CN115324623B - Advanced support method for deep broken rock mass roadway of metal ore - Google Patents
Advanced support method for deep broken rock mass roadway of metal ore Download PDFInfo
- Publication number
- CN115324623B CN115324623B CN202211140079.9A CN202211140079A CN115324623B CN 115324623 B CN115324623 B CN 115324623B CN 202211140079 A CN202211140079 A CN 202211140079A CN 115324623 B CN115324623 B CN 115324623B
- Authority
- CN
- China
- Prior art keywords
- roadway
- self
- rock mass
- support
- advanced
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/003—Machines for drilling anchor holes and setting anchor bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/107—Reinforcing elements therefor; Holders for the reinforcing elements
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/02—Setting anchoring-bolts with provisions for grouting
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0026—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
Description
技术领域Technical Field
本发明涉及深部破碎岩体支护技术领域,尤其涉及一种金属矿深部破碎岩体巷道超前支护方法。The invention relates to the technical field of deep broken rock mass support, and in particular to a method for advanced support of deep broken rock mass tunnels in metal mines.
背景技术Background Art
随着矿床开采深度的增加,深部采掘巷道穿越的地层复杂多变,多处于“高井深、高地应力、高地温、强采动”等特殊条件。特别是金属矿深部巷道所穿过的断层、破碎带等极软弱破碎岩体,具有应力高、岩体强度低、遇水泥化、完整性极差的特点。当前对穿越复杂破碎地层支护设计仍采用浅部“经验法”和“工程类比法”为主的管棚式或钢拱架支护设计方法,常导致掘进巷道垮冒严重、自稳时间短、安全性差、支护施工十分困难,如若采取不当的掘支施工工艺,不但会影响巷道的稳定、施工工期以及工人的人身安全,同时也会对该区域范围内的采掘工程的稳定性产生不利影响。As the mining depth of the ore deposit increases, the strata that deep mining tunnels pass through are complex and changeable, and are mostly in special conditions such as "high well depth, high ground stress, high ground temperature, and strong mining". In particular, the extremely weak and broken rock masses such as faults and broken zones that deep tunnels of metal mines pass through have the characteristics of high stress, low rock strength, cementation, and extremely poor integrity. At present, the support design for crossing complex and broken strata still adopts the pipe-roof or steel arch support design method based on the shallow "empirical method" and "engineering analogy method", which often leads to serious collapse of the excavation tunnel, short self-stabilization time, poor safety, and very difficult support construction. If improper excavation and support construction technology is adopted, it will not only affect the stability of the tunnel, the construction period, and the personal safety of the workers, but also have an adverse impact on the stability of the mining project within the area.
现有的针对穿越复杂破碎地层巷道的支护设计,支护方案是固定的,通常并不考虑自稳时间与施工效率之间的平衡,工序设计不合理,施工效率低,经济性差;且现有支护结构与巷道围岩不能完全耦合,支护效果差,安全性低;现有孔底锚固式锚索锚固力低、耐久性差且支护结构之间无关联,整体性和支护质量差。The existing support design for tunnels passing through complex and broken strata has a fixed support scheme, and usually does not consider the balance between self-stabilization time and construction efficiency. The process design is unreasonable, the construction efficiency is low, and the economy is poor. In addition, the existing support structure cannot be fully coupled with the tunnel surrounding rock, the support effect is poor, and the safety is low. The existing bottom-anchored anchor cables have low anchoring force, poor durability, and no connection between the support structures, resulting in poor integrity and support quality.
发明内容Summary of the invention
本发明所要解决的技术问题是,提供一种基于岩体自稳时间、自稳跨度、支护体与围岩充分耦合的超前支护方法,提高金属矿深部破碎巷道支护质量、支护效率和安全性,为金属矿深部巷道支护安全高效施工提供技术保障。The technical problem to be solved by the present invention is to provide an advanced support method based on the self-stabilization time, self-stabilization span of the rock mass, and full coupling of the support body and the surrounding rock, so as to improve the support quality, support efficiency and safety of deep broken tunnels in metal mines, and provide technical guarantee for the safe and efficient construction of deep tunnel support in metal mines.
本发明的技术方案如下:The technical solution of the present invention is as follows:
一种金属矿深部破碎岩体巷道超前支护方法,其特征在于:A method for advanced support of deep broken rock tunnels in metal mines, characterized by:
首先进行工程勘探对岩体质量分级,确定巷道自稳时间、自稳跨度和掘进进尺,如岩体自稳时间不足以完成支护作业循环,需在巷道掘进前进行超前支护作业,首先执行如下步骤2~7,然后循环执行步骤1~7;若是矿山施工效率高,在自稳时间内能够完成支护流程,则循环执行步骤1~6;First, conduct engineering exploration to classify the rock mass quality, determine the tunnel self-stabilization time, self-stabilization span and excavation advance. If the rock mass self-stabilization time is not enough to complete the support operation cycle, advance support operations must be performed before tunnel excavation. First, perform the following steps 2 to 7, and then execute steps 1 to 7 in a loop. If the mine construction efficiency is high and the support process can be completed within the self-stabilization time, then execute steps 1 to 6 in a loop.
步骤1:巷道掘进Step 1: Tunneling
采用钻爆法掘进,掘进进尺不大于自稳跨度;The drilling and blasting method is used for excavation, and the excavation footage is not greater than the self-stabilizing span;
步骤2:金属网+喷射混凝土Step 2: Metal Mesh + Shotcrete
采用钻爆法掘进完成后,立即架设金属网、喷射混凝土;After the excavation is completed by the drill and blast method, metal mesh and shotcrete are immediately set up;
步骤3:架设预制钢筋网架Step 3: Erection of prefabricated steel grid
将依据巷道断面形状、尺寸,围岩质量和地压条件设计的钢筋网架安装到喷射混凝土后的巷道围岩表面;钢筋网架的结构采用网格结构;The steel mesh frame designed according to the tunnel section shape, size, surrounding rock quality and ground pressure conditions is installed on the tunnel surrounding rock surface after shotcrete; the structure of the steel mesh frame adopts a grid structure;
步骤4:预应力锚杆+双筋条固定Step 4: Prestressed anchor rod + double reinforcement fixing
采用预应力锚杆+双筋条将钢筋网架固定到围岩上,使钢筋网架、预应力锚杆、双筋条及破碎围岩加固形成整体结构;Prestressed anchor rods + double bars are used to fix the steel grid to the surrounding rock, so that the steel grid, prestressed anchor rods, double bars and broken surrounding rock are reinforced to form an integral structure;
步骤5:喷射混凝土Step 5: Shotcrete
将步骤3架设好的预制钢筋网架+预应力锚杆+双筋条采用喷射混凝土加固,用于增加巷道支护强度,密封巷道围岩,并提高抗腐蚀能力;The prefabricated steel grid + prestressed anchor rods + double bars erected in step 3 are reinforced with shotcrete to increase the tunnel support strength, seal the tunnel surrounding rock, and improve corrosion resistance;
步骤6:安装孔底固定式锚索Step 6: Install the bottom anchor cable
为避免加固支护后的巷道围岩产生形变,安装孔底固定式锚索,使加固后的支护结构进一步提高,增强支护结构的稳定性;In order to avoid deformation of the surrounding rock of the tunnel after reinforcement and support, fixed anchor cables are installed at the bottom of the hole to further improve the reinforced support structure and enhance the stability of the support structure;
步骤7:超前注浆锚杆Step 7: Pre-grouting anchors
依据巷道掘进进尺确定超前注浆锚杆长度,超前注浆锚杆长度至少为巷道掘进进尺的1.5倍,超前注浆锚杆安装与巷道围岩表面呈15°~20°角,锚杆间距不大于30cm。The length of the advance grouting anchor rod is determined according to the tunnel excavation progress. The length of the advance grouting anchor rod is at least 1.5 times of the tunnel excavation progress. The advance grouting anchor rod is installed at an angle of 15° to 20° to the surface of the tunnel surrounding rock, and the spacing between anchor rods is not more than 30cm.
优选地,步骤1中,金属网网格尺寸不大于50mm×50mm,金属网钢筋直径不小于6mm;喷射混凝土强度不低于C20,厚度不小于20mm。Preferably, in step 1, the mesh size of the metal mesh is not greater than 50 mm×50 mm, and the diameter of the metal mesh reinforcement is not less than 6 mm; the strength of the shotcrete is not less than C20, and the thickness is not less than 20 mm.
优选地,步骤2中,所述钢筋网架由主筋和箍筋组成,其中主筋直径不小于20mm,箍筋直径不小于10mm。Preferably, in step 2, the steel mesh frame is composed of main bars and stirrups, wherein the diameter of the main bars is not less than 20 mm, and the diameter of the stirrups is not less than 10 mm.
优选地,步骤3中,预应力锚杆提供的预应力不小于8t;双筋条的安装尽量贴紧巷道壁;双筋条沿巷道掘进方向布置,双筋条直径不小于6mm,长度与巷道掘进进尺一致,采用点焊制作。Preferably, in step 3, the prestress provided by the prestressed anchor rod is not less than 8t; the double reinforcement bars are installed as close to the tunnel wall as possible; the double reinforcement bars are arranged along the tunnel excavation direction, the diameter of the double reinforcement bars is not less than 6mm, the length is consistent with the tunnel excavation footage, and they are manufactured by spot welding.
优选地,步骤4中,如某地段出现渗水,或者出现变形>100mm的情况,使用含物料重量2~3%的钢纤维喷射混凝土,以增大喷护层强度,达到耦合支护效果,使加固后的支护结构与巷道围岩协同形变;喷射混凝土强度等级不低于C20。Preferably, in step 4, if water seepage occurs in a certain area, or deformation > 100 mm occurs, steel fiber shotcrete containing 2 to 3% of the material weight is used to increase the strength of the shotcrete layer and achieve a coupled support effect, so that the reinforced support structure and the tunnel surrounding rock can be deformed in coordination; the strength grade of the shotcrete is not less than C20.
优选地,步骤5中,锚索长度不小于6m,孔底固定采用倒楔式结构,注水泥浆锚固,水泥浆水灰比不小于0.4:1,采用推锚器增加预应力,预应力不小于15t。Preferably, in step 5, the length of the anchor cable is not less than 6m, the bottom of the hole is fixed with an inverted wedge structure, cement slurry is injected for anchoring, the water-cement ratio of the cement slurry is not less than 0.4:1, and a push anchor is used to increase the prestress, and the prestress is not less than 15t.
优选地,步骤6中,注浆锚杆结构为锥形中空钢管,直径为40mm,在其端部钻凿直径为2mm孔,孔间距不大于5cm。Preferably, in step 6, the grouting anchor structure is a conical hollow steel pipe with a diameter of 40 mm, and holes with a diameter of 2 mm are drilled at the end thereof, and the hole spacing is not greater than 5 cm.
所述确定巷道自稳时间、自稳跨度和掘进进尺的方法是:根据工程勘察结果依据岩体地质力学(RMR)分类表对岩体进行质量评价,并根据评分结果确定巷道自稳时间、最大自稳跨度,掘进进尺不大于最大自稳跨度。The method for determining the tunnel self-stabilization time, self-stabilization span and excavation progress is: according to the engineering investigation results, the rock mass quality is evaluated according to the rock mass geomechanics (RMR) classification table, and the tunnel self-stabilization time and maximum self-stabilization span are determined according to the scoring results, and the excavation progress is not greater than the maximum self-stabilization span.
相对于现有技术,本发明的经济效果在于:Compared with the prior art, the economic effect of the present invention is:
第一、超前支护是十分耗时的,本发明在保证安全的前提下省略超前支护步骤,大幅度提高了施工效率。本发明通过RMR分级确定掘进进尺和自稳时间,要是在当前自稳时间内不能完成后续的支护工序就不能先进进行巷道掘进,需要进行超前支护。若是矿山施工效率高(每个矿山工人数量和机械设备,断面尺寸所决定),在自稳时间内可以完成支护流程,就可以直接掘进,省略超前支护。First, advance support is very time-consuming. The present invention omits the advance support step while ensuring safety, greatly improving construction efficiency. The present invention determines the excavation advance and self-stabilization time through RMR classification. If the subsequent support process cannot be completed within the current self-stabilization time, the tunnel excavation cannot be advanced and advance support is required. If the mine construction efficiency is high (determined by the number of workers and mechanical equipment in each mine, and the cross-sectional size), the support process can be completed within the self-stabilization time, and excavation can be carried out directly, omitting advance support.
第二、本发明通过对支护结构进行优化组合,使支护结构与巷道围岩能够相互耦合,可以最大程度的利用围岩的自撑能力及锚杆的支护能力,提高围岩的整体刚度,增强围岩的抗变形能力,加强围岩的整体性,提高金属矿深部破碎巷道支护质量、支护效率和安全性,为金属矿深部巷道支护安全高效施工提供技术保障。Second, the present invention optimizes the combination of support structures so that the support structures and the surrounding rock of the tunnel can be coupled with each other, which can maximize the use of the self-supporting capacity of the surrounding rock and the support capacity of the anchor rods, improve the overall stiffness of the surrounding rock, enhance the deformation resistance of the surrounding rock, strengthen the integrity of the surrounding rock, improve the support quality, support efficiency and safety of deep broken tunnels in metal mines, and provide technical guarantee for the safe and efficient construction of deep tunnel support in metal mines.
第三、不同于现有技术通常采用的U型钢支架,本发明采用钢筋加工成的支架作为网架并喷射混凝土。钻爆法掘进的断面通常是不规则,本发明此方法优势在于:网架易于调整形态以适应巷道的超欠挖,提高支护结构与围岩的耦合程度,增强其整体性,提高支护质量。Third, unlike the U-shaped steel bracket commonly used in the prior art, the present invention uses a bracket processed from steel bars as a grid and sprays concrete. The cross section of the drilling and blasting method is usually irregular. The advantages of this method of the present invention are: the grid is easy to adjust its shape to adapt to the over-excavation and under-excavation of the tunnel, improve the coupling degree between the support structure and the surrounding rock, enhance its integrity, and improve the support quality.
第四、不同于现有技术通常采用的孔底固定方式,本发明采用全长锚固注浆式,本发明此方法优势在于:锚固力高,锚索耐腐蚀提高耐久性,同时可以对锚索周边围岩额外起到注浆加固作用。Fourth, different from the hole bottom fixing method commonly used in the prior art, the present invention adopts full-length anchoring grouting. The advantages of this method of the present invention are: high anchoring force, corrosion resistance of anchor cable improves durability, and at the same time, it can play an additional grouting reinforcement role on the surrounding rock around the anchor cable.
第五、本发明采用预应力锚杆+双筋条固定预制的钢筋网架使每排的支护结构相互连接,进一步提高了支护结构的整体性和稳定性。Fifth, the present invention uses prestressed anchor rods + double ribs to fix the prefabricated steel grid so that each row of the supporting structure is interconnected, further improving the integrity and stability of the supporting structure.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1是本发明实施例巷道支护断面图(垂直巷道走向)。FIG1 is a cross-sectional view of a tunnel support according to an embodiment of the present invention (vertical to the direction of the tunnel).
图2是本发明实施例巷道支护剖面图(沿巷道走向)。FIG. 2 is a cross-sectional view of the tunnel support according to an embodiment of the present invention (along the direction of the tunnel).
图中,1、锚索,2、锚杆,3、注浆锚杆,4、混凝土,5、钢筋网架。In the figure, 1. anchor cable, 2. anchor rod, 3. grouting anchor rod, 4. concrete, 5. steel mesh.
具体实施方式DETAILED DESCRIPTION
以下结合实施例进一步说明本发明。The present invention is further described below with reference to the examples.
实施例一Embodiment 1
某地下金属矿-1070m水平巷道位于松软破碎岩体中,巷道围岩主要以绿帘石和大理岩为主,具有岩体强度低、遇水泥化、完整性极差的特点,针对构造带影响下-1070m巷道的掘进与支护施工所面临的问题。The -1070m horizontal tunnel of an underground metal mine is located in soft and broken rock. The tunnel surrounding rock is mainly composed of epidote and marble, which has the characteristics of low rock strength, cementation and extremely poor integrity. The problems faced in the excavation and support construction of the -1070m tunnel under the influence of the tectonic belt are addressed.
该支护区域岩体破碎,根据工程勘察结果依据岩体地质力学(RMR)分类表对岩体进行质量评价,并根据评分结果确定巷道自稳时间、最大自稳跨度,掘进进尺不大于最大自稳跨度。The rock mass in this support area is broken. The quality of the rock mass is evaluated according to the rock mass geomechanics (RMR) classification table based on the engineering investigation results, and the tunnel self-stabilization time and maximum self-stabilization span are determined based on the scoring results. The excavation advance is not greater than the maximum self-stabilization span.
根据RMR岩体质量评分<20,为V级岩体,由表1可知最大自稳跨度为1m,由此确定掘进进尺为1m,但由于自稳时间仅为30min,需在钻爆开挖之前提前进行支护。According to the RMR rock mass quality score of <20, it is Class V rock mass. From Table 1, we can know that the maximum self-stabilizing span is 1m, so the excavation advance is determined to be 1m. However, since the self-stabilizing time is only 30min, support is required in advance before drilling and blasting.
表1基于RMR总评分的岩体质量评价与工程特性Table 1 Rock mass quality evaluation and engineering properties based on RMR total score
参见图1和图2实施如下步骤。Refer to Figure 1 and Figure 2 to implement the following steps.
步骤1:巷道掘进Step 1: Tunneling
采用钻爆法掘进,掘进进尺为1m。The drilling and blasting method is used for excavation, with a penetration of 1m.
步骤2:金属网+喷射混凝土支护Step 2: Metal mesh + shotcrete support
采用菱形镀锌金属网,网度为50×50mm,金属网钢筋直径7mm金属网的安装要尽量贴紧巷道壁,最大限度的发挥金属网的作用。两片金属网的搭接长度为100mm,保证整个巷道锚网支护形成一体,并于巷道边墙、顶板以及矸石堆初喷混凝土,喷射混凝土强度C20,厚度50mm,以进行临时支护。The diamond-shaped galvanized metal mesh is used, with a mesh size of 50×50mm and a metal mesh steel bar diameter of 7mm. The metal mesh should be installed as close to the tunnel wall as possible to maximize the role of the metal mesh. The overlap length of the two metal meshes is 100mm to ensure that the entire tunnel anchor mesh support is integrated, and the initial concrete is sprayed on the tunnel side wall, top plate and waste rock pile. The sprayed concrete strength is C20 and the thickness is 50mm for temporary support.
步骤3:架设预制钢筋网架Step 3: Erection of prefabricated steel grid
本设计巷道掘进断面尺寸为:3.0×3.0m;钢筋网架5单个长度2.1m,宽0.3m。钢筋条侧面焊接有钢筋腿,腿长0.2m。巷道周长约为8m(除去底板),采用四个钢筋网架5架设安装到喷射混凝土后的巷道围岩表面,每个钢筋网架5搭接处用铁丝捆牢,搭接处为0.5~1m,钢筋网架5排距400mm(钢支架中心线距离),且每组钢筋网架5与围岩背实,不得留有空隙。The cross-sectional dimensions of the tunnel excavation in this design are: 3.0×3.0m; the length of a single steel mesh frame 5 is 2.1m and the width is 0.3m. Steel bars are welded on the side of the steel bar, and the leg length is 0.2m. The perimeter of the tunnel is about 8m (excluding the bottom plate). Four steel mesh frames 5 are installed on the surface of the tunnel surrounding rock after shotcrete. Each steel mesh frame 5 is tied with wire at the overlap, and the overlap is 0.5~1m. The spacing of the steel mesh frames 5 is 400mm (the distance between the center lines of the steel supports), and each group of steel mesh frames 5 is solid with the surrounding rock, and no gaps are left.
所述钢筋网架5由主筋和箍筋组成,其中主筋直径20mm,箍筋直径10mm。在地应力增加时,在现有网架基础上增加肋筋,以加强网架结构强度。所述钢筋网架5的具体结构是:四条平行设置的主筋组成截面形状为矩形的主体,通过若干条箍筋将四条主筋连接在一起。The steel mesh frame 5 is composed of main bars and stirrups, wherein the main bars have a diameter of 20 mm and the stirrups have a diameter of 10 mm. When the ground stress increases, ribs are added to the existing mesh frame to strengthen the strength of the mesh frame structure. The specific structure of the steel mesh frame 5 is: four parallel main bars form a main body with a rectangular cross-section, and the four main bars are connected together by a plurality of stirrups.
步骤4:预应力锚杆+双筋条固定Step 4: Prestressed anchor rod + double reinforcement bar fixation
钢筋网架5架设好后,采用预应力锚杆+双筋条将其固定到围岩上,钻凿锚杆孔采用Φ32mm的钻头,孔深2.3m,锚杆2露出长度不许超过150mm。钻孔时要垂直于巷道岩壁,两帮孔轴向夹角85°;拱顶边孔轴向夹角75°,拱顶中心孔径向夹角70°,底排锚孔夹角75°。预应力锚杆采用树脂锚杆,间排距800mm×800mm;直径:20mm,长度:2200mm。安装双筋条时必须从一端向另一端依次安装,锚杆2上预紧力时必须将螺母上紧,达到8t以上的预应力;分次支护间双筋条必须互相连接,最大限度地发挥预应力锚杆+双筋条对预制钢筋网架5的固定作用,使预制钢筋网架5、预应力锚杆、双筋条及破碎围岩加固形成整体结构。After the steel mesh frame 5 is erected, it is fixed to the surrounding rock with prestressed anchor rods + double bars. A Φ32mm drill bit is used to drill the anchor rod holes, the hole depth is 2.3m, and the exposed length of the anchor rod 2 is not allowed to exceed 150mm. The drilling should be perpendicular to the tunnel rock wall, the axial angle of the two side holes is 85°; the axial angle of the arch side hole is 75°, the radial angle of the arch center hole is 70°, and the angle of the bottom row anchor hole is 75°. The prestressed anchor rods use resin anchor rods, with a spacing of 800mm×800mm; diameter: 20mm, length: 2200mm. When installing double reinforcement bars, they must be installed from one end to the other end in sequence. When the prestressing force is applied to the anchor rod 2, the nut must be tightened to reach a prestress of more than 8t. The double reinforcement bars must be connected to each other between the staged supports to maximize the fixing effect of the prestressed anchor rods + double reinforcement bars on the prefabricated steel grid 5, so that the prefabricated steel grid 5, prestressed anchor rods, double reinforcement bars and broken surrounding rock reinforcement form an integral structure.
双筋条的安装要尽量贴紧巷道壁,最大限度的发挥预应力锚杆+双筋条对预制钢筋网架5的固定作用,预应力锚杆宜为树脂锚固类锚杆,其长度依据巷道围岩破坏深度确定;双筋条沿巷道掘进方向布置,双筋条直径6mm,长度与巷道掘进进尺一致,采用点焊制作。The installation of double reinforcement bars should be as close to the tunnel wall as possible to maximize the fixing effect of prestressed anchor rods + double reinforcement bars on the prefabricated steel mesh frame 5. The prestressed anchor rods should preferably be resin anchor rods, and their length is determined according to the depth of tunnel surrounding rock damage; the double reinforcement bars are arranged along the tunnel excavation direction, the double reinforcement bars have a diameter of 6mm, and the length is consistent with the tunnel excavation footage, and are manufactured by spot welding.
步骤5:喷射混凝土Step 5: Shotcrete
喷射强度为C25、厚度为50mm的混凝土4,将上一步骤中架设好的预制钢筋网架+预应力锚杆+双筋条加固,既可以增加巷道支护强度,又可以密封巷道围岩,提高抗腐蚀能力。The concrete 4 with a spraying strength of C25 and a thickness of 50 mm is used to reinforce the prefabricated steel grid + prestressed anchor rods + double bars erected in the previous step, which can not only increase the support strength of the tunnel, but also seal the tunnel surrounding rock and improve the corrosion resistance.
如某地段出现渗水,或者出现变形>100mm的情况,使用含物料重量2~3%的钢纤维喷射混凝土,以增大喷护层强度,达到耦合支护效果,使加固后的支护结构与巷道围岩协同形变。If water seepage occurs in a certain area, or deformation > 100mm occurs, use steel fiber shotcrete containing 2-3% of the material weight to increase the strength of the shotcrete layer and achieve a coupled support effect, so that the reinforced support structure and the tunnel surrounding rock can deform synergistically.
步骤6:安装孔底固定式锚索Step 6: Install the bottom anchor cable
钻凿锚索孔采用Φ28mm的钻头,孔深7m,采用孔底固定式注水泥浆锚索,注水泥浆锚固,锚索1长度不小于6m,孔底固定采用倒楔式结构,注水泥浆锚固,水泥浆水灰比0.4:1,并用锚索涨拉器拉紧锚索1,使预应力达到15t以上。A Φ28mm drill bit is used to drill the anchor hole, the hole depth is 7m, and a cement slurry anchor cable is used for fixing at the bottom of the hole. The length of the anchor cable 1 is not less than 6m. An inverted wedge structure is used for fixing at the bottom of the hole, and cement slurry is used for anchoring. The water-cement ratio of the cement slurry is 0.4:1. The anchor cable 1 is tightened with an anchor cable tensioner to make the prestress reach more than 15t.
步骤7:超前注浆锚杆Step 7: Pre-grouting anchors
依据巷道掘进进尺确定超前注浆锚杆3长度3200mm,超前注浆锚杆3安装与巷道围岩表面呈15°角,锚杆间距150mm,搭接长度1m,排距2m。注浆锚杆3结构为锥形中空钢管,直径42mm,在其端部钻凿直径为2mm孔,孔间距50mm;注浆材料依据围岩性质确定。According to the tunnel excavation progress, the length of the advance grouting anchor 3 is 3200mm. The advance grouting anchor 3 is installed at an angle of 15° to the tunnel surrounding rock surface, with an anchor spacing of 150mm, a lap length of 1m, and a row spacing of 2m. The structure of the grouting anchor 3 is a conical hollow steel pipe with a diameter of 42mm. A hole with a diameter of 2mm is drilled at its end, and the hole spacing is 50mm; the grouting material is determined according to the properties of the surrounding rock.
如此反复,循环作业。Repeat this process in a cycle.
实施例二Embodiment 2
某地下金属矿-960m水平巷道位于松软破碎岩体中,岩性以黄铁绢英岩化花岗质碎裂岩、绢英岩化花岗岩为主,岩石比较坚硬,区内断裂构造较发育,近主断面蚀变带内局部岩石较破碎,蚀变较强烈、裂隙较发育,岩芯较破碎。The -960m horizontal tunnel of an underground metal mine is located in soft and broken rock mass. The rock types are mainly pyrite sericite granite breccia and sericite granite. The rock is relatively hard and the fault structure is well developed in the area. The local rock in the alteration zone near the main section is relatively broken, the alteration is relatively strong, the cracks are well developed, and the core is relatively broken.
该支护区域岩体破碎,根据工程勘察结果依据岩体地质力学(RMR)分类表对岩体进行质量评价,并根据评分结果确定巷道自稳时间、最大自稳跨度,掘进进尺不大于最大自稳跨度。The rock mass in this support area is broken. The quality of the rock mass is evaluated according to the rock mass geomechanics (RMR) classification table based on the engineering investigation results, and the tunnel self-stabilization time and maximum self-stabilization span are determined based on the scoring results. The excavation advance is not greater than the maximum self-stabilization span.
根据RMR岩体质量评分30,为Ⅳ级岩体,由表1可知最大自稳跨度为2.5m,自稳时间约为10h,由此确定掘进进尺为2m,矿山机械化程度高,在自稳时间内可以完成支护流程,故循环执行实施例一所述步骤1至步骤6。According to the RMR rock mass quality score of 30, it is a Grade IV rock mass. From Table 1, it can be seen that the maximum self-stabilizing span is 2.5m and the self-stabilizing time is about 10h. Therefore, the excavation advance is determined to be 2m. The mine has a high degree of mechanization and the support process can be completed within the self-stabilizing time. Therefore, steps 1 to 6 described in Example 1 are executed in a loop.
本发明所述岩体地质力学(RMR)分类表见表2。The rock mass geomechanics (RMR) classification table described in the present invention is shown in Table 2.
表2岩体地质力学(RMR)分类表见表Table 2 Rock mass geomechanics (RMR) classification table See Table
分类时,根据各类参数的实测资料,按照标准分别评分;然后将各类参数的评分值相加得岩体质量总分RMR值;再按节理分类对其进行修正;最后,用修正后的RMR值将岩体分级。During classification, scores are given according to the measured data of various parameters according to the standards; then the score values of various parameters are added together to obtain the total rock mass quality score RMR value; then it is corrected according to the joint classification; finally, the rock mass is classified using the corrected RMR value.
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211140079.9A CN115324623B (en) | 2022-09-19 | 2022-09-19 | Advanced support method for deep broken rock mass roadway of metal ore |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202211140079.9A CN115324623B (en) | 2022-09-19 | 2022-09-19 | Advanced support method for deep broken rock mass roadway of metal ore |
Publications (2)
Publication Number | Publication Date |
---|---|
CN115324623A CN115324623A (en) | 2022-11-11 |
CN115324623B true CN115324623B (en) | 2024-10-29 |
Family
ID=83913509
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202211140079.9A Active CN115324623B (en) | 2022-09-19 | 2022-09-19 | Advanced support method for deep broken rock mass roadway of metal ore |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN115324623B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116658219B (en) * | 2023-08-02 | 2023-10-13 | 阳泉市广凯机械制造有限公司 | Anchor cable prestress control device and application method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1730459A1 (en) * | 1990-04-09 | 1992-04-30 | Криворожский Филиал Всесоюзного Научно-Исследовательского, Проектного И Конструкторского Института Горного Дела И Металлургии Цветных Металлов | Method of erection of reinforced shotcrete support |
CN105863669A (en) * | 2016-04-18 | 2016-08-17 | 东北大学 | Wave-absorbing energy-dissipation support method for regulating and controlling rockburst development process |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107237646B (en) * | 2017-06-28 | 2019-04-26 | 山东科技大学 | Large deformation constant resistance support grouting bolt, anchor cable and quantitative support method of roadway |
CN110486069B (en) * | 2019-09-10 | 2020-11-03 | 华北科技学院 | Large-mining-height coal wall caving control structure based on flexible reinforcement and construction equipment |
-
2022
- 2022-09-19 CN CN202211140079.9A patent/CN115324623B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1730459A1 (en) * | 1990-04-09 | 1992-04-30 | Криворожский Филиал Всесоюзного Научно-Исследовательского, Проектного И Конструкторского Института Горного Дела И Металлургии Цветных Металлов | Method of erection of reinforced shotcrete support |
CN105863669A (en) * | 2016-04-18 | 2016-08-17 | 东北大学 | Wave-absorbing energy-dissipation support method for regulating and controlling rockburst development process |
Also Published As
Publication number | Publication date |
---|---|
CN115324623A (en) | 2022-11-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108843332B (en) | Pass through fault belt large cross-section tunnel excavation and method for protecting support | |
CN109209392B (en) | Full-ring excavation method suitable for IV-V-grade surrounding rock of large-section tunnel | |
CN108915720B (en) | A construction method for a large-section tunnel crossing a fault fracture zone | |
CN108316941B (en) | Broken surrounding rock and soft rock roadway U-shaped steel canopy supporting method | |
CN108678769A (en) | Deep Gateway anchor note cuts top master control and stays lane method | |
CN102562093B (en) | Full-length anchoring supporting method with intensive resin anchor rod and anchor-shotcrete net | |
CN109026024B (en) | Roadway roof deformation control method under high-level stress action | |
CN113090284B (en) | Roadway support method for soft and broken rock mass of underground mine | |
CN211258623U (en) | Water-rich weak surrounding rock tunnel supporting system crossing fault fracture zone | |
CN103216244B (en) | Roadway soft roof anchoring beam-arch combined structure supporting system and supporting method | |
CN105909289B (en) | A kind of asymmetric roadway support structure of deep three-soft seam | |
CN113605893B (en) | Control method for pre-filling full gob-side entry driving surrounding rock | |
CN113073991B (en) | Roadway support method for extremely loose and broken rock mass of underground mine | |
CN115324623B (en) | Advanced support method for deep broken rock mass roadway of metal ore | |
CN110513129B (en) | Advanced roof-protecting supporting structure and method for roadway of soft and thick coal seam working face | |
CN114673527B (en) | Progressive roadway and tunnel broken surrounding rock reinforcing method | |
Tian et al. | Study on the deformation failure mechanism and coupling support technology of soft rock roadways in strong wind oxidation zones | |
CN110645018B (en) | Mine underground strong dynamic pressure roadway prestress anchor-charging integrated supporting structure and method | |
CN108035752A (en) | Coal road based on roof stability pushes up by force wall supporting anchor rod support method | |
CN110566238A (en) | Mud rock roof small coal pillar gob-side roadway supporting structure and method thereof | |
CN111720165A (en) | A flexible roadway protection method for gob-side entry retention in large dip angle coal seams | |
CN207620820U (en) | A kind of breaking surrounding rock and soft-rock tunnel U-shaped steel cover canopy supporting construction | |
CN110118085A (en) | A kind of compound advanced secondary tunneling method in two lane of top working face of large mining depth high working face | |
CN107869350A (en) | A kind of new drop rushes colliery bolting with wire mesh method | |
CN116104499A (en) | Retaining wall structure with lower middle section extending through horsehead door and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |