CN114714502A - Concrete beam steel bar framework support binding and mounting method - Google Patents
Concrete beam steel bar framework support binding and mounting method Download PDFInfo
- Publication number
- CN114714502A CN114714502A CN202210477155.9A CN202210477155A CN114714502A CN 114714502 A CN114714502 A CN 114714502A CN 202210477155 A CN202210477155 A CN 202210477155A CN 114714502 A CN114714502 A CN 114714502A
- Authority
- CN
- China
- Prior art keywords
- template
- long
- long support
- portal frame
- main rib
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 23
- 239000010959 steel Substances 0.000 title claims abstract description 23
- 239000004567 concrete Substances 0.000 title claims abstract description 19
- 238000000034 method Methods 0.000 title claims abstract description 14
- 230000002787 reinforcement Effects 0.000 claims abstract description 51
- 239000000725 suspension Substances 0.000 claims abstract description 26
- 238000009415 formwork Methods 0.000 claims description 18
- 238000004519 manufacturing process Methods 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims 1
- 239000011241 protective layer Substances 0.000 description 7
- 210000003205 muscle Anatomy 0.000 description 4
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B7/00—Moulds; Cores; Mandrels
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses a concrete beam steel reinforcement framework support binding and mounting method, which solves the problem that the position of a steel reinforcement framework in a beam entering a beam template cannot be accurately controlled in the conventional support; the method comprises the following steps that floor boards on two sides of a beam template are poured on a bottom template, a portal frame is movably erected, a screw rod threaded hole is formed in the middle of a top beam of the portal frame, a vertical suspension screw rod is screwed in the screw rod threaded hole, a long support plate is screwed on the lower portion of the vertical suspension screw rod, an upper main rib in the beam is arranged on the long support plate, the upper main rib in the beam arranged on the long support plate is used as a support, a lower main rib and a beam hoop rib in the beam are arranged in a suspension mode, the positions of the main ribs on two sides in the beam are controlled, and the distances between the main ribs on two sides in the beam and the outer side end of the long support plate are equal; after the reinforcement frameworks in the beam are bound, the suspended reinforcement frameworks in the beam are stably put into the beam template by rotating the vertical suspension lead screw; greatly improving the binding and mounting quality of the beam reinforcement framework.
Description
Technical Field
The invention relates to a temporary bracket for binding a beam steel reinforcement framework, in particular to a temporary bracket for binding a steel reinforcement framework of a reinforced concrete beam with a large cross section and a method for supporting, binding and sinking into a beam template.
Background
In the construction of a main structure of a cast-in-place concrete building, before binding of steel bars in a concrete beam, a beam bottom template, templates on two sides of the beam and a bottom template poured by a floor plate are generally erected, and then binding of a steel bar framework in the beam is carried out; because the width of the reinforcement framework in the beam is only smaller than the distance between the templates on the two sides of the beam by two protective layer distances, which are generally about 50 mm, and the height of the template on the side of the beam is larger, the reinforcement framework in the beam cannot be directly arranged on the bottom template of the beam for binding, but the reinforcement framework in the beam is lifted up right above the beam in a way of erecting a frame pipe support for binding the main reinforcements of the beam and the stirrups of the beam; after the whole framework is bound, the frame pipe support is removed, and the bound reinforcement framework in the beam is integrally placed in the beam template; the existing frame pipe support for binding the beam framework is erected by adopting a fastener steel pipe, and by adopting the method, the defects that the frame pipe support is inconvenient to erect and the safety coefficient is low exist, particularly, when the steel rib framework in the whole beam is placed down into a beam template after binding is finished, the position of the steel rib framework in the beam template cannot be accurately controlled, and the casting width of the concrete protective layer reserved on two sides of the steel rib framework in the beam is often inconsistent, so that the cast beam body is not in accordance with the design requirement.
Disclosure of Invention
The invention provides a concrete beam steel reinforcement framework support binding and mounting method, which solves the technical problem that the position of a steel reinforcement framework in a beam entering a beam template cannot be accurately controlled in the conventional support.
The invention solves the technical problems by the following technical scheme:
the general concept of the invention is: the method comprises the steps that bottom templates are poured on floor plates on two sides of a beam template, a portal frame is movably erected, a top beam of the portal frame is arranged right above the beam template, a screw rod screwed hole is formed in the middle of the top beam of the portal frame, a vertical suspension screw rod is screwed in the screw rod screwed hole, a long support plate is screwed at the lower part of the vertical suspension screw rod, the width of the long support plate is equal to the distance between the templates on two sides of the beam, upper main ribs in the beam are arranged on the long support plate, the upper main ribs in the beam arranged on the long support plate are used as supports, lower main ribs in the beam and beam stirrups are arranged in a suspension mode, the positions of the main ribs on two sides in the beam are controlled, and the distances between the main ribs on two sides in the beam and the outer side ends of the long support plate are equal; after the reinforcement framework in the beam is bound, the long support plate and the reinforcement framework in the beam suspended on the long support plate are stably put down into the beam template by rotating the vertical suspension lead screw, and finally, the long support plate is rotated by 90 degrees, the portal frame, the vertical suspension lead screw and the long support plate are upwards lifted and removed from the upper part of the beam template.
A temporary bracket for supporting and binding a concrete beam steel reinforcement framework comprises a floor slab pouring bottom template, wherein a beam template consisting of a beam left side template, a beam bottom template and a beam right side template is arranged on the floor slab pouring bottom template on two sides of the beam template, portal frames are arranged on the floor slab pouring bottom template on two sides of the beam template at intervals, a top cross beam of the portal frame is arranged right above the beam template, a screw rod screw thread hole is arranged on the top cross beam, a vertical suspension screw rod is screwed in the screw rod screw thread hole, a long strip supporting plate is screwed on the vertical suspension screw rod below the top cross beam through a long strip plate screw thread hole on the long strip supporting plate, a main rib at the top end of the left side in the beam is lapped on the top end surface of the left side of the long strip supporting plate, a main rib at the top end of the right side in the beam is lapped on the top end surface of the right side of the long strip supporting plate, a beam stirrup is arranged between the top main rib at the left side in the beam and the top main rib at the right side in the beam, and the bottom main rib at the left side in the beam and the bottom main rib at the right side in the beam are respectively hung at the lower end of the beam stirrup; the length of the long supporting plate is equal to the distance between the left side template and the right side template of the beam; the distance between the top main rib on the left side in the beam and the vertical face of the left end of the long supporting plate is equal to the thickness of the concrete beam protective layer, and the distance between the top main rib on the right side in the beam and the vertical face of the right end of the long supporting plate is equal to the thickness of the concrete beam protective layer.
The screw rod is in threaded connection with the screw hole and is arranged on the central axis of the beam template; on the left end top surface of rectangular backup pad, be provided with left side interval control recess, left side top owner muscle sets up in left side interval control recess in the roof beam, on the right-hand member top surface of rectangular backup pad, is provided with right side interval control recess, and right side top owner muscle sets up in right side interval control recess in the roof beam.
A concrete beam steel reinforcement framework support binding and mounting method comprises a floor slab pouring bottom formwork, wherein a beam formwork consisting of a beam left side formwork, a beam bottom formwork and a beam right side formwork is arranged on the floor slab pouring bottom formwork, and is characterized by comprising the following steps:
firstly, manufacturing a portal frame, wherein the height of the portal frame is greater than that of a reinforcement cage in a beam; a screw rod is arranged at the middle position of a top beam of the portal frame and is in threaded connection with a screw hole; manufacturing a long supporting plate, wherein a long strip plate is arranged in the middle of the long supporting plate and is in threaded connection with a screw hole, so that the length of the long supporting plate is equal to the distance between the left side template of the beam and the right side template of the beam; a left side distance control groove is arranged on the top surface of the left end of the long supporting plate, so that the distance between the left side distance control groove and the vertical surface of the left end of the long supporting plate is equal to 25 mm, and a right side distance control groove is arranged on the top surface of the right end of the long supporting plate, so that the distance between the right side distance control groove and the vertical surface of the right end of the long supporting plate is equal to 25 mm;
secondly, arranging portal frames at intervals on floor slab pouring bottom templates on two sides of the beam template, and enabling top beams of the portal frames to be arranged right above the beam template;
thirdly, screwing a vertical suspension screw rod into a screw rod screwing screw hole arranged in the middle of the top cross beam, screwing a long support plate on the vertical suspension screw rod below the top cross beam, adjusting the long support plates on each portal frame to the same horizontal plane, and enabling the long support plates and the central axis of the beam template to be mutually vertical;
fourthly, respectively overlapping a top end main rib on the left side in the beam and a top end main rib on the right side in the beam on a long support plate of each portal frame, so that the top end main rib on the left side in the beam is embedded into a left side interval control groove on the long support plate, and the top end main rib on the right side in the beam is embedded into a right side interval control groove of the long support plate;
fifthly, binding a beam stirrup, a beam inner left side bottom end main reinforcement and a beam inner right side bottom end main reinforcement by taking the beam inner left side top end main reinforcement and the beam inner right side top end main reinforcement as supports to finish binding of a beam inner reinforcement framework;
sixthly, simultaneously rotating the vertical suspension screws on the portal frames, and synchronously putting the long support plates and the in-beam reinforcement frameworks suspended on the long support plates onto the beam bottom template;
and seventhly, after the long support plates are separated from the support for the reinforcement frameworks in the beam, rotating the long support plates for 90 degrees, then synchronously lifting and hoisting the portal frames, and taking the long support plates and the vertical suspension screws out of the beam template.
Bottom supporting blocks are arranged at the bottom ends of the two upright posts of the portal frame; the lower bottom surface of the top cross beam is provided with a strip-shaped groove, the upper ends of two vertical columns of the portal frame are embedded into the strip-shaped groove, the front side vertical surface of the top cross beam is provided with screw holes at intervals, and the vertical columns of the portal frame are connected with the top cross beam through the screw holes by connecting bolts.
The invention realizes the binding process of the beam steel reinforcement framework and the accurate positioning when the whole framework is put into the beam template, and ensures that the thickness of the concrete protective layers at the two sides of the beam can meet the design requirement after the concrete is poured; the bracket is combined, can be flexibly adjusted according to the width of the beam body, has strong universality and can be repeatedly used; the whole operation process is simple, safe and reliable, and the binding and mounting quality of the beam reinforcement framework is greatly improved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a sectional view taken along line a-a in fig. 1.
Detailed Description
The invention is described in detail below with reference to the accompanying drawings:
a temporary bracket for supporting and binding a concrete beam steel reinforcement framework comprises a floor slab pouring bottom template 1, wherein a beam template consisting of a beam left side template 3, a beam bottom template 2 and a beam right side template 4 is arranged on the floor slab pouring bottom template 1 at two sides of the beam template, portal frames 5 are arranged on the floor slab pouring bottom template 1 at intervals, a top cross beam 6 of the portal frames 5 is arranged right above the beam template, a screw rod threaded screw hole 7 is arranged on the top cross beam 6, a vertical suspension screw 8 is screwed in the screw rod threaded screw hole 7, a long supporting plate 9 is screwed on the vertical suspension screw 8 below the top cross beam 6, the long supporting plate 9 is screwed on the vertical suspension screw 8 through a long strip plate threaded screw hole 10 on the long supporting plate, a main rib 11 at the top end of the left side in the beam is lapped on the top end face of the left side of the long supporting plate 9, and a right side top end face of the long supporting plate 9, the main reinforcement 12 at the top end of the right side in the beam is lapped, a beam stirrup 13 is arranged between the main reinforcement 11 at the top end of the left side in the beam and the main reinforcement 12 at the top end of the right side in the beam, and the main reinforcement 14 at the bottom end of the left side in the beam and the main reinforcement 15 at the bottom end of the right side in the beam are respectively hung at the lower end of the beam stirrup 13; the length of the long supporting plate 9 is equal to the distance between the beam left side template 3 and the beam right side template 4; the distance between the top main reinforcement 11 at the left side in the beam and the vertical face of the left end of the long supporting plate 9 is equal to the thickness of the concrete beam protective layer, and the distance between the top main reinforcement 12 at the right side in the beam and the vertical face of the right end of the long supporting plate 9 is equal to the thickness of the concrete beam protective layer.
The screw rod is in threaded connection with the screw hole 7 and is arranged on the central axis of the beam template; on the left end top surface of rectangular backup pad 9, be provided with left side interval control recess 16, left side top owner muscle 11 sets up in left side interval control recess 16 in the roof beam, on the right-hand member top surface of rectangular backup pad 9, is provided with right side interval control recess 17, and right side top owner muscle 12 sets up at right side interval control recess 17 in the roof beam.
A concrete beam steel reinforcement framework support binding and mounting method comprises a floor slab pouring bottom formwork 1, wherein a beam formwork which is composed of a beam left side formwork 3, a beam bottom formwork 2 and a beam right side formwork 4 is arranged on the floor slab pouring bottom formwork 1, and is characterized by comprising the following steps:
firstly, manufacturing a portal frame 5, wherein the height of the portal frame 5 is larger than that of a reinforcement cage in a beam; a screw rod is in threaded connection with a screw hole 7 at the middle position of a top cross beam 6 of the portal frame 5; manufacturing a long supporting plate 9, arranging a long strip plate in threaded connection with a screw hole 10 in the middle of the long supporting plate 9, and enabling the length of the long supporting plate 9 to be equal to the distance between the beam left side template 3 and the beam right side template 4; a left side distance control groove 16 is formed in the top face of the left end of the long support plate 9, so that the distance between the left side distance control groove 16 and the vertical face of the left end of the long support plate 9 is 25 mm, and a right side distance control groove 17 is formed in the top face of the right end of the long support plate 9, so that the distance between the right side distance control groove 17 and the vertical face of the right end of the long support plate 9 is 25 mm;
secondly, arranging portal frames 5 on the floor slab pouring bottom formwork 1 on two sides of the beam formwork at intervals, and enabling top beams 6 of the portal frames 5 to be arranged right above the beam formwork;
thirdly, screwing a vertical suspension screw 8 into a screw bolt screw hole 7 arranged in the middle of the top cross beam 6, screwing a strip support plate 9 onto the vertical suspension screw 8 below the top cross beam 6, adjusting the strip support plates 9 on each portal frame 5 to the same horizontal plane, and enabling the strip support plates 9 to be mutually vertical to the central axis of the beam template;
fourthly, respectively overlapping a top end main rib 11 at the left side in the beam and a top end main rib 12 at the right side in the beam on a long supporting plate 9 of each portal frame 5, so that the top end main rib 11 at the left side in the beam is embedded into a left side interval control groove 16 on the long supporting plate 9, and the top end main rib 12 at the right side in the beam is embedded into a right side interval control groove 17 of the long supporting plate 9;
fifthly, binding a beam stirrup 13, a beam inner left side bottom end main reinforcement 14 and a beam inner right side bottom end main reinforcement 15 by taking the beam inner left side top end main reinforcement 11 and the beam inner right side top end main reinforcement 12 as supports to complete binding of the beam inner reinforcement framework;
sixthly, simultaneously rotating the vertical suspension screws 8 on the portal frames 5, and synchronously putting the long support plates 9 and the in-beam reinforcement frameworks suspended on the long support plates onto the beam bottom template 2;
and seventhly, after the long support plates 9 are separated from supporting the steel reinforcement framework in the beam, rotating the long support plates 9 by 90 degrees, then synchronously lifting and hoisting the portal frames 5, and taking the long support plates 9 and the vertical suspension screws 8 out of the beam template.
Bottom supporting blocks 18 are arranged at the bottom ends of the two upright posts of the portal frame 5; a strip groove 19 is arranged on the lower bottom surface of the top cross beam 6, the upper ends of two vertical columns of the portal frame 5 are embedded in the strip groove 19, screw holes 20 are arranged on the front side vertical surface of the top cross beam 6 at intervals, connecting bolts 21 are connected, and the vertical columns of the portal frame 5 are connected with the top cross beam 6 through the screw holes 20; the two upright posts of the portal frame can be replaced according to the width and the height of the binding beam reinforcing steel bars, and the mounting positions of the upright posts and the top cross beam are changed so as to adapt to the requirement of beam binding.
Claims (2)
1. The utility model provides a concrete beam framework of steel reinforcement supports ligature and installation method, includes floor board pouring die block board (1), on floor board pouring die block board (1), is provided with the roof beam template of constituteing by roof beam left side template (3), roof beam die block board (2) and roof beam right side template (4), its characterized in that following step:
firstly, manufacturing a portal frame (5), wherein the height of the portal frame (5) is larger than that of a reinforcement cage in a beam; a screw rod is screwed with a screw hole (7) at the middle position of a top beam (6) of the portal frame (5); manufacturing a long supporting plate (9), arranging a long strip plate in a threaded connection screw hole (10) in the middle of the long supporting plate (9), and enabling the length of the long supporting plate (9) to be equal to the distance between the beam left side template (3) and the beam right side template (4); a left-side distance control groove (16) is formed in the top face of the left end of the long supporting plate (9), the distance between the left-side distance control groove (16) and the vertical face of the left end of the long supporting plate (9) is equal to 25 mm, and a right-side distance control groove (17) is formed in the top face of the right end of the long supporting plate (9), and the distance between the right-side distance control groove (17) and the vertical face of the right end of the long supporting plate (9) is equal to 25 mm;
secondly, arranging portal frames (5) on the floor slab pouring bottom formwork (1) on two sides of the beam formwork at intervals, and enabling top beams (6) of the portal frames (5) to be arranged right above the beam formwork;
thirdly, screwing a vertical suspension screw (8) into a screw screwing bolt hole (7) of the screw arranged in the middle of the top cross beam (6), screwing a long support plate (9) onto the vertical suspension screw (8) below the top cross beam (6), adjusting the long support plates (9) on each portal frame (5) to the same horizontal plane, and enabling the long support plates (9) and the central axis of the beam template to be mutually vertical;
fourthly, overlapping a top end main rib (11) at the left side in the beam and a top end main rib (12) at the right side in the beam on a long support plate (9) of each portal frame (5) respectively to enable the top end main rib (11) at the left side in the beam to be embedded into a left side interval control groove (16) on the long support plate (9) and enable the top end main rib (12) at the right side in the beam to be embedded into a right side interval control groove (17) of the long support plate (9);
fifthly, binding a beam stirrup (13), a beam inner left side bottom end main rib (14) and a beam inner right side bottom end main rib (15) by taking the beam inner left side top end main rib (11) and the beam inner right side top end main rib (12) as supports to finish binding of a beam inner reinforcement framework;
sixthly, rotating the vertical suspension screw rods (8) on the portal frames (5) simultaneously, and synchronously putting the long support plates (9) and the beam inner reinforcement frameworks suspended on the long support plates onto the beam bottom template (2);
and seventhly, after the long support plates (9) are separated from the support of the steel reinforcement framework in the beam, rotating the long support plates (9) for 90 degrees, then synchronously lifting and hoisting the portal frames (5), and taking the long support plates (9) and the vertical suspension screws (8) out of the beam template.
2. The concrete beam steel reinforcement framework support binding and mounting method as claimed in claim 1, wherein bottom support blocks (18) are arranged at the bottom ends of two upright columns of the portal frame (5); the lower bottom surface of the top cross beam (6) is provided with a strip groove (19), the upper ends of two vertical columns of the portal frame (5) are embedded into the strip groove (19), the front side vertical surface of the top cross beam (6) is provided with screw holes (20) at intervals, and connecting bolts (21) connect the vertical columns of the portal frame (5) with the top cross beam (6) through the screw holes (20).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210477155.9A CN114714502A (en) | 2022-05-03 | 2022-05-03 | Concrete beam steel bar framework support binding and mounting method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210477155.9A CN114714502A (en) | 2022-05-03 | 2022-05-03 | Concrete beam steel bar framework support binding and mounting method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN114714502A true CN114714502A (en) | 2022-07-08 |
Family
ID=82245366
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210477155.9A Pending CN114714502A (en) | 2022-05-03 | 2022-05-03 | Concrete beam steel bar framework support binding and mounting method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114714502A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115847580A (en) * | 2022-12-21 | 2023-03-28 | 中国人民解放军陆军勤务学院 | Frame muscle formula concrete mold |
| CN115958679A (en) * | 2022-12-21 | 2023-04-14 | 中国人民解放军陆军勤务学院 | Precast concrete test piece mould |
| CN116181072A (en) * | 2023-01-04 | 2023-05-30 | 中国建筑第八工程局有限公司 | A reinforcement tool for beam main reinforcement |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102979311A (en) * | 2012-12-06 | 2013-03-20 | 上海中锦建设集团股份有限公司 | Auxiliary device for binding reinforcements of reinforced concrete beam and application thereof |
| CN104989036A (en) * | 2015-06-23 | 2015-10-21 | 江苏南通三建集团有限公司 | Oversized reinforced concrete beam fixed rebar support structure and rebar binding method thereof |
| CN207296184U (en) * | 2017-08-22 | 2018-05-01 | 中国建筑第八工程局有限公司 | A kind of beam steel positioner |
| CN109707169A (en) * | 2018-12-28 | 2019-05-03 | 中国二十冶集团有限公司 | The quickly method of adjustment beam bottom cover to reinforcement |
| CN211647375U (en) * | 2019-12-25 | 2020-10-09 | 河南省第一建筑工程集团有限责任公司 | House construction stirrup binding tool |
| CN111764579A (en) * | 2020-07-10 | 2020-10-13 | 中国建筑第八工程局有限公司 | Steel bar positioning device of concrete beam and steel bar construction method thereof |
| CN212129960U (en) * | 2020-04-28 | 2020-12-11 | 山西建设投资集团有限公司 | Overhead installation device for frame beam reinforcing steel bars |
| CN112324153A (en) * | 2020-11-05 | 2021-02-05 | 中国二十二冶集团有限公司 | A reinforcement auxiliary device for job site |
-
2022
- 2022-05-03 CN CN202210477155.9A patent/CN114714502A/en active Pending
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102979311A (en) * | 2012-12-06 | 2013-03-20 | 上海中锦建设集团股份有限公司 | Auxiliary device for binding reinforcements of reinforced concrete beam and application thereof |
| CN104989036A (en) * | 2015-06-23 | 2015-10-21 | 江苏南通三建集团有限公司 | Oversized reinforced concrete beam fixed rebar support structure and rebar binding method thereof |
| CN207296184U (en) * | 2017-08-22 | 2018-05-01 | 中国建筑第八工程局有限公司 | A kind of beam steel positioner |
| CN109707169A (en) * | 2018-12-28 | 2019-05-03 | 中国二十冶集团有限公司 | The quickly method of adjustment beam bottom cover to reinforcement |
| CN211647375U (en) * | 2019-12-25 | 2020-10-09 | 河南省第一建筑工程集团有限责任公司 | House construction stirrup binding tool |
| CN212129960U (en) * | 2020-04-28 | 2020-12-11 | 山西建设投资集团有限公司 | Overhead installation device for frame beam reinforcing steel bars |
| CN111764579A (en) * | 2020-07-10 | 2020-10-13 | 中国建筑第八工程局有限公司 | Steel bar positioning device of concrete beam and steel bar construction method thereof |
| CN112324153A (en) * | 2020-11-05 | 2021-02-05 | 中国二十二冶集团有限公司 | A reinforcement auxiliary device for job site |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115847580A (en) * | 2022-12-21 | 2023-03-28 | 中国人民解放军陆军勤务学院 | Frame muscle formula concrete mold |
| CN115958679A (en) * | 2022-12-21 | 2023-04-14 | 中国人民解放军陆军勤务学院 | Precast concrete test piece mould |
| CN116181072A (en) * | 2023-01-04 | 2023-05-30 | 中国建筑第八工程局有限公司 | A reinforcement tool for beam main reinforcement |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109577534B (en) | Tool-based hanging die assembly type composite floor slab and construction method | |
| CN109736449B (en) | Stiff structure beam-column joint and construction method | |
| CN106906955B (en) | Shear wall integral prefabricated reinforcement mesh structure and construction method thereof | |
| CN115233960B (en) | Integral construction platform structure and method for adding core tube wall in air | |
| CN103669865A (en) | Stair construction method through shaped supports | |
| CN114482529A (en) | Back-jacking construction method for post-cast strip galvanized steel pipe support frame | |
| CN217461527U (en) | Temporary bracket for supporting and binding concrete beam steel reinforcement framework | |
| CN111206768B (en) | Light beam plate structure platform and construction method thereof | |
| CN115075613A (en) | Fabricated building supporting system and construction method thereof | |
| CN114351943B (en) | Shaped steel mould large-section stiff fair-faced concrete column structure and construction method | |
| CN222140476U (en) | Prefabricated post connection structure of assembled reinforced concrete | |
| CN110670873B (en) | A kind of support system and construction method of steel formwork for ultra-high-section concrete column | |
| CN220521751U (en) | Curved variable cross-section concrete double beam | |
| CN220285129U (en) | Filling box anti-floating device for cast-in-situ hollow floor system | |
| CN114856036B (en) | Recycled concrete ribbed membrane shell concrete shear wall | |
| CN114922351A (en) | Construction method of bidirectional protective layer cushion block for column and beam steel bar | |
| CN212224301U (en) | Anti structure of splitting of infilled wall combination | |
| CN114261006A (en) | Structure for fixing and dismantling prefabricated box girder template and construction method | |
| CN219732750U (en) | Combined template for roof cast-in-situ deformation joint | |
| CN214061940U (en) | A precast concrete prefabricated structure with a ribbed formwork structure | |
| CN215760451U (en) | Wet district concrete turn-ups construction mould | |
| CN111042549A (en) | Method for building aluminum frame plastic formwork room | |
| CN216142493U (en) | Assembled building storehouse | |
| CN218027222U (en) | Box girder forming template | |
| CN217680502U (en) | Staggered platform side formwork supporting system with beams arranged between high-low floor slabs |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20220708 |
|
| WD01 | Invention patent application deemed withdrawn after publication |