CN114892874A - A kind of containment long-span dome and its construction method - Google Patents
A kind of containment long-span dome and its construction method Download PDFInfo
- Publication number
- CN114892874A CN114892874A CN202210444362.4A CN202210444362A CN114892874A CN 114892874 A CN114892874 A CN 114892874A CN 202210444362 A CN202210444362 A CN 202210444362A CN 114892874 A CN114892874 A CN 114892874A
- Authority
- CN
- China
- Prior art keywords
- pouring
- section
- dome
- pouring section
- containment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B7/00—Roofs; Roof construction with regard to insulation
- E04B7/08—Vaulted roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional [3D] extent, e.g. lattice girders
- E04C5/0636—Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G9/00—Forming or shuttering elements for general use
- E04G9/02—Forming boards or similar elements
- E04G9/06—Forming boards or similar elements the form surface being of metal
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种安全壳大跨度穹顶,包括第一浇筑段、浇筑层及第二浇筑段,所述第一浇筑段连接于混凝土牛腿上,且与混凝土牛腿呈夹角;所述浇筑层呈弧形,一端连接于所述第一浇筑段上,其弧度方向朝向靠近地面的一方,且朝远离所述第一浇筑段的方向延伸;所述第二浇筑段的数量至少为一个,至少一个所述第二浇筑段连接于所述浇筑层远离地面的一面,与所述第二浇筑段贴合,并与所述第一浇筑段连接;所述第一浇筑段与所述第二浇筑段及所述浇筑层的连接处设置有环向主梁。本发明还提供一种安全壳大跨度穹顶的施工方法,采用本发明所述的安全壳大跨度穹顶及施工方法可在施工过程中,减少脚手架的搭建。
The invention relates to a large-span dome of a containment shell, comprising a first pouring section, a pouring layer and a second pouring section. The first pouring section is connected to the concrete corbel and forms an included angle with the concrete corbel; the pouring section The layer is arc-shaped, one end is connected to the first pouring section, and its arc direction is toward the side close to the ground and extends away from the first pouring section; the number of the second pouring section is at least one, At least one of the second pouring sections is connected to the side of the pouring layer away from the ground, is attached to the second pouring section, and is connected to the first pouring section; the first pouring section is connected to the second pouring section. An annular main beam is arranged at the connection between the pouring section and the pouring layer. The invention also provides a construction method for a large-span dome of a containment shell, and the use of the large-span dome of a containment shell and the construction method of the invention can reduce the construction of scaffolding during the construction process.
Description
技术领域technical field
本发明属于建筑结构的设计及施工领域,具体涉及一种安全壳大跨度穹顶及其施工方法。The invention belongs to the field of design and construction of building structures, in particular to a containment large-span dome and a construction method thereof.
背景技术Background technique
核电厂外层安全壳穹顶布置在反应堆厂房内层安全壳穹顶正上方,其具有施工可操作空间小、跨度大、厚度大、自重大等特点,属于超过一定规模的危险性较大工程,存在较大的施工风险和施工难度。The outer containment dome of the nuclear power plant is arranged directly above the inner containment dome of the reactor building. It has the characteristics of small construction and operation space, large span, large thickness, and self-heavy weight. It is a dangerous project exceeding a certain scale. Greater construction risk and construction difficulty.
目前,在核电项目中,一般采用传统的满堂撑脚手架施工方法,脚手架搭设与拆除工程量大,需要耗费大量的材料、人工及工期;且内壳为球形,人员通行问题比较突出,导致内外壳无可靠的工作平面,需搭设临时平台。混凝土施工荷载,直接传递到内壳穹顶,影响内穹顶的安全性,而且,内、外壳穹顶施工存在交叉作业,需要中途拆除脚手架工程,严重影响施工工期。At present, in nuclear power projects, the traditional construction method of full-floor scaffolding is generally adopted. The erection and dismantling of the scaffolding requires a lot of materials, labor and construction time; and the inner shell is spherical, and the problem of personnel passage is relatively prominent, resulting in the inner shell. There is no reliable working plane, and a temporary platform needs to be set up. The concrete construction load is directly transmitted to the inner shell dome, which affects the safety of the inner dome. Moreover, the construction of the inner dome and the outer shell dome has cross operations, which requires the removal of the scaffolding work in the middle, which seriously affects the construction period.
因此,需要一种受工作环境影响小、工程量小、施工耗费成本低的安全壳大跨度穹顶及施工方法。Therefore, there is a need for a large-span containment dome and a construction method that is less affected by the working environment, has a small amount of engineering, and has low construction costs.
发明内容SUMMARY OF THE INVENTION
针对现有技术中存在的缺陷,本发明的目的是提供一种安全壳大跨度穹顶及其施工方法以降低施工的繁琐程度。In view of the defects existing in the prior art, the purpose of the present invention is to provide a large-span dome of a containment and a construction method thereof to reduce the cumbersome degree of construction.
为达到以上目的,本发明采用的技术方案是:一种安全壳大跨度穹顶包括第一浇筑段、浇筑层及第二浇筑段,所述第一浇筑段连接于混凝土牛腿上,且与混凝土牛腿呈夹角;所述浇筑层呈弧形,一端连接于所述第一浇筑段上,其弧度方向朝向靠近地面的一方,且朝远离所述第一浇筑段的方向延伸;所述第二浇筑段的数量至少为一个,至少一个所述第二浇筑段连接于所述浇筑层远离地面的一面,与所述第二浇筑段贴合,并与所述第一浇筑段连接;所述第一浇筑段与所述第二浇筑段及所述浇筑层的连接处设置有环向主梁。In order to achieve the above purpose, the technical scheme adopted in the present invention is: a large-span dome of a containment shell includes a first pouring section, a pouring layer and a second pouring section, and the first pouring section is connected to the concrete corbel, and is connected with the concrete. The corbel is at an included angle; the pouring layer is in an arc shape, one end is connected to the first pouring section, and its arc direction is toward the side close to the ground and extends away from the first pouring section; the first pouring section is The number of the second pouring sections is at least one, and at least one of the second pouring sections is connected to the side of the pouring layer away from the ground, is attached to the second pouring section, and is connected to the first pouring section; the An annular main beam is arranged at the connection between the first pouring section, the second pouring section and the pouring layer.
进一步,所述第二浇筑段的数量为多个,多个所述第二浇筑段之间皆设置有所述环向主梁。Further, the number of the second pouring sections is multiple, and the annular main beams are arranged between the plurality of second pouring sections.
进一步,所述环向主梁处设置有连接拉筋,以防止浇筑后所述环向主梁的脱落。Further, the annular main beam is provided with connecting ties to prevent the annular main beam from falling off after pouring.
进一步,所述连接拉筋以焊接或套筒连接进行连接。Further, the connecting tie bars are connected by welding or sleeve connection.
进一步,所述浇筑层处还设置有分布钢筋。Further, distribution steel bars are also arranged at the pouring layer.
进一步,所述第二浇筑段上还设置有抗剪栓钉,以防止连接处混凝土滑移。Further, shear studs are also provided on the second pouring section to prevent the concrete from slipping at the connection.
进一步,所述第一浇筑段及所述第二浇筑段上还设置有穹顶钢筋,以增加浇筑后使用的安全性。Further, dome steel bars are also provided on the first pouring section and the second pouring section to increase the safety of use after pouring.
进一步,所述环向主梁为H型钢。Further, the annular main beam is H-beam.
进一步,所述通过焊接连接于所述第一浇筑段与浇筑层及所述第二浇筑段的连接处。Further, the welding is connected to the connection between the first pouring section, the pouring layer and the second pouring section.
本发明还提供一种安全壳大跨度穹顶的施工方法,其包括步骤:整体吊装固定穹顶施工钢模板;在施工缝处设置环向主梁,并在环向主梁处设置连接拉筋;绑扎穹顶钢筋,并浇筑第一浇筑段,形成第一段混凝土;在浇筑层处设置分布钢筋,并对浇筑层进行浇筑;在第二浇筑段处设置抗剪栓钉及连接拉筋;绑扎穹顶钢筋,浇筑第二段混凝土。The invention also provides a construction method for a large-span dome of a containment shell, which comprises the steps of: hoisting and fixing the steel formwork for the construction of the dome as a whole; arranging an annular main beam at the construction joint, and setting a connecting tie at the annular main beam; binding Dome steel bars, and pour the first pouring section to form the first section of concrete; set distribution steel bars at the pouring layer, and pour the pouring layer; set shear studs and connecting ties at the second pouring section; bind the dome steel bars , pour the second section of concrete.
本发明的效果在于:通过第一浇筑段、浇筑层及第二浇筑段分段浇筑的形式,可在施工过程中,取消脚手架的搭建,克服了传统施工方法脚手架搭设工程量大、施工风险大、交叉作业等缺点,保证了钢模板的施工安全,提高了现场施工效率,避免了交叉作业,缩短了施工周期。The effect of the present invention is that the construction of scaffolding can be canceled in the construction process through the form of segmented pouring of the first pouring section, the pouring layer and the second pouring section, and the traditional construction method overcomes the large amount of construction work and the high construction risk of scaffolding. , cross operation and other shortcomings, ensure the construction safety of the steel formwork, improve the on-site construction efficiency, avoid cross operation, and shorten the construction period.
附图说明Description of drawings
图1是本发明一种安全壳大跨度穹顶的剖面结构示意图;Fig. 1 is the sectional structure schematic diagram of a kind of containment long-span dome of the present invention;
图2是穹顶施工钢模板与钢筋的位置关系示意图;Figure 2 is a schematic diagram of the positional relationship between the dome construction steel formwork and the reinforcing bars;
图3是一种安全壳大跨度穹顶施工方法的步骤流程图。Fig. 3 is a flow chart of steps of a construction method for a large-span dome of a containment.
附图标记说明:Description of reference numbers:
10、第一浇筑段;20、浇筑层;30、第二浇筑段;10. The first pouring section; 20. The pouring layer; 30. The second pouring section;
21、分布钢筋;31、抗剪栓钉;40、环向主梁;41、连接拉筋;42、穹顶钢筋。21. Distribution steel bars; 31. Shear studs; 40. Circumferential main beams; 41. Connecting ties; 42. Dome steel bars.
具体实施方式Detailed ways
下面结合附图和具体实施方式对本发明作进一步描述。The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
如图1-3所示,本发明提供的一种安全壳大跨度穹顶,其包括第一浇筑段10、浇筑层20及第二浇筑段30,第一浇筑段10连接于混凝土牛腿上,且与混凝土牛腿呈夹角,形成有效的侧向支撑,以便于后续浇筑。浇筑层20呈弧形,一端连接于第一浇筑段10上,其弧度方向朝向靠近地面的一方,且朝远离第一浇筑段10的方向延伸。第二浇筑段30的数量至少为一个,至少一个的第二浇筑段30连接于浇筑层20远离地面的一面,皆与浇筑层20远离地面的一面贴合,并与第一浇筑段10连接,第一浇筑段10与浇筑层20及第二浇筑段30的连接处设置有环向主梁40,以增加第一浇筑段10与第二浇筑段30及浇筑层20的连接强度。As shown in Figures 1-3, the present invention provides a large-span containment dome, which includes a
可以理解,第一浇筑段10、浇筑层20及第二浇筑段30为穹顶的骨架,可以是整体连接好后,再吊装与混凝土牛腿连接,也可以是先与混凝土牛腿连接后,再依次连接。It can be understood that the
可以理解,第一浇筑段10、浇筑层20及第二浇筑段30皆由施工钢模板组成,如弧形钢板、型钢主梁、次梁等构件组成,具体的组成方式及组成结构视穹顶结构而定。It can be understood that the
可以理解,第二浇筑段30的数量根据浇筑载荷来确定,在载荷小的时候,第二浇筑段30可以为一个,优选的,第二浇筑段30的数量为多个。It can be understood that the number of the second pouring
可以理解,当第二浇筑段30的数量为多个时,多个第二浇筑段30依次连接,且皆连接于浇筑层20远离地面的一面上,其中,多个第二浇筑段30中靠近第一浇筑段10的一个,与第一浇筑段10连接。It can be understood that when the number of the second pouring
进一步地,第二浇筑段30为多个,多个第二浇筑段30之间皆设置有环向主梁40。Further, there are a plurality of second pouring
进一步地,环向主梁40处皆设置有连接拉筋41,以防止在浇筑后,环向主梁40脱落。Further, connecting
进一步地,连接拉筋41通过螺纹套筒或焊接的方式进行连接。Further, the connecting
可以理解,连接拉筋41可以是任意结构,其只要能起到浇筑后,防止环向主梁40掉落的效果即可。It can be understood that the connecting
进一步地,浇筑层20处设置有分布钢筋21,通过设置分布钢筋21,以在浇筑后,具有更大承载力。Further,
进一步地,第二浇筑段30上还设置有抗剪栓钉31,通过设置抗剪栓钉31,防止连接处混凝土滑移。Further, the second pouring
进一步地,第一浇筑段10及第二浇筑段30上还设置有穹顶钢筋42,通过设置穹顶钢筋42,以增加浇筑后使用的安全性。Further, the first pouring
可以理解,环向主梁40为H型钢,其通过焊接的方式,设置于施工缝处。It can be understood that the circumferential
可以理解,施工缝即为第一浇筑段10与浇筑层、第一浇筑段10与第二浇筑段30及多个第二浇筑段30之间的连接处。It can be understood that the construction joint is the connection between the first pouring
在本发明中,在第一浇筑段10、浇筑层20、第二浇筑段30、环向主梁40的钢结构完成预制后,通过整体吊装,按照上述方式固定在混凝土牛腿上,然后利用混凝土浇筑第一浇筑段10,形成第一段混凝土,接着浇筑混凝土层,形成浇筑层20,最后浇筑至少为一个的第二段浇筑段30,以完成安全壳大跨度穹顶的施工。In the present invention, after the steel structures of the first pouring
本发明还提供一种大跨度穹顶的施工方法,其包括步骤:The present invention also provides a construction method of a large-span dome, comprising the steps of:
S1,整体吊装固定穹顶施工钢模板;S1, the overall hoisting fixed dome construction steel formwork;
具体的,在穹顶的施工钢模板,包括弧形钢板、型钢主梁、次梁等构建预制完成后,将其通过吊装的方式,整体固定在混凝土牛腿上。Specifically, after the prefabrication of the construction steel formwork of the dome, including the arc-shaped steel plate, the main beam of profiled steel, the secondary beam, etc., is completed, it is fixed on the concrete corbel as a whole by means of hoisting.
以一个具体实例作为说明,当第一浇筑段、浇筑层、第二浇筑段及环向主梁完成预制后,将第一浇筑段的一端连接在混凝土牛腿上,另一端连接浇筑层及第二浇筑段,以完成穹顶各个施工钢模板的连接于固定。Taking a specific example as an illustration, after the prefabrication of the first pouring section, the pouring layer, the second pouring section and the circumferential girder is completed, one end of the first pouring section is connected to the concrete corbel, and the other end is connected to the pouring layer and the third section. The second pouring section is to complete the connection and fixation of each construction steel formwork of the dome.
可以理解,连接方式可以是螺钉、焊接、卡接等任意方式,只要能够将其进行固定即可。It can be understood that the connection method can be any method such as screw, welding, snap connection, etc., as long as it can be fixed.
S2,在施工缝处设置环向主梁,并在环向主梁处设置连接拉筋;S2, set up circumferential main beams at the construction joints, and set up connecting ties at the circumferential main beams;
具体的,在穹顶整体的施工钢模板吊装固定后,在施工缝处设置环向主梁,以加强连接整体施工模板的每一段,如第一浇筑段与浇筑层及第二浇筑段。Specifically, after the overall construction steel formwork of the dome is hoisted and fixed, a circumferential main beam is set at the construction joint to strengthen each section connecting the overall construction formwork, such as the first pouring section, the pouring layer and the second pouring section.
通过螺纹套或焊接的方式设置连接拉筋,以防止施工缝隙处的施工钢模板在浇筑后,受拉导致环向主梁脱落。Connecting tie bars are set by threaded sleeves or welding to prevent the construction steel formwork at the construction gap from being pulled off after pouring and causing the hoop girder to fall off.
S3,绑扎穹顶钢筋,并浇筑第一浇筑段,形成第一段混凝土;S3, bind the dome steel bars, and pour the first pouring section to form the first section of concrete;
具体的,在施工缝隙处设置好环向主梁,并设置好连接拉筋后,在第一浇筑段10上绑扎穹顶钢筋,先对第一浇筑段进行浇筑,形成第一混凝土段,进而形成对浇筑层和第二浇筑段的钢模板的侧向支撑。Specifically, after setting the girder in the construction gap and setting up the connecting tie bars, the dome steel bars are bound on the first pouring
S4,在浇筑层处设置分布钢筋,并对浇筑层进行浇筑;S4, set distribution steel bars at the pouring layer, and pour the pouring layer;
具体的,通过设置分布钢筋至浇筑层的表面,接着进行浇筑,形成具有更大承载力钢模板。Specifically, by arranging and distributing steel bars to the surface of the pouring layer, and then pouring, a steel formwork with greater bearing capacity is formed.
S5,在第二浇筑段处设置抗剪栓钉及连接拉筋;S5, set shear studs and connecting ties at the second pouring section;
具体的,在第二浇筑段的径向型钢主梁表面设置抗剪栓钉,以防止在浇筑后,施工缝界面混凝土滑移,在第二浇筑段上的环向主梁处设置连接拉筋,防止浇筑后,施工缝处的环向主梁脱落。Specifically, shear studs are arranged on the surface of the radial section steel main beam of the second pouring section to prevent the concrete from slipping at the interface of the construction joint after pouring, and connecting ties are arranged at the circumferential main beam on the second pouring section , to prevent the annular main beam at the construction joint from falling off after pouring.
S6,绑扎穹顶钢筋,浇筑第二段混凝土;S6, tie the dome steel bars, and pour the second section of concrete;
具体的,在完成上述步骤后,对第二浇筑段进行绑扎穹顶钢筋并浇筑,以形成第二段混凝土。Specifically, after the above steps are completed, the second pouring section is bound with dome steel bars and poured to form the second section of concrete.
通过上述实施例可以看出,本发明能够在核电厂外层安全大跨度穹顶的施工中,针对其施工可操作空间小、跨度大、厚度大、自重大等特点,省略脚手架的搭建,无需临时搭建平台,降低工作量。。It can be seen from the above-mentioned embodiments that the present invention can be used in the construction of the outer safety large-span dome of the nuclear power plant, in view of the characteristics of small construction operable space, large span, large thickness and self-heavy weight, etc., the construction of scaffolding is omitted, and there is no need for temporary Build a platform to reduce workload. .
本发明所述的装置并不限于具体实施方式中所述的实施例,本领域技术人员根据本发明的技术方案得出其他的实施方式,同样属于本发明的技术创新范围。The device described in the present invention is not limited to the embodiments described in the specific embodiments, and those skilled in the art can obtain other embodiments according to the technical solutions of the present invention, which also belong to the technical innovation scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210444362.4A CN114892874B (en) | 2022-04-26 | 2022-04-26 | Safety shell large-span dome and construction method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210444362.4A CN114892874B (en) | 2022-04-26 | 2022-04-26 | Safety shell large-span dome and construction method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN114892874A true CN114892874A (en) | 2022-08-12 |
| CN114892874B CN114892874B (en) | 2024-07-16 |
Family
ID=82719159
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210444362.4A Active CN114892874B (en) | 2022-04-26 | 2022-04-26 | Safety shell large-span dome and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114892874B (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116607636A (en) * | 2023-06-26 | 2023-08-18 | 中国核电工程有限公司 | Nuclear engineering dome and construction method thereof |
| CN117386121A (en) * | 2023-11-09 | 2024-01-12 | 中国核工业华兴建设有限公司 | Aluminum alloy template for containment spherical dome and its design method and construction method |
| CN118309253A (en) * | 2024-06-07 | 2024-07-09 | 北京城建集团有限责任公司 | Reinforced concrete dome structure template system and construction method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110761469A (en) * | 2019-10-29 | 2020-02-07 | 中海石油气电集团有限责任公司 | Layered and annular pouring control method for pressure-maintaining dome concrete in LNG storage tank stage |
| CN110761411A (en) * | 2019-11-11 | 2020-02-07 | 中国葛洲坝集团第二工程有限公司 | Large-span suspended spherical dome concrete pouring method |
| CN110905113A (en) * | 2019-10-23 | 2020-03-24 | 浙江勤业建工集团有限公司 | Construction method of large-span concrete dome structure |
| CN111576950A (en) * | 2020-04-09 | 2020-08-25 | 中核能源科技有限公司 | A kind of reactor single-layer containment and its construction method |
| CN113653241A (en) * | 2021-08-04 | 2021-11-16 | 中国建筑第八工程局有限公司 | Construction method of large-span special-shaped curved surface concrete dome structure |
-
2022
- 2022-04-26 CN CN202210444362.4A patent/CN114892874B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110905113A (en) * | 2019-10-23 | 2020-03-24 | 浙江勤业建工集团有限公司 | Construction method of large-span concrete dome structure |
| CN110761469A (en) * | 2019-10-29 | 2020-02-07 | 中海石油气电集团有限责任公司 | Layered and annular pouring control method for pressure-maintaining dome concrete in LNG storage tank stage |
| CN110761411A (en) * | 2019-11-11 | 2020-02-07 | 中国葛洲坝集团第二工程有限公司 | Large-span suspended spherical dome concrete pouring method |
| CN111576950A (en) * | 2020-04-09 | 2020-08-25 | 中核能源科技有限公司 | A kind of reactor single-layer containment and its construction method |
| CN113653241A (en) * | 2021-08-04 | 2021-11-16 | 中国建筑第八工程局有限公司 | Construction method of large-span special-shaped curved surface concrete dome structure |
Non-Patent Citations (1)
| Title |
|---|
| 史晨程等: ""‘华龙一号’外层安全壳穹顶钢模板优化设计经验总结"", 《核科学与工程》, vol. 41, no. 1, pages 154 - 160 * |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116607636A (en) * | 2023-06-26 | 2023-08-18 | 中国核电工程有限公司 | Nuclear engineering dome and construction method thereof |
| CN116607636B (en) * | 2023-06-26 | 2026-04-10 | 中国核电工程有限公司 | Nuclear Engineering Dome and its Construction Method |
| CN117386121A (en) * | 2023-11-09 | 2024-01-12 | 中国核工业华兴建设有限公司 | Aluminum alloy template for containment spherical dome and its design method and construction method |
| CN118309253A (en) * | 2024-06-07 | 2024-07-09 | 北京城建集团有限责任公司 | Reinforced concrete dome structure template system and construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN114892874B (en) | 2024-07-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2022161084A1 (en) | Fabricated concrete beam column joint and construction method therefor | |
| WO2022160386A1 (en) | Prefabricated assembly-type frame, prefabricated assembly-type beam-column joint and construction method therefor | |
| CN114892874A (en) | A kind of containment long-span dome and its construction method | |
| CN106677049A (en) | Assembled steel-concrete combination structure bridge and construction method | |
| WO2023279680A1 (en) | Fabricated concrete beam-column joint and construction method therefor | |
| CN112502714B (en) | Assembled shaft barrel structure and design and construction method | |
| CN104947588B (en) | Concrete-filled steel tube-composite girder cable-stayed bridge deck system and its construction method | |
| CN107989447A (en) | A kind of large-scale earthing concrete tank dome steel support structure and installation method | |
| CN113216409A (en) | Connecting structure of precast concrete tubular pile column with diagonal bracing and hollow floor or flat floor | |
| CN102261145A (en) | Integrally two-way and locally one-way steel-concrete slab composite floor system and construction method thereof | |
| CN108775084B (en) | Steel-concrete composite prefabricated beam and prefabricated column connection structure and construction method | |
| CN117845718B (en) | Reinforced concrete skeleton outsourcing prefabricated UHPC board arched bridge | |
| CN207919746U (en) | A kind of prefabricated node of high-strength high concrete assembled frame of ductility | |
| CN110700103B (en) | Construction method of continuous composite beam | |
| CN210086505U (en) | A detachable steel beam-concrete-filled steel tubular column through-core connection node | |
| CN211772853U (en) | An assembled suspension bridge tower | |
| CN209891049U (en) | The connection structure of the pier and the cover beam and the bridge | |
| CN116411702A (en) | Construction Method of Long-span Reinforced Concrete Horizontal Members | |
| CN115434425A (en) | Lattice type steel reinforced concrete prefabricated beam column joint and method | |
| CN212104818U (en) | Prefabricated reinforced concrete structural columns and connecting nodes | |
| CN221896741U (en) | Prefabricated concrete tower structure | |
| CN211228890U (en) | Novel steel-concrete-FRP combined structure | |
| CN112854603A (en) | Connecting structure of precast concrete tubular pile column and hollow floor or flat floor | |
| CN119083321A (en) | Prefabricated steel pipe inner core wrapped with UHPC arch rib connection node, arch bridge and method | |
| CN110080461A (en) | A kind of prestressing force regeneration concrete empty stomach composite beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
