CN115387228A - A high-stability steel truss girder jacking and floating drag frame construction method - Google Patents

A high-stability steel truss girder jacking and floating drag frame construction method Download PDF

Info

Publication number
CN115387228A
CN115387228A CN202211030400.8A CN202211030400A CN115387228A CN 115387228 A CN115387228 A CN 115387228A CN 202211030400 A CN202211030400 A CN 202211030400A CN 115387228 A CN115387228 A CN 115387228A
Authority
CN
China
Prior art keywords
steel truss
truss girder
floating
sliding
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211030400.8A
Other languages
Chinese (zh)
Inventor
王建国
陈诗伟
王钦国
任龄
贾秀峰
王金彧
刘振言
曾希琦
娄猛
刘凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Shanqiao Nantong Co ltd
Original Assignee
China Railway Shanqiao Nantong Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Shanqiao Nantong Co ltd filed Critical China Railway Shanqiao Nantong Co ltd
Priority to CN202211030400.8A priority Critical patent/CN115387228A/en
Publication of CN115387228A publication Critical patent/CN115387228A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a high-stability steel truss girder pushing and floating bracket construction method, and relates to the technical field of steel truss girder floating bracket construction. Preparing a steel truss girder before floating and towing construction: a platform is built on a pier, and a slide way and a sliding device are arranged; manufacturing a bracket on a floating ship; the steel truss girder is assembled and the floating towing bracket is arranged: assembling a steel truss girder with a plurality of sections above the slideway, assembling the steel truss girder by two rounds, moving the steel truss girder to piers at two sides by four-time pushing and floating dragging, and finally dropping the steel truss girder. The invention has the advantages that: by adopting the overall construction method of on-site assembly, slippage and floating, the steel truss beam is integrally assembled by two-time assembly, the problem that the operation site of the floating crane is limited is solved, the construction is not limited by the site, and the operation difficulty is reduced; the cantilever of the steel truss girder is large, the floating drag construction difficulty is reduced by pushing and floating drag for multiple times, the floating drag ship construction is more stable, and the navigation requirement can be ensured in the construction.

Description

一种稳定性高的钢桁梁顶推加浮拖架设施工方法A high-stability steel truss girder jacking and floating drag frame construction method

技术领域technical field

本发明涉及钢桁梁浮拖架设施工技术领域,具体涉及一种稳定性高的钢桁梁顶推加浮拖架设施工方法。The invention relates to the technical field of construction of a steel truss girder floating tow frame, in particular to a construction method of a steel truss girder pushing and floating tow frame with high stability.

背景技术Background technique

随着我国桥梁技术的快速发展,各种跨江河的桥梁形式层出不穷,尤其是钢桁梁以建筑高度低、样式美观、跨度大等优势在铁路、公路以及城市轨道交通中被大量使用。目前,在沿海城市及内陆河流较多的城市中修建铁路桥、高架桥的过程中,常会出现大跨度钢桁梁跨越通航运河的情况。With the rapid development of bridge technology in our country, various forms of bridges across rivers emerge in an endless stream, especially steel truss girders are widely used in railways, highways and urban rail transit due to their advantages of low building height, beautiful style and large span. At present, in the process of building railway bridges and viaducts in coastal cities and cities with many inland rivers, it often happens that large-span steel trusses cross navigable canals.

桥梁架设的施工方法有采用架梁吊机进行悬臂架设施工法、顶推或拖拉施工法。悬臂架设施工法存在需要大型的起吊设备或是构件定位拼装效率较低的缺陷;而采用顶推或拖拉施工法则需要设置导梁,以减小最大伸臂状态下结构的内力及倾覆力矩,其施工配套设施繁多,且需要多次体系转换,操作繁琐,施工效率较低。另外,以上方式在工程施工期间需封航,影响水上通行。The construction methods of bridge erection include cantilever erection construction method using girder crane, jacking or dragging construction method. The cantilever construction method has the disadvantages of requiring large-scale lifting equipment or low component positioning and assembly efficiency; while the push or drag construction method needs to set up guide beams to reduce the internal force and overturning moment of the structure at the maximum outstretched state. There are many supporting facilities for construction, and multiple system conversions are required, the operation is cumbersome, and the construction efficiency is low. In addition, the above methods need to be closed to navigation during the construction period, which will affect water traffic.

浮运拖拉法具有施工周期短、经济性好、断航时间短等优点,对于在有通航要求的河流上作业时优势明显,因此被广泛应用。但是现有技术中,浮运拖拉法是在滑道上直接将钢桁梁整体拼装完成,而实际施工中,浮吊作业会有场地受限的情况,直接整体组装操作困难,且钢桁梁拖拉悬臂较大,直接一次完成顶推使钢桁梁前部节间伸出支架悬空,会增加浮拖的难度,船只容易失稳。需提供一种稳定性高的钢桁梁顶推加浮拖架设施工方法,以使得钢桁梁浮拖架设的施工难度降低,施工过程更稳定,保证通航要求。The floating dragging method has the advantages of short construction period, good economy, and short sailing time. It has obvious advantages when operating on rivers with navigation requirements, so it is widely used. However, in the prior art, the floating and dragging method is to directly assemble the steel truss girder as a whole on the slideway, but in actual construction, the floating crane operation will have limited space, and the direct overall assembly operation is difficult, and the steel truss girder is dragged The cantilever is relatively large, and the jacking can be done directly at one time, so that the front section of the steel truss girder protrudes from the bracket and hangs in the air, which will increase the difficulty of floating towing, and the ship will easily lose stability. It is necessary to provide a construction method of steel truss girder jacking and floating towing frame with high stability, so as to reduce the construction difficulty of steel truss girder floating towing erection, make the construction process more stable, and ensure the navigation requirements.

发明内容Contents of the invention

本发明要解决的技术问题是提供一种稳定性高的钢桁梁顶推加浮拖架设施工方法,能够解决现有技术中浮吊作业会有场地受限的情况、直接整体组装操作困难、直接一次完成顶推使钢桁梁前部节间伸出支架悬空会增加浮拖的难度、船只容易失稳的问题。The technical problem to be solved by the present invention is to provide a high-stability steel truss girder jacking and floating trailer construction method, which can solve the situation of limited space for floating crane operations in the prior art, difficulty in direct overall assembly operation, Directly complete the jacking at one time, so that the front section of the steel truss girder protrudes from the bracket and hangs in the air, which will increase the difficulty of floating towing and the problem that the ship is prone to instability.

为解决上述技术问题,本发明的技术方案为:用于将钢桁梁架设于两侧的两个桥墩上,其特征在于:包括以下步骤:In order to solve the above-mentioned technical problems, the technical solution of the present invention is: for erecting steel truss girders on two bridge piers on both sides, characterized in that it includes the following steps:

S1、钢桁梁浮拖施工前准备:S1. Preparations before construction of steel truss girder floating tow:

S1.1、在桥墩之间的水中打桩设置临时钢管支撑架,并在架设钢桁梁的桥墩上设锚碇支架供悬臂浮拖用;在桥墩上建设平台,在平台的顶部架设纵梁,并在纵梁上设置滑道和滑移设备,滑道上设置垫块;S1.1. Set up temporary steel pipe support frames by piling in the water between the bridge piers, and set anchor brackets on the bridge piers erected with steel truss girders for cantilever floating towing; build a platform on the bridge piers, and erect longitudinal beams on the top of the platform, And set the slideway and sliding equipment on the longitudinal beam, and set the pad on the slideway;

S1.2、制作支架,将支架整体吊装到浮拖船舶的船舱中,并将支架与浮拖船舶的船体焊接牢固;S1.2, making the bracket, hoisting the bracket as a whole into the cabin of the floating towing ship, and welding the bracket and the hull of the floating towing ship firmly;

S2、钢桁梁拼装和浮拖架设:在滑道的上方拼装具有多个节间的钢桁梁,钢桁梁置于垫块上,考虑后场的浮吊作业场地受限,钢桁梁的组拼顺序为从大桩侧往小桩侧进行两轮组拼,再进行浮拖架设:S2. Assembly of steel truss girders and erection of floating tow: Assemble steel truss girders with multiple internodes above the slideway, and place the steel truss girders on pads. The order of assembly is two-wheel assembly from the side of the large pile to the side of the small pile, and then the floating tow erection:

S2.1、第一次组拼:从大桩侧开始组拼,除了小桩侧的最后一个节间构件外,其余节间构件组拼完成;S2.1. The first assembly: assemble from the side of the large pile, except for the last internode component on the side of the small pile, the assembly of other internode components is completed;

S2.2、第一次顶推:待第一次组拼、焊接并检测合格后,拆除与钢管支撑架间的临时连接,启动滑移设备,钢桁梁进行第一轮滑移施工,钢桁梁前端向浮拖方向滑移,钢桁梁前部一个节间伸出钢管支撑架悬空,悬臂1个节间,完成第一轮钢桁梁滑移施工;S2.2. The first push: After the first assembly, welding and inspection are qualified, the temporary connection with the steel pipe support frame is removed, the sliding equipment is started, and the steel truss girder is subjected to the first round of sliding construction. The front end of the truss girder slides in the direction of floating towing, and a section at the front of the steel truss girder protrudes from the steel pipe support frame to hang in the air, and cantilever 1 section, completing the first round of steel truss girder sliding construction;

S2.3、第二次组拼:钢桁梁进行第二次组拼,组拼最后一个节间构件,钢桁梁整体组拼完成;S2.3, the second assembly: the steel truss girder is assembled for the second time, the last internode member is assembled, and the overall assembly of the steel truss girder is completed;

S2.4、第二次顶推:二次顶推将钢桁梁继续向前推进一个节间,钢桁梁悬臂2个节间;S2.4, the second push: the second push pushes the steel truss beam forward by one section, and the steel truss cantilever has two sections;

S2.5、向浮拖船舱内压水下沉,支架顶部低于钢桁梁底部,然后将浮拖移至钢桁梁悬臂的第三个节点处,支架对准第三个节点,抽去浮拖船舱内压仓水,支架上浮托起钢桁梁前端,使得钢桁梁悬空10cm,拆除钢桁梁尾部各节点支点,拆除滑道上的垫块,仅通过钢桁梁尾端支点和支架支点两个支点受力,对钢桁梁进行支承;S2.5. Press water into the cabin of the floating tugboat to sink, the top of the support is lower than the bottom of the steel truss girder, then move the floating tow to the third node of the steel truss beam cantilever, align the support with the third node, and pull it out Ballast the water in the cabin of the floating tugboat, and the front end of the steel truss girder is lifted up by the support, so that the steel truss girder is suspended 10cm in the air, and the fulcrums of the nodes at the rear of the steel truss girder are removed, and the pads on the slideway are removed. The two fulcrums of the fulcrum bear force and support the steel truss girder;

S2.6、第三次顶推:启动钢桁梁尾部的滑移设备,将钢桁梁第三次向前顶推,至钢桁梁悬臂3个节间,钢桁梁尾部支点位于两组钢管支撑架中间位置,浮拖同时向前移动;S2.6. The third push: activate the sliding equipment at the tail of the steel truss girder, push the steel truss girder forward for the third time, to the 3 nodes of the steel truss girder cantilever, the fulcrum of the steel truss girder tail is located in the two groups In the middle position of the steel pipe support frame, the floating drag moves forward at the same time;

S2.7、第四次顶推:启动钢桁梁尾部的滑移设备,将钢桁梁向前滑移,浮拖及其上的支架随钢桁梁滑移速度,通过前行绞车和钢桁梁一同前进,并监控钢桁梁及浮拖运行方向,采用绞车的方向控制缆,稳定浮拖的运行方向,第四次顶推至钢桁梁的尾部到达一侧桥墩的上方,钢桁梁的前端到达另一侧桥墩的上方;S2.7, the fourth push: start the sliding equipment at the end of the steel truss girder, slide the steel truss girder forward, the floating tow and the support on it move with the sliding speed of the steel truss girder, and pass through the forward winch and the steel truss girder Move forward together, and monitor the running direction of the steel truss girder and the floating tow, use the direction control cable of the winch to stabilize the running direction of the floating tow, push the tail of the steel truss girder to the top of one side of the pier for the fourth time, and the steel truss girder The front end reaches the top of the pier on the other side;

S2.8、在两侧的两个桥墩的顶部各设置两台落梁千斤顶,落梁千斤顶设于滑道内侧,钢桁梁落在落梁千斤顶上,钢桁梁浮拖到位后,浮拖船舱内压水下沉,解除浮拖的支架与钢桁梁的约束,移开浮拖,完成浮拖作业,进行落梁施工;S2.8. Set up two drop beam jacks on the top of the two piers on both sides. The drop beam jacks are set on the inside of the slideway. Pressurized water sinks in the cabin, releases the constraints of the support of the floating tow and the steel truss girder, removes the floating tow, completes the floating tow operation, and proceeds to the beam drop construction;

S2.9、拆除一侧的桥墩与钢管支撑架之间的贝雷架支架和架梁设备,并安装支座,然后进行落梁施工,落梁时采用等比落梁进行控制,钢桁梁落于两侧的桥墩上完成钢桁梁的架设。S2.9. Remove the Bailey frame support and girder erection equipment between the bridge pier on one side and the steel pipe support frame, and install the support, and then carry out the beam drop construction. The erection of steel truss girders is completed on the piers on both sides.

进一步地,所述步骤S1.2中,所述支架设有两个,两个支架安装于浮拖船舶上,所述支架通过钢管桩和工字钢组焊成,所述工字钢拼接组成支架基础,横向和纵向上各有两根工字钢伸出支架基础的四周,用于和浮拖船舶以及另一侧的支架的连接固定,所述钢管桩立焊于支架基础上作为支架主体,所述钢管桩之间用槽钢做剪刀状支撑,在钢管桩顶部用双拼和四拼工字钢作为分配梁承载钢桁梁,最后将支架整体吊装到浮拖船舶的船舱中,与船体焊接牢固。Further, in the step S1.2, two brackets are provided, and the two brackets are installed on the floating tow ship. The brackets are welded by steel pipe piles and I-beams, and the I-beams are spliced Form the support foundation, two I-beams protrude from the periphery of the support foundation in the horizontal and vertical directions, and are used to connect and fix with the floating towed ship and the support on the other side. The steel pipe piles are welded on the support foundation to serve as The main body of the bracket, the channel steel is used as scissors support between the steel pipe piles, and the double and four-piece I-beams are used as distribution beams on the top of the steel pipe piles to carry the steel truss beams, and finally the whole bracket is hoisted to the floating tow ship In the cabin, it is firmly welded to the hull.

进一步地,所述步骤S2.8中,在桥墩的顶部设置落梁千斤顶前,先通过全站仪测量钢桁梁偏移数据,然后用四台三维落梁千斤顶布置在滑道内侧,同一桥墩顶部的两个落梁千斤顶用一台泵站进行操作,通过PLC控制系统进行钢桁梁的纠偏。Further, in the step S2.8, before setting the drop beam jacks on the top of the pier, first measure the offset data of the steel truss girder with a total station, and then use four three-dimensional drop beam jacks to be arranged on the inside of the slideway, and the same pier The two drop beam jacks on the top are operated by a pump station, and the deflection correction of the steel truss girder is carried out through the PLC control system.

进一步地,所述步骤S1和S2中的滑移设备为液压爬行器,所述液压爬行器为组合式结构,一端以楔形夹块与滑道连接,另一端以铰接点形式与滑移胎架或构件连接,中间利用液压油缸驱动爬行,所述液压爬行器的楔型夹块具有单向自锁作用,当油缸伸出时,楔型夹块工作实现夹紧,自动锁紧滑道;油缸缩回时,夹块不工作实现松开,与油缸同方向移动;Further, the sliding equipment in the steps S1 and S2 is a hydraulic crawler, the hydraulic crawler is a combined structure, one end is connected to the slideway by a wedge-shaped clamp block, and the other end is connected to the sliding tire frame in the form of a hinge point Or the components are connected, and the hydraulic cylinder is used to drive the crawling in the middle. The wedge-shaped clamping block of the hydraulic crawler has a one-way self-locking effect. When the oil cylinder is extended, the wedge-shaped clamping block works to achieve clamping and automatically locks the slideway; the oil cylinder When retracting, the clamp block does not work to achieve release, and moves in the same direction as the oil cylinder;

所述液压爬行器工作流程如下:The working process of the hydraulic crawler is as follows:

步骤1:液压爬行器夹紧装置中楔块与滑道夹紧,液压爬行器的油缸前端活塞杆销轴与滑移构件连接,油缸伸缸,推动滑移构件向前滑移;Step 1: Clamp the wedge and the slideway in the clamping device of the hydraulic crawler, connect the piston rod pin shaft at the front end of the cylinder of the hydraulic crawler to the sliding member, extend the cylinder, and push the sliding member to slide forward;

步骤2:液压爬行器的油缸伸缸一个行程,构件向前滑移300mm;Step 2: The cylinder of the hydraulic crawler is extended for one stroke, and the component slides forward by 300mm;

步骤3:一个行程伸缸完毕,滑移构件不动,油缸缩缸,使夹紧装置中楔块与滑道松开,并拖动夹紧装置向前滑移;Step 3: After the cylinder is extended for one stroke, the sliding member does not move, and the oil cylinder shrinks, so that the wedge in the clamping device and the slideway are released, and the clamping device is dragged to slide forward;

步骤4:液压爬行器一个行程缩缸完毕,拖动夹紧装置向前滑移300mm,一个爬行推进行程完毕,再次执行步骤1工序,如此往复使构件滑移至最终位置。Step 4: After one stroke of the hydraulic crawler is completed shrinking the cylinder, drag the clamping device to slide forward 300mm, and one crawling advance stroke is completed, then perform the process of step 1 again, and reciprocate in this way to slide the component to the final position.

进一步地,所述步骤S2中,浮拖施工过程中,所有滑移设备同步推动钢桁梁滑移,各台滑移设备均匀受载,计算机控制系统通过榕栅传感器反馈距离信号,控制每台滑移设备误差在20mm内,从而控制整个滑移单元的同步滑移,滑移单元对应滑道位置设横向挡块,确保整个滑移过程安全可靠。Further, in the step S2, during the floating construction process, all the sliding equipment synchronously push the steel truss girder to slide, and each sliding equipment is evenly loaded, and the computer control system feeds back the distance signal through the banyan grid sensor to control each The error of the sliding equipment is within 20mm, so as to control the synchronous sliding of the entire sliding unit. The sliding unit is equipped with a transverse stopper corresponding to the position of the slideway to ensure the safety and reliability of the entire sliding process.

进一步地,所述步骤S2.8和S2.9中,落梁施工时,落梁使用的落梁千斤顶,带顶部球形支承垫保险箍,共同作用的多台落梁千斤顶选用同一型号,用油管并联;落梁中,桥墩上的支承面及各垫层间放置石棉板防滑材料;为适应支点水平位移,落梁千斤顶底部设置MGE板垫座,垫座中心与落梁千斤顶中心轴重合,对顶落高程、支点反力、支点位移、跨中挠度的变化,进行观测和记录;在落梁过程中搁置在临时支座上时,应测量相邻两桁支点高差,当高差大于3mm时,调整两支点高程。Further, in the steps S2.8 and S2.9, during the construction of the falling beam, the falling beam jack used for the falling beam has a spherical support pad safety hoop at the top, and the multiple falling beam jacks acting together are selected from the same model, and the oil pipe Parallel connection; in the falling beam, asbestos board anti-skid material is placed between the supporting surface of the bridge pier and each cushion; in order to adapt to the horizontal displacement of the fulcrum, the bottom of the falling beam jack is provided with an MGE plate pedestal, and the center of the pedestal coincides with the central axis of the falling beam jack. Observe and record changes in the top-fall elevation, fulcrum reaction force, fulcrum displacement, and mid-span deflection; when the beam is placed on a temporary support during the fall process, the height difference between the two adjacent truss fulcrums should be measured, and when the height difference is greater than 3mm , adjust the elevation of the two fulcrums.

本发明的优点在于:采用现场拼装加滑移、浮拖的总体施工方法,钢桁梁通过两次组拼完成整体的拼装,解决了浮吊作业场地受限的情况,施工不受场地限制,降低操作难度;The advantage of the present invention is that: the overall construction method of on-site assembly plus sliding and floating towing is adopted, and the steel truss girder is assembled as a whole through two assembly, which solves the situation that the floating crane operation site is limited, and the construction is not limited by the site. Reduce the difficulty of operation;

钢桁梁在两次组拼完成后分别进行两次顶推,直至钢桁梁前端悬臂2个节间,再用浮拖上的支架顶托钢桁梁,支点设在第三个节点处,将钢桁梁拼装支点悬空后撤出调整垫块,仅通过尾部支点和浮拖支点支承钢桁梁,然后向前进行第三次和第四次顶推以及浮拖,直至将钢桁梁移至两侧的桥墩上,再通过落梁施工将钢桁梁最终落在两侧的桥墩上,完成钢桁梁浮拖架设的施工,钢桁梁的悬臂较大,通过分多次顶推加浮拖的方式,降低浮拖施工难度,浮拖船舶施工中更稳定,施工中可确保通航要求。After the steel truss girders are assembled twice, they are respectively pushed twice until the front end of the steel truss girder cantilever two sections, and then the steel truss girder is supported by the support on the floating tow, and the fulcrum is set at the third node. After the fulcrum of the steel truss girder is suspended in the air, withdraw the adjustment block, and only support the steel truss girder through the tail fulcrum and the floating fulcrum, and then carry out the third and fourth push forward and the floating tow until the steel truss girder is moved. to the bridge piers on both sides, and finally drop the steel truss girders on the bridge piers on both sides through the beam drop construction to complete the erection construction of the steel truss girders. The cantilever of the steel truss girders is relatively large. The way of floating towing reduces the difficulty of floating towing construction, and the construction of floating towing ships is more stable, and the navigation requirements can be guaranteed during construction.

附图说明Description of drawings

图1为本发明的浮拖船舶上的支架的结构示意图;Fig. 1 is the structural representation of the support on the floating towing ship of the present invention;

图2为本发明的钢桁梁第一次组拼的示意图;Fig. 2 is the schematic diagram of steel truss girder assembly of the present invention for the first time;

图3为本发明的钢桁梁第一次顶推后的示意图;Fig. 3 is the schematic diagram after the steel truss girder of the present invention pushes for the first time;

图4为本发明的钢桁梁整体组拼的示意图;Fig. 4 is the schematic diagram of the overall assembly of the steel truss girder of the present invention;

图5为本发明的钢桁梁第二次顶推后的示意图;Fig. 5 is the schematic diagram of steel truss girder of the present invention after pushing for the second time;

图6为本发明的浮拖船舶上的支架与钢桁梁的位置示意图;Fig. 6 is the schematic diagram of the position of the bracket and the steel truss beam on the floating tow ship of the present invention;

图7为本发明的钢桁梁第三次顶推后悬臂3个节间的示意图;Fig. 7 is a schematic diagram of three internodes of the cantilever after the steel truss girder of the present invention is pushed for the third time;

图8为本发明的钢桁梁顶推及浮拖后到达两侧的两个桥墩上的示意图;Fig. 8 is a schematic diagram showing that the steel truss girder of the present invention reaches two bridge piers on both sides after being pushed and floated;

图9为本发明的钢桁梁落梁后的示意图。Fig. 9 is a schematic diagram of the steel truss girder of the present invention after falling.

具体实施方式Detailed ways

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及具体实施方式,对本发明进行进一步详细说明。下面的实施例可以使本专业的技术人员更全面地理解本发明,但并不因此将本发明限制在所述的实施例范围之中。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. The following examples can enable those skilled in the art to understand the present invention more comprehensively, but the present invention is not limited to the scope of the described examples.

本具体实施方式的钢桁梁跨径为90m,全宽23m,主桁采用带竖杆的华伦式三角形腹杆体系,节间长度7.4m,主桁高度11m,高跨比 为1/8.07,两片主桁主心距22.1m,宽跨比为1/4.02,桥面宽度20.775m。The steel truss girder in this embodiment has a span of 90m and a full width of 23m. The main truss adopts a Warren triangular web bar system with vertical bars, the internode length is 7.4m, the main truss height is 11m, and the height-span ratio is 1/8.07 , the distance between the two main trusses is 22.1m, the width-span ratio is 1/4.02, and the bridge deck width is 20.775m.

主桥下部结构采用框架式桥墩,桥墩盖梁高2.5m,宽3.3m,材料采用C40混凝土,桥墩采用双柱式墩,横桥向5m,纵桥向2.5m,墩柱采用C40混凝土,承台采用矩形承台,承台厚度3.0m,基础采用10根直径1.5m钻孔灌注桩,桩基采用C30水下混凝土。The substructure of the main bridge adopts frame piers, the pier cover girder is 2.5m high and 3.3m wide, and the material is C40 concrete. The platform adopts a rectangular cap with a thickness of 3.0m. The foundation adopts 10 bored piles with a diameter of 1.5m, and the pile foundation adopts C30 underwater concrete.

本工程项目河面较宽,施工期间不得封航,必须保证通航要求,钢桁梁重量大。The river surface of this project is relatively wide, and the navigation shall not be closed during the construction period, and the navigation requirements must be guaranteed, and the steel truss girders are heavy.

具体施工方法包括以下步骤:The specific construction method includes the following steps:

考虑桥梁结构特点,采用“厂内分段加工+现场拼装+滑移、浮拖”的总体施工思路,在厂内先将钢桁梁分段加工完成,再进行现场拼装。Considering the structural characteristics of the bridge, the overall construction idea of "segmented processing in the factory + on-site assembly + sliding and floating towing" was adopted. The steel truss girders were firstly processed in sections in the factory and then assembled on site.

S1、钢桁梁3浮拖施工前准备:S1. Steel truss girder 3 floating towing preparations before construction:

S1.1、在9#~11#桥墩之间的水中打桩设置临时钢管支撑架,并在架设钢桁梁3的11#桥墩上设锚碇支架供悬臂浮拖用,钢桁梁3最终需要架设在11#和12#桥墩上,9#~11#桥墩上建设平台,在平台的顶部架设纵梁,并在纵梁上设置滑道和滑移设备,滑道上设置垫块。S1.1. Set up temporary steel pipe support frames by piling in the water between piers 9#~11#, and set anchor brackets on pier 11# where steel truss girder 3 is erected for cantilever floating towing. Steel truss girder 3 will eventually need Erection on the 11# and 12# bridge piers, build a platform on the 9#~11# bridge piers, set up the longitudinal beam on the top of the platform, and set the slideway and sliding equipment on the longitudinal beam, and set the pad on the slideway.

滑移设备为液压爬行器,液压爬行器为组合式结构,一端以楔形夹块与滑道连接,另一端以铰接点形式与滑移胎架或构件连接,中间利用液压油缸驱动爬行,液压爬行器的楔型夹块具有单向自锁作用,当油缸伸出时,楔型夹块工作实现夹紧,自动锁紧滑道;油缸缩回时,夹块不工作实现松开,与油缸同方向移动。The sliding equipment is a hydraulic crawler. The hydraulic crawler is a combined structure. One end is connected to the slideway with a wedge-shaped clamp, and the other end is connected to the sliding tire frame or component in the form of a hinge point. The hydraulic cylinder is used to drive the crawler in the middle. The wedge-shaped clamping block of the device has a one-way self-locking effect. When the oil cylinder is extended, the wedge-shaped clamping block works to realize clamping and automatically locks the slideway; when the oil cylinder is retracted, the clamping block does not work to realize loosening. direction to move.

液压爬行器工作流程如下:The working process of the hydraulic crawler is as follows:

步骤1:液压爬行器夹紧装置中楔块与滑道夹紧,液压爬行器的油缸前端活塞杆销轴与滑移构件连接,油缸伸缸,推动滑移构件向前滑移;Step 1: Clamp the wedge and the slideway in the clamping device of the hydraulic crawler, connect the piston rod pin shaft at the front end of the cylinder of the hydraulic crawler to the sliding member, extend the cylinder, and push the sliding member to slide forward;

步骤2:液压爬行器的油缸伸缸一个行程,构件向前滑移300mm;Step 2: The cylinder of the hydraulic crawler is extended for one stroke, and the component slides forward by 300mm;

步骤3:一个行程伸缸完毕,滑移构件不动,油缸缩缸,使夹紧装置中楔块与滑道松开,并拖动夹紧装置向前滑移;Step 3: After the cylinder is extended for one stroke, the sliding member does not move, and the oil cylinder shrinks, so that the wedge in the clamping device and the slideway are released, and the clamping device is dragged to slide forward;

步骤4:液压爬行器一个行程缩缸完毕,拖动夹紧装置向前滑移300mm,一个爬行推进行程完毕,再次执行步骤1工序,如此往复使构件滑移至最终位置。Step 4: After one stroke of the hydraulic crawler is completed shrinking the cylinder, drag the clamping device to slide forward 300mm, and one crawling advance stroke is completed, then perform the process of step 1 again, and reciprocate in this way to slide the component to the final position.

S1.2、制作支架2,将支架2整体吊装到浮拖船舶1的船舱中,并将支架2与浮拖船舶1的船体焊接牢固。S1.2. Make the bracket 2, hoist the bracket 2 as a whole into the cabin of the floating towing vessel 1, and weld the bracket 2 and the hull of the floating towing vessel 1 firmly.

在现场的组装平台上用φ529的钢管桩和I20a、I56的工字钢组焊成如图1中所示的两个支架2,支架2设有两个,两个支架2安装于浮拖船舶1上,支架2通过钢管桩22和工字钢组焊成,工字钢拼接组成支架基础21,横向和纵向上各有两根工字钢伸出支架基础21的四周,用于和浮拖船舶1以及另一侧的支架2的连接固定,钢管桩22立焊于支架基础21上作为支架主体,钢管桩22之间用槽钢做剪刀状支撑,在钢管桩22顶部用双拼和四拼工字钢作为分配梁23承载钢桁梁3,最后将支架2整体吊装到浮拖船舶1的船舱中,与船体焊接牢固。On the site assembly platform, the steel pipe piles of φ529 and the I-beams of I20a and I56 are welded into two brackets 2 as shown in Figure 1. There are two brackets 2 installed on the floating trailer. On the ship 1, the support 2 is welded by steel pipe piles 22 and I-shaped steel, and the I-shaped steel is spliced to form the support foundation 21. There are two I-beams protruding from the surroundings of the support foundation 21 in the horizontal and vertical directions, and are used for and The floating tow ship 1 and the support 2 on the other side are connected and fixed. The steel pipe piles 22 are vertically welded on the support foundation 21 as the main body of the support. Use double and four-piece I-beams as the distribution beam 23 to carry the steel truss girder 3, and finally lift the bracket 2 as a whole into the cabin of the floating towing ship 1, and weld it firmly with the hull.

S2、钢桁梁3拼装和浮拖架设:在滑道的上方拼装具有多个节间的钢桁梁3,钢桁梁3置于垫块4上,考虑后场的浮吊作业场地受限,钢桁梁3的组拼顺序为从大桩侧往小桩侧进行两轮组拼,大桩侧为11#桥墩侧,小桩侧为9#桥墩侧,再进行浮拖架设。S2. Steel truss girder 3 assembly and floating towing erection: Assemble steel truss girder 3 with multiple internodes above the slideway, and steel truss girder 3 is placed on pad 4, considering that the floating crane operation site in the back field is limited , the assembly sequence of the steel truss girder 3 is two-wheel assembly from the large pile side to the small pile side, the large pile side is the 11# pier side, and the small pile side is the 9# pier side, and then the floating tow is carried out.

S2.1、第一次组拼:从大桩侧开始组拼,除了小桩侧的最后一个节间构件外,其余节间构件组拼完成,如图2所示。S2.1. The first assembly: assemble from the side of the large pile, except for the last internode component on the side of the small pile, the assembly of the other internode components is completed, as shown in Figure 2.

S2.2、第一次顶推:待第一次组拼、焊接并检测合格后,拆除与钢管支撑架间的临时连接,启动滑移设备,钢桁梁3进行第一轮滑移施工,钢桁梁3前端向浮拖方向滑移,钢桁梁3前部一个节间伸出钢管支撑架悬空,悬臂1个节间,滑移距离16米,完成第一轮钢桁梁3滑移施工,第一次顶推后状态如图3所示。S2.2. The first push: After the first assembly, welding and inspection are qualified, the temporary connection with the steel pipe support frame is removed, the sliding equipment is started, and the steel truss girder 3 performs the first round of sliding construction. The front end of the steel truss girder 3 slides in the direction of the floating tow. One section at the front of the steel truss girder 3 protrudes from the steel pipe support frame and hangs in the air. There is one section of the cantilever, and the sliding distance is 16 meters. The first round of steel truss girder 3 sliding is completed. Construction, the state after the first push is shown in Figure 3.

施工过程中,所有滑移设备同步推动钢桁梁3滑移,各台滑移设备均匀受载,整个施工全过程应进行模拟计算分析,全程确保安装过程中结构的安全。During the construction process, all sliding equipment synchronously pushes the steel truss girder 3 to slide, and each sliding equipment is evenly loaded. The entire construction process should be simulated and analyzed to ensure the safety of the structure during the installation process.

在液压滑移过程中,注意观测设备系统的压力、荷载变化情况等,并认真做好记录工作;根据设计滑移荷载预先设定好泵源压力值,由此控制爬行器最大输出推力,保证整个滑移设施的安全;计算机控制系统通过榕栅传感器反馈距离信号,控制每台爬行器误差在20mm内,从而控制整个滑移单元的同步滑移。During the hydraulic sliding process, pay attention to observe the pressure and load changes of the equipment system, and carefully record the work; pre-set the pump source pressure value according to the design sliding load, thereby controlling the maximum output thrust of the crawler to ensure The safety of the entire sliding facility; the computer control system feeds back the distance signal through the banyan sensor to control the error of each crawler within 20mm, thereby controlling the synchronous sliding of the entire sliding unit.

滑移时水平方向基本无横向水平力,且滑移工况(考虑5%水平力)下滑道受力计算为安全,滑移单元对应滑道位置设横向挡块,整个滑移过程是安全可靠的。There is basically no horizontal force in the horizontal direction during sliding, and the force calculation on the glideway under the sliding condition (considering 5% horizontal force) is safe, and the sliding unit is equipped with a lateral stopper corresponding to the position of the slideway, so the entire sliding process is safe and reliable of.

爬行器为液压系统,通过流量控制,爬行器的启动、停止加速度几乎为零,对轨道的冲击力很小;滑移过程中应密切注意滑移轨道、液压爬行器、液压泵源系统、计算机同步控制系统、传感检测系统等的工作状态。The crawler is a hydraulic system. Through flow control, the acceleration of the crawler's start and stop is almost zero, and the impact on the track is very small; during the sliding process, pay close attention to the sliding track, hydraulic crawler, hydraulic pump source system, and computer. Synchronize the working status of the control system, sensor detection system, etc.

滑移过程同步监测控制方案:Slip process synchronous monitoring and control scheme:

1)根据预先通过计算得到的滑移滑移工况下各滑移点反力值,在计算机同步控制系统中,对每台液压爬行器的最大滑移力进行设定;当遇到滑移力超出设定值时,液压爬行器自动采取溢流卸载,以防止出现滑移点荷载分布严重不均,造成对结构或临时设施的破坏。1) According to the pre-calculated reaction force value of each slip point under slip slip conditions, in the computer synchronous control system, set the maximum slip force of each hydraulic crawler; when encountering slip When the force exceeds the set value, the hydraulic crawler automatically adopts overflow unloading to prevent the serious uneven load distribution of the slip point and cause damage to the structure or temporary facilities.

2)通过液压回路中设置的自锁装置以及机械自锁系统,在液压爬行器停止工作或遇到停电等情况时,能够长时间自动锁紧滑移轨道,确保滑移桁架的安全。2) Through the self-locking device and mechanical self-locking system set in the hydraulic circuit, when the hydraulic crawler stops working or encounters a power failure, the sliding track can be automatically locked for a long time to ensure the safety of the sliding truss.

3)传感监测系统:3) Sensor monitoring system:

通过行程传感检测,获得主油缸的位置信息;通过油压传感检测,获得各滑移点的滑移力信息;通过电机启动信号反馈,获得电机的运行状况;通过电磁阀得电信号反馈,获得阀的工作状态;通过比例阀电流信号反馈,获得系统流量(滑移速度)。Obtain the position information of the main oil cylinder through stroke sensing detection; obtain the slip force information of each slip point through oil pressure sensing detection; obtain the operating status of the motor through the feedback of the motor start signal; obtain the electric signal feedback through the solenoid valve , to obtain the working state of the valve; through the proportional valve current signal feedback, to obtain the system flow (slip speed).

4)计算机控制系统:4) Computer control system:

计算机网络系统将上述反馈和控制信号远程、实时、可靠地反映到中央控制室的人机界面上:显示当前系统运行状态和参数(如油缸状态、同步位移、负载油压),记录历史数据和曲线(如推进速度、同步精度、滑移点负载等时间历程曲线);The computer network system reflects the above feedback and control signals remotely, in real time and reliably to the man-machine interface in the central control room: display the current system operating status and parameters (such as cylinder status, synchronous displacement, load oil pressure), record historical data and Curves (such as time history curves of propulsion speed, synchronization accuracy, slip point load, etc.);

操作人员将通过点击计算机人机界面:设定运行状态、启动泵源电机、切换控制模式、调整推进速度、暂停推进过程;计算机控制系统将自动校验通信数据、纠正通信误码、改变控制算法、优化控制参数、修正同步精度;液压同步控制系统各传感检测信息相互冗余,各操作控制信号相互闭锁,构成了安全、可靠、高效、便捷的现代化实用装备。The operator will click on the computer man-machine interface: set the running state, start the pump source motor, switch the control mode, adjust the propulsion speed, pause the propulsion process; the computer control system will automatically verify the communication data, correct the communication error code, and change the control algorithm , Optimizing control parameters, correcting synchronization accuracy; the sensing and detection information of the hydraulic synchronous control system is redundant with each other, and the operation control signals are interlocked with each other, which constitutes a safe, reliable, efficient and convenient modern practical equipment.

滑移过程中为直观地监测滑移的同步性和滑移状态,初始滑移时以50mm作为最小滑移单位,在轨道上做出标记,并进行编号;滑移过程中随时观测各控制监测点相对轨道上标尺偏差情况,随时准确了解滑移状态,并作好记录;如发现同步偏差较大时立即进行调整,调整通过对单台爬行器进行点动控制,并分析初始滑移记录数据,报审项目总工及监控单位工程师审核,详细分析记录数据原因并在后续滑移施工过程中作相应调整;如果初始滑移状态良好,滑移轨道标尺单位可适当加大,以作为整个滑移过程中同步监测控制依据。In order to visually monitor the synchronization and slip state during the sliding process, 50mm is used as the minimum sliding unit during the initial sliding, and the track is marked and numbered; each control monitoring is observed at any time during the sliding process Points relative to the deviation of the scale on the track, accurately understand the slip state at any time, and make a record; if a large synchronization deviation is found, adjust it immediately, and adjust by jogging a single crawler and analyzing the initial slip record data , report to the chief engineer of the project and the engineer of the monitoring unit for review, analyze the reasons for the recorded data in detail and make corresponding adjustments in the subsequent sliding construction process; if the initial sliding state is good, the unit of the sliding track scale can be appropriately increased to serve as The basis for synchronous monitoring and control during the shifting process.

滑移施工注意事项:Precautions for sliding construction:

(1)在拼梁胎架上拼装钢桁梁3时,除保证支架有足够的承载力和预留压缩下沉量外,应特别注意钢桁梁3的拼装拱度曲线;(1) When assembling the steel truss girder 3 on the beam frame, in addition to ensuring that the support has sufficient bearing capacity and reserved compression sinkage, special attention should be paid to the assembled camber curve of the steel truss girder 3;

(2)明确钢桁梁3结构设计图、设计说明书、分块应力、重量表等情况;(2) Clarify the steel truss beam 3 structural design drawings, design instructions, block stress, weight table, etc.;

(3)在钢桁梁3安装过程中,由于温度变化和支点起落千斤顶,活动支座会沿桥轴方向有较大移动,梁体落于正式活动支座时,其位移量可能超过其设计最大容许偏移量,施工中避免梁体与支座间有压力时移动梁体,梁体纵横移动时,要使其脱离支座后移动,调整至正确位置后落于支座上;(3) During the installation process of the steel truss girder 3, due to temperature changes and fulcrum lifting jacks, the movable support will move greatly along the direction of the bridge axis. When the beam body falls on the official movable support, its displacement may exceed its design The maximum allowable offset. During construction, avoid moving the beam body when there is pressure between the beam body and the support. When the beam body moves vertically and horizontally, make it move away from the support, adjust it to the correct position, and then fall on the support;

(4)桥墩顶布置,严格按施工设计图纸办理,架设前要进行全面检查,并办理签认;其上均设置水平、中线观测点,随时观测架梁过程中沉陷和变位情况,以便及时调整;(4) The layout of the top of the bridge pier shall be handled in strict accordance with the construction design drawings, and a comprehensive inspection shall be carried out before erection, and a signature shall be processed; horizontal and midline observation points shall be set on it, and the subsidence and displacement during the girder erection process shall be observed at any time, so as to timely Adjustment;

(5)墩顶钢垫梁、钢垫块、千斤顶等接触面凡无螺栓连接者,均应垫石棉板或三合板之类的防滑材料;(5) Asbestos board or three-ply board and other non-slip materials should be padded on the contact surfaces of steel pad beams, steel pads, jacks and other contact surfaces without bolts;

(6)过程中定期检查滑移各设备是否正常及各线路连接是否正确;(6) During the process, regularly check whether the sliding equipment is normal and whether the connection of each line is correct;

(7)钢梁滑移施工中,测量人员应加强线型测量,发现偏差及时反馈并调整,确保钢梁架设精度,切实控制好各滑移设备的横向标高;(7) During the steel girder sliding construction, the surveyors should strengthen the line type measurement, and timely feedback and adjust the deviation when they are found, so as to ensure the accuracy of steel girder erection and effectively control the lateral elevation of each sliding equipment;

(8)滑移设备安装时必须横向水平;(8) The sliding equipment must be installed horizontally;

(9)设备安装时要控制水平千斤顶的前进方向,纵向与桥轴线平行,并保证设计纵坡;(9) When the equipment is installed, it is necessary to control the forward direction of the horizontal jack, the longitudinal direction is parallel to the bridge axis, and the designed longitudinal slope is guaranteed;

(10)各高压胶管连接时,其连接处必须用柴油清洗干净,以免将灰尘、杂质带入液压回路系统;工作场地不允许有尖锐物,以防划伤高压胶管;高压胶管及电气控制电缆应捆扎好,避免阻碍通行和施工作业时碰坏、砸断及大风刮落,确保安全施工;(10) When the high-pressure hoses are connected, the joints must be cleaned with diesel oil to avoid bringing dust and impurities into the hydraulic circuit system; sharp objects are not allowed in the workplace to prevent scratching the high-pressure hoses; high-pressure hoses and electrical control cables It should be tied up well to avoid obstruction of traffic and construction work, being damaged, broken and blown off by strong winds, so as to ensure safe construction;

(11)施工作业区内的电源线、高压油管,应不阻碍构件的前进;(11) Power lines and high-pressure oil pipes in the construction work area shall not hinder the advancement of components;

(12)滑移系统由专人保管和维护,使用人员应熟悉系统结构及其动作程序;(12) The sliding system is kept and maintained by special personnel, and the users should be familiar with the system structure and its action procedures;

(13)工作完成后拆卸油管时,应先使千斤顶内油压卸荷完,严禁带压力拔油管;高压胶管拆除后,应戴上各接头盖或用塑料袋包好以免灰尘微粒、杂物进入胶管;(13) When disassembling the oil pipe after the work is completed, the oil pressure in the jack should be unloaded first, and it is strictly forbidden to pull out the oil pipe under pressure; after the high-pressure hose is removed, each joint cover should be worn or wrapped in a plastic bag to avoid dust particles and sundries into the hose;

(14)设备长期存放应将各部件擦净,并用塑料袋罩好,若重新使用,则必须首先排除系统中积聚的空气,更换千斤顶中的易损件,检查提升千斤顶的动作是否正确;(14) For long-term storage of the equipment, all parts should be cleaned and covered with plastic bags. If it is reused, the air accumulated in the system must be removed first, the wearing parts in the jack must be replaced, and the lifting jack action must be checked.

(15)设备必需按制造商供货产品中的千斤顶、液压泵站、控制系统进行配套使用,不允许采用其他千斤顶、泵站、控制系统与本产品相混用,否则可能会出现非常严重的事故;(15) The equipment must be used in conjunction with the jacks, hydraulic pump stations, and control systems in the products supplied by the manufacturer. It is not allowed to mix other jacks, pump stations, and control systems with this product, otherwise very serious accidents may occur ;

(16)液压泵站中溢流阀的安全压力设定,每次施工应核定其负荷大小,根据负荷大小计算出相应的油压,以保护液压系统。(16) For the safety pressure setting of the relief valve in the hydraulic pump station, the load should be checked for each construction, and the corresponding oil pressure should be calculated according to the load to protect the hydraulic system.

S2.3、第二次组拼:钢桁梁3进行第二次组拼,组拼最后一个节间构件,钢桁梁3整体组拼完成,组装完成的钢桁梁3如图4所示。S2.3, the second assembly: the steel truss girder 3 is assembled for the second time, the last internode member is assembled, the overall assembly of the steel truss girder 3 is completed, and the assembled steel truss girder 3 is shown in Figure 4 .

S2.4、第二次顶推:二次顶推将钢桁梁3继续向前推进一个节间,向前推进12米,钢桁梁3悬臂2个节间,悬挑29.6米,第二次顶推后状态如图5所示。S2.4, the second push: the second push pushes the steel truss girder 3 forward by one section, and advances 12 meters. The state after the first push is shown in Figure 5.

S2.5、向浮拖船舱1内压水下沉,支架2顶部低于钢桁梁3底部,然后将浮拖移至钢桁梁3悬臂的第三个节点处,支架2对准第三个节点,如图6所示,抽去浮拖船舱内压仓水,支架2上浮托起钢桁梁3前端,使得钢桁梁3悬空10cm,拆除钢桁梁3尾部各节点支点,如图7所示,拆除滑道上的垫块,仅通过钢桁梁3尾端支点和支架支点两个支点受力,对钢桁梁3进行支承。S2.5. Sink under pressure in the cabin 1 of the floating tugboat, the top of the support 2 is lower than the bottom of the steel truss beam 3, and then move the floating tow to the third node of the cantilever of the steel truss beam 3, and the support 2 is aligned with the third node. As shown in Figure 6, the ballast water in the cabin of the floating tugboat is pumped out, the front end of the steel truss beam 3 is floated on the support 2, so that the steel truss beam 3 is suspended by 10 cm, and the fulcrums of each node at the rear of the steel truss beam 3 are removed, as shown in the figure As shown in Fig. 7, the spacer on the slideway is removed, and the steel truss girder 3 is supported only through the two fulcrums of the steel truss girder 3 end fulcrum and the support fulcrum.

S2.6、第三次顶推:启动钢桁梁3尾部的滑移设备,将钢桁梁3第三次向前顶推,至钢桁梁3悬臂3个节间,钢梁向前滑移12.5米,如图7所示,钢桁梁3尾部支点位于两组钢管支撑架中间位置,浮拖同时向前移动;S2.6. The third push: activate the sliding equipment at the tail of the steel truss girder 3, and push the steel truss girder 3 forward for the third time until the steel truss girder 3 cantilever 3 sections, and the steel girder slides forward by 12.5 m, as shown in Figure 7, the steel truss girder 3 tail fulcrum is located in the middle position of two groups of steel pipe support frames, and the floating drag moves forward at the same time;

S2.7、第四次顶推:启动钢桁梁3尾部的滑移设备,将钢桁梁3向前滑移,浮拖及其上的支架随钢桁梁3滑移速度,通过前行绞车和钢桁梁3一同前进,并监控钢桁梁3及浮拖运行方向,采用绞车的方向控制缆,稳定浮拖的运行方向,第四次顶推至钢桁梁3的尾部到达一侧桥墩的上方,钢桁梁3的前端到达另一侧桥墩的上方,如图8所示。S2.7, the fourth push: activate the sliding equipment at the tail of the steel truss girder 3, slide the steel truss girder 3 forward, the floating drag and the support on it will move forward with the sliding speed of the steel truss girder 3 The winch and the steel truss girder 3 move forward together, and monitor the running direction of the steel truss girder 3 and the floating tow, use the direction control cable of the winch to stabilize the running direction of the floating tow, and push the fourth time until the tail of the steel truss girder 3 reaches one side Above the pier, the front end of the steel truss girder 3 reaches above the pier on the other side, as shown in FIG. 8 .

在浮拖顶推作业中使用水平仪检测浮船的稳定性,若船只失稳,则通过浮船四角的水泵控制船只内部储水量调整船只稳定性。Use a level gauge to check the stability of the pontoon during the floating towing and pushing operation. If the ship loses stability, use the water pumps at the four corners of the pontoon to control the water storage inside the ship to adjust the stability of the ship.

S2.8、在两侧的11#、12#桥墩的顶部各设置两台400吨落梁千斤顶,落梁千斤顶设于滑道内侧,钢桁梁3落在落梁千斤顶上,钢桁梁3浮拖到位后,浮拖船舱内压水下沉,解除浮拖的支架与钢桁梁3的约束,浮拖加水下沉撤出航道,完成浮拖作业,用三维落梁千斤顶代替浮拖,进行落梁施工,如图9所示为钢桁梁3落梁后的示意图。S2.8. Set up two 400-ton drop beam jacks on the top of the 11# and 12# piers on both sides. The drop beam jacks are set on the inside of the slideway. After the floating tow is in place, pressurize the water in the cabin of the floating tow to sink, release the constraints of the support of the floating tow and the steel truss girder 3, add water to the floating tow and sink to withdraw from the channel, complete the floating tow operation, and use a three-dimensional drop beam jack to replace the floating tow. Carry out beam drop construction, as shown in Figure 9 is the schematic diagram of steel truss girder 3 after beam drop.

在桥墩的顶部设置落梁千斤顶前,先通过全站仪测量钢桁梁3偏移数据,然后用四台三维落梁千斤顶布置在滑道内侧,同一桥墩顶部的两个落梁千斤顶用一台泵站进行操作,通过PLC控制系统进行钢桁梁3的纠偏。Before installing the falling beam jacks on the top of the pier, measure the offset data of the steel truss girder 3 through the total station, and then use four three-dimensional falling beam jacks to arrange inside the slideway, and use one set of two falling beam jacks on the top of the same pier The pump station is operated, and the deviation correction of the steel truss beam 3 is performed through the PLC control system.

S2.9、拆除11#桥墩与钢管支撑架之间的贝雷架支架和架梁设备,并安装支座,然后进行落梁施工,落梁时采用等比落梁进行控制,钢桁梁3落于两侧的桥墩上完成钢桁梁3的架设。S2.9. Remove the Bailey frame support and girder erection equipment between the 11# bridge pier and the steel pipe support frame, install the support, and then carry out the beam drop construction. The erection of the steel truss girder 3 is completed on the piers on both sides.

落梁施工时,落梁使用的落梁千斤顶,带顶部球形支承垫保险箍,共同作用的多台落梁千斤顶选用同一型号,用油管并联;油压千斤顶、油泵、压力表、油管长度力求一致;为准确掌握支点反力,应对千斤顶、油泵、压力表一并配套校正。During the construction of falling beams, the falling beam jacks used for the falling beams have the top spherical support pad safety hoops, and the multiple falling beam jacks working together are selected to the same model and connected in parallel with oil pipes; the lengths of hydraulic jacks, oil pumps, pressure gauges, and oil pipes should be consistent ; In order to accurately grasp the fulcrum reaction force, the jack, oil pump and pressure gauge should be calibrated together.

落梁中,桥墩上的支承面及各垫层间放置石棉板防滑材料;为适应支点水平位移,落梁千斤顶底部设置MGE板垫座,垫座中心与落梁千斤顶中心轴重合;对顶落高程、支点反力、支点位移、跨中挠度的变化,进行观测和记录;顶落梁时必须设置保险支座,同一桥墩的上、下游点,除调整高程时分别起顶外,均同步进行;在落梁过程中搁置在临时支座上时,应测量相邻两桁支点高差,当高差大于3mm时,调整两支点高程;千斤顶安放在桥墩顶部及钢桁梁3底部的位置均应严格按设计规定安放,并不得随意更改。In the falling beam, the asbestos board anti-slip material is placed between the supporting surface of the pier and each cushion; in order to adapt to the horizontal displacement of the fulcrum, the bottom of the falling beam jack is provided with an MGE plate pedestal, and the center of the pedestal coincides with the central axis of the falling beam jack; Changes in elevation, fulcrum reaction force, fulcrum displacement, and mid-span deflection shall be observed and recorded; safety bearings must be set when jacking up and falling beams, and the upstream and downstream points of the same pier shall be lifted simultaneously except when the elevation is adjusted separately. ; When the beam is placed on the temporary support in the process of falling, the height difference between the adjacent two truss fulcrums should be measured. When the height difference is greater than 3mm, the elevation of the two fulcrums should be adjusted; It should be placed in strict accordance with the design regulations and should not be changed arbitrarily.

使用落梁千斤顶必须遵守下列原则:The use of drop beam jacks must comply with the following principles:

① 泵尽量摆在两桁中间,使油管长度大致相等;① The pump should be placed in the middle of the two girders as far as possible so that the length of the oil pipes is approximately equal;

② 尽可能使用锭子油;② Use spindle oil as much as possible;

③ 千斤顶起顶时,一定要随时旋上保险箍,顶的上、下各垫石棉板;③ When the jack is lifted, the safety hoop must be screwed on at any time, and asbestos boards are placed on the top and bottom of the jack;

④ 起顶时保险箍不能一次打到顶,亦不能顶死,需与缸体顶面保留5~10mm空隙,随时松旋,以防将保险箍压坏,随时预防万一。④ When jacking up, the safety hoop cannot be hit to the top at one time, nor can it be pushed to death. It is necessary to keep a gap of 5-10mm with the top surface of the cylinder body, and loosen it at any time to prevent the safety hoop from being crushed, and to prevent accidents at any time.

本具体实施方式采用现场拼装加滑移、浮拖的总体施工方法,钢桁梁通过两次组拼完成整体的拼装,解决了浮吊作业场地受限的情况,施工不受场地限制,降低操作难度;This specific implementation mode adopts the overall construction method of on-site assembly, sliding, and floating towing. The steel truss girder is assembled through two assemblings to complete the overall assembly, which solves the situation that the floating crane operation site is limited, and the construction is not limited by the site, reducing operation. difficulty;

钢桁梁在两次组拼完成后分别进行两次顶推,直至钢桁梁前端悬臂2个节间,再用浮拖上的支架顶托钢桁梁,支点设在第三个节点处,将钢桁梁拼装支点悬空后撤出调整垫块,仅通过尾部支点和浮拖支点支承钢桁梁,然后向前进行第三次和第四次顶推以及浮拖,直至将钢桁梁移至两侧的桥墩上,再通过落梁施工将钢桁梁最终落在两侧的桥墩上,完成钢桁梁浮拖架设的施工,钢桁梁的悬臂较大,通过分多次顶推加浮拖的方式,降低浮拖施工难度,浮拖船舶施工中更稳定,施工中可确保通航要求。After the steel truss girders are assembled twice, they are respectively pushed twice until the front end of the steel truss girder cantilever two sections, and then the steel truss girder is supported by the support on the floating tow, and the fulcrum is set at the third node. After the fulcrum of the steel truss girder is suspended in the air, withdraw the adjustment block, and only support the steel truss girder through the tail fulcrum and the floating fulcrum, and then carry out the third and fourth push forward and the floating tow until the steel truss girder is moved. to the bridge piers on both sides, and finally drop the steel truss girders on the bridge piers on both sides through the beam drop construction to complete the erection construction of the steel truss girders. The cantilever of the steel truss girders is relatively large. The way of floating towing reduces the difficulty of floating towing construction, and the construction of floating towing ships is more stable, and the navigation requirements can be guaranteed during construction.

以上显示和描述了本发明的基本原理和主要特征以及本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是说明本发明的原理,在不脱离本发明精神和范围的前提下,本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等效物界定。The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above. Those skilled in the industry should understand that the present invention is not limited by the above-mentioned embodiments. What are described in the above-mentioned embodiments and the description only illustrate the principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention will also have Variations and improvements are possible, which fall within the scope of the claimed invention. The protection scope of the present invention is defined by the appended claims and their equivalents.

Claims (6)

1.一种稳定性高的钢桁梁顶推加浮拖架设施工方法,用于将钢桁梁架设于两侧的两个桥墩上,其特征在于:包括以下步骤:1. A steel truss girder with high stability pushes and adds a floating drag frame construction method, which is used to erect the steel truss girder on two bridge piers on both sides, it is characterized in that: comprise the following steps: S1、钢桁梁浮拖施工前准备:S1. Preparations before construction of steel truss girder floating tow: S1.1、在桥墩之间的水中打桩设置临时钢管支撑架,并在架设钢桁梁的桥墩上设锚碇支架供悬臂浮拖用;在桥墩上建设平台,在平台的顶部架设纵梁,并在纵梁上设置滑道和滑移设备,滑道上设置垫块;S1.1. Set up temporary steel pipe support frames by piling in the water between the bridge piers, and set anchor brackets on the bridge piers erected with steel truss girders for cantilever floating towing; build a platform on the bridge piers, and erect longitudinal beams on the top of the platform, And set the slideway and sliding equipment on the longitudinal beam, and set the pad on the slideway; S1.2、制作支架,将支架整体吊装到浮拖船舶的船舱中,并将支架与浮拖船舶的船体焊接牢固;S1.2, making the bracket, hoisting the bracket as a whole into the cabin of the floating towing ship, and welding the bracket and the hull of the floating towing ship firmly; S2、钢桁梁拼装和浮拖架设:在滑道的上方拼装具有多个节间的钢桁梁,钢桁梁置于垫块上,考虑后场的浮吊作业场地受限,钢桁梁的组拼顺序为从大桩侧往小桩侧进行两轮组拼,再进行浮拖架设:S2. Assembly of steel truss girders and erection of floating tow: Assemble steel truss girders with multiple internodes above the slideway, and place the steel truss girders on pads. The order of assembly is two-wheel assembly from the side of the large pile to the side of the small pile, and then the floating tow erection: S2.1、第一次组拼:从大桩侧开始组拼,除了小桩侧的最后一个节间构件外,其余节间构件组拼完成;S2.1. The first assembly: assemble from the side of the large pile, except for the last internode component on the side of the small pile, the assembly of other internode components is completed; S2.2、第一次顶推:待第一次组拼、焊接并检测合格后,拆除与钢管支撑架间的临时连接,启动滑移设备,钢桁梁进行第一轮滑移施工,钢桁梁前端向浮拖方向滑移,钢桁梁前部一个节间伸出钢管支撑架悬空,悬臂1个节间,完成第一轮钢桁梁滑移施工;S2.2. The first push: After the first assembly, welding and inspection are qualified, the temporary connection with the steel pipe support frame is removed, the sliding equipment is started, and the steel truss girder is subjected to the first round of sliding construction. The front end of the truss girder slides in the direction of floating towing, and a section at the front of the steel truss girder protrudes from the steel pipe support frame to hang in the air, and cantilever 1 section, completing the first round of steel truss girder sliding construction; S2.3、第二次组拼:钢桁梁进行第二次组拼,组拼最后一个节间构件,钢桁梁整体组拼完成;S2.3, the second assembly: the steel truss girder is assembled for the second time, the last internode member is assembled, and the overall assembly of the steel truss girder is completed; S2.4、第二次顶推:二次顶推将钢桁梁继续向前推进一个节间,钢桁梁悬臂2个节间;S2.4, the second push: the second push pushes the steel truss beam forward by one section, and the steel truss cantilever has two sections; S2.5、向浮拖船舱内压水下沉,支架顶部低于钢桁梁底部,然后将浮拖移至钢桁梁悬臂的第三个节点处,支架对准第三个节点,抽去浮拖船舱内压仓水,支架上浮托起钢桁梁前端,使得钢桁梁悬空10cm,拆除钢桁梁尾部各节点支点,拆除滑道上的垫块,仅通过钢桁梁尾端支点和支架支点两个支点受力,对钢桁梁进行支承;S2.5. Press water into the cabin of the floating tugboat to sink, the top of the support is lower than the bottom of the steel truss girder, then move the floating tow to the third node of the steel truss beam cantilever, align the support with the third node, and pull it out Ballast the water in the cabin of the floating tugboat, and the front end of the steel truss girder is lifted up by the support, so that the steel truss girder is suspended 10cm in the air, and the fulcrums of the nodes at the rear of the steel truss girder are removed, and the pads on the slideway are removed. The two fulcrums of the fulcrum bear force and support the steel truss girder; S2.6、第三次顶推:启动钢桁梁尾部的滑移设备,将钢桁梁第三次向前顶推,至钢桁梁悬臂3个节间,钢桁梁尾部支点位于两组钢管支撑架中间位置,浮拖同时向前移动;S2.6. The third push: activate the sliding equipment at the tail of the steel truss girder, push the steel truss girder forward for the third time, to the 3 nodes of the steel truss girder cantilever, the fulcrum of the steel truss girder tail is located in the two groups In the middle position of the steel pipe support frame, the floating drag moves forward at the same time; S2.7、第四次顶推:启动钢桁梁尾部的滑移设备,将钢桁梁向前滑移,浮拖及其上的支架随钢桁梁滑移速度,通过前行绞车和钢桁梁一同前进,并监控钢桁梁及浮拖运行方向,采用绞车的方向控制缆,稳定浮拖的运行方向,第四次顶推至钢桁梁的尾部到达一侧桥墩的上方,钢桁梁的前端到达另一侧桥墩的上方;S2.7, the fourth push: start the sliding equipment at the end of the steel truss girder, slide the steel truss girder forward, the floating tow and the support on it move with the sliding speed of the steel truss girder, and pass through the forward winch and the steel truss girder Move forward together, and monitor the running direction of the steel truss girder and the floating tow, use the direction control cable of the winch to stabilize the running direction of the floating tow, push the tail of the steel truss girder to the top of one side of the pier for the fourth time, and the steel truss girder The front end reaches the top of the pier on the other side; S2.8、在两侧的两个桥墩的顶部各设置两台落梁千斤顶,落梁千斤顶设于滑道内侧,钢桁梁落在落梁千斤顶上,钢桁梁浮拖到位后,浮拖船舱内压水下沉,解除浮拖的支架与钢桁梁的约束,移开浮拖,完成浮拖作业,进行落梁施工;S2.8. Set up two drop beam jacks on the top of the two piers on both sides. The drop beam jacks are set on the inside of the slideway. Pressurized water sinks in the cabin, releases the constraints of the support of the floating tow and the steel truss girder, removes the floating tow, completes the floating tow operation, and proceeds to the beam drop construction; S2.9、拆除一侧的桥墩与钢管支撑架之间的贝雷架支架和架梁设备,并安装支座,然后进行落梁施工,落梁时采用等比落梁进行控制,钢桁梁落于两侧的桥墩上完成钢桁梁的架设。S2.9. Remove the Bailey frame support and girder erection equipment between the bridge pier on one side and the steel pipe support frame, and install the support, and then carry out the beam drop construction. The erection of steel truss girders is completed on the piers on both sides. 2.根据权利要求1所述的一种稳定性高的钢桁梁顶推加浮拖架设施工方法,其特征在于:所述步骤S1.2中,所述支架设有两个,两个支架安装于浮拖船舶上,所述支架通过钢管桩和工字钢组焊成,所述工字钢拼接组成支架基础,横向和纵向上各有两根工字钢伸出支架基础的四周,用于和浮拖船舶以及另一侧的支架的连接固定,所述钢管桩立焊于支架基础上作为支架主体,所述钢管桩之间用槽钢做剪刀状支撑,在钢管桩顶部用双拼和四拼工字钢作为分配梁承载钢桁梁,最后将支架整体吊装到浮拖船舶的船舱中,与船体焊接牢固。2. The construction method of a high-stability steel truss girder jacking plus floating tow frame construction method according to claim 1, characterized in that: in the step S1.2, two supports are provided, two supports Installed on a floating towing ship, the bracket is welded by steel pipe piles and I-beams, and the I-beams are spliced to form the bracket foundation, and two I-beams protrude from the surroundings of the bracket foundation in the horizontal and vertical directions. It is used for connection and fixation with the floating towing ship and the bracket on the other side. The steel pipe pile is vertically welded on the foundation of the bracket as the main body of the bracket. Channel steel is used as a scissor-like support between the steel pipe piles. The top uses double-joint and four-piece I-beams as distribution beams to carry steel truss beams. Finally, the bracket is hoisted as a whole into the cabin of the floating towing ship and welded firmly with the hull. 3.根据权利要求1所述的一种稳定性高的钢桁梁顶推加浮拖架设施工方法,其特征在于:所述步骤S2.8中,在桥墩的顶部设置落梁千斤顶前,先通过全站仪测量钢桁梁偏移数据,然后用四台三维落梁千斤顶布置在滑道内侧,同一桥墩顶部的两个落梁千斤顶用一台泵站进行操作,通过PLC控制系统进行钢桁梁的纠偏。3. The construction method of a high-stability steel truss girder jacking plus floating drag frame construction method according to claim 1, characterized in that: in the step S2.8, before setting the drop beam jack on the top of the bridge pier, first The steel truss girder offset data is measured by a total station, and then four three-dimensional drop beam jacks are arranged on the inside of the slideway. The two drop beam jacks on the top of the same pier are operated by a pump station, and the steel truss is carried out through the PLC control system. Correction of the beam. 4.根据权利要求1所述的一种稳定性高的钢桁梁顶推加浮拖架设施工方法,其特征在于:所述步骤S1和S2中的滑移设备为液压爬行器,所述液压爬行器为组合式结构,一端以楔形夹块与滑道连接,另一端以铰接点形式与滑移胎架或构件连接,中间利用液压油缸驱动爬行,所述液压爬行器的楔型夹块具有单向自锁作用,当油缸伸出时,楔型夹块工作实现夹紧,自动锁紧滑道;油缸缩回时,夹块不工作实现松开,与油缸同方向移动;4. The construction method of a high-stability steel truss girder pushing and floating tow frame construction method according to claim 1, characterized in that: the sliding equipment in the steps S1 and S2 is a hydraulic crawler, and the hydraulic crawler The crawler is a combined structure, one end is connected to the slideway with a wedge-shaped clamp, the other end is connected to the sliding tire frame or member in the form of a hinge point, and the hydraulic cylinder is used to drive the crawl in the middle. The wedge-shaped clamp of the hydraulic crawler has One-way self-locking function, when the oil cylinder is extended, the wedge-shaped clamp block works to clamp and automatically lock the slideway; when the oil cylinder retracts, the clamp block does not work to release, and moves in the same direction as the oil cylinder; 所述液压爬行器工作流程如下:The working process of the hydraulic crawler is as follows: 步骤1:液压爬行器夹紧装置中楔块与滑道夹紧,液压爬行器的油缸前端活塞杆销轴与滑移构件连接,油缸伸缸,推动滑移构件向前滑移;Step 1: Clamp the wedge and the slideway in the clamping device of the hydraulic crawler, connect the piston rod pin shaft at the front end of the cylinder of the hydraulic crawler to the sliding member, extend the cylinder, and push the sliding member to slide forward; 步骤2:液压爬行器的油缸伸缸一个行程,构件向前滑移300mm;Step 2: The cylinder of the hydraulic crawler is extended for one stroke, and the component slides forward by 300mm; 步骤3:一个行程伸缸完毕,滑移构件不动,油缸缩缸,使夹紧装置中楔块与滑道松开,并拖动夹紧装置向前滑移;Step 3: After the cylinder is extended for one stroke, the sliding member does not move, and the oil cylinder shrinks, so that the wedge in the clamping device and the slideway are released, and the clamping device is dragged to slide forward; 步骤4:液压爬行器一个行程缩缸完毕,拖动夹紧装置向前滑移300mm,一个爬行推进行程完毕,再次执行步骤1工序,如此往复使构件滑移至最终位置。Step 4: After one stroke of the hydraulic crawler is completed shrinking the cylinder, drag the clamping device to slide forward 300mm, and one crawling advance stroke is completed, then perform the process of step 1 again, and reciprocate in this way to slide the component to the final position. 5.根据权利要求1所述的一种稳定性高的钢桁梁顶推加浮拖架设施工方法,其特征在于:所述步骤S2中,浮拖施工过程中,所有滑移设备同步推动钢桁梁滑移,各台滑移设备均匀受载,计算机控制系统通过榕栅传感器反馈距离信号,控制每台滑移设备误差在20mm内,从而控制整个滑移单元的同步滑移,滑移单元对应滑道位置设横向挡块,确保整个滑移过程安全可靠。5. The construction method of a high-stability steel truss girder jacking plus floating tow frame construction method according to claim 1, characterized in that: in the step S2, during the construction process of the floating tow, all the sliding equipment synchronously push the steel truss The truss girder slips, and each sliding device is evenly loaded. The computer control system feeds back the distance signal through the banyan sensor to control the error of each sliding device within 20mm, thereby controlling the synchronous sliding of the entire sliding unit. The sliding unit A horizontal block is set corresponding to the position of the slideway to ensure the safety and reliability of the entire sliding process. 6.根据权利要求1所述的一种稳定性高的钢桁梁顶推加浮拖架设施工方法,其特征在于:所述步骤S2.8和S2.9中,落梁施工时,落梁使用的落梁千斤顶,带顶部球形支承垫保险箍,共同作用的多台落梁千斤顶选用同一型号,用油管并联;落梁中,桥墩上的支承面及各垫层间放置石棉板防滑材料;为适应支点水平位移,落梁千斤顶底部设置MGE板垫座,垫座中心与落梁千斤顶中心轴重合,对顶落高程、支点反力、支点位移、跨中挠度的变化,进行观测和记录;在落梁过程中搁置在临时支座上时,应测量相邻两桁支点高差,当高差大于3mm时,调整两支点高程。6. The construction method of a high-stability steel truss girder jacking plus floating tow frame construction method according to claim 1, characterized in that: in the steps S2.8 and S2.9, during the falling beam construction, the falling beam The falling beam jacks used are equipped with safety hoops with spherical support pads on the top. The multiple falling beam jacks used together are of the same model and connected in parallel with oil pipes; in the falling beams, asbestos board anti-skid materials are placed between the supporting surfaces of the pier and each cushion; In order to adapt to the horizontal displacement of the fulcrum, the bottom of the drop beam jack is equipped with an MGE plate pedestal, and the center of the pedestal coincides with the central axis of the drop beam jack, and the changes in the top drop elevation, fulcrum reaction force, fulcrum displacement, and mid-span deflection are observed and recorded; When the beam is placed on the temporary support during the falling process, the height difference between the two adjacent truss fulcrums should be measured, and when the height difference is greater than 3mm, the height of the two fulcrums should be adjusted.
CN202211030400.8A 2022-08-26 2022-08-26 A high-stability steel truss girder jacking and floating drag frame construction method Pending CN115387228A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211030400.8A CN115387228A (en) 2022-08-26 2022-08-26 A high-stability steel truss girder jacking and floating drag frame construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211030400.8A CN115387228A (en) 2022-08-26 2022-08-26 A high-stability steel truss girder jacking and floating drag frame construction method

Publications (1)

Publication Number Publication Date
CN115387228A true CN115387228A (en) 2022-11-25

Family

ID=84123477

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211030400.8A Pending CN115387228A (en) 2022-08-26 2022-08-26 A high-stability steel truss girder jacking and floating drag frame construction method

Country Status (1)

Country Link
CN (1) CN115387228A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116289632A (en) * 2023-05-24 2023-06-23 北京市第三建筑工程有限公司 Pendulum type pushing and sliding construction system and method for bridge unilateral construction assembly

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101560752A (en) * 2009-04-02 2009-10-21 中铁十局集团有限公司 Construction method for erecting steel truss girder on uplift pushing tow
KR20120050940A (en) * 2012-03-29 2012-05-21 원대연 Constrution method of prestressed composite truss girder with internal hinge structure
CN203684099U (en) * 2013-12-10 2014-07-02 中铁二院工程集团有限责任公司 Floating drag anchoring positioning system of high-pier large-span steel truss girder bridge
CN110396938A (en) * 2019-08-07 2019-11-01 中铁二十四局集团有限公司 Multi-point floating support and jacking construction system for long-span steel truss bridge
CN113756194A (en) * 2021-08-30 2021-12-07 中铁二十局集团第一工程有限公司 Construction method of steel truss girder of upper-span navigable channel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101560752A (en) * 2009-04-02 2009-10-21 中铁十局集团有限公司 Construction method for erecting steel truss girder on uplift pushing tow
KR20120050940A (en) * 2012-03-29 2012-05-21 원대연 Constrution method of prestressed composite truss girder with internal hinge structure
CN203684099U (en) * 2013-12-10 2014-07-02 中铁二院工程集团有限责任公司 Floating drag anchoring positioning system of high-pier large-span steel truss girder bridge
CN110396938A (en) * 2019-08-07 2019-11-01 中铁二十四局集团有限公司 Multi-point floating support and jacking construction system for long-span steel truss bridge
CN113756194A (en) * 2021-08-30 2021-12-07 中铁二十局集团第一工程有限公司 Construction method of steel truss girder of upper-span navigable channel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116289632A (en) * 2023-05-24 2023-06-23 北京市第三建筑工程有限公司 Pendulum type pushing and sliding construction system and method for bridge unilateral construction assembly
CN116289632B (en) * 2023-05-24 2023-07-18 北京市第三建筑工程有限公司 Pendulum type pushing and sliding construction system and method for bridge unilateral construction assembly

Similar Documents

Publication Publication Date Title
CN101736700B (en) Construction method for hoisting broad width steel box girder cantilever
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN103437296B (en) Steel tube arch bridge towerless buckling three-section type double-rib folding hoisting construction method
CN101712444B (en) Method for hoisting large-size workpiece in ordinary plant and hydraulic jacking equipment thereof
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN110230261B (en) Mounting construction method for upper frame beam of double-layer synchronous beam
CN104532748A (en) Exceeding thousand tons of linear steel trussed beam floating pushing erecting construction method
CN106192776A (en) A kind of big Span Continuous Flexible arch bridge with steel truss beam free cantilever erection construction technology
CN111501584A (en) Bridge dismantling construction method for prestressed concrete continuous beam
CN115387228A (en) A high-stability steel truss girder jacking and floating drag frame construction method
CN115748513A (en) Construction method of ultra-small high-span-ratio all-welded steel truss girder bridge based on cantilever aerial work platform
CN114508052A (en) Pier-beam assembly type integrated construction method
CN110685227A (en) Construction method of formwork support system of obstacle-crossing wide-width swivel bridge closure segment hanging bracket method
CN114032791A (en) A construction method for integral jacking of large-span steel truss bridges
CN108004930A (en) The construction method of vertical shift bowstring arch bridge
CN115874594B (en) Ocean booster station translation loading system and translation loading method thereof
Rosignoli Self-launching erection machines for precast concrete bridges.
CN112095490A (en) Large-span steel truss girder single cantilever construction method
CN114045752A (en) Floating crane aerial positioning cantilever assembling method for large-section steel truss box girder
CN220150110U (en) The main truss structure of the cantilever aerial work platform
CN219637727U (en) Transport system for cantilever aerial work platforms
CN219137447U (en) Forward moving equipment of cantilever aerial work platform
CN219637728U (en) Aerial working platform for cantilever assembly ultra-small high span ratio all-welded steel truss bridge
CN120231282A (en) A method for transporting steel box beams in a beam storage area and a harbor area
CN115821792A (en) Integral pushing construction method for large-tonnage multi-span high-gravity-center basket arch bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination