CN115432551A - A hoisting assembly and hoisting method for a steel box girder of a cross-sea bridge - Google Patents
A hoisting assembly and hoisting method for a steel box girder of a cross-sea bridge Download PDFInfo
- Publication number
- CN115432551A CN115432551A CN202211163703.7A CN202211163703A CN115432551A CN 115432551 A CN115432551 A CN 115432551A CN 202211163703 A CN202211163703 A CN 202211163703A CN 115432551 A CN115432551 A CN 115432551A
- Authority
- CN
- China
- Prior art keywords
- hoisting
- steel box
- box girder
- hanging
- buckles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 60
- 239000010959 steel Substances 0.000 title claims abstract description 60
- 238000000034 method Methods 0.000 title claims abstract description 21
- 238000009434 installation Methods 0.000 claims abstract description 12
- 239000000725 suspension Substances 0.000 claims description 25
- 230000002093 peripheral effect Effects 0.000 claims description 3
- 239000011120 plywood Substances 0.000 claims description 2
- 230000000712 assembly Effects 0.000 abstract description 5
- 238000000429 assembly Methods 0.000 abstract description 5
- 238000005192 partition Methods 0.000 abstract description 5
- 230000008901 benefit Effects 0.000 description 3
- 238000004891 communication Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000000354 decomposition reaction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本申请涉及钢箱梁吊装技术领域,特别涉及一种跨海大桥钢箱梁的吊装组件及吊装方法。The present application relates to the technical field of steel box girder hoisting, in particular to a hoisting component and hoisting method of a steel box girder of a cross-sea bridge.
背景技术Background technique
在这一部分中提供的信息是为了一般地呈现本公开的背景的目的。在本部分中描述的程度上,当前署名的发明人的工作以及在提交时可能不构成现有技术的描述的各方面,既不明示地也不暗示地被认为是本公开的现有技术。The information provided in this section is for the purpose of generally presenting the context of the disclosure. To the extent described in this section, the work of the presently named inventors, and aspects of the description that may not constitute prior art at the time of filing, are neither expressly nor impliedly admitted to be prior art to the present disclosure.
跨海大桥中钢箱连续梁一般在工厂拼装成整体大节段,大节段整体运输到桥位再安装连接,大节段在制造完毕后的装船、卸船作业为难度大及风险较大的施工,大节段装船除了滚装、滑移方法外,还有利用大型龙门吊装的方法,Steel box continuous girders in cross-sea bridges are generally assembled into large sections in the factory, and the large sections are transported to the bridge site as a whole and then installed and connected. After the large sections are manufactured, the loading and unloading operations are difficult and risky. For large-scale construction, in addition to rolling-on-rolling and sliding methods, there is also a method of using large-scale gantry hoisting for large-section loading.
由于钢箱梁的纵向腹板距离小于龙门吊两钩最小间距,常规的方案有:1、单钩单梁方案,即两台龙门吊上各使用一个小车,小车下横向连接一个整体吊梁,整体吊梁与钢箱梁上横隔板上布置的吊点进行连接;2、双钩单梁方案,每台龙门吊使用两台小车,两条小车上连接一个整体吊梁,钢箱梁吊点布置在中腹板上方与整体吊梁连接。Since the distance between the longitudinal web of the steel box girder is smaller than the minimum distance between the two hooks of the gantry crane, the conventional schemes are: 1. Single hook and single girder scheme, that is, a trolley is used on each of the two gantry cranes, and a whole hoisting beam is connected horizontally under the trolley. The beam is connected with the lifting points arranged on the upper transverse diaphragm of the steel box girder; 2. The double-hook single-girder scheme, each gantry crane uses two trolleys, and the two trolleys are connected to a whole hanging beam, and the steel box girder lifting points are arranged in the mid-belly The upper part of the board is connected with the integral suspension beam.
从以上两种方案看,整体吊梁结构复杂、尺寸大,在吊装前后钢箱梁的连接操作复杂困难,影响吊装效率,且该吊装结构仅能通过定制化的尺寸满足单座桥梁,吊装设备通用性差。Judging from the above two schemes, the overall hoisting beam structure is complex and large in size, and the connection operation of the steel box girder before and after hoisting is complicated and difficult, which affects the hoisting efficiency, and the hoisting structure can only meet the needs of a single bridge through customized dimensions, hoisting equipment Poor versatility.
发明内容Contents of the invention
针对现有技术中存在的缺陷,本申请提供一种跨海大桥钢箱梁的吊装组件及吊装方法,以解决现有技术中钢箱梁的吊装设备通用性差且拆装复杂的问题。Aiming at the defects existing in the prior art, the present application provides a hoisting assembly and hoisting method of a steel box girder of a cross-sea bridge to solve the problem of poor versatility and complicated disassembly and assembly of the hoisting equipment of the steel box girder in the prior art.
本发明的上述目的主要是通过如下技术方案予以实现的:Above-mentioned purpose of the present invention is mainly achieved through the following technical solutions:
一种跨海大桥钢箱梁的吊装组件,所述吊装组件设有两组,每组所述吊装组件包括:A hoisting assembly of a steel box girder of a cross-sea bridge, the hoisting assembly is provided with two groups, and each group of the hoisting assembly includes:
吊梁主体部,所述吊梁主体部顶部设有用于连接吊装设备的吊装端;The main part of the hanging beam, the top of the main part of the hanging beam is provided with a hoisting end for connecting hoisting equipment;
绳轮组,所述绳轮组设有两组,且每组所述绳轮组包括两个间隔布置的转轮,所述转轮可转动的设在所述吊梁主体部上;A sheave set, the sheave set is provided with two groups, and each set of the sheave set includes two runners arranged at intervals, and the runners are rotatably arranged on the main part of the suspension beam;
吊部,所述吊部设有两个,每个所述吊部包括吊绳和设在所述吊绳两端的吊扣,所述吊绳中部挂设在一个所述绳轮组中的两个转轮上,所述吊扣用于固定在钢箱梁两个相邻的U肋之间的横隔板上,且每两个相邻的所述吊扣之间的距离为相邻的所述U肋之间距离的整数倍。There are two hanging parts, each of the hanging parts includes a hanging rope and hanging buckles arranged at both ends of the hanging rope, and the middle part of the hanging rope is hung on two of the sheave groups On the running wheel, the lifting buckle is used to be fixed on the diaphragm between two adjacent U ribs of the steel box girder, and the distance between every two adjacent lifting buckles is An integer multiple of the distance between ribs.
进一步地,不同的所述转轮的中心线相互平行。Further, the centerlines of different running wheels are parallel to each other.
进一步地,所述吊绳呈首尾相连的环形,两个所述吊扣分别设置于所述吊绳的两端。Further, the hanging rope is in the form of a ring connected end to end, and the two hanging buckles are respectively arranged at two ends of the hanging rope.
进一步地,所述吊梁主体部上设有旋转轴,所述转轮可转动的套设在所述旋转轴上,且所述转轮的外周面上设有两个环形槽,所述吊绳挂置在所述环形槽内。Further, the main body of the hanging beam is provided with a rotating shaft, the runner is rotatably sleeved on the rotating shaft, and the outer peripheral surface of the runner is provided with two annular grooves, the hanging The rope hangs in the annular groove.
进一步地,所述吊扣包括钩部和固定杆,所述钩部上设有开口,所述固定杆与所述钩部活动连接,并可开合的设在所述开口处。Further, the hanging buckle includes a hook portion and a fixing rod, the hook portion is provided with an opening, and the fixing rod is movably connected with the hook portion, and can be opened and closed at the opening.
进一步地,所述吊扣还包括安装座和两个三角夹板,所述安装座上具有所述固定杆穿设的吊孔,两个所述三角夹板用于夹持在所述横隔板两侧并通过固定螺栓与所述横隔板固定连接,两个所述三角夹板与所述安装座用于夹持在顶板两侧并通过固定螺栓与所述顶板固定连接。Further, the hanging buckle also includes a mounting seat and two triangular splints, the mounting seat has a lifting hole through which the fixing rod passes, and the two triangular splints are used to clamp on both sides of the diaphragm And it is fixedly connected with the transverse diaphragm through fixing bolts, and the two triangular splints and the mounting seats are used to be clamped on both sides of the top plate and fixedly connected with the top plate through fixing bolts.
进一步地,所述三角夹板的宽度与两个相邻的所述U肋之间的距离相等。Further, the width of the triangular splint is equal to the distance between two adjacent U ribs.
进一步地,所述吊装端位于所述吊梁主体部的中部,且所述吊装端上贯穿设有安装孔。Further, the lifting end is located in the middle of the main body of the hanging beam, and an installation hole is formed through the lifting end.
基于一个相同的发明构思,本申请还提出一种跨海大桥钢箱梁的吊装方法,其包括如下步骤:Based on a same inventive concept, the application also proposes a hoisting method of a steel box girder of a sea-crossing bridge, which includes the following steps:
取两个如上述的跨海大桥钢箱梁的吊装组件,并分别将所述吊装端与吊装设备连接;Take two hoisting components of the steel box girder of the cross-sea bridge as mentioned above, and connect the hoisting ends to the hoisting equipment respectively;
操作吊装设备将吊梁主体部移动至钢箱梁的吊装位上部;Operate the hoisting equipment to move the main part of the hoisting beam to the upper part of the hoisting position of the steel box girder;
将每个所述吊扣固定在钢箱梁两个相邻的U肋之间的横隔板上;Each of the suspension buckles is fixed on the diaphragm between two adjacent U ribs of the steel box girder;
操作吊装设备带动吊梁主体部移动,直至钢箱梁移动至目标位置。Operate the hoisting equipment to drive the main part of the hoisting beam to move until the steel box girder moves to the target position.
进一步地,所述吊扣与所述横隔板固定前,吊装设备提升所述吊梁主体部并保持所述吊扣为自然下垂状态,并根据该状态下两个相邻的所述吊扣之间的距离再次操作吊装设备,直至所述吊扣相对应的移动至相邻的两个U肋之间,然后将所述吊扣与所述横隔板固定。Further, before the hanging buckle is fixed to the transverse partition, the hoisting device lifts the main body of the hanging beam and keeps the hanging buckle in a natural drooping state, and according to the distance between two adjacent hanging buckles in this state, Operate the hoisting device again until the buckle is correspondingly moved between two adjacent U-ribs, and then fix the buckle to the transverse partition.
与现有技术相比,本发明的优点在于:Compared with the prior art, the present invention has the advantages of:
本发明中的吊装组件设有两组,每组吊装组件包括用于连接吊装设备的吊梁主体部,在吊梁主体部上设置两组绳轮组,每组绳轮组包括两个间隔布置的转轮,两个转轮上挂设吊绳,吊绳两端设有吊扣,吊扣用于固定在钢箱梁两个相邻的U肋之间的横隔板上,且每两个相邻的吊扣之间的距离为相邻的U肋之间距离的整数倍,在实际吊装过程中,通过合理布置转轮的相对距离,可以将吊扣之间的距离与船体结构中的U肋之间的距离进行相对应的布置,将原本与中腹板连接的吊点合理布置在U肋之间的横隔板上,避免不同规格钢箱梁中腹板的相对位置造成对吊梁主体部的规格造成影响,达到吊扣可适用于不同规格钢箱梁上的横隔板安装位置,提高吊装组件的适用性,同时在吊绳端部设置吊扣,避免直接通过完整钢绳进行整体吊装,降低拆装难度,另外吊绳中部被可转动的转轮承托,可以进一步保持每个吊点受力均匀,且受益于吊扣之间距离与U肋之间距离的匹配关系,使得转轮与吊扣之间的吊绳保持竖直状态,提高吊装过程稳定性,需要进行吊装组件拆装时,只需要通过操作吊梁主体部上的吊装端以及吊扣即可完成,降低拆装难度,提高吊装作业的效率。The hoisting assembly in the present invention is provided with two groups, each group of hoisting assembly includes the main part of the hanging beam used to connect the hoisting equipment, two groups of sheave sets are arranged on the main part of the hanging beam, and each set of sheave sets includes two The two runners are hung with a sling, and the two ends of the sling are provided with a buckle, which is used to fix the diaphragm between two adjacent U ribs of the steel box girder, and every two The distance between adjacent lifting buckles is an integral multiple of the distance between adjacent U ribs. In the actual hoisting process, by reasonably arranging the relative distance of the runners, the distance between the lifting buckles and the distance between the U ribs in the hull structure can be adjusted. The distance between them is arranged correspondingly, and the lifting points originally connected to the middle web are reasonably arranged on the transverse diaphragm between the U ribs, so as to avoid the relative position of the web in different specifications of the steel box girder from causing the specification of the main part of the hanging beam to be affected. As a result, the lifting buckle can be applied to the installation position of the diaphragm on the steel box girder of different specifications, which improves the applicability of the lifting components. In addition, the middle part of the lifting rope is supported by a rotatable runner, which can further keep the force on each lifting point even, and benefit from the matching relationship between the distance between the hanging buckles and the distance between the U ribs, so that the distance between the running wheel and the hanging buckles The lifting rope is kept vertical to improve the stability of the hoisting process. When it is necessary to disassemble the hoisting components, it only needs to be completed by operating the hoisting end and the hoisting buckle on the main part of the hoisting beam, which reduces the difficulty of disassembly and improves the efficiency of hoisting operations .
附图说明Description of drawings
为了更清楚地说明本申请实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单的介绍,显而易见地,下面描述中的附图仅仅是本申请的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present application. For those skilled in the art, other drawings can also be obtained based on these drawings without creative effort.
图1为本申请实施例提供的吊装组件安装后的正视图;Fig. 1 is the front view after installation of the hoisting assembly provided by the embodiment of the present application;
图2为本申请实施例提供的吊梁主体部处的正视图;Fig. 2 is a front view of the main part of the suspension beam provided by the embodiment of the present application;
图3为本申请实施例提供的吊梁主体部处的侧视图;Fig. 3 is a side view of the main part of the suspension beam provided by the embodiment of the present application;
图4为本申请实施例提供的安装座处的局部放大示意图;FIG. 4 is a partially enlarged schematic diagram of the mounting seat provided by the embodiment of the present application;
图5为本申请实施例提供的安装座处的局部剖视图;Fig. 5 is a partial cross-sectional view of the mounting seat provided by the embodiment of the present application;
图中:1、吊梁主体部;11、吊装端;12、安装孔;2、绳轮组;21、转轮;31、吊绳;32、吊扣;33、旋转轴;34、环形槽;41、钩部;42、固定杆;51、安装座;52、三角夹板;53、吊孔;6、U肋;7、横隔板;8、顶板;9、吊装设备。In the figure: 1, the main part of the hanging beam; 11, the hoisting end; 12, the installation hole; 2, the rope wheel group; 21, the runner; 31, the hanging rope; 32, the hanging buckle; 33, the rotating shaft; 41. Hook; 42. Fixed rod; 51. Mounting base; 52. Triangular plywood; 53. Hanging hole; 6. U rib; 7. Transverse partition; 8. Top plate; 9. Hoisting equipment
具体实施方式detailed description
下面结合附图及具体实施例对本发明作进一步阐述。在此需要说明的是,对于这些实施例方式的说明用于帮助理解本发明,但并不构成对本发明的限定。本文公开的特定结构和功能细节仅用于描述本发明的示例实施例。然而,可用很多备选的形式来体现本发明,并且不应当理解为本发明限制在本文阐述的实施例中。The present invention will be further elaborated below in conjunction with the accompanying drawings and specific embodiments. It should be noted here that the descriptions of these embodiments are used to help understand the present invention, but are not intended to limit the present invention. Specific structural and functional details disclosed herein are for purposes of describing example embodiments of the invention only. However, the invention may be embodied in many alternative forms and should not be construed as limited to the embodiments set forth herein.
如图1-5所示,一种跨海大桥钢箱梁的吊装组件,所述吊装组件设有两组,每组所述吊装组件包括吊梁主体部、绳轮组和吊部,其中:As shown in Figure 1-5, a hoisting assembly of a steel box girder of a cross-sea bridge, the hoisting assembly is provided with two groups, and each group of the hoisting assembly includes a main part of the hoisting beam, a sheave set and a hoisting part, wherein:
所述吊梁主体部顶部设有用于连接吊装设备的吊装端,吊梁主体部与吊装设备之间为可拆卸的连接关系,吊梁主体部可以在吊装设备的驱动下上升或者下降,以及沿龙门吊的布置方向进行横向移动。The top of the main part of the hanging beam is provided with a hoisting end for connecting the lifting equipment. The main part of the hanging beam and the lifting equipment are in a detachable connection. The main part of the hanging beam can be driven up or down by the lifting equipment, and The arrangement direction of the gantry crane moves laterally.
所述绳轮组设有两组,且每组所述绳轮组包括两个间隔布置的转轮,所述转轮可转动的设在所述吊梁主体部上,每个吊梁主体部上设置两组绳轮组,其中,每个绳轮组上中的两个转轮都可单独旋转。Two sets of the sheave sets are provided, and each set of the sheave sets includes two runners arranged at intervals, and the runners are rotatably arranged on the main part of the hanging beam, and each main part of the hanging beam Two sets of sheave sets are arranged on the top, wherein the two running wheels in each set of sheave wheels can rotate independently.
所述吊部设有两个,每个所述吊部包括吊绳和设在所述吊绳两端的吊扣,所述吊绳中部挂设在一个所述绳轮组中的两个转轮上,也就是每一组绳轮组对应一个吊绳,同时每个吊绳上挂设两个吊扣。There are two hanging parts, each of which includes a hanging rope and hanging buckles at both ends of the hanging rope, and the middle part of the hanging rope is hung on two runners in one of the sheave sets , that is, each group of sheave groups corresponds to a suspension rope, and two suspension buckles are hung on each suspension rope.
所述吊扣用于固定在钢箱梁两个相邻的U肋之间的横隔板上,且每两个相邻的所述吊扣之间的距离为相邻的所述U肋之间距离的整数倍,当吊扣处于自然下垂状态时,两个吊扣之间的距离为两个U肋之间距离的整数倍,由于不同规格的钢箱梁内的U肋之间的距离相等,相应的,两个吊扣之间的距离使得一个吊扣装设在两个相邻的U肋之间后,该吊绳另一端的吊扣也可以顺利装设在两个相邻的U肋之间,且保持转轮与吊扣之间的吊绳为竖直状态,既满足了吊扣具有合适的安装位置,又保持吊绳竖直且稳定的吊装状态要求。The lifting buckle is used to be fixed on the diaphragm between two adjacent U ribs of the steel box girder, and the distance between every two adjacent lifting buckles is the distance between the adjacent U ribs Integer multiples of , when the buckle is in a natural drooping state, the distance between two buckles is an integer multiple of the distance between two U ribs, since the distances between U ribs in steel box girders of different specifications are equal, the corresponding , the distance between the two slings is such that after one sling is installed between two adjacent U-ribs, the sling at the other end of the sling can also be smoothly installed between two adjacent U-ribs, keeping The suspension rope between the runner and the suspension buckle is in a vertical state, which not only satisfies the requirement that the suspension buckle has a suitable installation position, but also keeps the suspension rope in a vertical and stable hoisting state.
在该吊装组件作业时,两个吊装组件对应两个吊梁主体部间隔布置在钢箱梁上部,四个绳轮组上挂置四个吊部,一共包含八个吊扣,每个吊梁主体部可以布置的位置更灵活,且覆盖面更广,在面对不同规格的钢箱梁时,可以在两个吊梁主体部之间设置不同的间距后,不额外增加其他结构以及不改变吊装组件的基础上,依然可以选取更合适的吊装位置进行钢箱梁的吊装作业,以保持不同钢箱梁吊装过程中稳定性,在面对不同规格的钢箱梁时,就不需要考虑钢箱梁中腹板的位置进行重新定制整体吊梁了,节约成本。When the hoisting assembly is in operation, two hoisting assemblies corresponding to the main parts of the two hanging beams are arranged at intervals on the upper part of the steel box girder, and four hanging parts are hung on the four sheave groups, including eight lifting buckles in total. The position that can be arranged is more flexible and the coverage is wider. When facing steel box girders of different specifications, different spacing can be set between the main parts of the two hanging beams without adding other structures and without changing the lifting components. On the basis of the above, it is still possible to select a more suitable hoisting position for the hoisting operation of the steel box girder to maintain the stability of the hoisting process of different steel box girders. When facing steel box girders of different specifications, there is no need to consider the steel box girder The position of the middle web is re-customized as a whole hanging beam, which saves cost.
本实施例的工作原理是:吊装组件设有两组,每组吊装组件包括用于连接吊装设备的吊梁主体部,在吊梁主体部上设置两组绳轮组,每组绳轮组包括两个间隔布置的转轮,两个转轮上挂设吊绳,吊绳两端设有吊扣,吊扣用于固定在钢箱梁两个相邻的U肋之间的横隔板上,且每两个相邻的吊扣之间的距离为相邻的U肋之间距离的整数倍,在实际吊装过程中,通过合理布置转轮的相对距离,可以将吊扣之间的距离与船体结构中的U肋之间的距离进行相对应的布置,将原本与中腹板连接的吊点合理布置在U肋之间的横隔板上,避免不同规格钢箱梁中腹板的相对位置造成对吊梁主体部的规格造成影响,达到吊扣可适用于不同规格钢箱梁上的横隔板安装位置,提高吊装组件的适用性,同时在吊绳端部设置吊扣,避免直接通过完整钢绳进行整体吊装,降低拆装难度,另外吊绳中部被可转动的转轮承托,可以进一步保持每个吊点受力均匀,且受益于吊扣之间距离与U肋之间距离的匹配关系,使得转轮与吊扣之间的吊绳保持竖直状态,提高吊装过程稳定性,需要进行吊装组件拆装时,只需要通过操作吊梁主体部上的吊装端以及吊扣即可完成,降低拆装难度,提高吊装作业的效率。The working principle of this embodiment is: two sets of hoisting assemblies are provided, each set of hoisting assemblies includes a main part of the hanging beam used to connect the hoisting equipment, and two sets of sheave groups are arranged on the main part of the hanging beam, and each set of sheave sets includes Two runners arranged at intervals, hanging ropes are hung on the two runners, the two ends of the hanging ropes are provided with hooks, and the hooks are used to fix on the diaphragm between two adjacent U ribs of the steel box girder, and The distance between every two adjacent buckles is an integer multiple of the distance between adjacent U ribs. In the actual hoisting process, by reasonably arranging the relative distance of the runners, the distance between the buckles and the hull structure can be adjusted. The distance between the U-ribs of the steel box girders is arranged correspondingly, and the lifting points originally connected to the middle web are reasonably arranged on the diaphragm between the U-ribs, so as to avoid the relative position of the webs of steel box girders of different specifications from causing serious damage to the hanging beams. The specifications of the main body are affected, and the hook can be applied to the installation position of the diaphragm on the steel box girder of different specifications, which improves the applicability of the hoisting components. , to reduce the difficulty of disassembly and assembly. In addition, the middle part of the lifting rope is supported by a rotatable runner, which can further keep the force on each lifting point even, and benefit from the matching relationship between the distance between the hanging buckles and the distance between the U ribs, so that the running wheel The sling between the hoisting rope and the buckle is kept vertical to improve the stability of the hoisting process. When it is necessary to disassemble the hoisting components, it only needs to be completed by operating the hoisting end and the hoisting buckle on the main part of the hoisting beam, which reduces the difficulty of disassembly and improves Efficiency of hoisting operations.
进一步地,在上述实施例的基础上,不同的所述转轮的中心线相互平行,当吊绳通过移动平衡不同吊扣处的受力时,吊绳在转轮上发生一定位移,转轮被带动旋转一定角度,在该过程中,转轮的中心线相互平行,以保持吊绳与转轮的相对位置关系,避免吊绳在转轮上沿转轮的轴向发生偏移,保持吊绳受力过程中的稳定性。Further, on the basis of the above-mentioned embodiment, the centerlines of the different runners are parallel to each other. When the suspension rope moves to balance the stress on different hanging buckles, the suspension rope will be displaced on the runner, and the runner will be moved. It is driven to rotate at a certain angle. During this process, the centerlines of the runners are parallel to each other to maintain the relative positional relationship between the sling and the runners, avoid the deviation of the sling on the runner along the axial direction of the runner, and keep the sling Stability during stress.
进一步地,在上述实施例的基础上,所述吊绳呈首尾相连的环形,两个所述吊扣分别设置于所述吊绳的两端,环形吊绳中部挂设在转轮上,吊绳与转轮之间的接触位置就有两个,便于受力的分解,使得吊绳可以吊装更重的钢箱梁,同时该状态下的吊绳两端更便于设置吊扣,避免需要再一次在吊绳上设置吊扣连接点。Further, on the basis of the above-mentioned embodiments, the sling is ring-shaped end-to-end, the two slings are respectively arranged at both ends of the sling, the middle part of the ring-shaped sling is hung on the runner, and the sling There are two contact positions with the runner, which is convenient for the decomposition of the force, so that the lifting rope can lift heavier steel box girders. Hanging buckle connection points are set on the hanging rope.
进一步地,在上述实施例的基础上,所述吊梁主体部上设有旋转轴,所述转轮可转动的套设在所述旋转轴上,且所述转轮的外周面上设有两个环形槽,所述吊绳挂置在所述环形槽内,进一步通过环形槽限制吊绳的活动位置,避免吊绳出现沿转轮轴向的位移。Further, on the basis of the above embodiments, the main body of the hanging beam is provided with a rotating shaft, the runner is rotatably sleeved on the rotating shaft, and the outer peripheral surface of the runner is provided with Two annular grooves, the suspension rope is hung in the said annular groove, the movable position of the suspension rope is further restricted by the annular groove, and the axial displacement of the suspension rope along the running wheel is avoided.
进一步地,在上述实施例的基础上,所述吊扣包括钩部和固定杆,所述钩部上设有开口,所述固定杆与所述钩部活动连接,并可开合的设在所述开口处,固定杆可以设置为与钩部螺纹连接,旋转操作固定杆,可以使钩部上的开口处于打开或者关闭状态,以便于吊扣的拆卸操作;还可以将固定杆一端与钩部之间铰接,另一端与钩部勾连,通过固定杆的旋转就可以实现钩部上的开口处保持在不同的状态。Further, on the basis of the above embodiments, the hanging buckle includes a hook and a fixing rod, the hook is provided with an opening, and the fixing rod is movably connected with the hook, and can be opened and closed at the At the above-mentioned opening, the fixing rod can be set to be threadedly connected with the hook, and the rotating operation of the fixing rod can make the opening on the hook open or close, so as to facilitate the disassembly operation of the hanging buckle; it is also possible to connect one end of the fixing rod with the hook The other end is connected with the hook, and the opening on the hook can be kept in different states through the rotation of the fixed rod.
进一步地,在上述实施例的基础上,所述吊扣还包括安装座和两个三角夹板,所述安装座上具有所述固定杆穿设的吊孔,两个所述三角夹板用于夹持在所述横隔板两侧并通过固定螺栓与所述横隔板固定连接,两个所述三角夹板与所述安装座用于夹持在顶板两侧并通过固定螺栓与所述顶板固定连接。Further, on the basis of the above-mentioned embodiment, the hanging buckle also includes a mounting seat and two triangular splints, the mounting seat has a lifting hole through which the fixing rod passes, and the two triangular splints are used for clamping On both sides of the diaphragm and fixedly connected to the diaphragm through fixing bolts, the two triangular splints and the mounting seat are used to clamp on both sides of the top plate and fixedly connected to the top plate through fixing bolts .
钢箱梁内的U肋贯穿不同位置的横隔板,横隔板顶面固定设有顶板,安装时通过两个三角夹板夹设在横隔板两侧,可以采用螺栓贯穿并固定连接,且两个三角夹板均位于两个相邻的U肋之间,安装座压设在顶板上,并与位于顶板下部的三角夹板通过螺栓贯穿后固定连接,此时吊扣既与横隔板固定连接,又与顶板固定连接,同时还位于两个相邻的U肋之间,便于拆装又不破坏钢箱梁原结构关系,也不受到中腹板的安装限制。The U-rib in the steel box girder runs through the diaphragm at different positions, and the top of the diaphragm is fixed with a top plate, which is clamped on both sides of the diaphragm by two triangular splints during installation, which can be penetrated and fixedly connected by bolts, and The two triangular splints are located between two adjacent U-ribs, and the installation seat is pressed on the top plate, and is fixedly connected with the triangular splint at the lower part of the top plate through bolts. It is fixedly connected with the top plate, and is also located between two adjacent U ribs, which is convenient for disassembly and assembly without destroying the original structural relationship of the steel box girder, and is not restricted by the installation of the middle web.
进一步地,在上述实施例的基础上,所述三角夹板的宽度与两个相邻的所述U肋之间的距离相等,提高三角夹板尺寸与U肋设置间隔的匹配度。Further, on the basis of the above embodiments, the width of the triangular splint is equal to the distance between two adjacent U ribs, which improves the matching degree between the size of the triangular splint and the spacing between the U ribs.
进一步地,在上述实施例的基础上,所述吊装端位于所述吊梁主体部的中部,吊梁主体部通过吊装端与吊装设备连接,限制吊装端位于中部,保持吊梁主体部整体的左右平衡,所述吊装端上贯穿设有安装孔,在连接吊装端的过程中,可以采用连接插销贯穿该安装孔达到快速与吊装设备的连接操作,提高操作效率。Further, on the basis of the above embodiments, the lifting end is located in the middle of the main body of the hanging beam, the main body of the hanging beam is connected to the lifting equipment through the lifting end, and the lifting end is limited to be located in the middle, so as to maintain the overall shape of the main body of the hanging beam. Balanced left and right, the lifting end is provided with a mounting hole through it, and in the process of connecting the lifting end, a connecting pin can be used to penetrate the mounting hole to achieve fast connection operation with the lifting equipment and improve operating efficiency.
基于一个相同的发明构思,本申请还提出一种跨海大桥钢箱梁的吊装方法,其包括如下步骤:Based on a same inventive concept, the application also proposes a hoisting method of a steel box girder of a sea-crossing bridge, which includes the following steps:
取两个如上述的跨海大桥钢箱梁的吊装组件,并分别将所述吊装端与吊装设备连接;Take two hoisting components of the steel box girder of the cross-sea bridge as mentioned above, and connect the hoisting ends to the hoisting equipment respectively;
操作吊装设备将吊梁主体部移动至钢箱梁的吊装位上部;Operate the hoisting equipment to move the main part of the hoisting beam to the upper part of the hoisting position of the steel box girder;
将每个所述吊扣固定在钢箱梁两个相邻的U肋之间的横隔板上;Each of the suspension buckles is fixed on the diaphragm between two adjacent U ribs of the steel box girder;
操作吊装设备带动吊梁主体部移动,直至钢箱梁移动至目标位置。Operate the hoisting equipment to drive the main part of the hoisting beam to move until the steel box girder moves to the target position.
进一步地,在上述实施例的基础上,在所述吊扣与所述横隔板固定前,吊装设备提升所述吊梁主体部并保持所述吊扣为自然下垂状态,并根据该状态下两个相邻的所述吊扣之间的距离再次操作吊装设备,直至所述吊扣相对应的移动至相邻的两个U肋之间,然后将所述吊扣与所述横隔板固定。Further, on the basis of the above embodiment, before the hanging buckle is fixed to the diaphragm, the hoisting equipment lifts the main body of the hanging beam and keeps the hanging buckle in a natural drooping state, and according to the two The distance between the adjacent hanging buckles operates the hoisting equipment again until the hanging buckles are correspondingly moved between two adjacent U-ribs, and then the hanging buckles are fixed to the transverse partition.
应当理解,术语第一、第二等仅用于区分描述,而不能理解为指示或暗示相对重要性。尽管本文可以使用术语第一、第二等等来描述各种单元,这些单元不应当受到这些术语的限制。这些术语仅用于区分一个单元和另一个单元。例如可以将第一单元称作第二单元,并且类似地可以将第二单元称作第一单元,同时不脱离本发明的示例实施例的范围。It should be understood that the terms first, second, etc. are only used for distinguishing descriptions, and cannot be interpreted as indicating or implying relative importance. Although the terms first, second, etc. may be used herein to describe various elements, these elements should not be limited by these terms. These terms are only used to distinguish one unit from another. For example, a first element could be termed a second element, and, similarly, a second element could be termed a first element, without departing from the scope of example embodiments of the present invention.
应当理解,本文中术语“和/或”,仅仅是一种描述关联对象的关联关系,表示可以存在三种关系,例如,A和/或B,可以表示:单独存在A,单独存在B,同时存在A和B三种情况,本文中术语“/和”是描述另一种关联对象关系,表示可以存在两种关系,例如,A/和B,可以表示:单独存在A,单独存在A和B两种情况,另外,本文中字符“/”,一般表示前后关联对象是一种“或”关系。It should be understood that the term "and/or" in this article is only an association relationship describing associated objects, indicating that there may be three relationships, for example, A and/or B may mean: A exists alone, B exists alone, and at the same time There are three situations of A and B. The term "/and" in this article describes another associated object relationship, which means that there can be two relationships, for example, A/ and B, which can mean: A exists alone, and A and B exist alone In both cases, in addition, the character "/" in this article generally indicates that the contextual objects are an "or" relationship.
应当理解,在本发明的描述中,术语“上”、“竖直”、“内”、“外”等指示的方位或位置关系,是该公开产品使用时惯常摆放的方位或位置关系,或者是本领域技术人员惯常理解的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It should be understood that in the description of the present invention, the orientation or positional relationship indicated by the terms "upper", "vertical", "inner", "outer", etc. is the orientation or positional relationship that the disclosed product is usually placed in use, Or the orientation or positional relationship commonly understood by those skilled in the art is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, Therefore, it should not be construed as limiting the invention.
在本发明的描述中,还需要说明的是,除非另有明确的规定和限定,术语“设置”、“安装”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以具体情况理解上述术语在本发明中的具体含义。In the description of the present invention, it should also be noted that, unless otherwise clearly specified and limited, the terms "setting", "installation" and "connection" should be interpreted in a broad sense, for example, it can be a fixed connection or an optional connection. Disassembled connection, or integral connection; it can be directly connected, or indirectly connected through an intermediary, and it can be the internal communication of two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present invention in specific situations.
本文使用的术语仅用于描述特定实施例,并且不意在限制本发明的示例实施例。如本文所使用的,单数形式“一”、“一个”以及“该”意在包括复数形式,除非上下文明确指示相反意思。还应当理解术语“包括”、“包括了”、“包含”、和/或“包含了”当在本文中使用时,指定所声明的特征、整数、步骤、操作、单元和/或组件的存在性,并且不排除一个或多个其他特征、数量、步骤、操作、单元、组件和/或他们的组合存在性或增加。The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of example embodiments of the invention. As used herein, the singular forms "a", "an" and "the" are intended to include plural forms unless the context clearly dictates otherwise. It should also be understood that the terms "comprises", "comprises", "comprises", and/or "comprises" when used herein designate the presence of stated features, integers, steps, operations, elements and/or components and does not exclude the existence or addition of one or more other features, quantities, steps, operations, units, components and/or combinations thereof.
在下面的描述中提供了特定的细节,以便于对示例实施例的完全理解。然而,本领域普通技术人员应当理解可以在没有这些特定细节的情况下实现示例实施例。在其他实施例中,可以不以非必要的细节来示出众所周知的过程、结构和技术,以避免使得示例实施例不清楚。In the following description specific details are provided to facilitate a thorough understanding of example embodiments. However, it will be understood by those of ordinary skill in the art that example embodiments may be practiced without these specific details. In other embodiments, well-known processes, structures and techniques may not be shown in unnecessary detail in order not to obscure the example embodiments.
以上仅是本申请的具体实施方式,使本领域技术人员能够理解或实现本申请。对这些实施例的多种修改对本领域的技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本申请的精神或范围的情况下,在其它实施例中实现。因此,本申请将不会被限制于本文所示的这些实施例,而是要符合与本文所申请的原理和新颖特点相一致的最宽的范围。The above are only specific implementation manners of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the application. Therefore, the present application will not be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features claimed herein.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211163703.7A CN115432551A (en) | 2022-09-23 | 2022-09-23 | A hoisting assembly and hoisting method for a steel box girder of a cross-sea bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211163703.7A CN115432551A (en) | 2022-09-23 | 2022-09-23 | A hoisting assembly and hoisting method for a steel box girder of a cross-sea bridge |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115432551A true CN115432551A (en) | 2022-12-06 |
Family
ID=84249409
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211163703.7A Pending CN115432551A (en) | 2022-09-23 | 2022-09-23 | A hoisting assembly and hoisting method for a steel box girder of a cross-sea bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115432551A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117246921A (en) * | 2023-11-04 | 2023-12-19 | 中交路桥建设有限公司 | A segmented assembly type variable cross-section box girder suspension assembly crane and hoisting method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN206784181U (en) * | 2017-03-10 | 2017-12-22 | 中交二航局结构工程有限公司 | A kind of steel box-girder simple and easy hoisting device |
| CN207891749U (en) * | 2018-01-27 | 2018-09-21 | 中交三公局桥梁隧道工程有限公司 | A steel box girder hanger |
| CN110240055A (en) * | 2019-07-22 | 2019-09-17 | 中国公路工程咨询集团有限公司 | A kind of steel box-girder hanging apparatus |
| CN210528240U (en) * | 2019-07-22 | 2020-05-15 | 中民筑友智能装备科技有限公司 | Lifting appliance for prefabricated part |
| CN217376980U (en) * | 2021-12-22 | 2022-09-06 | 中交二公局第三工程有限公司 | double-T-beam self-balancing hoisting sling |
-
2022
- 2022-09-23 CN CN202211163703.7A patent/CN115432551A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN206784181U (en) * | 2017-03-10 | 2017-12-22 | 中交二航局结构工程有限公司 | A kind of steel box-girder simple and easy hoisting device |
| CN207891749U (en) * | 2018-01-27 | 2018-09-21 | 中交三公局桥梁隧道工程有限公司 | A steel box girder hanger |
| CN110240055A (en) * | 2019-07-22 | 2019-09-17 | 中国公路工程咨询集团有限公司 | A kind of steel box-girder hanging apparatus |
| CN210528240U (en) * | 2019-07-22 | 2020-05-15 | 中民筑友智能装备科技有限公司 | Lifting appliance for prefabricated part |
| CN217376980U (en) * | 2021-12-22 | 2022-09-06 | 中交二公局第三工程有限公司 | double-T-beam self-balancing hoisting sling |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117246921A (en) * | 2023-11-04 | 2023-12-19 | 中交路桥建设有限公司 | A segmented assembly type variable cross-section box girder suspension assembly crane and hoisting method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP4605334A1 (en) | Crane having a crane boom provided with a tagline system | |
| CN103193165B (en) | Upper support of tower crane and tower crane | |
| CN102430923A (en) | Method for turning over turning wheel of water turbine in the air | |
| CN111017695A (en) | Process for hoisting large ship block by matching crawler crane with hoisting system | |
| CN214456342U (en) | Integrated super-lifting amplitude changing device for crane | |
| CN105780659A (en) | Lifting appliance special for erection of large-tonnage steel box beam segment in non-stayed cable area of cable-stayed bridge | |
| CN211769751U (en) | Hanging beam device for lifting double overhead travelling cranes | |
| CN114275660A (en) | Simple hoisting device and rapid hoisting method for steel reinforcement cage | |
| CN106480824B (en) | A kind of lifting method of steel cable tower | |
| CN215854573U (en) | Two precast beam hoists | |
| CN217578086U (en) | Lifting device for overweight parts in multi-wire centralized layout tippler factory building | |
| CN214031441U (en) | Hoisting equipment suitable for multiple traveling cranes and asymmetric balanced loads | |
| JP4975300B2 (en) | Lifting method using a plurality of cranes and lifting jig used therefor | |
| CN223163037U (en) | A lifting sling and box culvert lifting system | |
| WO2023087438A1 (en) | Tower crane upper structure and flat top tower crane | |
| CN222389455U (en) | Electric maintenance suspender device of tower crane | |
| CN209651778U (en) | A small steel structure hoisting device | |
| CN223254708U (en) | Building material conveying device | |
| CN223950582U (en) | Lifting appliance and lifting device | |
| CN215160476U (en) | Simple crane of offshore oilfield steel wire operation blowout prevention system | |
| CN220642215U (en) | Shoulder pole type hanging beam with adjustable arm length | |
| CN216141120U (en) | A hoist device for assembled coincide beam slab | |
| CN220598185U (en) | A continuous beam tensioning jack installation system | |
| CN222630827U (en) | A multi-joint hanger specially used for prefabricated cable trench | |
| CN222960945U (en) | Novel H-shaped steel beam quick connection and formwork moving and lifting device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |