Disclosure of Invention
The invention aims to provide a construction method for progressive excavation of a basin of a river reservoir in plain under the condition of mucky soil, and aims to solve the technical problems of complex operation, difficult construction, higher cost and long time consumption of the existing excavation method for earthwork in the mucky soil foundation.
In order to realize the purpose, the invention adopts the following technical scheme:
a construction method for progressive excavation of a plain river basin under mucky soil conditions comprises the following steps:
step 1, driving a circle of continuous stirring piles at the position of a peripheral dam foot in a reservoir basin to serve as a waterproof curtain;
step 2, dividing the whole warehouse basin into a plurality of large areas, enabling each large area to be adjacent to a main trunk of the warehouse basin, and excavating main drainage ditches on two sides of the main trunk of the warehouse basin;
step 3, paving a temporary construction road by utilizing the surface layer muck of the reservoir basin, compacting the road surface, excavating a secondary drainage ditch on the outer side of the temporary construction road, wherein the temporary construction road passes through all large areas to form a closed loop, and the temporary construction road is paved from the middle part of the reservoir basin to the outside so as to solve the problem that less soil is accumulated in the initial construction stage, and adjacent temporary construction roads can be communicated;
step 4, after the temporary construction road is paved by half, secondary drainage ditches are dug on the outer side of the temporary construction road from inside to outside, at the road intersection, the main drainage ditches and the secondary drainage ditches penetrate through the road intersection in a mode of pipe burying below, and adjacent secondary drainage ditches are communicated and are finally communicated with the main drainage ditches;
step 5, dividing an area between adjacent temporary construction roads into small areas, dividing each small area into a plurality of small strips, connecting one end of each strip with the temporary construction roads and the other end of each strip with a secondary drainage ditch, excavating from the strips of the small area at the outermost side of each large area, and excavating the strips at the outermost side of the large areas at the same time;
step 6, after the excavation of the small area on the outermost side is finished, the construction vehicle excavates the next small area through the temporary construction road and excavates the small areas to the center of the warehouse basin in sequence;
and 7, excavating the temporary construction road and the main road, and excavating the temporary construction road and the main road.
The construction method for progressive excavation of the plain river basin under the condition of mucky soil comprises the following steps of:
step 601, excavating in a small area on the outermost side in a strip mode, and reserving a temporary construction road in the excavating process;
and step 602, after the strip of the small area is excavated, excavating the temporary construction road at the strip.
According to the construction method for progressive excavation of the plain river-facing reservoir basin under the condition of mucky soil, two crossed trunk roads are arranged in the reservoir basin area, and the whole reservoir basin is divided into four large areas by the reservoir basin area trunk roads.
In the construction method for the progressive excavation of the basin of the plain river reservoir under the mucky soil condition, the closed loop is triangular, and the triangular closed loop at the center takes the main road as the bottom edge.
According to the construction method for the progressive excavation of the plain river basin under the mucky soil condition, the distance between adjacent temporary construction roads is 50-70 m.
According to the construction method for the progressive excavation of the basin of the plain river reservoir under the mucky soil condition, the vertexes of the closed-loop triangles are sequentially communicated through the temporary construction road from inside to outside. Or the side edge of the inner closed-loop triangle is vertically connected with the other side edge of the adjacent closed-loop triangle.
The construction method for the progressive excavation of the plain river basin under the condition of mucky soil further comprises water collecting wells, 1-3 water collecting wells are excavated in each secondary drainage ditch, the water overflows to the secondary drainage ditches after being filled with water, the peripheries of the water collecting wells are protected, and warning marks are arranged.
According to the construction method for progressive excavation of the plain river basin under the condition of mucky soil, the main drainage ditch is discharged outside through the drainage outlet.
The construction method for the progressive excavation of the plain river basin under the condition of mucky soil comprises the steps of grading excavated soil, carrying out mucky soil treatment, and filling hard muck to level a main drainage ditch, a secondary drainage ditch and a water collection well.
According to the construction method for progressive excavation of the plain river basin under the condition of mucky soil, a circle of main drainage ditch is excavated in the adjacent continuous stirring pile at one side of the continuous stirring pile, which is far away from a river.
In the step 6, after the excavation of the small region on the outermost side is completed, a secondary drainage ditch is reserved and communicated with the main drainage ditch on the outermost side and the secondary drainage ditch on the inner side.
The construction method for progressive excavation of the plain river reservoir basin under the mucky soil condition is applied to excavation of a mucky soil layer.
The beneficial effects of the invention are: the construction method adopts a mode of excavating from outside to inside by dividing the muddy reservoir basin into a large area, a small area and a strip, and the consolidation of the unearthed muddy soil is beneficial to construction vehicles and manual working for excavating construction of a central area, and basically no disturbance is formed on the muddy soil; and a plurality of large areas are excavated simultaneously, and the problems of long construction period and inconvenient operation of construction machinery in the excavation of the silt texture library basin are effectively solved by adopting a construction method of flow construction.
Detailed Description
The present invention will be described in further detail with reference to examples and drawings, but the embodiments of the present invention are not limited to the examples.
Example 1
A construction method for progressive excavation of a plain river basin under mucky soil conditions comprises the following steps:
step 1, driving a circle of continuous stirring piles 2 along the peripheral dam feet in a reservoir basin to serve as a waterproof curtain;
step 2, dividing the whole reservoir basin into a plurality of large areas, enabling each large area to be adjacent to a reservoir basin main trunk 4, and excavating main drainage ditches 3 on two sides of the reservoir basin main trunk 4;
step 3, paving a temporary construction road 5 by utilizing the surface layer muck of the basin area of the reservoir, compacting the pavement, excavating a secondary drainage ditch 6 at the outer side of the temporary construction road 5, wherein the temporary construction road 5 passes through all large areas to form a closed loop, the temporary construction road 5 is paved from the middle part of the basin of the reservoir to the outside so as to overcome the problem that less soil is accumulated at the initial construction stage, and the adjacent temporary construction roads 5 can be communicated; step 4, after the temporary construction road 5 is paved by a half, excavating a secondary drainage ditch 6 on the outer side of the temporary construction road 5 from inside to outside, wherein at the road intersection, the main drainage ditch 3 and the secondary drainage ditch 6 penetrate through in a mode of burying pipes below, and the adjacent secondary drainage ditches 6 are communicated and are finally communicated with the main drainage ditch 3;
step 5, dividing each small area into a plurality of small strips 7, connecting one end of each strip 7 with the temporary construction road 5, connecting the other end of each strip 7 with a secondary drainage ditch 6, excavating from the strip 7 of the outermost small area of each large area, and excavating the outermost strips 7 of the plurality of large areas at the same time;
step 6, after the excavation of the outermost small area is finished, the construction vehicle excavates the next small area through the temporary construction road 5 and excavates the small areas to the center of the warehouse basin in sequence;
and 7, excavating the temporary construction road 5 and the main road 4, and excavating the temporary construction road 5 and the main road 4.
Example 2
Based on the embodiment 1, the embodiment 2 lists a plurality of new technical features, and the embodiment 1 can be combined with the technical features alternatively or in a plurality, thereby forming a plurality of new and different technical schemes.
Further, the construction method for progressive excavation of the plain river basin under the mucky soil condition includes the following steps:
601, excavating the strips 7 in the area, and reserving a temporary construction road 5 in the excavation process;
and step 602, after the strip 7 in the area is excavated, excavating the temporary construction road 5 at the strip 7.
Optionally, in the construction method for progressively excavating the basin of the plain river reservoir under the mucky soil condition, two crossed main roads 4 exist in the reservoir basin region, and the whole reservoir basin is divided into four large areas by the reservoir basin region main road 4.
Preferably, in the construction method for progressively excavating the flatland riverside basin under the mucky soil condition, the closed loop is triangular, and the central triangular closed loop takes the adjacent main road 4 as the bottom edge.
Preferably, in the construction method for progressively excavating the basin in the plain river bank under the mucky soil condition, the distance between the adjacent temporary construction roads 5 is 50-70 m.
Preferably, in the construction method for progressive excavation of the plain river basin under the condition of mucky soil, the vertexes of the closed-loop triangle are sequentially communicated through the temporary construction road 5 from inside to outside. Or the side edge of the inner closed-loop triangle is vertically connected with the other side edge of the adjacent closed-loop triangle.
Further, in the step 6, after the excavation of the small region at the outermost side is completed, a secondary drainage ditch 6 is reserved and communicated with the main drainage ditch 3 at the outermost side and the secondary drainage ditch 6 at the inner side.
Further, the construction method for progressive excavation of the plain river basin under the condition of mucky soil further comprises water collecting wells, 1-3 water collecting wells are excavated in each secondary drainage ditch 6, the water overflows to the secondary drainage ditch 6 after being full of water, and the peripheries of the water collecting wells are enclosed and provided with warning marks.
Further, in the construction method for progressive excavation of the plain river basin under the condition of mucky soil, the main drainage ditch 3 is discharged outside through the drainage port.
Further, the construction method for the progressive excavation of the basin of the plain river reservoir under the mucky soil condition comprises the steps of grading excavated soil, carrying out mucky soil treatment and filling hard muck to level the main drainage ditch 3, the secondary drainage ditch 6 and the water collection well.
The construction method for progressive excavation of the plain river reservoir basin under the condition of mucky soil is applied to excavation of mucky soil layers.
Example 3
A construction method for the progressive excavation of a plain river basin under the condition of mucky soil comprises the following steps,
step 1, driving a circle of continuous stirring piles 2 into a basin of a river 1 along the peripheral dam feet to serve as a waterproof curtain;
step 2, dividing the whole reservoir into A, B, C, D four large areas by taking two crossed main roads 4 as dividing lines, and excavating main drainage ditches 3 on two sides of the main roads 4 in the reservoir basin area;
step 3, paving a temporary construction road 5 by utilizing the surface layer muck of the reservoir basin area, compacting the road surface, and excavating a secondary drainage ditch 6 on the outer side of the temporary construction road 5;
step 4, the area between the adjacent temporary construction roads 5 is small area, each small area is divided into a plurality of strip-shaped strips 7 by taking 60m width as a unit, strip excavation is carried out from the strip 7 of the small area at the outermost side of each large area, and the excavation of the four large areas is carried out simultaneously;
step 5, after the excavation of the outermost small area is finished, the construction vehicle excavates the next small area through the temporary construction road 5 and excavates the small areas to the center of the warehouse basin in sequence;
and 6, excavating the temporary construction road 5 and the main road 4.
For: step 1, driving a circle of continuous stirring piles 2 along the peripheral dam feet in a reservoir basin to serve as a waterproof curtain;
1. floor cleaning
Farmlands in the excavated areas of the warehouse basin are densely distributed, mainly including sugarcane fields and banana fields, and local parts of the farmlands include fish ponds and small rivers. The resident houses are basically gathered on both sides of the inland river and the rest houses are scattered in the dike. Before excavation, vegetation, construction waste and the like in an excavated area need to be cleaned, and conditions are created for warehouse basin excavation engineering.
2. Pile for continuous stirring
A row of continuous stirring piles 2 are driven into the dam feet at the periphery of the reservoir basin to form a waterproof curtain, so that underground water is prevented from permeating into a dam foundation, and consolidation of silt soil in the reservoir basin area during excavation is facilitated.
Step 2, dividing the whole reservoir into four large areas, and excavating main drainage ditches 3 on two sides of a main trunk road 4 in a reservoir basin area;
1. a circle of main drainage ditch 3 is arranged at a distance of 5m from a dam foot line, and the section of the main drainage ditch 3 is 2m multiplied by 1.5 m;
2. the main drainage ditch 3 is discharged outside by using a river surge drainage outlet.
3. The sump pit arranges along inferior escape canal 6, and every 6 nearby 1 ~ 2 sump pits that set up in inferior escape canal, overflow to inferior escape canal 6 after water is full. Meanwhile, in order to ensure safety, a movable iron horse is used for enclosing the periphery of the water collecting well and a related warning mark is set.
4. DN600 concrete pipes are pre-buried before construction of the temporary construction road 5 newly built in the basin and the cross drainage ditch of the proposed road.
Step 3, paving a temporary construction road 5 by utilizing the residue soil on the surface layer of the reservoir basin area, compacting the road surface, and excavating a secondary drainage ditch 6 on the outer side of the temporary construction road 5:
step 4, dividing each small area into a plurality of strip-shaped strips 7 by taking 60m as a unit, excavating the strips 7 from the small area at the outermost side of each large area, and excavating the four large areas simultaneously:
excavating the strips 7 in a small area, and reserving the temporary construction roads 5 of the strips 7 in the excavation process; after the excavation of the strip 7 in the area is completed, the temporary construction road 5 in the strip 7 is excavated.
Step 5, after the excavation of the peripheral small area is finished, the construction vehicle excavates the next small area through the temporary construction road 5, and excavates the center of the warehouse basin progressively in sequence:
after the consolidation of the soil of the excavation area of the outermost small area is completed, a construction vehicle enters the temporary construction road 5 of the warehousing basin area to perform excavation of the next small area;
step 6, excavating the temporary construction road 5 and the main road 4;
and (5) excavating a temporary construction road 5 and a main road 4 to finish the excavation construction of the whole warehouse basin.
The above description is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments, and all technical solutions belonging to the idea of the present invention belong to the protection scope of the present invention. It should be noted that modifications and adaptations to those skilled in the art without departing from the principles of the present invention should also be considered as within the scope of the present invention.