CN115262567A - An ultra-narrow full hard rock deep foundation pit excavation method - Google Patents
An ultra-narrow full hard rock deep foundation pit excavation method Download PDFInfo
- Publication number
- CN115262567A CN115262567A CN202210922820.0A CN202210922820A CN115262567A CN 115262567 A CN115262567 A CN 115262567A CN 202210922820 A CN202210922820 A CN 202210922820A CN 115262567 A CN115262567 A CN 115262567A
- Authority
- CN
- China
- Prior art keywords
- excavation
- foundation pit
- stone
- ultra
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F3/00—Dredgers; Soil-shifting machines
- E02F3/04—Dredgers; Soil-shifting machines mechanically-driven
- E02F3/28—Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02F—DREDGING; SOIL-SHIFTING
- E02F7/00—Equipment for conveying or separating excavated material
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Mechanical Engineering (AREA)
- Earth Drilling (AREA)
Abstract
一种超窄全硬岩深基坑开挖方法,在平面上,采用从两端向中间的开挖方式,同时根据基坑长度分成多个施工段落施工;竖向上,随着开挖的深入,在开挖剖面的不同开挖深度形成平台,通过不同平台上的开挖机械配合,实现接力开挖及运渣。该方法有效利用空间效应,平面上在基坑内外部不同位置合理设置机械,竖向上在设置台阶,在不同开挖层合理设置机械,可以实现多台挖机接力开挖、运渣、基坑中部处抓斗装车出渣的快速开挖效果,有效解决了超窄基坑宽度件下设备作业空间不足、小支撑间距无法设置常规马道出渣的施工难题。
An ultra-narrow full-hard rock deep foundation pit excavation method. On the plane, the excavation method is adopted from both ends to the middle, and the construction is divided into multiple construction sections according to the length of the foundation pit; vertically, with the depth of the excavation , Form platforms at different excavation depths of the excavation profile, and realize relay excavation and slag transportation through the cooperation of excavation machinery on different platforms. This method effectively utilizes the space effect. On the plane, the machine is reasonably arranged at different positions inside and outside the foundation pit. On the vertical direction, the steps are arranged, and the machine is reasonably arranged in different excavation layers. The rapid excavation effect of the grab bucket loading and slag removal effectively solves the construction problems of insufficient equipment working space under the ultra-narrow foundation pit width, and the small support spacing cannot be set up for conventional horse road slag removal.
Description
技术领域technical field
本发明属于岩土工程施工领域,具体而言为一种超窄全硬岩深基坑开挖方法。The invention belongs to the field of geotechnical engineering construction, and in particular relates to an ultra-narrow full-hard rock deep foundation pit excavation method.
背景技术Background technique
基坑是指为进行建筑物(包括构筑物)基础与地下室的施工所开挖的地面以下空间。深基坑是指开挖深度超过5米(含5米)或地下室三层以上(含三层),或深度虽未超过5米,但地质条件和周围环境及地下管线特别复杂的工程。硬岩是指颗粒牢固联结、有较高的力学强度的岩石。全硬岩指全断面硬岩,硬岩的抗压强度大于60Mpa。超窄是指基坑的宽度小于等于8米。The foundation pit refers to the space below the ground excavated for the construction of the foundation and basement of buildings (including structures). A deep foundation pit refers to a project where the excavation depth exceeds 5 meters (including 5 meters), or the basement has more than three floors (including three floors), or the depth does not exceed 5 meters, but the geological conditions, surrounding environment and underground pipelines are particularly complicated. Hard rock refers to rocks whose particles are firmly connected and have high mechanical strength. Full hard rock refers to full-section hard rock, and the compressive strength of hard rock is greater than 60Mpa. Ultra-narrow means that the width of the foundation pit is less than or equal to 8 meters.
公开号为CN109594564A的发明专利申请,公开了一种第地铁深基坑明挖防坍塌施工方法,其施工步骤包括:S1:采用井点降水方法,在基坑周边布设降水井,形成降水帷幕,进行基坑周围的降水;S2:旋挖钻钻孔桩,做围护桩;S3:施做冠梁砼支撑;S4:深基坑挖土,架设钢支撑;S5:修理边坡,土钉钻孔,安置土钉,土钉注浆;S6:重复步骤S4~S5直到施工至需求的基坑深度。步骤S4和步骤S5中,采取竖向分层,横向分块,拉槽开挖、留土护壁的方式开挖,及时架设钢支撑,减少基坑无支撑区域及暴露时间。在进行基坑施工时,先在基坑正中位置施工马道,先挖中间土方,基坑两侧保留侧压土,侧压土作为钢支撑的架设平台,待钢支撑架设完成后,再继续向下开挖,如此循环,直至基坑挖至设计的深度。The invention patent application with the publication number CN109594564A discloses a construction method for open excavation and anti-collapse of a deep foundation pit. Dewatering around the foundation pit; S2: Rotary drilling and drilling piles, making enclosure piles; S3: Concrete support for crown beams; S4: Excavating soil for deep foundation pits, erecting steel supports; S5: Repairing slopes, soil nailing Drilling, placing soil nails, and grouting soil nails; S6: Repeat steps S4-S5 until the required depth of the foundation pit is reached. In steps S4 and S5, adopt vertical layering, horizontal block excavation, trench excavation, and soil retaining wall excavation, erect steel supports in time, and reduce the unsupported area and exposure time of the foundation pit. When constructing the foundation pit, first construct the horseway in the center of the foundation pit, dig the earthwork in the middle first, keep the side pressure soil on both sides of the foundation pit, and use the side pressure soil as the erection platform for the steel support. After the steel support is erected, continue to Excavation is repeated in this way until the foundation pit is dug to the designed depth.
超窄基坑作业条件下,常规开挖设备不满足作业空间要求,同时,在施工环境较为复杂的情况下,基坑的内支撑体系多采用加强、加密设计,在狭窄作业宽度及小支撑间距情况下进行基坑施工,这种小支撑间距无法如CN109594564A的发明专利申请中的技术方案那样通过设置常规马道出渣,因此超窄全硬岩深基坑开挖的施工风险、技术复杂性及施工组织难度远大于常规基坑工程。Under ultra-narrow foundation pit operation conditions, conventional excavation equipment does not meet the requirements of the working space. At the same time, in the case of complex construction environments, the internal support system of the foundation pit is mostly designed with reinforcement and encryption. In the case of foundation pit construction, such a small support distance cannot be slag-discharged by setting a conventional horseway like the technical solution in the invention patent application of CN109594564A, so the construction risk, technical complexity and The difficulty of construction organization is much greater than that of conventional foundation pit engineering.
因此,亟待出现一种便捷、安全的超窄全硬岩深基坑开挖方法。Therefore, there is an urgent need for a convenient and safe method for excavating ultra-narrow full hard rock deep foundation pits.
发明内容Contents of the invention
本发明所要解决的技术问题为现有常规基坑开挖方法用于超窄全硬岩深基坑施工时,施工环境复杂,在狭窄作业宽度及小支撑间距情况下,常规开挖设备不满足作业空间要求且无法设置常规马道出渣。The technical problem to be solved by the present invention is that when the existing conventional foundation pit excavation method is used for ultra-narrow full hard rock deep foundation pit construction, the construction environment is complicated, and the conventional excavation equipment does not meet the requirements under the condition of narrow working width and small support spacing. The working space is required and it is impossible to set up conventional slag discharge.
为了弥补常规开挖技术的不足,解决上述技术问题,本发明采用如下技术方案:In order to make up for the deficiencies of conventional excavation techniques and solve the above-mentioned technical problems, the present invention adopts the following technical solutions:
一种超窄全硬岩基坑开挖方法,在平面上,采用从两端向中间的开挖方式,同时可根据基坑长度分成多个施工段落施工;竖向上,随着开挖的深入,在开挖剖面的不同开挖深度形成平台,通过不同平台上的开挖机械配合,实现接力开挖及运渣。An ultra-narrow all-hard rock foundation pit excavation method, on the plane, adopts the excavation method from both ends to the middle, and can be divided into multiple construction sections according to the length of the foundation pit; vertically, with the deepening of the excavation , platforms are formed at different excavation depths in the excavation profile, and through the cooperation of excavation machines on different platforms, relay excavation and slag transportation are realized.
上述超窄全硬岩基坑开挖方法,多个施工段同时施工加快了施工进度;同时,不同开挖深度平台上的开挖机械配合,接力开挖及运渣加快了基坑开挖速度及出渣速度。With the above ultra-narrow all-hard rock foundation pit excavation method, the simultaneous construction of multiple construction sections speeds up the construction progress; at the same time, the cooperation of excavation machinery on platforms with different excavation depths, relay excavation and slag transportation speed up the excavation speed of the foundation pit and slag discharge speed.
根据本发明的超窄全硬岩基坑开挖方法,其包括以下步骤:According to the ultra-narrow full hard rock foundation pit excavation method of the present invention, it comprises the following steps:
步骤S1、施作围护桩、围护冠梁及挡土墙等围护结构,待围护结构强度满足要求后进行基坑开挖;Step S1, building enclosure structures such as enclosure piles, enclosure crown beams and retaining walls, and excavating the foundation pit after the enclosure structure strength meets the requirements;
步骤S2、基坑开挖由两端向中间进行,严格控制坡比,在基坑内及基坑周边不同平面位置布置石方机械,并利用所述石方机械完成石方开挖及转运,随基坑开挖进度及时进行第一道钢支撑架设及边坡支护;Step S2, the excavation of the foundation pit is carried out from both ends to the middle, and the slope ratio is strictly controlled. Stonework machinery is arranged in different plane positions in the foundation pit and around the foundation pit, and the stonework machinery is used to complete the stonework excavation and transfer. The excavation progress of the foundation pit shall be carried out in time for the erection of the first steel support and slope support;
步骤S3、随着开挖的深入在开挖剖面的不同开挖深度上逐层布置开挖机械,并利用所述开挖机械完成基坑的开挖;随基坑开挖进度及时进行第二道钢支撑架设及边坡支护。Step S3, as the excavation deepens, arrange the excavation machinery layer by layer at different excavation depths of the excavation profile, and use the excavation machinery to complete the excavation of the foundation pit; carry out the second excavation in time with the excavation progress of the foundation pit. Daogang support erection and slope support.
根据本发明的上述超窄全硬岩基坑开挖方法,在开挖过程中利用机械在不同平面位置及不同标高的空间立体效应,加快基坑开挖进度及出渣效率。According to the method for excavating an ultra-narrow all-hard rock foundation pit of the present invention, the three-dimensional effect of machinery at different plane positions and different elevations is used during the excavation process to speed up the progress of foundation pit excavation and the efficiency of slag removal.
根据本发明的超窄全硬岩基坑开挖方法,其中,步骤S2中基坑开挖方式为松动爆破配合开挖机械,所述开挖机械包括石方开挖机械,并利用所述开挖机械完成基坑的开挖。According to the ultra-narrow full hard rock foundation pit excavation method of the present invention, wherein, in step S2, the foundation pit excavation method is loose blasting with excavation machinery, and the excavation machinery includes stonework excavation machinery, and the The excavator completes the excavation of the foundation pit.
根据本发明的超窄全硬岩基坑开挖方法,其中,步骤S2中不同平面位置包括基坑范围内、基坑范围外两侧,所述石方机械包括挖掘机、破碎锤、垂直抓斗机、石方运输车。According to the ultra-narrow full hard rock foundation pit excavation method of the present invention, in step S2, the different plane positions include the range of the foundation pit and the two sides outside the range of the foundation pit, and the stonework machinery includes an excavator, a breaker, a vertical grab Bucket machine, stone transport vehicle.
根据本发明的超窄全硬岩基坑开挖方法,其中,步骤S2、步骤S3中钢支撑为Φ609钢支撑,所述边坡支护包括锚杆支护和喷射混凝土支护。According to the method for excavating an ultra-narrow full hard rock foundation pit of the present invention, the steel supports in steps S2 and S3 are Φ609 steel supports, and the slope support includes bolt support and shotcrete support.
根据本发明的超窄全硬岩基坑开挖方法,其中,所述开挖剖面上形成不同标高的平台。包括靠近基坑顶部的顶部平台以及靠近基坑底部的底部平台。According to the method for excavating an ultra-narrow full hard rock foundation pit of the present invention, platforms of different elevations are formed on the excavation section. Includes a top platform near the top of the pit and a bottom platform near the bottom of the pit.
利用布置在顶部平台上的石方机械配合底部平台上的石方机械将底部平台内的石方转运至所述顶部平台上,利用垂直运输机械将所述顶部平台内石方提升至基坑外部,利用石方机械将所述石方运输至指定区域。Use the stonework machinery arranged on the top platform to cooperate with the stonework machinery on the bottom platform to transfer the stonework in the bottom platform to the top platform, and use the vertical transport machinery to lift the stonework in the top platform to the outside of the foundation pit , using the stonework machinery to transport the stonework to the designated area.
利用布置在底部平台上的石方机械把基坑底部石方开挖并与顶部平台上的石方机械配合将基坑底部石方转运至所述顶部平台上。The stonework machinery at the bottom platform is used to excavate the stonework at the bottom of the foundation pit and cooperate with the stonework machinery on the top platform to transfer the stonework at the bottom of the foundation pit to the top platform.
所述不同开挖深度形成平台的数量大于等于3个时,还包括标高位于顶部平台与底部平台之间的中间平台,中间平台可以为一个或标高不同的多个中间平台;利用布置在中间平台上的石方机械把底部平台上的石方转运至所述顶部平台上。When the number of platforms formed by different excavation depths is greater than or equal to 3, it also includes an intermediate platform whose elevation is located between the top platform and the bottom platform, and the intermediate platform can be one or a plurality of intermediate platforms with different elevations; The stonework machinery on the upper platform transfers the stonework on the bottom platform to the top platform.
所述顶部平台、底部平台、中间平台上布置的石方机械包括挖机、破碎锤。The stonework machines arranged on the top platform, bottom platform and middle platform include excavators and breaking hammers.
根据本发明的超窄全硬岩基坑开挖方法,其中,垂直运输机械为垂直抓斗机,所述石方机械包括:挖掘机、石方运输车。According to the method for excavating an ultra-narrow full hard rock foundation pit of the present invention, the vertical transportation machine is a vertical grab machine, and the stonework machinery includes: an excavator and a stonework transport vehicle.
根据本发明的超窄全硬岩深基坑开挖方法,有效利用空间效应,平面上在基坑内外部不同位置合理设置机械,竖向上设置台阶,在不同开挖层合理设置机械,以实现多台挖机接力开挖、运渣、基坑中部处抓斗装车出渣的快速开挖效果,有效解决了超窄基坑宽度件下设备作业空间不足、小支撑间距无法设置常规马道出渣的施工难题。According to the excavation method of the ultra-narrow full hard rock deep foundation pit of the present invention, the space effect is effectively utilized, the machinery is reasonably arranged at different positions inside and outside the foundation pit on the plane, steps are arranged vertically, and the machinery is reasonably arranged at different excavation layers to realize multiple excavations. The rapid excavation effect of table excavator relay excavation, slag transportation, and grab bucket loading and slag discharge in the middle of the foundation pit effectively solves the problem of insufficient working space for equipment under ultra-narrow foundation pit width parts and the inability to set up conventional horseway slag discharge with small support distances construction problems.
附图说明Description of drawings
图1为根据本发明所述的超窄全硬岩深基坑开挖施工方法的工艺流程图;Fig. 1 is the process flow chart of ultra-narrow full hard rock deep foundation pit excavation construction method according to the present invention;
图2为根据本发明所述的超窄全硬岩深基坑开挖施工方法的工况平面分布图;Fig. 2 is the plane distribution diagram of working conditions of the ultra-narrow full hard rock deep foundation pit excavation construction method according to the present invention;
图3为根据本发明所述的超窄全硬岩深基坑开挖施工方法的较佳方案的工况纵断示意图;Fig. 3 is a working condition longitudinal schematic diagram of a preferred scheme of the ultra-narrow full hard rock deep foundation pit excavation construction method according to the present invention;
图4为根据本发明所述的超窄全硬岩深基坑开挖施工方法的较佳方案的工况平面示意图。Fig. 4 is a schematic plan view of working conditions of a preferred solution of the ultra-narrow full hard rock deep foundation pit excavation construction method according to the present invention.
其中,in,
1——第一挖掘机;1 - the first excavator;
2——第二挖掘机;2 - the second excavator;
3——第三挖掘机;3 - the third excavator;
4——第四挖掘机;4 - the fourth excavator;
5——第五挖掘机;5 - the fifth excavator;
6——第六挖掘机;6 - the sixth excavator;
7——第一石方运输车;7——The first stone cube transport vehicle;
8——第二石方运输车;8——the second stone transport vehicle;
9——垂直提升抓斗机;9——Vertical lifting grab machine;
10——钢支撑;10——steel support;
11——第一挖机活动区域;11—the activity area of the first excavator;
12——第二挖机活动区域;12 - the second excavator activity area;
13——第三挖机活动区域;13—the third excavator activity area;
14——第四挖机活动区域;14—the fourth excavator activity area;
15——第五挖机活动区域;15—the fifth excavator activity area;
16——第六挖机活动区域。16—the activity area of the sixth excavator.
具体实施方式Detailed ways
下面结合附图1-4和具体实施例来对本发明做进一步详细的说明。The present invention will be further described in detail below in conjunction with accompanying drawings 1-4 and specific embodiments.
一种超窄全硬岩基坑开挖方法,在平面上,采用从两端向中间的开挖方式,如图2所示,箭头所示方向为开挖方向。可根据基坑长度分成多个施工段落同时施工。如图3、4所示,竖向上,随着开挖的深入,在开挖剖面的不同开挖深度形成平台,通过不同平台上的开挖机械配合,实现接力开挖及运渣。An ultra-narrow all-hard rock foundation pit excavation method adopts the excavation method from both ends to the middle on the plane, as shown in Figure 2, and the direction indicated by the arrow is the excavation direction. According to the length of the foundation pit, it can be divided into multiple construction sections for simultaneous construction. As shown in Figures 3 and 4, vertically, with the deepening of the excavation, platforms are formed at different excavation depths of the excavation section, and through the cooperation of excavation machines on different platforms, relay excavation and slag transportation are realized.
如图1所示,该超窄全硬岩深基坑开挖施工方法主要包括以下步骤:As shown in Figure 1, the ultra-narrow all-hard rock deep foundation pit excavation construction method mainly includes the following steps:
步骤S1:施作围护桩、围护冠梁及挡土墙等围护结构,待围护结构强度满足要求后进行基坑开挖;Step S1: Build enclosure structures such as enclosure piles, enclosure crown beams, and retaining walls, and excavate the foundation pit after the enclosure structure strength meets the requirements;
步骤S2:基坑开挖由两端向中间进行,严格控制坡比,在基坑内及基坑周边不同平面位置布置石方机械,并利用石方机械完成石方开挖及转运,随基坑开挖进度及时进行第一道钢支撑架设及边坡支护;Step S2: The excavation of the foundation pit is carried out from both ends to the middle, and the slope ratio is strictly controlled. Stonework machinery is arranged in different plane positions in the foundation pit and around the foundation pit, and the stonework machinery is used to complete the stonework excavation and transfer. The excavation progress shall be carried out in time for the erection of the first steel support and slope support;
步骤S3:随着开挖的深入在开挖剖面的不同开挖深度上逐层布置开挖机械,并利用开挖机械完成基坑的开挖。随基坑开挖进度及时进行第二道钢支撑架设及边坡支护。Step S3: As the excavation deepens, the excavation machines are arranged layer by layer at different excavation depths of the excavation profile, and the excavation machines are used to complete the excavation of the foundation pit. With the excavation progress of the foundation pit, the second steel support erection and slope support shall be carried out in time.
在步骤S2中,在平面上,如图2所示,采用从两端向中间的开挖方式,同时可根据基坑长度分成多个施工段落加快开挖速度。在基坑开挖过程中,由于基坑宽度超窄,支撑间距小,同断面内仅能容纳一台开挖设备,开挖机械无法正常转身通过回转改变开挖方向,且无法按常规方式设置马道出渣。在此情况下,上述平面内的开挖方式通过合理安排开挖机械数量、位置,且在机械进入基坑内提前规定开挖方向,通过不同开挖方向(前进开挖和倒退开挖)的开挖机械配合实现接力出渣,提高开挖效率。In step S2, on the plane, as shown in Fig. 2, the excavation method is adopted from both ends to the middle, and the excavation speed can be accelerated by dividing the excavation into multiple construction sections according to the length of the foundation pit. During the excavation of the foundation pit, due to the ultra-narrow width of the foundation pit and the small spacing between supports, only one excavation equipment can be accommodated in the same section, and the excavation machine cannot turn around normally to change the excavation direction by turning, and cannot be set up in a conventional way The road is slag. In this case, the above-mentioned excavation method in the plane is based on rationally arranging the number and location of excavation machines, and specifying the excavation direction in advance when the machines enter the foundation pit. Excavation machinery cooperates to realize relay slag discharge and improve excavation efficiency.
在基坑开挖过程步骤S3中,在不同平面位置合理设置石方机械,并利用机械完成石方开挖及转运。在开挖过程中充分利用机械在不同平面位置及不同标高的空间立体效应,加快基坑开挖进度及出渣效率。In step S3 of the foundation pit excavation process, rockwork machinery is reasonably installed at different plane positions, and the stonework excavation and transfer are completed by using the machinery. During the excavation process, the three-dimensional effect of the machine in different plane positions and different elevations is fully utilized to speed up the excavation progress of the foundation pit and the efficiency of slag discharge.
在步骤S3中,竖向上,随着开挖的深入在开挖剖面的不同开挖深度形成平台,供这些石方机械布置。开挖时,位于上层的挖机或破碎锤,在挖掘范围内对本层及下层的台阶进行开挖,待完成下层台阶后再利用该台阶作为平台来布置挖机或破碎锤,开挖过程中利用上下两层平台上的挖机对破碎石渣进行接力转运,并利用垂直运输机械将上层平台内集中堆放的破碎石渣提升至基坑外部,利用石方机械将石方运输至指定区域。按照此方法循环开挖至基坑底部,待基坑开挖完成后利用垂直提升机械将基坑内石方开挖机械提升至基坑外部。In step S3, vertically, as the excavation deepens, platforms are formed at different excavation depths of the excavation profile for the arrangement of these stonework machines. When excavating, the excavator or breaker located on the upper floor excavates the steps of this layer and the lower layer within the excavation range. After the lower steps are completed, the steps are used as a platform to arrange the excavator or breaker. During the excavation process Use the excavators on the upper and lower platforms to carry out relay transfer of crushed gravel, and use vertical transport machinery to lift the concentrated piled crushed gravel on the upper platform to the outside of the foundation pit, and use stonework machinery to transport the stonework to the designated area. Excavate circularly to the bottom of the foundation pit according to this method. After the excavation of the foundation pit is completed, use the vertical lifting machine to lift the stone excavation machine in the foundation pit to the outside of the foundation pit.
以图3为例,对步骤S3进行说明。施工开始阶段,布置4台挖掘机,所述挖掘机为第一挖掘机1、第二挖掘机2、第三挖掘机3、第四挖掘机4,其中第一挖掘机1、第三挖掘机3在基坑内以前进方式开挖靠近基坑顶部的顶部平台范围内的石方,第二挖掘机2、第四挖掘机4在基坑两侧转运石方渣土并配合第一石方运输车7、第二石方运输车8转运渣土;第二施工阶段,当开挖形成下层台阶后,第一挖掘机1、第三挖掘机3进入中间平台,以前进方式开挖下一层石方,当第一、第三挖机活动区域11、13石方开挖完成后,第一、第三挖机1、3停留在第一、第三挖机活动区域11、13内倒运石方至靠近第二、第四挖机活动区域12、14处,第二挖掘机2、第四挖掘机4由基坑外侧进入靠近基坑顶部的顶部平台,并以倒退方式开挖靠近基坑底部的底部平台上的石方,同时利用第一挖掘机1、第三挖掘机3配合第二挖掘机2、第四挖掘机4将底部平台内的石方转运至顶部平台上,在基坑顶部布置第五挖掘机5、第六挖掘机6,所述挖掘机均采用倒退方式开挖靠基坑顶部的顶部平台范围第五、第六挖机活动区域15、16内的石方,同时利用垂直运输机械垂直提升抓斗机9将所述顶部平台内石方提升至基坑外部;第三施工阶段,靠近基坑顶部的顶部平台开挖完成后,所有挖掘机均进入基坑内部,运用上述开挖步骤循环进行剩余基坑石方开挖,开挖过程中所有挖掘机行进方向均不改变,并利用垂直运输机械垂直提升抓斗机9将开挖产生的石方提升至基坑外部,所有石方开挖完成后利用垂直运输机械将挖掘机提升至基坑外部。Step S3 is described by taking FIG. 3 as an example. At the beginning of construction, 4 excavators are arranged, and the excavators are the first excavator 1, the second excavator 2, the third excavator 3, and the fourth excavator 4, wherein the first excavator 1, the third excavator 3 Excavate the stonework within the range of the top platform near the top of the foundation pit in a forward manner, and the second excavator 2 and the fourth excavator 4 transfer the stonework dregs on both sides of the foundation pit and cooperate with the first stonework transportation Vehicle 7 and the second stone transport vehicle 8 transfer the muck; in the second construction stage, when the lower steps are formed during excavation, the first excavator 1 and the third excavator 3 enter the middle platform to excavate the next layer in a forward manner Stonework, after the excavation of the first and third excavator activity areas 11 and 13 is completed, the first and third excavator machines 1 and 3 stay in the first and third excavator activity areas 11 and 13 to unload the stone The second excavator 2 and the fourth excavator 4 enter the top platform near the top of the foundation pit from the outside of the foundation pit, and excavate in a backward manner close to the foundation pit For the stonework on the bottom platform at the bottom, the first excavator 1 and the third excavator 3 cooperate with the second excavator 2 and the fourth excavator 4 to transfer the stonework in the bottom platform to the top platform. The
所述前进方式开挖指开挖方向由基坑两端向基坑中部开挖;所述倒退方式开挖指由基坑中部向基坑两端开挖。The forward excavation refers to excavation from both ends of the foundation pit to the middle of the foundation pit; the backward excavation refers to excavation from the middle of the foundation pit to both ends of the foundation pit.
以图4为例,对步骤S4进行说明。图4为步骤S3中石方机械平面位置变化示意图,分别对应施工开始阶段、第二施工阶段、第三施工阶段,其中开始施工阶段在基坑内部布置第一、第三挖掘机1、3,在基坑外部布置第二、第四挖掘机2、4和第一、二石方运输车7、8,第一、第三挖掘机1、3进行靠近基坑顶部的顶部平台范围内的石方开挖,第二、第四挖掘机2、4对开挖完成的石方进行转运并配合第一、二石方运输车7、8将石方转运至指定地点;第二施工阶段,增加布置第五、第六挖掘机5、6、垂直提升抓斗机9,所有挖掘机均布置在开挖形成的不同标高的顶部平台、底部平台、中间平台上,垂直提升抓斗机9布置在基坑外部,将开挖产生石方垂直提升至基坑外部;第三施工阶段石方开挖机械平面布置同第二施工阶段。Step S4 is described by taking FIG. 4 as an example. Fig. 4 is a schematic diagram of the position change of the stonework machine plane in step S3, corresponding to the construction start stage, the second construction stage, and the third construction stage respectively, wherein the first and
在基坑开挖过程中根据开挖进度及时完成基坑支护施工,保证基坑开挖施工安全。步骤S3中钢支撑10为Φ609钢支撑,边坡支护包括锚杆支护和喷射混凝土支护。During the excavation of the foundation pit, complete the foundation pit support construction in time according to the excavation progress to ensure the safety of the foundation pit excavation construction. In step S3, the
上述超窄全硬岩深基坑开挖方法,有效利用空间效应,平面上在基坑内外部不同位置合理设置机械,竖向上在设置台阶,在不同开挖层合理设置机械,可以实现多台挖机接力开挖、运渣、基坑中部处抓斗装车出渣的快速开挖效果,有效解决了超窄基坑宽度件下设备作业空间不足、小支撑间距无法设置常规马道出渣的施工难题。The above ultra-narrow full hard rock deep foundation pit excavation method effectively utilizes the space effect, rationally arranges machinery at different positions inside and outside the foundation pit on the plane, sets steps vertically, and reasonably arranges machinery at different excavation layers, so that multiple excavations can be realized. The rapid excavation effect of mechanical relay excavation, slag transportation, and slag loading by grab bucket in the middle of the foundation pit effectively solves the problem of insufficient equipment working space under the ultra-narrow foundation pit width, and the construction of conventional horse road slag discharge that cannot be set at a small support distance problem.
上述内容仅为本发明的优选实施方式,并非用于限制本发明。对本领域技术人员而言,本发明可以有各种更改和变化。凡在本发明的精神和原则之内所做的任何修改、等同替换或改进等,均包含在本发明的保护范围之内。The above content is only a preferred embodiment of the present invention, and is not intended to limit the present invention. Various modifications and variations of the present invention will occur to those skilled in the art. Any modifications, equivalent replacements or improvements made within the spirit and principles of the present invention are included within the protection scope of the present invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210922820.0A CN115262567A (en) | 2022-08-02 | 2022-08-02 | An ultra-narrow full hard rock deep foundation pit excavation method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210922820.0A CN115262567A (en) | 2022-08-02 | 2022-08-02 | An ultra-narrow full hard rock deep foundation pit excavation method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115262567A true CN115262567A (en) | 2022-11-01 |
Family
ID=83746947
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210922820.0A Pending CN115262567A (en) | 2022-08-02 | 2022-08-02 | An ultra-narrow full hard rock deep foundation pit excavation method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115262567A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115787768A (en) * | 2022-12-16 | 2023-03-14 | 中建海峡建设发展有限公司 | A method for excavating relatively hard rock in ultra-narrow and ultra-deep foundation pits |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102535474A (en) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | Construction method for deep-foundation pit excavation |
| CN105421463A (en) * | 2015-11-04 | 2016-03-23 | 中建三局集团有限公司 | Longitudinal excavation construction method of long-span dense-support super-long deep foundation pit |
| CN108643198A (en) * | 2018-04-18 | 2018-10-12 | 中国十七冶集团有限公司 | Excavation of earthwork structure and its construction method between a kind of long and narrow foundation pit pile of ultra-deep |
| CN111305218A (en) * | 2018-12-11 | 2020-06-19 | 宏润建设集团股份有限公司 | Construction method for foundation pit excavation |
| WO2022016720A1 (en) * | 2020-07-22 | 2022-01-27 | 深圳市工勘岩土集团有限公司 | Temporary passage construction method employing support structure in deep foundation pit |
-
2022
- 2022-08-02 CN CN202210922820.0A patent/CN115262567A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102535474A (en) * | 2010-12-13 | 2012-07-04 | 五冶集团上海有限公司 | Construction method for deep-foundation pit excavation |
| CN105421463A (en) * | 2015-11-04 | 2016-03-23 | 中建三局集团有限公司 | Longitudinal excavation construction method of long-span dense-support super-long deep foundation pit |
| CN108643198A (en) * | 2018-04-18 | 2018-10-12 | 中国十七冶集团有限公司 | Excavation of earthwork structure and its construction method between a kind of long and narrow foundation pit pile of ultra-deep |
| CN111305218A (en) * | 2018-12-11 | 2020-06-19 | 宏润建设集团股份有限公司 | Construction method for foundation pit excavation |
| WO2022016720A1 (en) * | 2020-07-22 | 2022-01-27 | 深圳市工勘岩土集团有限公司 | Temporary passage construction method employing support structure in deep foundation pit |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115787768A (en) * | 2022-12-16 | 2023-03-14 | 中建海峡建设发展有限公司 | A method for excavating relatively hard rock in ultra-narrow and ultra-deep foundation pits |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7352048B1 (en) | Construction method of large-span station with open wings and semi-top-down excavation and semi-reverse drilling | |
| CN102691300B (en) | Construction method of foundation pit earthwork | |
| US20140215959A1 (en) | Method for forming a retaining wall, and corresponding retaining wall | |
| CN102995659B (en) | Method for constructing from central area to periphery of ultra-large type underground engineering | |
| CN102817372A (en) | Construction method of underground deep foundation concrete by reverse formworks | |
| CN103775110A (en) | Underground excavation construction method for multilayer underground space of soft soil area | |
| CN111101540B (en) | A construction method for an open-cut tunnel passing through an existing power tunnel | |
| CN114232602A (en) | Underground continuous pile construction process | |
| CN118273366A (en) | Construction process for construction of locking steel pipe pile cofferdam on abrupt slope hard rock riverbed | |
| CN115262567A (en) | An ultra-narrow full hard rock deep foundation pit excavation method | |
| CN115506382A (en) | Construction method for pile plate wall of island building platform | |
| CN115125960A (en) | Common foundation pit excavation method for adjacent foundation pits with different bottom elevations | |
| CN111636726B (en) | A double-layer raw material yard structure for construction on a deep soft soil foundation and its construction method | |
| CN112627199A (en) | Construction method for foundation pit support of cyclone well | |
| CN111173523A (en) | Method for constructing underground box culvert by using open type shield tunneling machine | |
| CN100593052C (en) | Open cut foundation pit supporting and protecting method | |
| CN113669084B (en) | Lake facies deposition weak stratum subway tunnel-first and station-last segment dismantling method | |
| CN114737974A (en) | Construction method for receiving hard rock in rectangular pipe jacking | |
| CN109611114B (en) | An underground space excavation method for an existing tunnel lying under a soil-rock composite stratum | |
| CN115125962A (en) | Construction method of river-crossing foundation pit support | |
| CN217150172U (en) | Underground continuous wall system used under weak geological conditions of sea reclamation area | |
| TWI853491B (en) | Anti-collapse continuous wall construction method for special geological layers | |
| CN115434710B (en) | Tunnel tunneling method for shallow karst cave, middle shallow karst cave and middle deep karst cave region | |
| CN217974507U (en) | Protection system of subway tunnel structure crouches down during soft soil foundation ditch excavation | |
| CN209163806U (en) | A kind of big cross section rectangular top pipe construction received well foundation reinforcing structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20221101 |
