CN115402880A - A kind of power construction pay-off device and using method thereof - Google Patents
A kind of power construction pay-off device and using method thereof Download PDFInfo
- Publication number
- CN115402880A CN115402880A CN202211194115.XA CN202211194115A CN115402880A CN 115402880 A CN115402880 A CN 115402880A CN 202211194115 A CN202211194115 A CN 202211194115A CN 115402880 A CN115402880 A CN 115402880A
- Authority
- CN
- China
- Prior art keywords
- pay
- roller
- sides
- roller shaft
- wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H67/00—Replacing or removing cores, receptacles, or completed packages at paying-out, winding, or depositing stations
- B65H67/02—Arrangements for removing spent cores or receptacles and replacing by supply packages at paying-out stations
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H49/00—Unwinding or paying-out filamentary material; Supporting, storing or transporting packages from which filamentary material is to be withdrawn or paid-out
- B65H49/18—Methods or apparatus in which packages rotate
- B65H49/20—Package-supporting devices
- B65H49/32—Stands or frameworks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H49/00—Unwinding or paying-out filamentary material; Supporting, storing or transporting packages from which filamentary material is to be withdrawn or paid-out
- B65H49/18—Methods or apparatus in which packages rotate
- B65H49/34—Arrangements for effecting positive rotation of packages
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65H—HANDLING THIN OR FILAMENTARY MATERIAL, e.g. SHEETS, WEBS, CABLES
- B65H2701/00—Handled material; Storage means
- B65H2701/30—Handled filamentary material
- B65H2701/34—Handled filamentary material electric cords or electric power cables
Landscapes
- Electric Cable Installation (AREA)
Abstract
本发明涉及电力线缆施工技术领域的一种电力施工放线器及其使用方法,装置包括底座,底座上设置有丝杆模组,丝杆模组包括双头丝杆,双头丝杆的左右两侧对称安装有移动组件,丝杆模组的双头丝杆旋转时带动两侧移动组件相互靠拢或远离;两侧移动组件之间设置有线辊,包括辊轴,转轴两端穿过并架设于两侧移动组件上;其中一侧移动组件外壁安装有用于与辊轴一端连接以驱动线辊转动的驱动装置,另一侧移动组件外壁安装有用于抵压辊轴端部的缓冲推压装置;线辊的底部设置有用于顶撑线辊的辅助支撑装置,辅助支撑装置架设于底座上,通过自动化电动控制,可使辊轴实现自动转载和放线功能,可降低人工的劳动强度。
The invention relates to a power construction pay-off device in the technical field of electric power cable construction and a method for using the same. The device includes a base on which a screw module is arranged. The moving components are symmetrically installed on the left and right sides. When the double-headed screw of the screw module rotates, the moving components on both sides are moved closer or farther away; there are wire rollers between the moving components on both sides, including the roller shaft, and the two ends of the rotating shaft pass through and It is erected on the moving components on both sides; the outer wall of the moving component on one side is equipped with a driving device used to connect with one end of the roller shaft to drive the wire roller to rotate, and the outer wall of the moving component on the other side is installed with a buffer pushing against the end of the roller shaft Device; the bottom of the wire roller is equipped with an auxiliary support device for supporting the wire roller. The auxiliary support device is erected on the base. Through automatic electric control, the roller shaft can realize automatic reloading and wire release functions, which can reduce manual labor intensity.
Description
技术领域technical field
本发明涉及一种电力施工放线器及其使用方法,属于电力线缆施工的技术领域。The invention relates to a power construction pay-off device and a method for using the same, belonging to the technical field of power cable construction.
背景技术Background technique
在电线敷设施工过程中,现场电线放线方式基本采取人工手持电线放线或者直接将电线盘置于地面然后拉线,由于布线时,通常是三股线同步布置,采用人工手持方向极为浪费人工,而直接将电线盘置于地面则很容易导致电线缠绕;During the wire laying construction process, the on-site wire release method basically adopts manual hand-held wire release or directly puts the wire reel on the ground and then pulls the wires. Since the wiring is usually three-strand wires are arranged synchronously, it is extremely wasteful to use manual hand-held directions. Putting the wire reel directly on the ground can easily lead to wire entanglement;
中国发明专利CN201410551959.4公开了一种便携式可调节的电力线缆放线装置,包括放线装置支架、放线装置内支架、电力线缆收线盘支撑轮、支撑轮固定板面、电力线缆收线盘限位器、电力线缆收线盘辅助移动板、放线装置底座、第一手柄以及第二手柄,所述放线装置支架与放线装置内支架并列设于放线装置底座上,所述放线装置底座的放线装置支架与放线装置内支架相对一侧设有过渡台阶,该装置通过手动操作实现手柄以实现放线操作;Chinese invention patent CN201410551959.4 discloses a portable adjustable power cable pay-off device, including a pay-off device bracket, an inner bracket of the pay-off device, a power cable take-up reel support wheel, a support wheel fixing plate, and a power line The cable take-up reel stopper, the power cable take-up reel auxiliary moving plate, the base of the pay-off device, the first handle and the second handle, the support of the pay-off device and the inner support of the pay-off device are arranged in parallel on the base of the pay-off device Above, a transition step is provided on the opposite side of the pay-off device bracket of the pay-off device base and the inner support of the pay-off device, and the device realizes the handle by manual operation to realize the pay-off operation;
然而,例如此类电力施工放线器却无法起到帮助减少人工劳动强度以及减少劳作力的效果。However, for example, this type of power construction pay-off device cannot help reduce labor intensity and reduce labor force.
发明内容Contents of the invention
为了解决现有技术所存在的上述问题,本发明提供了一种电力施工放线器及其使用方法。In order to solve the above-mentioned problems existing in the prior art, the present invention provides a power construction pay-off device and its usage method.
本发明的技术方案如下:Technical scheme of the present invention is as follows:
一种电力施工放线器,包括底座,所述底座上设置有丝杆模组,所述丝杆模组包括双头丝杆,所述双头丝杆的左右两侧对称安装有移动组件,所述丝杆模组的双头丝杆旋转时带动两侧所述移动组件相互靠拢或远离;A pay-off device for electric power construction, including a base, on which a screw module is arranged, and the screw module includes a double-ended screw, and the left and right sides of the double-ended screw are symmetrically equipped with moving components, When the double-headed screw of the screw module rotates, it drives the moving components on both sides to move closer or away from each other;
两侧所述移动组件之间设置有线辊,所述包括辊轴,所述转轴两端穿过并架设于两侧所述移动组件上;Wire rollers are arranged between the moving components on both sides, including a roller shaft, and the two ends of the rotating shaft pass through and are erected on the moving components on both sides;
其中一侧所述移动组件外壁安装有用于与所述辊轴一端连接以驱动所述线辊转动的驱动装置,另一侧所述移动组件外壁安装有用于抵压所述辊轴端部的缓冲推压装置;The outer wall of the moving assembly on one side is equipped with a driving device for connecting with one end of the roller shaft to drive the rotation of the wire roller, and the outer wall of the moving assembly on the other side is installed with a buffer for pressing against the end of the roller shaft pushing device;
所述线辊的底部设置有用于顶撑所述线辊的辅助支撑装置,所述辅助支撑装置架设于所述底座上。The bottom of the wire roll is provided with an auxiliary support device for supporting the wire roll, and the auxiliary support device is erected on the base.
作为本发明的一种优选方案,所述双头丝杆转动安装于所述底座上,所述丝杆模组还包括安装于所述底座外壁上的调距电机,所述调距电机与所述双头丝杆传动连接。As a preferred solution of the present invention, the double-ended screw is rotatably mounted on the base, and the screw module also includes a pitch-adjusting motor mounted on the outer wall of the base, and the pitch-adjusting motor is connected to the The above-mentioned double-headed screw drive connection.
作为本发明的一种优选方案,所述移动组件包括与所述双头丝杆螺接的螺纹套筒,所述螺纹套筒底部设置有导向块,所述底座顶面开设有与所述导向块滑动配合的导向槽,所述螺纹套筒顶部设置有电动伸缩杆,所述电动伸缩杆的上端通过支撑柱连接有限位板,所述限位板上开设有供所述辊轴穿设连接的安装孔。As a preferred solution of the present invention, the moving assembly includes a threaded sleeve screwed to the double-ended screw rod, a guide block is provided at the bottom of the threaded sleeve, and a guide block is provided on the top surface of the base to connect with the guide block. block sliding fit guide groove, the top of the threaded sleeve is provided with an electric telescopic rod, the upper end of the electric telescopic rod is connected to the limit plate through the support column, and the limit plate is provided with a hole for the roller shaft to pass through and connect the mounting holes.
作为本发明的一种优选方案,所述线辊包括辊体,所述辊体两端设置有侧板,所述辊轴轴向贯穿所述辊体和侧板;As a preferred solution of the present invention, the wire roller includes a roller body, side plates are arranged at both ends of the roller body, and the roller shaft axially passes through the roller body and the side plates;
所述辊轴的外壁两端开设有若干环列分布的卡槽,所述辊轴的外壁套设有两个固定环,所述固定环内腔壁具有与所述卡槽配合的若干第一卡块,两个所述固定环主体均分别通过若干连接螺栓与两侧所述侧板固定安装。The two ends of the outer wall of the roller shaft are provided with a plurality of card slots distributed in ring rows, and the outer wall of the roller shaft is provided with two fixed rings, and the inner cavity wall of the fixed ring has a plurality of first grooves matched with the card slots. The clamping block, the main bodies of the two fixing rings are fixedly installed with the side plates on both sides through a plurality of connecting bolts respectively.
作为本发明的一种优选方案,所述驱动装置包括固定于所述移动组件上的第一筒体安装架,所述第一筒体安装架外端安装有放线电机,所述放线电机的内侧输出端伸入所述筒体安装架并连接有传动板,所述传动板侧壁上设置有若干与所述卡槽配合的第二卡块。As a preferred solution of the present invention, the driving device includes a first cylinder installation frame fixed on the moving assembly, and a pay-off motor is installed on the outer end of the first cylinder installation frame, and the pay-off motor The inner output end of the cylinder extends into the barrel mounting frame and is connected with a transmission plate, and the side wall of the transmission plate is provided with a plurality of second clamping blocks matched with the clamping grooves.
作为本发明的一种优选方案,所述缓冲推压装置包括固定于所述移动组件上的第二筒体安装架,所述第二筒体安装架的内壁设置有直线轴承,所述直线轴承内圈滑动连接有缓冲块,所述缓冲块的内端面上设置有若干与所述卡槽配合的第三卡块,所述缓冲块的外端面上固定连接有滑杆,所述滑杆贯穿所述第二筒体安装架端面并固定连接有限位挡板,所述第二筒体安装架内端面与所述缓冲块的外端面上均分别设置有永磁体。As a preferred solution of the present invention, the buffer pushing device includes a second cylinder installation frame fixed on the moving assembly, the inner wall of the second cylinder installation frame is provided with a linear bearing, and the linear bearing The inner ring is slidably connected with a buffer block, and the inner end surface of the buffer block is provided with a plurality of third blocks that cooperate with the card slots, and the outer end surface of the buffer block is fixedly connected with a slide bar, and the slide bar penetrates The end surface of the second cylinder installation frame is fixedly connected with the limit baffle, and the inner end surface of the second cylinder installation frame and the outer end surface of the buffer block are respectively provided with permanent magnets.
作为本发明的一种优选方案,所述辅助支撑装置包括两个间隔分布、可卡扣于所述底座上的卡板,两个卡板之间固定连接有承接板,所述承接板的顶部安装有千斤顶,千斤顶的顶部输出端固定安装有U形支撑杆,U形支撑杆的左右两端底部与对应的卡板之间还连接有导向伸缩杆,所述U形支撑杆的左右两侧顶端均分别连接有辅助支撑板。As a preferred solution of the present invention, the auxiliary support device includes two clamping plates that are distributed at intervals and can be buckled on the base, and a receiving plate is fixedly connected between the two clamping plates, and the top of the receiving plate A jack is installed, and a U-shaped support rod is fixedly installed on the top output end of the jack, and a guiding telescopic rod is also connected between the bottom of the left and right ends of the U-shaped support rod and the corresponding clamping plate, and the left and right sides of the U-shaped support rod The top ends are respectively connected with auxiliary support plates.
作为本发明的一种优选方案,所述辅助支撑板为弧形,辅助支撑板的内壁均安装有缓冲垫。As a preferred solution of the present invention, the auxiliary support plate is arc-shaped, and buffer pads are installed on the inner walls of the auxiliary support plate.
一种电力施工放线器的使用方法,包括以下工作步骤:A method for using a pay-off device for electric power construction, comprising the following working steps:
第一步:准备盘绕有线缆的线辊,通过丝杆模组调节两侧移动组件相互远离,通过起重机将辊体吊起并放入到两侧移动组件的辅助支撑装置上;The first step: Prepare the wire roll with the cable coiled, adjust the moving components on both sides to move away from each other through the screw module, lift the roll body by a crane and put it on the auxiliary support device of the moving component on both sides;
第二步:通过工具对千斤顶将线辊顶起,并与两侧的限位板的安装孔水平对齐,然后将辊轴与辊体进行固定安装;The second step: use the tool to jack up the wire roller, and align it horizontally with the mounting holes of the limit plates on both sides, and then fix the roller shaft and the roller body;
第三步:通过丝杆模组调节两侧移动组件相互靠拢,辊轴两端穿过对应的限位板的安装孔,对千斤顶进行泄压并将辅助支撑装置从底座上撤出;Step 3: Use the screw module to adjust the moving components on both sides to move closer to each other, and the two ends of the roller shaft pass through the installation holes of the corresponding limit plates to release the pressure on the jack and withdraw the auxiliary support device from the base;
第四步:开启放线电机并调节转速,通过控制放线电机带动辊轴转动,使辊轴实现自动放线。Step 4: Turn on the pay-off motor and adjust the speed, and drive the roller shaft to rotate by controlling the pay-off motor, so that the roller shaft can realize automatic pay-off.
本发明具有如下有益效果:The present invention has following beneficial effects:
1、本发明一种电力施工放线器及其使用方法,放线辊在安装完成后,调节转动电机的转速,转动电机可通过传动板、第二卡块带动中心辊转动,中心辊则进行缓慢的转动,中心辊转动是可实现自动的放线,可降低人工的劳动强度。1. An electric power construction pay-off device and its usage method of the present invention, after the pay-off roller is installed, adjust the rotating speed of the rotating motor, and the rotating motor can drive the center roller to rotate through the transmission plate and the second block, and the center roller will rotate Slow rotation, the rotation of the center roller can realize automatic pay-off, which can reduce the labor intensity of labor.
2、本发明一种电力施工放线器及其使用方法,本发明通过设置辅助支撑机构,可在放线辊放线前进行一个辅助的安装帮助,帮助放线辊能够处于水平被安装的状态,提高本发明放线辊整体的安装效率,并且通过千斤顶以及支撑杆和挡板的支撑,可保证放线辊在调节过程中的稳定性,以及挡板的内壁内设置有对线缆以及放线辊整体进行防护缓冲的缓冲垫,可提高对线缆的保护。2. The present invention provides an electric power construction pay-off and its use method. The present invention provides an auxiliary support mechanism before the pay-off roller can be used for an auxiliary installation, helping the pay-off roller to be installed horizontally. , improve the overall installation efficiency of the pay-off roller of the present invention, and through the support of the jack, the support rod and the baffle, the stability of the pay-off roller in the adjustment process can be ensured, and the inner wall of the baffle is provided with a pair of cables and a release The overall protection and cushioning of the wire roller can improve the protection of the cable.
3、本发明一种电力施工放线器及其使用方法,本发明通过的辅助支撑机构不仅使用简单,而且结构简单,方便操作,只需将两个卡板卡到底座上即可,此外方便面的辅助支撑机构还方便对放线辊的拆卸,在方向完成后,需要拆卸放线辊是,通过调节支撑杆和挡板的高度,可将放线辊从两个限位板之间稳定且安全的拆卸下来,提高了本发明的安全性。3. An electric power construction pay-off device of the present invention and its use method. The auxiliary supporting mechanism adopted by the present invention is not only easy to use, but also simple in structure and easy to operate. It only needs to clamp two clamps on the base. In addition, instant noodles The auxiliary support mechanism also facilitates the disassembly of the pay-off roller. After the direction is completed, the pay-off roller needs to be disassembled. By adjusting the height of the support rod and the baffle, the pay-off roller can be stabilized and moved from between the two limit plates. Safe detachment improves the safety of the present invention.
4、本发明一种电力施工放线器及其使用方法,两组电动液压杆的控制开关可设置在一个控制面板上以及一个控制开关上,可通过电动液压杆调节中心辊的高度,当中心辊上饶的线缆较多时,可通过调节中心辊的高度来满足更换的放线。4. An electric power construction pay-off device and its usage method of the present invention, the control switches of the two groups of electro-hydraulic rods can be set on a control panel and a control switch, and the height of the center roller can be adjusted through the electro-hydraulic rods. When there are many cables on the upper roller, the height of the center roller can be adjusted to meet the changing requirements.
5、本发明一种电力施工放线器及其使用方法,本发明通过设置移动机构,实现了可对放线辊进行快速的安装,再将放线辊保存水平状态后,通过两组支撑柱和对应限位板的相互靠近限位板,使得对中心辊的两端进行了限位,不仅将中心辊进行了限位,还对放线辊进行了限位,保证中心辊的稳定性,从而可提高中心辊放线的稳定性。5. A pay-off device for electric power construction and its use method according to the present invention. By setting a moving mechanism, the present invention realizes the rapid installation of the pay-off roller. The limit plate and the corresponding limit plate are close to each other, so that the two ends of the center roller are limited, not only the center roller is limited, but also the pay-off roller is limited to ensure the stability of the center roller. Thereby, the stability of the center roll pay-off can be improved.
附图说明Description of drawings
图1为本发明正面剖视图;Fig. 1 is a front sectional view of the present invention;
图2为本发明图1中A处放大图;Fig. 2 is the enlarged view of place A in Fig. 1 of the present invention;
图3为本发明图1中B处放大图;Fig. 3 is an enlarged view at B place in Fig. 1 of the present invention;
图4为本发明图1中C处放大图;Figure 4 is an enlarged view at C in Figure 1 of the present invention;
图5为本发明辅助支撑机构立体图;Fig. 5 is a perspective view of the auxiliary support mechanism of the present invention;
图6为本发明中心辊立体图;Fig. 6 is a three-dimensional view of the center roll of the present invention;
图7为本发明传动板立体图。Fig. 7 is a perspective view of the transmission plate of the present invention.
图例说明:illustration:
10、底座;11、螺纹套筒;12、导向块;13、导向槽;15、双头丝杆;16、调距电机;17、电动伸缩杆;18、支撑柱;19、限位板;20、辊体;21、侧板;22、辊轴;23、固定环;24、第一卡块;25、连接螺栓;26、第二筒体安装架;27、缓冲块;28、第三卡块;29、滑杆;30、限位挡板;31、永磁体;32、直线轴承;33、卡槽;34、第一筒体安装架;35、放线电机;36、传动板;37、第二卡块;40、卡板;41、承接板;42、导向伸缩杆;43、U形支撑杆;44、千斤顶;45、辅助支撑板;46、缓冲垫。10. Base; 11. Threaded sleeve; 12. Guide block; 13. Guide slot; 15. Double-headed screw; 16. Distance-adjusting motor; 17. Electric telescopic rod; 18. Support column; 20. Roller body; 21. Side plate; 22. Roller shaft; 23. Fixed ring; 24. First block; 25. Connecting bolt; 26. Second barrel mounting frame; 27. Buffer block; 28. Third Block; 29, sliding rod; 30, limit baffle; 31, permanent magnet; 32, linear bearing; 33, card slot; 34, first cylinder mounting frame; 37, the second clamping block; 40, clamping plate; 41, receiving plate; 42, guide expansion rod; 43, U-shaped support rod; 44, jack; 45, auxiliary support plate; 46, buffer pad.
具体实施方式Detailed ways
下面结合附图和具体实施例来对本发明进行详细的说明。The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.
参见图1-7,一种电力施工放线器,包括底座10,底座10为顶部敞口的矩形箱体,底座10上设置有丝杆模组,丝杆模组包括双头丝杆15,具体的,双头丝杆15转动安装于底座10上,丝杆模组还包括安装于底座10外壁上的调距电机16,调距电机16与双头丝杆15传动连接。Referring to Fig. 1-7, a pay-off device for electric power construction includes a
双头丝杆15的左右两侧对称安装有移动组件,丝杆模组的双头丝杆15旋转时带动两侧移动组件相互靠拢或远离;具体的,移动组件包括与双头丝杆15螺接的螺纹套筒11,螺纹套筒11底部设置有导向块12,底座10顶面开设有与导向块12滑动配合的导向槽13,螺纹套筒11顶部设置有电动伸缩杆17,电动伸缩杆17的上端通过支撑柱18连接有限位板19,限位板19上开设有供辊轴22穿设连接的安装孔。The left and right sides of the double-ended
两侧移动组件之间设置有线辊,线辊包括辊体20,包括辊轴22,转轴两端穿过并架设于两侧移动组件上,辊体20两端设置有侧板21,辊轴22轴向贯穿辊体20和侧板21;辊轴22的外壁两端开设有若干环列分布的卡槽33,辊轴22的外壁套设有两个固定环23,固定环23内腔壁具有与卡槽33配合的若干第一卡块24,两个固定环23主体均分别通过若干连接螺栓25与两侧侧板21固定安装。A wire roller is arranged between the moving components on both sides. The wire roller includes a
其中一侧移动组件外壁安装有用于与辊轴22一端连接以驱动线辊转动的驱动装置,具体的,驱动装置包括固定于移动组件上的第一筒体安装架34,第一筒体安装架34外端安装有放线电机35,放线电机35的内侧输出端伸入筒体安装架34并连接有传动板36,传动板36侧壁上设置有若干与卡槽33配合的第二卡块37。The outer wall of one side of the moving assembly is equipped with a driving device that is connected to one end of the
另一侧移动组件外壁安装有用于抵压辊轴22端部的缓冲推压装置;具体的,缓冲推压装置包括固定于移动组件上的第二筒体安装架26,第二筒体安装架26的内壁设置有直线轴承32,直线轴承32内圈滑动连接有缓冲块27,缓冲块27的内端面上设置有若干与卡槽33配合的第三卡块28,缓冲块27的外端面上固定连接有滑杆29,滑杆29贯穿第二筒体安装架26端面并固定连接有限位挡板30,第二筒体安装架26内端面与缓冲块27的外端面上均分别设置有永磁体31,两个永磁体31相互靠近的一侧壁面为磁极相同的一极,利用磁块同极相斥提供弹性缓冲作用力。The outer wall of the moving assembly on the other side is equipped with a buffer pushing device for resisting the end of the
线辊的底部设置有用于顶撑线辊的辅助支撑装置,辅助支撑装置架设于底座10上,具体的,辅助支撑装置包括两个间隔分布、可卡扣于底座10上的卡板40,两个卡板40之间固定连接有承接板41,承接板41的顶部安装有千斤顶44,千斤顶44的顶部输出端固定安装有U形支撑杆43,U形支撑杆43的左右两端底部与对应的卡板40之间还连接有导向伸缩杆42,U形支撑杆43的左右两侧顶端均分别连接有辅助支撑板45。The bottom of the wire roller is provided with an auxiliary supporting device for supporting the wire roller, and the auxiliary supporting device is erected on the
本发明的工作原理:Working principle of the present invention:
第一步:将饶有线缆的辊体20进行放置时,开启调距电机16,导向块12限位在导向槽13内,使得双头丝杆15转动,两组螺纹套筒11相互远离,使得两组限位板19相互远离,通过起重机将辊体20吊起,将辊体20放入到两组辅助支撑板45内;Step 1: When placing the
第二步:通过工具对千斤顶44进行按压,使得U形支撑杆43对辅助支撑板45以及辅助支撑板45内的辊体20产生往上的顶起,辊体20顶起后,将辊体20的轴心位置与两侧的限位板19调节呈水平对齐的状态,然后将辊轴22穿过辊体20,辊轴22的两端朝向两侧的限位板19,将两个固定环23分别安装到辊轴22的两侧,然后再通过连接螺栓25将固定环23与辊体20固定在一起;Step 2: Press the
第三步:再控制调距电机16动作,使得两组螺纹套筒11做相互靠近的运动,两侧的限位板19相互靠近,辊轴22两端穿过对应的限位板19并穿过限位板19上安装孔,直至辊轴22一端与缓冲块27弹压抵接并与第三卡块28卡合,另一端与传动板36抵接并与第二卡块37卡合,随后关闭调距电机16,再对千斤顶44进行泄压,使得U形支撑杆43往下运动,辅助支撑板45与辊轴22接触分离,再将辅助支撑板45以及U形支撑杆43从底座10上撤出;The third step: control the action of the distance-adjusting
第四步:此时可开启放线电机35的工作开关,调节放线电机35的转速,放线电机35可通过传动板36、第二卡块37带动辊轴22转动,辊轴22则进行缓慢的转动,使辊轴22实现自动放线。Step 4: At this time, the working switch of the pay-
以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。The above is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the description of the present invention and the contents of the accompanying drawings, or directly or indirectly used in other related technologies fields, all of which are equally included in the scope of patent protection of the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211194115.XA CN115402880B (en) | 2022-09-28 | 2022-09-28 | A kind of electric power construction wire release device and its use method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211194115.XA CN115402880B (en) | 2022-09-28 | 2022-09-28 | A kind of electric power construction wire release device and its use method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115402880A true CN115402880A (en) | 2022-11-29 |
CN115402880B CN115402880B (en) | 2024-08-16 |
Family
ID=84167943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211194115.XA Active CN115402880B (en) | 2022-09-28 | 2022-09-28 | A kind of electric power construction wire release device and its use method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115402880B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN118458504A (en) * | 2024-07-09 | 2024-08-09 | 国网山东省电力公司乳山市供电公司 | Wire guiding and paying-off device |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN212075950U (en) * | 2020-04-14 | 2020-12-04 | 深圳市丰光通信工程有限公司 | Communication cable winding and unwinding device for communication engineering |
CN113581920A (en) * | 2021-08-03 | 2021-11-02 | 吴明 | Cable pay-off device for power construction and pay-off method thereof |
WO2022095088A1 (en) * | 2020-11-03 | 2022-05-12 | 郑志敏 | Device for tidy winding of cable for building construction |
-
2022
- 2022-09-28 CN CN202211194115.XA patent/CN115402880B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN212075950U (en) * | 2020-04-14 | 2020-12-04 | 深圳市丰光通信工程有限公司 | Communication cable winding and unwinding device for communication engineering |
WO2022095088A1 (en) * | 2020-11-03 | 2022-05-12 | 郑志敏 | Device for tidy winding of cable for building construction |
CN113581920A (en) * | 2021-08-03 | 2021-11-02 | 吴明 | Cable pay-off device for power construction and pay-off method thereof |
Non-Patent Citations (1)
Title |
---|
曾茂燕;思常红;: "轿车自动升降辅助装置的研究与实施", 装备制造技术, no. 03, 15 March 2019 (2019-03-15) * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN118458504A (en) * | 2024-07-09 | 2024-08-09 | 国网山东省电力公司乳山市供电公司 | Wire guiding and paying-off device |
Also Published As
Publication number | Publication date |
---|---|
CN115402880B (en) | 2024-08-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN115402880A (en) | A kind of power construction pay-off device and using method thereof | |
CN219554788U (en) | Motor coil processing winding device | |
CN217808011U (en) | Cable take-up device | |
CN107701196B (en) | Gantry rock drilling vehicle | |
CN218102315U (en) | Portable transmission line crossing construction device | |
CN117428031A (en) | Automatic wire collecting device of high-precision metal wire drawing machine and working method | |
CN213879074U (en) | Electric power cable installation draw gear | |
CN216122126U (en) | Novel core pulling device of large motor | |
CN204772450U (en) | Material lifts rotatory shifter | |
CN209754343U (en) | Combined welding equipment | |
CN212298192U (en) | Adjustable electromechanical mounting device | |
CN218990964U (en) | Wallboard mounting equipment | |
CN112647989A (en) | Device and method for laying groove cover plate in tunnel | |
CN113572318A (en) | Novel core pulling device of large motor | |
CN222735979U (en) | Stator and rotor chip assembly clamping device | |
CN216967657U (en) | Stator and rotor assembling device for motor production line | |
CN222249897U (en) | Auxiliary lifting device for mounting electrical equipment on top side of mine roadway | |
CN218236940U (en) | Duplex position reciprocating motion formula cell phone stand roughness check out test set | |
CN221547971U (en) | Lifting device for pipeline design | |
CN221116441U (en) | Cable winding guide device for communication engineering construction | |
CN222376119U (en) | Auxiliary supporting device for building decoration | |
CN217552229U (en) | Trompil device is used in construction of assembled superimposed sheet | |
CN222007043U (en) | Large-scale motor rotor lifts by crane dismouting device | |
CN217889168U (en) | Curvature control device for large steel frame machining | |
CN213753794U (en) | Laborsaving cable pulls auxiliary device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |