CN115538326A - Method for installing and correcting steel box girder of bridge - Google Patents
Method for installing and correcting steel box girder of bridge Download PDFInfo
- Publication number
- CN115538326A CN115538326A CN202211353690.XA CN202211353690A CN115538326A CN 115538326 A CN115538326 A CN 115538326A CN 202211353690 A CN202211353690 A CN 202211353690A CN 115538326 A CN115538326 A CN 115538326A
- Authority
- CN
- China
- Prior art keywords
- steel box
- box girder
- bridge
- support
- temporary support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开的是公路交通工程技术领域的一种大桥钢箱梁安装校正方法,包括以下步骤:先在相邻两个桥墩之间搭设临时支架,在临时支架顶部设置可移动的支撑车架,并在支撑车架上设置液压千斤顶,然后利用吊车将钢箱梁吊至桥墩上方,使其两端分别放置在两个临时支架上的液压千斤顶上,再然后移动支撑车架并调整液压千斤顶的高度,使钢箱梁底部标高达到设计标高,并与桥墩和其它钢箱梁单元对齐,最后对钢箱梁的拼接处进行焊接固定,将桥墩与钢箱梁进行安装固定,随后拆除临时支架。采用本发明的校正方法,可实现钢箱梁的快速校正和固定,校正过程简单方便,省时省力,可提高钢箱梁的安装质量。
The invention discloses a method for installing and correcting a steel box girder of a bridge in the technical field of highway traffic engineering, which includes the following steps: firstly, a temporary support is erected between two adjacent bridge piers, and a movable support frame is arranged on the top of the temporary support, And install a hydraulic jack on the supporting frame, and then use a crane to hoist the steel box girder above the pier, so that its two ends are respectively placed on the hydraulic jacks on the two temporary supports, and then move the supporting frame and adjust the position of the hydraulic jack. Height, so that the bottom elevation of the steel box girder reaches the design elevation, and is aligned with the bridge pier and other steel box girder units. Finally, the joints of the steel box girder are welded and fixed, the bridge pier and the steel box girder are installed and fixed, and then the temporary support is removed. By adopting the correction method of the present invention, rapid correction and fixation of the steel box girder can be realized, the correction process is simple and convenient, time-saving and labor-saving, and the installation quality of the steel box girder can be improved.
Description
技术领域technical field
本发明涉及公路交通工程技术领域,尤其涉及一种大桥钢箱梁安装校正方法。The invention relates to the technical field of highway traffic engineering, in particular to a method for installing and correcting a steel box girder of a bridge.
背景技术Background technique
在钢箱梁的吊装施工过程中,通常需要先架设临时支架,然后将钢箱梁吊至桥墩上方,并通过临时支架进行辅助支撑,期间需要对钢箱梁的位置进行校正,最后待钢箱梁的两端与桥墩固定后再拆掉临时支架。目前在对钢箱梁进行校正时,通常是直接对临时支架进行调整,如果临时支架高了就对其进行切割,如果矮了就加垫钢板。这种方式费力费材,且受人为因素影响较大,安装和校正质量难以保证。还有一些采用比较复杂的定位结构进行定位安装,比如专利文献(CN114351590A),公开了一种采用激光进行精确定位的方法,其实现方式是通过在相邻两节钢箱梁的端部之间分别设置激光发射端和激光接收端,然后通过PC端调整数控千斤顶,带动钢箱梁移动,使激光发射端和激光接收端对齐,从而实现钢箱梁的对齐安装。该方式存在的缺点是需要首先精确控制临时支架的高度,其次数控千斤顶只能实现上下方向的调整,左右方向无法调整,对前期吊装要求较高。During the hoisting construction of the steel box girder, it is usually necessary to erect temporary supports first, then hoist the steel box girder to the top of the pier, and use the temporary supports for auxiliary support. During this period, the position of the steel box girder needs to be corrected, and finally the steel box After the two ends of the beam are fixed to the piers, the temporary supports are removed. At present, when correcting the steel box girder, the temporary support is usually directly adjusted. If the temporary support is high, it is cut, and if it is short, a steel plate is added. This method is laborious and material-intensive, and is greatly affected by human factors, so it is difficult to guarantee the quality of installation and calibration. There are also some more complex positioning structures for positioning and installation, such as patent literature (CN114351590A), which discloses a method for precise positioning using lasers. Set up the laser emitting end and the laser receiving end respectively, and then adjust the CNC jack through the PC to drive the steel box girder to move, so that the laser emitting end and the laser receiving end are aligned, so as to realize the alignment and installation of the steel box girder. The disadvantage of this method is that the height of the temporary support needs to be accurately controlled first, and secondly, the CNC jack can only be adjusted in the up and down directions, and the left and right directions cannot be adjusted, which requires higher hoisting in the early stage.
发明内容Contents of the invention
为克服现有钢箱梁安装定位存在的上述不足,本发明所要解决的技术问题是:提供一种方便快捷的大桥钢箱梁安装校正方法。In order to overcome the above-mentioned shortcomings in the installation and positioning of the existing steel box girders, the technical problem to be solved by the present invention is to provide a convenient and fast installation and correction method for the steel box girders of the bridge.
本发明解决其技术问题所采用的技术方案是:The technical solution adopted by the present invention to solve its technical problems is:
大桥钢箱梁安装校正方法,包括以下步骤:The installation and correction method of the steel box girder of the bridge includes the following steps:
步骤一:在相邻两个桥墩之间搭设临时支架,临时支架的长度方向与钢箱梁的宽度方向一致;Step 1: Set up a temporary support between two adjacent piers, and the length direction of the temporary support is consistent with the width direction of the steel box girder;
步骤二:在临时支架顶部设置可沿临时支架长度方向移动的支撑车架,并在支撑车架上设置液压千斤顶;Step 2: Set a support frame that can move along the length direction of the temporary support on the top of the temporary support, and set a hydraulic jack on the support frame;
步骤三:升起液压千斤顶,使其顶部标高高于钢箱梁底部的设计标高,随后利用吊车将钢箱梁吊至桥墩上方,使其两端分别放置在两个临时支架上的液压千斤顶上;Step 3: Raise the hydraulic jack so that the top elevation is higher than the design elevation of the bottom of the steel box girder, and then use a crane to hoist the steel box girder above the pier so that its two ends are respectively placed on the hydraulic jacks on the two temporary supports ;
步骤四:移动支撑车架,使钢箱梁的安装位置与桥墩上的安装位置对齐,以及相邻两节钢箱梁端部的拼接面对齐;Step 4: Move the support frame so that the installation position of the steel box girder is aligned with the installation position on the bridge pier, and the splicing surfaces at the ends of two adjacent steel box girders are aligned;
步骤五:调整液压千斤顶,使钢箱梁底部标高达到设计标高,对钢箱梁的拼接处进行焊接固定,将桥墩与钢箱梁进行安装固定,随后拆除临时支架。Step 5: Adjust the hydraulic jack to make the bottom elevation of the steel box girder reach the design elevation, weld and fix the joints of the steel box girder, install and fix the pier and the steel box girder, and then remove the temporary support.
进一步的是,在步骤一中,所述临时支架采用贝蕾梁和贝蕾柱结构进行搭建。Further, in
进一步的是,在步骤二中,所述临时支架顶部设有滑板,所述支撑车架包括采用H型钢制作的支撑板,以及可转动的设置在支撑板底部并与滑板滚动连接的多个支撑辊,所述支撑板顶部设有用于承载液压千斤顶的枕木。Further, in
进一步的是,在步骤三中,采用至少三台吊车进行吊装,其中两台分别位于钢箱梁两端,一台位于钢箱梁侧面。Further, in step three, at least three cranes are used for hoisting, two of which are located at both ends of the steel box girder, and one is located at the side of the steel box girder.
进一步的是,在步骤四中,直接用吊车拉动钢箱梁,使支撑车架在临时支架上移动来调整钢箱梁的位置。Further, in
进一步的是,在步骤五中,在将钢箱梁的位置和标高校正完成后,先根据钢箱梁底部到临时支架顶部的距离设置固定节,将固定节支撑在钢箱梁底部和临时支架顶部之间,然后再进行钢箱梁的固定。Furthermore, in
本发明的有益效果是:通过在临时支架顶部设置可滑动的支撑车架,并在支撑车架顶部设置液压千斤顶来承载钢箱梁,在吊装过程中可通过移动支撑车架的位置和控制液压千斤顶升降来调整钢箱梁的位置,从而实现钢箱梁的校正和固定,整个校正过程简单方便,省时省力,可提高钢箱梁的安装质量。The beneficial effects of the present invention are: by setting a slidable support frame on the top of the temporary support, and setting a hydraulic jack on the top of the support frame to carry the steel box girder, the position of the support frame can be moved and the hydraulic pressure can be controlled during the hoisting process. The jack lifts to adjust the position of the steel box girder, so as to realize the correction and fixation of the steel box girder. The whole correction process is simple and convenient, saves time and effort, and can improve the installation quality of the steel box girder.
附图说明Description of drawings
图1是本发明钢箱梁的吊装过程示意图;Fig. 1 is the hoisting process schematic diagram of steel box girder of the present invention;
图2是本发明支撑车架支撑的结构示意图;Fig. 2 is a schematic structural view of the support frame of the present invention;
图3是本发明固定节支撑的结构示意图;Fig. 3 is a structural schematic diagram of the support of the fixed joint of the present invention;
图中标记为,1-临时支架,2-支撑车架,3-固定节,4-钢箱梁,5-桥墩,6-吊车,11-滑板,12-贝蕾柱,13-贝蕾梁,21-液压千斤顶,22-支撑板,23-支撑辊,24-枕木。Marked in the picture, 1-Temporary support, 2-Support frame, 3-Fixed joint, 4-Steel box girder, 5-Pier, 6-Crane, 11-Skateboard, 12-Berry column, 13-Berry beam , 21-hydraulic jack, 22-support plate, 23-support roller, 24-crossties.
具体实施方式detailed description
下面结合附图对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings.
本发明的大桥钢箱梁安装校正方法,包括以下步骤:The bridge steel box girder installation correction method of the present invention comprises the following steps:
步骤一:在相邻两个桥墩5之间搭设临时支架1,临时支架1的长度方向与钢箱梁4的宽度方向一致;Step 1: Set up a
步骤二:在临时支架1顶部设置可沿临时支架1长度方向移动的支撑车架2,并在支撑车架2上设置液压千斤顶21;Step 2: Set a
步骤三:升起液压千斤顶21,使其顶部标高高于钢箱梁4底部的设计标高,随后利用吊车6将钢箱梁4吊至桥墩5上方,使其两端分别放置在两个临时支架1上的液压千斤顶21上;Step 3: Raise the
步骤四:移动支撑车架2,使钢箱梁4的安装位置与桥墩5上的安装位置对齐,以及相邻两节钢箱梁4端部的拼接面对齐;Step 4: Move the
步骤五:调整液压千斤顶21,使钢箱梁4底部标高达到设计标高,对钢箱梁4的拼接处进行焊接固定,将桥墩5与钢箱梁4进行安装固定,随后拆除临时支架1。Step 5: Adjust the
传统的临时支架一般是和桥墩设置在一起的,导致临时支架与钢箱梁接触面积较小,调整空间有限,如图1所示,本发明将临时支架1设置在桥墩5中间,可以对钢箱梁4的整个端部进行支撑,且具有较大的空间用于移动调整钢箱梁4的位置。在搭建临时支架1时,最好采用贝蕾梁13和贝蕾柱12的结构形式进行搭建,如图2所示,可保证临时支架1顶部具有较大的跨度和稳定性,便于通过支撑车架2设置多个液压千斤顶21来对钢箱梁4端部进行支撑。在吊装钢箱梁4之前,需要先升起液压千斤顶21,使钢箱梁4放置到临时支架1上,而又不与桥墩5接触,便于后续校正钢箱梁4的位置。在校正过程中,钢箱梁4在平面和高度上的位置可同步调整,也可根据钢箱梁4的实际情况选择调整的先后顺序。相比现有通过吊车来调整钢箱梁位置的方案,本发明利用支撑车架2和液压千斤顶21来承载钢箱梁4,可实现平面和高度位置上的调整,更容易在短时间内完成钢箱梁4的校正工作。The traditional temporary support is generally set together with the bridge pier, resulting in a small contact area between the temporary support and the steel box girder, and limited adjustment space. As shown in Figure 1, the present invention arranges the
为了使支撑车架2能够在临时支架1顶部平稳运行,在所述临时支架1顶部设有滑板11。对于支撑车架2,本发明的优选方案是采用H型钢来制作支撑板22,使其具有较高的结构强度,不容易发生变形,然后在支撑板22底部设置多个可转动的支撑辊23来实现支撑车架2与滑板11的滚动连接,支撑辊23为长条形,其长度可与支撑板22的宽度相当,以便增大与滑板11的接触面积,使受力分散,保证支撑的稳定性。所述支撑板22顶部还设有用于承载液压千斤顶21的枕木24,设置枕木24可起到一定的缓冲作用,避免吊装过程中的刚性冲击损坏液压千斤顶21或支撑车架2。In order to make the supporting
在用吊车6吊装钢箱梁4的过程中,应至少采用三台吊车6进行吊装,其中两台分别位于钢箱梁4两端,一台位于钢箱梁4侧面,并且应保证吊车6都位于坚固的地面上,保证吊装的安全性。端部的两台吊车6能很好的将钢箱梁4的端部对齐支撑车架2,而侧面的吊车6则能很好的控制钢箱梁4前后移动,因为本发明的支撑车架2可在宽度方向和高度方向上调整钢箱梁4的位置,在长度方向上的调整就需要在吊装过程中利用侧面的吊车6来实现。In the process of hoisting the
当需要在宽度方向上调整钢箱梁4的位置时,可利用额外的机器来推动支撑车架2移动,从而带动钢箱梁4移动。更优选的方式是直接用吊车6拉动钢箱梁4,使钢箱梁4带动支撑车架2在临时支架1上移动来调整钢箱梁4的位置,更加的方便快捷。When the position of the
如图3所示,在将钢箱梁4的位置和标高校正完成后,可先根据钢箱梁4底部到临时支架1顶部的距离设置固定节3,然后将固定节3支撑在钢箱梁4底部和临时支架1顶部之间,最后再进行钢箱梁4的固定。固定节3可采用钢筒段或H型钢段,其高度与钢箱梁4底部距离临时支架1顶部的高度相同,设置固定节3主要是为了对钢箱梁4起到固定作用,避免在后续施工过程中因支撑车架2移动而使钢箱梁4位置出现偏差。As shown in Figure 3, after correcting the position and elevation of the
本发明通过在临时支架1顶部设置可滑动的支撑车架2,并在支撑车架2顶部设置液压千斤顶21来承载钢箱梁4,在吊装过程中可通过移动支撑车架2的位置和控制液压千斤顶21升降来调整钢箱梁4的位置,从而实现钢箱梁4的校正和固定,整个校正过程简单方便,省时省力,可提高钢箱梁4的安装质量,具有很好的实用新和应用价值。In the present invention, a
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211353690.XA CN115538326A (en) | 2022-11-01 | 2022-11-01 | Method for installing and correcting steel box girder of bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211353690.XA CN115538326A (en) | 2022-11-01 | 2022-11-01 | Method for installing and correcting steel box girder of bridge |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115538326A true CN115538326A (en) | 2022-12-30 |
Family
ID=84717830
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211353690.XA Pending CN115538326A (en) | 2022-11-01 | 2022-11-01 | Method for installing and correcting steel box girder of bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115538326A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117418466A (en) * | 2023-10-13 | 2024-01-19 | 武汉一冶钢结构有限责任公司 | An adjustable device and correction method for longitudinal slope sliding in steel box girder construction |
| CN120537209A (en) * | 2025-07-28 | 2025-08-26 | 保利长大工程有限公司 | A temporary pier support for special environments |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20040012295A (en) * | 2002-08-02 | 2004-02-11 | 김정현 | Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent |
| CN102587291A (en) * | 2012-03-27 | 2012-07-18 | 中交四航局第一工程有限公司 | Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder |
| CN103266573A (en) * | 2013-06-17 | 2013-08-28 | 中铁山桥集团有限公司 | Self-anchored suspension bridge steel box girder three-slideway synchronous jacking construction method |
| CN105696469A (en) * | 2015-11-16 | 2016-06-22 | 中铁四局集团有限公司 | A Construction Method for Pushing and Installing Steel Box Girder with Long-span and Two-way Longitudinal Slope of Extra-Large Bridge |
| CN107254849A (en) * | 2017-07-14 | 2017-10-17 | 中国冶集团有限公司 | Steel box-girder installation method under a kind of clear height constrained state |
| CN212404839U (en) * | 2020-04-07 | 2021-01-26 | 中铁大桥科学研究院有限公司 | Device for assembling steel box girders of swivel cable-stayed bridge |
| CN114045752A (en) * | 2021-11-15 | 2022-02-15 | 中国建筑土木建设有限公司 | Floating crane aerial positioning cantilever assembling method for large-section steel truss box girder |
| CN216684227U (en) * | 2022-01-10 | 2022-06-07 | 重庆交通职业学院 | Temporary supporting equipment with good stability for box girder construction |
-
2022
- 2022-11-01 CN CN202211353690.XA patent/CN115538326A/en active Pending
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20040012295A (en) * | 2002-08-02 | 2004-02-11 | 김정현 | Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent |
| CN102587291A (en) * | 2012-03-27 | 2012-07-18 | 中交四航局第一工程有限公司 | Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder |
| CN103266573A (en) * | 2013-06-17 | 2013-08-28 | 中铁山桥集团有限公司 | Self-anchored suspension bridge steel box girder three-slideway synchronous jacking construction method |
| CN105696469A (en) * | 2015-11-16 | 2016-06-22 | 中铁四局集团有限公司 | A Construction Method for Pushing and Installing Steel Box Girder with Long-span and Two-way Longitudinal Slope of Extra-Large Bridge |
| CN107254849A (en) * | 2017-07-14 | 2017-10-17 | 中国冶集团有限公司 | Steel box-girder installation method under a kind of clear height constrained state |
| CN212404839U (en) * | 2020-04-07 | 2021-01-26 | 中铁大桥科学研究院有限公司 | Device for assembling steel box girders of swivel cable-stayed bridge |
| CN114045752A (en) * | 2021-11-15 | 2022-02-15 | 中国建筑土木建设有限公司 | Floating crane aerial positioning cantilever assembling method for large-section steel truss box girder |
| CN216684227U (en) * | 2022-01-10 | 2022-06-07 | 重庆交通职业学院 | Temporary supporting equipment with good stability for box girder construction |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117418466A (en) * | 2023-10-13 | 2024-01-19 | 武汉一冶钢结构有限责任公司 | An adjustable device and correction method for longitudinal slope sliding in steel box girder construction |
| CN120537209A (en) * | 2025-07-28 | 2025-08-26 | 保利长大工程有限公司 | A temporary pier support for special environments |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109629441B (en) | PLC multipoint synchronous three-dimensional hydraulic bridge pushing system and pushing method | |
| CN116335149B (en) | A construction method for small-scale ultra-deep foundation pits using a pre-installed steel support system | |
| CN102587291A (en) | Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder | |
| CN108590198B (en) | A steel truss sliding unit with columns and its cumulative sliding installation method | |
| CN219793684U (en) | Long-distance pushing steel box girder crossing existing highway girder falling guide device | |
| WO2021093732A1 (en) | Displacement inclination rectification method for building | |
| CN110723677B (en) | Precast Beam Assisted Lifting Trolley | |
| CN115710862A (en) | Steel girder construction accurate installation system and construction method | |
| CN111119071A (en) | Construction method for assembling precast concrete segment box girder | |
| CN110565983B (en) | Building jacking and shifting method | |
| CN222435958U (en) | Temporary support frame used in the top-pushing of the existing station building expansion | |
| CN115961549A (en) | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge | |
| CN117145268A (en) | Tire frame support system for steel structure sliding and steel structure construction method | |
| CN117051703A (en) | A small-section steel box beam installation structure and its construction technology | |
| CN111809529A (en) | Installation system for steel truss girder bridges | |
| CN115928583A (en) | On-site temporary assembly and erection method of multi-segment steel box girder of cable-stayed bridge spanning multi-storey highway | |
| CN112853998B (en) | An assembly-integrated bridge erecting machine suitable for small and medium spans and a construction method thereof | |
| CN212688731U (en) | Installation system for steel truss girder bridges | |
| CN214489421U (en) | Three-dimensional adjustable device | |
| CN111926714B (en) | Installation method of steel truss girder bridge | |
| CN115491993B (en) | A method for hoisting and installing small longitudinal and transverse sections of wide steel box beams | |
| CN112921718B (en) | Light rail track beam continuous jacking installation device and its use method | |
| CN108755384A (en) | A kind of belt track free cantilever erection steel girder bridge and its construction method | |
| CN211113199U (en) | Pre-assembly equipment for segmental beam | |
| CN211689964U (en) | Closure system for main beam of arch tower cable-stayed bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |
