包括工厂预制的组合筏板和组合支墩,所述组合筏板为复数个,复数个组合筏板呈矩阵分布在混凝土垫层上;所述组合支墩的数量为组合筏板数量的一半,每个组合支墩分别与两个相邻的组合筏板相对应,所述组合支墩位于组合筏板的上方,复数个组合筏板相互之间、组合筏板与组合支墩之间均通过螺栓连接形成一个整体。In order to achieve the above object, the technical solution adopted by the present invention is: a steel-concrete composite assembly type main transformer foundation, including a concrete cushion, and also includes a factory prefabricated composite raft and a composite pier, the composite raft is a plurality of , a plurality of combined rafts are distributed on the concrete cushion in a matrix; the number of the combined buttresses is half of the number of combined rafts, and each combined buttress corresponds to two adjacent combined rafts, the The composite buttress is located above the composite raft, and the plurality of composite rafts and the composite raft and the composite pier are all connected by bolts to form a whole.
进一步的,所述组合筏板包括矩形状的混凝土筏板,所述混凝土筏板的周侧设置有一对相垂直的筏板钢连接件,一对筏板钢连接件与混凝土筏板的其中一对直角边相平行;相邻组合筏板的筏板钢连接件之间通过第一高强度螺栓相连接。Further, the composite raft includes a rectangular concrete raft, a pair of vertical raft steel connectors are arranged on the peripheral side of the concrete raft, and one of the pair of raft steel connectors and the concrete raft The right-angle sides are parallel; the raft steel connectors of adjacent composite rafts are connected by first high-strength bolts.
进一步的,所述组合支墩包括矩形状的混凝土支墩,所述混凝土支墩的底部设有一对上支墩钢连接件;所述混凝土筏板的顶部设置有一个下支墩钢连接件,位置相对应的上支墩钢连接件与下支墩钢连接件之间通过第二高强度螺栓相连接。Further, the combined pier includes a rectangular concrete pier, a pair of steel connectors for the upper pier are provided at the bottom of the concrete pier; a steel connector for the lower pier is provided at the top of the concrete raft, The corresponding upper buttress steel connectors and lower buttress steel connectors are connected by second high-strength bolts.
进一步的,所述筏板钢连接件面向混凝土筏板的一侧面设置有多个筏板连接栓钉,筏板钢连接件与混凝土筏板通过多个筏板连接栓钉抗剪连接,筏板钢连接件远离混凝土筏板的一端设有多个沿其长度方向并排分布并用于与第一高强度螺栓相配合的筏板螺栓孔。Further, the side of the raft steel connector facing the concrete raft is provided with a plurality of raft connection pegs, the raft steel connector and the concrete raft are connected in shear through a plurality of raft connection pegs, and the raft The end of the steel connector away from the concrete raft is provided with a plurality of raft bolt holes distributed side by side along its length direction and used to cooperate with the first high-strength bolts.
进一步的,所述筏板钢连接件靠近混凝土筏板的一端设有若干个沿其长度方向并排分布的钢筋连接孔,所述钢筋连接孔远离混凝土筏板的一端固定有预埋钢筋垫板;所述混凝土筏板中预埋有与若干个钢筋连接孔的位置相对应的若干根筏板预埋钢筋,所述筏板预埋钢筋依次穿过钢筋连接孔和预埋钢筋垫板,并通过筏板预埋钢筋螺母固定。Further, the end of the raft steel connector close to the concrete raft is provided with several reinforcement connection holes distributed side by side along its length direction, and the end of the reinforcement connection holes away from the concrete raft is fixed with a pre-embedded reinforcement backing plate; The concrete raft is pre-embedded with several raft pre-embedded steel bars corresponding to the positions of several steel bar connection holes, and the raft pre-embedded steel bars pass through the steel bar connection holes and the pre-embedded steel backing plate in sequence, and pass through the The raft is fixed with pre-embedded steel bars and nuts.
进一步的,所述上支墩钢连接件水平设置,上支墩钢连接件的顶部设置有多个上支墩连接栓钉,上支墩钢连接件与混凝土支墩通过多个上支墩连接栓钉抗剪连接,上支墩钢连接件的底部设有若干个沿其长度方向并排分布的上支墩螺栓孔;所述下支墩钢连接件水平设置,下支墩钢连接件的底部设置有多个下支墩连接栓钉,下支墩钢连接件与混凝土筏板通过多个下支墩连接栓钉抗剪连接,下支墩钢连接件的顶部设有若干个沿其长度方向并排分布的下支墩螺栓孔,所述下支墩螺栓孔与上支墩螺栓孔的位置相对应,并以利于第二高强度螺栓贯穿。Further, the steel connector of the upper pier is arranged horizontally, the top of the steel connector of the upper pier is provided with a plurality of connecting studs for the upper pier, and the steel connector of the upper pier is connected to the concrete buttress through a plurality of upper buttresses Stud shear connection, the bottom of the upper pier steel connector is provided with a number of upper buttress bolt holes distributed side by side along its length; the lower buttress steel connector is arranged horizontally, and the bottom of the lower buttress steel connector There are multiple connecting studs for the lower pier. The steel connecting piece of the lower pier is connected to the concrete raft through a plurality of connecting studs for the lower pier. The top of the steel connecting piece for the lower pier is provided with several Bolt holes of the lower pier are distributed side by side, the bolt holes of the lower pier correspond to the bolt holes of the upper pier, and facilitate the penetration of the second high-strength bolt.
进一步的,所述混凝土支墩的顶部设有一对水平设置的支墩预埋钢板,所述支墩预埋钢板通过钢筋锚固于混凝土支墩上,支墩预埋钢板的中部设有浇筑圆孔。Further, the top of the concrete pier is provided with a pair of horizontally arranged pre-embedded steel plates for the pier, and the pre-embedded steel plates for the pier are anchored on the concrete pier through steel bars, and the middle part of the pre-embedded steel plate for the pier is provided with a round hole for pouring .
进一步的,所述混凝土支墩的内部配置有纵向的受力钢筋和横向的分布钢筋。Further, the inside of the concrete pier is equipped with longitudinal stress reinforcement and transverse distribution reinforcement.
本发明采用的另外一种技术方案是:一种钢混组合装配式主变压器基础的施工方法,包含如下步骤:Another technical solution adopted by the present invention is: a construction method for the steel-concrete assembled main transformer foundation, including the following steps:
步骤S1:完成变电站钢混组合装配式主变压器基础施工前期的工作,包括场地平整、测量放线与土方开挖;Step S1: Complete the pre-construction work of the steel-concrete composite assembled main transformer foundation of the substation, including site leveling, surveying and setting out, and earthwork excavation;
步骤S2:根据设计的要求确定组合筏板和组合支墩的数量;Step S2: Determine the number of composite rafts and composite piers according to design requirements;
步骤S3:在工厂内完成各个组合筏板和组合支墩的加工;Step S3: complete the processing of each composite raft and composite pier in the factory;
步骤S4:混凝土垫层模板的安装,完成混凝土垫层的混凝土浇筑并养护;Step S4: Installing the formwork of the concrete cushion, completing the concrete pouring and maintenance of the concrete cushion;
步骤S5:待工厂预制好的组合筏板和组合支墩运至施工现场后,根据设计要求定位复数个组合筏板的位置,随后利用第一高强度螺栓连接将各个组合筏板相互连接,使得各个组合筏板形成一个整体;Step S5: After the prefabricated composite raft and composite pier are transported to the construction site, locate the positions of multiple composite rafts according to the design requirements, and then use the first high-strength bolts to connect each composite raft to each other, so that Each combined raft forms a whole;
步骤S6:将组合支墩与步骤S5中已经相互连接形成整体的组合筏板利用第二高强度螺栓相互连接,完成施工。Step S6: Connect the composite pier and the composite raft that has been connected to each other in step S5 with the second high-strength bolts to complete the construction.
与现有技术相比,本发明具有以下效果:本发明结构设计合理,组合筏板采用分体式工厂预制,每一个组合筏板的体积较小,减小运输成本的同时提升了运输的效率;同时实现了模块化安装,灵活适用于不同主变设备的需要,施工安装灵活,解决了现有主变基础施工现场基础筏板和支墩整体浇筑引起的现场湿作业工作量大的问题,一定程度上缓解了施工所带来的环境污染问题,减少施工工序,提升了现场作业的效率和施工质量,大大减少人工成本。Compared with the prior art, the present invention has the following effects: the structural design of the present invention is reasonable, the combined raft is prefabricated in a split factory, and the volume of each combined raft is small, which reduces the transportation cost and improves the transportation efficiency; At the same time, modular installation is realized, which is flexibly applicable to the needs of different main transformer equipment, flexible construction and installation, and solves the problem of heavy on-site wet work workload caused by the integral pouring of foundation rafts and buttresses at the existing main transformer foundation construction site. To a certain extent, the environmental pollution problems caused by construction are alleviated, the construction process is reduced, the efficiency and construction quality of on-site operations are improved, and labor costs are greatly reduced.
附图说明:Description of drawings:
图1是本发明实施例的立体构造示意图;Fig. 1 is the three-dimensional structure schematic diagram of the embodiment of the present invention;
图2是本发明实施例的俯视构造示意图;Fig. 2 is a top view structural schematic view of an embodiment of the present invention;
图3是本发明实施例的主视构造示意图;Fig. 3 is a front view structural schematic diagram of an embodiment of the present invention;
图4是本发明实施例的侧视构造示意图;Fig. 4 is a side view structural schematic diagram of an embodiment of the present invention;
图5是本发明实施例中组合筏板的立体构造示意图;Fig. 5 is a schematic diagram of the three-dimensional structure of the combined raft in the embodiment of the present invention;
图6是本发明实施例中组合支墩的立体构造示意图;Fig. 6 is a schematic diagram of the three-dimensional structure of the combined pier in the embodiment of the present invention;
图7是本发明实施例中筏板钢连接件的立体构造示意图;Fig. 7 is a schematic diagram of the three-dimensional structure of the raft steel connector in the embodiment of the present invention;
图8是本发明实施例中下支墩钢连接件的立体构造示意图;Fig. 8 is a schematic diagram of the three-dimensional structure of the steel connector of the lower pier in the embodiment of the present invention;
图9是本发明实施例中上支墩钢连接件的立体构造示意图。Fig. 9 is a schematic perspective view of the three-dimensional structure of the upper buttress steel connector in the embodiment of the present invention.
图中:In the picture:
1-混凝土垫层;2-组合筏板;201-混凝土筏板;202-下支墩钢连接件;2021-下支墩钢连接件主体;2022-下支墩螺栓孔;2023-下支墩连接栓钉;203-筏板钢连接件;2031-筏板钢连接件主体;2032-筏板连接栓钉;2033-钢筋连接孔;2034-筏板螺栓孔;204-预埋钢筋垫板;205-筏板预埋钢筋螺母;206-筏板预埋钢筋;3-组合支墩;301-混凝土支墩;302-上支墩钢连接件;3021-上支墩钢连接件主体;3022-上支墩螺栓孔;3023-上支墩连接栓钉;303-支墩预埋钢板;304-浇筑圆孔;4-第一高强度螺栓;5-第二高强度螺栓。1-concrete cushion; 2-combined raft; 201-concrete raft; 202-steel connector for the lower pier; 2021-main body of the steel connector for the lower pier; 2022-bolt holes for the lower pier; Connecting studs; 203-raft steel connectors; 2031-main body of raft steel connectors; 2032-raft connecting studs; 2033-reinforcement connection holes; 2034-raft bolt holes; 204-embedded steel backing plate; 205- raft pre-embedded reinforcement nut; 206- raft pre-embedded reinforcement; 3-combined pier; 301- concrete pier; 302- upper pier steel connector; 3021- upper pier steel connector body; 3022- Bolt holes of the upper pier; 3023-connection studs of the upper pier; 303-embedded steel plate of the pier; 304-round holes for pouring; 4-first high-strength bolts; 5-second high-strength bolts.
具体实施方式:detailed description:
下面结合附图和具体实施方式对本发明做进一步详细的说明。The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.
在本发明的描述中,需要理解的是,术语“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In describing the present invention, it should be understood that the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", The orientations or positional relationships indicated by "horizontal", "top", "bottom", "inner", "outer", etc. are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention, rather than indicating or It should not be construed as limiting the invention by implying that a referenced device or element must have a particular orientation, be constructed, and operate in a particular orientation.
如图1~9所示,本发明一种钢混组合装配式主变压器基础,实现的目的是尽量减少现场的湿作业,缩短工程工期,减少施工现场的环境污染和噪声影响,提升工程质量,并解决装配式主变基础构件体积较大、运输困难、现场安装复杂等问题,具体结构包括混凝土垫层1、工厂预制的组合筏板2和组合支墩3,所述组合筏板2为复数个,复数个组合筏板2呈矩阵分布在混凝土垫层1上;所述组合支墩3的数量为组合筏板数量的一半,每个组合支墩3分别与沿纵向两个相邻的组合筏板2相对应,即:一个组合支墩3与两个组合筏板2相连接,每个组合筏板只与一个组合支墩连接;所述组合支墩3位于组合筏板2的上方,复数个组合筏板2相互之间、组合筏板2与组合支墩3之间均通过高强度螺栓连接形成一个整体。As shown in Figures 1 to 9, the steel-concrete combined assembly type main transformer foundation of the present invention aims to reduce the wet work on site as much as possible, shorten the construction period of the project, reduce the environmental pollution and noise impact on the construction site, and improve the quality of the project. It also solves the problems of large volume of prefabricated main transformer foundation components, difficult transportation, and complicated on-site installation. The specific structure includes
本实施例中,结合图5、图7-8进行说明,所述组合筏板2包括矩形状的混凝土筏板201,所述混凝土筏板201的周侧设置有一对相垂直的筏板钢连接件203,一对筏板钢连接件203与混凝土筏板201的其中一对直角边相平行;相邻组合筏板2的筏板钢连接件203之间通过第一高强度螺栓4相连接。在施工时,一对筏板钢连接件位于混凝土筏板的内侧,每个组合筏板的一对筏板钢连接件分别与其相邻的另外两个组合筏板相连接。In this embodiment, described in conjunction with Fig. 5 and Fig. 7-8, the
本实施例中,如图7所示,所述筏板钢连接件203包括截面呈类工字型的筏板钢连接件主体2031,筏板钢连接件主体2031面向混凝土筏板201的一侧面设置有多个筏板连接栓钉2032,筏板钢连接件主体2031与混凝土筏板201通过多个筏板连接栓钉2032抗剪连接,筏板钢连接件主体2031远离混凝土筏板201的一端设有多个沿其长度方向并排分布并用于与第一高强度螺栓4相配合的筏板螺栓孔2034。在施工时,复数个组合筏板呈矩阵分布,相邻的组合筏板依靠筏板钢连接件对接,相邻两个组合筏板的筏板钢连接件依靠第一高强度螺栓连接,以此实现相邻两个组合筏板的连接固定。In this embodiment, as shown in FIG. 7 , the
本实施例中,如图5所示,所述筏板钢连接件主体2031靠近混凝土筏板201的一端设有若干个沿其长度方向并排分布的钢筋连接孔2033,所述钢筋连接孔2033远离混凝土筏板201的一端固定有预埋钢筋垫板204;所述混凝土筏板201中预埋有与若干个钢筋连接孔2033的位置相对应的若干根筏板预埋钢筋206,所述筏板预埋钢筋206依次穿过钢筋连接孔2033和预埋钢筋垫板204,并通过筏板预埋钢筋螺母205固定。In this embodiment, as shown in Figure 5, the end of the raft steel connector
本实施例中,如图6所示,所述组合支墩3包括矩形状的混凝土支墩301,所述混凝土支墩301的底部设有一对上支墩钢连接件302;所述混凝土筏板301的顶部设置有一个下支墩钢连接件202,即:一个组合支墩的两个上支墩钢连接件分别与两个组合筏板顶部的下支墩钢连接件相对应,位置相对应的上支墩钢连接件302与下支墩钢连接件202之间通过第二高强度螺栓5相连接,以此实现组合支墩与组合筏板连接形成整体。In this embodiment, as shown in Figure 6, the combined
本实施例中,所述上支墩钢连接件302水平设置,上支墩钢连接件302包括上支墩钢连接件主体3021,上支墩钢连接件主体3021的顶部设置有多个上支墩连接栓钉3023,上支墩钢连接件主体3021与混凝土支墩301通过多个上支墩连接栓钉3023抗剪连接,上支墩钢连接件302的底部设有若干个沿其长度方向并排分布的上支墩螺栓孔3022,如图9所示。所述下支墩钢连接件202水平设置,下支墩钢连接件202包括下支墩钢连接件主体2021,下支墩钢连接件主体2021的底部设置有多个下支墩连接栓钉2023,下支墩钢连接件主体2021与混凝土筏板201通过多个下支墩连接栓钉2023抗剪连接,下支墩钢连接件主体2021的顶部设有若干个沿其长度方向并排分布的下支墩螺栓孔2022,所述下支墩螺栓孔2022与上支墩螺栓孔3022的位置相对应,并以利于第二高强度5螺栓贯穿,如图8所示。在施工时,一个组合支墩的两个上支墩钢连接件分别与两个组合筏板顶部的下支墩钢连接件相对应,上支墩钢连接件与下支墩钢连接件上下对接,下支墩螺栓孔与上支墩螺栓孔位置相对应并用于与第二高强度螺栓相配合,实现组合支墩与组合筏板连接固定。In this embodiment, the upper buttress
本实施例中,所述混凝土支墩301的顶部设有一对水平设置的支墩预埋钢板303,所述支墩预埋钢板303通过钢筋锚固于混凝土支墩301上,支墩预埋钢板303的中部设有浇筑圆孔304。In this embodiment, the top of the
本实施例中,所述混凝土支墩301的内部配置有纵向的受力钢筋和横向的分布钢筋。In this embodiment, the interior of the
本实施例中,所述筏板钢连接件主体、上支墩钢连接件主体以及下支墩钢连接件主体均包括一对相平行的侧板,一对侧板之间通过一对连接板相连接,所述连接板与侧板垂直分布,一对侧板与一对连接板组合形成的截面形状呈类工字型,一对侧板作为翼板,一对连接板之间围成的空腔作为腹板。In this embodiment, the main body of the raft steel connector, the main body of the steel connector for the upper pier, and the main body of the steel connector for the lower pier all include a pair of parallel side plates, and a pair of connecting plates pass between the pair of side plates. The connecting plates are vertically distributed with the side plates, the cross-sectional shape formed by the combination of a pair of side plates and a pair of connecting plates is I-shaped, a pair of side plates are used as wing plates, and a pair of connecting plates is surrounded by The cavity serves as the web.
实施例:以组合筏板为4个、组合支墩为2为例,4个组合筏板呈矩阵分布在混凝土垫层1上,2个组合支墩位于四个组合筏板的正上方,每个组合支墩位于沿纵向相邻的两个组合筏板上方,4个组合筏板相互之间依靠筏板钢连接件相对接,再利用第一高强度螺栓将相邻组合筏板的筏板钢连接件连接固定;而组合支墩与其位置相对应的两个组合筏板之间,利用上、下支墩钢连接件相对接,再利用第二高强度螺栓将上、下支墩钢连接件连接固定。应说明的是,为了确保每个组合支墩在纵向上与相邻的组合筏板相对应,当组合筏板进行矩阵分布时,其行数为复数,例如组合筏板为6个时,组合支墩为三根,6个组合筏板呈2行3列分布;若是组合筏板为8个,则为4行2列;若是组合筏板为10个,则为2行5列等等。Embodiment: Taking 4 combined rafts and 2 combined buttresses as an example, the 4 combined rafts are distributed in a matrix on the
本实施例中,施工时,包含如下步骤:In this embodiment, during construction, the following steps are included:
步骤S1:完成变电站钢混组合装配式主变压器基础施工前期的工作,包括场地平整、测量放线与土方开挖等;Step S1: Complete the pre-construction work of the steel-concrete composite assembled main transformer foundation of the substation, including site leveling, measurement setting-out and earthwork excavation, etc.;
步骤S2:根据设计的要求确定组合筏板2和组合支墩3的数量;Step S2: Determine the number of combined
步骤S3:根据需求,在工厂内完成各个组合筏板2和组合支墩3的加工;Step S3: According to the requirements, complete the processing of each combined
步骤S4:混凝土垫层模板的安装,完成混凝土垫层1的混凝土浇筑并养护;Step S4: Installing the formwork of the concrete cushion, completing the concrete pouring and curing of the
步骤S5:待工厂预制好的组合筏板2和组合支墩3运至施工现场后,根据设计要求定位复数个组合筏板2的位置,随后利用第一高强度螺栓4连接将各个组合筏板2相互连接,使得各个组合筏板形成一个整体;Step S5: After the prefabricated
步骤S6:将组合支墩3与步骤S5中已经相互连接形成整体的组合筏板2利用第二高强度螺栓5相互连接,完成施工。Step S6: Connect the
应说明的是,在施工过程中,上述步骤S1、S2以及S3可同步开展。It should be noted that, during the construction process, the above steps S1, S2 and S3 can be carried out simultaneously.
本发明的优点在于:(1)构造简单、施工安装灵活,实现了模块化安装,灵活适用于不同主变设备的需要,解决了现有主变基础施工现场基础筏板和支墩整体浇筑引起的现场湿作业工作量大的问题,一定程度上缓解了施工所带来的环境污染问题,减少施工工序,提升了现场作业的效率和施工质量,大大减少人工成本。(2)组合筏板分成若干个,每一个组合筏板的体积较小,减小运输成本的同时提升了运输的效率;(3)解决了传统现浇混凝土基础使用寿命一般的问题,本发明均为工厂预制件,使用高强材料,材料密实度高,延长了使用寿命。The advantages of the present invention are: (1) simple structure, flexible construction and installation, realizing modular installation, flexibly applicable to the needs of different main transformer equipment, and solving the problems caused by the integral pouring of foundation rafts and buttresses at the existing main transformer foundation construction site; The problem of heavy on-site wet work workload has alleviated the environmental pollution problems caused by construction to a certain extent, reduced construction procedures, improved the efficiency and construction quality of on-site operations, and greatly reduced labor costs. (2) The combined raft is divided into several, and each combined raft has a small volume, which reduces the transportation cost and improves the transportation efficiency; (3) solves the general problem of the service life of the traditional cast-in-place concrete foundation, and the present invention All are factory prefabricated parts, using high-strength materials with high density, which prolongs the service life.
本发明如果公开或涉及了互相固定连接的零部件或结构件,那么,除另有声明外,固定连接可以理解为:能够拆卸地固定连接( 例如使用螺栓或螺钉连接),也可以理解为:不可拆卸的固定连接(例如铆接、焊接),当然,互相固定连接也可以为一体式结构( 例如使用铸造工艺一体成形制造出来) 所取代(明显无法采用一体成形工艺除外)。If the present invention discloses or relates to parts or structural parts that are fixedly connected to each other, then, unless otherwise stated, the fixed connection can be understood as: a detachable fixed connection (for example, using bolts or screws), or it can also be understood as: Non-detachable fixed connection (such as riveting, welding), of course, the mutual fixed connection can also be replaced by an integrated structure (such as manufactured by integral forming by casting process) (except that the integral forming process cannot be used obviously).
另外,上述本发明公开的任一技术方案中所应用的用于表示位置关系或形状的术语除另有声明外其含义包括与其近似、类似或接近的状态或形状。In addition, unless otherwise stated, the terms used in any of the technical solutions disclosed in the present invention to indicate positional relationships or shapes include states or shapes that are similar, similar or close to them.
本发明提供的任一部件既可以是由多个单独的组成部分组装而成,也可以为一体成形工艺制造出来的单独部件。Any component provided by the present invention can be assembled from multiple individual components, or can be a single component manufactured by integral forming process.
最后应当说明的是:以上实施例仅用以说明本发明的技术方案而非对其限制;尽管参照较佳实施例对本发明进行了详细的说明,所属领域的普通技术人员应当理解:依然可以对本发明的具体实施方式进行修改或者对部分技术特征进行等同替换;而不脱离本发明技术方案的精神,其均应涵盖在本发明请求保护的技术方案范围当中。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them; although the present invention has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that: the present invention can still be The specific implementation mode of the invention is modified or some technical features are equivalently replaced; without departing from the spirit of the technical solution of the present invention, all of them shall be included in the scope of the technical solution claimed in the present invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211332513.3A CN115559340A (en) | 2022-10-28 | 2022-10-28 | Steel-concrete combined assembly type main transformer foundation and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211332513.3A CN115559340A (en) | 2022-10-28 | 2022-10-28 | Steel-concrete combined assembly type main transformer foundation and construction method thereof |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115559340A true CN115559340A (en) | 2023-01-03 |
Family
ID=84769006
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211332513.3A Pending CN115559340A (en) | 2022-10-28 | 2022-10-28 | Steel-concrete combined assembly type main transformer foundation and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115559340A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116005706A (en) * | 2023-02-23 | 2023-04-25 | 河北汇智电力工程设计有限公司 | Flat plate assembly type raft foundation and construction method |
| CN116607558A (en) * | 2023-05-29 | 2023-08-18 | 国网福建省电力有限公司经济技术研究院 | Prefabricated assembled foundation of main transformer equipment of transformer substation and construction method of prefabricated assembled foundation |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002167775A (en) * | 2000-11-30 | 2002-06-11 | Hitoshi Mori | Pc floor post footing and execution method therefor |
| CN205475312U (en) * | 2016-02-05 | 2016-08-17 | 国网山东省电力公司潍坊供电公司 | Prefabricated assembled owner becomes base apparatus |
| CN108755743A (en) * | 2018-07-10 | 2018-11-06 | 湖北别阁钢结构科技开发有限公司 | A kind of equipment, assembled beam foundation and its construction method |
| CN110172989A (en) * | 2019-06-28 | 2019-08-27 | 国网山西长治电力勘测设计有限公司 | High voltage joinery and its construction assembled main transformer foundation |
| CN213926343U (en) * | 2020-08-28 | 2021-08-10 | 金华华硕通信工程有限公司 | Raft foundation of communication tower |
-
2022
- 2022-10-28 CN CN202211332513.3A patent/CN115559340A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002167775A (en) * | 2000-11-30 | 2002-06-11 | Hitoshi Mori | Pc floor post footing and execution method therefor |
| CN205475312U (en) * | 2016-02-05 | 2016-08-17 | 国网山东省电力公司潍坊供电公司 | Prefabricated assembled owner becomes base apparatus |
| CN108755743A (en) * | 2018-07-10 | 2018-11-06 | 湖北别阁钢结构科技开发有限公司 | A kind of equipment, assembled beam foundation and its construction method |
| CN110172989A (en) * | 2019-06-28 | 2019-08-27 | 国网山西长治电力勘测设计有限公司 | High voltage joinery and its construction assembled main transformer foundation |
| CN213926343U (en) * | 2020-08-28 | 2021-08-10 | 金华华硕通信工程有限公司 | Raft foundation of communication tower |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116005706A (en) * | 2023-02-23 | 2023-04-25 | 河北汇智电力工程设计有限公司 | Flat plate assembly type raft foundation and construction method |
| CN116005706B (en) * | 2023-02-23 | 2025-07-01 | 河北汇智电力工程设计有限公司 | Flat plate assembled raft foundation and construction method |
| CN116607558A (en) * | 2023-05-29 | 2023-08-18 | 国网福建省电力有限公司经济技术研究院 | Prefabricated assembled foundation of main transformer equipment of transformer substation and construction method of prefabricated assembled foundation |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN209114309U (en) | Steel reinforced concrete combined bridge can be achieved and run through reinforcing bar quickly pinpoint PBL shear connector | |
| CN115559340A (en) | Steel-concrete combined assembly type main transformer foundation and construction method thereof | |
| CN218843147U (en) | High-strength bolted substation modular main transformer foundation | |
| CN107605038A (en) | A kind of assembled steel and concrete frame space modular structure and system and construction method | |
| CN110747996A (en) | A corrugated steel plate composite frame structure system and its application | |
| CN209722687U (en) | Anchorage structure of concrete tower of cable-stayed bridge | |
| CN111749364B (en) | A C-steel-based assembled composite wall and construction method thereof | |
| CN110725402A (en) | Multi-cavity combined shear wall and H-shaped steel beam assembled node and construction method thereof | |
| CN111794421B (en) | A kind of precast concrete floor assembling method | |
| CN210712907U (en) | Column base connecting and fixing structure | |
| CN203905214U (en) | Assembled type blend coupled wall system | |
| CN107938498B (en) | Assembled steel pier column and assembled gate-type steel pier | |
| CN211872631U (en) | Connecting device for bridge panels | |
| CN214168727U (en) | Steel beam and concrete pier column consolidation structure | |
| CN116876661B (en) | Modular single-layer lattice shell timber structure system | |
| CN211872641U (en) | Supporting device for bridge panel | |
| CN117605171A (en) | A kind of prestressed assembled concrete beam-column connection node and its construction method | |
| CN206625348U (en) | A kind of assembled integral bean column node | |
| CN212582723U (en) | Equipment base beam | |
| CN117947912A (en) | Steel bar jacking type connecting member, application structure and construction method thereof | |
| CN211646957U (en) | Assembled house ground reinforcing plate structure | |
| CN209040286U (en) | Steel concrete assembled connected node | |
| CN222161566U (en) | Assembled mixed frame-eccentric supporting structure | |
| CN213741566U (en) | Prefabricated reinforced concrete frame for fixing infill steel plates | |
| CN214574943U (en) | Assembled modularization lightweight steel construction wall body |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20230103 |
