CN114892819A - Pre-closing construction method for wall body of pipeline dense area - Google Patents

Pre-closing construction method for wall body of pipeline dense area Download PDF

Info

Publication number
CN114892819A
CN114892819A CN202210642953.2A CN202210642953A CN114892819A CN 114892819 A CN114892819 A CN 114892819A CN 202210642953 A CN202210642953 A CN 202210642953A CN 114892819 A CN114892819 A CN 114892819A
Authority
CN
China
Prior art keywords
pipeline
wall
wall body
chilled water
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210642953.2A
Other languages
Chinese (zh)
Inventor
田冰
廖雅
蒋俊志
罗敏学
周宋南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau
Original Assignee
Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau filed Critical Third Construction Shenzhen Co ltd Of China Construction Fifth Engineering Bureau
Priority to CN202210642953.2A priority Critical patent/CN114892819A/en
Publication of CN114892819A publication Critical patent/CN114892819A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/39Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra
    • E04C1/392Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra for ventilating, heating or cooling
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/39Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra
    • E04C1/397Building elements of block or other shape for the construction of parts of buildings characterised by special adaptations, e.g. serving for locating conduits, for forming soffits, cornices, or shelves, for fixing wall-plates or door-frames, for claustra serving for locating conduits

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention is suitable for the technical field of wall construction, and provides a pre-closing construction method for a wall in a pipeline dense area. The construction method includes the steps of comprehensively arranging a pipeline dense area in advance by means of a BIM technology, automatically typesetting brickworks of a wall body before drawing, accurately positioning pipeline wall penetrating positions of the pipeline dense area, optimizing concrete prefabricated blocks in advance by means of the BIM technology, performing three-dimensional arrangement on the concrete prefabricated blocks, analyzing and calculating to obtain the optimal size of the concrete prefabricated blocks, manufacturing concrete prefabricated block embedded parts before construction, embedding wall penetrating sleeves and reinforcing steel bars according to the size, pouring light aggregate concrete, and ensuring the fireproof performance of the concrete prefabricated blocks. After the wall body is built to the pipeline wall penetrating position of the pipeline dense area, the pipeline prefabricated blocks are installed on the wall body in a modularized mode, the wall body is guaranteed to have good air tightness, and the pipeline wall penetrating device has the advantages of being simple in construction process and short in period.

Description

Pre-closing construction method for wall body of pipeline dense area
Technical Field
The invention belongs to the technical field of wall construction, and particularly relates to a pre-closing construction method for a wall in a pipeline dense area.
Background
In the building construction, scientific and reasonable configuration of electromechanical pipelines plays an important role in successful development and implementation of building engineering, so that a building engineering project needs to master a pipeline comprehensive arrangement technology, the reasonable arrangement of pipeline arrangement is strengthened, and pipelines can be used for a water supply pipe and an air pipe to pass through so as to realize sealing and ensure the construction quality.
In the existing wall construction of pipeline through-wall, a pipeline opening is reserved at the dense position of a pipeline of a wall body, and the opening is subjected to fireproof plugging after the pipeline is installed, so that the situation that the fireproof plugging is not tight can be generated, the fireproof performance and the air tightness of the wall are poor, the appearance and the quality are influenced, the construction process is complex, and the period is long.
Disclosure of Invention
The technical problem to be solved by the embodiment of the invention is to provide a pre-sealing construction method for a wall body of a pipeline dense area, and the method is used for solving the problems of poor fire resistance, poor air tightness, complex construction procedures and long construction period in the pre-sealing construction of the wall body of the pipeline dense area in the prior art.
The embodiment of the invention is realized in such a way that a pre-closing construction method for a wall body of a pipeline dense area is provided, which comprises the following steps:
s1, before wall construction, automatically typesetting the wall of the pipeline dense area in advance by utilizing BIM technology under civil engineering and electromechanical collision inspection, accurately positioning the pipeline wall-penetrating position of the pipeline dense area, simulating the closed construction of the wall of the pipeline dense area in advance, and carrying out final deepening drawing on the selected wall of the pipeline dense area by utilizing BIM technology to obtain a deepened drawing of the pipeline of the wall;
s2, carrying out three-dimensional arrangement on the concrete precast blocks for closing the pipeline wall-penetrating positions by adopting a BIM technology to obtain the sizes of the concrete precast blocks;
s3, setting a template according to the size of the concrete precast block, making a mold, embedding embedded wall bushing, and embedding reinforcing steel bars in the concrete precast block according to design requirements and specifications;
s4, pouring light aggregate concrete into the mould, removing the template after the light aggregate concrete reaches the strength, and forming the concrete precast block into a pipeline precast block with a through hole at one time;
s5, constructing the wall body of the pipeline dense area according to the wall body dense pipeline deepening map, installing the pipeline precast blocks at the pipeline wall penetrating position of the pipeline dense area after the wall body is built to the pipeline wall penetrating position of the pipeline dense area, accurately placing the installation positions and the elevations according to the wall body dense pipeline deepening map, closely connecting the pipeline precast blocks and the wall body, enabling the pipeline precast blocks to be installed on the wall body in a modularized mode, and enabling the wall penetrating sleeve to penetrate through the wall body.
Further, the pipeline prefabricated section includes water pipe prefabricated section and tuber pipe prefabricated section, the wall bushing includes refrigerated water return sleeve pipe, refrigerated water supply sleeve pipe and ventilation sleeve pipe.
Further, in step S3, the quality of the water pipe prefabricated block and the air pipe prefabricated block is accurately controlled through analysis and calculation, the molds of the water pipe prefabricated block and the air pipe prefabricated block are manufactured respectively according to the wall intensive pipeline deepening drawing, the molds of the water pipe prefabricated block and the air pipe prefabricated block are cut and assembled according to the size, the redundant molds are cut by a cutting machine, the molds are spliced by reinforcing and connecting members, and the chilled water return sleeve, the chilled water supply sleeve and the ventilation sleeve customized for the selected area are accurately placed in the molds during operation, so that the molds are ensured to be compact and firm. .
Furthermore, according to the wall body intensive pipeline deepening drawing, the chilled water return sleeve, the chilled water supply sleeve and the ventilation sleeve are pre-embedded in a die for manufacturing the water pipe prefabricated block, and the axial lengths of the chilled water return sleeve, the chilled water supply sleeve and the ventilation sleeve are smaller than or equal to the thickness of the wall body.
Further, in the step S3, the reinforcing bars are uniformly arranged around the wall bushing.
Further, in the step S4, in the process of pouring the lightweight aggregate concrete into the mold, the vibrating rod is used to vibrate in time, the vibrating time is controlled, the dense combination and the flat surface of the lightweight aggregate concrete are ensured, the cellular pitted surface and the bubble phenomenon of the concrete are eliminated, the strength of the concrete is ensured, after the pouring is completed, the concrete precast block is immediately cured, the curing period is kept for at least 7 days, the anti-permeability requirement of the doped retarding additive is not less than 14 days, the watering and wetting curing are carried out, and when the curing is covered by a plastic film, the sealing is kept.
Further, after the step S5, the method further includes the following steps:
s6, correspondingly installing a chilled water return pipe on the chilled water return sleeve, correspondingly installing a chilled water supply pipe on the chilled water supply sleeve, correspondingly installing an air pipe on the ventilation sleeve, wherein the chilled water return pipe is connected with the chilled water return sleeve, the chilled water supply pipe is connected with the chilled water supply sleeve and the air pipe is connected with the ventilation sleeve through sealant.
Compared with the prior art, the embodiment of the invention has the advantages that: according to the pre-sealing construction method for the wall body of the pipeline dense area, provided by the invention, comprehensive arrangement is carried out on the pipeline dense area in advance under civil engineering and electromechanical collision inspection by means of the BIM technology, and a picture is drawn by one key of software, so that the time for selecting the dense pipeline area by contrasting a two-dimensional drawing is saved. The masonry of the wall is automatically typeset before drawing, the pipeline wall-penetrating position of the pipeline dense area is accurately positioned, the problem of successive construction of the electromechanical pipeline and the wall is effectively solved, and the accurate positioning of the size of the pipeline dense area is ensured; the concrete precast block is optimized in advance by adopting the BIM technology, three-dimensional arrangement is carried out on the concrete precast block, analysis and calculation are carried out, and the optimal size of the concrete precast block is obtained, so that in the wall construction process, when the concrete precast block is closely connected with a wall body, the construction procedures are reduced, and safety is ensured. In the secondary structure work progress, make the concrete precast block in advance according to the intensive pipeline deepening picture of wall body to carry out embedded wall bushing pre-buried according to the size, consolidate the back of fixing a position, carry out the reinforcing bar pre-buried outside the wall bushing in the mould of concrete precast block, pour light aggregate concrete again, ensure concrete precast block fire behavior, the piece one shot forming that buries. After the wall body is built to the pipeline wall penetrating position of the pipeline dense area, the pipeline precast blocks are installed on the wall body in a modularized mode, the wall body is guaranteed to have good air tightness, the problem that pipelines are difficult to block is effectively solved, and the pipeline wall has the advantages of being simple in construction process, short in period and high in safety performance.
Drawings
FIG. 1 is a schematic perspective view of a pre-closed structure of a wall in a dense pipeline area according to an embodiment of the present invention;
fig. 2 is a schematic view of an elevation structure in which the water pipe precast block and the air pipe precast block of fig. 1 are modularly installed on a wall body.
The figures are numbered:
1. a wall body; 2. water pipe prefabricated blocks; 3. a wind pipe prefabricated block; 4. a chilled water backwater sleeve; 5. a chilled water supply sleeve; 6. a chilled water return pipe; 7. a chilled water supply pipe; 8. a ventilation sleeve; 9. and (7) an air pipe.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1 and 2, the wall pre-sealing structure of a dense pipeline area provided in an embodiment of the present invention includes a wall 1, a water pipe prefabricated block 2, an air pipe prefabricated block 3, a wall bushing, a chilled water return pipe 6, a chilled water supply pipe 7, and an air pipe 9, where the wall bushing includes a chilled water return bushing 4, a chilled water supply bushing 5, and a ventilation bushing 9. Chilled water return pipe 4 runs through in water pipe prefabricated section 2 with chilled water supply casing 5 pre-buried on water pipe prefabricated section 2, and chilled water wet return 6 is installed on chilled water return pipe 4, and the chilled water delivery pipe is installed on chilled water supply casing 5, and ventilation sleeve 8 runs through in tuber pipe prefabricated section 3 pre-buried on tuber pipe prefabricated section 3, modular installation water pipe prefabricated section 2 and tuber pipe prefabricated section 3 on wall body 1.
The pre-closing construction method of the wall body of the pipeline dense area comprises the following steps:
s1, before the wall 1 is constructed, electromechanical pipelines of the wall 1 of the pipeline dense area are complex and complicated, the BIM technology is utilized to carry out comprehensive arrangement and automatic typesetting on the wall 1 of the pipeline dense area in advance under civil engineering and electromechanical collision check, the pipeline wall-penetrating position of the pipeline dense area is accurately positioned, the problem of successive construction of the electromechanical pipelines and the wall 1 is effectively solved, and the accurate positioning of the pipeline dense area is ensured; save the time of selecting dense pipeline district with reference to the two-dimensional drawing, ensure to become more meticulous, simulate the close construction of pipeline dense district wall body 1 in advance, carry out a key row brick to the pipeline dense district wall body 1 who selects through the BIM technique, reserve the entrance to a cave, confirm the refrigerated water return sleeve pipe 4 among the water pipe prefabricated section 2 and the tuber pipe 9 size among the refrigerated water supply sleeve pipe 5 and the tuber pipe prefabricated section 3, confirm water pipe prefabricated section 2 and the tuber pipe prefabricated section 3 size of sizes on the basis of wall body 1 and refrigerated water return sleeve pipe 4, refrigerated water supply sleeve pipe 5 and tuber pipe 9 position, carry out analysis and calculation to it after, carry out final deepening map again, obtain the dense pipeline deepening map of wall body.
And S2, carrying out three-dimensional arrangement on the concrete precast block at the position for closing the pipeline through the wall by adopting a BIM technology to obtain the accurate size of the concrete precast block.
And S3, setting a template according to the size of the concrete precast block, making a mold, embedding the embedded wall bushing, and embedding reinforcing steel bars in the concrete precast block according to design requirements and specifications.
Specifically, according to the intensive pipeline deepening drawing of wall body, through the accurate accuse of the water pipe prefabricated section 2 and 3 quality of wind pipe prefabricated section of analytic calculation, utilize the template, make the mould of water pipe prefabricated section 2 and wind pipe prefabricated section 3 respectively, assemble according to the size cutting, utilize the cutting machine to cut unnecessary template, recycle and consolidate connecting elements and carry out the template concatenation, carry out the accurate placing in the mould to the refrigerated water return sleeve pipe 4 of selected regional customization during the operation, refrigerated water supply sleeve pipe 5 and ventilation sleeve pipe 8, it is firm to ensure that the mould is tight real.
In the process of pre-embedding the chilled water return sleeve 4, the chilled water supply sleeve 5 and the ventilation sleeve 8 in the die for manufacturing the water pipe prefabricated block 2, the axial lengths of the chilled water return sleeve 4, the chilled water supply sleeve 5 and the ventilation sleeve 8 are less than or equal to the thickness of the wall body 1, and the die is tightly bonded by using a special adhesive.
When carrying out the arrangement of reinforcement to water pipe prefabricated section 2 and 3 components of tuber pipe prefabricated section, the reinforcing bar is evenly laid all around the wall bushing, evenly lays all around refrigerated water return sleeve 4, refrigerated water supply sleeve 5 and ventilation sleeve 8 promptly, and the reinforcing bar will accord with design and standard requirement, and reinforcing bar unloading length accords with design requirement and construction standard requirement according to component size, concrete protective layer thickness, reinforcing bar bending adjustment value and crotch increase length etc..
S4, after the chilled water return sleeve 4 and the chilled water supply sleeve 5 embedded in the water pipe precast block 2 and the steel bars are embedded and installed firmly and the ventilation sleeve 8 and the steel bars embedded in the air pipe precast block 3 and installed firmly, pouring light aggregate concrete with light dead weight, heat preservation, heat insulation, shock resistance, impermeability and good fire resistance into the mold, removing the mold after the concrete precast block reaches the strength, and forming the concrete precast block into the pipeline precast block with the through holes in one step.
Specifically, in step S4, during the process of pouring the lightweight aggregate concrete into the mold, the vibrating rod is used to vibrate in time, the vibrating time is controlled, the compact combination and the flat surface are ensured, the cellular pitted surface and the bubble phenomenon of the concrete are eliminated, the concrete strength is ensured, after the pouring is completed, the concrete precast block is immediately cured, the curing period is kept for at least 7 days, the delayed coagulation type admixture is doped, the anti-permeability requirement is not less than 14 days, the watering and wetting curing are carried out, and when the curing is covered by the plastic film, the sealing is kept.
S5, constructing the wall body 1 of the pipeline dense area according to the intensive pipeline deepening drawing of the wall body, installing the pipeline precast block at the pipeline wall penetrating position of the pipeline dense area after the wall body 1 is built to the pipeline wall penetrating position of the pipeline dense area, accurately placing the installation position and the elevation according to the intensive pipeline deepening drawing of the wall body 1, closely connecting the pipeline precast block and the wall body 1, enabling the pipeline precast block to be installed on the wall body 1 in a modularized mode, and enabling the wall penetrating sleeve to penetrate through the wall body 1.
S6, correspondingly installing the chilled water return pipe 6 on the chilled water return sleeve 4, correspondingly installing the chilled water supply pipe on the chilled water supply sleeve 5, correspondingly installing the air pipe 9 on the ventilation sleeve 8, and bonding the chilled water return pipe 6 with the chilled water return sleeve 4, the chilled water supply pipe with the chilled water supply sleeve 5 and the air pipe 9 with the ventilation sleeve 8 through sealants. In the installation process of the chilled water return pipe 6, the chilled water supply pipe and the air pipe 9, quality inspection is carried out at any time, and sundries cannot be left in the pipelines.
To adding sealed glue to seal after carrying out heat preservation processing etc. between refrigerated water wet return 6 and the refrigerated water return sleeve pipe 4, refrigerated water delivery pipe and refrigerated water supply sleeve pipe 5, tuber pipe 9 and ventilation sleeve pipe 8, between water pipe prefabricated section 2 and the wall body 1, between tuber pipe prefabricated section 38 and the wall body 1, thoroughly isolated air, steam flow after sealed, keep dry clean in the pipeline, effectively solve the not tight quality problem of shutoff.
In conclusion, according to the pre-sealing construction method for the wall body of the pipeline dense area, provided by the invention, comprehensive arrangement is carried out on the pipeline dense area in advance under civil engineering and electromechanical collision inspection by means of the BIM technology, and the drawing is carried out by one key of software, so that the time for selecting the dense pipeline area by contrasting a two-dimensional drawing is saved. The masonry of the wall body 1 is automatically typeset before drawing, the pipeline wall-penetrating position of the pipeline dense area is accurately positioned, the problem that the electromechanical pipeline and the wall body 1 are constructed in sequence is effectively solved, and the accurate positioning of the size of the pipeline dense area is ensured; adopt BIM technique to optimize water pipe prefabricated section 2 and tuber pipe prefabricated section 3 in advance, carry out three-dimensional to water pipe prefabricated section 2 and tuber pipe prefabricated section 3 and arrange to analysis and calculation obtains water pipe prefabricated section 2 and tuber pipe prefabricated section 3 optimum size of a dimension, makes in 1 construction process of wall body, when closely knit being connected water pipe prefabricated section 2, tuber pipe prefabricated section 3 respectively with wall body 1, has reduced the construction process, ensures safety. In the secondary structure work progress, to water pipe prefabricated section 2 in advance according to the intensive pipeline deepening picture of wall body, tuber pipe prefabricated section 3 makes, and according to water pipe prefabricated section 2, 3 sizes of tuber pipe prefabricated section carry out embedded wall bushing (refrigerated water return sleeve 4, refrigerated water supply sleeve 5 and ventilation sleeve 8) pre-buried, consolidate the location back, at water pipe prefabricated section 2, carry out the reinforcing bar pre-buried outside the wall bushing in tuber pipe prefabricated section 3's the mould, pour light aggregate concrete again, ensure water pipe prefabricated section 2 and tuber pipe prefabricated section 3's fire behavior, the piece one shot forming that buries. After the wall body 1 is built to the pipeline wall penetrating position of the pipeline dense area, the water pipe prefabricated blocks 2 and the air pipe prefabricated blocks 3 are installed on the wall body 1 in a modularized mode, the wall body 1 is guaranteed to have good air tightness, the problem that pipelines are difficult to block is effectively solved, and the pipeline wall penetrating device has the advantages of being simple in construction process, short in period and high in safety performance.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (7)

1. A pre-closing construction method for a wall body in a pipeline dense area is characterized by comprising the following steps:
s1, before wall construction, automatically typesetting the wall of the pipeline dense area in advance by utilizing BIM technology under civil engineering and electromechanical collision inspection, accurately positioning the pipeline wall-penetrating position of the pipeline dense area, simulating the closed construction of the wall of the pipeline dense area in advance, and finally deepening the selected wall of the pipeline dense area by utilizing BIM technology to obtain a deepened drawing of the pipeline of the wall;
s2, carrying out three-dimensional arrangement on the concrete precast blocks for closing the pipeline wall-penetrating positions by adopting a BIM technology to obtain the sizes of the concrete precast blocks;
s3, setting a template according to the size of the concrete precast block, making a mold, embedding an embedded wall bushing, and embedding reinforcing steel bars in the concrete precast block at the periphery of the wall bushing according to design requirements and specifications;
s4, pouring lightweight aggregate concrete into the mould, removing the template after the lightweight aggregate concrete reaches the strength, and forming the concrete precast block into a pipeline precast block with a through hole in one step;
s5, according to the intensive pipeline deepening drawing of wall body, to the intensive district wall body construction of pipeline, after the pipeline wall penetrating position of the intensive district of pipeline is built by laying bricks or stones to the wall body, install in the pipeline wall penetrating position of the intensive district of pipeline the pipeline prefabricated section, mounted position and elevation are strict according to the intensive pipeline deepening drawing of wall body is accurately placed, right the pipeline prefabricated section is closely connected with the wall body, makes the pipeline prefabricated section modularization install in on the wall body, the wall-penetrating sleeve pipe runs through the wall body.
2. The pre-closing construction method for the wall body of the pipeline compact area as claimed in claim 1, wherein the pipeline prefabricated block comprises a water pipe prefabricated block and a wind pipe prefabricated block, and the wall bushing comprises a chilled water return bushing, a chilled water supply bushing and a ventilation bushing.
3. The method for pre-closing construction of a wall body of a pipeline dense area as claimed in claim 2, wherein in the step S3, the quality of the water pipe prefabricated block and the air pipe prefabricated block is accurately controlled through analysis and calculation, the dies of the water pipe prefabricated block and the air pipe prefabricated block are respectively manufactured by using the templates according to the intensive pipeline deepening drawing of the wall body, the dies are cut and assembled according to the size, the redundant templates are cut by using a cutting machine, the die plates are spliced by using a reinforcing connecting member, and the chilled water return sleeve, the chilled water supply sleeve and the ventilation sleeve customized for the selected area are accurately placed in the dies during operation, so that the dies are ensured to be compact and firm.
4. The pre-closing construction method for the wall body of the pipeline dense area as claimed in claim 3, wherein the pre-embedding of the chilled water return sleeve, the chilled water supply sleeve and the ventilation sleeve is performed in a mold for manufacturing the water pipe precast block according to the wall body dense pipeline deepening drawing, and the axial lengths of the chilled water return sleeve, the chilled water supply sleeve and the ventilation sleeve are less than or equal to the thickness of the wall body.
5. The pre-closing construction method for the wall body of the pipeline dense area as claimed in claim 1, wherein in the step S3, the reinforcing bars are uniformly arranged around the wall bushing.
6. The method of pre-sealing a wall in a dense pipeline area according to claim 1, wherein in step S4, the lightweight aggregate concrete is poured into the mold, and the concrete is vibrated by the vibrating rod in time, the vibrating time is controlled, the dense combination and the flat surface are ensured, the cellular pitted surface and air bubbles of the concrete are eliminated, the strength of the concrete is ensured, after the pouring, the concrete precast block is cured immediately, the curing period is kept for at least 7 days, the anti-permeability requirement of the doped retarding admixture is not less than 14 days, and the water spraying and wet curing are carried out, and the sealing is kept when the concrete block is covered with the plastic film for curing.
7. The pre-closing construction method for the wall body of the pipeline dense area as claimed in claim 2, wherein after the step S5, the method further comprises the following steps:
s6, correspondingly installing a chilled water return pipe on the chilled water return sleeve, correspondingly installing a chilled water supply pipe on the chilled water supply sleeve, correspondingly installing an air pipe on the ventilation sleeve, wherein the chilled water return pipe is connected with the chilled water return sleeve, the chilled water supply pipe is connected with the chilled water supply sleeve and the air pipe is connected with the ventilation sleeve through sealant.
CN202210642953.2A 2022-06-08 2022-06-08 Pre-closing construction method for wall body of pipeline dense area Pending CN114892819A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210642953.2A CN114892819A (en) 2022-06-08 2022-06-08 Pre-closing construction method for wall body of pipeline dense area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210642953.2A CN114892819A (en) 2022-06-08 2022-06-08 Pre-closing construction method for wall body of pipeline dense area

Publications (1)

Publication Number Publication Date
CN114892819A true CN114892819A (en) 2022-08-12

Family

ID=82727231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210642953.2A Pending CN114892819A (en) 2022-06-08 2022-06-08 Pre-closing construction method for wall body of pipeline dense area

Country Status (1)

Country Link
CN (1) CN114892819A (en)

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11166275A (en) * 1997-12-03 1999-06-22 Katsuya Hiraoka Execution of building and concrete product
BRPI0804034A2 (en) * 2008-09-26 2011-11-22 Deleandro Faenelo double layer block configuration for building prefabricated masonry houses
CN102444750A (en) * 2010-10-14 2012-05-09 中冶天工集团有限公司 Construction method for prefabricating directly-buried uncompensated centralized heat supply pipeline by electrically preheating
CN203347227U (en) * 2013-06-13 2013-12-18 中国建筑第八工程局有限公司 Prefabricated sleeve pipe structure applied to building secondary structure
CN104746589A (en) * 2015-03-31 2015-07-01 中民筑友有限公司 Installation node of water supply and drainage integration module
CN105260541A (en) * 2015-10-13 2016-01-20 中国十七冶集团有限公司 Pipeline deepening method based on BIM model
CN106703279A (en) * 2017-03-16 2017-05-24 天津三建建筑工程有限公司 Improving method for pipeline burying construction of infilled wall
CN107227816A (en) * 2017-07-28 2017-10-03 陕西建工第十建设集团有限公司 A kind of wall bushing construction method based on wall bushing prefabricated section
WO2017181205A2 (en) * 2016-04-16 2017-10-19 Martinez Lazaro A Block interlocking module based (bim based) system to build architectural structures
CN107762053A (en) * 2017-11-17 2018-03-06 中国二十二冶集团有限公司 Prefabricated basement pipeline module and preparation method thereof
CN207079621U (en) * 2017-08-01 2018-03-09 武汉市政工程设计研究院有限责任公司 A kind of precast assembly fire wall suitable for pipe gallery
CN208518183U (en) * 2018-06-26 2019-02-19 中国水利水电第五工程局有限公司 Assembled type pipe prefabricated components
CN109514188A (en) * 2018-10-23 2019-03-26 筑梦高科建筑有限公司 Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
CN109853832A (en) * 2019-01-18 2019-06-07 江苏南通六建建设集团有限公司 A kind of construction method of filling wall masonry and electrical pre-embedded pipe synchronous construction
CN211312927U (en) * 2019-09-26 2020-08-21 中国水利水电第十四工程局有限公司 Prefabricated part for wall bushing of secondary structure refrigerant pipeline of subway station
CN211447334U (en) * 2019-11-18 2020-09-08 中国建筑第八工程局有限公司 One-step prefabricated structure for building complex nodes of wall body
CN111827263A (en) * 2020-08-06 2020-10-27 青岛理工大学 Method for prefabricating underground continuous wall with built-in capillary heat exchanger
CN113282986A (en) * 2021-05-27 2021-08-20 中国建筑第二工程局有限公司 Electromechanical integrated pipeline assembly type construction method
CN113550487A (en) * 2021-06-18 2021-10-26 广州市机电安装有限公司 Construction method of prefabricated air conditioner casing pipe
CN113789910A (en) * 2021-08-18 2021-12-14 中国二十冶集团有限公司 Upper lintel structure of masonry wall door and construction method thereof
WO2022052250A1 (en) * 2020-09-11 2022-03-17 浙江勤业建工集团有限公司 Same-model multi-person cooperative operation method for bim pipe integration deepening design

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11166275A (en) * 1997-12-03 1999-06-22 Katsuya Hiraoka Execution of building and concrete product
BRPI0804034A2 (en) * 2008-09-26 2011-11-22 Deleandro Faenelo double layer block configuration for building prefabricated masonry houses
CN102444750A (en) * 2010-10-14 2012-05-09 中冶天工集团有限公司 Construction method for prefabricating directly-buried uncompensated centralized heat supply pipeline by electrically preheating
CN203347227U (en) * 2013-06-13 2013-12-18 中国建筑第八工程局有限公司 Prefabricated sleeve pipe structure applied to building secondary structure
CN104746589A (en) * 2015-03-31 2015-07-01 中民筑友有限公司 Installation node of water supply and drainage integration module
CN105260541A (en) * 2015-10-13 2016-01-20 中国十七冶集团有限公司 Pipeline deepening method based on BIM model
WO2017181205A2 (en) * 2016-04-16 2017-10-19 Martinez Lazaro A Block interlocking module based (bim based) system to build architectural structures
CN106703279A (en) * 2017-03-16 2017-05-24 天津三建建筑工程有限公司 Improving method for pipeline burying construction of infilled wall
CN107227816A (en) * 2017-07-28 2017-10-03 陕西建工第十建设集团有限公司 A kind of wall bushing construction method based on wall bushing prefabricated section
CN207079621U (en) * 2017-08-01 2018-03-09 武汉市政工程设计研究院有限责任公司 A kind of precast assembly fire wall suitable for pipe gallery
CN107762053A (en) * 2017-11-17 2018-03-06 中国二十二冶集团有限公司 Prefabricated basement pipeline module and preparation method thereof
CN208518183U (en) * 2018-06-26 2019-02-19 中国水利水电第五工程局有限公司 Assembled type pipe prefabricated components
CN109514188A (en) * 2018-10-23 2019-03-26 筑梦高科建筑有限公司 Electromechanical pipeline and equipment batch production prefabricating and constructing based on BIM
CN109853832A (en) * 2019-01-18 2019-06-07 江苏南通六建建设集团有限公司 A kind of construction method of filling wall masonry and electrical pre-embedded pipe synchronous construction
CN211312927U (en) * 2019-09-26 2020-08-21 中国水利水电第十四工程局有限公司 Prefabricated part for wall bushing of secondary structure refrigerant pipeline of subway station
CN211447334U (en) * 2019-11-18 2020-09-08 中国建筑第八工程局有限公司 One-step prefabricated structure for building complex nodes of wall body
CN111827263A (en) * 2020-08-06 2020-10-27 青岛理工大学 Method for prefabricating underground continuous wall with built-in capillary heat exchanger
WO2022052250A1 (en) * 2020-09-11 2022-03-17 浙江勤业建工集团有限公司 Same-model multi-person cooperative operation method for bim pipe integration deepening design
CN113282986A (en) * 2021-05-27 2021-08-20 中国建筑第二工程局有限公司 Electromechanical integrated pipeline assembly type construction method
CN113550487A (en) * 2021-06-18 2021-10-26 广州市机电安装有限公司 Construction method of prefabricated air conditioner casing pipe
CN113789910A (en) * 2021-08-18 2021-12-14 中国二十冶集团有限公司 Upper lintel structure of masonry wall door and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
康晋宇;李绍东;姚健;范志强;姜镇涛;: "砌筑套管直埋技术在天津周大福金融中心项目中的应用", 施工技术, no. 23, 10 December 2017 (2017-12-10) *
曹建新;尹奎;何庆国;: "建筑密集管道预制组合技术", 安装, no. 09, 15 September 2016 (2016-09-15) *

Similar Documents

Publication Publication Date Title
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN101858114A (en) Construction method for cast-in-place integral light-weight partition wall
CN105459253A (en) Large-volume lining model pouring device for tunnel model test and method of large-volume lining model pouring device
CN103485370B (en) A kind of concrete construction control method preventing wallboard harmful cracks
CN107679297A (en) A kind of prefabricated assembled apron slope construction method based on BIM
CN114411945A (en) Bin jump construction method based on BIM technology
CN103741949B (en) Treatment of juncture between vertical structure and horizontal structure
CN104110083A (en) One-step-forming pouring construction method of ultrahigh thin wall
CN103867214A (en) Construction method for carrying out secondary lining and casting in shielded tunnel
CN114892819A (en) Pre-closing construction method for wall body of pipeline dense area
CN110046363B (en) Construction method for accurately embedding pipeline group in concrete structure
CN108425685B (en) Concrete crack control method based on cast-in-place tunnel
CN114000646A (en) Reverse-beating integrated wallboard of precast concrete composite heat-insulation template and preparation method
CN219863375U (en) Constructional column top reinforcing steel bar pre-burying device
CN107083804A (en) A kind of wall structure post joint bar construction method
CN110835930B (en) Layered and block construction method and structure for large-volume high-strength castable at bottom of coke oven
CN107762053A (en) Prefabricated basement pipeline module and preparation method thereof
CN111535482A (en) Aluminum mould construction concrete structure and tool and electromechanical reservation pre-embedding construction method
CN111516096A (en) Precast column concrete pouring method in fabricated building
CN204435616U (en) Truss bars double layer fibre gypsum plank, non-dismantling formwork wall body structure
CN103669401B (en) Epoxy resin cement concrete block placement outer wall of basement and construction method thereof
CN113373985B (en) Basement waterproof construction method
CN211172673U (en) Brickwork and mold processing thereof
CN104441234A (en) Method for manufacturing oversized prefabricated composite floor slab containing multiple built-in fittings
CN103174236B (en) Manufacture method for high-heat-preservation foaming sandwich building wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination