CN114855862A - Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly - Google Patents

Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly Download PDF

Info

Publication number
CN114855862A
CN114855862A CN202210207769.5A CN202210207769A CN114855862A CN 114855862 A CN114855862 A CN 114855862A CN 202210207769 A CN202210207769 A CN 202210207769A CN 114855862 A CN114855862 A CN 114855862A
Authority
CN
China
Prior art keywords
support
support rod
frame
auxiliary positioning
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210207769.5A
Other languages
Chinese (zh)
Inventor
王同华
张龙刚
张强
孟格格
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Huasizhuang Energy Technology Co ltd
Original Assignee
Qingdao Huasizhuang Energy Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Huasizhuang Energy Technology Co ltd filed Critical Qingdao Huasizhuang Energy Technology Co ltd
Priority to CN202210207769.5A priority Critical patent/CN114855862A/en
Publication of CN114855862A publication Critical patent/CN114855862A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00—Foundations as substructures
    • E02D27/32—Foundations for special purposes
    • E02D27/42—Foundations for poles, masts or chimneys
    • E02D27/425—Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/70—Wind energy
    • Y02E10/728—Onshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

本发明公开了风力发电技术领域的一种辅助定位龙骨架,包括左支撑架、右支撑架、上连接板、下连接板、支撑杆,所述左支撑架的内腔壁设有若干个左支撑托,所述每个左支撑托上设置有一个左支撑凹槽,所述右支撑架的内腔壁设有若干个右支撑托,所述每个右支撑托上设置有一个右支撑凹槽,所述左支撑凹槽和右支撑凹槽所在的圆心组成的圆与锚栓笼的外围锚栓轴心所在的圆相匹配。本发明还公开了一种使用辅助定位龙骨架的安装方法,通过辅助定位龙骨架的使用,可以实现锚栓笼的水平安装,不必借助吊车。本发明的有益效果如下:减少了吊车的使用,由原来垂直安装改为水平安装,提高了安装效率,且提高了安全性能,节约了成本并降低了安装的风险。

Figure 202210207769

The invention discloses an auxiliary positioning dragon frame in the technical field of wind power generation, comprising a left support frame, a right support frame, an upper connecting plate, a lower connecting plate and a support rod. Support brackets, each left support bracket is provided with a left support groove, the inner cavity wall of the right support frame is provided with a number of right support brackets, and each right support bracket is provided with a right support groove The circle formed by the center of the left support groove and the right support groove matches the circle where the outer anchor bolt axis of the anchor bolt cage is located. The invention also discloses an installation method using the auxiliary positioning dragon frame. By using the auxiliary positioning dragon frame, the horizontal installation of the anchor bolt cage can be realized without the aid of a crane. The beneficial effects of the invention are as follows: the use of cranes is reduced, the original vertical installation is changed to the horizontal installation, the installation efficiency is improved, the safety performance is improved, the cost is saved and the installation risk is reduced.

Figure 202210207769

Description

辅助定位龙骨架及预应力锚栓组合件的安装方法Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly

技术领域technical field

本发明属于风力发电技术领域,特别涉及一种辅助定位龙骨架及预应力锚栓组合件的安装方法。The invention belongs to the technical field of wind power generation, and in particular relates to an installation method of an auxiliary positioning dragon frame and a prestressed anchor bolt assembly.

背景技术Background technique

现有技术中锚栓笼的安装方法是将锚栓套入防粘结套管后再穿入上锚板,然后用吊车垂直起吊,使锚栓垂直,将下锚板水平放好,吊车缓慢下降,锚栓全部对准下锚板孔,全部穿入后将螺母拧紧再将锚栓笼放倒调整尺寸。The installation method of the anchor bolt cage in the prior art is to insert the anchor bolt into the anti-adhesion sleeve and then penetrate the upper anchor plate, and then lift it vertically with a crane to make the anchor bolt vertical, put the lower anchor plate horizontally, and the crane is slow. When descending, the anchor bolts are all aligned with the lower anchor plate holes. After all penetrations, tighten the nuts and then lay down the anchor bolt cage to adjust the size.

专利号为CN201510515415.7专利名称为一种可更换的预应力锚栓装置的一篇现有专利公开了一种预应力锚栓组合件的施工安装方法,包括以下步骤:1)先将下锚板固定在基础垫层并调平;2)吊起上锚板,将锚栓穿入塑料套管内,塑料套管上套有非金属调平螺母,然后将 锚栓穿过上锚板上的螺栓孔,然后在锚栓顶部拧上上螺母;3)用吊车移动上锚板至下锚板上方,慢慢吊下上锚板,使锚栓对应插入下锚板的 螺栓孔中;4)在顶部转动每根锚栓,将锚栓底端旋入焊接在下锚板下方的下螺母中;5)通过非金属调平螺母调平上锚板;6)绑扎基础钢筋并浇筑混泥土,将上锚板,下锚板和锚栓浇筑在混凝土基础内,等到混凝土达到规定强度后,吊上底部塔筒后,在上锚板上张拉锚栓。The patent number is CN201510515415.7 and an existing patent with the patent name of a replaceable prestressed anchor bolt device discloses a construction and installation method of a prestressed anchor bolt assembly, which includes the following steps: 1) first lower the anchor bolt The plate is fixed on the foundation cushion and leveled; 2) Lift the upper anchor plate, insert the anchor bolt into the plastic sleeve, cover the plastic sleeve with a non-metallic leveling nut, and then pass the anchor bolt through the upper anchor plate. bolt holes, and then screw nuts on the top of the anchor bolts; 3) Use a crane to move the upper anchor plate to the top of the lower anchor plate, and slowly lift the upper anchor plate, so that the anchor bolts are inserted into the bolt holes of the lower anchor plate accordingly; 4) Rotate each anchor bolt at the top, screw the bottom end of the anchor bolt into the lower nut welded under the lower anchor plate; 5) Level the upper anchor plate through the non-metal leveling nut; 6) Bind the foundation steel bars and pour concrete, and The upper anchor plate, the lower anchor plate and the anchor bolts are poured into the concrete foundation. After the concrete reaches the specified strength, the bottom tower is lifted, and the anchor bolts are tensioned on the upper anchor plate.

现有的技术需要用吊车,产生高空作业,需要脚手架辅助,产生安全隐患,安装效率低。The prior art requires a crane, which results in high-altitude operations and scaffolding assistance, which results in potential safety hazards and low installation efficiency.

发明内容SUMMARY OF THE INVENTION

为了解决以上问题,本发明决定研发一种辅助定位龙骨架及预应力锚栓组合件的安装方法。In order to solve the above problems, the present invention decides to develop an installation method for the auxiliary positioning dragon frame and the prestressed anchor bolt assembly.

一种辅助定位龙骨架,包括左支撑架、右支撑架、上连接板、下连接板、支撑杆,所述左支撑架的内腔壁设有若干个左支撑托,所述每个左支撑托上设置有一个左支撑凹槽,所述右支撑架的内腔壁设有若干个右支撑托,所述每个右支撑托上设置有一个右支撑凹槽,所述左支撑凹槽和右支撑凹槽所在的圆心组成的圆与锚栓笼的外围锚栓轴心所在的圆相匹配;所述左支撑架和右支撑架的内腔中安装有若干个支撑杆,所述支撑杆上设置有支撑杆凹槽,所述支撑杆凹槽的设置与锚栓笼的内部的中心锚栓匹配设置;所述左支撑架上设置有左上连接孔、左下连接孔,所述右支撑架上设置有右上连接孔、右下连接孔,所述左上连接孔、右上连接孔通过上连接板固定连接,所述左下连接孔、右下连接孔通过下连接板固定连接。An auxiliary positioning dragon frame, comprising a left support frame, a right support frame, an upper connecting plate, a lower connecting plate and a support rod, the inner cavity wall of the left support frame is provided with a plurality of left support brackets, and each left support A left support groove is provided on the support, the inner cavity wall of the right support frame is provided with a plurality of right support supports, each right support support is provided with a right support groove, and the left support groove and The circle formed by the center of the right support groove matches the circle where the outer anchor bolt axis of the anchor cage is located; several support rods are installed in the inner cavities of the left support frame and the right support frame, and the support rods A support rod groove is provided on the support rod, and the setting of the support rod groove is matched with the central anchor bolt inside the anchor bolt cage; the left support frame is provided with a left upper connecting hole and a left lower connecting hole, and the right support frame is provided with The upper right connecting hole and the lower right connecting hole are arranged on the upper part, the upper left connecting hole and the upper right connecting hole are fixedly connected through the upper connecting plate, and the lower left connecting hole and the lower right connecting hole are fixedly connected through the lower connecting plate.

进一步地,所述支撑杆包括上支撑杆、中支撑杆、下支撑杆,所述上支撑杆上设置有一个上支撑凹槽,所述中支撑杆上设置有两个中支撑凹槽,所述下支撑杆上设置有一个下支撑凹槽,所述上支撑杆、中支撑杆、下支撑杆的两端分别安装于左支撑托和右支撑托上。Further, the support rod includes an upper support rod, a middle support rod, and a lower support rod, the upper support rod is provided with an upper support groove, and the middle support rod is provided with two middle support grooves, so The lower support rod is provided with a lower support groove, and both ends of the upper support rod, the middle support rod and the lower support rod are respectively mounted on the left support bracket and the right support bracket.

进一步地,所述左支撑托上设置有左安装孔,所述右支撑托上设置有右安装孔,所述上支撑杆、中支撑杆、下支撑杆的一端通过左安装孔安装于左支撑托,所述上支撑杆、中支撑杆、下支撑杆的另一端通过右安装孔安装于右支撑托。Further, the left support bracket is provided with a left installation hole, the right support bracket is provided with a right installation hole, and one end of the upper support rod, the middle support rod, and the lower support rod are installed on the left support through the left installation hole. The other ends of the upper support rod, the middle support rod and the lower support rod are installed on the right support bracket through the right mounting hole.

一种使用所述辅助定位龙骨架的预应力锚栓组合件的安装方法,包括如下步骤:An installation method of a prestressed anchor bolt assembly using the auxiliary positioning dragon frame, comprising the following steps:

(1)通过上连接板、左上连接孔、右上连接孔将辅助定位龙骨架的左支撑架、右支撑架的上端固定,通过下连接板、左下连接孔、右下连接孔将辅助定位龙骨架的左支撑架、右支撑架的下端固定,并将上支撑杆、中支撑杆、下支撑杆分别安装在左支撑架的左安装孔、右支撑架的右安装孔,辅助定位龙骨架安装完成;(1) Fix the left support frame and the upper end of the right support frame of the auxiliary positioning dragon frame through the upper connecting plate, the upper left connecting hole and the upper right connecting hole, and the auxiliary positioning dragon frame through the lower connecting plate, the lower left connecting hole and the lower right connecting hole. The lower ends of the left support frame and the right support frame are fixed, and the upper support rod, the middle support rod and the lower support rod are respectively installed in the left installation hole of the left support frame and the right installation hole of the right support frame. The auxiliary positioning dragon frame is installed. ;

(2)在场地铺设一块钢板,将上锚板和辅助定位龙骨架垂直固定到钢板上,辅助定位龙骨架安装在下锚板位置的内侧10-30cm处;(2) Lay a steel plate on the site, fix the upper anchor plate and the auxiliary positioning dragon skeleton to the steel plate vertically, and install the auxiliary positioning dragon skeleton 10-30cm inside the position of the lower anchor plate;

(3)将锚栓上端尼龙螺母全部旋入到锚栓的图纸位置,从锚栓下端套入防粘结套管,再将锚栓下端的半螺母旋入到图纸尺寸,套入热缩管;(3) Screw all the nylon nuts at the upper end of the anchor bolt to the position of the anchor bolt in the drawing, insert the anti-adhesion sleeve from the lower end of the anchor bolt, and then screw the half nut at the lower end of the anchor bolt to the drawing size, and insert the heat shrinkable tube into it. ;

(4)工人手持锚栓先穿入固定环、上锚板,再将各锚栓分别放入到辅助定位龙骨架对应的左支撑凹槽、右支撑凹槽、上支撑凹槽、中支撑凹槽、下支撑凹槽,依次将所有锚栓安装到位,等全部锚栓固定到位后,调整固定环位置,用U形螺栓进行固定;(4) Workers hold the anchor bolts first through the fixing ring and the upper anchor plate, and then put each anchor bolt into the left support groove, right support groove, upper support groove, and middle support groove corresponding to the auxiliary positioning dragon skeleton. groove and lower support groove, install all the anchor bolts in place in sequence, and after all the anchor bolts are fixed in place, adjust the position of the fixing ring and fix it with U-shaped bolts;

(5)将上锚板上侧的上螺母旋紧;(5) Tighten the upper nut on the upper side of the upper anchor plate;

(6)将下锚板水平穿过锚栓,将下锚板下侧的下螺母全部旋紧,并施加图纸要求的扭矩;(6) Pass the lower anchor plate horizontally through the anchor bolt, tighten all the lower nuts on the lower side of the lower anchor plate, and apply the torque required by the drawing;

(7)检验相关尺寸后将辅助定位龙骨架拆除取出,即完成锚栓笼的安装。(7) After checking the relevant dimensions, remove the auxiliary positioning dragon skeleton, and complete the installation of the anchor cage.

本发明取得的有益效果如下:锚栓笼水平安装时,先借助辅助定位龙骨架支撑和定型,安装结束后将辅助定位龙骨架拆除不影响锚栓笼的结构,本安装方法减少了吊车的使用,由原来垂直安装改为水平安装,提高了安装效率,且提高了安全性能,节约了成本并降低了安装的风险。The beneficial effects obtained by the invention are as follows: when the anchor cage is installed horizontally, it is first supported and shaped by the auxiliary positioning dragon frame, and after the installation is completed, the auxiliary positioning dragon frame is removed without affecting the structure of the anchor bolt cage, and the installation method reduces the use of cranes , the original vertical installation is changed to the horizontal installation, which improves the installation efficiency, improves the safety performance, saves the cost and reduces the installation risk.

附图说明Description of drawings

图1为辅助定位龙骨架的结构分解图;Figure 1 is an exploded view of the structure of the auxiliary positioning dragon skeleton;

图2为辅助定位龙骨架的安装结构示意图;Figure 2 is a schematic diagram of the installation structure of the auxiliary positioning dragon skeleton;

图3为锚栓笼的结构示意图;Figure 3 is a schematic structural diagram of an anchor cage;

图4为锚栓笼A部分的结构示意图;Fig. 4 is the structural representation of part A of the anchor cage;

图5为锚栓笼B部分的结构示意图;Figure 5 is a schematic structural diagram of part B of the anchor cage;

图中附图标记为:The reference numbers in the figure are:

1左支撑架、2右支撑架、3左下连接孔、4右下连接孔、5左上连接孔、6右上连接孔、7上支撑杆、8上支撑凹槽、9中支撑杆、10中支撑凹槽、11下支撑杆、12下支撑凹槽、13左支撑凹槽、14右支撑凹槽、15左支撑托、16右支撑托、17上连接板、18下连接板、19外围锚栓、20中心锚栓、21上锚板、22下锚板、23固定环、24左安装孔、25右安装孔、26U形螺栓、27防粘结套管、28尼龙螺母、29上螺母、30柱脚法兰板、31热缩管、32下螺母、33半螺母。1 left support frame, 2 right support frame, 3 lower left connecting hole, 4 lower right connecting hole, 5 upper left connecting hole, 6 upper right connecting hole, 7 upper support rod, 8 upper support groove, 9 middle support rod, 10 middle support Groove, 11 lower support rod, 12 lower support groove, 13 left support groove, 14 right support groove, 15 left support bracket, 16 right support bracket, 17 upper connecting plate, 18 lower connecting plate, 19 peripheral anchor bolt , 20 center anchor bolt, 21 upper anchor plate, 22 lower anchor plate, 23 fixing ring, 24 left mounting hole, 25 right mounting hole, 26 U-bolt, 27 anti-adhesion sleeve, 28 nylon nut, 29 upper nut, 30 Column foot flange plate, 31 heat shrinkable tube, 32 lower nut, 33 half nut.

具体实施方式Detailed ways

实施例1Example 1

如图1-5,一种辅助定位龙骨架,包括左支撑架1、右支撑架2、上连接板17、下连接板18、上支撑杆7、中支撑杆9、下支撑杆11,所述左支撑架1的内腔壁设有若干个左支撑托15,所述每个左支撑托15上设置有一个左支撑凹槽13,所述右支撑架2的内腔壁设有若干个右支撑托16,所述每个右支撑托16上设置有一个右支撑凹槽14,所述左支撑凹槽13和右支撑凹槽14所在的圆心组成的圆与锚栓笼的外围锚栓轴心所在的圆相匹配;所述左支撑架1和右支撑架2的内腔中安装有上支撑杆7、中支撑杆9、下支撑杆11,所述上支撑杆7上设置有一个上支撑凹槽8,所述中支撑杆9上设置有两个中支撑凹槽10,所述下支撑杆11上设置有一个下支撑凹槽12,所述上支撑杆7、中支撑杆9、下支撑杆11的两端分别安装于左支撑托15和右支撑托16上,所述上支撑凹槽8、中支撑凹槽10、下支撑凹槽12的设置与锚栓笼的内部的中心锚栓20匹配设置;所述左支撑托13上设置有左安装孔24,所述右支撑托16上设置有右安装孔25,所述上支撑杆7、中支撑杆9、下支撑杆11两端分别通过左安装孔24安装于左支撑托13,通过右安装孔14安装于右支撑托16。As shown in Figures 1-5, an auxiliary positioning dragon frame includes a left support frame 1, a right support frame 2, an upper connecting plate 17, a lower connecting plate 18, an upper support rod 7, a middle support rod 9, and a lower support rod 11. The inner cavity wall of the left support frame 1 is provided with a number of left support brackets 15, each of the left support brackets 15 is provided with a left support groove 13, and the inner cavity wall of the right support bracket 2 is provided with a number of left support brackets 15. The right support bracket 16, each right support bracket 16 is provided with a right support groove 14, the center of the circle where the left support groove 13 and the right support groove 14 are located and the outer anchor bolt of the anchor bolt cage The circle where the axis is located is matched; the inner cavity of the left support frame 1 and the right support frame 2 are installed with an upper support rod 7, a middle support rod 9, and a lower support rod 11, and the upper support rod 7 is provided with a The upper support groove 8, the middle support rod 9 is provided with two middle support grooves 10, the lower support rod 11 is provided with a lower support groove 12, the upper support rod 7, the middle support rod 9 , The two ends of the lower support rod 11 are respectively installed on the left support bracket 15 and the right support bracket 16. The settings of the upper support groove 8, the middle support groove 10, and the lower support groove 12 are the same as those of the interior of the anchor bolt cage. The central anchor bolt 20 is matched and arranged; the left support bracket 13 is provided with a left installation hole 24, the right support bracket 16 is provided with a right installation hole 25, the upper support rod 7, the middle support rod 9, the lower support rod Both ends of 11 are respectively mounted on the left support bracket 13 through the left mounting hole 24 , and are mounted on the right support bracket 16 through the right mounting hole 14 .

所述左支撑架1上设置有左上连接孔5、左下连接孔3,所述右支撑架2上设置有右上连接孔6、右下连接孔4,所述左上连接孔5、右上连接孔6通过上连接板17固定连接,所述左下连接孔3、右下连接孔4通过下连接板18固定连接。The left support frame 1 is provided with an upper left connection hole 5 and a lower left connection hole 3, the right support frame 2 is provided with an upper right connection hole 6 and a lower right connection hole 4, and the upper left connection hole 5 and the upper right connection hole 6 are provided. The upper connecting plate 17 is fixedly connected, and the lower left connecting hole 3 and the lower right connecting hole 4 are fixedly connected through the lower connecting plate 18 .

一种使用辅助定位龙骨架的预应力锚栓组合件的安装方法,包括如下步骤:An installation method of a prestressed anchor bolt assembly using an auxiliary positioning dragon frame, comprising the following steps:

(1)通过上连接板17、左上连接孔5、右上连接孔6将辅助定位龙骨架的左支撑架1、右支撑架2的上端固定,通过下连接板18、左下连接孔3、右下连接孔4将辅助定位龙骨架的左支撑架1、右支撑架2的下端固定,并将上支撑杆7、中支撑杆9、下支撑杆11分别安装在左支撑架1的左安装孔24、右支撑架2的右安装孔25,辅助定位龙骨架安装完成;(1) The upper ends of the left support frame 1 and the right support frame 2 of the auxiliary positioning dragon frame are fixed through the upper connecting plate 17 , the upper left connecting hole 5 and the upper right connecting hole 6 . The connecting hole 4 fixes the lower ends of the left support frame 1 and the right support frame 2 of the auxiliary positioning dragon frame, and installs the upper support rod 7 , the middle support rod 9 and the lower support rod 11 on the left mounting hole 24 of the left support frame 1 respectively. , the right installation hole 25 of the right support frame 2, the auxiliary positioning dragon frame is installed;

(2)在场地铺设一块钢板,将上锚板21和辅助定位龙骨架垂直固定到钢板上,辅助定位龙骨架安装在下锚板22位置的内侧10-30cm处;(2) Lay a steel plate on the site, vertically fix the upper anchor plate 21 and the auxiliary positioning dragon frame to the steel plate, and install the auxiliary positioning dragon frame 10-30cm inside the position of the lower anchor plate 22;

(3)将锚栓上端尼龙螺母28全部旋入到锚栓的图纸位置,从锚栓下端套入防粘结套管27,再将锚栓下端的半螺母33旋入到图纸尺寸,套入热缩管31;(3) Screw all the nylon nuts 28 at the upper end of the anchor bolt into the drawing position of the anchor bolt, insert the anti-adhesion sleeve 27 from the lower end of the anchor bolt, and then screw the half nut 33 at the lower end of the anchor bolt to the drawing size and insert heat shrinkable tube 31;

(4)工人手持锚栓先穿入固定环23、上锚板21,再将各锚栓分别放入到辅助定位龙骨架对应的左支撑凹槽13、右支撑凹槽14、上支撑凹槽8、中支撑凹槽10、下支撑凹槽12,依次将所有锚栓安装到位,等全部锚栓固定到位后,调整固定环23位置,用U形螺栓26进行固定;(4) Workers hold the anchor bolts first through the fixing ring 23 and the upper anchor plate 21, and then put the anchor bolts into the left support groove 13, right support groove 14 and upper support groove corresponding to the auxiliary positioning dragon frame respectively. 8. In the middle support groove 10 and the lower support groove 12, install all the anchor bolts in place in sequence. After all the anchor bolts are fixed in place, adjust the position of the fixing ring 23 and fix it with U-shaped bolts 26;

(5)将上锚板21上侧的上螺母29旋紧;(5) Tighten the upper nut 29 on the upper side of the upper anchor plate 21;

(6)将下锚板22水平穿过锚栓,将下锚板22下侧的下螺母32全部旋紧,并施加图纸要求的扭矩;(6) Pass the lower anchor plate 22 through the anchor bolt horizontally, tighten all the lower nuts 32 on the lower side of the lower anchor plate 22, and apply the torque required by the drawing;

(7)检验相关尺寸后将辅助定位龙骨架拆除取出,即完成锚栓笼的安装。(7) After checking the relevant dimensions, remove the auxiliary positioning dragon skeleton, and complete the installation of the anchor cage.

Claims (4)

1.一种辅助定位龙骨架,其特征在于:包括左支撑架、右支撑架、上连接板、下连接板、支撑杆,所述左支撑架的内腔壁设有若干个左支撑托,所述每个左支撑托上设置有一个左支撑凹槽,所述右支撑架的内腔壁设有若干个右支撑托,所述每个右支撑托上设置有一个右支撑凹槽,所述左支撑凹槽和右支撑凹槽所在的圆心组成的圆与锚栓笼的外围锚栓轴心所在的圆相匹配;所述左支撑架和右支撑架的内腔中安装有若干个支撑杆,所述支撑杆上设置有支撑杆凹槽,所述支撑杆凹槽的设置与锚栓笼的内部的中心锚栓匹配设置;所述左支撑架上设置有左上连接孔、左下连接孔,所述右支撑架上设置有右上连接孔、右下连接孔,所述左上连接孔、右上连接孔通过上连接板固定连接,所述左下连接孔、右下连接孔通过下连接板固定连接。1. An auxiliary positioning dragon skeleton is characterized in that: comprising a left support frame, a right support frame, an upper connecting plate, a lower connecting plate and a support rod, and the inner cavity wall of the left support frame is provided with several left support brackets, Each left support bracket is provided with a left support groove, the inner cavity wall of the right support frame is provided with a number of right support brackets, and each right support bracket is provided with a right support groove, so The circle formed by the center of the left support groove and the right support groove is matched with the circle where the outer anchor bolt axis of the anchor bolt cage is located; a number of supports are installed in the inner cavity of the left support frame and the right support frame The support rod is provided with a support rod groove, and the setting of the support rod groove is matched with the central anchor bolt inside the anchor bolt cage; the left support frame is provided with an upper left connecting hole and a lower left connecting hole , the right support frame is provided with an upper right connecting hole and a lower right connecting hole, the upper left connecting hole and the upper right connecting hole are fixedly connected through the upper connecting plate, and the lower left connecting hole and the lower right connecting hole are fixedly connected through the lower connecting plate. . 2.根据权利要求1所述的一种辅助定位龙骨架,其特征在于:所述支撑杆包括上支撑杆、中支撑杆、下支撑杆,所述上支撑杆上设置有一个上支撑凹槽,所述中支撑杆上设置有两个中支撑凹槽,所述下支撑杆上设置有一个下支撑凹槽,所述上支撑杆、中支撑杆、下支撑杆的两端分别安装于左支撑托和右支撑托上。2 . The auxiliary positioning dragon frame according to claim 1 , wherein the support rod comprises an upper support rod, a middle support rod and a lower support rod, and an upper support groove is provided on the upper support rod. 3 . , the middle support rod is provided with two middle support grooves, the lower support rod is provided with a lower support groove, and the two ends of the upper support rod, the middle support rod and the lower support rod are respectively installed on the left on the support bracket and the right support bracket. 3.根据权利要求2所述的一种辅助定位龙骨架,其特征在于:所述左支撑托上设置有左安装孔,所述右支撑托上设置有右安装孔,所述上支撑杆、中支撑杆、下支撑杆的一端通过左安装孔安装于左支撑托,所述上支撑杆、中支撑杆、下支撑杆的另一端通过右安装孔安装于右支撑托。3. An auxiliary positioning dragon frame according to claim 2, characterized in that: the left support bracket is provided with a left installation hole, the right support bracket is provided with a right installation hole, the upper support rod, One ends of the middle support rod and the lower support rod are installed on the left support bracket through the left installation hole, and the other ends of the upper support rod, the middle support rod and the lower support rod are installed on the right support bracket through the right installation hole. 4.一种使用权利要求1-3任一条所述辅助定位龙骨架的预应力锚栓组合件的安装方法,其特征在于包括如下步骤:4. A method for installing a prestressed anchor bolt assembly using the auxiliary positioning keel frame described in any one of claims 1-3, characterized in that it comprises the following steps: (1)通过上连接板、左上连接孔、右上连接孔将辅助定位龙骨架的左支撑架、右支撑架的上端固定,通过下连接板、左下连接孔、右下连接孔将辅助定位龙骨架的左支撑架、右支撑架的下端固定,并将上支撑杆、中支撑杆、下支撑杆分别安装在左支撑架的左安装孔、右支撑架的右安装孔,辅助定位龙骨架安装完成;(1) Fix the left support frame and the upper end of the right support frame of the auxiliary positioning dragon frame through the upper connecting plate, the upper left connecting hole and the upper right connecting hole, and the auxiliary positioning dragon frame through the lower connecting plate, the lower left connecting hole and the lower right connecting hole. The lower ends of the left support frame and the right support frame are fixed, and the upper support rod, the middle support rod and the lower support rod are respectively installed in the left installation hole of the left support frame and the right installation hole of the right support frame. The auxiliary positioning dragon frame is installed. ; (2)在场地铺设一块钢板,将上锚板和辅助定位龙骨架垂直固定到钢板上,辅助定位龙骨架安装在下锚板位置的内侧10-30cm处;(2) Lay a steel plate on the site, fix the upper anchor plate and the auxiliary positioning dragon skeleton to the steel plate vertically, and install the auxiliary positioning dragon skeleton 10-30cm inside the position of the lower anchor plate; (3)将锚栓上端尼龙螺母全部旋入到锚栓的图纸位置,从锚栓下端套入防粘结套管,再将锚栓下端的半螺母旋入到图纸尺寸,套入热缩管;(3) Screw all the nylon nuts at the upper end of the anchor bolt to the position of the anchor bolt in the drawing, insert the anti-adhesion sleeve from the lower end of the anchor bolt, and then screw the half nut at the lower end of the anchor bolt to the drawing size, and insert the heat shrinkable tube into it. ; (4)工人手持锚栓先穿入固定环、上锚板,再将各锚栓分别放入到辅助定位龙骨架对应的左支撑凹槽、右支撑凹槽、上支撑凹槽、中支撑凹槽、下支撑凹槽,依次将所有锚栓安装到位,等全部锚栓固定到位后,调整固定环位置,用U形螺栓进行固定;(4) Workers hold the anchor bolts first through the fixing ring and the upper anchor plate, and then put each anchor bolt into the left support groove, right support groove, upper support groove, and middle support groove corresponding to the auxiliary positioning dragon skeleton. groove and lower support groove, install all the anchor bolts in place in sequence, and after all the anchor bolts are fixed in place, adjust the position of the fixing ring and fix it with U-shaped bolts; (5)将上锚板上侧的上螺母旋紧;(5) Tighten the upper nut on the upper side of the upper anchor plate; (6)将下锚板水平穿过锚栓,将下锚板下侧的下螺母全部旋紧,并施加图纸要求的扭矩;(6) Pass the lower anchor plate horizontally through the anchor bolt, tighten all the lower nuts on the lower side of the lower anchor plate, and apply the torque required by the drawing; (7)检验相关尺寸后将辅助定位龙骨架拆除取出,即完成锚栓笼的安装。(7) After checking the relevant dimensions, remove the auxiliary positioning dragon skeleton, and complete the installation of the anchor cage.
CN202210207769.5A 2022-03-04 2022-03-04 Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly Pending CN114855862A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210207769.5A CN114855862A (en) 2022-03-04 2022-03-04 Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210207769.5A CN114855862A (en) 2022-03-04 2022-03-04 Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly

Publications (1)

Publication Number Publication Date
CN114855862A true CN114855862A (en) 2022-08-05

Family

ID=82627444

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210207769.5A Pending CN114855862A (en) 2022-03-04 2022-03-04 Installation method of auxiliary positioning dragon frame and prestressed anchor bolt assembly

Country Status (1)

Country Link
CN (1) CN114855862A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050060410A (en) * 2003-12-16 2005-06-22 건원공업 주식회사 Apparatus for adjusting space of anchor bolt
CN208105060U (en) * 2018-03-15 2018-11-16 沈阳公路工程监理有限责任公司 A kind of box beam steel reinforcement cage sizing mould bases
CN211304617U (en) * 2019-07-24 2020-08-21 偃师市华泰综合利用建材有限公司 Evaporate and press aerated concrete reinforcement panel cylinder mould locating rack
CN112324152A (en) * 2020-10-30 2021-02-05 上海二十冶建设有限公司 Construction method for accurately installing annular foundation steel reinforcement framework of rotary hearth furnace
CN213539043U (en) * 2020-09-30 2021-06-25 中国能源建设集团黑龙江省电力设计院有限公司 Anchor bolt cage for fan foundation
CN214557029U (en) * 2020-12-08 2021-11-02 江苏阳湖建设项目管理有限公司 Prefabricated bed-jig device of overpass beam pier column steel reinforcement cage
CN217174892U (en) * 2022-03-04 2022-08-12 青岛华斯壮能源科技有限公司 Auxiliary positioning keel frame

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050060410A (en) * 2003-12-16 2005-06-22 건원공업 주식회사 Apparatus for adjusting space of anchor bolt
CN208105060U (en) * 2018-03-15 2018-11-16 沈阳公路工程监理有限责任公司 A kind of box beam steel reinforcement cage sizing mould bases
CN211304617U (en) * 2019-07-24 2020-08-21 偃师市华泰综合利用建材有限公司 Evaporate and press aerated concrete reinforcement panel cylinder mould locating rack
CN213539043U (en) * 2020-09-30 2021-06-25 中国能源建设集团黑龙江省电力设计院有限公司 Anchor bolt cage for fan foundation
CN112324152A (en) * 2020-10-30 2021-02-05 上海二十冶建设有限公司 Construction method for accurately installing annular foundation steel reinforcement framework of rotary hearth furnace
CN214557029U (en) * 2020-12-08 2021-11-02 江苏阳湖建设项目管理有限公司 Prefabricated bed-jig device of overpass beam pier column steel reinforcement cage
CN217174892U (en) * 2022-03-04 2022-08-12 青岛华斯壮能源科技有限公司 Auxiliary positioning keel frame

Similar Documents

Publication Publication Date Title
JP4850151B2 (en) Hybrid tower for wind power generation and its construction method
JP5822509B2 (en) Hybrid tower construction method for wind power generator
CN103328820B (en) Method for assembling shell segments for forming tower segments of a hybrid wind turbine tower
CN103243654B (en) Mounting method for steel anchor beam of cable-stayed bridge and assembly jig and cable bent tower mounting platform used in method
CN110965470A (en) A main tower transverse brace structure system and construction method capable of bearing three-way loads
CN111827483B (en) Construction method for roof curved surface # -shaped combined steel truss girder
CN215594016U (en) Mounting structure of shock insulation support
CN105780922A (en) Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss
CN116971278A (en) Construction method of ultra-high super-thick super-large span bent cap support
CN110526153B (en) A jack-assisted pile foundation steel cage lifting structure and construction method thereof
CN211772852U (en) Main tower cross brace structure system capable of bearing three-way load
CN217174892U (en) Auxiliary positioning keel frame
CN115492400A (en) Steel structure net rack lifting construction method
CN115233824A (en) Large-cantilever eccentric ring steel structure and construction method thereof
CN109838087A (en) Reusable assembled architecture support device
CN214459664U (en) Floor-free pier column bent cap template dismounting device
CN217732445U (en) Double-lifting-point lifting support attached to unequal-height concrete columns
CN106592623B (en) Pit structure installation method
CN214195007U (en) Combined connection node of steel reinforced concrete beam and column
CN215857280U (en) High mound river-crossing bridge penetrating bar cantilever supporting system
CN117802883A (en) A method for integrated construction of cable tower cross brace and cross beam steel frame
CN216196958U (en) Cooling tower with double-cross inclined strut structure
CN112412152B (en) A construction method for a bottom-hung, non-derrick, variable-section rectangular chimney support system
CN218346228U (en) Steel-pipe pile prefabricated extension basis
CN216588593U (en) Anti-expansion formwork and platform deformation resistant shaft creeping formwork supporting system

Legal Events