CN115387242A - Method for erecting sliding support structure of extra-large steel bridge section - Google Patents

Method for erecting sliding support structure of extra-large steel bridge section Download PDF

Info

Publication number
CN115387242A
CN115387242A CN202211244232.2A CN202211244232A CN115387242A CN 115387242 A CN115387242 A CN 115387242A CN 202211244232 A CN202211244232 A CN 202211244232A CN 115387242 A CN115387242 A CN 115387242A
Authority
CN
China
Prior art keywords
steel pipe
bailey
support structure
steel
sliding support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211244232.2A
Other languages
Chinese (zh)
Inventor
何文生
唐一中
戴凤波
孙路
黄华
徐咏春
仇卫冲
田涛
王晶菁
徐小怀
徐怀俊
沈嘉骅
喻加彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN202211244232.2A priority Critical patent/CN115387242A/en
Publication of CN115387242A publication Critical patent/CN115387242A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种特大钢桥梁段滑移支撑结构的搭设方法,其特点是采用钢管桩与贝雷纵梁组合的滑移支撑结构,具体搭设包括:钢管桩施工、平联钢管桩及斜撑、吊装贝雷纵梁、安装补强支撑架、侧向限位架、枕梁、轨道梁和超载预压等步骤。本发明与现有技术相比具有滑移支撑结构承载力大,可满足特大钢桥梁段的滑移施工,结构简单,装配效率高,制作安装便捷,桥位搭设的支架量少,大大缩短了现场安装工期,受大风、雨等不利环境的影响小,钢箱梁焊接质量得到了进一步保证,确保了特大斜拉桥超宽分离式钢箱梁高效、高质量架设,实现了经济合理及高效安全的目标,具有良好的应用前景。

Figure 202211244232

The invention discloses a method for erecting a sliding support structure of an extra-large steel bridge section, which is characterized in that the sliding support structure combined with steel pipe piles and Bailey longitudinal beams is adopted, and the specific erection includes: construction of steel pipe piles, parallel connection of steel pipes Pile and braces, hoisting Bailey longitudinal beams, installing reinforcement support frames, lateral limit frames, corbel beams, track beams, and overload preloading. Compared with the prior art, the present invention has a large bearing capacity of the sliding support structure, which can meet the sliding construction of super large steel bridge sections, has a simple structure, high assembly efficiency, convenient production and installation, and less support for bridge erection, which greatly shortens the construction time. The on-site installation period is less affected by adverse environments such as strong winds and rain, and the welding quality of steel box girders has been further guaranteed, ensuring efficient and high-quality erection of ultra-wide and separated steel box girders for extra-large cable-stayed bridges, achieving economical rationality and high efficiency It is a safe target and has a good application prospect.

Figure 202211244232

Description

一种特大钢桥梁段滑移支撑结构的搭设方法A method of erecting a sliding support structure for an extra-large steel bridge section

技术领域technical field

本发明涉及钢结构桥梁施工技术领域,尤其是一种特大钢桥梁段滑移支撑结构的搭设方法。The invention relates to the technical field of steel structure bridge construction, in particular to a method for erecting a sliding support structure of an extra-large steel bridge section.

背景技术Background technique

特大钢桥梁段划分时呈大节段趋势,尽可能的工厂内进行大节段预制,现场支架法散拼对钢桥梁段拼装质量、精度不利,尤其大风、大雨等影响构件焊接质量。为此大节段预制整体安装是当前钢桥施工的主要思路,对于岸侧长距离大节段无法实现浮吊吊装至设计位置,需要将梁段吊装至江侧拼装支架上进行逐节段滑移。陆上滑移支架体系一般采用格构式,水上滑移支架体系可采取格构式或框架式,根据钢桥梁段截面形式、重量、河床地质情况等综合确定。The division of extra-large steel bridge sections tends to be large sections. Prefabrication of large sections in the factory is carried out as much as possible. The loose assembly of on-site support method is not good for the assembly quality and accuracy of steel bridge sections, especially strong winds and heavy rains affect the welding quality of components. For this reason, the prefabricated overall installation of large sections is the main idea of the current steel bridge construction. For the long-distance large sections on the shore side, it is impossible to lift them to the design position by floating crane. shift. The sliding support system on land generally adopts the lattice type, and the sliding support system on the water can adopt the lattice type or frame type, which is determined comprehensively according to the section form, weight, and geological conditions of the riverbed of the steel bridge section.

现有技术的滑移支撑采用钢管桩基础、焊接主纵梁支撑结构形式,主纵梁一般采用焊接箱型或承载能力大的桁架,但成本较高、施工周期长、材料需求量大。为了满足超重、超宽、大型分离式梁段先单侧滑移后整体滑移的施工需求,提供一种施工工期短、材料可周转使用、经济高效、安全合理的支架体系是滑移支撑结构设计的关键。The sliding support in the prior art adopts steel pipe pile foundation and welded main longitudinal beam support structure. The main longitudinal beam generally adopts welded box type or truss with large bearing capacity, but the cost is high, the construction period is long, and the demand for materials is large. In order to meet the construction needs of overweight, ultra-wide, and large separated beam sections that slide on one side and then slide as a whole, providing a support system with a short construction period, reusable materials, economical efficiency, safety and reasonableness is the key to the design of sliding support structures. The essential.

发明内容Contents of the invention

本发明的目的是针对现有技术的不足而提供的一种特大钢桥梁段滑移支撑结构的搭设方法,采用钢管桩与贝雷纵梁组合的支撑结构,贝雷纵梁由桁架单元纵向、横向连接组成,并设置在联排钢管桩的横梁上,支撑结构具有承载力大,可满足特大钢桥梁段的滑移施工,结构简单,装配效率高,制作安装便捷,桥位搭设的支架量少,大大缩短了现场安装工期,受大风、雨等不利环境的影响小,钢箱梁焊接质量得到了进一步保证,确保了特大斜拉桥超宽分离式钢箱梁高效、高质量架设,实现了经济合理及高效安全的目标,具有良好的应用前景。The object of the present invention is to provide a method for erecting a sliding support structure of a super large steel bridge section in view of the deficiencies in the prior art. , horizontal connection, and set on the crossbeam of the row of steel pipe piles, the supporting structure has a large bearing capacity, which can meet the sliding construction of the super large steel bridge section, the structure is simple, the assembly efficiency is high, the production and installation are convenient, and the bridge position The amount of brackets is small, which greatly shortens the on-site installation period, and is less affected by adverse environments such as strong winds and rains. The welding quality of steel box girders is further guaranteed, ensuring the efficient and high-quality erection of ultra-wide separated steel box girders for extra-large cable-stayed bridges , has achieved the goal of economical rationality, high efficiency and safety, and has a good application prospect.

实现本发明目的具体技术方案是:一种特大钢桥梁段滑移支撑结构的搭设方法,其特点是采用钢管桩与贝雷纵梁组合的滑移支撑结构,具体搭设包括以下步骤:The specific technical solution for realizing the object of the present invention is: a method for erecting a sliding support structure of an extra-large steel bridge section, which is characterized in that the sliding support structure adopting steel pipe piles and Bailey longitudinal beams is combined, and the specific erection includes the following steps:

S1、采用旋挖钻成孔施工钢管桩,所述钢管桩采用全站仪放样桩位并实时监测钢管桩偏位、垂直度及进尺情况;S1. Rotary excavation is used to drill holes to construct steel pipe piles, and the steel pipe piles are staked out by a total station and real-time monitoring of steel pipe pile deviation, verticality and footage;

S2、钢管桩的顶标高结合滑移设备高度、钢轨、轨道梁、枕梁、贝雷纵梁以及油缸行程,通过滑移线形插值确定,并控制为负偏差;S2. The top elevation of the steel pipe pile is determined by sliding linear interpolation in combination with the height of the sliding equipment, steel rails, track beams, corbel beams, Bailey longitudinal beams and oil cylinder strokes, and is controlled as a negative deviation;

S3、钢管桩下沉到位后进行该排钢管桩间的平联和斜撑,增加管桩的稳定性;S3. After the steel pipe piles are sunk in place, perform parallel connection and diagonal bracing between the rows of steel pipe piles to increase the stability of the pipe piles;

S4、调节钢管桩的顶标高,施工桩顶的横梁,所述横梁与钢管桩为焊接;S4, adjust the top elevation of the steel pipe pile, construct the crossbeam on the top of the pile, and the crossbeam and the steel pipe pile are welded;

S5、采用分片吊装贝雷纵梁的桁架单元,并用临时支撑侧面防止倾倒,安装桁架销轴,完成第一桁架单元与第二桁架单元之间的纵向连接;S5. The truss unit of the Bailey longitudinal beam is hoisted in pieces, and the side is temporarily supported to prevent tipping, and the truss pin is installed to complete the longitudinal connection between the first truss unit and the second truss unit;

S6、散件安装补强支撑架,利用撑架螺栓横向连接贝雷纵梁;S6. Install the reinforcing support frame in parts, and use the support bolts to connect the Bailey longitudinal beam horizontally;

S7、将侧向限位架安装在贝雷纵梁两侧,并与横梁焊接,所述贝雷纵梁的纵向布置应将桁架单元阴阳头置于钢管桩上部且与中轴线对齐;S7. Install the lateral limiters on both sides of the Bailey longitudinal beam and weld them to the beam. The longitudinal arrangement of the Bailey longitudinal beam should place the male and female heads of the truss unit on the upper part of the steel pipe pile and align with the central axis;

S8、依次定位安装枕梁、轨道梁,滑移支撑结构搭设完毕后对其进行1.1倍超载预压;S8. Position and install the corbel and track beams in sequence, and carry out 1.1 times overload preload on the sliding support structure after erection;

S9、预压合格后定位安装钢轨,控制好直线度、轨道间距和轨道接头处错位,具备滑移设备落轨条件。S9. After the preloading is qualified, position and install the rails, control the straightness, rail spacing and misalignment of the rail joints, and meet the conditions for sliding equipment to fall off the rails.

所述钢管桩为嵌岩桩,嵌入深度按设计要求确定。The steel pipe piles are rock-socketed piles, and the embedding depth is determined according to design requirements.

所述钢管桩之间通过钢管或双拼槽钢进行平联,钢管桩的间距根据工况确定,为贝雷桁架单元标准长度3m的倍数,且不大于12m。The steel pipe piles are parallel connected through steel pipes or double channel steel, and the distance between the steel pipe piles is determined according to the working conditions, which is a multiple of 3m of the standard length of the Bailey truss unit and is not greater than 12m.

贝雷纵梁由若干标准321桁架单元通过横向、纵向连接组成,其桁架单元间距为200mm。The Bailey longitudinal beam is composed of several standard 321 truss units connected horizontally and vertically, and the distance between the truss units is 200mm.

所述补强支撑架安装在桁架单元接头处,并通过标准321贝雷架撑架螺栓进行栓接,其开设的螺栓孔直径为24mm,孔间距为200mm。The reinforcing support frame is installed at the joint of the truss unit, and is bolted through the standard 321 Bailey frame support bolts. The diameter of the bolt holes is 24mm, and the hole spacing is 200mm.

所述桁架销轴的长度为贝雷纵梁宽度的1/2,连接时从外侧打入桁架孔。The length of the truss pin is 1/2 of the width of the Bailey beam, and it is driven into the truss hole from the outside during connection.

所述枕梁布置的间距为1.5m。The spacing between the corbels is 1.5m.

所述钢轨的标高应根据滑移线形插值确定,钢轨的轨道卡板间距为0.5m。The elevation of the rail should be determined according to the slip linear interpolation, and the distance between the rail clamping plates of the rail is 0.5m.

本发明与现有技术相比具有滑移支撑结构承载力大,可满足特大钢桥梁段的滑移施工,结构简单,装配效率高,制作安装便捷,桥位搭设的支架量少,大大缩短了现场安装工期,受大风、雨等不利环境的影响小,钢箱梁焊接质量得到了进一步保证,确保了特大斜拉桥超宽分离式钢箱梁高效、高质量架设,实现了经济合理及高效安全的目标,具有良好的应用前景。Compared with the prior art, the present invention has a large bearing capacity of the sliding support structure, which can meet the sliding construction of super large steel bridge sections, has a simple structure, high assembly efficiency, convenient production and installation, and less support for the bridge position, which greatly shortens the construction time. The on-site installation period is less affected by adverse environments such as strong winds and rain, and the welding quality of steel box girders has been further guaranteed, ensuring the efficient and high-quality erection of super-wide separated steel box girders for extra-large cable-stayed bridges, achieving economical rationality and high efficiency It is a safe target and has a good application prospect.

附图说明Description of drawings

图1为本发明的支撑结构示意图;Fig. 1 is a schematic diagram of a supporting structure of the present invention;

图2为图1的 A-A剖视图;Fig. 2 is A-A sectional view of Fig. 1;

图3为图1的

Figure 768455DEST_PATH_IMAGE002
节点结构示意图; Figure 3 is for Figure 1
Figure 768455DEST_PATH_IMAGE002
Schematic diagram of the node structure;

图4为图3的B-B剖视图。Fig. 4 is a B-B sectional view of Fig. 3 .

具体实施方式Detailed ways

以下通过具体实施对本发明作进一步的详细说明。The present invention will be further described in detail through specific implementation below.

实施例1Example 1

参阅图1~图2,本发明采用平联的钢管桩上设置横梁与贝雷纵梁组合的滑移支撑结构,具体搭设包括以下步骤:Referring to Fig. 1~Fig. 2, the present invention adopts the sliding supporting structure that crossbeam and Bailey longitudinal beam combination are set on the steel pipe pile of parallel connection, specifically set up and comprise the following steps:

S1、采用旋挖钻成孔施工嵌岩钢管桩1,钢管桩1采用全站仪放样桩位并实时监测钢管桩1偏位、垂直度及进尺情况;S1. The rock-socketed steel pipe pile 1 is constructed by rotary drilling and drilling. The steel pipe pile 1 uses a total station to stake out the pile position and monitor the deviation, verticality and footage of the steel pipe pile 1 in real time;

S2、钢管桩1接桩控制好桩顶标高为负偏差;S2. The steel pipe pile 1 is connected to the pile and the pile top elevation is controlled to be a negative deviation;

S3、钢管桩1下沉到位后,进行该排钢管桩1间平联、斜撑,增加桩的稳定性。S3. After the steel pipe piles 1 are sunk in place, carry out parallel connection and diagonal bracing between the row of steel pipe piles to increase the stability of the piles.

S4、调节钢管桩1顶标高,施工桩顶横梁2,横梁2与钢管桩1焊接。S4. Adjust the elevation of the top of the steel pipe pile 1, construct the beam 2 on the top of the pile, and weld the beam 2 to the steel pipe pile 1.

S5、分片吊装贝雷纵梁桁架单元,并用临时支撑侧面防止倾倒,安装桁架销轴31,完成第一桁架单元、第二桁架单元之间纵向连接。S5. Hoist the Bailey longitudinal beam truss unit in pieces, and use temporary support to prevent the side from toppling over, install the truss pin 31, and complete the longitudinal connection between the first truss unit and the second truss unit.

S6、散件安装补强支撑架32,利用撑架螺栓33横向连接贝雷纵梁。S6. Install the reinforcing support frame 32 in bulk, and use the support bolt 33 to connect the Bailey longitudinal beam horizontally.

S7、将侧向限位架34安装在贝雷纵梁两侧与横梁2焊接。S7. Install the lateral limit frame 34 on both sides of the Bailey longitudinal beam and weld it to the beam 2.

S8、依次定位安装枕梁、轨道梁,对滑移支撑结构进行1.1倍超载预压。S8. Position and install the corbel and track beams in sequence, and carry out 1.1 times overload preloading on the sliding support structure.

S9、预压合格后定位安装钢轨,控制好直线度、轨道间距、轨道接头处错位,具备滑移设备落轨条件。S9. After the preloading is qualified, position and install the rails, control the straightness, rail spacing, and misalignment of the rail joints, and meet the conditions for sliding equipment to fall off the rails.

参阅图1~图2,本发明的滑移支撑结构采用钢管桩与贝雷梁结合的支撑体系,该滑移支撑结构由钢管桩1、横梁2、贝雷纵梁3、枕梁4、轨道梁5、钢轨6和滑移设备7组成;所述钢管桩1是滑移支撑结构基础,采用螺旋焊接钢管;所述横梁2为双拼或三拼工字钢形式,腹板两侧设置有加劲板21;所述枕梁4为固定设置在贝雷纵梁3上,且垂直于钢桥轴线的H型钢;所述轨道梁5为H型钢结构,置于枕梁4翼缘上侧,且与枕梁4上翼缘焊接连接;所述钢轨6置于轨道梁5上部与其中线平齐布置,钢轨6与轨道梁5利用卡板61卡压固定;所述滑移设备7置于钢轨6上侧用于钢箱梁滑移施工;所述侧向限位支架34置于贝雷架两侧,焊接在横梁2上侧,防止贝雷纵梁侧向偏移。Referring to Fig. 1~Fig. 2, the sliding supporting structure of the present invention adopts the support system that steel pipe pile and Bailey beam combine, and this sliding supporting structure is made up of steel pipe pile 1, crossbeam 2, Bailey longitudinal beam 3, corbel 4 , track beam 5, steel rail 6 and sliding equipment 7; the steel pipe pile 1 is the foundation of the sliding support structure, and adopts spiral welded steel pipe; A stiffening plate 21 is provided on the side; the corbel 4 is an H-shaped steel fixedly arranged on the Bailey longitudinal beam 3 and perpendicular to the axis of the steel bridge; the track beam 5 is an H-shaped steel structure placed on the flange of the corbel 4 The upper side is welded to the upper flange of the corbel 4; the rail 6 is placed on the upper part of the track beam 5 and arranged flush with its midline, and the rail 6 and the track beam 5 are fixed by clamping plate 61; the sliding device 7 is placed on the upper side of the rail 6 for the sliding construction of the steel box girder; the lateral limit bracket 34 is placed on both sides of the Bailey frame and welded on the upper side of the beam 2 to prevent the Bailey longitudinal beam from laterally shifting.

参阅图3~图4,所述贝雷纵梁3由第一桁架单元35、第二桁架单元36、桁架销轴31、补强支撑架32、撑架螺栓33、侧向限位支架34组成;所述第一桁架单元35、第二桁架单元36采用标准贝雷桁架单元,第一桁架单元35、第二桁架单元36之间阴阳头通过桁架销轴31进行连接,桁架单元之间采用补强支撑架32进行横向连接;所述侧向限位支架34置于贝雷架两侧,焊接在横梁2上侧,防止贝雷纵梁侧向偏移;所述桁架销轴31为特制机加工销轴,用于连接桁架单元阴阳头;所述补强支撑架32由槽钢或角钢焊接组成,通过撑架螺栓33横向连接贝雷桁架单元。Referring to Figures 3 to 4, the Bailey longitudinal beam 3 is composed of a first truss unit 35, a second truss unit 36, a truss pin 31, a reinforcing support frame 32, a support bolt 33, and a lateral limit bracket 34. ; The first truss unit 35 and the second truss unit 36 adopt standard Bailey truss units, the male and female ends between the first truss unit 35 and the second truss unit 36 are connected by truss pins 31, and the truss units are supplemented The strong support frame 32 is connected horizontally; the lateral limit bracket 34 is placed on both sides of the Bailey frame and welded on the upper side of the beam 2 to prevent the lateral deviation of the Bailey longitudinal beam; the truss pin 31 is a special machine Processing pin shafts are used to connect the male and female heads of the truss units; the reinforcement support frame 32 is composed of channel steel or angle steel welded, and the Bailey truss units are connected horizontally through the support bolts 33 .

以上只是对本发明作进一步的说明,并非用以限制本专利,凡为本发明等效实施,均应包含于本专利的权利要求范围之内。The above is only a further description of the present invention, and is not intended to limit this patent. All equivalent implementations of the present invention should be included in the scope of claims of this patent.

Claims (8)

1.一种特大钢桥梁段滑移支撑结构的搭设方法,其特征在于采用平联的钢管桩上设置横梁与贝雷纵梁组合的滑移支撑结构,具体搭设包括以下步骤:1. A method for setting up the sliding support structure of an extra-large steel bridge section is characterized in that the steel pipe pile of the parallel connection is used to set the sliding support structure of the crossbeam and Bailey longitudinal beam combination, and the specific setting up comprises the following steps: S1、采用旋挖钻成孔施工钢管桩,所述钢管桩采用全站仪放样桩位并实时监测钢管桩偏位、垂直度及进尺情况;S1. Rotary excavation is used to drill holes to construct steel pipe piles, and the steel pipe piles are staked out by a total station and real-time monitoring of steel pipe pile deviation, verticality and footage; S2、钢管桩的顶标高结合滑移设备高度、钢轨、轨道梁、枕梁、贝雷纵梁以及油缸行程,通过滑移线形插值确定,并控制为负偏差;S2. The top elevation of the steel pipe pile is determined by sliding linear interpolation in combination with the height of the sliding equipment, steel rails, track beams, corbel beams, Bailey longitudinal beams and oil cylinder strokes, and is controlled as a negative deviation; S3、钢管桩下沉到位后进行该排钢管桩间的平联和斜撑;S3. After the steel pipe piles are sunk in place, perform parallel connection and diagonal bracing between the row of steel pipe piles; S4、调节钢管桩的顶标高,施工桩顶的横梁,所述横梁与钢管桩为焊接;S4, adjust the top elevation of the steel pipe pile, construct the crossbeam on the top of the pile, and the crossbeam and the steel pipe pile are welded; S5、采用分片吊装贝雷纵梁的桁架单元,并用临时支撑侧面防止倾倒,安装桁架销轴,完成第一桁架单元与第二桁架单元之间的纵向连接;S5. The truss unit of the Bailey longitudinal beam is hoisted in pieces, and the side is temporarily supported to prevent tipping, and the truss pin is installed to complete the longitudinal connection between the first truss unit and the second truss unit; S6、安装补强支撑架,利用撑架螺栓横向连接贝雷纵梁;S6, install the reinforcing support frame, and use the support bolts to connect the Bailey longitudinal beam horizontally; S7、将侧向限位架安装在贝雷纵梁两侧,并与横梁焊接,所述贝雷纵梁的纵向布置应将桁架单元阴阳头置于钢管桩上部且与中轴线对齐;S7. Install the lateral limiters on both sides of the Bailey longitudinal beam and weld them to the beam. The longitudinal arrangement of the Bailey longitudinal beam should place the male and female heads of the truss unit on the upper part of the steel pipe pile and align with the central axis; S8、依次定位安装枕梁、轨道梁,滑移支撑结构搭设完毕后对其进行1.1倍超载预压;S8. Position and install the corbel and track beams in sequence, and carry out 1.1 times overload preload on the sliding support structure after erection; S9、预压合格后定位安装钢轨,控制好直线度、轨道间距和轨道接头处错位,具备滑移设备落轨条件。S9. After the preloading is qualified, position and install the rails, control the straightness, rail spacing and misalignment of the rail joints, and meet the conditions for sliding equipment to fall off the rails. 2.根据权利要求1所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述钢管桩为嵌岩桩,嵌入深度按设计要求确定。2. The erection method of the sliding support structure of the extra-large steel bridge section according to claim 1, wherein the steel pipe piles are rock-socketed piles, and the embedding depth is determined according to the design requirements. 3.根据权利要求1所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述贝雷纵梁由若干标准321桁架单元通过横向、纵向连接组成,其桁架单元间距为200mm。3. The erection method of the sliding support structure of the extra-large steel bridge section according to claim 1, wherein the Bailey longitudinal beam is composed of several standard 321 truss units connected horizontally and vertically, and the distance between the truss units is 200mm. 4.根据权利要求1所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述补强支撑架安装在桁架单元接头处,并通过标准321贝雷架撑架螺栓进行栓接,其开设的螺栓孔直径为24mm,孔间距为200mm。4. according to the erection method of the sliding support structure of the super large steel bridge section of claim 1, it is characterized in that the reinforcing support frame is installed at the joint of the truss unit, and is bolted by standard 321 Bailey frame support bolts, The diameter of the bolt holes opened is 24mm, and the hole spacing is 200mm. 5.根据权利要求1所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述桁架销轴的长度为贝雷纵梁宽度的1/2,连接时从外侧打入桁架孔。5. The erection method of the sliding support structure of the extra-large steel bridge section according to claim 1, characterized in that the length of the truss pin is 1/2 of the width of the Bailey longitudinal beam, and the truss hole is driven from the outside when connecting. 6.根据权利要求1所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述枕梁设置的间距为1.5m。6. The erection method of the sliding support structure of the extra-large steel bridge section according to claim 1, characterized in that the distance between the corbels is 1.5m. 7.根据权利要求1所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述钢轨的标高根据滑移线形插值确定,钢轨的轨道卡板间距为0.5m。7. The erection method of the sliding support structure of the extra-large steel bridge section according to claim 1, characterized in that the elevation of the rail is determined according to slip line interpolation, and the distance between rail clamping plates of the rail is 0.5m. 8.根据权利要求1或权利要求2所述特大钢桥梁段滑移支撑结构的搭设方法,其特征在于所述钢管桩之间通过钢管或双拼槽钢进行平联,钢管桩的间距为贝雷桁架单元标准长度3m的倍数,且不大于12m。8. According to claim 1 or claim 2, the erection method of the sliding support structure of the extra-large steel bridge section is characterized in that the steel pipe piles are connected in parallel through steel pipes or double channel steel, and the distance between the steel pipe piles is It is a multiple of the standard length of the Bailey truss unit of 3m and not greater than 12m.
CN202211244232.2A 2022-10-12 2022-10-12 Method for erecting sliding support structure of extra-large steel bridge section Pending CN115387242A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211244232.2A CN115387242A (en) 2022-10-12 2022-10-12 Method for erecting sliding support structure of extra-large steel bridge section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211244232.2A CN115387242A (en) 2022-10-12 2022-10-12 Method for erecting sliding support structure of extra-large steel bridge section

Publications (1)

Publication Number Publication Date
CN115387242A true CN115387242A (en) 2022-11-25

Family

ID=84129316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211244232.2A Pending CN115387242A (en) 2022-10-12 2022-10-12 Method for erecting sliding support structure of extra-large steel bridge section

Country Status (1)

Country Link
CN (1) CN115387242A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116856263A (en) * 2023-07-11 2023-10-10 中交第三航务工程局有限公司 Bailey beam fixing device and fixing method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736697A (en) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 Construction method for pushing and furling complete bracket of steel box girders
CN101736699A (en) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 Accurate positioning method of sliding of full-support frame steel box girder
CN108755377A (en) * 2018-06-07 2018-11-06 广西路桥工程集团有限公司 A kind of construction method of deep water intectate steel trestle
CN216640288U (en) * 2021-12-22 2022-05-31 中交第三航务工程局有限公司 Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN217325062U (en) * 2022-04-13 2022-08-30 中交路桥建设有限公司 Assembling sliding support of large-tonnage steel cross beam of cable-stayed bridge cable tower
CN115058957A (en) * 2022-07-01 2022-09-16 中交路桥建设有限公司 Dual-purpose trestle support structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736697A (en) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 Construction method for pushing and furling complete bracket of steel box girders
CN101736699A (en) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 Accurate positioning method of sliding of full-support frame steel box girder
CN108755377A (en) * 2018-06-07 2018-11-06 广西路桥工程集团有限公司 A kind of construction method of deep water intectate steel trestle
CN216640288U (en) * 2021-12-22 2022-05-31 中交第三航务工程局有限公司 Tower-passing sliding platform for steel box girder of cable-stayed bridge
CN217325062U (en) * 2022-04-13 2022-08-30 中交路桥建设有限公司 Assembling sliding support of large-tonnage steel cross beam of cable-stayed bridge cable tower
CN115058957A (en) * 2022-07-01 2022-09-16 中交路桥建设有限公司 Dual-purpose trestle support structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116856263A (en) * 2023-07-11 2023-10-10 中交第三航务工程局有限公司 Bailey beam fixing device and fixing method

Similar Documents

Publication Publication Date Title
CN110847063B (en) Method for dismantling multi-span double-arch bridge
CN110847062A (en) Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory
CN110424411B (en) Irregular foundation pit assembled steel supporting device and construction application method thereof
CN110847169A (en) Construction method of steel pipe pile steel trestle
WO2025222845A1 (en) Self-balancing modular fully-prefabricated elevated station transition structure construction method and structure
CN108560562A (en) A kind of stay length adjustable deep foundation pit support prestressing force fish belly sill
CN115387242A (en) Method for erecting sliding support structure of extra-large steel bridge section
CN117449320A (en) Construction and monitoring methods of support system for semi-covered excavation foundation pits of subway stations in floodplain soft soil areas
CN218345972U (en) Sliding support structure for extra-large steel bridge section
CN212077961U (en) Lattice type section steel combined supporting system
CN111088904B (en) An integral hoisting device and process for a 100-meter-high cylindrical iron chimney steel frame
CN115679840A (en) A Sliding Support Structure for Extra Large Steel Bridge Sections
CN111608085A (en) An all-welded steel truss girder aqueduct erection method
CN112144413A (en) Whole-span in-situ splicing and erecting method for steel-concrete composite beam in mountainous area
CN112177042A (en) Rail transit station construction method without affecting ground traffic
CN118360949A (en) A large-area deep foundation pit support system and construction method
CN214657161U (en) Rectangular staggered joint assembled well wall structure
CN113863736B (en) Construction process of continuous-span common-column C-shaped stock yard
CN113897968B (en) Mounting system for assembling, sinking and positioning water surface under water-moving condition of block-type hydraulic building
CN116479781A (en) Construction method for large-span prefabricated steel-concrete composite beam
CN103374916B (en) Pre-pressure steel arch foundation pit supporting construction
CN114737626A (en) Foundation reinforcement construction method during bridge operation
CN211922713U (en) A difference settlement orthotic devices for underground pipe gallery construction
CN114215072B (en) Lifting type foundation pit construction platform and using method thereof
CN113774797B (en) Urban mountain forest assembled steel structure pedestrian overpass installation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20221125