CN115559190A - Main beam structure of double-layer four-line railway steel truss girder cable-stayed bridge - Google Patents
Main beam structure of double-layer four-line railway steel truss girder cable-stayed bridge Download PDFInfo
- Publication number
- CN115559190A CN115559190A CN202211154990.5A CN202211154990A CN115559190A CN 115559190 A CN115559190 A CN 115559190A CN 202211154990 A CN202211154990 A CN 202211154990A CN 115559190 A CN115559190 A CN 115559190A
- Authority
- CN
- China
- Prior art keywords
- bridge
- deck system
- bridge deck
- steel
- ballast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D12/00—Bridges characterised by a combination of structures not covered as a whole by a single one of groups E01D2/00 - E01D11/00
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/268—Composite concrete-metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明涉及双层四线铁路钢桁梁技术领域,特别是一种双层四线铁路钢桁梁斜拉桥主梁构造。The invention relates to the technical field of double-layer four-track railway steel truss girders, in particular to a main girder structure of a double-layer four-line railway steel truss girder cable-stayed bridge.
背景技术Background technique
近年来我国铁路行业高速发展,跨越大江大河及高等级通航河流的大跨度桥梁日渐增多,大江大河上建造过多的大桥会对沿岸生态、景观及总体的规划造成不利影响。以节省过江通道资源为目的,通常将多线铁路规划采用同一过江通道进行建设。In recent years, my country's railway industry has developed rapidly, and the number of long-span bridges spanning large rivers and high-level navigable rivers is increasing day by day. Too many bridges built on large rivers will adversely affect the ecology, landscape and overall planning of the coast. For the purpose of saving channel resources across the river, multi-line railways are usually planned to be constructed using the same channel across the river.
目前国内外四线铁路钢桁梁桥布置形式主要采用四线铁路置于同一层布置,如宁安铁路安庆长江大桥、杭绍台铁路椒江特大桥、南昌枢纽东新赣江特大桥等。四线铁路同层布置,如采用钢桁梁,则使得桁宽较宽,部分桥梁采用三主桁布置形式,用钢量较大;如采用钢箱梁,则在整体竖向刚度上略小于钢桁梁。在个别情况下同一层布置为桥梁两岸疏解工程带来一定困难,不同铁路线需绕行,增加疏解难度;存在货运铁路与客运专线铁路并行情况,降低两岸疏解效率,增加工程复杂性。当钢桁梁连接隧道时,四线铁路平层隧道洞径过大,施工风险剧增。At present, the layout of steel truss bridges for four-line railways at home and abroad mainly adopts four-line railways placed on the same floor, such as the Anqing Yangtze River Bridge on the Ning'an Railway, the Jiaojiang Super Bridge on the Hangzhou-Shaoxing-Taiwan Railway, and the East New Ganjiang Bridge on the Nanchang Junction. If the four-line railway is arranged on the same floor, if steel truss girders are used, the truss width will be wider, and some bridges will be arranged in the form of three main trusses, and the amount of steel used will be larger; if steel box girders are used, the overall vertical stiffness will be slightly less than steel trusses. In some cases, the arrangement of the same floor brings certain difficulties to the deconstruction project on both sides of the bridge. Different railway lines need to be detoured, which increases the difficulty of deconstruction; there are freight railways and passenger dedicated railways running in parallel, which reduces the efficiency of deconstruction on both sides of the bridge and increases the complexity of the project. When the steel truss girders are connected to the tunnel, the diameter of the level tunnel of the fourth-line railway is too large, and the construction risk increases sharply.
发明内容Contents of the invention
本发明的目的在于:针对现有技术的跨越大江大河的四线铁路钢桁梁桥置于同一层布置,存在桁宽较宽,用钢量较大,为桥梁两岸疏解工程带来一定困难的问题,提供一种双层四线铁路钢桁梁斜拉桥主梁构造。The purpose of the present invention is to: for the existing four-line railway steel truss bridge across the big rivers placed on the same floor layout, there is a wide truss width, a large amount of steel, which brings certain difficulties to the dredging project on both sides of the bridge To solve the problem, provide a main girder structure of a double-deck four-track railway steel truss girder cable-stayed bridge.
为了实现上述目的,本发明采用的技术方案为:In order to achieve the above object, the technical scheme adopted in the present invention is:
一种双层四线铁路钢桁梁斜拉桥主梁构造,包括位于桥梁横向两侧的主桁,所述主桁包括上弦杆、下弦杆和若干竖向设置的腹杆,所述上弦杆和所述下弦杆均沿纵桥向设置,所述腹杆上端连接所述上弦杆、下端连接所述下弦杆,所有所述腹杆沿纵桥向间隔设置;A main girder structure of a double-deck four-line railway steel truss girder cable-stayed bridge, comprising main trusses located on both lateral sides of the bridge, the main trusses comprising an upper chord, a lower chord and several vertically arranged webs, the upper chord and the lower chord are arranged along the longitudinal bridge direction, the upper end of the web is connected to the upper chord, and the lower end is connected to the lower chord, and all the webs are arranged at intervals along the longitudinal bridge;
两个所述主桁的两个所述下弦杆之间连接有下桥面系,两个所述主桁的两个所述上弦杆之间连接有上桥面系,所述下桥面系上方和所述上桥面系上方分别设置两条铁路,所述上桥面系上方的两条所述铁路对应设于所述下桥面系上方的两条所述铁路正上方,所述上桥面系和所述下桥面系的纵桥向均间隔设有桥面系横梁,所述桥面系横梁两端对应连接两侧所述主桁的所述上弦杆或所述下弦杆;A lower deck system is connected between the two lower chords of the two main trusses, an upper deck system is connected between the two upper chords of the two main trusses, and the lower deck system Two railways are respectively arranged above and above the upper deck system, and the two railways above the upper bridge deck system are correspondingly arranged directly above the two railway lines above the lower bridge deck system. The bridge deck system and the lower bridge deck system are evenly spaced in the longitudinal direction of the bridge deck system, and the two ends of the bridge deck system beam are correspondingly connected to the upper chord or the lower chord of the main truss on both sides;
两侧所述主桁的对应两个所述腹杆顶部之间均连接有横联,所述横联上侧连接所述上桥面系的下侧;Cross-links are connected between the tops of the two corresponding web members of the main girders on both sides, and the upper side of the cross-links is connected to the lower side of the upper deck system;
所述上桥面系沿纵桥向分为第一桥面系和第二桥面系,所述第一桥面系对应所述桥梁的中跨及边跨的非压重段,所述第二桥面系对应所述桥梁的边跨的压重段,所述下桥面系沿纵桥向分为第三桥面系和第四桥面系,所述第三桥面系对应所述桥梁的中跨及边跨的非压重段,所述第四桥面系对应所述桥梁的边跨的压重段,所述第一桥面系和所述第三桥面系均为正交异形板,所述正交异形板顶面用于设置所述铁路;所述第二桥面系和/或所述第四桥面系包括钢箱、钢箱顶部的钢桥面板、填充于所述钢箱内的压重体,所述钢桥面板用于设置所述铁路。The upper deck system is divided into a first deck system and a second deck system along the longitudinal direction of the bridge. The first deck system corresponds to the non-pressure section of the middle span and side span of the bridge. The second deck system corresponds to the weight section of the side span of the bridge, and the lower deck system is divided into a third deck system and a fourth deck system along the longitudinal bridge direction, and the third deck system corresponds to the The non-pressure section of the middle span and side span of the bridge, the fourth deck system corresponds to the ballast section of the side span of the bridge, the first bridge deck system and the third bridge deck system are positive Orthogonal profiled plate, the top surface of the orthogonal profiled plate is used to set the railway; the second bridge deck system and/or the fourth bridge deck system includes a steel box, a steel bridge deck on the top of the steel box, filled in The ballast body in the steel box, the steel bridge deck is used to set the railway.
采用本方案的双层四线铁路钢桁梁斜拉桥主梁构造,通过双层布置,每层设置两条铁路,能够减小钢桁梁的横向跨度,使得仅仅需要两侧所述主桁,且通过在两侧所述主桁的对应两个所述腹杆顶部之间均连接有横联,即通过钢桁梁横向两侧的腹杆顶部之间均连接有横联,使得能够通过两侧所述主桁以及顶部横联将上桥面系稳定的支撑住;且对应所述桥梁的中跨及边跨的非压重段的第一桥面系和第三桥面系采用正交异形板,结构构造轻,桥面可以整体传递纵向力,分担主桁轴力压力;对应所述桥梁的边跨的压重段的第二桥面系和/或所述第四桥面系采用钢箱、钢箱内的压重体和钢桥面板的组合截面形式,解决了压重区的压重难题的基础上,减少了用钢量,同时可以有效解决辅助墩处的负弯矩区混凝土板受力难题;进而使得上下两层能够均分设置铁路线,而无需像双层六线一样,只能够将上层设置四线,下层设置两线,无法均分设置,这种双层四线的设置方式,相比于单层四线的结构形式,能够降低钢桁梁的桁宽,充分利用了钢桁梁断面,大大减少用钢量,而且能够降低桥梁两岸的疏解工程的难度。The main girder structure of the double-layer four-line railway steel truss girder cable-stayed bridge of this scheme can reduce the transverse span of the steel truss girder through double-layer arrangement and two railways on each floor, so that only the main trusses on both sides are required , and the cross-links are connected between the tops of the two corresponding web members of the main truss on both sides, that is, the cross-links are connected between the tops of the web members on both lateral sides of the steel truss girder, so that it can be passed The main trusses on both sides and the top cross-links will stably support the upper deck system; Cross-shaped slabs, light in structure, the bridge deck can transmit longitudinal force as a whole, and share the axial pressure of the main truss; the second deck system and/or the fourth deck system corresponding to the weight section of the side span of the bridge The steel box, the combined section form of the ballast in the steel box and the steel bridge deck solves the ballast problem in the ballast area, reduces the amount of steel used, and can effectively solve the negative moment area at the auxiliary pier The concrete slab is difficult to bear the force; thus, the upper and lower layers can be equally divided to set up railway lines, instead of setting up four lines on the upper level and two lines on the lower level like double-layer six-line lines, which cannot be set equally. This double-layer four-line Compared with the single-layer four-line structure, the line setting method can reduce the truss width of the steel truss girder, make full use of the steel truss girder section, greatly reduce the amount of steel used, and reduce the difficulty of deconstruction work on both sides of the bridge.
优选的,所述钢箱由底板、所述桥梁横向两侧的侧板和相邻两个所述桥面系横梁组成,所述底板和所述侧板均设置于相邻两个所述桥面系横梁之间,所述底板、两个所述侧板、两个所述桥面系横梁和所述钢桥面板围成封闭箱式结构,所述压重体填充于所述封闭箱式结构内。Preferably, the steel box is composed of a bottom plate, side plates on both lateral sides of the bridge and two adjacent deck beams, and the bottom plate and the side plates are arranged on two adjacent bridges. Between the surface beams, the bottom plate, the two side plates, the two deck beams and the steel bridge deck form a closed box structure, and the ballast is filled in the closed box structure Inside.
本方案中,通过底板、两个所述侧板、对应的相邻两个所述桥面系横梁和所述钢桁梁的钢桥面板围成封闭箱式结构,使得相邻两个桥面系横梁之间的空间能够通过压重材料填充满,使得压重区构造与钢桁梁结合在一起,实现压重功能。压重体可采用现有技术中的混凝土、砂浆等压重材料浇筑而成等;压重体的容重及封闭箱式结构根据实际施工情况设计,底板、侧板根据实际施工情况设计。In this solution, a closed box-type structure is formed by the bottom plate, the two side plates, the corresponding two adjacent bridge deck beams and the steel bridge decks of the steel truss girders, so that the two adjacent bridge decks The space between the tie beams can be filled with ballast materials, so that the ballast area structure is combined with the steel truss beams to realize the ballast function. The ballast body can be poured with concrete, mortar and other ballast materials in the prior art; the bulk density of the ballast body and the closed box structure are designed according to the actual construction conditions, and the bottom plate and side plates are designed according to the actual construction conditions.
本方案中,底板和两个侧板均通过桥面系横梁支撑,故无需单独设置小纵梁支撑;且封闭箱式结构是一个大的且封闭的压重箱,封闭箱式结构借助于钢桁梁的桥面系和钢桥面板形成,其简化了压重区与钢桁梁的连接构造;且钢桁梁的桥面系和钢桥面板不仅是桥梁结构,还是压重体的压重箱的一部分,钢材利用率高;且封闭箱式结构相比于现有技术的相邻两个桥面系横梁之间的压重箱的总体积更大,能够降低压重材料的容重,进而降低成本,无需像现有技术通过增高桥面系横梁或较大的增高桥面系横梁来增加压重;上述原因使得压重区的用钢量更小。且因无需设置小纵梁,只需要在相邻两个桥面系横梁之间安装底板和侧板,施工空间更大,施工步骤更少,施工更简单;底板和侧板均能够在安装完相邻两个桥面系横梁后及时安装,能够提高安装效率。通过压重材料填充满封闭箱式结构后,压重材料能够对钢桥面板形成直接的支撑,能够有效的改善钢桥面板的疲劳特性,使得封闭箱式结构处钢桥面板及下方桥面系均无需进行后期养护,整个压重区也无需维护。In this scheme, the bottom slab and the two side slabs are supported by beams on the bridge deck, so there is no need to set up small longitudinal beams separately; and the closed box structure is a large and closed ballast box, and the closed box structure is supported by steel trusses. The bridge deck system of the girder and the steel deck are formed, which simplifies the connection structure between the ballast area and the steel truss girder; and the deck system of the steel truss girder and the steel bridge deck are not only a bridge structure, but also a part of the ballast box of the ballast body , the steel utilization rate is high; and the total volume of the closed box structure is larger than that of the ballast box between two adjacent bridge deck beams in the prior art, which can reduce the bulk density of the ballast material, thereby reducing the cost, without As in the prior art, the ballast is increased by increasing the height of the bridge deck beam or by increasing the height of the bridge deck beam; the above reasons make the amount of steel used in the ballast area smaller. And because there is no need to set small longitudinal beams, only the bottom plate and side plates need to be installed between two adjacent deck beams, the construction space is larger, the construction steps are fewer, and the construction is simpler; both the bottom plate and the side plates can be installed after installation. The two adjacent bridge decks are installed in time after the beams are tied, which can improve the installation efficiency. After the closed box structure is filled with the ballast material, the ballast material can form a direct support for the steel bridge deck, which can effectively improve the fatigue characteristics of the steel bridge deck, so that the steel bridge deck at the closed box structure and the lower bridge deck system Neither post-maintenance nor maintenance is required in the entire ballast area.
进一步优选的,所述压重体下部为普通混凝土层、上部为自密实水泥砂浆层。Further preferably, the lower part of the ballast body is an ordinary concrete layer, and the upper part is a self-compacting cement mortar layer.
本方案通过采用封闭箱式结构,相比于现有技术的相邻两个桥面系横梁之间的所有压重箱的总体积更大,在保证相同压重的情况下,使得能够采用比重混凝土的容重更小的普通混凝土和自密实水泥砂浆来实现压重,封闭箱式结构内下部的普通混凝土层的承载能力强,自密实水泥砂浆层有利于填充满封闭箱式结构上部,同时保证了安全性和密实性,且相比于重混凝土,通过普通混凝土层和自密实水泥砂浆层填充满封闭箱式结构内部空间,其施工更加简单,且材料自身的成本也较低,进而能够节省施工成本。This solution adopts a closed box structure, compared with the total volume of all ballast boxes between two adjacent bridge deck beams in the prior art, which enables the use of specific gravity concrete while ensuring the same ballast Ordinary concrete and self-compacting cement mortar with a smaller bulk density are used to realize the pressure. The ordinary concrete layer in the lower part of the closed box structure has a strong bearing capacity, and the self-compacting cement mortar layer is conducive to filling the upper part of the closed box structure, while ensuring Safety and compactness, and compared with heavy concrete, the internal space of the closed box structure is filled with ordinary concrete layer and self-compacting cement mortar layer, the construction is simpler, and the cost of the material itself is also lower, which can save construction cost.
优选的,所述第二桥面系的所述钢箱由底板、所述桥梁横向两侧的上弦杆和相邻两个所述桥面系横梁组成,所述底板设置于相邻两个所述桥面系横梁之间,所述底板、两侧的上弦杆、两个所述桥面系横梁和所述钢桥面板围成封闭箱式结构,所述压重体填充于所述封闭箱式结构内;Preferably, the steel box of the second deck system is composed of a bottom plate, upper chords on both lateral sides of the bridge and two adjacent beams of the bridge deck system, and the bottom plate is arranged on two adjacent Between the bridge deck beams, the bottom plate, the upper chords on both sides, the two deck beams and the steel bridge deck form a closed box structure, and the ballast is filled in the closed box structure. within the structure;
所述第四桥面系的所述钢箱由底板、所述桥梁横向两侧的下弦杆和相邻两个所述桥面系横梁组成,所述底板设置于相邻两个所述桥面系横梁之间,所述底板、两侧的下弦杆、两个所述桥面系横梁和所述钢桥面板围成封闭箱式结构,所述压重体填充于所述封闭箱式结构内。The steel box of the fourth deck system is composed of a bottom plate, lower chords on both sides of the bridge laterally, and two adjacent beams of the bridge deck system, and the bottom plate is arranged on two adjacent bridge decks. Between the tie beams, the bottom plate, the lower chords on both sides, the two bridge deck tie beams and the steel bridge deck form a closed box structure, and the ballast is filled in the closed box structure.
本方案中,无需单独设置侧板,通过上弦杆作为侧板能够围成第二桥面系的封闭箱式结构,通过下弦杆作为侧板能够围成第四桥面系的封闭箱式结构,通过这种设置方式,能够无需设置侧板,使得封闭箱式结构的安装能够方便,且使得第四桥面系和第二桥面系能够直接与对应弦杆形成一体,稳定性更高,传力能够更好;且能够加宽封闭箱式结构,增加能够设置的压重体的体积,能够增强压重能力。In this scheme, there is no need to set up side plates separately, and the closed box structure of the second deck system can be formed by using the upper chord as the side plate, and the closed box structure of the fourth deck system can be formed by using the lower chord as the side plate. Through this setting method, no need to set side plates, the installation of the closed box structure can be facilitated, and the fourth deck system and the second deck system can be directly integrated with the corresponding chords, which has higher stability and transmission. The force can be better; and the closed box structure can be widened, the volume of the ballast body that can be set can be increased, and the ballast capacity can be enhanced.
进一步优选的,仅在所述第四桥面系设有所述钢箱;Further preferably, the steel box is only provided on the fourth bridge deck;
或,or,
所述第四桥面系和所述第二桥面系均设有所述钢箱,所述第四桥面系的所述钢箱的体积大于所述第二桥面系的所述钢箱的体积。Both the fourth deck system and the second deck system are provided with the steel box, and the volume of the steel box of the fourth deck system is larger than that of the steel box of the second deck system volume of.
因为增强了压重能力,仅在所述第四桥面系设置能够满足钢桁梁双层的压重时,可以不在上层的第二桥面系底部设置钢箱。如果仅在所述第四桥面系设置不能够满足钢桁梁双层的压重时,就优先在第四桥面系设置大的压重,在第二桥面系设置小的压重,即使得所述第四桥面系的所述钢箱的体积大于所述第二桥面系的所述钢箱的体积。这种设置方式使得全部钢箱或者较大的钢箱尽量在下层进行施工,施工更加方便,同时能够尽量不在上层设置压重体或减小上层设置压重体的体积,能够避免或减小上层压重体对下桥面系及其线路造成影响。Because of the increased ballast capacity, steel boxes may not be arranged at the bottom of the second bridge deck system on the upper floor only when the fourth deck system is set to meet the double-layer ballast weight of the steel truss girder. If only the arrangement of the fourth deck system cannot satisfy the double-layer ballast weight of the steel truss girder, a large ballast weight is firstly set on the fourth deck system, and a small ballast weight is set on the second deck system, That is, the volume of the steel box of the fourth deck system is larger than the volume of the steel box of the second deck system. This arrangement makes it possible for all steel boxes or larger steel boxes to be constructed on the lower floor, making the construction more convenient. At the same time, it is possible to avoid or reduce the volume of the ballast on the upper floor as much as possible, which can avoid or reduce the pressure on the upper floor. It will affect the lower deck system and its lines.
优选的,所述压重体包括至少两层分层填充的收缩性补偿混凝土层,能够保证压重体填充密实,且能够放置混凝土收缩,使得避免压重体与封闭箱式结构脱离,保证桥面系的整体性。Preferably, the ballast body includes at least two layers of shrinkage-compensating concrete layers filled in layers, which can ensure that the ballast body is filled densely, and can prevent the concrete from shrinking, so as to prevent the ballast body from detaching from the closed box structure and ensure the stability of the bridge deck system. Wholeness.
优选的,所述钢桥面板底部沿横桥向间隔分布有若干第一加劲肋,所述第一加劲肋沿纵桥向设置;通过第一加劲肋使得压重体与钢桥面板能够更好的结合在一起;Preferably, the bottom of the steel bridge deck is distributed with several first stiffeners at intervals along the transverse bridge direction, and the first stiffeners are arranged along the longitudinal bridge direction; through the first stiffeners, the ballast body and the steel bridge deck can be better integrate;
当所述压重体下部为普通混凝土层时,所述普通混凝土层顶面高度不高于所述钢桥面板的第一加劲肋底部。普通混凝土层的实际高度根据具体的压重量来确定,但普通混凝土层顶面高度不宜高于所述钢桥面板的第一加劲肋底部,使得能够通过自密实水泥砂浆更好的填充钢桥面板的第一加劲肋等角落部位,提高封闭箱式结构内的填充效果。When the lower part of the ballast body is an ordinary concrete layer, the height of the top surface of the ordinary concrete layer is not higher than the bottom of the first stiffener of the steel bridge deck. The actual height of the ordinary concrete layer is determined according to the specific weight, but the height of the top surface of the ordinary concrete layer should not be higher than the bottom of the first stiffener of the steel bridge deck, so that the steel bridge deck can be better filled with self-compacting cement mortar The corner parts such as the first stiffener of the steel pipe can improve the filling effect in the closed box structure.
优选的,所述底板上方设有若干第二加劲肋,若干所述第二加劲肋沿纵桥向设置,所述桥面系横梁的腹板和下翼板的转角处沿纵桥向竖直设有接头板,所述第二加劲肋与所述桥面系横梁的对应的接头板通过第一高强螺栓连接;Preferably, several second stiffeners are arranged above the bottom plate, and several second stiffeners are arranged along the longitudinal bridge direction, and the corners of the web of the bridge deck and the lower wing plate are vertical along the longitudinal bridge direction. A joint plate is provided, and the second stiffener is connected to the corresponding joint plate of the bridge deck beam through first high-strength bolts;
和/或;and / or;
所述封闭箱式结构的四侧均设有若干剪力钉。Several shear studs are provided on the four sides of the closed box structure.
接头板竖直设置在所述桥面系横梁的腹板和下翼板的转角处,沿纵桥向并对应于接头板的位置在所述底板顶面设置第二加劲肋,在保证对底板充足的加强的同时,还能够通过第一高强螺栓将底板和桥面系横梁更稳定的连接。且接头板能够使得压重体与桥面系横梁的结合效果更好,第二加劲肋能够使得压重体与底板的结合效果更好,通过这种方式,不仅能够加强桥面系横梁和底板,还能够加强压重体与钢箱的结合性能,使得整个压重区的桥面系的整体压重能力更强,刚度更大,列车行驶性能优异。The joint plate is vertically arranged at the corner of the web of the bridge deck beam and the lower wing plate, and the second stiffener is arranged on the top surface of the bottom plate along the longitudinal direction of the bridge and corresponding to the position of the joint plate, so as to ensure the stability of the bottom plate. At the same time of sufficient reinforcement, the bottom plate and the bridge deck beam can be connected more stably through the first high-strength bolts. And the joint plate can make the combination effect of the ballast body and the bridge deck beam better, and the second stiffener can make the ballast body and the bottom plate better. In this way, not only the bridge deck beam and the bottom plate can be strengthened, but also The combination performance of the ballast body and the steel box can be strengthened, so that the overall ballast capacity of the bridge deck system in the whole ballast area is stronger, the rigidity is greater, and the train running performance is excellent.
优选的,所述横联的横桥向两侧与对应所述腹杆栓接,所述横联的上侧与所述上桥面系的下侧焊接,避免了上桥面系螺栓掉落对下层铁路安全的影响,又保证了安装便捷性。Preferably, the transverse bridges of the transverse link are bolted to the corresponding web members on both sides, and the upper side of the transverse link is welded to the lower side of the upper deck system, so as to prevent the bolts of the upper deck system from falling The impact on the safety of the lower railway, but also to ensure the convenience of installation.
优选的,所述横联包括横杆和若干斜杆,所述斜杆上端连接所述横杆上侧、下端连接所述上桥面系下侧,所述横杆、所述上桥面系和所有所述斜杆共同组成若干沿所述横桥向连续排布的等边三角形构造,减小杆件的同时,能够与上桥面系结合在一起,提高对上桥面系的支撑效果。Preferably, the cross-connection includes a cross bar and several oblique bars, the upper end of the oblique bar is connected to the upper side of the cross bar, and the lower end is connected to the lower side of the upper deck system, and the cross bar, the upper deck system Together with all the oblique rods, it forms several equilateral triangle structures arranged continuously along the horizontal bridge direction. While reducing the number of rods, it can be combined with the upper deck system to improve the supporting effect on the upper bridge deck system. .
综上所述,由于采用了上述技术方案,本发明的有益效果是:In summary, owing to adopting above-mentioned technical scheme, the beneficial effect of the present invention is:
1、本发明所述双层四线铁路钢桁梁斜拉桥主梁构造,通过双层布置,每层设置两条铁路,能够减小钢桁梁的横向跨度,使得仅仅需要两侧所述主桁,且通过在两侧所述主桁的对应两个所述腹杆顶部之间均连接有横联,即通过钢桁梁横向两侧的腹杆顶部之间均连接有横联,使得能够通过两侧所述主桁以及顶部横联将上桥面系稳定的支撑住;且对应所述桥梁的中跨及边跨的非压重段的第一桥面系和第三桥面系采用正交异形板,结构构造轻,桥面可以整体传递纵向力,分担主桁轴力压力;对应所述桥梁的边跨的压重段的第二桥面系和/或所述第四桥面系采用钢箱、钢箱内的压重体和钢桥面板的组合截面形式,解决了单层四线的压重结构无法适用于双层四线的压重区的压重难题,还减少了用钢量,同时可以有效解决辅助墩处的负弯矩区混凝土板受力难题;进而使得上下两层能够均分设置铁路线,而无需像双层六线一样,只能够将上层设置四线,下层设置两线,无法均分设置,这种双层四线的设置方式,相比于单层四线的结构形式,能够降低钢桁梁的桁宽,充分利用了钢桁梁断面,大大减少用钢量,而且能够减少铁路绕行,可实现客货分流,降低桥梁两岸的疏解工程的难度。1. The main girder structure of the double-layer four-line railway steel truss girder cable-stayed bridge of the present invention can reduce the transverse span of the steel truss girder through the double-layer arrangement and two railways on each floor, so that only the two sides are required. The main truss, and the cross-links are connected between the tops of the two corresponding webs of the main trusses on both sides, that is, the cross-links are connected between the tops of the webs on both sides of the steel truss transversely, so that The upper deck system can be stably supported by the main truss on both sides and the top cross-link; and the first deck system and the third deck system corresponding to the non-pressure section of the middle span and side span of the bridge Orthogonal special-shaped slabs are used, the structure is light, and the bridge deck can transmit longitudinal force as a whole, and share the axial pressure of the main truss; the second bridge deck system corresponding to the ballast section of the side span of the bridge and/or the fourth bridge The surface system adopts the steel box, the combined section form of the ballast body in the steel box and the steel bridge deck, which solves the ballast problem that the single-layer four-line ballast structure cannot be applied to the double-layer four-line ballast area, and also reduces The amount of steel used can effectively solve the stress problem of the concrete slab in the negative bending moment area at the auxiliary pier; thus, the upper and lower floors can be equally divided to set the railway line, instead of only setting four lines on the upper floor like the double-layer six-line , the lower layer is equipped with two lines, which cannot be equally divided. Compared with the single-layer four-line structure, this double-layer four-line structure can reduce the truss width of the steel truss girder, make full use of the steel truss section, and greatly It reduces the amount of steel used, and can reduce the detour of the railway, which can realize the diversion of passengers and goods, and reduce the difficulty of the deconstruction project on both sides of the bridge.
2、将位于压重区的第二桥面系和/或所述第四桥面系采用封闭箱式结构和压重体的整体截面形式,使得压重结构与受力结构结合在一起,使得压重区的压重能力更强、结构简单、耗材少、施工便捷、成本低,能够有效改善钢桥面板的疲劳特性,使得封闭箱式结构处钢桥面板及下方桥面系均无需进行后期养护,整个压重区也无需维护。2. The second bridge deck system and/or the fourth bridge deck system located in the ballast area adopts a closed box structure and the overall cross-sectional form of the ballast body, so that the ballast structure and the stressed structure are combined together, so that the pressure The weight capacity of the heavy area is stronger, the structure is simple, the consumables are less, the construction is convenient, and the cost is low, which can effectively improve the fatigue characteristics of the steel bridge deck, so that the steel deck of the closed box structure and the deck system below do not need post-maintenance , the whole ballast area also requires no maintenance.
3、通过上弦杆作为侧板能够围成第二桥面系的封闭箱式结构,通过下弦杆作为侧板能够围成第四桥面系的封闭箱式结构,通过这种设置方式,能够无需设置侧板,使得封闭箱式结构的安装能够方便,且使得第四桥面系和第二桥面系能够直接与对应弦杆形成一体,稳定性更高,传力能够更好;且能够加宽封闭箱式结构,增加能够设置的压重体的体积,能够增强压重能力。3. The closed box structure of the second deck system can be formed by using the upper chord as the side plate, and the closed box structure of the fourth deck system can be formed by using the lower chord as the side plate. The side panels are provided to facilitate the installation of the closed box structure, and enable the fourth deck system and the second deck system to be directly integrated with the corresponding chords, resulting in higher stability and better force transmission; The wide closed box structure increases the volume of the ballast body that can be set, and can enhance the ballast capacity.
4、采用顶面全焊接、侧面与腹杆栓接的横联结构,避免了上桥面系的螺栓掉落对下层铁路安全的影响,又保证了安装便捷性。4. Adopting the cross-connection structure with the top fully welded and the side bolted to the web, which avoids the influence of the bolts on the upper deck system on the safety of the lower railway and ensures the convenience of installation.
5、相比于平层四线结构及全钢桥面桁梁结构,刚度大,列车行驶性能优异。5. Compared with the flat four-line structure and the all-steel bridge deck truss structure, it has higher rigidity and excellent train driving performance.
附图说明Description of drawings
图1是本发明所述双层四线铁路钢桁梁斜拉桥主梁构造的中跨及边跨的非压重段的横截面示意图;Fig. 1 is the cross-sectional schematic view of the non-pressurized section of the mid-span and side span of the double-deck four-line railway steel truss girder cable-stayed bridge girder structure of the present invention;
图2是实施例1中所述双层四线铁路钢桁梁斜拉桥主梁构造的边跨的压重段的横截面示意图;Fig. 2 is the cross-sectional schematic view of the ballast section of the side span of the main girder structure of the double-layer four-line railway steel truss girder cable-stayed bridge described in
图3是图2中第四桥面系的横截面示意图;Fig. 3 is a schematic cross-sectional view of the fourth bridge deck system in Fig. 2;
图4是实施例2中边跨的压重区的上桥面系或下桥面系的横截面示意图;Fig. 4 is the cross-sectional schematic view of the upper deck system or the lower deck system of the weight zone of the side span in
图5是图4中A-A处的断面示意图;Fig. 5 is a schematic cross-sectional view at the A-A place in Fig. 4;
图6是图4中B-B处的断面示意图;Fig. 6 is a schematic cross-sectional view at the B-B place in Fig. 4;
图7是实施例2中边跨的压重区的上桥面系或下桥面系的平面结构示意图。Fig. 7 is a schematic plan view of the upper deck system or the lower deck system of the ballast area of the side span in
图标:1-上弦杆;2-下弦杆;3-腹杆;41-第一桥面系;42-第二桥面系;51-第三桥面系;52-第四桥面系;6-横联;7-铁路;81-第一高强螺栓;82-第二高强螺栓;9-侧板;91-人孔;10-钢桥面板;11-底板;12-第一加劲肋;13-第二加劲肋;131-第三加劲肋;14-桥面系横梁;151-普通混凝土层;152-自密实水泥砂浆层;153-收缩性补偿混凝土层;1511-第一层;1512-第二层;16-剪力钉;17-接头板;18-桥面板纵梁。Icons: 1-top chord; 2-bottom chord; 3-web; 41-first deck system; 42-second deck system; 51-third bridge deck system; 52-fourth deck system; 6 -cross-connection; 7-railway; 81-first high-strength bolt; 82-second high-strength bolt; 9-side plate; 91-manhole; 10-steel bridge deck; 11-bottom plate; 12-first stiffener; 13 -Second stiffener; 131-Third stiffener; 14-Deck beam; 151-Ordinary concrete layer; 152-Self-compacting cement mortar layer; 153-Shrinkage compensation concrete layer; 1511-First layer; 1512- The second layer; 16-shear nails; 17-joint plate; 18-bridge deck longitudinal girder.
具体实施方式detailed description
下面结合附图,对本发明作详细的说明。Below in conjunction with accompanying drawing, the present invention is described in detail.
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
实施例1Example 1
本实施例提供一种双层四线铁路钢桁梁斜拉桥主梁构造,参见图1-3,展示横桥向,包括位于桥梁横向两侧的主桁,所述主桁包括上弦杆1、下弦杆2和若干竖向设置的腹杆3,所述上弦杆1和所述下弦杆2均沿纵桥向设置,所述腹杆3上端连接所述上弦杆1、下端连接所述下弦杆2,所有所述腹杆3沿纵桥向间隔设置;This embodiment provides a main girder structure of a double-layer four-line railway steel truss girder cable-stayed bridge, referring to Figures 1-3, showing the transverse direction of the bridge, including the main trusses located on both sides of the bridge, and the main trusses include
两个所述主桁的两个所述下弦杆2之间连接有下桥面系,两个所述主桁的两个所述上弦杆1之间连接有上桥面系,所述下桥面系上方和所述上桥面系上方分别设置两条铁路7,所述上桥面系上方的两条所述铁路7对应设于所述下桥面系上方的两条所述铁路7正上方,所述上桥面系和所述下桥面系的纵桥向均间隔设有桥面系横梁14,所述桥面系横梁14两端对应连接两侧所述主桁的所述上弦杆1或所述下弦杆2;A lower deck system is connected between the two
两侧所述主桁的对应两个所述腹杆3顶部之间均连接有横联6,所述横联6上侧连接所述上桥面系的下侧;Cross-links 6 are connected between the tops of the corresponding two
如图1-2所示,所述上桥面系沿纵桥向分为第一桥面系41和第二桥面系42,所述第一桥面系41对应所述桥梁的中跨及边跨的非压重段,所述第二桥面系42对应所述桥梁的边跨的压重段,所述下桥面系沿纵桥向分为第三桥面系51和第四桥面系52,所述第三桥面系51对应所述桥梁的中跨及边跨的非压重段,所述第四桥面系52对应所述桥梁的边跨的压重段,所述第一桥面系41和所述第三桥面系51均为正交异形板,所述正交异形板顶面用于设置所述铁路7;所述第二桥面系42和/或所述第四桥面系52包括钢箱、钢箱顶部的钢桥面板10、填充于所述钢箱内的压重体,所述钢桥面板10用于设置所述铁路7。As shown in Figure 1-2, the upper deck system is divided into a
采用本方案的双层四线铁路钢桁梁斜拉桥主梁构造,如图1所示,通过上下双层布置,每层设置两条铁路7,上下铁路7对应设置,能够减小钢桁梁的横向跨度,使得仅仅需要设置两侧的所述主桁,且通过在两侧所述主桁的对应两个所述腹杆3顶部之间均连接有横联6,横联6上部连接所述上桥面系的底部,即通过钢桁梁横向两侧的腹杆3顶部之间均连接有横联6,使得能够通过两侧所述主桁以及顶部横联6与上桥面系结合成一体,并将上桥面系稳定的支撑住;且对应所述桥梁的中跨及边跨的非压重段的第一桥面系41和第三桥面系51采用正交异形板,如图1所示,结构构造轻,桥面可以整体传递纵向力,分担主桁轴力压力;对应所述桥梁的边跨的压重段的第二桥面系42和/或所述第四桥面系52采用钢箱、钢箱内的压重体和钢桥面板10的组合截面形式,如图2所示,解决了压重区的压重难题的基础上,减少了用钢量,同时可以有效解决辅助墩处的负弯矩区混凝土板受力难题;进而使得上下两层能够均分设置铁路线,而无需像双层六线一样,只能够将上层设置四线,下层设置两线,因受力问题无法均分设置,这种双层四线的设置方式,相比于单层四线的结构形式,能够降低钢桁梁的桁宽,充分利用了钢桁梁断面,大大减少用钢量,而且能够降低桥梁两岸的疏解工程的难度。The main girder structure of the double-layer four-line railway steel truss girder cable-stayed bridge adopts this scheme, as shown in Figure 1, through the upper and lower double-layer arrangement, two
其中,图2展示的压重区的横截面,图2中上桥面系和下桥面系均采用设置钢箱和压重体的形式。当然,根据实际情况,如果在下层设置钢箱和压重体的形式能够满足双层的压重,那就无需在上层设置钢箱和压重体的形式。同理,即可以只将上桥面系设置为具有压重体的截面形式、或只将下桥面系设置为具有压重体的截面形式,如果在单层设置压重体的截面形式无法满足双层的压重,则需要将上桥面系和下桥面系均设置为具有压重体的截面形式。作为一种较优的实施方式,仅在所述第四桥面系52设有所述钢箱;或,所述第四桥面系52和所述第二桥面系42均设有所述钢箱,所述第四桥面系52的所述钢箱的体积大于所述第二桥面系42的所述钢箱的体积。因为增强了压重能力,仅在所述第四桥面系52设置能够满足钢桁梁双层的压重时,可以不在上层的第二桥面系42底部设置钢箱。如果仅在所述第四桥面系52设置不能够满足钢桁梁双层的压重时,就优先在第四桥面系52设置大的压重,在第二桥面系42设置小的压重,即使得所述第四桥面系52的所述钢箱的体积大于所述第二桥面系42的所述钢箱的体积。这种设置方式使得全部钢箱或者较大的钢箱尽量在下层进行施工,施工更加方便,同时能够尽量不在上层设置压重体或减小上层设置压重体的体积,能够避免或减小上层压重体对下桥面系及其线路造成影响。Among them, Fig. 2 shows the cross-section of the ballast area. In Fig. 2, both the upper deck system and the lower deck system adopt the form of setting steel boxes and ballast bodies. Certainly, according to the actual situation, if the form of setting steel box and ballast body in the lower layer can meet the double-layer ballast weight, then there is no need to arrange the form of steel box and ballast body in the upper layer. In the same way, only the upper deck system can be set to have a cross-section form with ballast bodies, or only the lower deck system can be set to have a cross-section form with ballast bodies. ballast, it is necessary to set both the upper deck system and the lower deck system to have the cross-section form of the ballast body. As a preferred embodiment, the steel box is only provided on the
如图2-3所示,所述第二桥面系42的所述钢箱由底板11、所述桥梁横向两侧的上弦杆1和相邻两个所述桥面系横梁14组成,桥面系横梁14可以参考图5中的结构形式,其中,图1中的第一桥面系41和第三桥面系51均沿纵桥向设有桥面系横梁14,第一桥面系41和第三桥面系51的桥面系横梁14的间距为2.5-4m,保证第一桥面系41和第三桥面系51的正交异形板的强度;图2中的第二桥面系42和第四桥面系52也均沿纵桥向设有桥面系横梁14,第二桥面系42和第四桥面系52的桥面系横梁14的间距为3-3.5m,使得能够将压重体能够与桥面系结合在一起,使得能够满足压重要求。所述底板11设置于相邻两个所述桥面系横梁14之间,所述底板11、两侧的上弦杆1、两个所述桥面系横梁14和所述钢桥面板10围成封闭箱式结构,所述压重体填充于所述封闭箱式结构内;As shown in Figures 2-3, the steel box of the
所述第四桥面系52的所述钢箱由底板11、所述桥梁横向两侧的下弦杆2和相邻两个所述桥面系横梁14组成,所述底板11设置于相邻两个所述桥面系横梁14之间,所述底板11、两侧的下弦杆2、两个所述桥面系横梁14和所述钢桥面板10围成封闭箱式结构,所述压重体填充于所述封闭箱式结构内。The steel box of the
本实施例中,无需单独设置侧板9,通过上弦杆1作为侧板9能够围成第二桥面系42的封闭箱式结构,通过下弦杆2作为侧板9能够围成第四桥面系52的封闭箱式结构,通过这种设置方式,能够无需设置侧板9,使得封闭箱式结构的安装能够方便,且使得第四桥面系52和第二桥面系42能够直接与对应弦杆形成一体,稳定性更高,传力能够更好;且能够加宽封闭箱式结构,增加能够设置的压重体的体积,能够增强压重能力。In this embodiment, there is no need to separately set up the side plate 9, the closed box structure of the second
本实施例中,所述压重体包括至少两层分层填充的收缩性补偿混凝土层153。能够保证压重体填充密实,且能够放置混凝土收缩,使得避免压重体与封闭箱式结构脱离,保证桥面系的整体性。In this embodiment, the ballast body includes at least two layers of shrinkage-compensating
如图3所示,所述钢桥面板10底部沿横桥向间隔分布有若干第一加劲肋12,所述第一加劲肋12沿纵桥向设置;通过第一加劲肋12使得压重体与钢桥面板10能够更好的结合在一起,同时能够对钢桥面板10进行加强。第一加劲肋12可以采用U肋形式。As shown in Figure 3, the bottom of the
可以选择的,所述底板11上方设有若干第二加劲肋13,若干所述第二加劲肋13沿纵桥向设置,第二加劲肋13能够加强底板11,使得底板11的厚度能够减小,进而能够降低钢材的使用,且第二加劲肋13能够使得压重体与底板11的结合效果更好。本实施例中,所述桥面系横梁14的腹板和下翼板的转角处沿纵桥向竖直设有接头板17,可以参考图5,所述第二加劲肋13与所述桥面系横梁14的对应的接头板17通过第一高强螺栓81连接;接头板17竖直设置在所述桥面系横梁14的腹板和下翼板的转角处,沿纵桥向并对应于接头板17的位置在所述底板11顶面设置第二加劲肋13,在保证对底板11充足的加强的同时,还能够通过第一高强螺栓81将底板11和桥面系横梁14更稳定的连接。且接头板17能够使得压重体与桥面系横梁14的结合效果更好。Optionally, several
通过接头板17、第一加劲肋12和第二加劲肋13,不仅能够分别加强桥面系横梁14、钢桥面板10和底板11,还能够加强压重体与钢箱的结合性能,使得整个压重区的桥面系的整体压重能力更强,刚度更大,列车行驶性能优异。Through the
可以选择的,所述封闭箱式结构的四侧均设有若干剪力钉16,加强压重体与钢箱的结合性能,使得整个压重区的桥面系的整体压重能力更强,刚度更大,列车行驶性能优异。Optionally, a number of
本实施例中,如图1-2所示,所述横联6的横桥向两侧与对应所述腹杆3栓接,所述横联6的上侧与所述上桥面系的下侧焊接。避免了上桥面系螺栓掉落对下层铁路7安全的影响,又保证了安装便捷性。作为较优的选择,所述横联6包括横杆和若干斜杆,所述斜杆上端连接所述横杆上侧、下端连接所述上桥面系下侧,所述横杆、所述上桥面系和所有所述斜杆共同组成若干沿所述横桥向连续排布的等边三角形构造,减小杆件的同时,能够与上桥面系结合在一起,提高对上桥面系的支撑效果。除外,还能够将下层铁路7接触网可以设置于上层的桥面系横梁14或横联6上,避免额外设置接触网固定架。In this embodiment, as shown in Figure 1-2, the transverse bridge of the
本实施例中,在边跨压重区每层横向两侧的弦杆、顶部钢桥面板10、纵向相邻的两个所述桥面系横梁14、底板11均是形成一体的封闭箱式结构,再通过在钢桥面板10开灌注孔的方式分层灌注收缩性补偿混凝土,顶部采用压浆灌注收缩性补偿混凝土的方式,保证灌注密实,使得整个截面为一个实心的钢混整体结构,既能够实现压重,又能够对上部的钢桥面板10进行支撑加强,使得列车的运行安全、舒适度均能够更好。In this embodiment, the chords on both lateral sides of each floor in the side-span pressure zone, the top
实施例2Example 2
本实施例提供一种双层四线铁路钢桁梁斜拉桥主梁构造,与实施例1不同之处在于,压重区的截面构造存在不同,参见图4-7,本实施例中,在两个弦杆之间设置有侧板9,如图4所示,以两个下弦杆2之间的设置为例,所述钢箱由底板11、所述桥梁横向两侧的侧板9和相邻两个所述桥面系横梁14组成,所述底板11和所述侧板9均设置于相邻两个所述桥面系横梁14之间,所述底板11、两个所述侧板9、两个所述桥面系横梁14和所述钢桥面板10围成封闭箱式结构,所述压重体填充于所述封闭箱式结构内。This embodiment provides a main girder structure of a double-layer four-track railway steel truss girder cable-stayed bridge. The difference from
本方案中,通过底板11、两个所述侧板9、对应的相邻两个所述桥面系横梁14之间的空间能够通过压重材料填充满,使得压重区构造与钢桁梁结合在一起,实现压重功能。压重体可采用现有技术中的混凝土、砂浆等压重材料浇筑而成等;压重体的容重及封闭箱式结构根据实际施工情况设计,底板11、侧板9根据实际施工情况设计。In this solution, the space between the
本方案中,底板11和两个侧板9均通过桥面系横梁14支撑,故无需单独设置小纵梁支撑;且封闭箱式结构是一个大的且封闭的压重箱,封闭箱式结构借助于钢桁梁的桥面系和钢桥面板10形成,其简化了压重区与钢桁梁的连接构造;且钢桁梁的桥面系和钢桥面板10不仅是桥梁结构,还是压重体的压重箱的一部分,钢材利用率高;且封闭箱式结构相比于现有技术的相邻两个桥面系横梁14之间的压重箱的总体积更大,能够降低压重材料的容重,进而降低成本,无需像现有技术通过增高桥面系横梁14或较大的增高桥面系横梁14来增加压重;上述原因使得压重区的用钢量更小。且因无需设置小纵梁,只需要在相邻两个桥面系横梁14之间安装底板11和侧板9,施工空间更大,施工步骤更少,施工更简单;底板11和侧板9均能够在安装完相邻两个桥面系横梁14后及时安装,能够提高安装效率。通过压重材料填充满封闭箱式结构后,压重材料能够对钢桥面板10形成直接的支撑,能够有效的改善钢桥面板10的疲劳特性,使得封闭箱式结构处钢桥面板10及下方桥面系均无需进行后期养护,整个压重区也无需维护。In this solution, the
进一步优选的,所述压重体下部为普通混凝土层151、上部为自密实水泥砂浆层152。本方案通过采用封闭箱式结构,相比于现有技术的相邻两个桥面系横梁14之间的所有压重箱的总体积更大,在保证相同压重的情况下,使得能够采用比重混凝土的容重更小的普通混凝土和自密实水泥砂浆来实现压重,封闭箱式结构内下部的普通混凝土层151的承载能力强,自密实水泥砂浆层152有利于填充满封闭箱式结构上部,同时保证了安全性和密实性,且相比于重混凝土,通过普通混凝土层151和自密实水泥砂浆层152填充满封闭箱式结构内部空间,其施工更加简单,且材料自身的成本也较低,进而能够节省施工成本。Further preferably, the lower part of the ballast body is an ordinary
本实施例中,所述底板11、侧板9、钢桥面板10均设有加劲结构,加劲结构用于对底板11、侧板9和钢桥面板10进行加强,使得能够通过底板11和侧板9来承受普通混凝土层151和自密实水泥砂浆层152整体的压力,钢桥面板10能够更好的承受铁路7和列车的压力。如图4、5和7所示,所述桥面系横梁14的腹板和下翼板的转角处沿纵桥向设有竖直的接头板17,所述底板11的加劲结构为若干对应于所述接头板17设置的第二加劲肋13,所述第二加劲肋13沿纵桥向设置,所述第二加劲肋13与对应的所述接头板17通过第一高强螺栓81连接。沿纵桥向并对应于接头板17的位置在所述底板11顶面设置第二加劲肋13,在保证对底板11充足的加强的同时,还能够便于底板11和桥面系横梁14更稳定的连接。且第二加劲肋13设置在所述底板11顶面,使得底板11与普通混凝土层151的连接更加紧密,提高压重区构造的整体性和稳定性。In this embodiment, the
侧板9的内侧是指侧板9面向封闭箱式结构内部的一侧。如图6所示,所述桥面系横梁14的腹板具有竖直设置的腹板加劲板,所述侧板9的纵桥向两侧分别对应与两个所述桥面系横梁14的腹板加劲板通过第二高强螺栓82连接,使得侧板9与桥面系横梁14的连接更加稳定。且所述侧板9的加劲结构为若干第三加劲肋131,所述第三加劲肋131竖向设置于所述侧板9的内侧,因侧板9的竖向高度相比现有压重箱的高度更高,通过设置竖向的第三加劲肋131,能够更好的对侧板9进行加强。且将第三加劲肋131设置于所述侧板9的内侧,使得侧板9能够与普通混凝土层151和自密实水泥砂浆层152的连接更紧密,提高压重区构造的整体性和稳定性。The inner side of the side plate 9 refers to the side of the side plate 9 facing the inside of the closed box structure. As shown in Figure 6, the web of the
在通过上述第二加劲肋13和第三加劲肋131加强后,使得能够采用厚度较薄的底板11和侧板9,即可以采用厚度为10-16mm的底板11,可以采用厚度为大于或等于10mm的侧板9,进而能够减少用钢量,节约成本,且更便于侧板9和底板11的吊装。After being strengthened by the above-mentioned
且所述侧板9设有人孔91,所述人孔91的顶部高于所述普通混凝土层151的顶面,本实施例中,每个封闭箱式结构仅有一个侧板9设有一个人孔91,通过所述人孔91浇筑所述普通混凝土层151,施工人员能够进入人孔91浇筑普通混凝土,便于普通混凝土层151的浇筑,且能够提高浇筑质量,而且无需单独在侧板9上开设多余的浇筑口用于浇筑普通混凝土层151,能够提高封闭箱式结构的完整性。且浇筑普通混凝土层151可以分成至少两层一次浇筑,如先浇筑位于底下的第一层1511,参见图6,再在第一层1511顶部浇筑第二层1512,这种浇筑方式,能够将浇筑的第一层1511和底板11结合后一起作为下模板,用于承受后面的第二层1512的浇筑,这种方式可以使得底板11的厚度能够尽可能的减薄,能够减少钢材用量,同时还能够使得浇筑的密实度更高,压重效果以及对钢桥面板10的支撑能力更好。且浇筑至人孔91高度时,需要对人孔91进行封堵,可采用边封堵边浇筑的循环作业模式。And the side plate 9 is provided with a
如:所述普通混凝土层151分为两层施工,先在底板11上浇筑第一层1511,待第一层1511强度达标后,在第一层1511上浇筑第二层1512,在所述第二层1512浇筑过程中,当浇筑的普通混凝土的高度高于所述人孔91底部标高时,先封堵所述人孔91的底部的一部分,然后进行普通混凝土浇筑,普通混凝土至将从人孔91溢出时,再次向上对人孔91的一部分进行封堵,再进行普通混凝土浇筑,采用逐步向上封堵所述人孔91的方式进行普通混凝土的浇筑,直至所述第二层1512浇筑完成,再完全封堵所述人孔91;有效的利用了第一层1511普通混凝土的承载能力,使得较薄的底板11和第二加劲肋13仅需要能承受第一层1511普通混凝土的重量即可,第一层1511普通混凝土成型后与底板11形成的钢混结构,能够有效承受第二层1512普通混凝土和自密实水泥砂浆层152的总重量。将所述普通混凝土层151分为两层施工,使得所需底板11的厚度更薄,所需的第二加劲肋13的强度更小,能够节约钢材,同时使得底板11和第二加劲肋13的安装更加轻松。For example: the ordinary
待第二层1512强度达标后,在所述钢桥面板10对应于其U肋和U肋之间或U肋和桥面板纵梁18之间的上方开浇筑孔,通过浇筑孔浇筑自密实水泥砂浆层152,直至填满所述封闭箱式结构。其中,浇筑孔的大小为4-6cm,适宜为5cm,并设置排气管和浇注管,采用微膨胀自密实水泥砂浆,带压强灌注,保证压重箱内满灌。通过浇筑孔浇筑自密实水泥砂浆层152,能够更方便、快捷且高质量的填满封闭箱式结构,避免U肋和桥面板纵梁18的角落部位无法填充完全。这种通过人孔91配合小的浇筑孔的施工方式能够尽量减少对压重区构造的开设大量较大的浇筑口,保证压重区构造的完整性,提高压重区构造的质量。After the strength of the
本实施例所述钢桁梁斜拉桥的压重区的截面形式,结构简单,安装方便。该压重区构造更好的利用了钢桁梁的主体结构,只需增设底板11与侧板9连接桥面系横梁14、配合钢桥面板10形成整体封闭箱式结构作为压重区域,简化了压重区与钢桁梁的连接构造,且采用第一高强螺栓81和第二高强螺栓82连接,可分块安装,施工方便。且其结构受力明确,不改变钢桁梁的受力体系和受力性能,拉索力仍保持从弦杆向桥面传力途径。具有良好的经济性,相比传统压重箱,可以节约钢材40%以上。采用了两种压重材料,底层的普通混凝土层151的承载能力强,顶层的自密实水泥砂浆层152便于从顶板开小孔灌注,保证了密实性。且该压重区构造安全性强,普通混凝土层151的普通混凝土成型后和底板11形成整体,且有第一高强螺栓81和桥面系横梁14连接,即使第一高强螺栓81失效,该压重区构造也可有效支撑在桥面系横梁14的下翼板,不会脱落。且还具有免维护和耐久性强的特点,封闭箱式结构内通过普通混凝土和自密实水泥砂浆满灌,无需检修;钢桥面板10在封闭箱式结构、其内的普通混凝土层151和自密实水泥砂浆层152的支撑下,受力改善,耐久性加强。且封闭箱式结构的外表面光滑整洁,便于养护。The section form of the ballast area of the steel truss girder cable-stayed bridge described in this embodiment has a simple structure and is easy to install. The structure of the ballast area makes better use of the main structure of the steel truss girder. It only needs to add the
上述实施例1和实施例2中的双层四线铁路钢桁梁斜拉桥主梁构造,相比于传统将四线铁路置于同一层的钢桁梁截面,双层四线铁路正交异形板钢桁梁主梁截面可减少桁宽,最大程度的利用截面尺寸,减少用钢量。且可以实现客货分层形式,实现客货分流,减少其相互影响。中跨及边跨非压重段采用正交异形板,边跨压重段采用钢箱混凝土组合桥面结构的形式,解决了多线钢桁梁压重难题,压重结构与受力结构结合,经济性好,免于维护。钢箱可采用板厚10~12mm面板和8mm加劲肋,相比传统16mm桥面板+U肋+钢压重箱的结构,可节省钢材40%以上。钢箱混凝土组合桥面结构无需布置预应力,靠顶面钢桥面板10抵抗辅助墩的负弯矩效应,避免了混凝土桥面板开裂影响耐久性难题。采用顶面全焊接、侧面栓接横联6结构,避免了上层桥面螺栓掉落对下层铁路7安全的影响,又保证了安装便捷性。相比于平层结构及全钢桥面桁梁结构,刚度大,列车行驶性能优异。The main girder structure of the steel truss girder cable-stayed bridge for the double-layer four-track railway in the above-mentioned
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention should be included in the protection of the present invention. within range.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211154990.5A CN115559190B (en) | 2022-09-21 | 2022-09-21 | Main girder structure of double-layer four-wire railway steel truss girder cable-stayed bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211154990.5A CN115559190B (en) | 2022-09-21 | 2022-09-21 | Main girder structure of double-layer four-wire railway steel truss girder cable-stayed bridge |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115559190A true CN115559190A (en) | 2023-01-03 |
| CN115559190B CN115559190B (en) | 2025-07-22 |
Family
ID=84741620
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211154990.5A Active CN115559190B (en) | 2022-09-21 | 2022-09-21 | Main girder structure of double-layer four-wire railway steel truss girder cable-stayed bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115559190B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117385724A (en) * | 2023-10-08 | 2024-01-12 | 中铁大桥勘测设计院集团有限公司 | A bridge assembled ballast box and its parameter design method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202401384U (en) * | 2011-12-26 | 2012-08-29 | 中铁二院工程集团有限责任公司 | Ballasting structure of steel-truss cable-stayed bridge |
| CN202865731U (en) * | 2011-12-26 | 2013-04-10 | 中铁二院工程集团有限责任公司 | Saddle weight steel box structure of steel truss cable-stayed bridge |
| CN103225255A (en) * | 2013-04-27 | 2013-07-31 | 中铁二院工程集团有限责任公司 | Steel truss girder constitution for large-span six-line double-layered railway bridge |
| CN110359355A (en) * | 2019-07-31 | 2019-10-22 | 中铁二院工程集团有限责任公司 | Combine beam section in the case of rail-road mixed-arrangement-purlin |
| WO2019227516A1 (en) * | 2018-05-31 | 2019-12-05 | 中国铁道科学研究院铁道建筑研究所 | Steel-concrete composite beam structure suitable for heavy haul railway |
-
2022
- 2022-09-21 CN CN202211154990.5A patent/CN115559190B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202401384U (en) * | 2011-12-26 | 2012-08-29 | 中铁二院工程集团有限责任公司 | Ballasting structure of steel-truss cable-stayed bridge |
| CN202865731U (en) * | 2011-12-26 | 2013-04-10 | 中铁二院工程集团有限责任公司 | Saddle weight steel box structure of steel truss cable-stayed bridge |
| CN103225255A (en) * | 2013-04-27 | 2013-07-31 | 中铁二院工程集团有限责任公司 | Steel truss girder constitution for large-span six-line double-layered railway bridge |
| WO2019227516A1 (en) * | 2018-05-31 | 2019-12-05 | 中国铁道科学研究院铁道建筑研究所 | Steel-concrete composite beam structure suitable for heavy haul railway |
| CN110359355A (en) * | 2019-07-31 | 2019-10-22 | 中铁二院工程集团有限责任公司 | Combine beam section in the case of rail-road mixed-arrangement-purlin |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117385724A (en) * | 2023-10-08 | 2024-01-12 | 中铁大桥勘测设计院集团有限公司 | A bridge assembled ballast box and its parameter design method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115559190B (en) | 2025-07-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109958049B (en) | Modular steel-concrete combined small box girder simply-supported continuous bridge and construction method thereof | |
| CN109440625B (en) | Steel-concrete combined continuous rigid frame steel truss bridge | |
| CN106758856B (en) | The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block | |
| CN105002816B (en) | Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method | |
| CN106677049A (en) | Assembled steel-concrete combination structure bridge and construction method | |
| CN113481826B (en) | Prefabricated assembled corrugated steel web plate combined box girder | |
| CN114319065B (en) | Main beam unit with UHPC (ultra high performance polycarbonate) formwork structure, main beam structure and construction method of main beam structure | |
| CN106400666A (en) | Prestressed concrete-corrugated web steel box connecting beam hybrid beam structural system | |
| CN109082998A (en) | Integral prefabricated steel plate combination girder construction and construction method | |
| CN104762871A (en) | Prestressed concrete-steel tank beam bond beam continuous beam bridge | |
| CN104088221B (en) | A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck | |
| CN108221636B (en) | Steel-concrete composite beam bridge constructed by adopting bracket-free scheme for midspan and bridge forming method | |
| CN208668250U (en) | The good Mid and minor spans steel plate combination beam of cracking resistance | |
| CN109024219A (en) | A kind of prefabricated ultra-high performance concrete-normal concrete composite beam bridge girder construction and construction method | |
| CN106930181A (en) | A kind of simple-supported thencontinuous steel reinforced concrete combined bridge hogging moment area structure | |
| CN112962416A (en) | Steel plate girder bridge suitable for mountain area construction and construction method thereof | |
| CN113106845A (en) | Assembled tie bar rectangular steel tube concrete truss composite beam and construction method thereof | |
| CN106087711A (en) | Antinode work beam-steel concrete top board-external prestressing combines T-shaped simply supported beam | |
| CN114197321B (en) | Prestressed UHPC-NC combined continuous box girder bridge and construction method thereof | |
| CN110331664B (en) | Steel-concrete mixed continuous box girder bridge deck joint structure and construction method thereof | |
| WO2019227516A1 (en) | Steel-concrete composite beam structure suitable for heavy haul railway | |
| CN106835930B (en) | A kind of bolt connecting type steel concrete combination beam | |
| CN115559190A (en) | Main beam structure of double-layer four-line railway steel truss girder cable-stayed bridge | |
| CN219671054U (en) | An integrally hoisted, prefabricated steel-concrete composite small box beam | |
| CN115679794B (en) | Large cantilever ultra-wide UHPC box girder unit, large cantilever ultra-wide UHPC box girder bridge and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |