CN115313292A - Cable down-hole and method for laying cable in cable down-hole - Google Patents
Cable down-hole and method for laying cable in cable down-hole Download PDFInfo
- Publication number
- CN115313292A CN115313292A CN202211039155.7A CN202211039155A CN115313292A CN 115313292 A CN115313292 A CN 115313292A CN 202211039155 A CN202211039155 A CN 202211039155A CN 115313292 A CN115313292 A CN 115313292A
- Authority
- CN
- China
- Prior art keywords
- cable
- tunnel
- manhole
- shaft
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G9/00—Installations of electric cables or lines in or on the ground or water
- H02G9/06—Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/08—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G9/00—Installations of electric cables or lines in or on the ground or water
- H02G9/08—Installations of electric cables or lines in or on the ground or water in tunnels
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G9/00—Installations of electric cables or lines in or on the ground or water
- H02G9/10—Installations of electric cables or lines in or on the ground or water in cable chambers, e.g. in manhole or in handhole
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
本发明用于井道施工领域,特别涉及一种电缆引下井及电缆引下井中铺设电缆的方法,电缆引下井,包括横井,横井的侧边设有电缆排管,横井内部设有电缆支架;竖井,竖井设在横井的一侧,竖井与横井的连接处设有人孔,人孔高于电缆排管的高度。由于横井与竖井之间设置了人孔,人孔高度高于横井中电缆排管的高度,人孔能够防止积水进入隧道内部,从而避免了隧道内电气设备受潮及损坏。电缆引下井中铺设电缆的方法,电缆从电缆排管穿设到横井中;将电缆架设在呈台阶式上升排布的电缆支架上;电缆穿过人孔进入到竖井中,然后穿过隧道顶板上的管孔进入隧道;电缆铺设完毕后,将人孔和隧道顶板上的管孔进行封堵,避免了隧道内电气设备受潮及损坏。
The invention is used in the field of hoistway construction, and particularly relates to a cable downhole and a method for laying cables in the cable downhole. The vertical shaft is located on one side of the horizontal well, and the connection between the vertical shaft and the horizontal well is provided with a manhole, and the manhole is higher than the height of the cable pipe. Since the manhole is set between the horizontal well and the vertical shaft, the height of the manhole is higher than the height of the cable pipe in the horizontal well, and the manhole can prevent the accumulation of water from entering the tunnel, thereby preventing the electrical equipment in the tunnel from being damp and damaged. The method of laying the cable in the cable downhole, the cable is passed from the cable pipe to the horizontal well; the cable is erected on the cable support arranged in a stepped ascending arrangement; the cable enters the vertical shaft through the manhole, and then passes through the tunnel roof The pipe holes on the tunnel enter the tunnel; after the cables are laid, the manholes and the pipe holes on the top plate of the tunnel are blocked to avoid moisture and damage to the electrical equipment in the tunnel.
Description
技术领域technical field
本发明用于井道施工领域,特别是涉及一种电缆引下井及电缆引下井中铺设电缆的方法。The invention is used in the field of shaft construction, and in particular relates to a cable-leading well and a method for laying cables in the cable-leading well.
背景技术Background technique
目前电缆进入电力隧道采用在电力隧道结构外壁钻孔敷设电缆进入隧道,并在进入隧道处覆土,该方式施工很粗糙,存在很多风险和隐患,电缆管孔容易导致漏水。电力隧道工作井结构顶板一般离市政路面1.5米左右,有的甚至更深,普通电缆井深度无法满足电缆从电力隧道结构侧壁进入,只能从电力隧道结构顶板往下钻孔进入,管孔缝隙处和电缆本体老化后非常容易漏水,导致隧道内电气设备受潮及损坏。At present, cables enter the power tunnel by drilling holes on the outer wall of the power tunnel structure, laying cables into the tunnel, and covering the entry tunnel with soil. This method is very rough in construction, and there are many risks and hidden dangers. The cable pipe hole is easy to cause water leakage. The roof of the power tunnel working well structure is generally about 1.5 meters away from the municipal road surface, and some are even deeper. The depth of ordinary cable wells cannot meet the requirements for cables to enter from the side wall of the power tunnel structure. It is very easy to leak water after aging and the cable body, resulting in damp and damage to the electrical equipment in the tunnel.
发明内容Contents of the invention
为解决上述技术问题中的至少之一,本发明提供一种电缆引下井及电缆引下井中铺设电缆的方法,所采用的技术方案如下。In order to solve at least one of the above technical problems, the present invention provides a cable downhole and a method for laying cables in a cable downhole, and the adopted technical solutions are as follows.
一种电缆引下井,包括A cable-guided downhole, comprising
横井,所述横井的侧边设有电缆排管,所述横井内部设有电缆支架;A horizontal well, the side of the horizontal well is provided with a cable pipe, and the inside of the horizontal well is provided with a cable support;
竖井,所述竖井设在所述横井的一侧,所述竖井与所述横井的连接处设有人孔,所述人孔高于所述电缆排管的高度。A vertical shaft, the vertical shaft is arranged on one side of the horizontal shaft, and a manhole is provided at the connection between the vertical shaft and the horizontal shaft, and the manhole is higher than the height of the cable conduit.
本发明实施例的电缆引下井至少具有如下有益效果:由于横井与竖井之间设置了人孔,人孔高度高于横井中电缆排管的高度,人孔较高,能够有效防止横井中的积水越过人孔从竖井进入隧道内部,从而避免了隧道内电气设备受潮及损坏。The cable guide shaft of the embodiment of the present invention has at least the following beneficial effects: since a manhole is set between the horizontal shaft and the vertical shaft, the height of the manhole is higher than the height of the cable pipes in the horizontal shaft, and the manhole is higher, which can effectively prevent accumulation in the horizontal shaft. Water enters the interior of the tunnel from the shaft through the manhole, thereby preventing the electrical equipment in the tunnel from being damp and damaged.
根据本发明的另一些实施例的电缆引下井,所述横井的底部设有集水口。According to other embodiments of the cable guide shaft of the present invention, the bottom of the horizontal shaft is provided with a water collection port.
根据本发明的另一些实施例的电缆引下井,所述横井的井口设有井盖,所述井盖与所述横井的井口相互配合。According to some other embodiments of the present invention, the wellhead of the horizontal well is provided with a well cover, and the well cover cooperates with the wellhead of the horizontal well.
根据本发明的另一些实施例的电缆引下井,所述电缆支架设有多个,沿着所述电缆排管向所述人孔的方向,各个所述电缆支架呈台阶式上升排布。According to some other embodiments of the present invention, there are multiple cable supports, and each cable support is arranged in a step-up manner along the direction of the cable conduit to the manhole.
根据本发明的另一些实施例的电缆引下井,所述横井的井口采用角钢包边。According to some other embodiments of the present invention, the wellhead of the horizontal well is wrapped with angle steel.
根据本发明的另一些实施例的电缆引下井,所述竖井内部设有爬梯。According to other embodiments of the present invention, a ladder is provided inside the shaft.
根据本发明的另一些实施例的电缆引下井,所述电缆排管设有多个。According to other embodiments of the present invention, there are multiple cable conduits.
一种电缆引下井中铺设电缆的方法,包括以下步骤:A method for laying a cable in a cable lead downhole, comprising the following steps:
电缆从电缆排管穿设到横井中;The cable is passed through the cable pipe into the horizontal well;
将电缆架设在呈台阶式上升排布的电缆支架上;Erect the cables on the cable supports arranged in a step-up manner;
电缆穿过人孔进入到竖井中,然后穿过隧道顶板上的管孔进入隧道;The cable enters the shaft through the manhole, and then enters the tunnel through the pipe hole on the roof of the tunnel;
电缆铺设完毕后,将人孔和隧道顶板上的管孔进行封堵。After the cables are laid, the manholes and the pipe holes on the roof of the tunnel are blocked.
本发明实施例的电缆引下井中铺设电缆的方法至少具有如下有益效果:这样架设的电缆能够有效防止积水进入到隧道中。The method for laying cables in a cable leading downhole in the embodiment of the present invention has at least the following beneficial effects: the cables erected in this way can effectively prevent accumulated water from entering the tunnel.
根据本发明的另一些实施例的电缆引下井中铺设电缆的方法,人孔采用砖块和堵漏胶泥进行封堵。According to other embodiments of the method for laying a cable in a downhole with a cable, the manhole is sealed with bricks and plugging mortar.
根据本发明的另一些实施例的电缆引下井中铺设电缆的方法,隧道顶板上穿设电缆的管孔采用堵漏胶进行封堵,隧道顶板上没有穿设电缆的管孔采用管塞和堵漏胶泥进行封堵。According to other embodiments of the present invention, the method for laying cables in a cable lead downhole, the pipe holes on the tunnel roof where cables are passed through are sealed with leak-stopping adhesive, and the pipe holes on the tunnel roof where no cables are passed through are sealed with pipe plugs and plugs. Leakage cement to seal.
附图说明Description of drawings
下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:
图1是电缆穿设在本发明一个实施例的电缆引下井中的结构示意图;Fig. 1 is a schematic diagram of the structure of a cable passing through a cable downhole according to an embodiment of the present invention;
图2是本发明一个实施例中电缆引下井的俯视图;Fig. 2 is the top view of the cable downhole in one embodiment of the present invention;
图3是图2中A-A向剖视图;Fig. 3 is a sectional view along A-A in Fig. 2;
图4是是图2中B-B向剖视图;Fig. 4 is a B-B sectional view in Fig. 2;
图5是图2中C-C向剖视图;Fig. 5 is a sectional view to C-C in Fig. 2;
图6是图2中D-D向剖视图。Fig. 6 is a sectional view taken along line D-D in Fig. 2 .
具体实施方式Detailed ways
本部分将详细描述本发明的具体实施例,本发明之较佳实施例在附图中示出,附图的作用在于用图形补充说明书文字部分的描述,使人能够直观地、形象地理解本发明的每个技术特征和整体技术方案,但其不能理解为对本发明保护范围的限制。This part will describe the specific embodiment of the present invention in detail, and the preferred embodiment of the present invention is shown in the accompanying drawings. Each technical feature and overall technical solution of the invention should not be construed as limiting the protection scope of the present invention.
本发明中,如果有描述到方向(上、下、左、右、前及后)时,其仅是为了便于描述本发明的技术方案,而不是指示或暗示所指的技术特征必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the present invention, if there is a description of directions (up, down, left, right, front and back), it is only for the convenience of describing the technical solution of the present invention, rather than indicating or implying that the referred technical features must have specific Orientation, construction and operation in a particular orientation, therefore should not be construed as limiting the invention.
本发明中,“若干”的含义是一个或者多个,“多个”的含义是两个以上,“大于”“小于”“超过”等理解为不包括本数;“以上”“以下”“以内”等理解为包括本数。在本发明的描述中,如果有描述到“第一”“第二”仅用于区分技术特征为目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量或者隐含指明所指示的技术特征的先后关系。In the present invention, "several" means one or more, "multiple" means more than two, "greater than", "less than", "exceeding", etc. are understood as excluding the original number; "above", "below", "within" " and so on are understood as including the original number. In the description of the present invention, if "first" and "second" are used only for the purpose of distinguishing technical features, it should not be understood as indicating or implying relative importance or implicitly indicating the number of indicated technical features or Implicitly indicates the sequence of the indicated technical features.
本发明中,除非另有明确的限定,“设置”“安装”“连接”等词语应做广义理解,例如,可以是直接相连,也可以通过中间媒介间接相连;可以是固定连接,也可以是可拆卸连接,还可以是一体成型;可以是机械连接,也可以是电连接或能够互相通讯;可以是两个元件内部的连通或两个元件的相互作用关系。所属技术领域技术人员可以结合技术方案的具体内容合理确定上述词语在本发明中的具体含义。In the present invention, words such as "setting", "installing" and "connecting" should be understood in a broad sense unless otherwise clearly defined. For example, they can be directly connected or indirectly connected through an intermediary; The detachable connection can also be integrally formed; it can be a mechanical connection, it can also be an electrical connection or can communicate with each other; it can be the internal communication of two components or the interaction relationship between two components. Those skilled in the art can reasonably determine the specific meanings of the above words in the present invention in combination with the specific content of the technical solution.
随着大城市电网建设以及人们对生活环境要求的提高,越来越多高压架空线存在“下地”需求,大城市中心区域出现越来越多电力隧道。明挖段电力隧道结构一般离市政路面至少2米深,顶管段电力隧道结构一般离市政路面6米深左右,大概500米左右设置一座隧道工作井,工作井根据需要建成负二层或者负三层结构,最底层接通电力隧道。由于城市美观要求以及征地困难等多种因素,较多隧道设置配电房于隧道工作井负一层,配电房中设置变压器、高压开关柜和低压配电柜等电气设备,为隧道的通风、照明等提供电源。隧道永久电源需从隧道工作井附近架空线或开关房接取,电缆需从路面10kV电缆走廊进入电力隧道工作井配电房。目前较多施工单位直接在电力隧道工作井顶板结构外壁钻孔敷设电缆进入隧道,并在进入隧道处覆土,存在漏水隐患以及电缆抢修时需开挖的缺点,隧道工作井顶板漏水会增大电房内空气湿度,产生很大的安全隐患,若渗漏的水直接滴在电气设备上可能会产生更为严重的停电事故。因此,防止隧道工作井顶板漏水对工作井配电房中的电气设备稳定安全运行至关重要。With the construction of power grids in big cities and the improvement of people's living environment requirements, more and more high-voltage overhead lines have the need to "go underground", and more and more power tunnels appear in the central areas of big cities. The power tunnel structure of the open-cut section is generally at least 2 meters deep from the municipal road surface, and the power tunnel structure of the pipe jacking section is generally about 6 meters deep from the municipal road surface. A tunnel working well is set about 500 meters away. The working well is built on the second floor or third floor according to needs Layer structure, the bottom layer is connected to the power tunnel. Due to various factors such as urban aesthetic requirements and land acquisition difficulties, many tunnels set up a power distribution room on the first floor of the tunnel working shaft. Electrical equipment such as transformers, high-voltage switch cabinets, and low-voltage power distribution cabinets are installed in the power distribution room to provide ventilation for the tunnel. , lighting, etc. to provide power. The permanent power supply of the tunnel needs to be taken from the overhead line or switch room near the tunnel working well, and the cables need to enter the power distribution room of the power tunnel working well from the 10kV cable corridor on the road. At present, many construction units directly drill holes on the outer wall of the roof structure of the power tunnel working well to lay cables into the tunnel, and cover the place where they enter the tunnel with soil. There are hidden dangers of water leakage and the shortcomings of excavation required for cable repairs. Water leakage on the roof of the working well of the tunnel will increase the power supply. The air humidity in the room creates a great potential safety hazard. If the leaking water drops directly on the electrical equipment, it may cause a more serious power outage. Therefore, preventing water leakage from the roof of the working shaft of the tunnel is very important for the stable and safe operation of the electrical equipment in the power distribution room of the working shaft.
目前电缆进入电力隧道采用在电力隧道结构外壁钻孔敷设电缆进入隧道,并在进入隧道处覆土,该方式施工很粗糙,存在以下风险和隐患:At present, cables enter the power tunnel by drilling holes on the outer wall of the power tunnel structure, laying cables into the tunnel, and covering the place where the tunnel enters. This method is very rough in construction and has the following risks and hidden dangers:
1.抢修不方便。当电缆损坏,需要新敷一根电缆进入隧道进行抢修时,需要重新挖开原有电缆进入隧道处覆土,施工工程量和施工难度较大,影响抢修时间和效率。1. It is inconvenient to repair. When the cable is damaged and it is necessary to lay a new cable into the tunnel for emergency repair, it is necessary to re-excavate the covering soil where the original cable enters the tunnel.
2.电缆管孔容易导致漏水。电力隧道工作井结构顶板一般离市政路面1.5米左右,有的甚至更深,普通电缆井深度无法满足电缆从电力隧道结构侧壁进入,只能从电力隧道结构顶板往下钻孔进入,管孔缝隙处非常容易漏水,导致隧道内电气设备受潮及损坏。2. The cable pipe hole is easy to cause water leakage. The roof of the power tunnel working well structure is generally about 1.5 meters away from the municipal road surface, and some are even deeper. The depth of ordinary cable wells cannot meet the requirements for cables to enter from the side wall of the power tunnel structure. It is very easy to leak water, which will cause moisture and damage to the electrical equipment in the tunnel.
3.电缆表层容易导致漏水。电缆表层绝缘胶皮损坏后,路面积水容易沿着电缆表皮绝缘胶皮进入隧道,导致隧道内电气设备受潮及损坏。3. The surface of the cable is easy to cause water leakage. After the insulation rubber on the surface of the cable is damaged, the accumulated water on the road will easily enter the tunnel along the insulation rubber on the cable surface, causing the electrical equipment in the tunnel to be damp and damaged.
为了解决上述技术问题,本发明提供了一种电缆引下井。In order to solve the above technical problems, the present invention provides a cable-guided downhole.
参见图1至图6,电缆引下井包括横井100和竖井200,横井100的侧边设有电缆排管101,横井100内部设有电缆支架102,竖井200设在横井100的一侧,竖井200与横井100的连接处设有人孔201,人孔201高于电缆排管101的高度。Referring to Fig. 1 to Fig. 6, the cable downhole includes a
由于横井100与竖井200之间设置了人孔201,人孔201高度高于横井100中电缆排管101的高度,人孔201能够有效防止横井100内的积水越过人孔201通过竖井200进入隧道内部,从而避免了隧道内电气设备受潮及损坏。Since the
电缆排管101和竖井200分布在横井100两侧,其中电缆排管101横向穿设固定在横井100的井壁并向外延伸。The
在一些实施例中,电缆排管101设有多个,方便同时穿设多根电缆001。In some embodiments, there are
横井100的主筋为II级、箍筋为I级,横井100的垫层106采用纵横钢筋网,砼用C15制作成型,横井100侧壁采用砌体砌筑,砌体均用Mu10砖M7.5水泥砂浆砌成,横井100内壁及外露面均用1:2水泥砂浆涂抹包覆。The main reinforcement of
竖井200建于隧道顶板300之上,隧道顶板300上设置一排用于穿设电缆001的管孔301。The
在一些实施例中,横井100的底部设有集水口103,通过集水口103能够将进入横井100中的水排走。In some embodiments, the bottom of the
具体的,横井100中设置PVC管的集水口103,PVC管内填满粗砂,纵向集水坡度不小于0.5%,防止横井100中积水。Specifically, the
为了方便电缆001损坏时进行抢修,在一些实施例中,横井100的井口处设有井盖104,井盖104与横井100的井口相互配合。In order to facilitate emergency repair when the
具体的,井盖104采用防盗型水泥盖板,井盖104顶面标高应与地面标高一致,横井100的井口设为台阶式结构,井盖104装配在台阶式结构的井口中,当电缆001损坏,需要新敷一根电缆001进入隧道进行抢修时,不涉及土建开挖,只需打开井盖104,进入横井100内将人孔201处的砖块和堵漏胶泥砸掉直接敷设新电缆001即可,提高了抢修效率,缩短了停电时间,减小了施工工程量和施工难度,同时电缆引下井的存在方便运行人员对电缆001进行维护。Specifically, the
在一些实施例中,横井100的井口采用角钢105包边,提高井口的强度。In some embodiments, the wellhead of the
进一步的,角钢105为镀锌角钢。Further, the
在一些实施例中,竖井200内部设有爬梯202。In some embodiments, a
具体的,爬梯202由圆铁制作沿着竖井200的高度方向依次排布,方便施工人员到达竖井200底部。Specifically, the
在一些实施例中,电缆支架102设有多个,沿着电缆排管101向人孔201的方向,各个电缆支架102呈台阶式上升排布。In some embodiments, there are multiple cable supports 102 , and each
当电缆001架设在电缆支架102上之后,电缆001就处于倾斜的状态,当电缆001老化后,电缆001上的积水无法通过电缆001表皮进入隧道内部。After the
在一些实施例中,电缆001绑定在电缆支架102上,保证电缆001在电缆支架102上安装牢固。In some embodiments, the
竖井200修筑在隧道顶板300上,竖井200底部钻设一排管孔301。The
待电缆001放置完毕后,将人孔201用砖块和堵漏胶泥进行封堵,隧道顶板300上穿设电缆的管孔301采用堵漏胶泥进行封堵,隧道顶板300上没有穿设电缆的管孔301采用管塞和堵漏胶泥进行封堵。After the
竖井200侧壁和顶部由钢筋网和砼一体浇筑而成,砼采用C20,竖井200内壁及外露面均用1:2水泥砂浆涂抹包覆,竖井200的高度与地面标高一致,竖井200的高度可以根据现场实际情况进行调节。The side wall and top of the
本发明还提供了一种电缆引下井中铺设电缆的方法,包括以下步骤:The present invention also provides a method for laying cables in a cable-guided well, comprising the following steps:
电缆001从电缆排管101穿设到横井100中;The
将电缆001架设在呈台阶式上升排布的电缆支架102上;Erecting the
电缆001穿过人孔201进入到竖井200中,然后穿过隧道顶板300上的管孔301进入隧道;The
电缆001铺设完毕后,将人孔201和隧道顶板300上的管孔301进行封堵。After the
这样架设的电缆001能够有效防止积水进入到隧道中。The
在一些实施例中,人孔201采用砖块和堵漏胶泥进行封堵。In some embodiments, the
在一些实施例中,隧道顶板300上穿设电缆的管孔301采用堵漏胶泥进行封堵,隧道顶板300上没有穿设电缆的管孔301采用管塞和堵漏胶泥进行封堵。In some embodiments, the pipe holes 301 on the
堵漏胶泥不仅具有防水效果,而且人孔201和管孔301处堵漏胶泥还具有防火性能,发生火灾时能够阻断火势的传播,避免火灾进一步扩大。The leakage plugging putty not only has waterproof effect, but also the plugging putty at the
当然,本申请并不局限于上述实施方式,熟悉本领域的技术人员在不违背本发明精神的前提下还可作出等同变形或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。Of course, the present application is not limited to the above-mentioned embodiments. Those skilled in the art can also make equivalent modifications or replacements without departing from the spirit of the present invention. These equivalent modifications or replacements are all included in the claims of the application. In the range.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211039155.7A CN115313292A (en) | 2022-08-29 | 2022-08-29 | Cable down-hole and method for laying cable in cable down-hole |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211039155.7A CN115313292A (en) | 2022-08-29 | 2022-08-29 | Cable down-hole and method for laying cable in cable down-hole |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115313292A true CN115313292A (en) | 2022-11-08 |
Family
ID=83864325
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211039155.7A Pending CN115313292A (en) | 2022-08-29 | 2022-08-29 | Cable down-hole and method for laying cable in cable down-hole |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115313292A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116526372A (en) * | 2023-07-03 | 2023-08-01 | 常熟虞通光电科技有限公司 | Method for laying cable by means of large-caliber drainage pipeline |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10325168A (en) * | 1997-05-27 | 1998-12-08 | Haneda Hume Pipe Co Ltd | Multifunctional manhole |
| CN109085687A (en) * | 2018-09-30 | 2018-12-25 | 广州供电局有限公司 | Optical cable accommodates well and cable duct |
| CN209066493U (en) * | 2018-09-29 | 2019-07-05 | 广东华方工程设计有限公司 | A kind of pipeline configuration of pipeline disengaging basement |
| CN212772472U (en) * | 2020-06-30 | 2021-03-23 | 陕西春秋建工工程集团有限公司 | Brick-concrete linear cable well |
| CN213062105U (en) * | 2020-06-17 | 2021-04-27 | 宾向思 | Cable hand hole well theftproof node structure |
| CN113914368A (en) * | 2021-09-26 | 2022-01-11 | 北京首钢国际工程技术有限公司 | Switching well that underground cable tunnel and cable pit link up |
-
2022
- 2022-08-29 CN CN202211039155.7A patent/CN115313292A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10325168A (en) * | 1997-05-27 | 1998-12-08 | Haneda Hume Pipe Co Ltd | Multifunctional manhole |
| CN209066493U (en) * | 2018-09-29 | 2019-07-05 | 广东华方工程设计有限公司 | A kind of pipeline configuration of pipeline disengaging basement |
| CN109085687A (en) * | 2018-09-30 | 2018-12-25 | 广州供电局有限公司 | Optical cable accommodates well and cable duct |
| CN213062105U (en) * | 2020-06-17 | 2021-04-27 | 宾向思 | Cable hand hole well theftproof node structure |
| CN212772472U (en) * | 2020-06-30 | 2021-03-23 | 陕西春秋建工工程集团有限公司 | Brick-concrete linear cable well |
| CN113914368A (en) * | 2021-09-26 | 2022-01-11 | 北京首钢国际工程技术有限公司 | Switching well that underground cable tunnel and cable pit link up |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116526372A (en) * | 2023-07-03 | 2023-08-01 | 常熟虞通光电科技有限公司 | Method for laying cable by means of large-caliber drainage pipeline |
| CN116526372B (en) * | 2023-07-03 | 2023-09-01 | 常熟虞通光电科技有限公司 | Method for laying cable by means of large-caliber drainage pipeline |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202969415U (en) | Multifunctional assembled comprehensive pipe gallery | |
| CN115182737A (en) | Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method | |
| CN112228130B (en) | Construction method for pulling out anchor cable intruding into shield zone of urban subway | |
| CN105065009B (en) | A method for expanding shield construction subway station | |
| CN103670448B (en) | A kind of underground utilities protective device and apply the supporting method of this device | |
| CN110144967A (en) | A cable-type comprehensive pipe gallery system | |
| CN104878771B (en) | The construction method of vacuum tube well precipitation system | |
| CN109695247B (en) | Deep foundation pit temporary pipeline comprehensive arrangement system and construction method | |
| CN210766871U (en) | A basic comprehensive pipe gallery applied to municipal roads | |
| CN115313292A (en) | Cable down-hole and method for laying cable in cable down-hole | |
| CN110578341A (en) | A kind of power cable pipe drilling well and its construction method | |
| CN107240901B (en) | A kind of direct-burried high-voltage cable joint protection structure | |
| CN203357324U (en) | Embedding device for ultra-long inclinometer tubes | |
| CN206144599U (en) | Tunnel emergency evacuation and rescue system | |
| CN210507520U (en) | City utility tunnel structure | |
| CN204258213U (en) | A kind of cable trough structure through body of wall place | |
| CN102593781B (en) | Transformer substation assembled type cable groove body and cable channel system thereof | |
| CN209760299U (en) | A Subway Station Structure Combining Excavation and Excavation to Avoid House Demolition | |
| CN111648773A (en) | Construction method of connection channel communicated with existing underground structure of central urban area | |
| CN112049643A (en) | Flow logging structure | |
| CN207673370U (en) | A kind of existing tunnel road surface drainage modernization system | |
| CN110374137A (en) | A kind of assembled pipe gallery push type construction technology | |
| CN212535664U (en) | Flow logging structure | |
| CN214363571U (en) | An underground cavern precipitation system that is not affected by obstacles | |
| CN204464856U (en) | A construction site temporary power cable erection device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20221108 |
