CN114775604A - Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation - Google Patents

Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation Download PDF

Info

Publication number
CN114775604A
CN114775604A CN202210218220.6A CN202210218220A CN114775604A CN 114775604 A CN114775604 A CN 114775604A CN 202210218220 A CN202210218220 A CN 202210218220A CN 114775604 A CN114775604 A CN 114775604A
Authority
CN
China
Prior art keywords
steel pipe
pipe pile
pile
steel
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210218220.6A
Other languages
Chinese (zh)
Inventor
周松
赵勇
黎辉
谢文善
黄峰峡
叶绍其
舒传林
张健
门保振
匡奇缘
赵凌永
郭江峰
罗哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
5th Engineering Co Ltd of MBEC
Original Assignee
5th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 5th Engineering Co Ltd of MBEC filed Critical 5th Engineering Co Ltd of MBEC
Priority to CN202210218220.6A priority Critical patent/CN114775604A/en
Publication of CN114775604A publication Critical patent/CN114775604A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/06Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers for observation while placing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a construction method for underwater positioning of an implanted rock-socketed foundation steel pipe pile. The underwater steel pipe pile positioning construction method can realize underwater positioning construction of the steel pipe pile, is simple and flexible in structure and convenient to construct, saves materials and simplifies construction procedures; the lifting lugs and the limiting devices are arranged on the outer side of the upper part of the steel pipe pile, and the positioning blocks are welded during lower laying construction, so that the plane position of the steel pipe pile can be accurately controlled, and the steel pipe pile is simple and convenient to construct and flexible to operate; the pile top elevation of the underwater steel pipe pile can be directly measured by adopting the steel wire measuring rope, underwater measurement is converted into overwater control, the method is visual and controllable, and launching construction and underwater measurement work is avoided.

Description

Construction method for underwater positioning of steel pipe pile implanted rock-socketed foundation
Technical Field
The invention relates to the field of wind power and bridge construction, in particular to a construction method for underwater positioning of steel pipe piles implanted into rock-socketed foundations.
Background
The foundation construction technology in the offshore wind power plant construction is high in requirement and complex in process, and is a key factor in the wind power plant construction process. The wind turbine foundation types are various, the difference of applicable geological conditions is large, the wind turbine foundation types are comprehensively influenced by factors such as geology, climate, waves, water flow and tides, and the appropriate foundation type is very important for the construction of offshore wind farms, so that the wind turbine foundation types are preferably used according to the principles of safety, economy, practicability and durability.
The embedded rock foundation is suitable for a fan foundation form with a shallow covering layer and a pile foundation needing to be embedded into a rock stratum below weathered middle, and can be used for construction conditions with severe sea conditions and complex geology.
At present, the embedded rock foundation is the world initiative, and the construction experience of reference is unavailable. The steel pipe pile implanted into the rock-socketed foundation has the advantages of heavy weight, long pile length and pile top below the water surface, and the underwater positioning construction difficulty of the steel pipe pile is high during construction, so that the installation precision is difficult to guarantee. In order to ensure the construction precision of the steel pipe pile implanted with the rock-socketed foundation, accelerate the construction progress and ensure the construction safety, the invention provides a construction method for underwater positioning of the steel pipe pile.
Disclosure of Invention
The invention aims to provide a construction method for underwater positioning of an embedded rock foundation steel pipe pile, which is simple and convenient to construct and high in installation precision, and can effectively reduce the construction difficulty and ensure the construction precision.
The purpose of the invention is realized as follows:
a construction method for underwater positioning of an embedded rock foundation steel pipe pile is characterized by comprising the following steps: the method comprises the following specific steps:
A. a pair of main lifting lugs is symmetrically welded on the left outer side wall and the right outer side wall of the upper part of the steel pipe pile, a pair of limiting devices is symmetrically welded on the front outer side wall and the rear outer side wall of the upper part of the steel pipe pile, and the two main lifting lugs and the two limiting devices are on the same horizontal plane; the two main lifting lugs and the two limiting devices jointly form a steel pipe pile positioning device;
B. the upper end of a hoisting steel wire rope is hung on a floating crane lifting hook before hoisting, the lower end of the hoisting steel wire rope is fixed on a hanging lug of a hanging hanger, a floating crane is adopted in a construction site to lift and lower a steel pipe pile through the hanging hanger and the hanging steel wire rope, the center of the steel pipe pile is aligned to the center of a steel pile casing, the steel pile casing is slowly lowered to the position 1.5m away from the top surface of a hanging platform along the steel pile casing, positioning blocks are welded on the outer sides of a main lifting lug and a limiting device, the clearance between the outer edge of each positioning block and the inner wall of the steel pile casing is not more than 1.0cm, and two steel wire measuring ropes are arranged on the pile top and used for measuring the lowering depth of the steel pipe pile and controlling the pile top elevation of the steel pipe pile;
C. continuously lowering the steel pipe pile along the steel casing, and when the distance between the pile top and the designed elevation is about 0.5m, respectively measuring the height H1 between the pile top and the bottom surface of the suspension hanger and the height H2 between the pile top and the top surface of the suspension platform by using a steel wire measuring rope, and calculating the height H3 between the bottom surface of the suspension hanger and the top surface of the suspension platform, wherein H3= H1-H2;
D. installing a cushion block on the top surface of the hanging platform, and after ensuring that the position and the height H3 of the landing pad are correct, firmly welding the cushion block and the hanging platform by adopting a welding seam;
E. the floating crane slowly loosens the lifting hook of the floating crane until the hanging hanger is placed on the top surface of the cushion block, the elevation of the pile top is remeasured by using the steel wire measuring rope, and after the design requirement is met, the connection between the hoisting steel wire rope and the lifting hook of the floating crane is removed;
F. and repeating the step B, C, D, E to finish the lowering installation construction of the rest steel pipe piles.
According to the invention, a pair of main lifting lugs are arranged on the left outer side wall and the right outer side wall of the same horizontal plane at the upper part of the steel pipe pile, a pair of limiting devices are arranged on the front outer side wall and the rear outer side wall, positioning blocks are welded on the outer sides of the main lifting lugs and the limiting devices when the steel pipe pile is placed down for horizontal positioning of the steel pipe pile, and a steel wire measuring rope is installed on the pile top for controlling the elevation of the pile top, so that the underwater positioning construction of the steel pipe pile is completed.
Compared with the prior art, the invention has the advantages that:
1. the outer side of the upper part of the steel pipe pile is provided with a lifting lug and a limiting device, a positioning block is welded on site during laying construction, and the plane position of the steel pipe pile can be accurately controlled;
2. the two steel wire measuring ropes are arranged at the top of the steel pipe pile, the pile top elevation of the underwater steel pipe pile can be directly measured and controlled on a construction platform, underwater measurement is converted into overwater control, the underwater steel pipe pile is visual and controllable, and launching construction and underwater measurement work is avoided;
3. the underwater steel pipe pile positioning device can realize underwater positioning construction of steel pipe piles, is simple and flexible in structure, simple and convenient in construction, high in installation precision and flexible in operation, saves materials and simplifies construction procedures.
Drawings
FIG. 1 is a schematic structural view of a steel pipe pile;
FIG. 2 is a top view taken at A-A of FIG. 1;
FIG. 3 is a vertical plane layout of steel pipe pile hanging;
FIG. 4 is a layout view of the hanging side of the steel pipe pile;
FIG. 5 is a construction drawing of step B of steel pipe pile implantation construction
FIG. 6 is a construction drawing of step B of steel pipe pile implantation construction;
FIG. 7 is a construction drawing of step C of steel pipe pile implantation construction;
fig. 8 is a construction drawing of step D, E of steel pipe pile implantation construction.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings in conjunction with embodiments.
With reference to the attached drawings 1-8, an implementation mode of the construction method for underwater positioning of the steel pipe pile implanted with the rock-socketed foundation is as follows:
A. a pair of main lifting lugs 2 are symmetrically welded on the left outer side wall and the right outer side wall of the upper part of the steel pipe pile 1, a pair of limiting devices 3 are symmetrically welded on the front outer side wall and the rear outer side wall of the upper part of the steel pipe pile 1, and the two main lifting lugs 2 and the two limiting devices 3 are on the same horizontal plane; the two main lifting lugs 2 and the two limiting devices 3 jointly form a steel pipe pile positioning device;
B. the upper end of a hoisting steel wire rope 12 before hoisting is hung on a floating crane lifting hook 13, the lower end of the hoisting steel wire rope 12 is fixed on a hanging lug 14 of a hanging hanger 5, the floating hanger 4 is adopted in a construction site to lift and lower the steel pipe pile 1 through the hanging hanger 5 and the hanging steel wire rope 6, the center of the steel pipe pile 1 is aligned to the center of a steel casing 7, the steel casing 7 is slowly lowered to the position 1.5m away from the top surface of a hanging platform 8 along the top of the steel pipe pile 1 (hereinafter referred to as the pile top), a positioning block 9 is welded on the outer sides of a main lifting lug 2 and a limiting device 3, the gap between the outer edge of the positioning block 9 and the inner wall of the steel casing 7 is not more than 1.0cm, and meanwhile, two steel wire measuring ropes 10 are arranged on the pile top and used for measuring the lowering depth of the steel pipe pile 1 and controlling the pile top elevation of the steel pipe pile 1;
C. continuously lowering the steel pipe pile 1 along the steel casing 7, and when the pile top is about 0.5m away from the designed elevation, respectively measuring the height H1 from the pile top of the steel pipe pile 1 to the bottom surface of the hanging hanger 5 and the height H2 from the top surface of the hanging platform 8 by adopting a steel wire measuring rope 10, and calculating the height H3 of a landing pad between the bottom surface of the hanging hanger 5 and the top surface of the hanging platform 8, wherein H3= H1-H2;
D. installing a cushion block 11 on the top surface of the hanging platform 8, and after ensuring that the position and the height H3 of the landing pad are correct, firmly welding the cushion block 11 and the hanging platform 8 by adopting a welding seam;
E. the floating crane 4 slowly loosens the floating crane hook 13 until the hanging sling 5 is placed on the top surface of the cushion block 11, the steel wire measuring rope 10 is used for re-measuring the elevation of the pile top, and after the design requirement is met, the connection between the hoisting steel wire rope 12 and the floating crane hook 13 is removed;
F. and repeating the step B, C, D, E to finish the lowering, installation and construction of the rest steel pipe piles 1.
The present invention is not limited to the above-mentioned preferred embodiments, and any structural changes made under the teaching of the present invention shall fall within the protection scope of the present invention, which has the same or similar technical solutions as the present invention.

Claims (1)

1. A construction method for underwater positioning of steel pipe piles implanted into rock-socketed foundation is characterized by comprising the following steps: the method comprises the following specific steps:
A. a pair of main lifting lugs are symmetrically welded on the left outer side wall and the right outer side wall of the upper part of the steel pipe pile, a pair of limiting devices are symmetrically welded on the front outer side wall and the rear outer side wall of the upper part of the steel pipe pile, and the two main lifting lugs and the two limiting devices are on the same horizontal plane; the two main lifting lugs and the two limiting devices jointly form a steel pipe pile positioning device;
B. the upper end of a hoisting steel wire rope is hung on a floating crane hook before hoisting, the lower end of the hoisting steel wire rope is fixed on a hanger of a hanging hanger, a floating crane is adopted in a construction site to hoist and lower a steel pipe pile through the hanging hanger and the hoisting steel wire rope, the center of the steel pipe pile is aligned to the center of a steel protecting cylinder, when the steel protecting cylinder is slowly lowered to the position, 1.5m away from the top surface of a hanging platform, of the top of the steel pipe pile, a positioning block is welded on the outer side of a main lifting lug and the outer side of a limiting device, the gap between the outer edge of the positioning block and the inner wall of the steel protecting cylinder is not more than 1.0cm, and meanwhile, two steel wire measuring ropes are arranged at the pile top and used for measuring the lowering depth of the steel pipe pile and controlling the pile top elevation of the steel pipe pile;
C. continuously lowering the steel pipe pile along the steel casing, and when the distance between the pile top and the designed elevation is about 0.5m, respectively measuring the height H1 between the pile top and the bottom surface of the suspension hanger and the height H2 between the pile top and the top surface of the suspension platform by using a steel wire measuring rope, and calculating the height H3 between the bottom surface of the suspension hanger and the top surface of the suspension platform, wherein H3= H1-H2;
D. installing a cushion block on the top surface of the hanging platform, and after ensuring that the position and the height H3 of the lifting pad are correct, firmly welding the cushion block and the hanging platform by adopting a welding seam;
E. the floating crane slowly loosens the lifting hook of the floating crane until the hanging hanger is placed on the top surface of the cushion block, the elevation of the pile top is remeasured by using the steel wire measuring rope, and after the design requirement is met, the connection between the hoisting steel wire rope and the lifting hook of the floating crane is removed;
F. and repeating the step B, C, D, E to finish the lowering installation construction of the rest steel pipe piles.
CN202210218220.6A 2022-03-08 2022-03-08 Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation Pending CN114775604A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210218220.6A CN114775604A (en) 2022-03-08 2022-03-08 Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210218220.6A CN114775604A (en) 2022-03-08 2022-03-08 Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation

Publications (1)

Publication Number Publication Date
CN114775604A true CN114775604A (en) 2022-07-22

Family

ID=82422965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210218220.6A Pending CN114775604A (en) 2022-03-08 2022-03-08 Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation

Country Status (1)

Country Link
CN (1) CN114775604A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019065755A1 (en) * 2017-09-28 2019-04-04 調和工業株式会社 Pile construction method, manifold device, and manifold device design method
CN113006075A (en) * 2021-02-02 2021-06-22 中铁大桥局集团第五工程有限公司 Steel pipe pile implanting method for implanting rock-socketed pile foundation construction
CN215165629U (en) * 2021-04-07 2021-12-14 中交路桥建设有限公司 Structure for lowering steel cofferdam by utilizing steel pipe pile of drilling platform

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019065755A1 (en) * 2017-09-28 2019-04-04 調和工業株式会社 Pile construction method, manifold device, and manifold device design method
CN113006075A (en) * 2021-02-02 2021-06-22 中铁大桥局集团第五工程有限公司 Steel pipe pile implanting method for implanting rock-socketed pile foundation construction
CN215165629U (en) * 2021-04-07 2021-12-14 中交路桥建设有限公司 Structure for lowering steel cofferdam by utilizing steel pipe pile of drilling platform

Similar Documents

Publication Publication Date Title
CN101725112B (en) Construction method for piers
CN108842806B (en) Construction process of offshore wind power foundation non-rock-socketed single pile
CN102251530B (en) Construction process of double-wall steel cofferdam for construction of pier bearing platform in main river water of Yellow River
CN109629568A (en) The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating
CN203393714U (en) Precisely positioned offshore piling guide frame
CN113006075B (en) Steel pipe pile implanting method for implanting rock-socketed pile foundation construction
CN110295648B (en) A facility for taking water from a rapid riverbed and its overall installation and construction method
CN113897959A (en) Underwater positioning guide frame for offshore wind power foundation pile sinking and pile sinking construction method
CN114673153A (en) Construction method of super long diameter pile foundation casing structure in complex stratum
CN115787645A (en) Quick pile sinking construction process for four-pile jacket foundation by offshore wind power deepwater pile-first method
CN104805814A (en) Self-elevating platform pile leg mounting method
CN106337971A (en) A buoyancy variable buoyancy tank and its application
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
CN107761751A (en) A kind of Double-Wall Steel Boxed Cofferdam and its construction method
CN119041476A (en) Foundation construction method of offshore special-shaped root-opened rock-socketed jacket pile
CN202969333U (en) Steel truss rock-socketed wharf structure
CN114775604A (en) Construction method for underwater positioning of steel pipe pile implanted into rock-socketed foundation
CN102720211B (en) Wedge type bottom-end deviation fine-rectifying system for immersed pipe and rectifying process of wedge type bottom-end deviation fine-rectifying system
CN115872290B (en) Water intake head hoisting method of water intake pump station
CN215594060U (en) A ground connection wall guide wall structure adjacent to pipelines in a narrow space
CN209636844U (en) A non-rock-socketed back pile method inclined pile jacket construction system
CN117166438A (en) Suction barrel foundation suitable for submarine booster station and installation resistance calculation method thereof
CN104047276B (en) The on-the-spot joining method of a kind of lattice steel sheet pile large cylinder nominative sheet pile 1/4 cylinder
CN116161172A (en) A combined concrete anchorage offshore construction method
KR20230130375A (en) Jacking type offshore wind farm structure with seabed setting frame and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220722