CN115321359A - Method for installing bridge crane in limited space - Google Patents
Method for installing bridge crane in limited space Download PDFInfo
- Publication number
- CN115321359A CN115321359A CN202211086803.4A CN202211086803A CN115321359A CN 115321359 A CN115321359 A CN 115321359A CN 202211086803 A CN202211086803 A CN 202211086803A CN 115321359 A CN115321359 A CN 115321359A
- Authority
- CN
- China
- Prior art keywords
- hoist
- hoisting
- bridge crane
- main
- trolley
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C17/00—Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C19/00—Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention relates to the technical field of bridge crane installation, in particular to a method for installing a bridge crane in a limited space, which comprises the steps of erecting a supporting platform, installing a hoisting winch and adjusting the hoisting winch by utilizing a girder at the top of a steel structure factory building, then sequentially hoisting a main beam, a secondary beam, an end beam and a trolley of the bridge crane, completing assembly, finally dismantling the supporting platform, installing the hoisting winch and adjusting the hoisting winch, and recovering the original appearance of the steel structure of the factory building; the bridge crane is hoisted by the method, large-scale hoisting equipment is not required to be leased, the construction cost is saved, the occupied space of the equipment used in the method is small, the steel structure of a workshop is not required to be dismantled or damaged, the construction time is shortened, the construction cost is reduced, the bridge crane is transported and loaded immediately, and the bridge crane is not required to be loaded and unloaded.
Description
Technical Field
The invention relates to the technical field of bridge crane installation, in particular to a bridge crane installation method in a limited space.
Background
The bridge crane is widely applied to industrial factory workshops, is an important tool for industrial production hoisting, and has the characteristics of large volume, heavy weight, high height and the like, so that the bridge crane is generally the main technical difficulty in the installation process of industrial production equipment; under the general condition, the bridge crane installation can be installed at the completion initial stage of steel construction factory building construction, but because of reasons such as production condition changes, sometimes still need to install bridge crane in the workshop that the factory building was sealed has been accomplished, at this moment, can install through renting large-scale hoisting equipment usually, not only there is the high problem of lease expense, and simultaneously, because the factory building has been accomplished sealedly, construction space receives reasons such as restriction, still need to make the dismantlement with confined factory building, vacate the large-scale hoisting equipment of being convenient for in great place and remove in factory building department, bridge crane still has the difficulty of taking one's place during hoist and mount, construction cycle is long, and is with high costs, equipment adjustment inflexible scheduling problem.
Disclosure of Invention
The invention aims to solve the problems, and provides a bridge crane installation method which can save construction cost, does not need to damage a workshop structure and does not occupy a limited space of a larger field.
The invention solves the problems and adopts the technical scheme that:
a method for installing a bridge crane in a confined space comprises the following steps:
s1, setting up a supporting platform: a supporting platform is erected between two transverse girders arranged at intervals in a workshop, the supporting platform comprises a main rib and side ribs, the main rib is arranged at the longitudinal central line of the workshop, the side ribs are symmetrically arranged at two sides of the main rib, the main rib and the side ribs are both longitudinally arranged, and two ends of the main rib and two ends of the side ribs are respectively connected to the two girders;
s2, arranging a winch: a hoisting winch is arranged at the half part of the main rib, an adjusting winch is arranged on each side rib, and the hoisting winch and the adjusting winches are arranged in a straight line;
s3, entering a main beam and an auxiliary beam of the bridge crane: when the main beam enters a workshop, the overlooking position of the main beam is required to coincide with a straight line where a hoisting winch and an adjusting winch are located, the middle point of the main beam coincides with the overlooking position of the hoisting winch, and the approach position of the auxiliary beam is consistent with that of the main beam;
s4, hoisting the main beam and the auxiliary beam of the bridge crane in place: hoisting the winch and adjusting the winch to hoist the main beam until wheels at two ends of the main beam are higher than the track beam, and stopping hoisting the winch and adjusting the winch; connecting chain blocks at two ends of a main beam, connecting the chain blocks on steel columns of a workshop at two sides, tensioning the chain blocks, simultaneously lowering steel wire ropes of two side adjusting windlasses, and slowly rotating the main beam until the main beam is vertical to the longitudinal central line of the workshop; finally, operating the hoisting winch to lower the main beam to enable wheels at two ends of the main beam to fall in the track of the track beam, wherein the hoisting method of the auxiliary beam is consistent with that of the main beam;
s5, entering a bridge crane end beam: the method comprises the following steps that end beams of the automobile loading bridge crane enter a workshop, and the overlooking positions of the two end beams are required to be respectively located at two ends of a main beam and located between the main beam and a secondary beam;
s6, hoisting the end beam of the bridge crane in place: after the traction ropes are hung on the end beams, the two end beams are respectively hoisted by utilizing the adjusting winches on the two sides, and after the end beams are hoisted to the specified height, the traction ropes are tightened to ensure that the end beams are fixed between the main beam and the auxiliary beam;
s7, the bridge crane trolley enters a workshop: loading a bridge crane trolley by an automobile to enable the trolley to be located between a main beam and a secondary beam, enabling the center of the trolley to be superposed with the overlooking position of a hoisting winch, hoisting the trolley by the hoisting winch and an adjusting winch after a traction rope is hung on the trolley, stopping hoisting until wheels of the trolley are higher than travelling rails on the main beam and the secondary beam, connecting chain blocks at two ends of the trolley, connecting the chain blocks on workshop steel columns at two sides, tensioning the chain blocks, simultaneously lowering steel wire ropes of the adjusting winch at two sides, enabling the trolley to slowly rotate, enabling wheels of the trolley to be aligned with the travelling rails, and then controlling the hoisting winch to slowly lower the trolley to enable the trolley to fall on the travelling rails on the main beam and the secondary beam;
s8, dismantling the supporting platform: and dismantling the hoisting winch, adjusting the winch, the supporting platform and the chain block, and recovering the original appearance of the steel structure of the workshop.
Preferably, in step S1, the support platform further includes reinforcing ribs arranged throughout the length, and the reinforcing ribs connect the center beam and the side beams.
Preferably, in step S2, an included angle between a straight line where the hoisting winch and the plurality of adjusting winches are located and a longitudinal center line of the workshop is not more than 65 °.
Preferably, in the step S4, when the main beam and the auxiliary beam are hoisted, the main beam and the auxiliary beam are hoisted in a manner of a big pocket at the bottom, steel wire ropes are hung on the hoisting winch and the two adjusting winches, the steel wire ropes must be kept vertical in the hoisting process, and the hoisting winch and the two adjusting winches are synchronously started to hoist.
Compared with the prior art, the invention adopting the technical scheme has the prominent characteristics that:
the bridge crane is hoisted in a workshop by the method without leasing large-scale hoisting equipment, so that the construction cost is saved, the hoisting winch and the adjusting winch are used for hoisting and lowering, the hoisting piece is stabilized by the hoisting winch in the middle, meanwhile, the direction of the hoisting piece can be adjusted by the adjusting winch, the hoisting can be completed quickly, meanwhile, the bridge crane can be reversely dismantled by the method, and the bridge crane can be quickly disassembled and assembled in a narrow space; the method has the advantages that the occupied space of the used equipment is small, the steel structure of a workshop does not need to be dismantled or damaged, the construction time is shortened, the construction cost is reduced, the purposes of transporting and loading immediately and unloading are achieved, and the method is free from loading and unloading.
Drawings
FIG. 1 is a schematic structural diagram of a bridge crane according to an embodiment of the present invention during installation;
FIG. 2 is a schematic structural diagram of a support platform according to an embodiment of the present invention;
FIG. 3 is a schematic structural view of a main beam of an embodiment of the present invention when entering a field;
FIG. 4 is a schematic structural view of the main beam during adjustment according to the embodiment of the present invention;
FIG. 5 is a schematic structural view of the main beam, the secondary beam and the end beam of the embodiment of the present invention during installation;
FIG. 6 is a schematic structural view of the cart according to the embodiment of the present invention.
In the figure: 1. a girder; 2. a main rib; 3. side ribs; 4. reinforcing ribs; 5. hoisting a winch; 6. adjusting the winch; 7. a track beam; 8. workshop steel columns; 9. a main beam; 10. a secondary beam; 11. a trolley; 12. chain rewinding; 13. an end beam.
Detailed Description
The invention will be further illustrated by the following examples, which are intended only for a better understanding of the present invention and therefore do not limit the scope of the invention.
As shown in fig. 1 to 6, a method for installing a bridge crane in a confined space comprises the following steps:
s1, building a supporting platform: a supporting platform is erected between two transverse girders 1 arranged at intervals in a workshop, the supporting platform comprises a main rib 2, two side ribs 3 and three to six reinforcing ribs 4, the main rib 2 is arranged at the longitudinal central line of the workshop, the side ribs 3 are symmetrically arranged at two sides of the main rib 2, the main rib 2 and the side ribs 3 are longitudinally arranged, two ends of the main rib 2 and two ends of the side ribs 3 are respectively connected to the two girders 1, and the reinforcing ribs 4 are arranged in a full length mode and are connected with a central beam and a side beam; the main ribs 2 and the side ribs 3 are made of H-shaped steel, and the reinforcing ribs 4 are made of channel steel.
S2, arranging a winch: a hoisting winch 5 is fixed at one half of the main rib 2, an adjusting winch 6 is fixed on each side rib 3, and the hoisting winch 5 and the two adjusting winches 6 are arranged in a straight line; the included angle between the straight line where the hoisting winch 5 and the two adjusting winches 6 are located and the longitudinal center line of the workshop is not more than 65 degrees, the two sides of the hoisting winch 5 are hoisted on the main rib 2, and the two sides of the adjusting winch 6 are welded with stop blocks on the side ribs 3, so that the hoisting winch 5 and the adjusting winch 6 can be prevented from moving horizontally.
S3, entering a main beam 9 and an auxiliary beam 10 of the bridge crane: when the main beam 9 enters a workshop, the overlooking position of the main beam 9 is required to be coincident with the straight line where the hoisting winch 5 and the adjusting winch 6 are located, the middle point of the main beam 9 is coincident with the overlooking position of the hoisting winch 5, and the approach position of the auxiliary beam 10 is consistent with that of the main beam 9.
S4, hoisting the main beam 9 and the auxiliary beam 10 of the bridge crane in place: the hoisting winch 5 and the two adjusting winches 6 are respectively connected with steel wire ropes in a hanging manner, the steel wire ropes of the hoisting winch 5 are tensioned and fixed at one half of the main beam 9, the steel wire ropes of the two adjusting winches 6 are respectively tensioned and fixed at two ends of the main beam 9, the hoisting is carried out in a mode of a big pocket at the bottom, the steel wire ropes are required to be kept vertical in the hoisting process, and the hoisting winch 5 and the two adjusting winches 6 are required to be synchronously started for hoisting;
hoisting the winch 5 and adjusting the winch 6 to hoist the main beam 9 until the wheels at the two ends of the main beam 9 are higher than the track beam 7, and stopping hoisting the winch 5 and adjusting the winch; connecting a chain block 12 at two ends of a main beam 9, connecting the chain block 12 on a workshop steel column 8 at two sides, tensioning the chain block 12, simultaneously lowering steel wire ropes of two side adjusting windlasses 6, and slowly rotating the main beam 9 until the main beam 9 is vertical to the longitudinal central line of the workshop; and finally, operating the hoisting winch 5 to lower the main beam 9, so that wheels at two ends of the main beam 9 fall in the track of the track beam 7, and the hoisting method of the auxiliary beam 10 is consistent with that of the main beam 9.
S5, entering a bridge crane end beam 13: the end beams 13 of the automobile loading bridge crane enter a workshop, and the overlooking positions of the two end beams 13 are respectively positioned at two ends of the main beam 9 and between the main beam 9 and the auxiliary beam 10.
S6, hoisting the end beam 13 of the bridge crane in place: after the traction rope is hung on the end beam 13, the two end beams 13 are respectively hoisted by utilizing the adjusting winches 6 at the two sides, after the end beam 13 is lifted to a specified height, the traction rope is tightened, and the two ends of the end beam 13 are respectively and fixedly connected to the main beam 9 and the auxiliary beam 10.
S7, the bridge crane trolley 11 enters a workshop: the method comprises the steps that a trolley 11 of the automobile loading bridge crane is parallel to a main beam 9 and is located between the main beam 9 and a secondary beam 10, the center of the trolley 11 is enabled to be coincident with the overlooking position of a hoisting winch 5, after traction ropes are hung in the middle and two ends of the trolley 11, the trolley is hoisted by the hoisting winch 5 and an adjusting winch 6, the trolley 11 stops hoisting after wheels of the trolley 11 are higher than travelling rails on the main beam 9 and the secondary beam 10, chain blocks 12 are connected to two ends of the trolley 11, the chain blocks 12 are connected to workshop steel columns 8 on two sides, steel wire ropes of the adjusting winch 6 on two sides are tensioned and lowered simultaneously by the chain blocks 12, the trolley 11 rotates slowly by 90 degrees, wheels of the trolley 11 are aligned with the travelling rails, and then the hoisting winch 5 is controlled to slowly lower the trolley 11, so that the trolley 11 falls on the travelling rails on the main beam 9 and the secondary beam 10.
S8, dismantling the supporting platform: and (3) dismantling the hoisting winch 5, adjusting the hoisting winch 6, the supporting platform and the chain block 12, and recovering the original appearance of the steel structure of the factory building.
By the method, the bridge crane is hoisted in a workshop without leasing large-scale hoisting equipment, so that the construction cost is saved, the middle hoisting winch 5 is responsible for adjusting and controlling the height of hoisting pieces (the main beam 9, the auxiliary beam 10, the end beam 13 and the trolley 11), the hoisting pieces can be rotated and adjusted to a proper direction by adjusting the winches 6 at two sides, and the bridge crane can be quickly disassembled and assembled in a narrow space; occupation space is less, need not to demolish or destroy the workshop steel construction, has shortened the engineering time, has reduced construction cost, has realized transporting promptly and has adorned promptly, need not the loading and unloading.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the scope of the present invention, which is defined in the appended claims.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211086803.4A CN115321359A (en) | 2022-09-07 | 2022-09-07 | Method for installing bridge crane in limited space |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211086803.4A CN115321359A (en) | 2022-09-07 | 2022-09-07 | Method for installing bridge crane in limited space |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115321359A true CN115321359A (en) | 2022-11-11 |
Family
ID=83929693
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211086803.4A Pending CN115321359A (en) | 2022-09-07 | 2022-09-07 | Method for installing bridge crane in limited space |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115321359A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115611188A (en) * | 2022-12-22 | 2023-01-17 | 中交第二航务工程局有限公司 | Mounting device and construction method for prefabricated middle partition plate in tunnel |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1143683A1 (en) * | 1983-10-05 | 1985-03-07 | Проектно-Технологический И Конструкторский Институт Организации Производства И Экономики Монтажных И Специальных Строительных Работ | Method of mounting single-i-beam travelling crane |
| CN201325826Y (en) * | 2008-11-17 | 2009-10-14 | 中国水利水电第七工程局有限公司机电安装分局 | Rock anchor beam hoisting device for underground power house |
| CN102267664A (en) * | 2011-05-27 | 2011-12-07 | 中国一冶集团有限公司 | Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof |
| JP2012025563A (en) * | 2010-07-26 | 2012-02-09 | Sankyu Inc | Method for installing overhead crane |
| CN102849626A (en) * | 2012-09-24 | 2013-01-02 | 中国建筑第八工程局有限公司 | Indoor non-standard crane installation method |
| CN111377371A (en) * | 2020-04-28 | 2020-07-07 | 中国一冶集团有限公司 | System and method for mounting travelling beam by means of factory building column in closed factory building |
-
2022
- 2022-09-07 CN CN202211086803.4A patent/CN115321359A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1143683A1 (en) * | 1983-10-05 | 1985-03-07 | Проектно-Технологический И Конструкторский Институт Организации Производства И Экономики Монтажных И Специальных Строительных Работ | Method of mounting single-i-beam travelling crane |
| CN201325826Y (en) * | 2008-11-17 | 2009-10-14 | 中国水利水电第七工程局有限公司机电安装分局 | Rock anchor beam hoisting device for underground power house |
| JP2012025563A (en) * | 2010-07-26 | 2012-02-09 | Sankyu Inc | Method for installing overhead crane |
| CN102267664A (en) * | 2011-05-27 | 2011-12-07 | 中国一冶集团有限公司 | Method for installing bridge crane using load-supporting roof beam for hoisting and usage thereof |
| CN102849626A (en) * | 2012-09-24 | 2013-01-02 | 中国建筑第八工程局有限公司 | Indoor non-standard crane installation method |
| CN111377371A (en) * | 2020-04-28 | 2020-07-07 | 中国一冶集团有限公司 | System and method for mounting travelling beam by means of factory building column in closed factory building |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115611188A (en) * | 2022-12-22 | 2023-01-17 | 中交第二航务工程局有限公司 | Mounting device and construction method for prefabricated middle partition plate in tunnel |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7346246B2 (en) | Heavy object moving method using heavy object moving device and heavy object moving device | |
| US5255489A (en) | Construction apparatus for buildings and constructing method therewith | |
| JP4872940B2 (en) | Bridge erection device, floor slab erection method, and bridge erection method | |
| JP4962252B2 (en) | Bridge erection method and erection device | |
| CN112160246B (en) | Method for installing composite beam | |
| CN115680173B (en) | Construction methods for ultra-large glass curtain walls in confined spaces | |
| CN116043713A (en) | A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air | |
| JPH06167089A (en) | Facing of lower surface of aerial framing body | |
| CN111335182A (en) | Portable single-rail bridge girder erection machine and steel column and steel girder installation method in bridge erecting process | |
| CN115321359A (en) | Method for installing bridge crane in limited space | |
| CN116853963B (en) | A hoisting device and hoisting method for main beam of cable-stayed bridge | |
| CN115182265B (en) | Integrated bridge girder erection machine used under working condition of dry spliced segment bent cap and construction method | |
| CN103086276A (en) | Construction method for hoisting bridge type crane in high-rise well tower type building | |
| CN111502293A (en) | Method and system for hoisting single peripheral component of assembly type building | |
| CN114045861B (en) | Tower crane foundation connecting structure transferring force to existing column and construction method thereof | |
| CN115405115A (en) | Slidable assembled jig frame and application method | |
| WO2026036686A1 (en) | Turnover facility structure used after removal of internal floor formwork supports, and construction method | |
| CN115838129B (en) | A method for dismantling large factory buildings using tower cranes during expansion. | |
| JPH06272389A (en) | Temporary unloading stage | |
| CN112030777A (en) | A down-type mobile formwork support bracket spanning transfer construction method | |
| CN108612317A (en) | A kind of band waves column type gate-type combination steel frame construction installation method | |
| JPH08333898A (en) | Trestle for vertically and horizontally conveying building blocks | |
| CN222294726U (en) | A movable steel box girder first section support removal device | |
| CN115976980B (en) | A method for installing continuous beam segment steel cages | |
| CN109056741B (en) | Method for dismantling lower steel support in multi-layer steel support |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20221111 |