CN115284431A - Operation method of air brick production line - Google Patents

Operation method of air brick production line Download PDF

Info

Publication number
CN115284431A
CN115284431A CN202210782377.1A CN202210782377A CN115284431A CN 115284431 A CN115284431 A CN 115284431A CN 202210782377 A CN202210782377 A CN 202210782377A CN 115284431 A CN115284431 A CN 115284431A
Authority
CN
China
Prior art keywords
fixedly connected
water
production line
storage tank
servo motor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210782377.1A
Other languages
Chinese (zh)
Inventor
王翔
王军勇
尤克卫
季鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Hongji New Material Technology Co ltd
Original Assignee
Luoyang Hongji New Material Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Hongji New Material Technology Co ltd filed Critical Luoyang Hongji New Material Technology Co ltd
Priority to CN202210782377.1A priority Critical patent/CN115284431A/en
Publication of CN115284431A publication Critical patent/CN115284431A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/087Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould
    • B28B1/0873Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould the mould being placed on vibrating or jolting supports, e.g. moulding tables
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/243Setting, e.g. drying, dehydrating or firing ceramic articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28CPREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28C5/00Apparatus or methods for producing mixtures of cement with other substances, e.g. slurries, mortars, porous or fibrous compositions
    • B28C5/08Apparatus or methods for producing mixtures of cement with other substances, e.g. slurries, mortars, porous or fibrous compositions using driven mechanical means affecting the mixing
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28CPREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28C7/00Controlling the operation of apparatus for producing mixtures of clay or cement with other substances; Supplying or proportioning the ingredients for mixing clay or cement with other substances; Discharging the mixture
    • B28C7/04Supplying or proportioning the ingredients
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28CPREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28C7/00Controlling the operation of apparatus for producing mixtures of clay or cement with other substances; Supplying or proportioning the ingredients for mixing clay or cement with other substances; Discharging the mixture
    • B28C7/16Discharge means, e.g. with intermediate storage of fresh concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Dispersion Chemistry (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)

Abstract

本发明涉及透气砖生产技术领域,且公开了一种透气砖生产线的操作方法,包括厂房,厂房的顶部固定连接有承重顶墙,承重顶墙的左侧固定安装有第一伺服电机。本发明中,传统的透气砖生产线,将上一道工序完成的物料加入到下一道工序中大多都是通过人力完成的,本环节耗时耗力,增加工人工作量的同时还会影响整个生产线的生产效率,本发明通过给生产线中加入了驱动结构和加水结构,通过驱动结构上的吊装装置可以解决大多数物料转移的问题,在减少人力消耗的同时可以避免工人在转移物料过程中可能出现的危险,而加水结构可以通过水泵更加快速的完成加水,再次减少人力消耗的同时也进一步提高了整个生产线的生产效率。

Figure 202210782377

The invention relates to the technical field of production of air-permeable bricks, and discloses an operation method of a production line of air-permeable bricks. In the present invention, in the traditional air-permeable brick production line, most of the materials completed in the previous process are added to the next process by manpower. This process is time-consuming and labor-intensive, which increases the workload of workers and affects the performance of the entire production line. Production efficiency, the present invention adds a driving structure and a water adding structure to the production line, and can solve most of the material transfer problems through the hoisting device on the driving structure, while reducing labor consumption, it can avoid the workers that may occur in the process of transferring materials. Dangerous, and the water adding structure can complete the water addition more quickly through the water pump, which reduces the labor consumption and further improves the production efficiency of the entire production line.

Figure 202210782377

Description

一种透气砖生产线的操作方法An operating method of a breathable brick production line

技术领域technical field

本发明涉及透气砖生产技术领域,具体为一种透气砖生产线的操作方法。The invention relates to the technical field of breathable brick production, in particular to an operation method of a breathable brick production line.

背景技术Background technique

透气砖是一种高寿命节能降耗新产品,结构设计合理,具有良好的热稳定性、抗冲刷性、耐侵蚀性、和抗渗透性,具吹通率高,操作安全可靠,使用寿命长等特点,透气砖的结构主要有弥散型透气砖、直通定向型透气砖、狭缝定向型透气砖,为了提高透气砖的生产效率,需要一种透气砖生产线的操作方法。Air permeable brick is a new product with long service life, energy saving and consumption reduction. It has reasonable structure design, good thermal stability, erosion resistance, corrosion resistance and permeability resistance, high blowing rate, safe and reliable operation and long service life. And other characteristics, the structure of the breathable brick mainly includes dispersion type breathable brick, straight through directional breathable brick, slit oriented breathable brick, in order to improve the production efficiency of breathable brick, an operation method of the breathable brick production line is needed.

而现有的技术中,现有的透气砖生产线都是基本可以完成透气砖从原料到加工成型的整个过程,但一些透气砖生产线较为复杂,布局不够合理,且一般的没有可以自由前后左右移动的吊装装置来辅助生产线进行生产,这样可能会耗费较多人力,不但增加了操作工人的工作量也让生产线的生产效率低下。In the existing technology, the existing breathable brick production lines can basically complete the whole process of breathable bricks from raw materials to processing and molding, but some breathable brick production lines are more complicated, the layout is not reasonable enough, and generally there is no freedom to move back and forth. The lifting device is used to assist the production line, which may consume more manpower, which not only increases the workload of the operators but also reduces the production efficiency of the production line.

发明内容Contents of the invention

解决的技术问题Technical issues resolved

针对现有技术的不足,本发明提供了一种透气砖生产线的操作方法,具备可以自由前后左右移动的吊装装置的优点,解决了一些透气砖生产线较为复杂,布局不够合理,且一般的没有可以自由前后左右移动的吊装装置来辅助生产线进行生产,这样可能会耗费较多人力,不但增加了操作工人的工作量也让生产线的生产效率低下的问题。Aiming at the deficiencies of the prior art, the present invention provides an operation method for a breathable brick production line, which has the advantages of a hoisting device that can freely move back and forth, left and right, and solves the problem that some breathable brick production lines are relatively complicated, the layout is not reasonable enough, and generally there is no The hoisting device that moves back and forth freely to assist the production line may consume more manpower, which not only increases the workload of the operators but also reduces the production efficiency of the production line.

(二)技术方案(2) Technical solution

为实现上述目的,本发明提供如下技术方案:一种透气砖生产线的操作方法,包括厂房,所述厂房的顶部固定连接有承重顶墙,所述承重顶墙的内部设置有驱动结构,所述厂房的内部固定连接有混料机,所述厂房的内部设置有加水结构;In order to achieve the above object, the present invention provides the following technical solutions: an operation method of a breathable brick production line, including a factory building, the top of the factory building is fixedly connected with a load-bearing top wall, and the inside of the load-bearing top wall is provided with a drive structure, the The interior of the factory building is fixedly connected with a mixer, and the interior of the factory building is provided with a water adding structure;

所述驱动结构包括第一伺服电机、第一驱动杆、第一限位板、第一螺纹杆、第一螺纹块、驱动箱、第二伺服电机、第二驱动杆、第二限位板、第二螺纹杆、第二螺纹块和吊装装置,所述承重顶墙的左侧固定安装有第一伺服电机,所述第一伺服电机的输出端固定连接有第一驱动杆,所述第一驱动杆的外表面固定连接有第一限位板,所述第一驱动杆的内部固定连接有第一螺纹杆,所述第一螺纹杆的外表面螺纹连接有第一螺纹块,所述第一螺纹块的底部固定连接有驱动箱,所述驱动箱的后表面固定安装有第二伺服电机,所述第二伺服电机的输出端固定连接有第二驱动杆,所述第二驱动杆的外表面固定连接有第二限位板,所述第二驱动杆的内部固定连接有第二螺纹杆,所述第二螺纹杆的外表面螺纹连接有第二螺纹块,所述第二螺纹块的底部设置有吊装装置。The drive structure includes a first servo motor, a first drive rod, a first limit plate, a first threaded rod, a first thread block, a drive box, a second servo motor, a second drive rod, a second limit plate, The second threaded rod, the second threaded block and the hoisting device, the first servo motor is fixedly installed on the left side of the load-bearing top wall, the output end of the first servo motor is fixedly connected with the first drive rod, the first The outer surface of the driving rod is fixedly connected with a first limiting plate, the inside of the first driving rod is fixedly connected with a first threaded rod, the outer surface of the first threaded rod is threaded with a first threaded block, and the first threaded rod is connected with a first threaded block. A drive box is fixedly connected to the bottom of a threaded block, a second servo motor is fixedly installed on the rear surface of the drive box, and a second drive rod is fixedly connected to the output end of the second drive rod. The outer surface is fixedly connected with a second limiting plate, the inside of the second driving rod is fixedly connected with a second threaded rod, the outer surface of the second threaded rod is threaded with a second threaded block, and the second threaded block The bottom is provided with a hoisting device.

优选的,所述加水结构包括储水箱、机箱、水泵、第一连通管、第二连通管、计量水箱和第一称重平台,所述厂房的内部分别固定连接有储水箱和机箱,所述机箱的内部固定安装有水泵,所述水泵的输出端固定连接有第一连通管,所述第一连通管的内部固定连通有第二连通管,所述混料机的顶部固定连接有第一称重平台,所述第一称重平台的顶部设置有计量水箱,所述第二连通管的内部与储水箱的内部固定连通,所述第二连通管远离储水箱的一端与计量水箱的内部固定连通。Preferably, the water adding structure includes a water storage tank, a cabinet, a water pump, a first communication pipe, a second communication pipe, a metering water tank and a first weighing platform, and the water storage tank and the cabinet are fixedly connected to the inside of the workshop, and the A water pump is fixedly installed inside the cabinet, the output end of the water pump is fixedly connected with a first connecting pipe, the inside of the first connecting pipe is fixedly connected with a second connecting pipe, and the top of the mixer is fixedly connected with a first connecting pipe. Weighing platform, the top of the first weighing platform is provided with a metering water tank, the inside of the second communication pipe is fixedly connected with the inside of the water storage tank, and the end of the second communication pipe far away from the water storage tank is connected with the inside of the metering water tank Fixed connectivity.

优选的,所述吊装装置的内部设置有吊钩,所述吊钩的内表面设置有双重绕绳,所述厂房的内部固定连接有支撑底座,所述支撑底座的内部固定连接有料仓,吊装装置使用吊钩可以将吨袋吊起,将内部的原材料倒入到料仓内,吊钩配合双重绕绳可以用来固定接料小车和模具,让吊装装置的功能性更强,支撑底座起到固定和支撑料仓的作用。Preferably, the inside of the hoisting device is provided with a hook, the inner surface of the hook is provided with double ropes, the inside of the plant is fixedly connected with a support base, and the inside of the support base is fixedly connected with a silo. The device uses a hook to lift the large bag and pour the internal raw materials into the silo. The hook and the double rope can be used to fix the receiving trolley and the mould, which makes the lifting device more functional and supports the base. To fix and support the role of the silo.

优选的,所述料仓的右侧固定连接有出料管,所述出料管的内部设置有阀门,所述厂房的内部固定连接有第二称重平台,所述第二称重平台的顶部设置有接料小车,将接料小车移动到所需的料仓下方,打开阀门让原料通过出料管进入到接料小车内,根据第二称重平台让小车内接够一块砖所需重量的原料后,关闭阀门停止下料。Preferably, the right side of the silo is fixedly connected with a discharge pipe, the inside of the discharge pipe is provided with a valve, the inside of the workshop is fixedly connected with a second weighing platform, and the inside of the second weighing platform There is a material receiving trolley on the top, move the material receiving trolley to the bottom of the required silo, open the valve to let the raw materials enter the material receiving trolley through the discharge pipe, and let the trolley receive enough for a brick according to the second weighing platform. After weighing the raw material, close the valve to stop feeding.

优选的,所述厂房的内部固定安装有振动平台,所述振动平台的顶部设置有模具,所述混料机的底部与模具的顶部相适配,所述混料机的顶部活动连接有密封盖,所述储水箱的顶部螺纹连接有螺纹盖,混料机搅拌物料至充分混合后,从混料机下方出料口进入到用以成型的模具中,模具下面有振动平台,在成型过程中振动平台持续振动。Preferably, a vibrating platform is fixedly installed inside the workshop, a mold is arranged on the top of the vibrating platform, the bottom of the mixer is matched with the top of the mould, and the top of the mixer is movably connected with a sealing Cover, the top of the water storage tank is threadedly connected with a threaded cover. After the mixer stirs the material until it is fully mixed, it enters the mold for molding from the outlet below the mixer. There is a vibration platform under the mold. During the molding process The medium vibration platform vibrates continuously.

优选的,所述厂房的内部分别固定连接有窑炉和支架,所述支架的外表面与窑炉的内部相适配,所述支架的内部设置有滑轨,且滑轨的内部设置有模具车,模具中倒满物料后,再次使用吊装装置将盛满物料的模具放在模具车上,模具车下面的支架内有轨道,轨道连通至窑炉内部,模具车上放满模具后,将模具车推入窑炉中进行高温烧制,最后冷却脱模后,即生产完成。Preferably, the inside of the factory building is fixedly connected with a kiln and a bracket, the outer surface of the bracket is adapted to the inside of the kiln, the inside of the bracket is provided with a slide rail, and the inside of the slide rail is provided with a mold Car, after the mold is filled with materials, use the lifting device again to place the mold full of materials on the mold car. There is a track in the bracket under the mold car, and the track is connected to the inside of the kiln. After the mold car is full of molds, put The mold car is pushed into the kiln for high-temperature firing, and finally the production is completed after cooling and demoulding.

优选的,所述承重顶墙的内部开设有滑槽,所述滑槽的内部滑动卡接有滑动卡块,所述滑动卡块的底部与驱动箱的顶部固定连接,驱动箱上的滑动卡块可以在滑槽内滑动,起到辅助支撑驱动箱的作用。Preferably, the inside of the load-bearing top wall is provided with a chute, the inside of the chute is slidably engaged with a sliding block, the bottom of the sliding block is fixedly connected to the top of the drive box, and the slide block on the drive box The block can slide in the chute to play the role of supporting the drive box.

与现有技术相比,本发明提供了一种透气砖生产线的操作方法,具备以下有益效果:Compared with the prior art, the present invention provides an operation method of a breathable brick production line, which has the following beneficial effects:

1、传统的透气砖生产线,将上一道工序完成的物料加入到下一道工序中大多都是通过人力完成的,本环节耗时耗力,增加工人工作量的同时还会影响整个生产线的生产效率,本发明通过给生产线中加入了驱动结构和加水结构,通过驱动结构上的吊装装置可以解决大多数物料转移的问题,在减少人力消耗的同时可以避免工人在转移物料过程中可能出现的危险,而加水结构可以通过水泵更加快速的完成加水,再次减少人力消耗的同时也进一步提高了整个生产线的生产效率。1. In the traditional breathable brick production line, adding the materials completed in the previous process to the next process is mostly done by manpower. This link is time-consuming and labor-intensive, which increases the workload of workers and also affects the production efficiency of the entire production line. , the present invention adds a driving structure and a water adding structure to the production line, and the lifting device on the driving structure can solve most of the problems of material transfer, while reducing manpower consumption, it can avoid the possible danger of workers in the process of transferring materials. The water adding structure can complete water adding more quickly through the water pump, which reduces manpower consumption and further improves the production efficiency of the entire production line.

2、该透气砖生产线,通过驱动结构上的吊装装置将吨包中的原材料倒入对应的料仓中存放,再通过吊钩和双重绕绳将达到重量的接料小车固定住,再通过吊装装置将小车吊起并将内部的原料倒入到混料机内,启动加水结构让水泵将储水箱内的水抽入到计量水箱内,达到重量后将水加入到混料机内,再使用吊装装置将注满混合后原料的模具放到模具车内,模具车放满后通过支架上的滑轨将模具车推入到窑炉内高温烧制,最终冷却脱模后,即生产完成,本生产线结构简单且布局合理,在不影响产品质量的同时还提高了生产效率。2. The breathable brick production line, through the hoisting device on the driving structure, pours the raw materials in the ton bag into the corresponding silo for storage, and then fixes the receiving trolley that has reached the weight through the hook and double winding rope, and then hoist it The device lifts the trolley and pours the internal raw materials into the mixer, activates the water adding structure to let the water pump pump the water in the water storage tank into the metering water tank, and adds the water into the mixer after reaching the weight, and then uses it The hoisting device puts the mold filled with mixed raw materials into the mold car. After the mold car is full, the mold car is pushed into the kiln through the slide rail on the bracket for high-temperature firing. After the final cooling and demoulding, the production is completed. The production line has a simple structure and a reasonable layout, which improves production efficiency without affecting product quality.

附图说明Description of drawings

图1为本发明主视结构示意图;Fig. 1 is a schematic diagram of the main view structure of the present invention;

图2为本发明混料机俯视结构示意图;Fig. 2 is the top view structure schematic diagram of mixer of the present invention;

图3为本发明驱动箱侧视结构示意图。Fig. 3 is a side view structural schematic diagram of the drive box of the present invention.

其中:1、厂房;2、承重顶墙;3、驱动结构;301、第一伺服电机;302、第一驱动杆;303、第一限位板;304、第一螺纹杆;305、第一螺纹块;306、驱动箱;307、第二伺服电机;308、第二驱动杆;309、第二限位板;310、第二螺纹杆;311、第二螺纹块;312、吊装装置;4、混料机;5、加水结构;501、储水箱;502、机箱;503、水泵;504、第一连通管;505、第二连通管;506、计量水箱;507、第一称重平台;6、吊钩;7、双重绕绳;8、支撑底座;9、料仓;10、出料管;11、阀门;12、第二称重平台;13、接料小车;14、振动平台;15、模具;16、密封盖;17、螺纹盖;18、窑炉;19、支架;20、模具车;21、滑槽;22、滑动卡块。Among them: 1. Factory building; 2. Load-bearing top wall; 3. Driving structure; 301. The first servo motor; 302. The first driving rod; 303. The first limiting plate; 304. The first threaded rod; 305. The first Threaded block; 306, drive box; 307, second servo motor; 308, second drive rod; 309, second limit plate; 310, second threaded rod; 311, second threaded block; 312, hoisting device; 4 , mixing machine; 5, water adding structure; 501, water storage tank; 502, chassis; 503, water pump; 504, first connecting pipe; 505, second connecting pipe; 506, metering water tank; 507, first weighing platform; 6. Hook; 7. Double winding rope; 8. Supporting base; 9. Material bin; 10. Discharge pipe; 11. Valve; 12. Second weighing platform; 13. Receiving trolley; 14. Vibration platform; 15. Mould; 16. Sealing cover; 17. Threaded cover; 18. Kiln; 19. Bracket; 20. Mold car; 21. Chute; 22. Slide block.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

请参阅图1-3,一种透气砖生产线的操作方法,包括厂房1,厂房1的顶部固定连接有承重顶墙2,承重顶墙2的内部设置有驱动结构3,厂房1的内部固定连接有混料机4,厂房1的内部设置有加水结构5,驱动结构3包括第一伺服电机301、第一驱动杆302、第一限位板303、第一螺纹杆304、第一螺纹块305、驱动箱306、第二伺服电机307、第二驱动杆308、第二限位板309、第二螺纹杆310、第二螺纹块311和吊装装置312,承重顶墙2的左侧固定安装有第一伺服电机301,第一伺服电机301的输出端固定连接有第一驱动杆302,第一驱动杆302的外表面固定连接有第一限位板303,第一驱动杆302的内部固定连接有第一螺纹杆304,第一螺纹杆304的外表面螺纹连接有第一螺纹块305,第一螺纹块305的底部固定连接有驱动箱306,驱动箱306的后表面固定安装有第二伺服电机307,第二伺服电机307的输出端固定连接有第二驱动杆308,第二驱动杆308的外表面固定连接有第二限位板309,第二驱动杆308的内部固定连接有第二螺纹杆310,第二螺纹杆310的外表面螺纹连接有第二螺纹块311,第二螺纹块311的底部设置有吊装装置312,吊装装置312的内部设置有吊钩6,滑动卡块22的底部与驱动箱306的顶部固定连接。Please refer to Figure 1-3, an operation method of a breathable brick production line, including a factory building 1, a load-bearing roof wall 2 is fixedly connected to the top of the factory building 1, and a driving structure 3 is arranged inside the load-bearing roof wall 2, and the inside of the factory building 1 is fixedly connected There is a mixer 4, a water adding structure 5 is provided inside the factory building 1, and the driving structure 3 includes a first servo motor 301, a first driving rod 302, a first limiting plate 303, a first threaded rod 304, and a first threaded block 305 , the drive box 306, the second servo motor 307, the second drive rod 308, the second limit plate 309, the second threaded rod 310, the second threaded block 311 and the hoisting device 312, the left side of the load-bearing top wall 2 is fixedly installed with The first servo motor 301, the output end of the first servo motor 301 is fixedly connected with the first driving rod 302, the outer surface of the first driving rod 302 is fixedly connected with the first limiting plate 303, and the inside of the first driving rod 302 is fixedly connected There is a first threaded rod 304, the outer surface of the first threaded rod 304 is threadedly connected with a first threaded block 305, the bottom of the first threaded block 305 is fixedly connected with a driving box 306, and the rear surface of the driving box 306 is fixedly installed with a second servo Motor 307, the output end of the second servo motor 307 is fixedly connected with the second driving rod 308, the outer surface of the second driving rod 308 is fixedly connected with the second limit plate 309, and the inside of the second driving rod 308 is fixedly connected with the second Threaded rod 310, the outer surface of the second threaded rod 310 is threadedly connected with a second threaded block 311, the bottom of the second threaded block 311 is provided with a hoisting device 312, the inside of the hoisting device 312 is provided with a suspension hook 6, the sliding block 22 The bottom is fixedly connected to the top of the drive box 306 .

根据上述技术方案,通过分别启动第一伺服电机301和第二伺服电机307可以控制吊装装置312前后左右自由移动,即可让吊装装置312可以满足整个生产线使用。According to the above technical solution, by starting the first servo motor 301 and the second servo motor 307 respectively, the hoisting device 312 can be controlled to move freely, forward, backward, left, and right, so that the hoisting device 312 can be used by the entire production line.

具体的,厂房1的内部固定连接有混料机4,厂房1的内部设置有加水结构5,加水结构5包括储水箱501、机箱502、水泵503、第一连通管504、第二连通管505、计量水箱506和第一称重平台507,厂房1的内部分别固定连接有储水箱501和机箱502,机箱502的内部固定安装有水泵503,水泵503的输出端固定连接有第一连通管504,第一连通管504的内部固定连通有第二连通管505,混料机4的顶部固定连接有第一称重平台507,第一称重平台507的顶部设置有计量水箱506,第二连通管505的内部与储水箱501的内部固定连通,第二连通管505远离储水箱501的一端与计量水箱506的内部固定连通。Specifically, the inside of the plant 1 is fixedly connected with a mixer 4, and the inside of the plant 1 is provided with a water adding structure 5. The water adding structure 5 includes a water storage tank 501, a cabinet 502, a water pump 503, a first connecting pipe 504, and a second connecting pipe 505. , a metering water tank 506 and a first weighing platform 507, a water storage tank 501 and a cabinet 502 are fixedly connected to the inside of the factory building 1, a water pump 503 is fixedly installed inside the cabinet 502, and a first communication pipe 504 is fixedly connected to the output end of the water pump 503 , the inside of the first communication pipe 504 is fixedly connected with a second communication pipe 505, the top of the mixer 4 is fixedly connected with a first weighing platform 507, the top of the first weighing platform 507 is provided with a metering water tank 506, the second communication The inside of the tube 505 is fixedly communicated with the inside of the water storage tank 501 , and the end of the second communication tube 505 away from the water storage tank 501 is fixedly communicated with the inside of the metering water tank 506 .

根据上述方案,启动水泵503可以将储水箱501内的水抽入到计量水箱506内,根据第一称重平台507让计量水箱506内接够所需重量的水后通过与混料机4连通的注水口倒入混料机4中。According to the above scheme, start the water pump 503 to pump the water in the water storage tank 501 into the metering water tank 506, and let the metering water tank 506 receive enough water of the required weight according to the first weighing platform 507 to communicate with the mixer 4 The water injection port is poured in the mixer 4.

具体的,吊钩6的内表面设置有双重绕绳7,厂房1的内部固定连接有支撑底座8,支撑底座8的内部固定连接有料仓9,料仓9的右侧固定连接有出料管10,出料管10的内部设置有阀门11,厂房1的内部固定连接有第二称重平台12,第二称重平台12的顶部设置有接料小车13,厂房1的内部固定安装有振动平台14,振动平台14的顶部设置有模具15,混料机4的底部与模具15的顶部相适配,混料机4的顶部活动连接有密封盖16,储水箱501的顶部螺纹连接有螺纹盖17,厂房1的内部分别固定连接有窑炉18和支架19,支架19的外表面与窑炉18的内部相适配,支架19的内部设置有滑轨,且滑轨的内部设置有模具车20,承重顶墙2的内部开设有滑槽21,滑槽21的内部滑动卡接有滑动卡块22。Specifically, the inner surface of the hook 6 is provided with a double rope 7, the inside of the factory building 1 is fixedly connected with a support base 8, the inside of the support base 8 is fixedly connected with a feed bin 9, and the right side of the feed bin 9 is fixedly connected with a discharge pipe 10. A valve 11 is installed inside the discharge pipe 10, a second weighing platform 12 is fixedly connected to the inside of the factory building 1, and a receiving trolley 13 is arranged on the top of the second weighing platform 12, and a vibrating device is fixedly installed inside the factory building 1. Platform 14, the top of vibrating platform 14 is provided with mold 15, the bottom of mixer 4 is matched with the top of mold 15, and the top of mixer 4 is movably connected with sealing cover 16, and the top screw connection of water storage tank 501 has screw thread Cover 17, the interior of workshop 1 is fixedly connected with kiln 18 and support 19 respectively, the outer surface of support 19 is adapted to the inside of kiln 18, and the interior of support 19 is provided with slide rail, and the interior of slide rail is provided with mold The inside of the car 20 and the load-bearing top wall 2 is provided with a chute 21 , and the inside of the chute 21 is slidably engaged with a sliding block 22 .

根据上述方案,吊钩6配合双重绕绳7让吊装装置312可以解决大部分问题,支撑底座8起到固定支撑料仓9的作用,打开阀门11将需要的原材料流入到接料小车13内,将经过称量后的原材料和水加入到混料机4内,混合完成后流入到模具15内,在成型过程中振动平台14持续振动,模具车20放满后推入到窑炉18内高温烧制,滑动卡块22在滑槽21内滑动起到辅助支撑驱动箱306的作用。According to the above scheme, the hoisting device 312 can solve most of the problems by combining the hook 6 with the double rope 7, the support base 8 plays the role of fixing the support bin 9, and the valve 11 is opened to flow the required raw materials into the receiving trolley 13, Add the weighed raw materials and water into the mixer 4, and flow into the mold 15 after the mixing is completed. During the molding process, the vibration platform 14 continues to vibrate. After the mold car 20 is full, it is pushed into the kiln 18 for high temperature. During firing, the sliding block 22 slides in the chute 21 to play an auxiliary role in supporting the driving box 306 .

为了使得本机械在使用的时候更加便捷,本发明优选使用金源泰JYT的180伺服电机。In order to make the machine more convenient to use, the present invention preferably uses the 180 servo motor of Jinyuantai JYT.

工作原理:该透气砖生产线,在使用的时候,首先要运行驱动结构3中的第一伺服电机301和第二伺服电机307,第一伺服电机301可以通过第一驱动杆302带动第一螺纹杆304转动,让第一螺纹块305带动驱动箱306一起左右移动,第二伺服电机307可以通过第二驱动杆308带动第二螺纹杆310转动,让第二螺纹块311连带吊装装置312一起前后移动,让吊装装置312可以将吨包中的原材料倒入对应的料仓9中存放,一个料仓9对应一种透气砖的原材料,将接料小车13移动到所需的料仓9下方,打开阀门11让原料通过出料管10进入到接料小车13内,根据第二称重平台12让小车内接够一块砖所需重量的原料后,关闭阀门11停止下料,打开混料机4上的密封盖16,将接料小车13中的物料通过吊装装置312倾倒入混料机4内,启动水泵503,让其通过第一连通管504和第二连通管505将储水箱501内的水抽入到计量水箱506内,根据第一称重平台507让计量水箱506内接够所需重量的水后通过与混料机4连通的注水口倒入混料机4中,混料机4搅拌物料至充分混合后,从混料机4下方出料口进入到用以成型的模具15中,模具15下面设置有振动平台14,在成型过程中振动平台14持续振动,模具15中倒满物料后,再次使用吊装装置312将盛满物料的模具15放在模具车20上,模具车20下面的支架19内有轨道,轨道连通至窑炉18内部,模具车20上放满模具15后,将模具车20推入窑炉18中进行高温烧制,最后冷却脱模后,即生产完成,两个第一限位板303起到限制第一螺纹块305移动范围的作用,两个第二限位板309起到限制第二螺纹块311移动范围的作用,支撑底座8分别起到支撑和固定料仓9的作用,打开螺纹盖17可以给储水箱501内补充水源,驱动箱306上的滑动卡块22可以在滑槽21内滑动,起到辅助支撑驱动箱306的作用。Working principle: When the breathable brick production line is in use, the first servo motor 301 and the second servo motor 307 in the drive structure 3 must be operated first, and the first servo motor 301 can drive the first threaded rod through the first drive rod 302 304 rotates, let the first threaded block 305 drive the drive box 306 to move left and right together, and the second servo motor 307 can drive the second threaded rod 310 to rotate through the second drive rod 308, so that the second threaded block 311 and the lifting device 312 move forward and backward together , so that the hoisting device 312 can pour the raw materials in the ton bag into the corresponding silo 9 for storage, one silo 9 corresponds to a raw material of a kind of breathable brick, move the receiving trolley 13 to the bottom of the required silo 9, open The valve 11 allows the raw materials to enter the material receiving trolley 13 through the discharge pipe 10, and after the second weighing platform 12 allows the trolley to receive enough raw materials of the required weight for a brick, close the valve 11 to stop feeding, and open the mixer 4 The sealing cover 16 on the top, the material in the receiving trolley 13 is poured into the mixer 4 through the hoisting device 312, and the water pump 503 is started to let it pass through the first connecting pipe 504 and the second connecting pipe 505. Water is pumped into the metering water tank 506, according to the first weighing platform 507, the water of the required weight is connected in the metering water tank 506 and then poured into the mixer 4 through the water injection port communicated with the mixer 4, and the mixer 4 Stir the materials until they are fully mixed, and then enter the mold 15 for molding from the discharge port below the mixer 4. A vibration platform 14 is arranged below the mold 15. During the molding process, the vibration platform 14 continues to vibrate, and the mold 15 is poured After the material is full, use the hoisting device 312 again to place the mold 15 full of materials on the mold car 20. There is a track in the support 19 below the mold car 20, and the track is connected to the inside of the kiln 18. The mold car 20 is filled with molds 15 Finally, the mold car 20 is pushed into the kiln 18 for high-temperature firing, and finally the production is completed after cooling and demoulding. The second limiting plate 309 plays the role of limiting the movement range of the second threaded block 311, and the support base 8 plays the role of supporting and fixing the feed bin 9 respectively. Opening the threaded cover 17 can replenish the water source in the water storage tank 501, and the drive box 306 The upper sliding block 22 can slide in the chute 21 to play the role of supporting the drive box 306 .

尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes, modifications and substitutions can be made to these embodiments without departing from the principle and spirit of the present invention. and modifications, the scope of the invention is defined by the appended claims and their equivalents.

Claims (7)

1. An operation method of an air brick production line, which comprises a factory building (1) and is characterized in that: the top of the factory building (1) is fixedly connected with a bearing top wall (2), a driving structure (3) is arranged inside the bearing top wall (2), a mixer (4) is fixedly connected inside the factory building (1), and a water adding structure (5) is arranged inside the factory building (1);
the driving structure (3) comprises a first servo motor (301), a first driving rod (302), a first limiting plate (303), a first threaded rod (304), a first threaded block (305), a driving box (306), a second servo motor (307), a second driving rod (308), a second limiting plate (309), a second threaded rod (310), a second threaded block (311) and a hoisting device (312), wherein the first servo motor (301) is fixedly arranged on the left side of the bearing top wall (2), the first driving rod (302) is fixedly connected with the output end of the first servo motor (301), the first limiting plate (303) is fixedly connected with the outer surface of the first driving rod (302), the first threaded rod (304) is fixedly connected with the inner part of the first driving rod (302), the first threaded block (305) is fixedly connected with the outer surface of the first threaded rod (304), the driving box (306) is fixedly connected with the bottom of the first threaded block (305), the second servo motor (307) is fixedly connected with the rear surface of the driving box (306), the output end of the second servo motor (307) is fixedly connected with the second threaded block (308), the second driving rod (309) is fixedly connected with the outer surface of the second driving rod (308), and the second driving rod (310) is fixedly connected with the inner part of the second driving rod (308), the outer surface of the second threaded rod (310) is in threaded connection with a second threaded block (311), and the bottom of the second threaded block (311) is provided with a hoisting device (312);
the operation method of the air brick production line comprises the following specific operation steps:
when the material receiving trolley is used, firstly, a first servo motor (301) and a second servo motor (307) in a driving structure (3) need to be operated, the first servo motor (301) can drive a first threaded rod (304) to rotate through a first driving rod (302), a first threaded block (305) drives a driving box (306) to move left and right together, a second servo motor (307) can drive a second threaded rod (310) to rotate through a second driving rod (308), a second threaded block (311) is connected with a hoisting device (312) to move back and forth, the hoisting device (312) can pour raw materials in ton bags into corresponding storage bins (9) to be stored, one storage bin (9) corresponds to raw materials of an air brick, the material receiving trolley (13) is moved to the lower part of a required storage bin (9), a valve (11) is opened to enable a discharge pipe of the raw materials to enter the material receiving trolley (13) through a discharge pipe (10), the raw materials of the trolley are poured into a water storage tank (13) through a water pump (16) and a water storage tank (501) and a water pump (501) which are started according to pour water tank (501) and a water tank (3) which is connected with a water tank (505) and a water pump (505) which is connected with the material storage tank (312) and is connected with the material storage tank (504) and is connected with the material storage tank (3) in the material storage tank (12) in the material receiving trolley, according to the first weighing platform (507), water with enough required weight is filled in a metering water tank (506) and then poured into a mixer (4) through a water filling port communicated with the mixer (4), the mixer (4) stirs materials until the materials are fully mixed, the materials enter a mold (15) for molding from a discharge port below the mixer (4), a vibration platform (14) is arranged below the mold (15), the vibration platform (14) continuously vibrates in the molding process, after the mold (15) is fully filled with the materials, a hoisting device (312) is used again to place the mold (15) filled with the materials on a mold vehicle (20), a rail is arranged in a support (19) below the mold vehicle (20) and communicated to the inside of a kiln (18), after the mold vehicle (20) is fully placed with the mold (15), the mold vehicle (20) is pushed into the kiln (18) for high-temperature firing, after cooling and demolding, production is completed, two first limiting plates (303) play a role in limiting a first thread block (305) moving range, two second limiting plates (309) play a role in limiting water tank (17) and can be respectively supported by a sliding chute (17), and a water storage tank (311) which can be supported by a second thread block (9) which can be opened, and a water storage tank (311) can be supported by a water storage tank (9), the auxiliary supporting function is realized by the auxiliary supporting function of the driving box (306).
2. The method for operating a gas permeable brick production line according to claim 1, wherein: the water adding structure (5) comprises a water storage tank (501), a case (502), a water pump (503), a first communicating pipe (504), a second communicating pipe (505), a metering water tank (506) and a first weighing platform (507), wherein the inside of the factory building (1) is fixedly connected with the water storage tank (501) and the case (502) respectively, the water pump (503) is fixedly arranged inside the case (502), the first communicating pipe (504) is fixedly connected with an output end of the water pump (503), the second communicating pipe (505) is fixedly communicated inside the first communicating pipe (504), the first weighing platform (507) is fixedly connected with the top of the mixer (4), the metering water tank (506) is arranged at the top of the first weighing platform (507), the inside of the second communicating pipe (505) is fixedly communicated with the inside of the water storage tank (501), and one end, far away from the water storage tank (501), of the second communicating pipe (505) is fixedly communicated with the inside of the metering water tank (506).
3. The method for operating a gas permeable brick production line according to claim 1, wherein: the inside of hoist device (312) is provided with lifting hook (6), the internal surface of lifting hook (6) is provided with dual wiring (7), the inside fixedly connected with of factory building (1) supports base (8), support inside fixedly connected with feed bin (9) of base (8).
4. The method for operating a gas permeable brick production line according to claim 3, wherein: the right side fixedly connected with discharging pipe (10) of feed bin (9), the inside of discharging pipe (10) is provided with valve (11), the inside fixedly connected with second weighing platform (12) of factory building (1), the top of second weighing platform (12) is provided with and connects material dolly (13).
5. The method for operating a gas permeable brick production line according to claim 1, wherein: the inside fixed mounting of factory building (1) has vibration platform (14), the top of vibration platform (14) is provided with mould (15), the bottom of blendor (4) and the top looks adaptation of mould (15), the top swing joint of blendor (4) has sealed lid (16), the top threaded connection of storage water tank (501) has screw cap (17).
6. The method for operating a gas permeable brick production line according to claim 1, wherein: the inside of factory building (1) is fixedly connected with kiln (18) and support (19) respectively, the surface of support (19) and the inside looks adaptation of kiln (18), the inside of support (19) is provided with the slide rail, and the inside of slide rail is provided with mould car (20).
7. The method for operating a gas permeable brick production line according to claim 1, wherein: a sliding groove (21) is formed in the bearing top wall (2), a sliding clamping block (22) is connected to the inside of the sliding groove (21) in a sliding clamping mode, and the bottom of the sliding clamping block (22) is fixedly connected with the top of the driving box (306).
CN202210782377.1A 2022-07-05 2022-07-05 Operation method of air brick production line Pending CN115284431A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210782377.1A CN115284431A (en) 2022-07-05 2022-07-05 Operation method of air brick production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210782377.1A CN115284431A (en) 2022-07-05 2022-07-05 Operation method of air brick production line

Publications (1)

Publication Number Publication Date
CN115284431A true CN115284431A (en) 2022-11-04

Family

ID=83821631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210782377.1A Pending CN115284431A (en) 2022-07-05 2022-07-05 Operation method of air brick production line

Country Status (1)

Country Link
CN (1) CN115284431A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH091532A (en) * 1995-06-16 1997-01-07 Misawa Homes Co Ltd Apparatus and method for supplying concrete slurry
CN102555052A (en) * 2012-02-03 2012-07-11 张建兴 Production line for self-insulation building blocks
CN103144187A (en) * 2012-12-31 2013-06-12 泰安昆泰长荣新型建材有限公司 Flat die and stand die combined product line for producing wallboard
CN204748909U (en) * 2015-06-23 2015-11-11 郑州振东科技有限公司 Automatic brickmaking system
CN110605775A (en) * 2019-10-08 2019-12-24 德州天元集团有限责任公司 Intelligent brick making system equipment
CN211389398U (en) * 2019-11-21 2020-09-01 秦皇岛森烁科技发展有限公司 Chain-type assembly wallboard production system
CN212554375U (en) * 2020-06-03 2021-02-19 中冶焦耐(大连)工程技术有限公司 Prefabricated block ingredient mixing, vibration forming, curing and demoulding system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH091532A (en) * 1995-06-16 1997-01-07 Misawa Homes Co Ltd Apparatus and method for supplying concrete slurry
CN102555052A (en) * 2012-02-03 2012-07-11 张建兴 Production line for self-insulation building blocks
CN103144187A (en) * 2012-12-31 2013-06-12 泰安昆泰长荣新型建材有限公司 Flat die and stand die combined product line for producing wallboard
CN204748909U (en) * 2015-06-23 2015-11-11 郑州振东科技有限公司 Automatic brickmaking system
CN110605775A (en) * 2019-10-08 2019-12-24 德州天元集团有限责任公司 Intelligent brick making system equipment
CN211389398U (en) * 2019-11-21 2020-09-01 秦皇岛森烁科技发展有限公司 Chain-type assembly wallboard production system
CN212554375U (en) * 2020-06-03 2021-02-19 中冶焦耐(大连)工程技术有限公司 Prefabricated block ingredient mixing, vibration forming, curing and demoulding system

Similar Documents

Publication Publication Date Title
CN102586643A (en) Semi-continuous production line of closed-cell aluminum foam
CN103252458B (en) Automatic non-die sand mold manufacturing system
CN105672660B (en) A kind of building concrete cast in situs device
CN115284431A (en) Operation method of air brick production line
CN101629403B (en) High and low elastic modulus cement emulsified asphalt mortar general mixing pump pouring vehicle
CN202480230U (en) Foaming concrete inorganic insulation board production line
CN108189211A (en) A kind of light cellular partition board automated production equipment
CN203418639U (en) A production line of inorganic fireproof heat insulation board
CN209453849U (en) A fully automatic concrete plate making machine
CN218659754U (en) Air brick production line
CN205201811U (en) Sand material feed system and mortar robot
CN105971285B (en) A kind of concrete stirring pours device
CN207747211U (en) The material distributing machine of concrete automatic blanking
CN117505814A (en) A low-pressure casting pool-type holding furnace aluminum liquid conveying device and method thereof
CN117532711A (en) A low-cost and environmentally friendly phosphogypsum water-resistant thermal insulation partition board and its manufacturing process
CN203427162U (en) Environment-friendly forming machine with built-in mold core
CN114292063B (en) Lightweight foam concrete and preparation method thereof
CN115847572A (en) Pulse vibration crucible forming equipment
CN205021819U (en) mixing equipment
CN209469015U (en) A pouring device for construction engineering
CN208148117U (en) The automation preparation facilities of ceramic particle reinforced metal base composites precast body
CN115464779A (en) Mixer for block forming production line
CN115319919A (en) Preparation method of heat-preservation foaming cement
CN222099058U (en) Quartz sand ton bag batching equipment
CN221793211U (en) PCCP tube core vertical forming automatic production system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination