CN115013057B - A new type of rapidly constructed coal mine closed wall and its construction technology - Google Patents
A new type of rapidly constructed coal mine closed wall and its construction technology Download PDFInfo
- Publication number
- CN115013057B CN115013057B CN202210330103.9A CN202210330103A CN115013057B CN 115013057 B CN115013057 B CN 115013057B CN 202210330103 A CN202210330103 A CN 202210330103A CN 115013057 B CN115013057 B CN 115013057B
- Authority
- CN
- China
- Prior art keywords
- eps module
- coal mine
- steel bars
- roadway
- wall body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F11/00—Rescue devices or other safety devices, e.g. safety chambers or escape ways
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B30/00—Energy efficient heating, ventilation or air conditioning [HVAC]
- Y02B30/90—Passive houses; Double facade technology
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- Emergency Management (AREA)
- Pulmonology (AREA)
- Building Environments (AREA)
Abstract
Description
技术领域Technical field
本发明涉及煤矿临时和永久密闭墙技术领域,具体地说是一种快速构筑的新型煤矿密闭墙及其施工工艺。The present invention relates to the technical field of temporary and permanent sealed walls in coal mines, specifically a new type of rapidly constructed coal mine sealed wall and its construction technology.
背景技术Background technique
煤矿井下构筑的临时和永久密闭墙是矿井主要的通风构筑物及封闭火区的重要工程。目前,煤矿井下构筑的临时和永久密闭墙主要为砖石结构和全混凝土结构。砖石结构和混凝土结构的密闭墙构筑周期长达一周,所需墙体材料重量大,运输困难,且构筑工序复杂,工人劳动作业时间长。砖石和混凝土结构墙体,为全刚性结构,强度大。巷道来压时,容易损坏墙体,且重新修复墙体较为困难,煤矿易出现火区封闭不严和瓦斯异常涌出的危险情况。Temporary and permanent sealing walls constructed underground in coal mines are the main ventilation structures in mines and important projects for sealing fire zones. At present, the temporary and permanent closed walls constructed underground in coal mines are mainly masonry structures and all-concrete structures. The construction period of closed walls of masonry and concrete structures is as long as one week. The required wall materials are heavy and difficult to transport. The construction process is complicated and workers work for a long time. The masonry and concrete structural walls are fully rigid structures with high strength. When the tunnel is under pressure, the wall is easily damaged and it is difficult to repair the wall. Coal mines are prone to dangerous situations such as lax sealing of the fire area and abnormal gas outflow.
因此,煤矿井下如何能够既快速和高效的构筑稳定性好的临时和永久密闭墙,保证煤矿的安全生产工作;又能节省煤矿的人力、物力、财力投入成为科研工作者亟待解决的问题。Therefore, how to quickly and efficiently build temporary and permanent sealing walls with good stability underground in coal mines to ensure the safe production of coal mines; and how to save human, material and financial investment in coal mines has become an urgent problem for scientific researchers.
发明内容Contents of the invention
本发明针对上述现有技术存在的构筑周期长,材料运输困难,工人劳动作业时间长,墙体结构稳定性差,破坏后修复困难等问题,提供一种快速构筑的新型煤矿密闭墙及其施工工艺。The present invention aims at the problems existing in the above-mentioned prior art such as long construction period, difficulty in material transportation, long working hours for workers, poor stability of the wall structure, and difficulty in repairing after damage, and provides a new type of rapidly constructed coal mine closed wall and its construction technology. .
本发明的一种快速构筑的新型煤矿密闭墙及其施工工艺,包括巷道顶板(1)、巷道底板(2)、巷道两帮(3)、凹槽(4)、交叉钢筋(5)和EPS模块墙体(6);封闭区里侧所述EPS模块墙体(6)表面喷涂有高密度防火阻燃高分子材料的内防护涂层(7);封闭区外侧所述EPS模块墙体(6)表面按照顺序喷涂有膨胀玻化微珠层(8)、粘接砂浆层(9)、抗裂网格布(10)、抹面砂浆层(11)和外喷涂层(12);所述的一种快速构筑的新型煤矿密闭墙按照以下过程进行施工:The invention provides a new type of rapidly constructed coal mine closed wall and its construction technology, which includes a tunnel roof (1), a tunnel bottom plate (2), two gangways of the tunnel (3), a groove (4), a cross steel bar (5) and EPS. The module wall (6); the EPS module wall (6) on the inside of the enclosed area is sprayed with an inner protective coating (7) of high-density fireproof and flame-retardant polymer material; the EPS module wall on the outside of the enclosed area ( 6) The surface is sprayed in sequence with an expanded vitrified microbead layer (8), an adhesive mortar layer (9), an anti-crack mesh cloth (10), a plastering mortar layer (11) and an outer spray layer (12); as described A new type of rapidly constructed coal mine closed wall is constructed according to the following process:
第一阶段:在需要设置密闭墙体的巷道顶板(1)、巷道底板(2)和巷道两帮(3)开凿深度为30cm的凹槽(4);The first stage: dig grooves (4) with a depth of 30cm in the tunnel roof (1), tunnel floor (2) and tunnel sides (3) where airtight walls need to be installed;
第二阶段:根据设立密闭墙处的巷道断面形状,将不同种类、不同规格、不同形状的EPS模块体(13)插入预留的纵向钢筋(14),通过凹凸卡扣(1305)或者接插口(1302)固定,然后,在钢筋卡槽(1306)内放置横向钢筋(15),形成交叉钢筋(5);The second stage: According to the cross-sectional shape of the tunnel where the closed wall is set up, insert EPS modules (13) of different types, specifications, and shapes into the reserved longitudinal steel bars (14), and use concave and convex buckles (1305) or sockets to (1302) is fixed, and then, the transverse steel bars (15) are placed in the steel bar slots (1306) to form cross steel bars (5);
第三阶段:在形成的EPS模具墙体(6)内,浇筑混泥土(16)即可形成软—硬—软形式的坚固墙体;The third stage: in the formed EPS mold wall (6), pour concrete (16) to form a solid wall in the form of soft-hard-soft;
第四阶段:在封闭区里侧EPS模块墙体(6)表面喷涂高密度防火阻燃高分子材料的内防护涂层(7),封闭区外侧EPS模块墙体(6)表面按照顺序喷涂膨胀玻化微珠层(8)、粘接砂浆层(9)、抗裂网格布(10)、抹面砂浆层(11)和外喷涂层(12)。The fourth stage: Spray the inner protective coating (7) of high-density fireproof and flame-retardant polymer material on the surface of the EPS module wall (6) inside the enclosed area, and spray and expand the surface of the EPS module wall (6) outside the enclosed area in sequence. Vitrified microbead layer (8), bonding mortar layer (9), anti-crack mesh cloth (10), plastering mortar layer (11) and external spray layer (12).
所述的EPS模块体(13)用可发性珠粒加热发泡,通过工厂标准化生产设备一次成型制得的具有闭孔结构的泡沫塑料型材或构件,两侧保温板(1301)厚度为6cm,通过活动肋板连接(1303),中间有13cm的空隙。The EPS module body (13) is heated and foamed with expandable beads, and is a foam plastic profile or component with a closed cell structure that is formed in one step by factory standardized production equipment. The thickness of the insulation boards (1301) on both sides is 6cm. , connected through movable ribs (1303), with a 13cm gap in the middle.
所述的EPS模块体(13)构件上,上下边均匀分布有接插口(1302),部分EPS模块体(13)构件左右两边有凹凸卡扣(1305)、内外表面有均匀分布的燕尾槽(1304),钢筋卡槽(1306)位于活动肋板(1303)上。The described EPS module body (13) component has sockets (1302) evenly distributed on the upper and lower sides. Some EPS module body (13) components have concave and convex buckles (1305) on the left and right sides, and evenly distributed dovetail grooves (1305) on the inner and outer surfaces. 1304), the steel bar slot (1306) is located on the movable floor plate (1303).
所述的交叉钢筋(5)中的纵向钢筋(14)和横向钢筋(15)通过细钢丝连接固定,且长度均需延伸至煤矿巷道顶板(1)、巷道底板(2)和巷道两帮(3)内。The longitudinal steel bars (14) and transverse steel bars (15) in the cross steel bars (5) are connected and fixed by thin steel wires, and their lengths need to extend to the coal mine tunnel roof (1), the tunnel bottom plate (2) and the two sides of the tunnel ( 3) Inside.
所述的EPS模块墙体(6)每搭接三层EPS模块体(13)浇筑混凝土(16)一次。The EPS module wall (6) is poured with concrete (16) every time it overlaps three layers of EPS module bodies (13).
所述的粘接砂浆层(9)喷涂厚度为0.5cm。The spraying thickness of the bonding mortar layer (9) is 0.5cm.
所述的抹面砂浆层(11)喷涂厚度为0.8cm。The spraying thickness of the plastering mortar layer (11) is 0.8cm.
本发明的有益效果:本发明提供的一种快速构筑的新型煤矿密闭墙及其施工工艺,打破原始的砖石和混凝土密闭墙结构,提出使用重量较轻,造价更低的EPS模块体,采用搭积木式的简单施工工艺,构筑了软—硬—软式的临时或永久EPS模块墙体。该技术方案构筑的临时或永久密闭墙稳定性较高,能够有效的卸除矿井来压的破坏力,隔热密封性能优异,每平米造价相对于砖石结构节省200元;且采用上述的施工工艺,能够将密闭墙的构筑时长缩短至一个工作班(8小时以内),大大节省了煤矿的人力、物力和财力投入。Beneficial effects of the present invention: The present invention provides a new type of rapidly constructed coal mine sealed wall and its construction technology, which breaks the original masonry and concrete sealed wall structure and proposes the use of EPS modules with lighter weight and lower cost. The simple construction technology of building blocks constructs a soft-hard-soft temporary or permanent EPS module wall. The temporary or permanent closed walls constructed by this technical solution have high stability, can effectively remove the destructive force of mine pressure, have excellent heat insulation and sealing performance, and save 200 yuan per square meter in cost compared to masonry structures; and the above-mentioned construction is adopted The technology can shorten the construction time of the airtight wall to one working shift (within 8 hours), which greatly saves the coal mine’s human, material and financial investment.
附图说明Description of the drawings
图1是本发明提供的一种快速构筑的新型煤矿密闭墙整体结构示意图Figure 1 is a schematic diagram of the overall structure of a new type of rapidly constructed coal mine closed wall provided by the present invention.
图2是图1的A—A剖面图Figure 2 is a cross-sectional view along line A-A in Figure 1
图3是凹卡扣和凸卡扣EPS模块体的连接示意图Figure 3 is a schematic diagram of the connection between the concave buckle and the convex buckle EPS module body.
图4是不同形状EPS模块体结构示意图Figure 4 is a schematic diagram of the structure of EPS modules of different shapes.
图5是单个EPS模块体与横向钢筋连接示意图Figure 5 is a schematic diagram of the connection between a single EPS module and transverse steel bars.
图中:1-巷道顶板;2-巷道底板;3-巷道两帮;4-凹槽;5-交叉钢筋;6-EPS模块墙体;7-内防护涂层;8-膨胀玻化微珠层;9-粘接砂浆层;10-抗裂网格布;11-抹面砂浆层;12-外喷涂层;13-EPS模块体;1301-两侧保温板;1302-接插口;1303-活动肋板;1304-燕尾槽;1305-凹凸卡扣;1306-钢筋卡槽;14-纵向钢筋;15-横向钢筋;16-混凝土。In the picture: 1-tunnel roof; 2-tunnel floor; 3-two sides of the tunnel; 4-grooves; 5-cross steel bars; 6-EPS module wall; 7-inner protective coating; 8-expanded vitrified microbeads layer; 9-bonding mortar layer; 10-anti-crack mesh cloth; 11-surface mortar layer; 12-external spray coating; 13-EPS module body; 1301-insulation panels on both sides; 1302-socket; 1303-movable Rib plate; 1304-dovetail groove; 1305-concave and convex buckle; 1306-reinforcement bar slot; 14-longitudinal steel bar; 15-transverse steel bar; 16-concrete.
具体实施方式Detailed ways
下面结合附图,对本发明的一个具体实施范例进行详细说明:A specific implementation example of the present invention will be described in detail below with reference to the accompanying drawings:
如图1--图5所示:本发明的一种快速构筑的新型煤矿密闭墙及其施工工艺,包括巷道顶板1、巷道底板2、巷道两帮3、凹槽4、交叉钢筋5和EPS模块墙体6。封闭区里侧所述EPS模块墙体6表面喷涂有高密度防火阻燃高分子材料的内防护涂层7;封闭区外侧所述EPS模块墙体6表面按照顺序喷涂有膨胀玻化微珠层8、粘接砂浆层9、抗裂网格布10、抹面砂浆层11和外喷涂层12;As shown in Figures 1 to 5: a new type of rapidly constructed coal mine closed wall of the present invention and its construction technology, including a tunnel roof 1, a tunnel bottom plate 2, two gangways of the tunnel 3, a groove 4, a cross steel bar 5 and EPS Modular wall 6. The surface of the EPS module wall 6 inside the enclosed area is sprayed with an inner protective coating 7 of high-density fireproof and flame-retardant polymer material; the surface of the EPS module wall 6 outside the enclosed area is sprayed with a layer of expanded vitrified microbeads in sequence. 8. Bonding mortar layer 9, anti-crack mesh cloth 10, plastering mortar layer 11 and exterior spray layer 12;
在本发明具体实施范例中,EPS模块体13构件上,上下边均匀分布有接插口1302,部分EPS模块体13构件左右两边有凹凸卡扣1305、内外表面有均匀分布的燕尾槽1304,钢筋卡槽1306位于活动肋板1303上;交叉钢筋5中的纵向钢筋14和横向钢筋15通过细钢丝连接固定,且长度均需延伸至煤矿巷道顶板1、巷道底板2和巷道两帮3内;EPS模块墙体6每搭接三层EPS模块体13浇筑混凝土16一次;粘接砂浆层9喷涂厚度为0.5cm;抹面砂浆层11喷涂厚度为0.8cm。In the specific implementation example of the present invention, the EPS module body 13 components have sockets 1302 evenly distributed on the upper and lower sides. Some EPS module body 13 components have concave and convex buckles 1305 on the left and right sides, and evenly distributed dovetail grooves 1304 on the inner and outer surfaces. The steel bar clips The groove 1306 is located on the movable floor 1303; the longitudinal steel bars 14 and the transverse steel bars 15 in the cross steel bars 5 are connected and fixed by thin steel wires, and their lengths need to extend to the coal mine tunnel roof 1, the tunnel bottom plate 2 and the tunnel two sides 3; EPS module Concrete 16 is poured once for every three overlapping layers of EPS modules 13 of the wall 6; the spraying thickness of the bonding mortar layer 9 is 0.5cm; the spraying thickness of the plastering mortar layer 11 is 0.8cm.
一种快速构筑的新型煤矿密闭墙按照以下过程进行施工:A new type of rapidly constructed coal mine closed wall is constructed according to the following process:
第一阶段:在需要设置密闭墙体的巷道顶板1、巷道底板2和巷道两帮3开凿深度为30cm的凹槽4;The first stage: dig grooves 4 with a depth of 30cm in the tunnel roof 1, tunnel floor 2 and tunnel sides 3 where airtight walls need to be installed;
第二阶段:根据设立密闭墙处的巷道断面形状,将不同种类、不同规格、不同形状的EPS模块体13插入预留的纵向钢筋14,通过凹凸卡扣1305或者接插口1302固定,然后,在钢筋卡槽1306内放置横向钢筋15,形成交叉钢筋5;The second stage: According to the cross-sectional shape of the tunnel where the airtight wall is set up, insert EPS module bodies 13 of different types, specifications and shapes into the reserved longitudinal steel bars 14, and fix them through concave and convex buckles 1305 or sockets 1302, and then, Transverse steel bars 15 are placed in the steel bar slots 1306 to form cross steel bars 5;
第三阶段:在形成的EPS模具墙体6内,浇筑混泥土即可形成软—硬—软形式的坚固墙体;The third stage: in the formed EPS mold wall 6, concrete is poured to form a solid wall in the form of soft-hard-soft;
第四阶段:在封闭区里侧EPS模块墙体6表面喷涂高密度防火阻燃高分子材料的内防护涂层7,封闭区外侧EPS模块墙体6表面按照顺序喷涂膨胀玻化微珠层8、粘接砂浆层9、抗裂网格布10、抹面砂浆层11和外喷涂层12。The fourth stage: Spray the inner protective coating 7 of high-density fireproof and flame-retardant polymer material on the surface of the EPS module wall 6 inside the enclosed area, and spray the expanded vitrified microbead layer 8 on the surface of the EPS module wall 6 outside the enclosed area in sequence. , bonding mortar layer 9, anti-crack mesh cloth 10, plastering mortar layer 11 and outer spray layer 12.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210330103.9A CN115013057B (en) | 2022-03-28 | 2022-03-28 | A new type of rapidly constructed coal mine closed wall and its construction technology |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210330103.9A CN115013057B (en) | 2022-03-28 | 2022-03-28 | A new type of rapidly constructed coal mine closed wall and its construction technology |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115013057A CN115013057A (en) | 2022-09-06 |
| CN115013057B true CN115013057B (en) | 2023-12-12 |
Family
ID=83066789
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210330103.9A Active CN115013057B (en) | 2022-03-28 | 2022-03-28 | A new type of rapidly constructed coal mine closed wall and its construction technology |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115013057B (en) |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4516879A (en) * | 1983-05-26 | 1985-05-14 | The Celotex Corporation | Foam slabs in mine tunnel stoppings |
| CN206190323U (en) * | 2016-11-22 | 2017-05-24 | 中国神华能源股份有限公司 | Colliery is fire dam reinforced structure in pit |
| CN207892077U (en) * | 2017-12-14 | 2018-09-21 | 王春宁 | A kind of heat preserving type composite type reinforced concrete wall |
| CN111520187A (en) * | 2020-04-08 | 2020-08-11 | 中国矿业大学 | Modified EPS module composite high-water-content sealing wall and construction method thereof |
| CN213392269U (en) * | 2020-10-15 | 2021-06-08 | 中国矿业大学(北京) | Novel coal mine underground sealing wall using 3D printing technology |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20020017070A1 (en) * | 2000-06-30 | 2002-02-14 | Batch Juan R. | Plastic module for insulated concrete waffle wall |
-
2022
- 2022-03-28 CN CN202210330103.9A patent/CN115013057B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4516879A (en) * | 1983-05-26 | 1985-05-14 | The Celotex Corporation | Foam slabs in mine tunnel stoppings |
| CN206190323U (en) * | 2016-11-22 | 2017-05-24 | 中国神华能源股份有限公司 | Colliery is fire dam reinforced structure in pit |
| CN207892077U (en) * | 2017-12-14 | 2018-09-21 | 王春宁 | A kind of heat preserving type composite type reinforced concrete wall |
| CN111520187A (en) * | 2020-04-08 | 2020-08-11 | 中国矿业大学 | Modified EPS module composite high-water-content sealing wall and construction method thereof |
| CN213392269U (en) * | 2020-10-15 | 2021-06-08 | 中国矿业大学(北京) | Novel coal mine underground sealing wall using 3D printing technology |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115013057A (en) | 2022-09-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102505779B (en) | A modular hoisting and assembling wall system and its construction method | |
| CA2621224C (en) | Modular elements, network, supporting structure, construction and process for obtaining thereof | |
| CN107023160A (en) | A kind of assembly concrete shear wall structure dedicated aluminium alloy template | |
| KR101079646B1 (en) | Internal and external insulation construction method of building using formwork composite panel | |
| KR100588788B1 (en) | Foamed plastic hollow panel assembly | |
| CN115013057B (en) | A new type of rapidly constructed coal mine closed wall and its construction technology | |
| KR102159180B1 (en) | Architectural Middle Insulation System and Construction Method of this | |
| CN108978989B (en) | Assembled self preservation temperature fire prevention sound insulation wallboard | |
| CN204212346U (en) | Heat insulation decoration formwork integral structure and comprise its structural wall | |
| CN113338472A (en) | Assembled phosphogypsum composite wallboard and prefabricating method thereof | |
| CN111133158A (en) | building construction system | |
| CN108457414A (en) | A kind of combination type heat insulating cavity module | |
| CN115853109A (en) | A non-transparent enclosure structure of an ultra-low energy consumption building and its construction method | |
| EP3194680B1 (en) | A building wall and its method for manufacture | |
| CN110714573B (en) | HJ prefabricated multifunctional wall panel | |
| CN111074939A (en) | A formwork-free concrete single-cabin pipe gallery or multi-cabin pipe gallery and its construction method | |
| CN209924198U (en) | A prefabricated infill wall and infill wall system with deformable wall panels | |
| CN102182262A (en) | Armored foamed concrete thermal insulation wall | |
| CN116357034B (en) | No-removable formwork decorative panels for building exterior walls and building exterior wall structures | |
| KR102588136B1 (en) | Sandwich insulation wall system of construction with improved workability, insulation performance and design, and method for constructing sandwich insulation wall system of construction with patterns formed on double-sided exposed concrete walls | |
| CN2911049Y (en) | In-situ light-weight composite wall | |
| KR200338055Y1 (en) | Expanded plastic hollow panel assembly | |
| CN203654565U (en) | Prefabricated cavity component | |
| US20240376708A1 (en) | 3d-printed integrated wall panel assembly | |
| CN223661108U (en) | Light externally hung wallboard system with grooved and tongued profile steel frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |