CN115450125A - High pier capping beam integrated construction platform installing and dismantling method - Google Patents

High pier capping beam integrated construction platform installing and dismantling method Download PDF

Info

Publication number
CN115450125A
CN115450125A CN202211174522.4A CN202211174522A CN115450125A CN 115450125 A CN115450125 A CN 115450125A CN 202211174522 A CN202211174522 A CN 202211174522A CN 115450125 A CN115450125 A CN 115450125A
Authority
CN
China
Prior art keywords
bearing beam
platform
construction
hoop
lifting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211174522.4A
Other languages
Chinese (zh)
Inventor
陈会景
周建光
高永吉
孙引浩
王永锋
姚建明
刘强华
欧阳冰
魏琛宇
徐鑫
刘砺
成龙
邓伟
熊礼
曹璐
朱晓腾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No1 Engineering Corp Ltd Of Cr20g
China Railway 20th Bureau Group Corp
Original Assignee
No1 Engineering Corp Ltd Of Cr20g
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No1 Engineering Corp Ltd Of Cr20g, China Railway 20th Bureau Group Corp filed Critical No1 Engineering Corp Ltd Of Cr20g
Priority to CN202211174522.4A priority Critical patent/CN115450125A/en
Publication of CN115450125A publication Critical patent/CN115450125A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种高墩盖梁一体化施工平台安拆方法,属于盖梁施工技术领域,包括以下步骤:S1、平整墩柱底部地面;S2、平台升降装置的安装;S3、施工作业平台的组装;S4、抱箍安装;S5、平台升降装置的拆除;S6、盖梁施工;S7、平台升降装置的再安装;S8、抱箍拆除;S9、施工作业平台拆除;S10、平台升降装置的再拆除。本发明高墩盖梁一体化平台安拆方法,整个安拆过程作业人员均处于较安全的位置,安全有保障,降低了盖梁施工作业平台安装时存在的高空作业风险,同时也大大提高了施工作业平台的安装质量和安拆速度,降低了工程成本。

Figure 202211174522

The invention discloses a method for installing and dismantling a high pier-cover-beam integrated construction platform, belonging to the technical field of cover-beam construction, comprising the following steps: S1, leveling the ground at the bottom of a pier column; S2, installing a platform lifting device; S3, construction work platform S4, hoop installation; S5, platform lifting device removal; S6, cover beam construction; S7, platform lifting device reinstallation; S8, hoop removal; S9, construction work platform removal; S10, platform lifting device to dismantle. The installation and disassembly method of the high-pier-cover-beam integrated platform of the present invention ensures that the operating personnel are in a relatively safe position during the entire installation and disassembly process, and the safety is guaranteed. The installation quality and installation and disassembly speed of the construction work platform reduce the engineering cost.

Figure 202211174522

Description

一种高墩盖梁一体化施工平台安拆方法A method for installing and dismantling an integrated construction platform of high pier cover and beam

技术领域technical field

本发明属于盖梁施工技术领域,更具体地,涉及一种高墩盖梁一体化施工平台安拆方法。The invention belongs to the technical field of cover beam construction, and more specifically relates to a method for installing and dismantling a high pier cover beam integrated construction platform.

背景技术Background technique

盖梁作为桥梁结构中支承、分布和传递上部结构荷载的重要构件,在整个桥梁结构中起着承上启下的作用。抱箍法和支架法是目前盖梁施工工艺中使用较多的两种施工方法。As an important component of the bridge structure to support, distribute and transmit the load of the superstructure, the cap beam plays a role of connecting the preceding and the following in the entire bridge structure. The hoop method and the bracket method are two construction methods that are widely used in the current cap beam construction technology.

抱箍法是在墩柱上的适当部位安装抱箍,抱箍安装完成后,依次安装承重梁、分配梁、组合钢模板、人员作业踏板以及安全护栏等组成构件,安装完成后以此作为盖梁施工的作业平台。在整个施工作业平台安装过程中,受施工工序限制,人员作业踏板以及安全护栏需要在承重梁、分配梁安装完成后才能安装,因此在抱箍、承重梁、分配梁安装时,作业人员如果在没有做好安全保障措施的情况下作业,存在较大的高处坠落、物体打击的风险,尤其在盖梁比较高的情况下,这种风险更加突出。与此同时,在高墩盖梁施工作业平台安装时,由于盖梁高度较高,受到天气、机械、作业人员心理状况等各种因素影响,施工作业平台的安装质量以及安拆速度都得不到保障,也在一定程度上加大了高空作业的风险。The hoop method is to install the hoop at the appropriate position on the pier column. After the hoop is installed, install the load-bearing beam, distribution beam, combined steel formwork, personnel operation pedal and safety guardrail in sequence. After the installation is completed, use it as a cover Work platform for beam construction. During the installation process of the entire construction work platform, limited by the construction process, the personnel operating pedals and safety guardrails need to be installed after the load-bearing beams and distribution beams are installed. There is a greater risk of falling from high places and being hit by objects when working without safety measures, especially when the cover beam is relatively high, this risk is more prominent. At the same time, during the installation of the high pier cover beam construction work platform, due to the high height of the cover beam, it is affected by various factors such as weather, machinery, and the psychological state of the operators, so the installation quality and installation speed of the construction work platform have to be limited. To a certain extent, it also increases the risk of working at heights.

支架法是采用钢管搭设支架,支架上搭设盖梁施工作业平台。支架法施工一般对地基的承载力要求较高,对地基的处理要花费较多人力物力。如果对地基的处理不当,可能造成支架整体下沉或不均匀下沉,严重影响盖梁的施工安全和质量;支架法用于高墩盖梁施工时,支架搭设时间较长,且必须对支架进行预压以消除非弹性变形和弹性变形,需要消耗大量、人力、物力,工程成本较高。The support method is to use steel pipes to set up a support, and a cover beam construction work platform is set up on the support. The construction of the bracket method generally has higher requirements on the bearing capacity of the foundation, and the treatment of the foundation requires more manpower and material resources. If the foundation is not handled properly, it may cause the support to sink as a whole or unevenly, which will seriously affect the construction safety and quality of the cover beam; Preloading to eliminate inelastic deformation and elastic deformation requires a lot of labor, manpower, and material resources, and the project cost is relatively high.

发明内容Contents of the invention

针对现有技术的缺陷,本发明的目的在于提供一种高墩盖梁一体化平台安拆方法,旨在解决现有高墩盖梁施工过程中高空作业风险大、安装质量低、拆装速度慢、工程成本较高的问题。Aiming at the defects of the prior art, the purpose of the present invention is to provide a method for installing and dismantling an integrated platform of high pier and cover beams, which aims to solve the problems of high risk of high-altitude operations, low installation quality, and speed of disassembly and assembly during the construction process of existing high pier and cover beams. Slow and high engineering cost.

为实现上述目的,本发明提供了一种高墩盖梁一体化施工平台安拆方法,包括以下步骤:In order to achieve the above object, the present invention provides a method for installing and dismantling a high pier-cover-beam integrated construction platform, comprising the following steps:

S1、平整墩柱底部地面;S1. Level the ground at the bottom of the pier column;

S2、平台升降装置的安装:所述平台升降装置包括顶承重梁、底承重梁以及电动葫芦,所述电动葫芦安装在所述顶承重梁上,用于所述顶承重梁分别和所述底承重梁与抱箍的连接拆装;S2. Installation of the platform lifting device: the platform lifting device includes a top load-bearing beam, a bottom load-bearing beam and an electric hoist. The electric hoist is installed on the top load-bearing beam for the top load-bearing beam and the bottom load-bearing beam respectively The connection and disassembly of the load-bearing beam and the hoop;

顶承重梁通过吊具平稳吊放在墩柱上端面并固定,底承重梁通过电动葫芦和顶承重梁连接并位于墩柱底部地面上;The top load-bearing beam is stably hoisted and fixed on the upper end of the pier column by the spreader, and the bottom load-bearing beam is connected with the top load-bearing beam through an electric hoist and is located on the ground at the bottom of the pier column;

S3、施工作业平台的组装:所述施工作业平台包括有水平放置在底承重梁上的主承重梁,所述底承重梁和所述主承重梁的长度方向相互垂直,所述主承重梁之间连接有分配梁,所述分配梁位于所述主承重梁上方,所述分配梁上方固定有人员作业踏板,所述人员作业踏板四周设有安全护栏;S3. Assembly of the construction work platform: the construction work platform includes a main load-bearing beam horizontally placed on the bottom load-bearing beam, the length directions of the bottom load-bearing beam and the main load-bearing beam are perpendicular to each other, and the main load-bearing beam A distribution beam is connected between them, the distribution beam is located above the main load-bearing beam, and a personnel operation pedal is fixed above the distribution beam, and safety guardrails are provided around the personnel operation pedal;

S4、抱箍安装:通过平台升降装置将施工作业平台上升至设计标高,抱箍通过电动葫芦上升至设计标高,抱箍牛腿和主承重梁下端面贴合并和墩柱外壁抱紧固定用于支撑施工作业平台;S4. Hoop installation: The construction work platform is raised to the design elevation through the platform lifting device, the hoop is raised to the design elevation through the electric hoist, the hoop corbel is attached to the lower end surface of the main load-bearing beam and is tightly fixed to the outer wall of the pier column for Support construction work platform;

S5、平台升降装置的拆除:底承重梁通过电动葫芦下降至地面拆除,顶承重梁通过吊具进行拆除;S5. Removal of the platform lifting device: the bottom load-bearing beam is lowered to the ground by the electric hoist and removed, and the top load-bearing beam is removed by the spreader;

S6、盖梁施工:搭建盖梁底模,完成盖梁施工;S6. Covering beam construction: build the bottom formwork of the cover beam, and complete the construction of the cover beam;

S7、平台升降装置的再安装:顶承重梁通过吊具放置在盖梁顶,顶承重梁通过电动葫芦将底承重梁上升拖住施工作业平台底部;S7. Reinstallation of the platform lifting device: the top load-bearing beam is placed on the top of the cover beam through the spreader, and the top load-bearing beam lifts the bottom load-bearing beam to the bottom of the construction work platform through the electric hoist;

S8、抱箍拆除:通过登高车将作业人员运输至抱箍拆除位置,将抱箍拆除后,通过电动葫芦将抱箍下降至地面;S8. Removal of the hoop: transport the operator to the hoop removal position by the climbing car, and after the hoop is removed, lower the hoop to the ground through the electric hoist;

S9、施工作业平台拆除:作业人员通过平台升降装置将施工作业平台下降至地面,对主承重梁、分配梁、人员作业踏板和安全护栏进行拆除;S9. Removal of the construction operation platform: the operator lowers the construction operation platform to the ground through the platform lifting device, and removes the main load-bearing beam, distribution beam, personnel operation pedal and safety guardrail;

S10、平台升降装置的再拆除:作业人员将底承重梁进行拆除,采用登高车将作业人员运输至拆除位置对电动葫芦和顶承重梁进行拆除,并采用吊具将拆除后的电动葫芦和顶承重梁运输至地面;重复步骤S1-S10,完成下一盖梁施工。S10. Re-removal of the platform lifting device: the operator removes the bottom load-bearing beam, uses a climbing vehicle to transport the operator to the removal position, removes the electric hoist and the top load-bearing beam, and uses a spreader to remove the removed electric hoist and the top load-bearing beam. Transport the load-bearing beam to the ground; repeat steps S1-S10 to complete the construction of the next cover beam.

更进一步地,所述顶承重梁四角和所述底承重梁两端均设有用于安装电动葫芦的吊环,所述顶承重梁中间设有可拆卸挂板,所述可拆卸挂板连接用于所述抱箍拆装的电动葫芦。Further, the four corners of the top load-bearing beam and the two ends of the bottom load-bearing beam are provided with lifting rings for installing electric hoists, and a detachable hanging plate is provided in the middle of the top load-bearing beam, and the detachable hanging plate is connected for The electric hoist with the hoop disassembled.

更进一步地,所述S7具体为:将可拆卸挂板拆除后,通过吊具将顶承重梁放置在盖梁顶上,顶承重梁一侧通过电动葫芦和抱箍连接,用于抱箍拆除下降至地面;顶承重梁另一侧通过两个电动葫芦连接底承重梁用于抱箍拆除时支撑施工作业平台。Furthermore, the S7 is specifically: after the detachable hanging plate is removed, the top load-bearing beam is placed on the top of the cover beam through a spreader, and one side of the top load-bearing beam is connected by an electric hoist and a hoop for removal of the hoop Lower to the ground; the other side of the top load-bearing beam is connected to the bottom load-bearing beam through two electric hoists to support the construction work platform when the hoop is removed.

更进一步地,所述步骤S3包括:Further, the step S3 includes:

S31、安装主承重梁:主承重梁位于底承重梁上且垂直底承重梁长度方向放置;主承重梁上均布有分配梁,分配梁垂直主承重梁长度方向固定设置;S31. Install the main load-bearing beam: the main load-bearing beam is located on the bottom load-bearing beam and placed perpendicular to the length direction of the bottom load-bearing beam; distribution beams are evenly distributed on the main load-bearing beam, and the distribution beam is fixedly arranged vertically to the length direction of the main load-bearing beam;

S32、固定人员作业踏板:人员作业踏板固定在分配梁上;S32. Fixed personnel operation pedal: the personnel operation pedal is fixed on the distribution beam;

S33、安全护栏的安装:人员作业踏板四周固定安全护栏。S33. Installation of safety guardrails: fix safety guardrails around the personnel operation pedal.

更进一步地,所述顶承重梁为王字型,所述底承重梁为一字型。Furthermore, the top load-bearing beam is king-shaped, and the bottom load-bearing beam is straight-shaped.

更进一步地,所述盖梁顶上设有支座垫石或预埋件导致所述顶承重梁无法平稳放置,所述顶承重梁可由两根平行设置的底承重梁替换。Furthermore, the top load-bearing beam cannot be placed stably due to the support pad stone or embedded parts on the top of the cover beam, and the top load-bearing beam can be replaced by two bottom load-bearing beams arranged in parallel.

总体而言,通过本发明所构思的以上技术方案与现有技术相比,具有以下有益效果:Generally speaking, compared with the prior art, the above technical solution conceived by the present invention has the following beneficial effects:

1、通过平台升降装置可使施工作业平台的安装、拆除均在地面进行,安装完成后提升至设计标高;抱箍利用登高车和升降装置进行安装和拆除。整个安拆过程作业人员始终处在较安全的位置,安全有保障,较大程度地降低了盖梁施工作业平台安装时存在的高空作业风险;1. Through the platform lifting device, the installation and dismantling of the construction work platform can be carried out on the ground, and after the installation is completed, it can be lifted to the design elevation; the hoop can be installed and dismantled by the climbing car and the lifting device. During the whole installation and dismantling process, the operators are always in a relatively safe position, and the safety is guaranteed, which greatly reduces the risk of working at heights during the installation of the cover beam construction work platform;

2、此外,地面安装施工作业平台可减小天气、机械、作业人员心理状况等各种因素对施工作业平台的安装质量以及安拆速度的影响,提高了安装质量和安拆速度;2. In addition, the installation of the construction work platform on the ground can reduce the influence of various factors such as weather, machinery, and psychological conditions of the operators on the installation quality and installation and disassembly speed of the construction work platform, and improve the installation quality and installation and disassembly speed;

3、而且,对地基承载力要求较小,仅需对墩柱底部地面进行简单平整即可,节省人力物力,降低了工程成本。3. Moreover, the requirements for the bearing capacity of the foundation are small, and only the ground at the bottom of the pier column needs to be simply leveled, which saves manpower and material resources, and reduces the engineering cost.

附图说明Description of drawings

图1是本发明平台升降装置的结构示意图;Fig. 1 is the structural representation of platform lifting device of the present invention;

图2是本发明施工作业平台的安装示意图;Fig. 2 is the installation sketch map of construction operation platform of the present invention;

图3是本发明施工作业平台的拆除示意图。Fig. 3 is a schematic diagram of dismantling the construction work platform of the present invention.

附图中各数字标记对应的结构为:1-顶承重梁,2-可拆卸挂板,3-吊环,4-底承重梁,5-电动葫芦,6-施工作业平台,7-抱箍,8-主承重梁,9-分配梁,10-安全护栏,11-人员作业踏板,12-盖梁底模,13-墩柱,14-盖梁。The structures corresponding to the numbers in the drawings are: 1-top load-bearing beam, 2-detachable hanging plate, 3-hanging ring, 4-bottom load-bearing beam, 5-electric hoist, 6-construction work platform, 7-clamp hoop, 8-main load-bearing beam, 9-distribution beam, 10-safety guardrail, 11-personnel operation pedal, 12-cover beam base form, 13-pier column, 14-cover beam.

具体实施方式detailed description

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

参阅图1至图3,本发明提供一种高墩盖梁一体化施工平台安拆方法,包括以下步骤:Referring to Fig. 1 to Fig. 3, the present invention provides a method for installing and dismantling an integrated construction platform of high piers and cap beams, comprising the following steps:

S1、平整墩柱13底部地面;S1, leveling the ground at the bottom of the pier column 13;

S2、平台升降装置的安装:平台升降装置包括顶承重梁1、底承重梁4和电动葫芦5,顶承重梁1上安装有电动葫芦5,电动葫芦的输出端和底承重梁4、抱箍7连接,用于底承重梁4和抱箍7的拆装;具体的安装步骤为:顶承重梁1通过吊具平稳吊放在墩柱13上端面并固定,底承重梁4通过电动葫芦5和顶承重梁1连接并位于墩柱13底部地面上,在本实施例中,顶承重梁1为王字型,底承重梁4为一字型,一根顶承重梁对应两根底承重梁。S2. Installation of platform lifting device: platform lifting device includes top load-bearing beam 1, bottom load-bearing beam 4 and electric hoist 5, electric hoist 5 is installed on top load-bearing beam 1, output end of electric hoist and bottom load-bearing beam 4, hoop 7 connection, used for the disassembly and assembly of the bottom load-bearing beam 4 and the hoop 7; the specific installation steps are: the top load-bearing beam 1 is stably hoisted on the upper end surface of the pier column 13 by the spreader and fixed, and the bottom load-bearing beam 4 is passed through the electric hoist 5 It is connected with the top load-bearing beam 1 and is located on the ground at the bottom of the pier column 13. In this embodiment, the top load-bearing beam 1 is king-shaped, and the bottom load-bearing beam 4 is in-line shape, and one top load-bearing beam corresponds to two bottom load-bearing beams.

S3、施工作业平台的组装:施工作业平台6包括有水平放置在底承重梁4上的主承重梁8,底承重梁4和主承重梁8的长度方向相互垂直,主承重梁8之间通过分配梁9连接,分配梁9上方固定有人员作业踏板11,人员作业踏板11四周设有安全护栏10,并采取螺栓、焊接或其他固定措施使其形成一个整体;其具体的组装顺序为:S3. Assembly of the construction work platform: the construction work platform 6 includes a main load-bearing beam 8 placed horizontally on the bottom load-bearing beam 4, the length directions of the bottom load-bearing beam 4 and the main load-bearing beam 8 are perpendicular to each other, and the main load-bearing beams 8 pass through The distribution beam 9 is connected, and a personnel operation pedal 11 is fixed above the distribution beam 9, and a safety guardrail 10 is provided around the personnel operation pedal 11, and bolts, welding or other fixing measures are taken to form a whole; the specific assembly sequence is:

S31、安装主承重梁:主承重梁8位于底承重梁4上且垂直底承重梁4长度方向放置;主承重梁8上均布有分配梁9,分配梁9垂直主承重梁8长度方向固定设置;S31. Install the main load-bearing beam: the main load-bearing beam 8 is located on the bottom load-bearing beam 4 and placed perpendicular to the length direction of the bottom load-bearing beam 4; the distribution beam 9 is evenly distributed on the main load-bearing beam 8, and the distribution beam 9 is fixed vertically to the length direction of the main load-bearing beam 8 set up;

S32、固定人员作业踏板:人员作业踏板11通过焊接、螺栓等方式固定在分配梁上;S32. Fixing the personnel operation pedal: the personnel operation pedal 11 is fixed on the distribution beam by means of welding or bolts;

S33、安全护栏的安装:人员作业踏板11通过焊接、螺栓等方式固定安全护栏10;S33. Installation of the safety guardrail: the personnel operation pedal 11 fixes the safety guardrail 10 by means of welding, bolts, etc.;

S4、抱箍安装:通过电动葫芦5将施工作业平台6上升至设计标高,抱箍7也通过电动葫芦5上升至设计标高,抱箍牛腿和主承重梁8下端面贴合并和墩柱13外壁抱紧固定用于支撑施工作业平台;S4. Hoop installation: the construction work platform 6 is raised to the design elevation through the electric hoist 5, and the hoop 7 is also raised to the design elevation through the electric hoist 5, and the hoop corbel and the lower end surface of the main load-bearing beam 8 are attached and merged with the pier column 13 The outer wall is tightly fixed to support the construction work platform;

S5、平台升降装置的拆除:底承重梁4通过电动葫芦5下降至地面拆除,顶承重梁1通过吊具进行拆除;S5. Removal of the platform lifting device: the bottom load-bearing beam 4 is lowered to the ground by the electric hoist 5 and removed, and the top load-bearing beam 1 is removed by the spreader;

S6、盖梁施工;搭建盖梁底模12,完成盖梁14施工;S6, cover beam construction; build cover beam bottom mold 12, finish cover beam 14 construction;

S7、平台升降装置的再安装;顶承重梁1通过吊具放置在盖梁14顶,顶承重梁1通过电动葫芦5将底承重梁4上升拖住施工作业平台6底部;S7. Reinstallation of the platform lifting device; the top load-bearing beam 1 is placed on the top of the cover beam 14 through the spreader, and the top load-bearing beam 1 lifts the bottom load-bearing beam 4 to the bottom of the construction work platform 6 through the electric hoist 5;

S8、抱箍拆除:通过登高车将作业人员运输至抱箍拆除位置,将抱箍拆除后,通过电动葫芦将抱箍下降至地面;S8. Removal of the hoop: transport the operator to the hoop removal position by the climbing car, and after the hoop is removed, lower the hoop to the ground through the electric hoist;

S9、施工作业平台拆除:作业人员通过平台升降装置将施工作业平台下降至地面,对主承重梁、分配梁、人员作业踏板和安全护栏进行拆除;S9. Removal of the construction operation platform: the operator lowers the construction operation platform to the ground through the platform lifting device, and removes the main load-bearing beam, distribution beam, personnel operation pedal and safety guardrail;

S10、平台升降装置的再拆除:作业人员将底承重梁进行拆除,采用登高车将作业人员运输至拆除位置对电动葫芦和顶承重梁进行拆除,并采用吊具将拆除后的电动葫芦和顶承重梁运输至地面;重复步骤S1-S10,完成下一盖梁施工。S10. Re-removal of the platform lifting device: the operator removes the bottom load-bearing beam, uses a climbing vehicle to transport the operator to the removal position, removes the electric hoist and the top load-bearing beam, and uses a spreader to remove the removed electric hoist and the top load-bearing beam. Transport the load-bearing beam to the ground; repeat steps S1-S10 to complete the construction of the next cover beam.

为了方便电动葫芦5的拆装,顶承重梁1四角和底承重梁4两端均设有用于安装电动葫芦5的吊环3,在本实施例中,为了方便抱箍拆装时对电动葫芦的位置进行调节,因此在顶承重梁1中间设有可拆卸挂板2,可拆卸挂板2连接用于抱箍7拆装的电动葫芦,所以本实施例中对应的步骤S7具体为:将可拆卸挂板2拆除后,通过吊具将顶承重梁1放置在盖梁14顶上,顶承重梁1一侧通过电动葫芦5和抱箍7连接,用于抱箍7拆除下降至地面;顶承重梁1另一侧通过两个电动葫芦5连接底承重梁4用于抱箍拆除时支撑施工作业平台;进一步的,当盖梁14顶上设有支座垫石或预埋件导致顶承重梁无法平稳放置,顶承重梁1可由两根平行设置的底承重梁4替换,且吊环3方向向下,如图3所示。In order to facilitate the disassembly and assembly of the electric hoist 5, the four corners of the top load-bearing beam 1 and the two ends of the bottom load-bearing beam 4 are all provided with lifting rings 3 for installing the electric hoist 5. The position is adjusted, so a detachable hanging plate 2 is provided in the middle of the top load-bearing beam 1, and the detachable hanging plate 2 is connected to the electric hoist used for the disassembly and assembly of the hoop 7, so the corresponding step S7 in this embodiment is specifically: After the hanging plate 2 is removed, the top load-bearing beam 1 is placed on the top of the cover beam 14 through a spreader, and one side of the top load-bearing beam 1 is connected by the electric hoist 5 and the hoop 7, which is used to remove the hoop 7 and lower it to the ground; The other side of the load-bearing beam 1 is connected to the bottom load-bearing beam 4 through two electric hoists 5 to support the construction work platform when the hoop is removed; The beam cannot be placed stably, the top load-bearing beam 1 can be replaced by two bottom load-bearing beams 4 arranged in parallel, and the direction of the lifting ring 3 is downward, as shown in Figure 3 .

本发明提供的高墩盖梁一体化施工平台安拆方法,安装之前,对墩柱底部地面进行平整,随后在平整地面上将整个施工平台组装完成,然后利用平台升降装置将整个施工作业平台提升至设计标高,并采用抱箍固定。施工作业平台安装完成后进行盖梁施工,盖梁施工完成后,再次利用平台升降装置将整个施工作业平台下降至墩柱底部地面后,拆除施工作业平台,整个安拆过程作业人员均处于较安全的位置,安全有保障,较大程度地降低了盖梁施工作业平台安装时存在的高空作业风险,同时也大大提高了施工作业平台的安装质量和安拆速度,减少了时间、人力、物力等成本投入,降低了工程成本。The installation and disassembly method of the high pier cover beam integrated construction platform provided by the present invention, before installation, the ground at the bottom of the pier column is leveled, and then the entire construction platform is assembled on the flat ground, and then the entire construction operation platform is lifted by the platform lifting device to the design level and fixed with hoops. After the installation of the construction work platform is completed, the cover beam construction is carried out. After the construction of the cover beam is completed, the entire construction work platform is lowered to the ground at the bottom of the pier by using the platform lifting device again, and then the construction work platform is removed. During the whole installation and disassembly process, the operators are in a relatively safe environment. The location is safe and secure, which greatly reduces the risk of high-altitude operation during the installation of the cover beam construction work platform, and also greatly improves the installation quality and speed of installation and disassembly of the construction work platform, reducing time, manpower and material resources, etc. Cost input reduces engineering costs.

本领域的技术人员容易理解,以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。It is easy for those skilled in the art to understand that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention, All should be included within the protection scope of the present invention.

Claims (6)

1. A high pier capping beam integrated construction platform mounting and dismounting method is characterized by comprising the following steps:
s1, leveling the ground at the bottom of the pier stud;
s2, mounting a platform lifting device: the platform lifting device comprises a top bearing beam, a bottom bearing beam and an electric hoist, wherein the electric hoist is arranged on the top bearing beam and is used for connecting, dismounting and mounting the top bearing beam with the bottom bearing beam and the hoop respectively;
the top bearing beam is stably hung on the upper end surface of the pier stud through a hanger and is fixed, and the bottom bearing beam is connected with the top bearing beam through an electric hoist and is positioned on the ground at the bottom of the pier stud;
s3, assembling the construction operation platform: the construction operation platform comprises a main bearing beam horizontally placed on a bottom bearing beam, the length directions of the bottom bearing beam and the main bearing beam are mutually vertical, a distribution beam is connected between the main bearing beams and positioned above the main bearing beam, a personnel operation pedal is fixed above the distribution beam, and safety guardrails are arranged around the personnel operation pedal;
s4, hoop installation: the construction operation platform is lifted to a designed elevation through the platform lifting device, the hoop is lifted to the designed elevation through the electric hoist, and the hoop bracket is attached to the lower end face of the main bearing beam and tightly held and fixed with the outer wall of the pier column to support the construction operation platform;
s5, dismantling the platform lifting device: the bottom bearing beam is lowered to the ground through the electric hoist to be dismantled, and the top bearing beam is dismantled through the lifting appliance;
s6, bent cap construction: building a bent cap bottom die to complete bent cap construction;
s7, reinstallation of the platform lifting device: the top bearing beam is placed on the top of the cover beam through a lifting appliance, and the bottom bearing beam is lifted by the top bearing beam through an electric hoist to drag the bottom of the construction operation platform;
s8, removing the hoop: transporting the operating personnel to the hoop dismounting position through the climbing vehicle, and descending the hoop to the ground through the electric hoist after dismounting the hoop;
s9, dismantling the construction operation platform: an operator lowers the construction operation platform to the ground through the platform lifting device, and removes the main bearing beam, the distribution beam, the personnel operation pedal and the safety barrier;
s10, dismantling the platform lifting device again: an operator removes the bottom bearing beam, transports the operator to a removal position by adopting a climbing vehicle to remove the electric hoist and the top bearing beam, and transports the removed electric hoist and the top bearing beam to the ground by adopting a lifting appliance; and repeating the steps S1-S10 to finish the construction of the next bent cap.
2. The method for assembling and disassembling the high pier capping beam integrated construction platform according to claim 1, characterized in that: the top load-bearing beam four corners with end spandrel girder both ends all are equipped with the rings that are used for installing electric block, be equipped with in the middle of the top load-bearing beam and dismantle the link plate, can dismantle the link plate connection and be used for the electric block of staple bolt dismouting.
3. The method for assembling and disassembling the high pier capping beam integrated construction platform according to claim 2, wherein the step S7 is specifically as follows: after the detachable hanging plate is detached, the top bearing beam is placed on the top of the cover beam through a lifting appliance, and one side of the top bearing beam is connected with the hoop through an electric hoist and used for the hoop to be detached and descend to the ground; the other side of the top bearing beam is connected with the bottom bearing beam through two electric hoists and used for supporting the construction operation platform when the hoop is detached.
4. The method for installing and dismantling the high pier capping beam integrated construction platform according to claim 1, wherein the step S3 comprises:
s31, mounting a main bearing beam: the main bearing beam is positioned on the bottom bearing beam and is arranged vertical to the length direction of the bottom bearing beam; the main bearing beam is uniformly distributed with distribution beams which are fixedly arranged perpendicular to the length direction of the main bearing beam;
s32, fixing a personnel operating pedal: the personnel operation pedal is fixed on the distribution beam;
s33, installation of the safety barrier: safety guardrails are fixed around the personnel operation pedal.
5. The method for assembling and disassembling the high pier capping beam integrated construction platform according to claim 1, characterized in that: the top bearing beam is in a shape like the Chinese character 'wang', and the bottom bearing beam is in a shape like a straight line.
6. The method for assembling and disassembling the high pier capping beam integrated construction platform according to claim 3, characterized in that: the top bearing beam can not be stably placed due to the fact that the top of the cover beam is provided with the support cushion stone or the embedded part, and the top bearing beam can be replaced by the two bottom bearing beams which are arranged in parallel.
CN202211174522.4A 2022-09-26 2022-09-26 High pier capping beam integrated construction platform installing and dismantling method Pending CN115450125A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211174522.4A CN115450125A (en) 2022-09-26 2022-09-26 High pier capping beam integrated construction platform installing and dismantling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211174522.4A CN115450125A (en) 2022-09-26 2022-09-26 High pier capping beam integrated construction platform installing and dismantling method

Publications (1)

Publication Number Publication Date
CN115450125A true CN115450125A (en) 2022-12-09

Family

ID=84307269

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211174522.4A Pending CN115450125A (en) 2022-09-26 2022-09-26 High pier capping beam integrated construction platform installing and dismantling method

Country Status (1)

Country Link
CN (1) CN115450125A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117418459A (en) * 2023-10-08 2024-01-19 中交路桥建设有限公司 A self-lifting pier working platform
CN117536105A (en) * 2023-10-31 2024-02-09 江苏玖沐精工装备科技有限公司 Capping beam construction device and capping beam construction process
CN119593306A (en) * 2024-12-09 2025-03-11 保利长大工程有限公司 An integral lifting and disassembly construction process for a cantilever cap beam support

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100981982B1 (en) * 2010-06-11 2010-09-13 (주)대우건설 Precast coping lifting system
CN211665584U (en) * 2019-11-30 2020-10-13 中交路桥建设有限公司 Staple bolt installation construction hanging flower basket on column pier
CN212404859U (en) * 2020-05-21 2021-01-26 中交二公局第三工程有限公司 Auxiliary device for falling of bottom die of bent cap
CN215104693U (en) * 2021-01-04 2021-12-10 中交二航局第二工程有限公司 A kind of installation and disassembly tool for large cantilever cover beam bracket of high pier in the sea
CN113981825A (en) * 2021-10-19 2022-01-28 中铁十六局集团第四工程有限公司 An integrally removable cover beam construction platform
CN114606870A (en) * 2022-04-02 2022-06-10 中铁六局集团有限公司 Integral dismantling method for hoop-method bent cap supporting system
CN217264293U (en) * 2022-01-17 2022-08-23 中交一公局西北工程有限公司 Circular column mound staple bolt installation device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100981982B1 (en) * 2010-06-11 2010-09-13 (주)대우건설 Precast coping lifting system
CN211665584U (en) * 2019-11-30 2020-10-13 中交路桥建设有限公司 Staple bolt installation construction hanging flower basket on column pier
CN212404859U (en) * 2020-05-21 2021-01-26 中交二公局第三工程有限公司 Auxiliary device for falling of bottom die of bent cap
CN215104693U (en) * 2021-01-04 2021-12-10 中交二航局第二工程有限公司 A kind of installation and disassembly tool for large cantilever cover beam bracket of high pier in the sea
CN113981825A (en) * 2021-10-19 2022-01-28 中铁十六局集团第四工程有限公司 An integrally removable cover beam construction platform
CN217264293U (en) * 2022-01-17 2022-08-23 中交一公局西北工程有限公司 Circular column mound staple bolt installation device
CN114606870A (en) * 2022-04-02 2022-06-10 中铁六局集团有限公司 Integral dismantling method for hoop-method bent cap supporting system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117418459A (en) * 2023-10-08 2024-01-19 中交路桥建设有限公司 A self-lifting pier working platform
CN117536105A (en) * 2023-10-31 2024-02-09 江苏玖沐精工装备科技有限公司 Capping beam construction device and capping beam construction process
CN119593306A (en) * 2024-12-09 2025-03-11 保利长大工程有限公司 An integral lifting and disassembly construction process for a cantilever cap beam support

Similar Documents

Publication Publication Date Title
CN101922143B (en) Cover beam construction method
CN203947771U (en) A kind of Bailey beam pendent form support system
CN104141383A (en) Bailey beam suspension formwork supporting system and construction method thereof
CN208702197U (en) A kind of big displacement integral jacking Compact Mounts
CN202810173U (en) Mounting and construction platform for steel lining bracket and circular crane track girder of nuclear power plant
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN105464216A (en) Construction method for ultrahigh oblique post with super-large cross section based on integral lifting formwork reinforcing system
CN116427553A (en) A kind of upside-down construction method of cross-story steel truss
CN108018781A (en) A kind of big segment double-template system of self-crawling type and its construction method for bridge tower construction
CN114808759A (en) Cantilever concrete formwork support structure of steel-concrete composite beam bridge and cantilever concrete construction method
CN110526153B (en) A jack-assisted pile foundation steel cage lifting structure and construction method thereof
CN102286927A (en) Integral mounting construction method of bridge pier column bent cap reinforcement cage
CN115043330B (en) Support structure of inner climbing frame of tower crane in non-core tube area, inner climbing frame and tower crane
CN104963295A (en) Support frame for non-ground internal-force balanced cast-in-place beam and construction method thereof
CN207727438U (en) A kind of big segment double-template system of self-crawling type for bridge tower construction
CN207793884U (en) The steel frame structure of the tower column on the cable tower
CN210289075U (en) Adjustable elevator shaft operating platform system that can have enough to meet need
CN219280494U (en) Tower beam temporary consolidation supporting structure for bridge tower stability control
CN115821763B (en) Construction method for one-step lifting and stepwise descending of double pier stud bent cap support system
CN111335172A (en) Movable pier column beam prestressed tension hanger construction platform and construction method
CN218714838U (en) Self-lifting heavy-load construction platform
CN204662933U (en) A kind of hoistway operation frame lift-type steel platform
CN105350698A (en) Large-span dome installation construction method
CN113737661B (en) A construction method for steel-concrete joint section of cable-stayed bridge pylon
CN215519870U (en) Elevator shaft operating platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Country or region after: China

Address after: 215151 No. 10, Datong Road, high tech Zone, Suzhou, Jiangsu

Applicant after: China Railway Construction Urban Construction Transportation Development Co.,Ltd.

Applicant after: CHINA RAILWAY 20 BUREAU Group Corp.

Address before: 215151 No. 10, Datong Road, high tech Zone, Suzhou, Jiangsu

Applicant before: NO.1 ENGINEERING CORPORATION LIMITED OF CR20G

Country or region before: China

Applicant before: CHINA RAILWAY 20 BUREAU Group Corp.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20221209

RJ01 Rejection of invention patent application after publication