A segmented armor joint device and construction method thereof Download PDF

Info

Publication number
CN115110714A
CN115110714A CN202210900966.5A CN202210900966A CN115110714A CN 115110714 A CN115110714 A CN 115110714A CN 202210900966 A CN202210900966 A CN 202210900966A CN 115110714 A CN115110714 A CN 115110714A
Authority
CN
China
Prior art keywords
plug
groove rail
rail part
segmented
seam device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210900966.5A
Other languages
Chinese (zh)
Inventor
胡成鑫
林腾
张�杰
李瑶
苏泽强
靳源源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CSCEC Strait Construction and Development Co Ltd
Original Assignee
CSCEC Strait Construction and Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CSCEC Strait Construction and Development Co Ltd filed Critical CSCEC Strait Construction and Development Co Ltd
Priority to CN202210900966.5A priority Critical patent/CN115110714A/en
Publication of CN115110714A publication Critical patent/CN115110714A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • E04F15/14Construction of joints, e.g. dividing strips
    • E04F15/142Dividing strips or boundary strips
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/20Implements for finishing work on buildings for laying flooring
    • E04F21/24Implements for finishing work on buildings for laying flooring of masses made in situ, e.g. smoothing tools

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to a sectional type armor seam device and a construction method thereof in the technical field of building construction, wherein the device comprises a grooved rail part and an insert part inserted on the grooved rail part, and the lower end of the insert part is inserted into the grooved rail part and is locked by a plurality of first bolts; the groove rail part includes horizontal bottom plate, and the fixed groove rail that is provided with in the middle of the horizontal bottom plate top, plug-in components part include the font picture peg that two block symmetries in the left and right sides set up, and two font picture pegs lean on the setting dorsad and pass through the second bolt lock solid, can effectively reduce the corrosion hidden danger, need not the on-the-spot welding installation, reduce manpower and materials and drop into to guarantee terrace construction joint department concrete and steel sheet anchoring's the continuity of guaranteeing terrace construction joint department concrete and armor seam in succession and effectively anchoring.

Description

一种分段式铠甲缝装置及其施工方法A segmented armor joint device and construction method thereof

技术领域technical field

本发明涉及一种分段式铠甲缝装置及其施工方法,属于建筑施工的技术领域。The invention relates to a segmented armor joint device and a construction method thereof, belonging to the technical field of building construction.

背景技术Background technique

现代新式物流仓储及工业厂房大部分实现了机械设备自动化,机械设备精密程度提高,如果地坪的平整度不够,从而使地坪在使用过程中带来较多的不便。为保证设备的正常使用,对地坪的平整度要求也不断提高,并要求地面地坪均需一次性成型,因此加大了施工难度。混凝土地坪在满足承载力要求下,用户对地坪的整体平整度、裂缝控制、美观及后期维护等方面均提出要求。Most of the modern new logistics warehouses and industrial plants have realized the automation of machinery and equipment, and the precision of machinery and equipment has been improved. If the flatness of the floor is not enough, it will bring more inconvenience to the use of the floor. In order to ensure the normal use of the equipment, the requirements for the flatness of the floor are also continuously improved, and the floor and floor are required to be formed at one time, thus increasing the difficulty of construction. Under the condition that the concrete floor meets the bearing capacity requirements, the user puts forward requirements for the overall flatness, crack control, aesthetics and post-maintenance of the floor.

普通混凝土地坪每隔4~6米设置切割缝,目前市面上铠甲缝大多采用普通钢板,容易生锈且影响使用;且使用时大多需要在现场进行焊接安装,导致安装不便(如专利申请号为CN201921114192.3的中国实用新型专利公开了一种铠甲缝装置);此外现有的铠甲缝装置由于中间缝隙未完全消除,不能保证地坪施工缝处混凝土和钢板锚固的连续性。Ordinary concrete floors are set with cutting seams every 4 to 6 meters. At present, most of the armor seams on the market are made of ordinary steel plates, which are easy to rust and affect the use; and most of them need to be welded and installed on site, resulting in inconvenient installation (such as patent application No. An armor joint device is disclosed for the Chinese utility model patent of CN201921114192.3); in addition, the existing armor joint device cannot guarantee the continuity of the anchorage of concrete and steel plate at the construction joint of the floor because the intermediate gap is not completely eliminated.

发明内容SUMMARY OF THE INVENTION

为了解决现有技术所存在的上述问题,本发明提供了一种分段式铠甲缝装置及其施工方法。In order to solve the above problems existing in the prior art, the present invention provides a segmented armor seam device and a construction method thereof.

本发明的技术方案如下:The technical scheme of the present invention is as follows:

一种分段式铠甲缝装置及其施工方法,包括槽轨部分以及插置于所述槽轨部分上的插件部分,所述插件部分下端插入所述槽轨部分并通过若干第一螺栓锁固;A segmented armor seam device and a construction method thereof, comprising a slot rail part and an insert part inserted on the slot rail part, the lower end of the insert part is inserted into the slot rail part and locked by a plurality of first bolts ;

所述槽轨部分包括水平底板,所述水平底板顶部中间固定设置有槽轨,所述槽轨与水平底板相互垂直形成T形结构;The groove rail part includes a horizontal bottom plate, a groove rail is fixedly arranged in the middle of the top of the horizontal bottom plate, and the groove rail and the horizontal bottom plate are perpendicular to each other to form a T-shaped structure;

所述插件部分包括左右两块对称设置的字形插板,两块所述字形插板背向并靠设置并通过第二螺栓锁固。The plug-in part includes two symmetrically arranged glyph inserts on the left and right, and the two glyph inserts are arranged opposite to each other and are locked by second bolts.

其中,所述水平底板的两侧翼向下弯折形成第一嵌埋翼缘。Wherein, the two side wings of the horizontal bottom plate are bent downward to form a first embedded flange.

其中,两块所述字形插板之间留置有缝隙,所述缝隙下方垫设有弹性垫衬片,所述缝隙上灌注有填缝胶。Wherein, a gap is left between the two zigzag inserts, an elastic pad is placed under the gap, and a gap filling glue is poured on the gap.

其中,所述字形插板的外侧壁中部水平连接有传力板,所述传力板外侧设置有塑料保护套。Wherein, a force transmission plate is horizontally connected to the middle part of the outer side wall of the character-shaped insert plate, and a plastic protective cover is arranged on the outer side of the force transmission plate.

其中,所述字形插板的顶部水平段外端向下弯折形成第二嵌埋翼缘。Wherein, the outer end of the top horizontal section of the character-shaped insert plate is bent downward to form a second embedded flange.

其中,所述第二嵌埋翼缘上并排阵列开设有镂空口。Wherein, hollow openings are arranged in a side-by-side array on the second embedded flange.

其中,所述插件部分的下端横向开设有用于安装各个所述第一螺栓的安装长槽。Wherein, the lower end of the plug-in part is provided with a long installation slot for installing each of the first bolts.

其中,所述槽轨部分以及插件部分均采用镀锌钢板制成。Wherein, the groove rail part and the plug-in part are made of galvanized steel plate.

一种分段式铠甲缝装置的施工方法,包括以下施工步骤:A construction method for a segmented armor joint device, comprising the following construction steps:

步骤1、将槽轨部分预埋固定于基层混凝土中;Step 1. Pre-embed and fix the groove rail part in the base concrete;

步骤2、将插件部分对应插置于槽轨部分上;Step 2. Insert the plug-in part on the groove rail part correspondingly;

步骤3、通过若干第一螺栓对槽轨部分和插件部分进行锁固;Step 3. Lock the groove rail part and the plug-in part by several first bolts;

步骤4、在插件部分上进行地坪混凝土浇筑即可。Step 4. Just pour the floor concrete on the plug-in part.

本发明具有如下有益效果:The present invention has the following beneficial effects:

本发明分段式铠甲缝装置及其施工方法,槽轨部分以及插件部分均采用镀锌钢板制成,镀锌层在钢板表面形成保层,起到隔绝空气和水分的作用,可有效降低锈蚀隐患。The segmented armor joint device and its construction method of the present invention, the groove rail part and the plug-in part are made of galvanized steel plate, the galvanized layer forms a protective layer on the surface of the steel plate, plays the role of isolating air and moisture, and can effectively reduce corrosion hidden danger.

本发明分段式铠甲缝装置及其施工方法,同时采用分段式铠甲缝,包括独立的槽轨部分上的插件部分,施工安装时插件部分下端插入槽轨部分并通过若干第一螺栓锁固,无需现场焊接安装,减少人力物力投入。The segmented armor seam device and its construction method of the present invention also adopts the segmented armor seam, which includes a plug-in part on an independent groove rail part. During construction and installation, the lower end of the plug-in part is inserted into the groove rail part and locked by a plurality of first bolts. , No need for on-site welding and installation, reducing manpower and material resources.

本发明分段式铠甲缝装置及其施工方法,在构成插件部分的两块字形插板之间留置有缝隙,缝隙下方垫设有弹性垫衬片,缝隙上灌注有填缝胶,以确保两块字形插板之间完全密合,保证接缝的紧密性,从而保证地坪施工缝处混凝土和钢板锚固的连续保证地坪施工缝处混凝土与铠甲缝有效锚固的连续性。The segmented armor seam device and its construction method of the present invention have a gap left between the two character-shaped insert plates constituting the plug-in part, an elastic gasket is placed under the gap, and a gap filling glue is poured on the gap to ensure the two The block-shaped inserts are completely sealed to ensure the tightness of the joints, thereby ensuring the continuity of the concrete and steel plate anchoring at the floor construction joints and ensuring the continuity of the effective anchoring of the concrete and armor joints at the floor construction joints.

附图说明Description of drawings

图1为本发明一种分段式铠甲缝装置及其施工方法的立体结构示意图;Fig. 1 is a three-dimensional schematic diagram of a segmented armor joint device and a construction method thereof of the present invention;

图2为本发明一种分段式铠甲缝装置及其施工方法侧向结构示意图;Fig. 2 is a kind of side structure schematic diagram of a segmented armor joint device and a construction method thereof of the present invention;

图3为本发明一种分段式铠甲缝装置及其施工方法实际施工步骤一示意图;Fig. 3 is a schematic diagram of the actual construction step one of a segmented armor joint device and its construction method according to the present invention;

图4为本发明一种分段式铠甲缝装置及其施工方法实际施工步骤二示意图;Fig. 4 is a schematic diagram of the actual construction step 2 of a segmented armor joint device and a construction method thereof according to the present invention;

图5为本发明一种分段式铠甲缝装置及其施工方法实际施工步骤三示意图;5 is a schematic diagram of the actual construction step three of a segmented armor joint device and a construction method thereof according to the present invention;

图6为本发明一种分段式铠甲缝装置及其施工方法实际施工步骤四示意图。FIG. 6 is a schematic diagram of the fourth actual construction step of a segmented armor joint device and its construction method according to the present invention.

图中附图标记表示为:The reference numbers in the figure are indicated as:

1-槽轨部分、101-水平底板、102-槽轨、103-第一嵌埋翼缘、2-插件部分、201-7字形插板、202-弹性垫衬片、203-填缝胶、204-传力板、205-塑料保护套、206-第二嵌埋翼缘、207-镂空口、208-安装长槽、3-第一螺栓、4-第二螺栓。1-slot rail part, 101-horizontal bottom plate, 102-slot rail, 103-first embedded flange, 2-insertion part, 201-7-shaped insert plate, 202-elastic gasket, 203-gap filler, 204-force transmission plate, 205-plastic protective cover, 206-second embedded flange, 207-hollow opening, 208-installation slot, 3-first bolt, 4-second bolt.

具体实施方式Detailed ways

下面结合附图和具体实施例来对本发明进行详细的说明。The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.

参见图1-2,一种分段式铠甲缝装置及其施工方法,它包括槽轨部分1以及插置于槽轨部分1上的插件部分2,插件部分2下端插入槽轨部分1并通过若干第一螺栓3锁固,采用分段式铠甲缝,无需现场焊接安装,减少人力物力投入,保证地坪施工缝处混凝土于铠甲缝有效锚固的连续性,本发明结构简单,方便实用且安装快捷;Referring to Figure 1-2, a segmented armor joint device and its construction method include a slot rail part 1 and an insert part 2 inserted on the slot rail part 1, the lower end of the insert part 2 is inserted into the slot rail part 1 and passes through Several first bolts 3 are locked, and segmented armor joints are used, which does not require on-site welding and installation, reduces manpower and material investment, and ensures the continuity of effective anchoring between concrete and armor joints at floor construction joints. The invention has a simple structure, is convenient and practical, and can be installed fast;

槽轨部分1以及插件部分2均采用镀锌钢板制成,镀锌层在钢板表面形成保层,起到隔绝空气和水分的作用,可有效降低锈蚀隐患;The groove rail part 1 and the plug-in part 2 are made of galvanized steel plate, and the galvanized layer forms a protective layer on the surface of the steel plate, which plays the role of isolating air and moisture, which can effectively reduce the hidden danger of corrosion;

槽轨部分1包括水平底板101,水平底板101顶部中间固定设置有槽轨102,槽轨102由两块平行设置的钢板构成,槽轨102与水平底板101相互垂直形成T形结构,中间留置与插件部分2下端厚度匹配的插槽;The groove rail part 1 includes a horizontal bottom plate 101, and a groove rail 102 is fixed in the middle of the top of the horizontal bottom plate 101. The groove rail 102 is composed of two parallel steel plates. The groove rail 102 and the horizontal bottom plate 101 are perpendicular to each other to form a T-shaped structure. A slot with matching thickness at the lower end of the plug-in part 2;

水平底板101的两侧翼向下弯折形成第一嵌埋翼缘103,第一嵌埋翼缘103一方面可起到加强结构抗弯矩变形的作用,另一方面可作为锚固结构在浇筑基层混凝土时嵌入混凝土中进行固定;The two sides of the horizontal base plate 101 are bent downward to form the first embedded flanges 103. On the one hand, the first embedded flanges 103 can play a role in strengthening the structure against bending moment deformation, and on the other hand, it can be used as an anchoring structure in the pouring base. When the concrete is embedded in the concrete, it is fixed;

插件部分2包括左右两块对称设置的7字形插板201,插件部分2的下端横向开设有用于安装各个第一螺栓3的安装长槽208,两块7字形插板201背向并靠设置并通过第二螺栓4锁固,插件部分2插入槽轨部分1并装上第一螺栓3完全紧固前,鉴于安装长槽208的横向连通特点,可横向移动调整插件部分2的位置,在进行第一螺栓3完全紧固,安装长槽208起到安装时的可微调作用;The plug-in part 2 includes two symmetrically arranged 7-shaped plug-in boards 201 on the left and right. The lower end of the plug-in part 2 is provided with a long installation slot 208 for installing each first bolt 3. Locked by the second bolt 4, the plug-in part 2 is inserted into the groove rail part 1 and the first bolt 3 is installed before it is completely tightened, in view of the lateral communication characteristics of the installation long groove 208, the position of the plug-in part 2 can be adjusted by lateral movement. The first bolt 3 is completely tightened, and the installation long groove 208 can be used for fine adjustment during installation;

两块7字形插板201之间留置有缝隙,缝隙下方垫设有弹性垫衬片202,弹性垫衬片202可采用如泡沫板等材料,缝隙上灌注有填缝胶203,两块7字形插板201贴附安装时,现在贴合面之间垫入弹性垫衬片202,初步确定缝隙以便于留置缝隙注胶,接着锁固第二螺栓4夹紧,最后在缝隙上方灌注填缝胶203,以确保两块7字形插板201之间完全密合,保证接缝的紧密性,从而保证地坪施工缝处混凝土和钢板锚固的连续;A gap is left between the two 7-shaped inserts 201, and an elastic pad 202 is placed under the gap. When the plug board 201 is attached and installed, the elastic pad 202 is now placed between the bonding surfaces, and the gap is preliminarily determined to facilitate the indwelling gap injection, then the second bolt 4 is locked and clamped, and finally the gap is filled with caulking glue 203, to ensure complete closeness between the two 7-shaped inserts 201, to ensure the tightness of the joints, so as to ensure the continuity of the anchorage of concrete and steel plates at the construction joints of the floor;

7字形插板201的外侧壁中部水平连接有传力板204,地坪混凝土浇筑后,传力板204外端嵌在地坪混凝土浇筑层中,由于两侧7字形插板201相对固定,因此可通过传力板204的传力作用,保证后期两侧地坪混凝土同步沉降,传力板204外侧设置有塑料保护套205,可增加传力面积、增大传力板204与混凝土接触的面积;A power transmission plate 204 is horizontally connected to the middle of the outer side wall of the 7-shaped plug board 201. After the floor concrete is poured, the outer end of the force transmission board 204 is embedded in the floor concrete pouring layer. The force transmission effect of the force transmission plate 204 can ensure the synchronous settlement of the floor concrete on both sides in the later stage. The outer side of the force transmission plate 204 is provided with a plastic protective cover 205, which can increase the force transmission area and increase the contact area between the force transmission plate 204 and the concrete. ;

7字形插板201的顶部水平段外端向下弯折形成第二嵌埋翼缘206,第二嵌埋翼缘206主要作为锚固结构在浇筑基层混凝土时嵌入混凝土中进行固定;进一步的,第二嵌埋翼缘206上并排阵列开设有镂空口207,在地坪混凝土浇筑后,完全填充镂空口207,能够进一步提升第二嵌埋翼缘206与地坪混凝土之间的连结性,进而保证锚固稳固性。The outer end of the top horizontal section of the 7-shaped plug board 201 is bent downward to form a second embedded flange 206, and the second embedded flange 206 is mainly used as an anchoring structure to be embedded in the concrete when pouring the base concrete for fixing; further, the first Hollow holes 207 are arranged side by side on the second embedded flange 206. After the floor concrete is poured, the hollow holes 207 are completely filled, which can further improve the connection between the second embedded flange 206 and the floor concrete, thereby ensuring Anchoring stability.

本发明的工作原理:The working principle of the present invention:

市面上现有铠甲缝装置在地坪混凝土浇筑前按照设计位置施工缝布置铠甲缝,同时调整铠甲缝顶标高与地坪标高一致,并通过焊接锚固钢筋将铠甲缝与基层之间进行固定,随后进行地坪混凝土浇筑。The existing armor seam device on the market arranges the armor seam according to the design position of the construction seam before the floor concrete is poured. At the same time, the top elevation of the armor seam is adjusted to be consistent with the floor elevation, and the armor seam and the base layer are fixed by welding anchoring steel bars. Perform floor concrete pouring.

为克服现有技术对上述工序的不足,本发明采用分段式铠甲缝装置及其施工方法,的材质上采用两块镀锌的7字形插板201,通过第二螺栓4连接,在两块7字形插板201之间形成有夹缝,在夹缝的下部填装有弹性垫衬片202,在夹缝的上部设有填缝胶203,从此创新材质杜绝后期铠甲缝锈蚀风险,同时基层混凝土浇筑过程中预埋槽轨部分1,后续地坪混凝土浇筑前仅需要手工将插件部分2与槽轨部分1进行插接并通过若干第一螺栓3锁固,无需焊接及锚固钢筋固定,缩短工期,降低人力物力的消耗,同时该方案有效解决铠甲缝的定位、标高及固定问题,方便快捷便于施工。In order to overcome the deficiencies of the prior art for the above-mentioned procedures, the present invention adopts a segmented armor seam device and a construction method thereof. The material adopts two galvanized 7-shaped inserts 201, which are connected by the second bolt 4, and the two A gap is formed between the 7-shaped insert plates 201, the lower part of the gap is filled with an elastic pad 202, and the upper part of the gap is provided with a gap filler 203. From then on, the innovative material can eliminate the risk of corrosion of the armor gap in the later stage, and at the same time, the base concrete pouring process The groove rail part 1 is embedded in the middle. Before the subsequent floor concrete is poured, the plug-in part 2 and the groove rail part 1 only need to be manually inserted and locked by a number of first bolts 3. No welding and anchoring steel bars are required, which shortens the construction period and reduces the At the same time, the solution effectively solves the positioning, elevation and fixing problems of the armor seam, which is convenient, fast and convenient for construction.

实施步骤如图3-6所示,首先,放线定位确定铠甲缝位置,在基层混凝土上预埋槽轨部分1,安装示意如附图3所示;The implementation steps are shown in Figure 3-6. First, the position of the armor seam is determined by the positioning of the line, and the groove rail part 1 is embedded in the base concrete. The installation schematic is shown in Figure 3;

浇筑基层混凝土,待地坪混凝土施工前,将本装置插件部分2插入槽轨部分1,安装示意如附图4所示;When pouring the base concrete, before the construction of the floor concrete, insert the plug-in part 2 of the device into the groove rail part 1, and the installation schematic is shown in Figure 4;

随后通过若干第一螺栓3进行装置固定,可以保证地坪施工缝处混凝土和钢板锚固的连续性,安装示意如附图5所示;Subsequently, the device is fixed by several first bolts 3, which can ensure the continuity of the anchorage of the concrete and the steel plate at the construction joint of the floor. The installation schematic is shown in Figure 5;

最后,在插件部分2上进行地坪混凝土浇筑,安装示意如附图6所示。Finally, the floor concrete is poured on the plug-in part 2, and the installation schematic is shown in FIG. 6 .

以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。The above descriptions are only the embodiments of the present invention, and are not intended to limit the scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the description and drawings of the present invention, or directly or indirectly applied to other related technologies Fields are similarly included in the scope of patent protection of the present invention.

Claims (10)

1.一种分段式铠甲缝装置,其特征在于:包括槽轨部分(1)以及插置于所述槽轨部分(1)上的插件部分(2),所述插件部分(2)下端插入所述槽轨部分(1)并通过若干第一螺栓(3)锁固;1. A segmented armor seam device, characterized in that: it comprises a groove rail part (1) and a plug-in part (2) inserted on the groove rail part (1), the lower end of the plug-in part (2) Inserted into the groove rail part (1) and locked by several first bolts (3); 所述槽轨部分(1)包括水平底板(101),所述水平底板(101)顶部中间固定设置有槽轨(102),所述槽轨(102)与水平底板(101)相互垂直形成T形结构;The groove rail part (1) comprises a horizontal bottom plate (101), a groove rail (102) is fixedly arranged in the middle of the top of the horizontal bottom plate (101), and the groove rail (102) and the horizontal bottom plate (101) are perpendicular to each other to form a T shape structure; 所述插件部分(2)包括左右两块对称设置的7字形插板(201),两块所述7字形插板(201)背向并靠设置并通过第二螺栓(4)锁固。The plug-in part (2) includes two left and right 7-shaped plug-in boards (201) symmetrically arranged, and the two 7-shaped plug-in boards (201) are arranged opposite to each other and are locked by second bolts (4). 2.如权利要求1所述的一种分段式铠甲缝装置,其特征在于:所述水平底板(101)的两侧翼向下弯折形成第一嵌埋翼缘(103)。2 . The segmented armor seam device according to claim 1 , wherein the two side wings of the horizontal bottom plate ( 101 ) are bent downward to form a first embedded flange ( 103 ). 3 . 3.如权利要求1所述的一种分段式铠甲缝装置,其特征在于:两块所述7字形插板(201)之间留置有缝隙,所述缝隙下方垫设有弹性垫衬片(202),所述缝隙上灌注有填缝胶(203)。3. A segmented armor seam device according to claim 1, characterized in that: a gap is left between the two 7-shaped insert plates (201), and an elastic pad is provided under the gap. (202), the gap is filled with a caulking glue (203). 4.如权利要求1所述的一种分段式铠甲缝装置,其特征在于:所述7字形插板(201)的外侧壁中部水平连接有传力板(204)。4. The segmented armor seam device according to claim 1, characterized in that: a force transmission plate (204) is horizontally connected to the middle of the outer side wall of the 7-shaped insert plate (201). 5.如权利要求4所述的一种分段式铠甲缝装置,其特征在于:所述传力板(204)外侧设置有塑料保护套(205)。5 . The segmented armor seam device according to claim 4 , wherein a plastic protective cover ( 205 ) is provided on the outer side of the force transmission plate ( 204 ). 6 . 6.如权利要求1所述的一种分段式铠甲缝装置,其特征在于:所述7字形插板(201)的顶部水平段外端向下弯折形成第二嵌埋翼缘(206)。6. A segmented armor seam device according to claim 1, characterized in that: the outer end of the top horizontal section of the 7-shaped insert plate (201) is bent downward to form a second embedded flange (206) ). 7.如权利要求6所述的一种分段式铠甲缝装置,其特征在于:所述第二嵌埋翼缘(206)上并排阵列开设有镂空口(207)。7 . The segmented armor seam device according to claim 6 , wherein the second embedded flanges ( 206 ) are provided with hollow openings ( 207 ) in a side-by-side array. 8 . 8.如权利要求1所述的一种分段式铠甲缝装置,其特征在于:所述插件部分(2)的下端横向开设有用于安装各个所述第一螺栓(3)的安装长槽(208)。8. A segmented armor seam device according to claim 1, characterized in that: the lower end of the plug-in part (2) is laterally provided with a long installation slot (for installing each of the first bolts (3) 208). 9.如权利要求1所述的一种分段式铠甲缝装置,其特征在于:所述槽轨部分(1)以及插件部分(2)均采用镀锌钢板制成。9 . The segmented armor seam device according to claim 1 , wherein the groove rail part ( 1 ) and the insert part ( 2 ) are made of galvanized steel sheet. 10 . 10.一种分段式铠甲缝装置的施工方法,其特征在于,包括以下施工步骤:10. A construction method of a segmented armor joint device, characterized in that, comprising the following construction steps: 步骤1、将槽轨部分(1)预埋固定于基层混凝土中;Step 1. Pre-embed and fix the groove rail part (1) in the base concrete; 步骤2、将插件部分(2)对应插置于槽轨部分(1)上;Step 2. Insert the plug-in part (2) on the groove rail part (1) correspondingly; 步骤3、通过若干第一螺栓(3)对槽轨部分(1)和插件部分(2)进行锁固;Step 3. Lock the groove rail part (1) and the plug-in part (2) by several first bolts (3); 步骤4、在插件部分(2)上进行地坪混凝土浇筑即可。Step 4. The floor concrete can be poured on the plug-in part (2).
CN202210900966.5A 2022-07-28 2022-07-28 A segmented armor joint device and construction method thereof Pending CN115110714A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210900966.5A CN115110714A (en) 2022-07-28 2022-07-28 A segmented armor joint device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210900966.5A CN115110714A (en) 2022-07-28 2022-07-28 A segmented armor joint device and construction method thereof

Publications (1)

Publication Number Publication Date
CN115110714A true CN115110714A (en) 2022-09-27

Family

ID=83334945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210900966.5A Pending CN115110714A (en) 2022-07-28 2022-07-28 A segmented armor joint device and construction method thereof

Country Status (1)

Country Link
CN (1) CN115110714A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR970009879U (en) * 1995-08-31 1997-03-29 이남승 Fixing device for elastic joints for concrete slabs
KR101458961B1 (en) * 2014-04-09 2014-11-07 (주)나우종합건축사사무소 Hypocaust type laminate floor structure of the building
CN108049540A (en) * 2017-11-30 2018-05-18 中建六局第三建筑工程有限公司 More super flat anticracking one-pass molding load bearing heat preserving floor construction engineering methods in temperature control cold chain storehouse
CN213681550U (en) * 2020-09-19 2021-07-13 北京九洋建设工程有限公司 Waterproof expansion joint structure
CN215564229U (en) * 2021-07-13 2022-01-18 芜湖建中建设有限公司 Cleaning device for armor seam
CN217871594U (en) * 2022-07-28 2022-11-22 中建海峡建设发展有限公司 Sectional type armor seam device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR970009879U (en) * 1995-08-31 1997-03-29 이남승 Fixing device for elastic joints for concrete slabs
KR101458961B1 (en) * 2014-04-09 2014-11-07 (주)나우종합건축사사무소 Hypocaust type laminate floor structure of the building
CN108049540A (en) * 2017-11-30 2018-05-18 中建六局第三建筑工程有限公司 More super flat anticracking one-pass molding load bearing heat preserving floor construction engineering methods in temperature control cold chain storehouse
CN213681550U (en) * 2020-09-19 2021-07-13 北京九洋建设工程有限公司 Waterproof expansion joint structure
CN215564229U (en) * 2021-07-13 2022-01-18 芜湖建中建设有限公司 Cleaning device for armor seam
CN217871594U (en) * 2022-07-28 2022-11-22 中建海峡建设发展有限公司 Sectional type armor seam device

Similar Documents

Publication Publication Date Title
CN109853800B (en) Assembled low-energy-consumption curtain wall system and construction method thereof
CN108797847B (en) Assembled steel frame infilled wall structure system and construction method thereof
CN109322425A (en) An external hanging connection system of a composite wall panel and a manufacturing method thereof
CN113482208B (en) Dry-wet combined connecting structure of precast concrete floor slab and construction method
CN206174206U (en) Embedded outer wall suitable for steel house room
EP3981932A1 (en) Floor frame
CN208934190U (en) A prefabricated steel frame infill wall structural system
CN105275089A (en) Fully-prefabricated cold-formed steel house modular unit and assembly connection method
CN111395682A (en) Installation structure and construction method of rock wool thermal insulation integrated board for outer wall of high-rise residential buildings
CN223088896U (en) Bottom casting formwork at the joint of prefabricated building composite panels
CN115110714A (en) A segmented armor joint device and construction method thereof
CN215210624U (en) Assembled culvert
CN111438800B (en) A kind of prefabricated formwork system of fence board on expressway and its construction method
CN217871594U (en) Sectional type armor seam device
CN211201169U (en) Prefabricated assembled window that wafts
CN211817040U (en) Slurry leakage prevention structure at splicing part of assembled laminated slab
CN209293247U (en) Out-of-plane connection node between cross-story cladding and floor slab
CN210263417U (en) Structure of bearing node is connected with girder steel to translation formula precast concrete externally-hung wallboard
CN217634268U (en) Vertical fixing device of concrete pump pipe
CN102877580B (en) Back fastening locking type close seam mounting stone curtain wall dry hanging structure
CN216665082U (en) Leveling device for prefabricated floor slab
CN205917862U (en) Connected node on basis
CN210002249U (en) Combined stone railing
CN211662293U (en) Prefabricated template system of fence board on highway
CN109184054B (en) Out-of-plane connection node between cross-layer external hanging board and floor slab and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination