Curtain wall fixing device and curtain wall construction method Download PDFInfo
- Publication number
- CN115059225A CN115059225A CN202210753620.7A CN202210753620A CN115059225A CN 115059225 A CN115059225 A CN 115059225A CN 202210753620 A CN202210753620 A CN 202210753620A CN 115059225 A CN115059225 A CN 115059225A
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- supporting
- fixing device
- connecting plate
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 40
- 238000009434 installation Methods 0.000 claims description 27
- 229910052782 aluminium Inorganic materials 0.000 claims description 13
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 10
- 239000010959 steel Substances 0.000 claims description 10
- 238000003466 welding Methods 0.000 claims description 8
- 229910001335 Galvanized steel Inorganic materials 0.000 claims description 7
- 239000008397 galvanized steel Substances 0.000 claims description 7
- 230000001154 acute effect Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 12
- 239000000463 material Substances 0.000 abstract description 6
- 238000009415 formwork Methods 0.000 abstract description 4
- 238000009435 building construction Methods 0.000 abstract description 2
- 238000011065 in-situ storage Methods 0.000 abstract 1
- 239000011521 glass Substances 0.000 description 7
- 238000005260 corrosion Methods 0.000 description 3
- 230000007797 corrosion Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000004321 preservation Methods 0.000 description 3
- 239000000126 substance Substances 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 239000011248 coating agent Substances 0.000 description 2
- 238000000576 coating method Methods 0.000 description 2
- 238000005520 cutting process Methods 0.000 description 2
- 229920001821 foam rubber Polymers 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 239000010935 stainless steel Substances 0.000 description 2
- 229910001220 stainless steel Inorganic materials 0.000 description 2
- 229910000838 Al alloy Inorganic materials 0.000 description 1
- 206010040007 Sense of oppression Diseases 0.000 description 1
- 239000000956 alloy Substances 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000001680 brushing effect Effects 0.000 description 1
- 239000003086 colorant Substances 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 229920001971 elastomer Polymers 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000004907 flux Effects 0.000 description 1
- 238000005246 galvanizing Methods 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 150000002739 metals Chemical class 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000008707 rearrangement Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000005341 toughened glass Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/885—Curtain walls comprising a supporting structure for flush mounted glazing panels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
The invention relates to the technical field of building construction, and discloses a curtain wall fixing device and a curtain wall construction method. A plurality of curtain stand are used for installing the curtain, and supporting component includes a plurality of support frames that set up with a plurality of curtain stand one-to-ones, and the one end of every support frame all is connected with the crossbeam of floor below, and the other end all is connected with the curtain stand that corresponds. The connecting assembly comprises a connecting piece and a first fastener, one end of the connecting piece is connected with the supporting frame, and the other end of the connecting piece is connected with the curtain wall upright post through the first fastener. According to the invention, an external hanging beam is not required to be cast in situ below the floor slab, and only the supporting frame is required to be arranged on the cross beam, so that the curtain wall construction process is simplified, a large amount of manpower and material resources can be saved, and the construction cost is reduced. And the support frame can regard as prefab direct mount, compares in cast-in-place outer beam of hanging, has saved formwork, has pour and has waited for the time that the concrete solidifies, and the efficiency of construction improves greatly, can effectively shorten construction period.
Description
Technical Field
The invention relates to the technical field of building construction, in particular to a curtain wall fixing device and a curtain wall construction method.
Background
The curtain wall is the exterior wall enclosure of the building, does not bear the weight, hangs like the curtain, so is also called as "curtain wall". The curtain wall is a light wall with decorative effect commonly used in modern large and high-rise buildings, and is composed of a panel and a supporting structure system, the curtain wall can have certain displacement capacity relative to a main structure or certain deformation capacity per se, the artistic effect is good, architects can design various shapes according to own requirements, can present different colors, coordinate with the surrounding environment, and cooperate with illumination and the like to enable the buildings to be integrated with the nature, so that the oppression feeling of the high-rise buildings is reduced.
In the prior art, most curtain walls are installed on outer boundary beams of a building through upright posts, but due to the special design requirements of part of building structures, the curtain walls cannot be arranged on the outer boundary beams and need to be arranged below inner floor slabs. The existing method is to cast a lower hanging beam on site below a floor slab to provide a fixed foundation for a stand column of a curtain wall, and the construction method is complex in process, needs to invest more manpower and material resources and is high in construction cost.
Therefore, a curtain wall fixing device and a curtain wall construction method are needed to solve the above problems.
Disclosure of Invention
Based on the above problems, the invention aims to provide a curtain wall fixing device and a curtain wall construction method, which have the advantages of simple construction steps, capability of realizing rapid installation of a curtain wall, low construction cost and capability of effectively shortening the construction period.
In order to achieve the purpose, the invention adopts the following technical scheme:
in one aspect, a curtain wall fixing device is provided, including:
the curtain wall upright posts are used for installing curtain walls;
the supporting assembly comprises a plurality of supporting frames, the supporting frames and the curtain wall stand columns are arranged in a one-to-one correspondence mode, one end of each supporting frame is connected with a cross beam below the floor slab, and the other end of each supporting frame is connected with the corresponding curtain wall stand column;
the connecting assembly comprises a connecting piece and a first fastener, one end of the connecting piece is connected with the supporting frame, and the other end of the connecting piece is connected with the curtain wall upright post through the first fastener.
As a preferable scheme of the curtain wall fixing device of the invention, the support frame comprises a first support beam and a second support beam which are arranged at an included angle, one end of the first support beam is connected with the cross beam, the other end of the first support beam is connected with the connecting piece, one end of the second support beam is connected with the cross beam, and the other end of the second support beam is connected with the first support beam.
As a preferable scheme of the curtain wall fixing device of the present invention, the curtain wall fixing device further includes a second fastener, the support frame further includes a first connecting plate and a second connecting plate, one end of the first support beam is connected to the first connecting plate, the other end of the first support beam is connected to the second connecting plate, the first connecting plate is fixedly connected to the cross beam through the second fastener, and the second connecting plate is fixedly connected to the connecting member.
As a preferable scheme of the curtain wall fixing device of the present invention, the curtain wall fixing device further includes a third fastener, the support frame further includes a third connecting plate, one end of the second support beam, which is far away from the first support beam, is connected to the third connecting plate, and the third connecting plate is fixedly connected to the cross beam through the third fastener.
In a preferred embodiment of the curtain wall fixing device according to the present invention, the first support beam and the first connection plate, the second support beam and the third connection plate, and the first support beam and the second support beam are welded to each other.
As a preferable scheme of the curtain wall fixing device, the connecting piece and the second connecting plate are in welded connection, the connecting piece is made of angle steel, and the first connecting plate and the second connecting plate are both made of galvanized steel plates.
As a preferable aspect of the curtain wall fixing device of the present invention, an included angle between the first support beam and the second support beam is an acute angle.
As a preferable scheme of the curtain wall fixing device of the invention, the support frame further comprises a third support beam, one end of the third support beam is connected with the curtain wall upright post, the other end of the third support beam is overhung, and the third support beam is used for mounting an aluminum veneer of the curtain wall.
As a preferred embodiment of the curtain wall fixing device of the present invention, the curtain wall fixing device further includes a supporting plate and an insulating layer disposed on the supporting plate, one end of the supporting plate is connected to the floor slab, the other end of the supporting plate is connected to the aluminum veneer of the curtain wall, and the insulating layer is located on one side of the supporting plate facing the supporting frame.
On the other hand, the curtain wall construction method is provided, the curtain wall fixing device is adopted for construction, and the method comprises the following steps:
s1, determining the size and the preset installation position of the support frame according to the installation position of the curtain wall;
s2, sequentially fixing the support frames on the cross beam according to the preset installation positions;
s3, mounting the connecting piece at one end of each support frame far away from the cross beam;
s4, fixing the curtain wall upright post and the corresponding connecting piece through the first fastener;
and S5, mounting the curtain wall on the curtain wall upright posts.
The invention has the beneficial effects that:
according to the curtain wall fixing device and the curtain wall construction method, when the curtain wall is installed below the floor slab, the preset installation position of the supporting frame on the cross beam is determined according to the position of the curtain wall, and the supporting frame with the corresponding size is manufactured. Then, a plurality of support frames are sequentially arranged on the cross beam, a connecting piece is arranged at one end, far away from the cross beam, of each support frame, and the curtain wall stand columns are fixedly connected with the connecting pieces through first fastening pieces, so that the curtain wall stand columns and the support frames form a fixed foundation of the curtain wall. And finally, installing the curtain walls on the curtain wall stand columns. A plurality of support frames can be flexibly arranged according to the shape of the curtain wall to adapt to the fixed position of the curtain wall upright post, the arc-shaped curtain wall and the curtain wall with various special-shaped trends can be installed, and the universality is stronger. The setting of connecting piece and first fastener can a plurality of curtain stand of easy to assemble, guarantees the joint strength of support frame and curtain stand to ensure the installation stability of curtain. In addition, the curtain wall fixing device does not need to cast an external hanging beam below a floor slab in a cast-in-place mode, and only needs to install the supporting frame on the cross beam, so that the curtain wall construction process is simplified, a large amount of manpower and material resources can be saved, and the construction cost is reduced. And the support frame can regard as prefab direct mount, compares in cast-in-place outer beam of hanging, has saved formwork, has pour and has waited for the time that the concrete solidifies, and the efficiency of construction improves greatly, can effectively shorten construction period.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings used in the description of the embodiments of the present invention will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the contents of the embodiments of the present invention and the drawings without creative efforts.
FIG. 1 is a cross-sectional view of a curtain wall attachment apparatus for attaching a curtain wall to a beam in accordance with an embodiment of the present invention;
FIG. 2 is an enlarged view of a portion of FIG. 1 at A;
fig. 3 is a partially enlarged view at B in fig. 1.
In the figure:
1-curtain wall upright post; 2-a support frame; 3-connecting the components; 4-a second fastener; 5-a third fastener; 6-branch
A supporting plate; 7-insulating layer; 8-mounting corner connectors; 9-an adaptor;
21-a first support beam; 22-a second support beam; 23-a first connection plate; 24-a second connecting plate; 25-third
A connecting plate; 26-a third support beam;
31-a connector; 311-mounting holes; 32-a first fastener; 33-a gasket;
100-curtain wall; 101-aluminum veneer; 102-a glass plate; 103-decorative strips;
200-a cross beam; 300-floor.
Detailed Description
In order to make the technical problems solved, technical solutions adopted and technical effects achieved by the present invention clearer, the technical solutions of the embodiments of the present invention will be described in further detail below with reference to the accompanying drawings, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and the like are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. Wherein the terms "first position" and "second position" are two different positions.
In the description of the present invention, it should be noted that unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection or a removable connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in a specific case to those of ordinary skill in the art.
As shown in fig. 1, the present embodiment provides a curtain wall fixing apparatus that can be used to install a curtain wall 100 under a floor 300. The curtain wall fixing device comprises a plurality of curtain wall stand columns 1, a supporting assembly and a connecting assembly 3.
Wherein, a plurality of curtain stand 1 are used for installing curtain 100, and supporting component includes a plurality of support frames 2, a plurality of support frames 2 and a plurality of curtain stand 1 one-to-one setting, and the one end of every support frame 2 all is connected with crossbeam 200 of floor 300 below, and the other end all is connected with corresponding curtain stand 1. The connecting assembly 3 comprises a connecting piece 31 and a first fastener 32, one end of the connecting piece 31 is connected with the support frame 2, and the other end of the connecting piece is connected with the curtain wall upright post 1 through the first fastener 32.
According to the curtain wall fixing device provided by the embodiment, when the curtain wall 100 is installed below the floor 300, the preset installation position of the support frame 2 on the cross beam 200 is determined according to the position of the curtain wall 100, and the support frame 2 with the corresponding size is manufactured. Then, a plurality of support frames 2 are sequentially installed on the cross beam 200, a connecting piece 31 is installed at one end of each support frame 2 far away from the cross beam 200, and the curtain wall upright 1 is fixedly connected with the connecting piece 31 through a first fastener 32, so that the plurality of curtain wall uprights 1 and the plurality of support frames 2 form a fixed foundation of the curtain wall 100. Finally, the curtain wall 100 is installed on the plurality of curtain wall uprights 1. The support frames 2 can be flexibly arranged according to the shape of the curtain wall 100 to adapt to the fixed position of the curtain wall upright post 1, the arc-shaped curtain wall 100 and the curtain walls 100 with various special-shaped trends can be installed, and the universality is stronger. The setting of connecting piece 31 and first fastener 32 can a plurality of curtain stand 1 of easy to assemble, guarantees support frame 2 and curtain stand 1's joint strength to ensure the installation stability of curtain 100. In addition, this curtain fixing device need not to hang the roof beam outside cast-in-place below floor 300, only need on crossbeam 200 erection bracing frame 2 can, simplified curtain 100 construction processes, can save a large amount of manpower and materials, reduce construction cost. And support frame 2 can regard as prefab direct mount, compares in cast-in-place outer beam of hanging, has saved formwork, has pour and wait for the time that the concrete solidifies, and the efficiency of construction improves greatly, can effectively shorten construction period.
Alternatively, referring to fig. 1, the supporting frame 2 includes a first supporting beam 21 and a second supporting beam 22 arranged at an included angle, one end of the first supporting beam 21 is connected to the cross beam 200, the other end is connected to the connecting member 31, one end of the second supporting beam 22 is connected to the cross beam 200, and the other end is connected to the first supporting beam 21. In this embodiment, the included angle between the first support beam 21 and the second support beam 22 is an acute angle. The first supporting beam 21 is parallel to the ground and extends outwards in an overhanging mode, one end, far away from the cross beam 200, of the second supporting beam 22 is fixedly connected with the overhanging end of the first supporting beam 21, and the first supporting beam 21 and the second supporting beam are V-shaped. After the first supporting beam 21 and the second supporting beam 22 are fixed on the cross beam 200, a triangular supporting structure can be formed, the supporting is more stable, and the installation stability of the curtain wall 100 can be ensured.
Furthermore, the first supporting beam 21 and the second supporting beam 22 are connected by welding, so that the connection is firm, the site construction is convenient, and the operation is easy. Preferably, the first support beam 21 and the second support beam 22 are made of steel, i.e. solid square steel. The steel flux has sufficient strength, can guarantee the structural strength of support frame 2 to improve the installation stability of curtain wall 100. The length of the steel tube is determined according to the distance between the spot beam 200 and the fixed position of the curtain wall 100, and the steel tube with the proper length can be cut on the spot through a cutting device. The cross-sectional dimension of the steel tube is selected according to the load bearing requirement, as long as the steel tube can bear the weight of the curtain wall 100, and is exemplarily 150mm × 100mm × 5 mm.
Optionally, referring to fig. 1, the curtain wall fixing device further includes a second fastening member 4, the support frame 2 further includes a first connecting plate 23 and a second connecting plate 24, one end of the first support beam 21 is connected to the first connecting plate 23, the other end of the first support beam is connected to the second connecting plate 24, the first connecting plate 23 is fixedly connected to the cross beam 200 through the second fastening member 4, and the second connecting plate 24 is fixedly connected to the connecting member 31. The first connecting plate 23 is provided so that the first support beam 21 can be conveniently fixed to the cross beam 200, and the second connecting plate 24 is provided so that the first support beam 21 can be conveniently connected to the connecting member 31. During specific installation, the first connecting plate 23 is fixed on the cross beam 200 through the second fastener 4, then one end of the first supporting beam 21 is connected with the first connecting plate 23, the second connecting plate 24 is installed at the other end of the first supporting beam 21, and the fixed connecting piece 31 is installed on the second connecting plate 24 to provide a fixed foundation for installation of the curtain wall upright 1.
Optionally, the first support beam 21 and the first connecting plate 23 and the second connecting plate 24 are welded, and the connecting member 31 and the second connecting plate 24 are also welded. The welding process is simple to operate and easy to realize, and the connection strength between every two welding processes can be ensured. Preferably, the connecting member 31 is made of angle steel, and has sufficient strength to ensure the connection strength between the first support beam 21 and the curtain wall upright 1. The first connecting plate 23 and the second connecting plate 24 are made of galvanized steel plates, the galvanized steel plates are good in corrosion resistance, durable and sufficient in structural strength, the galvanizing process is quicker than other coating construction methods, and the time for brushing a coating on site can be saved. The second fastening piece 4 is preferably a stainless steel chemical anchor bolt which has strong anchoring force, is embedded as well, has no expansion stress, is installed quickly and can save the construction time. Illustratively, the second fastening members 4 are provided in six, and both ends of the first connection plate 23 are fixed using three second fastening members 4, respectively. In other embodiments, the number of second fastening members 4 may also be increased or decreased adaptively.
In this embodiment, curtain stand 1 is formed by the preparation of aluminum alloy material, can set up the rubber pad between connecting piece 31 and the curtain stand 1 for prevent to produce chemical corrosion between the different metals, ensure the stability of being connected between curtain stand 1 and the support frame 2, prolong the life of curtain stand 1 simultaneously.
Optionally, referring to fig. 1 and fig. 2, the connecting assembly 3 further includes a gasket 33, the connecting member 31 is provided with a mounting hole 311, and the curtain wall upright 1 is also provided with a through hole at a corresponding position. The first fastening member 32 is preferably a bolt and a nut, and the washer 33 is interposed between the nut of the bolt and the connecting member 31. When the connecting piece 31 is fixed with the curtain wall upright post 1, the bolt sequentially penetrates through the gasket 33, the mounting hole 311 and the through hole and then is connected with the nut. The arrangement of the spacer 33 can increase the contact area between the nut of the bolt and the connecting member 31, and increase the connecting strength. Preferably, the mounting hole 311 is a bar-shaped hole for finely tuning the mounting position of the curtain wall upright post 1, and the mounting hole 311 and the through hole are not aligned when the mounting is performed, so that the mounting efficiency is improved.
Optionally, referring to fig. 1, the curtain wall fixing device further includes a third fastener 5, the support frame 2 further includes a third connecting plate 25, an end of the second support beam 22 away from the first support beam 21 is connected to the third connecting plate 25, and the third connecting plate 25 is fixedly connected to the cross beam 200 through the third fastener 5. The setting of third connecting plate 25 makes second supporting beam 22 can conveniently fix on crossbeam 200, during specific installation, fix third connecting plate 25 on crossbeam 200 through third fastener 5 earlier, then be connected second supporting beam 22's one end and third connecting plate 25, second supporting beam 22's the other end and the overhanging end of first supporting beam 21 are connected to increase the joint strength between first supporting beam 21 and the crossbeam 200, provide firm basis for the installation of curtain stand 1.
Optionally, the second support beam 22 and the third connecting plate 25, and the first support beam 21 and the second support beam 22 are welded. The welding process is simple to operate and easy to realize, and the connection strength between every two welding processes can be ensured. Preferably, the third connecting plate 25 is made of a galvanized steel sheet, which has good corrosion resistance, is durable, can adapt to complex environmental conditions, and has sufficient structural strength. Further, in this embodiment, the third fastening member 5 is also a stainless steel chemical anchor bolt, and the anchoring force is strong, so that the connection strength between the second supporting beam 22 and the cross beam 200 can be ensured, and the installation is fast, so that the construction time can be saved.
Optionally, referring to fig. 1 and 3, the support frame 2 further comprises a third support beam 26, one end of the third support beam 26 is connected to the curtain wall upright 1, and the other end of the third support beam 26 is cantilevered outwards, and the third support beam 26 is used for mounting the aluminum veneer 101 of the curtain wall 100. The aluminum veneer 101 is used for shielding the floor 300, and the decorative attractiveness is improved. In this embodiment, the third supporting beam 26 is made of galvanized steel, and has sufficient structural strength, and the aluminum single plate 101 and the third supporting beam 26 may be connected and fixed by a ceiling corner brace.
Referring to fig. 3, an end of the aluminum single plate 101 is connected with an adaptor 9, an upper portion of the adaptor 9 is fixedly connected with the third supporting beam 26, and one end of the adaptor 9, which is far away from the aluminum single plate 101, is fixedly connected with the curtain wall upright post 1 through an installation angle brace 8. The adaptor 9 is provided with a U-shaped groove with a downward opening, the top end of the glass plate 102 of the curtain wall 100 is inserted into the U-shaped groove, and a gap between the U-shaped groove and the glass plate 102 is filled with foam rubber for sealing.
Optionally, referring to fig. 1 and 3, the curtain wall fixing device further includes a supporting plate 6 and an insulating layer 7 disposed on the supporting plate 6, one end of the supporting plate 6 is connected to the floor 300, the other end is connected to the aluminum veneer 101 of the curtain wall 100, and the insulating layer 7 is located on one side of the supporting plate 6 facing the supporting frame 2. Specifically, the lower end of the support plate 6 is bent toward the adaptor 9 and is fixedly connected with the adaptor 9, and the top end of the support plate 6 is fixed on the floor 300 by an anchor bolt. The support plate 6 is preferably a galvanized steel plate, which can play a role in fire prevention. The heat preservation performance in the building can be improved to the setting of heat preservation 7, and the preferred fire prevention material of heat preservation 7 improves the security performance of building.
The embodiment also provides a curtain wall construction method, which adopts the curtain wall fixing device for construction and specifically comprises the following steps:
s1, determining the size and the preset installation position of the support frame 2 according to the installation position of the curtain wall 100;
s2, sequentially fixing a plurality of support frames 2 on the cross beam 200 according to the preset installation positions;
s3, installing a connecting piece 31 at one end of each support frame 2 far away from the cross beam 200;
s4, fixing the curtain wall upright post 1 and the corresponding connecting piece 31 through the first fastener 32;
and S5, mounting the curtain wall 100 on the curtain wall upright posts 1.
In step S1, the first and second support beams 21 and 22 of the support frame 2 are sized in length according to the distance between the spot beam 200 and the curtain wall 100 fixing position, and the first and second support beams 21 and 22 of the corresponding lengths may be cut in the spot by a cutting apparatus. The preset installation position of the support frame 2 is arranged according to the shape of the curtain wall 100.
In step S2, when each supporting frame 2 is fixed, the first connecting plate 23 may be fixed on the cross beam 200 by the plurality of second fasteners 4, and then the first supporting beam 21 may be welded to the first connecting plate 23 by using a welding device. Then, the third connecting plate 25 is fixed to the cross member 200 by the third fastening member 5, and one end of the second support beam 22 is welded to the third connecting plate 25 and the other end is welded to the top surface of the first support beam 21. Finally, the second connecting plate 24 is welded to the overhanging end portion of the first support beam 21 (alternatively, the second connecting plate 24 and the first support beam 21 may be welded to each other on the ground, and then the first support beam 21 and the first connecting plate 23 fixed to the cross beam 200 are welded to each other).
In step S3, one connecting piece 31 is welded on each second connecting plate 24 on each first support beam 21 by a welding device to prepare for installation of the curtain wall pillar 1.
In step S4, the curtain wall uprights 1 are fixed to the corresponding connecting members 31 by the first fasteners 32, so that the installation of the curtain wall uprights 1 is completed, and then a third support beam 26 is welded to each curtain wall upright 1 to prepare for the installation of the aluminum veneers 101 of the curtain wall 100.
In step S5, the adaptor 9 is welded to the third support beam 26, and the adaptor 9 is connected to the curtain wall pillar 1. Then, the supporting plate 6 is connected between the floor 300 and the adaptor 9, the insulating layer 7 is arranged on the rear side of the supporting plate 6, and the aluminum veneer 101 is mounted on the third supporting beam 26. Then, the glass plate 102 of the curtain wall 100 (the glass plate 102 is usually hollow toughened glass) is installed, the upper end of the glass plate 102 is inserted into the U-shaped groove of the adaptor 9, and is fixed by filling foam rubber. Finally, the installation of the curtain wall 100 is completed by installing the decorative strip 103 on the side of the glass plate 102 opposite to the support frame 2, and the decorative strip 103 can increase the aesthetic property of the curtain wall 100.
The curtain wall construction method provided by the embodiment has the advantages that the cast-in-place external hanging beam below the floor slab 300 is not needed, the construction process of the curtain wall 100 is simplified, a large amount of manpower and material resources can be saved, and the construction cost is reduced. And support frame 2 can regard as prefab direct mount, compares in cast-in-place outer beam of hanging, has saved formwork, has pour and wait for the time that the concrete solidifies, and the efficiency of construction improves greatly, can effectively shorten construction period. Meanwhile, the construction method can install the arc-shaped curtain wall 100 and the curtain walls 100 with various special-shaped trends by flexibly arranging the positions of the plurality of support frames 2, and the universality is stronger.
It is to be noted that the foregoing is only illustrative of the preferred embodiments of the present invention and the technical principles employed. It will be understood by those skilled in the art that the present invention is not limited to the particular embodiments illustrated herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the invention. Therefore, although the present invention has been described in greater detail by the above embodiments, the present invention is not limited to the above embodiments, and may include other equivalent embodiments without departing from the spirit of the present invention, and the scope of the present invention is determined by the scope of the appended claims.
Claims (10)
1. A curtain wall fixing device is characterized by comprising:
the curtain wall comprises a plurality of curtain wall uprights (1), wherein the curtain wall uprights (1) are used for mounting a curtain wall (100);
the supporting assembly comprises a plurality of supporting frames (2), the supporting frames (2) are arranged in one-to-one correspondence with the curtain wall upright posts (1), one end of each supporting frame (2) is connected with a cross beam (200) below a floor (300), and the other end of each supporting frame is connected with the corresponding curtain wall upright post (1);
connecting assembly (3), including connecting piece (31) and first fastener (32), the one end of connecting piece (31) with support frame (2) are connected, and the other end passes through first fastener (32) with curtain wall pillar (1) is connected.
2. The curtain wall fixing device according to claim 1, wherein the supporting frame (2) comprises a first supporting beam (21) and a second supporting beam (22) which are arranged at an included angle, one end of the first supporting beam (21) is connected with the cross beam (200), the other end of the first supporting beam is connected with the connecting piece (31), one end of the second supporting beam (22) is connected with the cross beam (200), and the other end of the second supporting beam is connected with the first supporting beam (21).
3. The curtain wall fixing device according to claim 2, characterized in that the curtain wall fixing device further comprises a second fastener (4), the supporting frame (2) further comprises a first connecting plate (23) and a second connecting plate (24), one end of the first supporting beam (21) is connected with the first connecting plate (23), the other end of the first supporting beam is connected with the second connecting plate (24), the first connecting plate (23) is fixedly connected with the cross beam (200) through the second fastener (4), and the second connecting plate (24) is fixedly connected with the connecting piece (31).
4. The curtain wall fixing device according to claim 3, characterized in that the curtain wall fixing device further comprises a third fastener (5), the supporting frame (2) further comprises a third connecting plate (25), one end of the second supporting beam (22) far away from the first supporting beam (21) is connected with the third connecting plate (25), and the third connecting plate (25) is fixedly connected with the cross beam (200) through the third fastener (5).
5. The curtain wall fixing device according to claim 4, characterized in that the welding is performed between the first supporting beam (21) and the first and second connecting plates (23, 24), between the second supporting beam (22) and the third connecting plate (25), and between the first supporting beam (21) and the second supporting beam (22).
6. The curtain wall fixing device according to claim 3, characterized in that the connecting piece (31) is in welded connection with the second connecting plate (24), the connecting piece (31) is made of angle steel, and the first connecting plate (23) and the second connecting plate (24) are both made of galvanized steel.
7. Curtain wall fixing device according to claim 2, characterized in that the angle between the first support beam (21) and the second support beam (22) is acute.
8. Curtain wall fixing device according to any one of claims 1 to 7, characterized in that the support frame (2) further comprises a third support beam (26), one end of the third support beam (26) is connected to the curtain wall upright (1), and the other end is cantilevered outwards, and the third support beam (26) is used for mounting an aluminum veneer (101) of the curtain wall (100).
9. The curtain wall fixing device according to any one of claims 1 to 7, further comprising a support plate (6) and an insulating layer (7) disposed on the support plate (6), wherein one end of the support plate (6) is connected to the floor (300), the other end is connected to the aluminum veneer (101) of the curtain wall (100), and the insulating layer (7) is disposed on a side of the support plate (6) facing the support frame (2).
10. A curtain wall construction method using the curtain wall fixing device as claimed in any one of claims 1 to 9 for construction, comprising the steps of:
s1, determining the size and the preset installation position of the support frame (2) according to the installation position of the curtain wall (100);
s2, sequentially fixing the support frames (2) on the cross beam (200) according to the preset installation positions;
s3, mounting the connecting piece (31) at one end of each support frame (2) far away from the cross beam (200);
s4, fixing the curtain wall upright post (1) and the corresponding connecting piece (31) through the first fastener (32);
s5, mounting the curtain wall (100) on the curtain wall upright posts (1).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210753620.7A CN115059225A (en) | 2022-06-28 | 2022-06-28 | Curtain wall fixing device and curtain wall construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210753620.7A CN115059225A (en) | 2022-06-28 | 2022-06-28 | Curtain wall fixing device and curtain wall construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115059225A true CN115059225A (en) | 2022-09-16 |
Family
ID=83204424
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210753620.7A Pending CN115059225A (en) | 2022-06-28 | 2022-06-28 | Curtain wall fixing device and curtain wall construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115059225A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117027246A (en) * | 2023-07-11 | 2023-11-10 | 上海强荣建设集团有限公司 | A kind of construction technology of semi-unit aluminum plate curtain wall |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE4423255A1 (en) * | 1994-07-02 | 1996-01-04 | C & N Dankert Naturstein Gmbh | Method for mounting rear ventilated facade panels |
| CN106917463A (en) * | 2017-05-04 | 2017-07-04 | 四川盛邦建设股份有限公司 | Curtain wall construction and building |
| CN106969431A (en) * | 2017-06-02 | 2017-07-21 | 安徽天澄钢构有限公司 | A kind of air-conditioning steel structure support |
| CN111119386A (en) * | 2020-01-14 | 2020-05-08 | 中铁建工集团有限公司 | Lower sitting type unit curtain wall for inner layer of balcony |
| CN112411824A (en) * | 2020-11-23 | 2021-02-26 | 中铁八局集团建筑工程有限公司 | Installation structure and method for inner corner of curtain wall |
-
2022
- 2022-06-28 CN CN202210753620.7A patent/CN115059225A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE4423255A1 (en) * | 1994-07-02 | 1996-01-04 | C & N Dankert Naturstein Gmbh | Method for mounting rear ventilated facade panels |
| CN106917463A (en) * | 2017-05-04 | 2017-07-04 | 四川盛邦建设股份有限公司 | Curtain wall construction and building |
| CN106969431A (en) * | 2017-06-02 | 2017-07-21 | 安徽天澄钢构有限公司 | A kind of air-conditioning steel structure support |
| CN111119386A (en) * | 2020-01-14 | 2020-05-08 | 中铁建工集团有限公司 | Lower sitting type unit curtain wall for inner layer of balcony |
| CN112411824A (en) * | 2020-11-23 | 2021-02-26 | 中铁八局集团建筑工程有限公司 | Installation structure and method for inner corner of curtain wall |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117027246A (en) * | 2023-07-11 | 2023-11-10 | 上海强荣建设集团有限公司 | A kind of construction technology of semi-unit aluminum plate curtain wall |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110106981B (en) | Assembled steel structure building and construction process thereof | |
| CN111155681B (en) | Steel concrete composite connection multilayer prefabricated section steel concrete shear wall structure and preparation and construction method thereof | |
| CN115059225A (en) | Curtain wall fixing device and curtain wall construction method | |
| CN211007158U (en) | Prefabricated self-insulation concrete shear wall system | |
| CN215858373U (en) | Prefabricated shear wall of assembly type structure | |
| CN116065741A (en) | UHPC hanging plate glass combined curtain wall structure and construction method thereof | |
| CN214461592U (en) | Assembled peripheral wall panel of steel structure frame | |
| CN217782474U (en) | Assembled heat-insulating supporting wallboard unit | |
| CN116752670B (en) | A kind of overhanging eaves aluminum plate curtain wall structure and construction method thereof | |
| CN218562657U (en) | Steel construction assembled outer surrounding ALC wallboard installation node | |
| CN115341684B (en) | Externally hung transverse sandwich wallboard structure for bearing windows and house building | |
| CN220285061U (en) | Firewall mounting structure | |
| CN220184076U (en) | Fixing base for construction of large-span cable bridge | |
| CN222252884U (en) | Beam column connection structure with exterior finishing | |
| CN223468905U (en) | Building outer wall assembly wallboard | |
| CN112227566A (en) | Construction method of prefabricated house structure system based on composite heat-insulation wallboard | |
| CN217711222U (en) | Detachable wall body of curtain wall of elevated station | |
| CN219710679U (en) | Back-bolt type dry-hanging stone corner connection structure | |
| CN116127805B (en) | A design method for a fireproof and noise-reducing wall and its structure for a main transformer. | |
| CN218265122U (en) | Fire control vestibule bottom sprag device | |
| CN223482012U (en) | Door opening curtain wall mounting steel truss structure | |
| CN219196381U (en) | Construction structure is articulated to peripheral backplate | |
| CN223468944U (en) | A lintel supporting structure for curtain wall | |
| US20240200338A1 (en) | Prefab Panel, Modular Facade, and Mounting Method Thereof | |
| CN216740291U (en) | Cascade formula building curtain convenient to installation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220916 |