CN114993068A - Hot-blast device of recycling in air cooling island - Google Patents

Hot-blast device of recycling in air cooling island Download PDF

Info

Publication number
CN114993068A
CN114993068A CN202210487362.2A CN202210487362A CN114993068A CN 114993068 A CN114993068 A CN 114993068A CN 202210487362 A CN202210487362 A CN 202210487362A CN 114993068 A CN114993068 A CN 114993068A
Authority
CN
China
Prior art keywords
air
cooling
hot
boiler
hot air
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210487362.2A
Other languages
Chinese (zh)
Inventor
罗明高
王明达
雷普
薛永奇
陈海军
于滨
丁静波
米禄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia Dengkou Jinniu Coal Power Co ltd
Original Assignee
Inner Mongolia Dengkou Jinniu Coal Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia Dengkou Jinniu Coal Power Co ltd filed Critical Inner Mongolia Dengkou Jinniu Coal Power Co ltd
Priority to CN202210487362.2A priority Critical patent/CN114993068A/en
Publication of CN114993068A publication Critical patent/CN114993068A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F28HEAT EXCHANGE IN GENERAL
    • F28BSTEAM OR VAPOUR CONDENSERS
    • F28B9/00Auxiliary systems, arrangements, or devices
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23LSUPPLYING AIR OR NON-COMBUSTIBLE LIQUIDS OR GASES TO COMBUSTION APPARATUS IN GENERAL ; VALVES OR DAMPERS SPECIALLY ADAPTED FOR CONTROLLING AIR SUPPLY OR DRAUGHT IN COMBUSTION APPARATUS; INDUCING DRAUGHT IN COMBUSTION APPARATUS; TOPS FOR CHIMNEYS OR VENTILATING SHAFTS; TERMINALS FOR FLUES
    • F23L15/00Heating of air supplied for combustion
    • F23L15/04Arrangements of recuperators
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/34Indirect CO2mitigation, i.e. by acting on non CO2directly related matters of the process, e.g. pre-heating or heat recovery

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The application discloses device that air cooling island is hot-blast to recycle for improve the utilization ratio of air cooling island steam resource, reduce the waste of steam resource. The device of this application includes: the air cooling island comprises an air cooling island body, air cooling radiating fins, a first fan, an air cooling top cover, a hot air main pipeline and a boiler air smoke system; the air cooling island body is internally connected with a steam exhaust pipeline which is used for exhausting the exhaust steam of the steam turbine; the air cooling radiating fins are arranged in the air cooling island body and fixedly connected with the steam exhaust pipeline, and are used for radiating the exhaust steam in the steam exhaust pipeline; the first fan is arranged in the air cooling island body and is positioned below the air cooling radiating fins, and the first fan is used for blowing cold air to the air cooling radiating fins and the steam exhaust pipeline so as to carry out air cooling heat dissipation on the steam exhaust pipeline and the air cooling radiating fins; an air cooling top cover is fixedly connected above the air cooling island; the air cooling top cover is connected with the boiler air smoke system through a hot air main pipeline and used for conveying hot air generated after air cooling and heat dissipation to the boiler air smoke system through the hot air main pipeline.

Description

一种空冷岛热风再利用的装置A device for reusing hot air in an air-cooled island

技术领域technical field

本申请涉及直接空冷领域,尤其涉及一种空冷岛热风再利用的装置。The present application relates to the field of direct air cooling, and in particular, to a device for reusing hot air from an air-cooled island.

背景技术Background technique

空冷凝汽器及配套的空冷风机等直接空冷设备安装于距地面一定高度的平台上,电厂工作人员将此高空区域统称为空冷岛,通常代指空冷凝汽器。The direct air cooling equipment such as the air-cooling condenser and the supporting air-cooling fan are installed on the platform at a certain height from the ground. The power plant staff collectively refer to this high-altitude area as the air-cooling island, which usually refers to the air-cooling condenser.

目前,火力发电厂所使用的直接空冷系统是将汽轮机的排汽通过主排汽管道送到室外布置的空冷凝汽器内,轴流冷却风机使空气流过散热器的外表面,将排汽冷却成水,凝结水再经凝结泵送回汽轮机的回热系统。At present, the direct air cooling system used in thermal power plants sends the exhaust steam of the steam turbine to the air-cooled condenser arranged outdoors through the main exhaust steam pipe, and the axial cooling fan makes the air flow over the outer surface of the radiator, and the exhaust steam is discharged. It is cooled into water, and the condensed water is sent back to the regenerative system of the steam turbine through the condensing pump.

然而,由于目前直接空冷系统中空冷凝汽器的结构,在经过散热器换热后的产生的废热空气将直接排放到大气中,容易造成热气资源的浪费。However, due to the structure of the air-cooled condenser in the current direct air cooling system, the waste hot air generated after heat exchange by the radiator will be directly discharged into the atmosphere, which is likely to cause waste of hot air resources.

发明内容SUMMARY OF THE INVENTION

为了解决上述问题,本申请提供了一种空冷岛热风再利用的装置,用于使空冷岛热气资源的利用率提高,减少热气资源的浪费。In order to solve the above problems, the present application provides a device for reusing the hot air of the air-cooled island, which is used to improve the utilization rate of the hot air resources of the air-cooled island and reduce the waste of the hot air resources.

本申请提供的空冷岛热风再利用的装置,包括:The device for reusing air-cooled island hot air provided by this application includes:

空冷岛本体、空冷散热片、第一风机、空冷顶盖、热风主管道以及锅炉风烟系统;Air-cooled island body, air-cooled heat sink, first fan, air-cooled top cover, hot air main pipe and boiler air and smoke system;

所述空冷岛本体内连接有排汽管道,所述排汽管道用于排出汽轮机的乏汽;The air-cooling island body is connected with a steam exhaust pipe, and the steam exhaust pipe is used to discharge the exhausted steam of the steam turbine;

所述空冷散热片安装在所述空冷岛本体内,且与所述排汽管道固定连接,所述空冷散热片用于对所述排汽管道内的乏汽进行散热;The air-cooling fins are installed in the air-cooling island body and are fixedly connected with the exhaust pipe, and the air-cooling fins are used to dissipate the exhausted steam in the exhaust pipe;

所述第一风机安装在所述空冷岛本体内,且位于所述空冷散热片下方,所述第一风机用于向所述空冷散热片和所述排汽管道吹出冷风,以使得对所述排汽管道和所述空冷散热片进行风冷散热;The first fan is installed in the air-cooling island body, and is located below the air-cooling fins, and the first fan is used to blow cold air to the air-cooling fins and the exhaust duct, so that the The exhaust duct and the air cooling fins are used for air cooling and heat dissipation;

所述空冷岛上方固定连接空冷顶盖;An air-cooling top cover is fixedly connected above the air-cooling island;

所述空冷顶盖通过所述热风主管道与所述锅炉风烟系统连接,用于通过所述热风主管道向所述锅炉风烟系统输送风冷散热后产生的热风。The air-cooled top cover is connected to the boiler air and fume system through the hot air main pipeline, and is used for conveying the hot air generated after air cooling and heat dissipation to the boiler air and fume system through the hot air main pipeline.

可选地,所述空冷顶盖上方设置有出风口;Optionally, an air outlet is provided above the air-cooled top cover;

所述热风主管道设置在所述空冷顶盖上方,并与所述空冷顶盖的出风口固定连接。The hot air main duct is arranged above the air-cooled top cover and is fixedly connected with the air outlet of the air-cooled top cover.

可选地,所述锅炉风烟系统包括锅炉;Optionally, the boiler fume system includes a boiler;

所述锅炉设置有一次风入口和二次风入口;The boiler is provided with a primary air inlet and a secondary air inlet;

所述热风主管道分别与所述一次风入口和所述二次风入口连通,用于为锅炉提供热风源。The hot air main pipes are respectively communicated with the primary air inlet and the secondary air inlet, and are used to provide a hot air source for the boiler.

可选地,所述装置还包括第二风机;Optionally, the device further includes a second fan;

所述第二风机设置在所述热风主管道与所述锅炉风烟系统之间,用于抽出所述热风主管道内的热风并向所述锅炉风烟系统输送所述热风。The second fan is arranged between the main hot air duct and the boiler fume system, and is used to extract the hot air in the main hot air duct and deliver the hot air to the boiler fume system.

可选地,所述锅炉包括一次风暖风器和二次风暖风器;Optionally, the boiler includes a primary air heater and a secondary air heater;

所述第二风机设置有吸风口和送风口;The second fan is provided with an air suction port and an air supply port;

所述热风主管道包括第一热风管道和第二热风管道;The hot air main duct includes a first hot air duct and a second hot air duct;

所述空冷顶盖通过所述第一热风管道与所述第二风机的吸风口连接;The air-cooled top cover is connected to the air suction port of the second fan through the first hot air duct;

所述第二风机的送风口通过所述第二热风管道与所述一次风暖风器的吸风口以及二次风暖风器的吸风口连接,用于为所述一次风暖风器和二次风暖风器提供热风源。The air supply port of the second fan is connected to the air suction port of the primary air heater and the air suction port of the secondary air heater through the second hot air duct, and is used for the primary air heater and the secondary air heater. The secondary air heater provides the hot air source.

可选地,所述空冷岛本体由金属材质制成,所述空冷顶盖由金属材质制成。Optionally, the air-cooling island body is made of metal material, and the air-cooling top cover is made of metal material.

可选地,所述金属材质为彩钢。Optionally, the metal material is color steel.

可选地,所述空冷岛本体包括空冷岛围墙;Optionally, the air-cooled island body includes an air-cooled island enclosure;

所述空冷岛围墙与所述空冷顶盖通过焊接方式固定连接。The air-cooling island enclosure wall and the air-cooling top cover are fixedly connected by welding.

可选地,所述装置包括若干个空冷散热片和若干个第一风机;Optionally, the device includes several air cooling fins and several first fans;

所述若干个空冷散热片平行排列设置在所述空冷岛本体内;The plurality of air-cooling fins are arranged in parallel in the air-cooling island body;

所述若干个第一风机平行排列在所述若干个空冷散热片下方,且与所述空冷散热片一一对应。The plurality of first fans are arranged in parallel below the plurality of air-cooling fins and correspond to the air-cooling fins one-to-one.

可选地,所述排汽管道围绕在所述空冷散热片外部。Optionally, the steam exhaust duct surrounds the outside of the air cooling fins.

从以上技术方案可以看出,本申请具有以下优点:As can be seen from the above technical solutions, the present application has the following advantages:

本申请装置包括空冷岛本体、空冷散热片、第一风机、空冷顶盖、热风主管道以及锅炉风烟系统;空冷岛本体内连接有排汽管道,排汽管道用于排出汽轮机的乏汽;空冷散热片安装在空冷岛本体内,且与排汽管道固定连接,空冷散热片用于对排汽管道内的乏汽进行散热;第一风机安装在空冷岛本体内,且位于空冷散热片下方,第一风机用于向空冷散热片和排汽管道吹出冷风,以使得对排汽管道和空冷散热片进行风冷散热;空冷岛上方固定连接空冷顶盖;空冷顶盖通过热风主管道与锅炉风烟系统连接,用于通过热风主管道向锅炉风烟系统输送风冷散热后产生的热风。The device of the present application comprises an air-cooling island body, an air-cooling fin, a first fan, an air-cooling top cover, a main hot air pipe, and a boiler air and smoke system; the air-cooling island body is connected with a steam exhaust pipe, and the steam exhaust pipe is used to discharge the exhausted steam of the steam turbine; The air-cooling fins are installed in the air-cooling island body and are fixedly connected to the exhaust pipe. The air-cooling fins are used to dissipate heat from the exhausted steam in the exhaust pipes; the first fan is installed in the air-cooling island body and is located below the air-cooling fins , the first fan is used to blow cold air to the air-cooling fins and the exhaust duct, so that the exhaust duct and the air-cooling fins are air-cooled and dissipated; the air-cooling top cover is fixedly connected to the top of the air-cooling island; the air-cooling top cover is connected to the boiler through the main hot air pipe The air-smoke system connection is used to transport the hot air generated by air-cooling and heat dissipation to the boiler air-smoke system through the hot air main pipe.

在空冷岛本体上方加装空冷顶盖用于存储汽轮机乏汽散热后的热风,然后通过热风主管道输送到锅炉风烟系统,从而为锅炉风烟系统提供热风源,进而提高锅炉风烟系统的助燃风温度,节约锅炉风烟系统的能耗,同时提高空冷岛热气资源的利用率,减少热气资源的浪费。An air-cooling top cover is installed above the air-cooling island body to store the hot air after the exhaust steam of the steam turbine is dissipated, and then transported to the boiler air and smoke system through the main hot air pipeline, so as to provide a hot air source for the boiler air and smoke system, thereby improving the boiler air and smoke system. The temperature of the combustion-supporting air can save the energy consumption of the boiler air and smoke system, and at the same time improve the utilization rate of the hot gas resources of the air-cooled island, and reduce the waste of hot gas resources.

附图说明Description of drawings

图1为本申请提供的空冷岛热风再利用的装置一个实施例结构示意图。FIG. 1 is a schematic structural diagram of an embodiment of a device for reusing hot air in an air-cooled island provided by the application.

具体实施方式Detailed ways

本申请提供了一种空冷岛热风再利用的装置,用于提高空冷岛热气资源的利用率,减少热气资源的浪费。The present application provides a device for reusing hot air in an air-cooled island, which is used to improve the utilization rate of hot air resources in the air-cooled island and reduce the waste of hot air resources.

在本申请中,术语“上”、“下”、“左”、“右”、“前”、“后”、“顶”、“底”、“内”、“外”、“中”、“竖直”、“水平”、“横向”、“纵向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅用于说明各部件或组成部分之间的相对位置关系,并不特别限定各部件或组成部分的具体安装方位。In this application, the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inner", "outer", "middle", The orientation or positional relationship indicated by "vertical", "horizontal", "horizontal", "longitudinal", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only used to illustrate the relative positional relationship between each component or component , and does not specifically limit the specific installation orientation of each component or component.

并且,上述部分术语除了可以用于表示方位或位置关系以外,还可能用于表示其他含义,例如术语“上”在某些情况下也可能用于表示某种依附关系或连接关系。对于本领域普通技术人员而言,可以根据具体情况理解这些术语在本申请中的具体含义。In addition, some of the above-mentioned terms may be used to express other meanings besides orientation or positional relationship. For example, the term "on" may also be used to express a certain attachment or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in the present application can be understood according to specific situations.

此外,术语“安装”、“设置”、“设有”、“连接”、“相连”应做广义理解。例如,可以是固定连接,可拆卸连接,或整体式构造;可以是机械连接,或电连接;可以是直接相连,或者是通过中间媒介间接相连,又或者是两个装置、元件或组成部分之间内部的连通。对于本领域普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。Furthermore, the terms "installed", "arranged", "provided", "connected", "connected" should be construed broadly. For example, it may be a fixed connection, a detachable connection, or a unitary structure; it may be a mechanical connection, or an electrical connection; it may be directly connected, or indirectly connected through an intermediary, or between two devices, elements, or components. internal communication. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific situations.

此外,在本申请中所附图式所绘制的结构、比例、大小等,均仅用于配合说明书所揭示的内容,以供本领域技术人员了解与阅读,并非用于限定本申请可实施的限定条件,故不具有技术上的实质意义,任何结构的修饰、比例关系的改变或大小的调整,在不影响本申请所能产生的功效及所能达成的目的下,均仍应落在本申请所揭示的技术内容涵盖的范围内。In addition, the structures, proportions, sizes, etc. drawn in the drawings in this application are only used to cooperate with the contents disclosed in the description, so as to be understood and read by those skilled in the art, and are not used to limit the implementation of this application. Therefore, it does not have technical substantive significance. Any modification of structure, change of proportional relationship or adjustment of size shall still fall within this within the scope of the technical content disclosed in the application.

此外,本申请中所提及的术语“第一”、“第二”、“第三”等(如果存在)是用于区别类似的对象,而不必用于描述特定的顺序或先后次序。应该理解这样使用的术语在适当的情况下可以互换,以便本申请描述的实施例能够以除了在这里图示或描述的内容以外的顺序实施。Furthermore, the terms "first", "second", "third", etc. (if any) mentioned in this application are used to distinguish similar objects and are not necessarily used to describe a particular order or sequence. It is to be understood that the terms so used are interchangeable under appropriate circumstances such that the embodiments described herein can be practiced in sequences other than as illustrated or described herein.

下面将结合本申请中的附图,对本申请中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本申请一部分实施例,而不是全部的实施例。基于本申请中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本申请保护的范围。The technical solutions in the present application will be clearly and completely described below with reference to the accompanying drawings in the present application. Obviously, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present application.

请参阅图1,本申请提供的空冷岛热风再利用的装置包括:Please refer to FIG. 1, the device for reusing the hot air of the air-cooled island provided by this application includes:

空冷岛本体1、空冷散热片2、第一风机3、空冷顶盖4、热风主管道5以及锅炉风烟系统6;该空冷岛本体1内连接有排汽管道,该排汽管道用于排出汽轮机的乏汽;该空冷散热片2安装在该空冷岛本体1内,且与该排汽管道固定连接,该空冷散热片2用于对该排汽管道内的乏汽进行散热;该第一风机3安装在该空冷岛本体1内,且位于该空冷散热片2下方,该第一风机3用于向该空冷散热片2和该排汽管道吹出冷风,以使得对该排汽管道和该空冷散热片2进行风冷散热;该空冷岛上方固定连接空冷顶盖4;该空冷顶盖4通过该热风主管道5与该锅炉风烟系统6连接,用于通过该热风主管道5向该锅炉风烟系统6输送风冷散热后产生的热风。The air-cooling island body 1, the air-cooling fins 2, the first fan 3, the air-cooling top cover 4, the hot air main pipe 5 and the boiler air and smoke system 6; the air-cooling island body 1 is connected with a steam exhaust pipe, and the steam exhaust pipe is used to discharge The exhausted steam of the steam turbine; the air-cooled fins 2 are installed in the air-cooled island body 1 and are fixedly connected to the exhaust pipe, and the air-cooled fins 2 are used to dissipate the exhausted steam in the exhaust pipe; the first The fan 3 is installed in the air-cooling island body 1 and is located below the air-cooling fins 2. The first fan 3 is used to blow cold air to the air-cooling fins 2 and the exhaust duct, so that the exhaust duct and the exhaust duct can be blown out. The air-cooled fins 2 are air-cooled and dissipated; the air-cooled top cover 4 is fixedly connected to the top of the air-cooled island; The boiler air and fume system 6 conveys the hot air generated after air cooling and heat dissipation.

本实施例中,空冷岛本体1为利用空气作为冷却介质的一种空气冷却器,具体可作为一种电厂空气冷却装置。空冷岛本体1主要由排汽管道、支架等组成。排汽管道与汽轮机连接,以使得汽轮机排放的乏汽在管内流通到达空冷岛进行散热。空冷岛本体1内底部设置有第一风机3,第一风机3上方为由包括空冷散热片2和排汽管道组成的“A”字型汽机房。具体地,空冷散热片2布置在“A”字型汽机房表面。排汽管道一端由与汽轮机连接的主排汽管道引出,另一端设置在“A”子型汽机房底部且向平行于“A”字型汽机房的两侧分别分支出水平排汽管道。然后,两侧的水平排汽管道分别朝向“A”字型汽机房的顶部分支出若干条垂直排汽管道,用于引流出汽轮机内排放的热乏汽。空冷散热片2与若干条垂直排汽管道连接,用于吸收该若干条垂直排汽管道上的热量。例如,可设置空冷散热片2与若干条垂直排汽管道贴合,以提高空冷散热片2与排汽管道的接触面积,从而提高排汽管道内乏汽热量向空冷散热片2传导的传热效率。排汽管道可由导热性高的材料制成,例如,铜材、铝材等,具体此处不做限定。然后,在空冷岛本体1上方固定连接空冷顶盖4;该空冷顶盖4再与锅炉风烟系统6通过热风主管道5连通。In this embodiment, the air-cooling island body 1 is an air cooler that uses air as a cooling medium, and can specifically be used as an air cooling device for a power plant. The air-cooling island body 1 is mainly composed of exhaust pipes, brackets and the like. The exhaust steam pipe is connected with the steam turbine, so that the exhausted steam discharged from the steam turbine circulates in the pipe and reaches the air cooling island for heat dissipation. A first fan 3 is arranged at the inner bottom of the air-cooling island body 1, and above the first fan 3 is an "A"-shaped steam engine room consisting of air-cooling fins 2 and exhaust pipes. Specifically, the air cooling fins 2 are arranged on the surface of the "A"-shaped turbine room. One end of the exhaust pipe is drawn from the main exhaust pipe connected to the steam turbine, and the other end is set at the bottom of the "A" sub-type steam engine room and branches out to the horizontal steam exhaust pipes parallel to the two sides of the "A" type steam engine room. Then, the horizontal steam exhaust pipes on both sides respectively extend several vertical steam exhaust pipes toward the top part of the "A"-shaped steam turbine house, which are used to divert the hot exhaust steam discharged from the steam turbine. The air cooling fins 2 are connected with several vertical steam exhaust pipes, and are used to absorb the heat on the plurality of vertical steam exhaust pipes. For example, the air cooling fins 2 can be arranged to fit with several vertical steam exhaust pipes to increase the contact area between the air cooling fins 2 and the exhaust pipes, thereby improving the heat transfer of the exhaust heat in the exhaust pipes to the air cooling fins 2. efficiency. The steam exhaust pipe can be made of a material with high thermal conductivity, such as copper material, aluminum material, etc., which is not specifically limited here. Then, an air-cooling top cover 4 is fixedly connected above the air-cooling island body 1 ;

在直接空冷换热过程中,汽轮机排放的乏汽热流体通过排汽管道流动,热量传导到空冷散热片2上。第一风机3启动并向上方的空冷散热片2及排汽管道吹出冷风,冷空气应用到空冷散热片和排汽管道,将排汽管道中的热蒸汽冷凝。,与此同时,第一风机3吹出的冷风吸收热量后变成热风,热风向上流通被空冷顶盖4遮挡,避免排放到大气中,然后热风通过热风主管道5流通到锅炉风烟系统6,为锅炉风烟系统6的空气预热提供热风资源,从而节约锅炉风烟系统6的能耗,同时提高空冷岛的热气资源的利用率,减少了热气资源的浪费。In the direct air-cooled heat exchange process, the hot fluid of the exhausted steam discharged from the steam turbine flows through the exhaust pipe, and the heat is conducted to the air-cooled fins 2 . The first fan 3 starts and blows cold air to the upper air cooling fins 2 and the exhaust duct, and the cold air is applied to the air cooling fins and the exhaust duct to condense the hot steam in the exhaust duct. At the same time, the cold air blown by the first fan 3 absorbs heat and becomes hot air, and the hot air circulates upwards and is blocked by the air-cooled top cover 4 to avoid being discharged into the atmosphere, and then the hot air flows through the hot air main pipe 5 to the boiler air and smoke system 6, Hot air resources are provided for the air preheating of the boiler air fume system 6, thereby saving the energy consumption of the boiler air fume system 6, and at the same time improving the utilization rate of the hot air resources of the air cooling island, and reducing the waste of hot air resources.

可选地,该空冷顶盖4上方设置有出风口;该热风主管道5设置在该空冷顶盖4上方,并与该空冷顶盖4的出风口固定连接。Optionally, an air outlet is provided above the air-cooled top cover 4 ; the hot air main duct 5 is provided above the air-cooled top cover 4 and is fixedly connected to the air outlet of the air-cooled top cover 4 .

本实施例中,空冷顶盖4的出风口设置在顺流区,具体地,设置在空冷顶盖4的上方。然后,热风主管道5一端与该空冷顶盖4上方开设的出风口连接,另一端与锅炉风烟系统6连接,以使得空冷岛内的热风能顺风向上流动,并从上方出风口和热风主管道6流出,提高热风流出效率。In this embodiment, the air outlet of the air-cooled top cover 4 is arranged in the downstream area, specifically, above the air-cooled top cover 4 . Then, one end of the hot air main duct 5 is connected to the air outlet opened above the air-cooled top cover 4, and the other end is connected to the boiler air and fume system 6, so that the hot air in the air-cooled island can flow upward in the downwind, and from the upper air outlet and the hot air main Pipe 6 flows out to improve the efficiency of hot air outflow.

可选地,该锅炉风烟系统6包括锅炉;该锅炉设置有一次风入口和二次风入口;该热风主管道5分别与该一次风入口和该二次风入口连通,用于为锅炉提供热风源。Optionally, the boiler air fume system 6 includes a boiler; the boiler is provided with a primary air inlet and a secondary air inlet; the hot air main duct 5 is communicated with the primary air inlet and the secondary air inlet, respectively, for providing the boiler. hot air source.

本实施例中,锅炉风烟系统6包括锅炉,或者称为锅炉房。其具体包括锅炉及水泵等附属设备,一般用于供暖和生产使用。锅炉设置有一次风入口和二次风入口。一般来说,一次风为燃料风,用来输送、干燥煤粉进入锅炉燃烧,二次风用来助燃,为煤粉燃烧提供充足的氧气。本实施例中,将热风主管道5与锅炉的一次风入口和二次风入口连通,可为锅炉的一次风和二次风提供热风源,提高一次风干燥煤粉的干燥效果,同时还可提高二次风助燃的效果。In this embodiment, the boiler fume system 6 includes a boiler, or is called a boiler room. It specifically includes auxiliary equipment such as boilers and pumps, which are generally used for heating and production use. The boiler is provided with a primary air inlet and a secondary air inlet. Generally speaking, the primary air is the fuel air, which is used to transport and dry the pulverized coal into the boiler for combustion, and the secondary air is used to support combustion and provide sufficient oxygen for the combustion of the pulverized coal. In this embodiment, the hot air main pipe 5 is connected with the primary air inlet and the secondary air inlet of the boiler, which can provide the hot air source for the primary air and the secondary air of the boiler, improve the drying effect of the primary air drying pulverized coal, and also can Improve the effect of secondary air combustion.

可选地,该装置还包括第二风机7;该第二风机7设置在该热风主管道5与该锅炉风烟系统6之间,用于抽出该热风主管道5内的热风并向该锅炉风烟系统6输送该热风。Optionally, the device also includes a second fan 7; the second fan 7 is arranged between the hot air main duct 5 and the boiler fume system 6, and is used to extract the hot air in the hot air main duct 5 to the boiler. The fume and fume system 6 delivers this hot air.

本实施例中,在热风主管道5和锅炉之间还设置有第二风机7,通过第二风机7对经过热风主管道5的热风源进行抽送,将热风源更快速的抽送到锅炉中,提热风源的输送效率,减少热风源在空冷顶盖4内和热风主管道5内的停留时间。In this embodiment, a second fan 7 is also provided between the main hot air duct 5 and the boiler, and the hot air source passing through the main hot air duct 5 is pumped by the second fan 7, and the hot air source is pumped to the boiler more quickly, The transportation efficiency of the hot air source is improved, and the residence time of the hot air source in the air cooling top cover 4 and the hot air main duct 5 is reduced.

可选地,该锅炉包括一次风暖风器和二次风暖风器;该第二风机7设置有吸风口和送风口;该热风主管道5包括第一热风管道和第二热风管道;该空冷顶盖4通过该第一热风管道与该第二风机7的吸风口连接;该第二风机7的送风口通过该第二热风管道与该一次风暖风器的吸风口以及二次风暖风器的吸风口连接,用于为该一次风暖风器和二次风暖风器提供热风源。Optionally, the boiler includes a primary air heater and a secondary air heater; the second fan 7 is provided with an air suction port and an air supply port; the hot air main duct 5 includes a first hot air duct and a second hot air duct; the The air-cooled top cover 4 is connected to the air suction port of the second fan 7 through the first hot air duct; the air supply port of the second fan 7 is connected to the suction port of the primary air heater and the secondary air heater through the second hot air duct The air suction port of the fan is connected to provide a hot air source for the primary air heater and the secondary air heater.

本实施例中,通常在送风入口和锅炉的空气预热器之间设置暖风器。该暖风器是一种利用机低压抽汽加热空气预热器进口空气的热交换器。加装暖风器之后,可通过暖风器使空气预热器的空气温度升高,使空气预热器的传热温差减小,减少空气预热器的低温腐蚀。In this embodiment, an air heater is usually provided between the air supply inlet and the air preheater of the boiler. The air heater is a heat exchanger that uses the low-pressure extraction steam of the machine to heat the inlet air of the air preheater. After installing the air heater, the air temperature of the air preheater can be raised by the air heater, so that the heat transfer temperature difference of the air preheater can be reduced, and the low temperature corrosion of the air preheater can be reduced.

本实施例中,在空冷顶盖4和第二风机7的吸风口之间通过第一热风管道连接,将空冷岛内的热风源通过第一热风管道输送到第二风机7的吸风口。然后,第二风机7的送风口与一次风暖风器的吸风口以及二次风暖风器的吸风口通过第二热风管道连接。具体地,可以是第二热风管道一端与第二风机7的送风口连接,然后第二热风管道另一端分支出两条支管道,两条支管道分别与一次风暖风器的吸风口和二次风暖风器的吸风口连接。通过热风管道和第二风机7为一次风暖风器和二次风暖风器提供热风源,提高风源温度,从而提高空气预热器的空气温度,可有效降低暖风器的电耗。In this embodiment, the air-cooled top cover 4 and the suction port of the second fan 7 are connected by a first hot air duct, and the hot air source in the air-cooled island is transported to the suction port of the second fan 7 through the first hot air duct. Then, the air supply port of the second fan 7 is connected to the air suction port of the primary air heater and the air suction port of the secondary air heater through the second hot air duct. Specifically, one end of the second hot air duct can be connected to the air supply port of the second fan 7, and then the other end of the second hot air duct is branched into two branch pipes, which are respectively connected to the air suction port and the two branch pipes of the primary air heater. The suction port of the secondary air heater is connected. A hot air source is provided for the primary air heater and the secondary air heater through the hot air duct and the second fan 7, and the temperature of the air source is increased, thereby increasing the air temperature of the air preheater, which can effectively reduce the power consumption of the heater.

可选地,该空冷岛本体1由金属材质制成,该空冷顶盖4由金属材质制成。例如,该金属材质为彩钢或其他合金钢材质。Optionally, the air-cooled island body 1 is made of metal material, and the air-cooled top cover 4 is made of metal material. For example, the metal material is color steel or other alloy steel material.

本实施例中,可使用耐腐蚀和耐久性的金属材质制作空冷岛本体1和空冷顶盖4。例如,彩钢、钢筋混凝土等,还可以是其他金属材质,具体此处不做限定。本实施例中,可优选彩钢材料制作空冷岛本体1和空冷顶盖4,因为彩钢为一种带有有机涂层的钢板,不仅具有耐腐蚀性好、抗风性和耐久性好等优点,同时还加工成型方便,可减少加工成本。In this embodiment, the air-cooling island body 1 and the air-cooling top cover 4 can be made of corrosion-resistant and durable metal materials. For example, color steel, reinforced concrete, etc., may also be other metal materials, which are not specifically limited here. In this embodiment, the air-cooled island body 1 and the air-cooled top cover 4 can be made of color steel material, because color steel is a kind of steel plate with organic coating, which not only has good corrosion resistance, wind resistance and durability, etc. At the same time, it is also convenient to process and form, which can reduce the processing cost.

可选地,该空冷岛本体1包括空冷岛围墙;该空冷岛围墙与该空冷顶盖4通过焊接方式固定连接。Optionally, the air-cooling island body 1 includes an air-cooling island wall; the air-cooling island wall and the air-cooling top cover 4 are fixedly connected by welding.

本实施例中,空冷岛本体1包括空冷岛内部设备以及空冷岛围墙。该空冷岛围墙将空冷岛内部设备围绕起来,顶部为中空结构。从而,在空冷岛围墙上方可加装空冷顶盖4以回收空冷岛空冷散热时产生的热风源。具体地,在空冷岛围墙和空冷顶盖4之间的连接处通过焊接方式固定连接,以提高连接的稳固性。In this embodiment, the air-cooling island body 1 includes internal equipment of the air-cooling island and an air-cooling island enclosure. The air-cooling island enclosure wall surrounds the internal equipment of the air-cooling island, and the top is a hollow structure. Therefore, an air-cooling top cover 4 can be installed above the enclosure wall of the air-cooling island to recover the hot air source generated when the air-cooling island is air-cooled for heat dissipation. Specifically, the connection between the air-cooling island enclosure wall and the air-cooling top cover 4 is fixedly connected by welding, so as to improve the stability of the connection.

可选地,该装置包括若干个空冷散热片2和若干个第一风机3;该若干个空冷散热片2平行排列设置在该空冷岛本体1内;该若干个第一风机3平行排列在该若干个空冷散热片2下方,且与该空冷散热片2一一对应。Optionally, the device includes several air-cooling fins 2 and several first fans 3; the several air-cooling fins 2 are arranged in parallel in the air-cooling island body 1; the several first fans 3 are arranged in parallel in the air-cooling island body 1. Below a plurality of air-cooling fins 2, and corresponding to the air-cooling fins 2 one-to-one.

本实施例中,可在空冷岛本体1内设置有若干个由空冷散热片2和排汽管道组成的“A”字型汽机房,和若干个第一风机3,在每个“A”字型汽机房下方设置一个第一风机3,用于对上方的空冷散热片2和排汽管道进行风冷散热。例如,在空冷岛本体1内设置有五排六列的“A”字型汽机房和第一风机3,且每一“A”字型汽机房和第一风机3平行排列设置。本实施例中,设置平行排列的“A”字型汽机房和第一风机3,不仅使得外观美观,而且可使排汽管道内的乏汽能均匀散热,提高散热效果。In this embodiment, several "A"-shaped steam engine rooms composed of air-cooling fins 2 and exhaust pipes, and several first fans 3 can be arranged in the air-cooling island body 1. A first fan 3 is arranged below the type steam engine room, which is used for air-cooling heat dissipation to the air-cooling fins 2 and exhaust pipes above. For example, five rows and six rows of "A"-shaped turbine rooms and the first fan 3 are arranged in the air-cooling island body 1, and each "A"-shaped turbine room and the first fan 3 are arranged in parallel. In this embodiment, the parallel arrangement of the "A"-shaped turbine room and the first fan 3 not only makes the appearance beautiful, but also enables the exhausted steam in the exhaust pipe to be uniformly radiated, thereby improving the radiating effect.

需要说明的是,对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本申请。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本申请的范围的情况下,在其它实施例中实现。因此,本申请不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。It should be noted that the above description of the disclosed embodiments enables those skilled in the art to realize or use the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be implemented in other embodiments without departing from the scope of the present application. Therefore, the present application is not to be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1.一种空冷岛热风再利用的装置,其特征在于,所述装置包括:1. a device for reusing air-cooled island hot air, is characterized in that, described device comprises: 空冷岛本体、空冷散热片、第一风机、空冷顶盖、热风主管道以及锅炉风烟系统;Air-cooled island body, air-cooled heat sink, first fan, air-cooled top cover, hot air main pipe and boiler air and smoke system; 所述空冷岛本体内连接有排汽管道,所述排汽管道用于排出汽轮机的乏汽;The air-cooling island body is connected with a steam exhaust pipe, and the steam exhaust pipe is used to discharge the exhausted steam of the steam turbine; 所述空冷散热片安装在所述空冷岛本体内,且与所述排汽管道固定连接,所述空冷散热片用于对所述排汽管道内的乏汽进行散热;The air-cooling fins are installed in the air-cooling island body and are fixedly connected with the exhaust pipe, and the air-cooling fins are used to dissipate the exhausted steam in the exhaust pipe; 所述第一风机安装在所述空冷岛本体内,且位于所述空冷散热片下方,所述第一风机用于向所述空冷散热片和所述排汽管道吹出冷风,以使得对所述排汽管道和所述空冷散热片进行风冷散热;The first fan is installed in the air-cooling island body, and is located below the air-cooling fins, and the first fan is used to blow cold air to the air-cooling fins and the exhaust duct, so that the The exhaust duct and the air cooling fins are used for air cooling and heat dissipation; 所述空冷岛上方固定连接空冷顶盖;An air-cooling top cover is fixedly connected above the air-cooling island; 所述空冷顶盖通过所述热风主管道与所述锅炉风烟系统连接,用于通过所述热风主管道向所述锅炉风烟系统输送风冷散热后产生的热风。The air-cooled top cover is connected to the boiler air and fume system through the hot air main pipeline, and is used for conveying the hot air generated after air cooling and heat dissipation to the boiler air and fume system through the hot air main pipeline. 2.根据权利要求1所述的装置,其特征在于,所述空冷顶盖上方设置有出风口;2. The device according to claim 1, wherein an air outlet is provided above the air-cooled top cover; 所述热风主管道设置在所述空冷顶盖上方,并与所述空冷顶盖的出风口固定连接。The hot air main duct is arranged above the air-cooled top cover and is fixedly connected with the air outlet of the air-cooled top cover. 3.根据权利要求1所述的装置,其特征在于,所述锅炉风烟系统包括锅炉;3. The device according to claim 1, wherein the boiler fume system comprises a boiler; 所述锅炉设置有一次风入口和二次风入口;The boiler is provided with a primary air inlet and a secondary air inlet; 所述热风主管道分别与所述一次风入口和所述二次风入口连通,用于为锅炉提供热风源。The hot air main pipes are respectively communicated with the primary air inlet and the secondary air inlet, and are used to provide a hot air source for the boiler. 4.根据权利要求1所述的装置,其特征在于,所述装置还包括第二风机;4. The device according to claim 1, wherein the device further comprises a second fan; 所述第二风机设置在所述热风主管道与所述锅炉风烟系统之间,用于抽出所述热风主管道内的热风并向所述锅炉风烟系统输送所述热风。The second fan is arranged between the main hot air duct and the boiler fume system, and is used to extract the hot air in the main hot air duct and deliver the hot air to the boiler fume system. 5.根据权利要求4所述的装置,其特征在于,所述锅炉包括一次风暖风器和二次风暖风器;5. The device according to claim 4, wherein the boiler comprises a primary air heater and a secondary air heater; 所述第二风机设置有吸风口和送风口;The second fan is provided with an air suction port and an air supply port; 所述热风主管道包括第一热风管道和第二热风管道;The hot air main duct includes a first hot air duct and a second hot air duct; 所述空冷顶盖通过所述第一热风管道与所述第二风机的吸风口连接;The air-cooled top cover is connected to the air suction port of the second fan through the first hot air duct; 所述第二风机的送风口通过所述第二热风管道与所述一次风暖风器的吸风口以及二次风暖风器的吸风口连接,用于为所述一次风暖风器和二次风暖风器提供热风源。The air supply port of the second fan is connected to the air suction port of the primary air heater and the air suction port of the secondary air heater through the second hot air duct, and is used for the primary air heater and the secondary air heater. The secondary air heater provides the hot air source. 6.根据权利要求1至5中任一项所述的装置,其特征在于,所述空冷岛本体由金属材质制成,所述空冷顶盖由金属材质制成。6 . The device according to claim 1 , wherein the air-cooling island body is made of a metal material, and the air-cooled top cover is made of a metal material. 7 . 7.根据权利要求6所述的装置,其特征在于,所述金属材质为彩钢。7. The device according to claim 6, wherein the metal material is color steel. 8.根据权利要求6所述的装置,其特征在于,所述空冷岛本体包括空冷岛围墙;8. The device according to claim 6, wherein the air-cooling island body comprises an air-cooling island enclosure; 所述空冷岛围墙与所述空冷顶盖通过焊接方式固定连接。The air-cooling island enclosure wall and the air-cooling top cover are fixedly connected by welding. 9.根据权利要求1至5中任一项所述的装置,其特征在于,所述装置包括若干个空冷散热片和若干个第一风机;9. The device according to any one of claims 1 to 5, wherein the device comprises several air cooling fins and several first fans; 所述若干个空冷散热片平行排列设置在所述空冷岛本体内;The plurality of air-cooling fins are arranged in parallel in the air-cooling island body; 所述若干个第一风机平行排列在所述若干个空冷散热片下方,且与所述空冷散热片一一对应。The plurality of first fans are arranged in parallel below the plurality of air-cooling fins and correspond to the air-cooling fins one-to-one. 10.根据权利要求1至5中任一项所述的装置,其特征在于,所述排汽管道贴合在所述空冷散热片外部。10. The device according to any one of claims 1 to 5, wherein the exhaust duct is fitted outside the air cooling fins.
CN202210487362.2A 2022-05-06 2022-05-06 Hot-blast device of recycling in air cooling island Pending CN114993068A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210487362.2A CN114993068A (en) 2022-05-06 2022-05-06 Hot-blast device of recycling in air cooling island

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210487362.2A CN114993068A (en) 2022-05-06 2022-05-06 Hot-blast device of recycling in air cooling island

Publications (1)

Publication Number Publication Date
CN114993068A true CN114993068A (en) 2022-09-02

Family

ID=83025601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210487362.2A Pending CN114993068A (en) 2022-05-06 2022-05-06 Hot-blast device of recycling in air cooling island

Country Status (1)

Country Link
CN (1) CN114993068A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201926327U (en) * 2010-10-20 2011-08-10 中国电力工程顾问集团西北电力设计院 Device for improving energy efficiency of mechanical ventilation direct air-cooling condenser
CN203657534U (en) * 2013-10-31 2014-06-18 华北电力大学(保定) Air cooling and radiating unit for air cooling island of direct air cooling machine group
CN203848317U (en) * 2013-12-30 2014-09-24 哈尔滨空调股份有限公司 Air inlet device of direct-air-cooling boiler
CN106225005A (en) * 2016-08-31 2016-12-14 吉林省电力科学研究院有限公司 A kind of Direct Air-Cooled tower waste heat circulation system
WO2018014768A1 (en) * 2016-07-21 2018-01-25 京能(锡林郭勒)发电有限公司 Residual heat reuse system for turbine-boiler integrated heat energy circulation
CN208818022U (en) * 2018-06-22 2019-05-03 华北电力大学(保定) A direct air-cooled condenser air-cooled island hot air recovery system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201926327U (en) * 2010-10-20 2011-08-10 中国电力工程顾问集团西北电力设计院 Device for improving energy efficiency of mechanical ventilation direct air-cooling condenser
CN203657534U (en) * 2013-10-31 2014-06-18 华北电力大学(保定) Air cooling and radiating unit for air cooling island of direct air cooling machine group
CN203848317U (en) * 2013-12-30 2014-09-24 哈尔滨空调股份有限公司 Air inlet device of direct-air-cooling boiler
WO2018014768A1 (en) * 2016-07-21 2018-01-25 京能(锡林郭勒)发电有限公司 Residual heat reuse system for turbine-boiler integrated heat energy circulation
CN106225005A (en) * 2016-08-31 2016-12-14 吉林省电力科学研究院有限公司 A kind of Direct Air-Cooled tower waste heat circulation system
CN208818022U (en) * 2018-06-22 2019-05-03 华北电力大学(保定) A direct air-cooled condenser air-cooled island hot air recovery system

Similar Documents

Publication Publication Date Title
CN201412195Y (en) Device for directly utilizing condensation heat of steam exhausted from steam turbine of power plant
CN106765760A (en) A kind of heating system for reclaiming computer room liquid-cooling heat radiation amount
CN101551201A (en) Thermal power plant combined ventilation direct air cooling system
CN106196125B (en) A kind of exhaust-gas treatment structure applied to incinerator
CN204100844U (en) Thermal power plant's Air-cooled Unit hot-air recycling system
CN104533545A (en) Novel air cooling system
CN202485478U (en) Direct air-cooling condensing system with peak cooler
CN114993068A (en) Hot-blast device of recycling in air cooling island
CN210053752U (en) Packaging and printing equipment heat abstractor
CN201497387U (en) Direct air cooling system for combined ventilation of heat power plant
CN207585383U (en) A kind of cooling device of high-temperature flue gas
CN102607291A (en) Direct air-cooling and condensing system with peak cooler
CN201650390U (en) A device capable of reducing condensation loss of steam turbine exhaust in a power plant
CN210835973U (en) Computer water-cooling turbine radiator
CN206458610U (en) A kind of thermoelectricity house service pump cooling device
CN206073125U (en) A kind of Direct Air-Cooled tower waste heat circulation system
CN212992804U (en) Novel electromechanical device's heat dissipation protection device
CN213396660U (en) Explosion-proof water-cooled heat pipe exchanger device
CN204402591U (en) A kind of novel air cooling system
CN207962704U (en) A kind of hot-air system of energy-saving, environmental protection boiler
CN217442309U (en) Condensation suspension tower
CN219776413U (en) Feed factory exhaust gas waste heat recycling device
CN105698209B (en) A kind of cooling tower warm wind heat utilization system indirectly
CN211040998U (en) VOC exhaust treatment device
CN215491175U (en) High-efficient waste heat recovery cooling tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination