CN115110435A - Construction method of orthotropic combined bridge deck - Google Patents

Construction method of orthotropic combined bridge deck Download PDF

Info

Publication number
CN115110435A
CN115110435A CN202210940720.0A CN202210940720A CN115110435A CN 115110435 A CN115110435 A CN 115110435A CN 202210940720 A CN202210940720 A CN 202210940720A CN 115110435 A CN115110435 A CN 115110435A
Authority
CN
China
Prior art keywords
steel
concrete
bridge deck
prefabricated
steel cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210940720.0A
Other languages
Chinese (zh)
Other versions
CN115110435B (en
Inventor
魏建东
黄毅
吴清波
陈宇飞
张天航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou University
Original Assignee
Zhengzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou University filed Critical Zhengzhou University
Priority to CN202210940720.0A priority Critical patent/CN115110435B/en
Publication of CN115110435A publication Critical patent/CN115110435A/en
Application granted granted Critical
Publication of CN115110435B publication Critical patent/CN115110435B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种正交异性组合桥面板的施工方法,属于桥梁结构技术领域。该桥面板包括U形纵肋、横肋、钢盖板、混凝土板,钢盖板上表面焊接有支撑件,支撑件上连接抗剪连接件,抗剪连接件埋入混凝土内。支撑件间有空腔。本发明用工字钢弯制出带U形纵肋的小钢箱,小钢箱横向焊接组成桥面结构的主体。该施工方法使制作模块化,加快了制作进度;避免了常规的正交异性组合桥面板中发生在U形纵肋上,及起始于U形纵肋和钢盖板焊缝的疲纹,有利于提高结构寿命;支撑件间预留空腔,可提高桥面板结构的抗弯能力,钢盖板和混凝土板的材料性能得到充分发挥;在同组的支撑件内灌注混凝土,可进一步提高正交异性组合桥面板的刚度和主梁的刚度。

Figure 202210940720

The invention relates to a construction method of an orthotropic composite bridge deck, belonging to the technical field of bridge structures. The bridge deck includes U-shaped longitudinal rib, transverse rib, steel cover plate, and concrete plate. A support piece is welded on the surface of the steel cover board, and the support piece is connected with a shear connector, and the shear connector is embedded in the concrete. There are cavities between the supports. The invention uses I-beam to bend a small steel box with U-shaped longitudinal ribs, and the small steel box is transversely welded to form the main body of the bridge deck structure. The construction method makes the production modularized and speeds up the production progress; it avoids the fatigue pattern that occurs on the U-shaped longitudinal rib in the conventional orthotropic composite deck, and starts from the U-shaped longitudinal rib and the welding seam of the steel cover. It is beneficial to improve the life of the structure; the cavity reserved between the supports can improve the bending resistance of the bridge deck structure, and the material properties of the steel cover plate and the concrete slab can be fully exerted; pouring concrete into the supports of the same group can further improve the Orthotropic combination of deck stiffness and girder stiffness.

Figure 202210940720

Description

一种正交异性组合桥面板的施工方法A kind of construction method of orthotropic composite bridge deck

技术领域technical field

本发明涉及一种桥面板的施工方法,特别地涉及一种正交异性组合桥面板的施工方法,属于桥梁工程技术领域。The invention relates to a construction method of a bridge deck, in particular to a construction method of an orthotropic composite bridge deck, and belongs to the technical field of bridge engineering.

背景技术Background technique

随着我国经济的快速发展,一批大跨径跨江跨海公路桥梁相继开工,并陆续建成通车,在我国桥梁建筑史上出现了空前的建设大跨径桥梁的高潮。钢箱梁的抗扭刚度大,弯曲应力图合理,剪应力小,特别适用于大跨径桥梁、弯桥和窄墩柱桥。再考虑到轻量化、预制加工和经济性,公路大跨度悬索桥和斜拉桥基本上都选择流线型的钢箱梁做加劲梁。钢箱梁一般采用正交异性桥面板。正交异性桥面板由钢盖板、纵向加劲肋及横向加劲肋组成,由于其纵向刚度和与其垂直的横向刚度有所不同,因此称之为正交异性桥面板。凭借其承载能力大、自重轻、施工快和结构美观等优点,很好的解决了桥梁的自重、承重和跨径之间的矛盾,已经成为大跨径钢桥的首选桥面形式。With the rapid development of my country's economy, a number of large-span river and sea-crossing highway bridges have been started successively, and have been completed and opened to traffic one after another. In the history of bridge construction in my country, there has been an unprecedented climax of building large-span bridges. The steel box girder has high torsional rigidity, reasonable bending stress diagram and small shear stress, and is especially suitable for large-span bridges, curved bridges and narrow-pier-column bridges. Considering light weight, prefabrication and economy, the long-span suspension bridges and cable-stayed bridges of highways basically choose streamlined steel box girders as stiffening girders. Steel box girders generally use orthotropic decks. The orthotropic bridge deck is composed of steel cover plate, longitudinal stiffeners and transverse stiffeners. Because of its different longitudinal stiffness and transverse stiffness perpendicular to it, it is called an orthotropic deck. With its advantages of large bearing capacity, light weight, fast construction and beautiful structure, it has solved the contradiction between the self-weight, load-bearing and span of the bridge, and has become the preferred bridge deck form for long-span steel bridges.

正交异性桥面板构造复杂,焊缝数量多,不但要反复承受车辆轮载的作用,而且作为主梁的一部分共同参与钢箱梁整体受力。局部承受的应力循环次数过多,且在梁体焊接过程中会引起不可避免的应力集中及焊接缺陷,使得桥面板在运营一段时间后,极易产生疲劳裂纹。大跨度钢桥一旦出现疲劳裂纹,不仅维修困难、费用昂贵,而且会引起桥梁突然破坏的灾难性事故。The orthotropic bridge deck has a complex structure and a large number of welds. It not only has to bear the wheel load of the vehicle repeatedly, but also participates in the overall stress of the steel box girder as a part of the main beam. The local stress cycles are too many, and it will cause inevitable stress concentration and welding defects during the welding process of the beam body, so that the bridge deck is prone to fatigue cracks after a period of operation. Once a long-span steel bridge has fatigue cracks, it is not only difficult and expensive to maintain, but also causes a catastrophic accident of sudden bridge failure.

如何避免疲劳裂纹的产生,确保正交异性桥面板的耐久性,长久以来都是一个重难点课题。目前实桥设计中,解决桥面板疲劳问题主要措施包括:合理匹配纵肋、横肋和桥面板尺寸,构造恰当的弧形切口尺;桥面结构改用混凝土桥面板,如东海大桥、武汉二七长江大桥,主梁均为叠合梁结构,桥面采用混凝土桥面板;也可以简单地增加铺装层,如加筋高性能混凝土、夹心钢板层、聚合物改性混凝土、环氧树脂沥青混凝土、钢纤维加强混凝土等。这些措施或者只能稍微延缓开裂,或者在大幅度增加桥面板重量后刚度没有大的提升。How to avoid fatigue cracks and ensure the durability of orthotropic bridge decks has long been a difficult issue. At present, in the actual bridge design, the main measures to solve the fatigue problem of the bridge deck include: reasonably matching the dimensions of the longitudinal ribs, transverse ribs and the bridge deck, and constructing appropriate arc-shaped incision rulers; For the Seventh Yangtze River Bridge, the main girder is a composite girder structure, and the bridge deck is made of concrete deck; pavement layers can also be simply added, such as reinforced high-performance concrete, sandwich steel plate layer, polymer-modified concrete, epoxy resin asphalt Concrete, steel fiber reinforced concrete, etc. These measures either retarded the cracking only slightly, or there was no major increase in stiffness after a substantial increase in deck weight.

发明内容SUMMARY OF THE INVENTION

为了克服现有技术上的不足,本发明开发了一种正交异性组合桥面板的施工方法,目的是减少正交异性桥面结构的疲劳裂纹。In order to overcome the deficiencies in the prior art, the present invention develops a construction method of an orthotropic composite bridge deck, which aims to reduce the fatigue cracks of the orthotropic bridge deck structure.

本发明提出的技术方案为一种正交异性组合桥面板的施工方法,该组合桥面板包括U形纵肋、横肋、钢盖板、混凝土板,其特征在于:钢盖板上表面连接支撑件,支撑件上连接抗剪连接件,抗剪连接件埋入混凝土,支撑件间有空腔或泡沫体。The technical solution proposed by the present invention is a construction method of an orthotropic composite bridge deck, the composite bridge deck comprises U-shaped longitudinal ribs, transverse ribs, steel cover plates, and concrete slabs, and is characterized in that: the upper surface of the steel cover plate is connected and supported The support is connected with a shear connector, the shear connector is embedded in concrete, and there is a cavity or foam between the supports.

优选地,所述的支撑件为角钢,一个边的端部与钢盖板垂直焊接,另一边平行于钢盖板上表面。Preferably, the support member is an angle steel, the end of one side is welded perpendicular to the steel cover plate, and the other side is parallel to the upper surface of the steel cover plate.

优选地,所述的支撑件为槽钢,槽钢的腹板垂直于钢盖板,槽钢的一个翼板的两侧通过角焊缝连接钢盖板上表面;或者所述的支撑件为工字钢,工字钢的腹板垂直于钢盖板,工字钢的一个翼板的两侧通过角焊缝连接钢盖板上表面。Preferably, the support member is channel steel, the web of the channel steel is perpendicular to the steel cover plate, and the two sides of one wing plate of the channel steel are connected to the upper surface of the steel cover plate through fillet welds; or the support member is I-beam, the web of the I-beam is perpendicular to the steel cover plate, and the two sides of a wing plate of the I-beam are connected to the upper surface of the steel cover plate through fillet welds.

优选地,所述的支撑件连接在U形纵肋的侧板与钢盖板的相交线的上方。Preferably, the support member is connected above the intersection line of the side plate of the U-shaped longitudinal rib and the steel cover plate.

优选地,所述的相交线的上方连接有两个支撑件;这两个支撑件对称于所述的相交线排列,形成一个支撑件组。Preferably, two support members are connected above the intersection line; the two support members are symmetrically arranged with respect to the intersection line to form a support member group.

优选地,所述支撑件组间为空腔或泡沫体,所述支撑件组内的空间内填充有混凝土。Preferably, the space between the support member groups is a cavity or a foam body, and the space in the support member group is filled with concrete.

优选地,所述的混凝土板为预制板,预制板上有预留槽,所述预留槽的位置与抗剪连接件的位置相对应;预制板放置在支撑件上,抗剪连接件的顶端低于预制板上表面。Preferably, the concrete slab is a prefabricated slab, and there are reserved grooves on the prefabricated slab, and the positions of the reserved slots correspond to the positions of the shear connectors; the prefabricated slabs are placed on the support members, and the shear connectors are The top is lower than the upper surface of the prefabricated board.

优选地,所述的预制板包括边板和中板,边板三面有伸出的钢筋,中板的四面都伸出有钢筋;所述的预制板通过现浇混凝土连接带成为一体;横向的连接带与其下方的横肋或横向连接构造的位置对应;纵向的连接带位于支撑件组上,现浇混凝土进入该支撑件组的内部空间。Preferably, the prefabricated panel includes a side panel and a middle panel, three sides of the side panel are protruded with reinforcing bars, and four sides of the center panel are protruded with reinforcing bars; the prefabricated panel is integrated by a cast-in-place concrete connecting belt; The connection strips correspond to the positions of the transverse ribs or transverse connection structures below them; the longitudinal connection strips are located on the support group, and the cast-in-place concrete enters the inner space of the support group.

一种正交异性组合桥面板的施工方法,施工包括以下步骤,A construction method for an orthotropic composite bridge deck, the construction comprising the following steps:

步骤1在钢构件制作车间,将工字钢弯制和焊接形成带U形纵肋和顶板的小钢箱;多个小钢箱并排连接在一起,所述的顶板形成钢盖板;Step 1: In the steel component manufacturing workshop, the I-beam is bent and welded to form a small steel box with U-shaped longitudinal ribs and a top plate; a plurality of small steel boxes are connected side by side, and the top plate forms a steel cover plate;

步骤2在U形纵肋的侧板与钢盖板相交线的上方的钢盖板上表面,对称地焊接两条支撑件。这两个支撑件,形成一个支撑件组;在支撑件的顶面焊接剪力连接件,相互靠拢的多个剪力连接件形成一个连接件组;Step 2 On the upper surface of the steel cover plate above the intersection line of the side plate of the U-shaped longitudinal rib and the steel cover plate, symmetrically weld two support members. The two supports form a support group; the shear connectors are welded on the top surface of the supports, and a plurality of shear connectors close to each other form a connector group;

步骤3将步骤2制作的桥面钢构件随同钢箱梁的其它组件,组装成钢箱梁节段,运到桥梁工地;Step 3: Assemble the bridge deck steel members produced in Step 2 together with other components of the steel box girder into steel box girder segments, and transport them to the bridge construction site;

步骤4计划分区浇筑混凝土,并在各分区间预留后浇带,并将纵向后浇带设在支撑件组上方。在各分区内,支撑件组间填充塑料泡沫;绑扎钢筋网,浇筑各分区混凝土,并养护;随后,浇筑各分区间的后浇带,养护。Step 4: Plan to pour concrete in different zones, reserve post-pouring belts between the sub-areas, and set the longitudinal post-casting belts above the support group. In each partition, the support member groups are filled with plastic foam; the steel mesh is bound, concrete is poured in each partition, and maintained; then, the post-casting belt between each partition is poured and maintained.

一种正交异性组合桥面板的施工方法,施工包括以下步骤,A construction method for an orthotropic composite bridge deck, the construction comprising the following steps:

步骤1在钢构件制作车间,将工字钢弯制和焊接形成带U形纵肋和顶板的小钢箱;多个小钢箱并排连接在一起,所述的顶板形成钢盖板;Step 1: In the steel component manufacturing workshop, the I-beam is bent and welded to form a small steel box with U-shaped longitudinal ribs and a top plate; a plurality of small steel boxes are connected side by side, and the top plate forms a steel cover plate;

步骤2在U形纵肋的侧板与钢盖板相交线的上方的钢盖板上表面,对称地焊接两条支撑件。这两个支撑件,形成一个支撑件组;在支撑件的顶面焊接剪力连接件,相互靠拢的多个剪力连接件形成一个连接件组;在混凝土预制场,用混凝土预制各预制板;Step 2 On the upper surface of the steel cover plate above the intersection line of the side plate of the U-shaped longitudinal rib and the steel cover plate, symmetrically weld two support members. The two supports form a support group; the shear connectors are welded on the top surface of the supports, and multiple shear connectors close to each other form a connector group; in the concrete precast field, each prefabricated slab is prefabricated with concrete ;

步骤3将混凝土预制板运到工地现场;将步骤2制作的桥面钢构件随同钢箱梁的其它组件,组装成钢箱梁节段,运到桥梁工地;In step 3, the precast concrete slabs are transported to the construction site; the bridge deck steel members produced in step 2 are assembled into steel box girder segments together with other components of the steel box girder, and transported to the bridge construction site;

步骤4在计划的预制板各安装分区的横向现浇带边缘,焊接隔板作为模板;在支撑件组的两个支撑件的边缘沿纵向粘贴橡胶条,确保安装预制板后各支撑件组内部和外部间封闭;安放混凝土预制板;在沿桥梁横向的现浇带处,用建筑密封胶封闭预制板与模板间、预制板与连接件顶面间的缝隙;Step 4: On the horizontal cast-in-place edge of each installation zone of the planned prefabricated panel, weld the clapboard as a template; paste rubber strips along the longitudinal direction on the edges of the two supports of the support group to ensure that the interior of each support group after the prefabricated panel is installed Close the gap between the prefabricated slab and the outside; place the precast concrete slab; at the cast-in-place belt along the transverse direction of the bridge, seal the gap between the prefabricated slab and the formwork and between the prefabricated slab and the top surface of the connector with building sealant;

步骤5通过预留槽向对应混凝土预制板的支撑件组内灌注混凝土,灌注次序为沿桥梁纵向从预制板的一端到另一端,在每个预留槽处灌注作业时,直到前方预留槽有混凝土排出;再从刚有混凝土排出的预留槽灌筑,直到下一个邻近的预留槽有混凝土排出;如此顺序作业。所预留槽内灌满混凝土后,现浇各预制板间的连接带。现浇混凝土用塑料膜覆盖,养护。Step 5: Concrete is poured into the support group corresponding to the precast concrete slab through the reserved slot. The pouring sequence is from one end of the prefabricated slab to the other end along the longitudinal direction of the bridge. Concrete is discharged; then pour from the reserved groove that has just been discharged until concrete is discharged from the next adjacent reserved groove; this is the sequence of operations. After the reserved grooves are filled with concrete, the connecting belts between the prefabricated slabs are cast in place. The cast-in-place concrete is covered with plastic film and cured.

本发明的有益效果包括以下几个方面:The beneficial effects of the present invention include the following aspects:

(1)正交异性桥面板的疲劳裂纹中的大部分与U形纵肋相关,比如出现在U形纵肋上,及起源于U形纵肋与钢盖板接缝、U形纵肋贯穿横肋和横隔板时的交叉连接部位、U形纵肋对接焊缝等处的裂纹。本发明用工字钢弯制出带U形纵肋的小钢箱,小钢箱横向焊接组成桥面结构的主体。该施工方法取消了U形纵肋与钢盖板的连接焊缝,从源头上大幅度地减少了此处可能出现的疲劳裂纹的数量。虽然钢盖板上增加了焊缝,但很少有报道钢盖板间的接缝处出现疲劳裂纹的,原因是此处在U形纵肋的上方,应力相对较小,受力状态较好;(1) Most of the fatigue cracks of the orthotropic bridge deck are related to the U-shaped longitudinal ribs, such as appearing on the U-shaped longitudinal ribs, and originating from the joints between the U-shaped longitudinal ribs and the steel cover plate, and the penetration of the U-shaped longitudinal ribs. Cracks at the cross-connection of transverse ribs and diaphragms, butt welds of U-shaped longitudinal ribs, etc. The invention uses I-beam to bend a small steel box with U-shaped longitudinal ribs, and the small steel box is transversely welded to form the main body of the bridge deck structure. This construction method cancels the connection weld between the U-shaped longitudinal rib and the steel cover plate, and greatly reduces the number of fatigue cracks that may occur here from the source. Although welds have been added to the steel cover, there are few reports of fatigue cracks occurring at the joints between the steel covers. The reason is that the stress is relatively small and the stress state is better at the top of the U-shaped longitudinal rib. ;

(2)用工字钢弯制出带U形纵肋的小钢箱,用型钢做支撑件,整个桥面钢结构均采用型钢,取材方便,制作模块化,便于运输和搬运,加快了制作进度;(2) Bend a small steel box with U-shaped longitudinal ribs from I-beam, and use section steel as a support. Section steel is used for the entire bridge deck steel structure. ;

(3)起始于U形纵肋和钢盖板焊缝的裂纹的减少,有利于提高结构寿命;(3) The reduction of cracks starting from the U-shaped longitudinal rib and the weld of the steel cover plate is conducive to improving the structural life;

(4)起始于U形纵肋和钢盖板焊缝的裂纹的减少,减少了后期维修工作量,因为深入钢盖板的裂缝不易发现,一旦发现就已经开裂程度严重,且修补困难。因为修复需要中断交通;(4) The reduction of cracks starting from the U-shaped longitudinal rib and the weld of the steel cover plate reduces the maintenance workload in the later period, because the cracks deep into the steel cover plate are not easy to find. Once found, the cracking degree is serious and repairing is difficult. Because repairs require interruption of traffic;

(5)钢盖板上焊接支撑件,支撑件上安装预制混凝土板,可提高组合桥面板结构的抗弯能力;(5) Welding supports on the steel cover plate and installing precast concrete slabs on the supports can improve the bending resistance of the composite bridge deck structure;

(6)支撑件组内的空间内灌注混凝土,可进一步提高正交异性组合桥面板的刚度和主梁的刚度,并改善钢盖板的受力状态;(6) Concrete is poured into the space in the support group, which can further improve the stiffness of the orthotropic composite bridge deck and the stiffness of the main beam, and improve the stress state of the steel cover;

(7)本发明中的钢结构部分在工厂内制作,预制混凝土板也提前在预制场制作,在现场拼装,加快了施工进度,有利于快速施工;(7) The steel structure part in the present invention is made in the factory, and the prefabricated concrete slab is also made in the prefabrication field in advance, and assembled on site, which speeds up the construction progress and is conducive to rapid construction;

(8)横肋和横隔板上方为现浇混凝土连接带,从而增强了桥面板的横向刚度。(8) Above the transverse rib and the diaphragm, there are cast-in-place concrete connecting belts, thereby enhancing the lateral stiffness of the bridge deck.

附图说明Description of drawings

图1工字钢制作小钢箱的过程示意图;Figure 1 is a schematic diagram of the process of making a small steel box from I-beam;

图2小钢箱拼装的钢桥面组合件示意图;Figure 2 Schematic diagram of the steel bridge deck assembly assembled with small steel boxes;

图3焊接剪力钉后的结构示意图;Figure 3 Schematic diagram of the structure after welding shear nails;

图4角钢组间填充后的结构示意图;Figure 4 is a schematic diagram of the structure after filling between the angle steel groups;

图5浇筑片分布示意图;Figure 5 is a schematic diagram of the distribution of pouring pieces;

图6绑扎钢筋网后的结构横断面示意图;Figure 6 is a schematic cross-sectional view of the structure after the steel mesh is bound;

图7分片浇筑混凝土后的结构示意图;Figure 7 is a schematic diagram of the structure after the concrete is poured in pieces;

图8安装水平模板后的结构横断面示意图;Figure 8 is a schematic cross-sectional view of the structure after installing the horizontal formwork;

图9实施例1的组合桥面板结构横断面示意图;9 is a schematic cross-sectional view of the composite bridge deck structure in Embodiment 1;

图10实施例2中的混凝土预制板边板示意图;Figure 10 is a schematic diagram of the side plate of the precast concrete slab in Example 2;

图11实施例2中的混凝土预制板中板示意图;Fig. 11 is the schematic diagram of the middle plate of the concrete precast slab in Example 2;

图12实施例2中混凝土预制板分布规划示意图;Figure 12 is a schematic diagram of the distribution planning of precast concrete slabs in Example 2;

图13过图12中A—A的结构横断面示意图;Figure 13 is a schematic cross-sectional view of the structure through A-A in Figure 12;

图14实施例2中安放预制板后的结构俯视示意图;Figure 14 is a schematic top view of the structure after the prefabricated panels are placed in Embodiment 2;

图15实施例2中浇筑混凝土后的结构俯视示意图;Figure 15 is a schematic plan view of the structure after pouring concrete in Example 2;

图16过图15中B—B的结构横断面示意图;Figure 16 is a schematic cross-sectional view of the structure through B-B in Figure 15;

图17过图15中C—C的结构横断面示意图;Figure 17 is a schematic cross-sectional view of the structure through C-C in Figure 15;

图18实施例3安放永久底膜后的结构示意图;Figure 18 is a schematic view of the structure after the permanent base film is placed in Example 3;

图19实施例3绑扎钢筋网后的结构横断面示意图;Figure 19 is a schematic cross-sectional view of the structure after binding the steel mesh in Embodiment 3;

图20实施例3的组合桥面板结构横断面示意图;Figure 20 is a schematic cross-sectional view of the composite bridge deck structure in Embodiment 3;

图21实施例4中混凝土预制板分布规划示意图;Figure 21 is a schematic diagram of the distribution planning of precast concrete slabs in Example 4;

图22实施例4中对应图15中C—C的结构横断面示意图。FIG. 22 is a schematic cross-sectional view of the structure corresponding to C-C in FIG. 15 in Embodiment 4. FIG.

图中:钢盖板1,U形纵肋2,剪力钉3,横肋4,预制板5,钢筋6,预留槽7,小隔板8,大隔板9,边板10,中板11,连接带12,现浇混凝土13,模具梁14,小钢箱15,工字钢16,角钢17,聚丙烯泡沫板18,钢筋网19,波折板20。In the picture: steel cover plate 1, U-shaped longitudinal rib 2, shear nail 3, transverse rib 4, prefabricated plate 5, steel bar 6, reserved groove 7, small partition 8, large partition 9, side plate 10, middle plate Plate 11, connecting belt 12, cast-in-place concrete 13, mould beam 14, small steel box 15, I-beam 16, angle steel 17, polypropylene foam board 18, steel mesh 19, corrugated board 20.

具体实施方式Detailed ways

实施例1Example 1

本实施例在组合桥面板中埋设有泡沫板。组合桥面板的钢结构部分见图1-图3,图1显示了利用工字钢16制作小钢箱15的过程,在钢结构制作厂车间内,工字钢16被放在模具梁14上,模具梁14为钢梁且两端被支承,两排与上方推力杆铰接的冲压头,分别从上方对称地压在工字钢16的腹板的两个端部,将工字钢16弯折形成小钢箱15,焊接中间的接缝。多个小钢箱15并排焊接在一起,小钢箱15的顶板就形成钢盖板1,对应工字钢16的腹板部分就成了U形纵肋2。在U形纵肋2的侧板与钢盖板1的相交线的上方,焊接角钢17作为支撑件,两个角钢17对称于相交线排列,形成一个支撑件组。角钢17一边的端部与钢盖板1焊接,另一边平行于钢盖板1上表面。在角钢17上焊接剪力钉3作为抗剪连接件,同一处的4个剪力钉3作为一个连接件组,参见图5。将制作的桥面钢构件随同钢箱梁的其它组件组装成钢箱梁节段,运到桥梁工地。In this embodiment, a foam board is embedded in the composite bridge deck. The steel structure part of the composite bridge deck is shown in Figures 1-3. Figure 1 shows the process of making the small steel box 15 by using the I-beam 16. In the workshop of the steel structure manufacturing plant, the I-beam 16 is placed on the mold beam 14. , the die beam 14 is a steel beam and both ends are supported, and the two rows of punching heads hinged with the upper thrust rod are symmetrically pressed on the two ends of the web of the I-beam 16 from above, and the I-beam 16 is bent. Fold it to form a small steel box 15, and weld the seam in the middle. A plurality of small steel boxes 15 are welded side by side, the top plate of the small steel boxes 15 forms the steel cover plate 1 , and the web portion corresponding to the I-beam 16 becomes the U-shaped longitudinal rib 2 . Above the intersection line of the side plate of the U-shaped longitudinal rib 2 and the steel cover plate 1, the welded angle steel 17 is used as a support, and the two angle steels 17 are symmetrically arranged on the intersection line to form a support group. One end of the angle steel 17 is welded with the steel cover plate 1 , and the other side is parallel to the upper surface of the steel cover plate 1 . The shear nails 3 are welded on the angle steel 17 as a shear connector, and the four shear nails 3 at the same place are used as a connector group, see Figure 5. The fabricated bridge deck steel members and other components of the steel box girder are assembled into steel box girder segments and transported to the bridge construction site.

在工地架设钢箱梁节段并焊接为一体。在支撑件组间放置聚丙烯泡沫板18,见图4和图5。将计划浇筑的混凝土桥面板划分为多个区域,区域间留后浇带,主要是为了避免大面积浇筑后混凝土板出现裂缝。聚丙烯泡沫板18安装在各个区域内的相邻支撑件组间。纵向后浇带设在支撑件组上方。横向后浇带的位置设置在与其下方的横肋或横隔板对应;绑扎钢筋网19,见图6;浇筑各分区混凝土,并养护,分片浇筑混凝土后的结构示意图见图7;随后,浇筑各分区间的连接带12,养护,见图8。图9为实施例1的组合桥面板结构位于非横肋和非横隔板位置的横断面示意图,现浇混凝土13填充了各支撑件组内部的空间,并形成上方的混凝土桥面板,从而使图9中的各个组件形成有机的整体,成为正交异性组合桥面板。Steel box girder segments are erected on the site and welded into one. A polypropylene foam board 18 is placed between the sets of supports, see FIGS. 4 and 5 . The concrete bridge deck planned to be poured is divided into several areas, and post-pouring belts are left between the areas, mainly to avoid cracks in the concrete slab after large-scale pouring. Polypropylene foam panels 18 are installed between adjacent sets of support members in each zone. The longitudinal post-casting belt is arranged above the support group. The position of the transverse post-casting belt is set to correspond to the transverse rib or diaphragm below it; the reinforcement mesh 19 is bound, see Figure 6; the concrete is poured in each zone and cured, and the schematic diagram of the structure after the concrete is poured in pieces is shown in Figure 7; then, The connecting belts 12 between each subarea are poured and maintained, as shown in Figure 8. 9 is a schematic cross-sectional view of the composite bridge deck structure of Example 1 at positions other than transverse ribs and non-diaphragm plates. The cast-in-place concrete 13 fills the space inside each support group and forms the upper concrete bridge deck, so that the The various components in Figure 9 form an organic whole and become an orthotropic composite bridge deck.

实施例2Example 2

本实施例是对实施例1的修正,桥面板采用了混凝土预制件。混凝土板采用预制板5拼装并现浇接缝而成,预制板5上有预留槽7,且预留槽7的位置与连接件组的位置相对应;预制板5分为边板10和中板11两种类型,见图10和图11。边板10三面有伸出的钢筋6,中板11的四面都伸出有钢筋6,钢筋6外伸长度为200mm。预制板5放置在支撑件组上后,连接件组进入预留槽7,且剪力钉3的顶端低于预制板5上表面20mm;相邻预制板5间接缝两侧的钢筋6可向相反的方向水平扳弯折,避免安装时相互干扰。预制板5的宽度,使横向接缝下刚好为横肋或横隔板的位置,且纵向的接缝位于支撑件组上。安放预制板5前,需在横向接缝位置焊接小隔板8和大隔板9作为模板,见图12和图13。在各预制板5的规划区域内的连接件组前、后,焊接小隔板8。小隔板8和大隔板9的的顶端与角钢17的顶面平齐。在支撑件组的两个角钢17的顶面边缘沿纵向粘贴2mm厚的橡胶条,确保安装预制板5后各支撑件组内部和外部间封闭;安放预制板5,见图14;在沿桥梁横向的现浇带处,用建筑密封胶封闭预制板5与模板间、预制板5与角钢17顶面间的缝隙。This embodiment is a modification of Embodiment 1, and the bridge deck adopts concrete prefabricated parts. The concrete slab is made of prefabricated slabs 5 assembled and cast-in-place joints. The prefabricated slab 5 has a reserved slot 7, and the position of the reserved slot 7 corresponds to the position of the connector group; the prefabricated slab 5 is divided into side slabs 10 and 7. There are two types of middle plate 11, see Figure 10 and Figure 11. Three sides of the side plate 10 have protruding steel bars 6, and four sides of the middle plate 11 are protruded with steel bars 6, and the extension length of the steel bars 6 is 200mm. After the prefabricated board 5 is placed on the support group, the connector group enters the reserved groove 7, and the top of the shear nail 3 is 20 mm lower than the upper surface of the prefabricated board 5; Bend horizontally in opposite directions to avoid mutual interference during installation. The width of the prefabricated panel 5 is such that the transverse seam is just below the position of the transverse rib or the transverse partition, and the longitudinal seam is located on the support group. Before placing the prefabricated panel 5, it is necessary to weld the small partition plate 8 and the large partition plate 9 at the transverse joint position as a template, as shown in Figure 12 and Figure 13. Small baffles 8 are welded before and after the connector group in the planned area of each prefabricated panel 5 . The tops of the small partition 8 and the large partition 9 are flush with the top surface of the angle steel 17 . Paste 2mm thick rubber strips along the longitudinal direction on the top edge of the two angle steels 17 of the support group to ensure that the interior and exterior of each support group are closed after installing the prefabricated panels 5; place the prefabricated panels 5, see Figure 14; At the horizontal cast-in-place belt, use building sealant to seal the gaps between the prefabricated plate 5 and the formwork, and between the prefabricated plate 5 and the top surface of the angle steel 17.

通过预留槽7向对应混凝土预制板5的支撑件组内灌注混凝土,灌注次序为沿桥梁纵向从预制板5的一端到另一端,在每个预留槽7处灌注作业时,直到前方预留槽7有混凝土排出;再从刚有混凝土排出的预留槽7灌筑,直到下一个邻近的预留槽7有混凝土排出;如此顺序作业。所预留槽7内灌满混凝土后,现浇各预制板间的连接带12,见图15。现浇混凝土用塑料膜覆盖,养护。过图15中B—B的结构横断面示意图见图16,过图15中C—C的结构横断面示意图见图17,图17中可见横肋4。横肋4为T型钢,腹板在上,焊接在钢盖板1的下表面。横肋4的腹板上挖有孔洞,以便U形纵肋2穿过。Concrete is poured into the support group corresponding to the precast concrete slab 5 through the reserved slot 7. The pouring sequence is from one end of the prefabricated slab 5 to the other end along the longitudinal direction of the bridge. Concrete is discharged from the retaining groove 7; and then poured from the reserved groove 7 where the concrete has just been discharged, until the next adjacent reserved groove 7 has concrete discharged; this is the sequence of operations. After the reserved groove 7 is filled with concrete, the connecting strips 12 between the prefabricated slabs are cast in place, as shown in Figure 15. The cast-in-place concrete is covered with plastic film and cured. The schematic cross-sectional view of the structure through B-B in FIG. 15 is shown in FIG. 16 , the schematic cross-sectional view of the structure through C-C in FIG. 15 is shown in FIG. 17 , and the transverse rib 4 can be seen in FIG. 17 . The transverse rib 4 is T-shaped steel, the web is on top, and it is welded on the lower surface of the steel cover plate 1 . Holes are dug in the web of the transverse rib 4 so that the U-shaped longitudinal rib 2 can pass through.

实施例3Example 3

本实施例是对实施例1的修正,混凝土板与钢盖板1间设置孔洞,见图18-图20。图18为安放永久底膜后的结构示意图,在相邻的支撑件组间安放波折板20,波折板20作为永久模板,在成桥后不再拆除。波折板20采用一块钢板,通过固定其两个长边,压制其中部而成。波折板20与角钢17顶面边缘焊接。绑扎钢筋网19后的结构横断面示意图见图19。仍如实施例1中分区域浇筑混凝土,并随后浇筑连接带12,最终得到的组合桥面板结构的横断面如图20所示,该组合桥面板的钢盖板1的上方就设置有孔洞,在减轻自重的情况下,增加了组合桥面板的抗弯能力,同时也增加了整个主梁的抗弯能力,从而可减少疲劳裂纹。This embodiment is a modification of Embodiment 1, and holes are arranged between the concrete slab and the steel cover plate 1, as shown in Figures 18-20. Fig. 18 is a schematic view of the structure after the permanent bottom film is placed. A corrugated plate 20 is placed between adjacent support member groups. The corrugated plate 20 is used as a permanent template and will not be removed after the bridge is formed. The corrugated plate 20 is made of a steel plate by fixing its two long sides and pressing its middle. The corrugated plate 20 is welded with the edge of the top surface of the angle steel 17 . Figure 19 shows a schematic cross-sectional view of the structure after binding the steel mesh 19. Still as in Example 1, the concrete is poured in different areas, and then the connecting belt 12 is poured. The cross-section of the finally obtained composite bridge deck structure is shown in Figure 20. The upper part of the steel cover plate 1 of the composite bridge deck is provided with holes, In the case of reducing its own weight, the bending resistance of the composite bridge deck is increased, and the bending resistance of the entire main beam is also increased, thereby reducing fatigue cracks.

实施例4Example 4

本实施例是对实施例2的修正,支撑件组内均灌注混凝土。见图21-图22。各预制板5下方的连接件组前后不再设置小隔板8。成桥后,组合桥面板的结构横断面示意图见图22,此处不在横隔板位置,也不是横肋设置。在支撑件组的内部浇筑混凝土后,增加了车辆荷载向钢盖板1传递时,钢盖板1的受力面积,可进一步改善钢盖板1的受力状态。This embodiment is a modification of Embodiment 2, and concrete is poured into the support group. See Figures 21-22. The small partitions 8 are no longer provided before and after the connector group under each prefabricated board 5 . After the bridge is completed, the schematic cross-sectional view of the composite bridge deck is shown in Figure 22, which is not located at the position of the diaphragm, nor is the transverse rib set. After concrete is poured inside the support group, the stress area of the steel cover 1 when the vehicle load is transmitted to the steel cover 1 is increased, which can further improve the stress state of the steel cover 1 .

本发明中的“上方”包括正上方和斜上方,类似的其它位置关系也同理做出理解。In the present invention, "above" includes directly above and obliquely above, and other similar positional relationships are also to be understood in the same way.

Claims (10)

1.一种正交异性组合桥面板,包括U形纵肋、横肋、钢盖板、混凝土板,其特征在于:钢盖板上表面连接支撑件,支撑件上连接抗剪连接件,抗剪连接件埋入混凝土,支撑件间有空腔或泡沫体。1. An orthotropic composite bridge deck, comprising U-shaped longitudinal ribs, transverse ribs, steel cover plates, and concrete slabs, is characterized in that: the upper surface of the steel cover plate is connected to a support member, and the support member is connected to a shear connector, which is resistant to The shear connectors are embedded in concrete, with cavities or foam between the supports. 2.根据权利要求1所述的正交异性组合桥面板,其特征在于:所述的支撑件为角钢,一个边的端部与钢盖板垂直焊接,另一边平行于钢盖板上表面。2 . The orthotropic composite bridge deck according to claim 1 , wherein the supporting member is an angle steel, the end of one side is vertically welded to the steel cover plate, and the other side is parallel to the upper surface of the steel cover plate. 3 . 3.根据权利要求1所述的正交异性组合桥面板,其特征在于:所述的支撑件为槽钢,槽钢的腹板垂直于钢盖板,槽钢的一个翼板的两侧通过角焊缝连接钢盖板上表面;或者所述的支撑件为工字钢,工字钢的腹板垂直于钢盖板,工字钢的一个翼板的两侧通过角焊缝连接钢盖板上表面。3. The orthotropic composite bridge deck according to claim 1, characterized in that: the support member is channel steel, the web of the channel steel is perpendicular to the steel cover plate, and the two sides of a wing plate of the channel steel pass through The fillet weld is connected to the upper surface of the steel cover; or the support is an I-beam, the web of the I-beam is perpendicular to the steel cover, and the two sides of a wing plate of the I-beam are connected to the steel cover through fillet welds board surface. 4.根据权利要求1所述的正交异性组合桥面板,其特征在于:所述的支撑件连接在U形纵肋的侧板与钢盖板的相交线的上方。4. The orthotropic composite bridge deck according to claim 1, wherein the supporting member is connected above the intersection line of the side plate of the U-shaped longitudinal rib and the steel cover plate. 5.根据权利要求4所述的正交异性组合桥面板,其特征在于:所述的相交线的上方连接有两个支撑件;这两个支撑件对称于所述的相交线排列,形成一个支撑件组。5 . The orthotropic composite bridge deck according to claim 4 , wherein two support members are connected above the intersection line; the two support members are arranged symmetrically with respect to the intersection line to form a Support group. 6.根据权利要求5所述的正交异性组合桥面板,其特征在于:所述支撑件组间为空腔或泡沫体,所述支撑件组内的空间内填充有混凝土。6 . The orthotropic composite bridge deck according to claim 5 , wherein the supporting member groups are hollow or foamed, and the spaces in the supporting member groups are filled with concrete. 7 . 7.根据权利要求6所述的正交异性组合桥面板,其特征在于:所述的混凝土板为预制板,预制板上有预留槽,所述预留槽的位置与抗剪连接件的位置相对应;预制板放置在支撑件上,抗剪连接件的顶端低于预制板上表面。7. The orthotropic composite bridge deck according to claim 6, characterized in that: the concrete slab is a prefabricated slab, and the prefabricated slab has a reserved groove, and the position of the reserved groove is the same as that of the shear connector. The positions are corresponding; the prefabricated board is placed on the support, and the top of the shear connector is lower than the upper surface of the prefabricated board. 8.根据权利要求7所述的正交异性组合桥面板,其特征在于:所述的预制板包括边板和中板,边板三面有伸出的钢筋,中板的四面都伸出有钢筋;所述的预制板通过现浇混凝土连接成为一体;横向的连接带与其下方的横肋或横向连接构造的位置对应;纵向的连接带位于支撑件组上,现浇混凝土进入该支撑件组的内部空间。8. The orthotropic composite bridge deck according to claim 7, characterized in that: the prefabricated plate comprises a side plate and a middle plate, three sides of the side plate have protruding steel bars, and four sides of the middle plate are protruded with steel bars The prefabricated slabs are connected into one by the cast-in-place concrete; the horizontal connecting belt corresponds to the position of the transverse rib or the horizontal connecting structure below it; interior space. 9.一种正交异性组合桥面板的施工方法,其特征在于:施工包括以下步骤,9. A construction method for an orthotropic composite bridge deck, characterized in that: the construction comprises the following steps, 步骤1在钢构件制作车间,将工字钢弯制和焊接形成带U形纵肋和顶板的小钢箱;多个小钢箱并排连接在一起,所述的顶板形成钢盖板;Step 1: In the steel component manufacturing workshop, the I-beam is bent and welded to form a small steel box with U-shaped longitudinal ribs and a top plate; a plurality of small steel boxes are connected side by side, and the top plate forms a steel cover plate; 步骤2在U形纵肋的侧板与钢盖板相交线的上方的钢盖板上表面,对称地焊接两条支撑件;这两个支撑件,形成一个支撑件组;在支撑件的顶面焊接剪力连接件,相互靠拢的多个剪力连接件形成一个连接件组;Step 2 On the upper surface of the steel cover plate above the intersection line of the side plate of the U-shaped longitudinal rib and the steel cover plate, two support members are symmetrically welded; the two support members form a support member group; Surface welded shear connectors, and multiple shear connectors close to each other form a connector group; 步骤3将步骤2制作的桥面钢构件随同钢箱梁的其它组件,组装成钢箱梁节段,运到桥梁工地;Step 3: Assemble the bridge deck steel members produced in Step 2 together with other components of the steel box girder into steel box girder segments, and transport them to the bridge construction site; 步骤4计划分区浇筑混凝土,并在各分区间预留后浇带,并将纵向后浇带设在支撑件组上方;在各分区内,支撑件组间填充塑料泡沫;绑扎钢筋网,浇筑各分区混凝土,并养护;随后,浇筑各分区间的后浇带,养护。Step 4: Plan to pour concrete in different zones, reserve post-pouring belts between the sub-sections, and set the longitudinal post-casting belts above the support member groups; in each zone, fill plastic foam between the support member groups; bind steel mesh, pour each Partition concrete, and cure; then, pour the post-pouring belt between each partition, and cure. 10.一种正交异性组合桥面板的施工方法,其特征在于:施工包括以下步骤,10. A construction method for an orthotropic composite bridge deck, characterized in that: the construction comprises the following steps, 步骤1在钢构件制作车间,将工字钢弯制和焊接形成带U形纵肋和顶板的小钢箱;多个小钢箱并排连接在一起,所述的顶板形成钢盖板;Step 1: In the steel component manufacturing workshop, the I-beam is bent and welded to form a small steel box with U-shaped longitudinal ribs and a top plate; a plurality of small steel boxes are connected side by side, and the top plate forms a steel cover plate; 步骤2在U形纵肋的侧板与钢盖板相交线的上方的钢盖板上表面,对称地焊接两条支撑件;这两个支撑件,形成一个支撑件组;在支撑件的顶面焊接剪力连接件,相互靠拢的多个剪力连接件形成一个连接件组;在混凝土预制场,用混凝土预制各预制板;Step 2 On the upper surface of the steel cover plate above the intersection line of the side plate of the U-shaped longitudinal rib and the steel cover plate, two support members are symmetrically welded; the two support members form a support member group; Surface welded shear connectors, and multiple shear connectors close to each other form a connector group; in the concrete prefabrication field, each prefabricated slab is prefabricated with concrete; 步骤3将混凝土预制板运到工地现场;将步骤2制作的桥面钢构件随同钢箱梁的其它组件,组装成钢箱梁节段,运到桥梁工地;In step 3, the precast concrete slabs are transported to the construction site; the bridge deck steel members produced in step 2 are assembled into steel box girder segments together with other components of the steel box girder, and transported to the bridge construction site; 步骤4在计划的预制板各安装分区的横向现浇带边缘,焊接隔板作为模板;在支撑件组的两个支撑件的边缘沿纵向粘贴橡胶条,确保安装预制板后各支撑件组内部和外部间封闭;安放混凝土预制板;在沿桥梁横向的现浇带处,用建筑密封胶封闭预制板与模板间、预制板与连接件顶面间的缝隙;Step 4: On the horizontal cast-in-place edge of each installation zone of the planned prefabricated panel, weld the clapboard as a template; paste rubber strips along the longitudinal direction on the edges of the two supports of the support group to ensure that the interior of each support group after the prefabricated panel is installed Close the gap between the prefabricated slab and the outside; place the precast concrete slab; at the cast-in-place belt along the transverse direction of the bridge, seal the gap between the prefabricated slab and the formwork and between the prefabricated slab and the top surface of the connector with building sealant; 步骤5通过预留槽向对应混凝土预制板的支撑件组内灌注混凝土,灌注次序为沿桥梁纵向从预制板的一端到另一端,在每个预留槽处灌注作业时,直到前方预留槽有混凝土排出;再从刚有混凝土排出的预留槽灌筑,直到下一个邻近的预留槽有混凝土排出;如此顺序作业。所预留槽内灌满混凝土后,现浇各预制板间的连接带。现浇混凝土用塑料膜覆盖,养护。Step 5: Concrete is poured into the support group corresponding to the precast concrete slab through the reserved slot. The pouring sequence is from one end of the precast slab to the other end along the longitudinal direction of the bridge. Concrete is discharged; then pour from the reserved groove that has just been discharged until concrete is discharged from the next adjacent reserved groove; this is the sequence of operations. After the reserved grooves are filled with concrete, the connecting belts between the prefabricated slabs are cast in place. The cast-in-place concrete is covered with plastic film and cured.
CN202210940720.0A 2022-08-06 2022-08-06 A construction method for orthotropic composite bridge deck Active CN115110435B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210940720.0A CN115110435B (en) 2022-08-06 2022-08-06 A construction method for orthotropic composite bridge deck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210940720.0A CN115110435B (en) 2022-08-06 2022-08-06 A construction method for orthotropic composite bridge deck

Publications (2)

Publication Number Publication Date
CN115110435A true CN115110435A (en) 2022-09-27
CN115110435B CN115110435B (en) 2025-08-26

Family

ID=83334260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210940720.0A Active CN115110435B (en) 2022-08-06 2022-08-06 A construction method for orthotropic composite bridge deck

Country Status (1)

Country Link
CN (1) CN115110435B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007211552A (en) * 2006-02-13 2007-08-23 Sumitomo Mitsui Construction Co Ltd Continuous viaduct
CN101314935A (en) * 2008-07-17 2008-12-03 南京工业大学 A composite bridge deck
CN103114527A (en) * 2013-03-19 2013-05-22 南京工业大学 Orthotropic steel plate-composite hollow slab combined bridge deck structure
CN203144900U (en) * 2013-03-19 2013-08-21 南京工业大学 Orthotropic steel plate-composite hollow slab combined bridge deck structure
CN203890860U (en) * 2014-04-26 2014-10-22 郑州大学 N-shaped precast beam
CN108193597A (en) * 2018-03-13 2018-06-22 长沙慧桥科技有限公司 A kind of high-performance steel bridge floor structure
CN112160241A (en) * 2020-10-29 2021-01-01 西南交通大学 An orthotropic steel bridge deck fatigue reinforcement structure and its construction method
CN112627001A (en) * 2021-01-15 2021-04-09 太原理工大学 Steel plate concrete composite slab bridge
CN114411551A (en) * 2022-01-14 2022-04-29 中铁大桥局集团有限公司 A bridge deck structure and an express road maintenance construction technology

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007211552A (en) * 2006-02-13 2007-08-23 Sumitomo Mitsui Construction Co Ltd Continuous viaduct
CN101314935A (en) * 2008-07-17 2008-12-03 南京工业大学 A composite bridge deck
CN103114527A (en) * 2013-03-19 2013-05-22 南京工业大学 Orthotropic steel plate-composite hollow slab combined bridge deck structure
CN203144900U (en) * 2013-03-19 2013-08-21 南京工业大学 Orthotropic steel plate-composite hollow slab combined bridge deck structure
CN203890860U (en) * 2014-04-26 2014-10-22 郑州大学 N-shaped precast beam
CN108193597A (en) * 2018-03-13 2018-06-22 长沙慧桥科技有限公司 A kind of high-performance steel bridge floor structure
CN210458941U (en) * 2018-03-13 2020-05-05 湖南品智工程技术有限公司 High-performance steel bridge deck structure
CN112160241A (en) * 2020-10-29 2021-01-01 西南交通大学 An orthotropic steel bridge deck fatigue reinforcement structure and its construction method
CN112627001A (en) * 2021-01-15 2021-04-09 太原理工大学 Steel plate concrete composite slab bridge
CN114411551A (en) * 2022-01-14 2022-04-29 中铁大桥局集团有限公司 A bridge deck structure and an express road maintenance construction technology

Also Published As

Publication number Publication date
CN115110435B (en) 2025-08-26

Similar Documents

Publication Publication Date Title
CN107245934A (en) A kind of assembled steel profiled sheet concrete combined board small box girder
CN113481826B (en) Prefabricated assembled corrugated steel web plate combined box girder
CN110424242A (en) Assembled Wavelike steel webplate steel reinforced concrete composite beam bridge and construction method
CN104762871A (en) Prestressed concrete-steel tank beam bond beam continuous beam bridge
CN102704394A (en) Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure
CN106758856A (en) The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
CN113699876A (en) Pier is assembled in prefabricated of segment of vertical continuous band tenon fourth of twelve earthly branches structure
CN114592440A (en) Fabricated steel-concrete composite bridge superstructure and construction process thereof
CN109930484A (en) A kind of very-high performance deck structrue and its construction method
CN108316120A (en) It can rapidly-assembled precast bridge and its construction method
CN210086022U (en) Assembled single-box multi-chamber corrugated steel web box girder
CN112281663B (en) Construction method for widening connection of upper structures of new and old bridges
CN114960422A (en) An orthotropic bridge deck
CN211815592U (en) Prefabricated assembled composite slab structure
CN115305800B (en) A continuous composite small box girder bridge structure with corrugated steel webs and its construction method
CN215758474U (en) Assembled steel bridge of U-shaped section steel box girder
CN214737317U (en) Steel-concrete combined rigid frame bridge connected through slots
CN111733697A (en) Prefabricated Assembled Laminated Panel Construction
CN207958956U (en) A kind of assembly steel-concrete combination beam
CN114875785A (en) UHPC prefabricated bridge deck unit without temporary support, bridge deck and construction method thereof
CN205188792U (en) Prefabricated internal prestressing force steel and concrete composite simply supported girder bridge of assembling of fish belly wave form steel web
CN115110435A (en) Construction method of orthotropic combined bridge deck
CN219176337U (en) Ribbed composite board for tunnel lining reinforcement and tunnel lining reinforcing structure
CN219671054U (en) An integrally hoisted, prefabricated steel-concrete composite small box beam
CN216515070U (en) Prefabricated bridge deck structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant