CN114622917A - Construction Methods for Handling Tunnel Collapse - Google Patents

Construction Methods for Handling Tunnel Collapse Download PDF

Info

Publication number
CN114622917A
CN114622917A CN202210263406.3A CN202210263406A CN114622917A CN 114622917 A CN114622917 A CN 114622917A CN 202210263406 A CN202210263406 A CN 202210263406A CN 114622917 A CN114622917 A CN 114622917A
Authority
CN
China
Prior art keywords
grouting
tunnel
wall
construction
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210263406.3A
Other languages
Chinese (zh)
Inventor
陆峰
张书通
赵立孔
李守玺
王慧光
唐定
徐晓锋
肖川峰
万金辉
齐良玉
李永鑫
王晓飞
刘健
高国正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority to CN202210263406.3A priority Critical patent/CN114622917A/en
Publication of CN114622917A publication Critical patent/CN114622917A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/01Methods or apparatus for enlarging or restoring the cross-section of tunnels, e.g. by restoring the floor to its original level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction method for treating tunnel collapse, which comprises the steps of marking, covering and intercepting drainage in a tunnel surface subsidence area, cleaning an excavated section of the tunnel, constructing a back pressure soil body, wall corner concrete in front of a tunnel face and grout stopping wall concrete, constructing a temporary support above the back pressure soil body in time, embedding a two-liquid grouting guide pipe on the grout stopping wall, performing water stopping and reinforcement on soil body surrounding rocks behind the grout stopping wall, constructing a guide wall in front of the grout stopping wall, constructing large pipe shed grouting, further performing grouting reinforcement on the soil body surrounding rocks above the back of the grout stopping wall, arranging small advanced guide pipes between grouting large pipe sheds below the subsidence area and grouting, simultaneously reinforcing vault surrounding rocks by adopting two methods of large pipe shed grouting and small advanced guide pipe grouting, excavating, spraying, supporting and supporting the tunnel face, and backfilling the subsidence area. The invention has the advantages of convenient construction, high disposal speed and high construction efficiency, effectively shortens the construction period and improves the construction safety.

Description

处理隧道塌方的施工方法Construction Methods for Handling Tunnel Collapse

技术领域technical field

本发明涉及隧道开挖技术领域,尤其是涉及一种处理隧道塌方的施工方法。The invention relates to the technical field of tunnel excavation, in particular to a construction method for dealing with tunnel collapse.

背景技术Background technique

隧道进洞口段在夏季施工时,如遇连续强降雨天气会有很大风险导致塌方。由于隧道掌子面土石分界明显,降水对隧道洞顶覆盖土层不间断渗透和浸泡,掌子面土体逐渐趋向饱和软化,自重增加,土体的摩擦力和粘聚力降低,容易产生塑性变形;进一步地,在掌子面岩石分布区域的爆破震动作用下,拱顶土体顺着土岩分界线开始向下掉落,最终造成土体塌方,导致塌方部位的钢拱架部分被压弯和折断;更严重的是,如果隧道处于富水砂层段,进行洞内处理时,掌子面会持续存在涌水,并且还会随时发生二次溃砂塌方,无法保证人员设备安全,施工风险过高。为了降低风险而采用的两台阶法、三台阶法、CD法、CRD法支撑进行开挖施工,施工工期较长,且仍然不能避免溃砂塌方灾害在施工期内的持续发展。During the construction of the tunnel entrance section in summer, there is a great risk of landslides in case of continuous heavy rainfall. Due to the obvious boundary between soil and stone on the tunnel face, the precipitation continuously penetrates and soaks the covering soil layer on the top of the tunnel, the soil on the face gradually tends to be saturated and softened, the self-weight increases, the friction and cohesion of the soil decreases, and it is easy to produce plasticity. Deformation; further, under the action of blasting vibration in the rock distribution area of the face, the vault soil began to fall down along the soil-rock boundary, eventually causing the soil to collapse, resulting in the partial compression of the steel arch at the collapsed site. Bending and breaking; more seriously, if the tunnel is in the water-rich sand layer, when the tunnel is treated, water will continue to flow on the tunnel face, and secondary sand collapse will occur at any time, which cannot guarantee the safety of personnel and equipment, and construction risks. too high. The two-step method, three-step method, CD method, and CRD method adopted in order to reduce the risk are used to support the excavation construction.

发明内容SUMMARY OF THE INVENTION

为了解决上述问题,本发明提供一种处理隧道塌方的施工方法,具体可采取如下技术方案:In order to solve the above-mentioned problems, the present invention provides a construction method for dealing with tunnel collapse. Specifically, the following technical solutions can be adopted:

本发明所述的处理隧道塌方的施工方法,包括如下步骤:The construction method for processing tunnel collapse according to the present invention comprises the following steps:

第一步,在隧道地表塌陷区进行标识、遮盖和截流引排;The first step is to identify, cover and intercept and drain the tunnel in the subsidence area of the tunnel surface;

第二步,清理隧道已开挖段,边清淤泥边换填反压土体,反压回填一条机械设备施工通道,再施工掌子面前方墙角混凝土、止浆墙混凝土,并及时施工反压土体上方的临时支撑;The second step is to clean up the excavated section of the tunnel, replace the backpressure soil while clearing the silt, backfill a mechanical equipment construction channel with backpressure, and then construct the corner concrete in front of the front of the tunnel and the concrete for the grout wall, and construct the backpressure in time. Temporary support above the soil mass;

第三步,在止浆墙上埋设双液注浆导管,对止浆墙后方的土体围岩进行止水加固;The third step is to embed a double-liquid grouting conduit on the grouting wall, and perform water-stop reinforcement on the surrounding rock of the soil behind the grouting wall;

第四步,在止浆墙前方施工导向墙,并在导向墙顶部沿斜向上方向安装延伸至止浆墙背后的管棚孔口管,再施工大管棚注浆,进一步对止浆墙后上方的土体围岩进行注浆加固;The fourth step is to construct a guide wall in front of the grout stop wall, and install the pipe shed orifice pipe extending to the back of the grout stop wall at the top of the guide wall in an oblique upward direction, and then construct a large pipe shed grouting, and further grouting the back of the grout stop wall. The upper soil surrounding rock shall be grouted for reinforcement;

第五步,依次开挖已施工初支段前方的加固土体,直至塌陷区下方时,在注浆大管棚之间布设超前小导管并注浆,采用大管棚注浆和超前小导管注浆两种方法同时加固拱顶围岩,进行掌子面开挖喷射支护;The fifth step is to excavate the reinforced soil in front of the constructed initial support section in turn, and when it reaches the bottom of the collapse area, arrange and grouting between the grouting large pipe sheds, and use large pipe shed grouting and advanced small pipes The two methods of grouting reinforce the surrounding rock of the vault at the same time, and carry out the excavation and jetting support of the tunnel face;

第六步,按照步骤五重复施工,并进行二衬施工和地表塌陷区回填。The sixth step, repeat the construction according to the fifth step, and carry out the secondary lining construction and the backfilling of the surface subsidence area.

所述第二步中施工掌子面前方墙角混凝土时,首先在止浆墙前方的反压土体内埋设竖向注浆导管,然后进行注浆加固,用于防止注浆压力造成止浆墙后土体压力推移止浆墙。In the second step, when constructing the corner concrete in front of the face, firstly, a vertical grouting conduit is embedded in the back pressure soil body in front of the grouting wall, and then grouting reinforcement is performed to prevent the back of the grouting wall from being caused by the grouting pressure. Soil pressure pushes the grout wall.

所述第二步中的临时支撑与上台阶拱架焊接相连,且相邻临时支撑间距为1m。The temporary support in the second step is connected to the upper step arch by welding, and the distance between adjacent temporary supports is 1m.

所述第三步中通过双液注浆导管进行注浆时,浆液首先对止浆墙后方的淤泥土体孔隙进行填充,之后不断充挤土层直至达到对掌子面后方土体围岩进行加固的状态。In the third step, when grouting is carried out through the double-liquid grouting conduit, the grout first fills the pores of the silt body behind the grouting wall, and then continuously fills the soil layer until the surrounding rock of the soil body behind the tunnel face is filled. reinforced state.

所述第四步中每一根注浆大管棚均穿设在导向墙顶部的孔口管中。In the fourth step, each large grouting pipe shed is passed through the orifice pipe on the top of the guide wall.

所述第四步中注浆大管棚至少持续注浆10min,且进浆速度为开始进浆速度的1/4或进浆量达到设计进浆量时注浆结束。In the fourth step, the grouting large pipe shed is continuously grouted for at least 10 minutes, and the grouting speed is 1/4 of the initial grouting speed or the grouting ends when the grouting amount reaches the designed grouting amount.

所述第五步中初支混凝土喷射厚度为28cm。In the fifth step, the spray thickness of the initial concrete is 28cm.

所述第六步中地表塌陷区回填的具体施工步骤如下:The specific construction steps of backfilling in the surface subsidence area in the sixth step are as follows:

第一步,选取塌坑附近50m范围内较平整的地段,进行地面硬化,作为加工拌制回填料的场地;The first step is to select a relatively flat area within 50m of the collapse pit for ground hardening as a site for processing and mixing backfill;

第二步,拌制回填料机械进场后,采用P.O42.5普通硅酸盐袋装水泥与掺合发泡剂进行回填料拌制;The second step is to use P.O42.5 ordinary silicate bagged cement and blended foaming agent for backfill mixing after the mixing and backfilling machinery enters the site;

第三步,在塌坑30m外安装发泡机,将回填料灌注至原地表以下10m处结束第一次回填工作;The third step is to install a foaming machine 30m outside the collapse pit, and pour the backfill to 10m below the original surface to complete the first backfill;

第四步,采用素土进行二次回填,直至与原地表平齐;The fourth step is to use plain soil for secondary backfilling until it is flush with the original surface;

第五步,在素土以上施做30cm厚石灰土进行封顶隔水处理。The fifth step is to apply 30cm thick lime soil above the plain soil for capping and water-proofing.

所述第一次回填时,发泡机每次回填2米。During the first backfilling, the foaming machine backfills 2 meters each time.

本发明提供的处理隧道塌方的施工方法,通过多种方式的注浆对塌方地段的土体进行了加固,并对塌方部位进行回填修复,从根本上解决了隧道的二次塌方;其施工方便,处置速度快,施工效率高,有效地缩短了施工工期,提高了施工安全性。The construction method for dealing with tunnel collapse provided by the present invention reinforces the soil in the collapsed section by grouting in various ways, and performs backfilling and repair on the collapsed part, which fundamentally solves the secondary collapse of the tunnel; the construction is convenient. , The disposal speed is fast, the construction efficiency is high, the construction period is effectively shortened, and the construction safety is improved.

附图说明Description of drawings

图1是本发明的结构示意图。Figure 1 is a schematic structural diagram of the present invention.

图2是图1中导向墙部分的A-A剖面图。FIG. 2 is an A-A sectional view of the guide wall portion of FIG. 1. FIG.

图3是图1中的B-B剖面图。FIG. 3 is a B-B sectional view in FIG. 1 .

具体实施方式Detailed ways

下面结合附图对本发明的实施例作详细说明,本实施例在以本发明技术方案为前提下进行实施,给出了详细的实施方式和具体的施工过程,但本发明的保护范围不限于下述实施例。The embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. The present embodiment is implemented on the premise of the technical solution of the present invention, and provides detailed implementation methods and specific construction processes, but the protection scope of the present invention is not limited to the following described embodiment.

如图1-3所示,本发明所述的处理隧道塌方的施工方法,包括如下步骤:As shown in Figures 1-3, the construction method for dealing with tunnel collapse according to the present invention includes the following steps:

第一步,在隧道地表塌陷区进行标识、遮盖和截流引排;The first step is to identify, cover and intercept and drain the tunnel in the subsidence area of the tunnel surface;

具体地,在原地表陷坑M(位于掌子面右侧的地表处,见图1)周围及隧道内设立专项安全员,陷坑周边设置围挡栏杆、彩旗、醒目贴等安全标识;根据现场周边原地形地貌采用现浇60型混凝土截排水沟0.4×0.6m保障雨水排水顺畅,避免雨水下渗;在塌坑影响范围内,搭设钢管支架,其上采用防雨篷布覆盖防止雨水渗入;同时,隧道内安排变形观测人员,主要为地表沉降、位移监测,隧道拱顶沉降及拱部收敛四项,检测过程中单日累积沉降超过5mm停止洞内作业。Specifically, set up special safety officers around the original surface pit M (located on the surface on the right side of the tunnel face, see Figure 1) and in the tunnel, and set up safety signs such as fence railings, colorful flags, and eye-catching stickers around the pit; The topography adopts cast-in-place 60-type concrete intercepting and drainage ditch 0.4×0.6m to ensure smooth drainage of rainwater and avoid rainwater infiltration; within the impact range of the collapse pit, a steel pipe bracket is erected, which is covered with a rain-proof tarpaulin to prevent rainwater from infiltrating; at the same time, Deformation observers are arranged in the tunnel, mainly for surface settlement and displacement monitoring, tunnel vault settlement and arch convergence. During the detection process, the cumulative settlement in a single day exceeds 5mm to stop the operation in the tunnel.

第二步,清理隧道已开挖段,边清淤泥边换填反压土体1,反压回填一条机械设备施工通道,再施工掌子面2前方墙角混凝土3、止浆墙4混凝土,并及时施工反压土体上方的临时支撑5,用于控制竖向沉降;The second step is to clean up the excavated section of the tunnel, replace the back pressure soil body 1 while clearing the silt, backfill a mechanical equipment construction channel with back pressure, and then construct the front corner concrete 3 of the tunnel face 2, and the mortar stop wall 4 concrete, and Temporary support 5 above the back pressure soil is constructed in time to control vertical settlement;

具体地,在进行隧道已开挖段清理时,事先预留约1500方砂质泥岩洞渣进行掌子面堆积反压,以确保掌子面安全稳定,避免发生更大范围的突泥、涌泥事件。上述反压土体1一直延伸至止浆墙4处,其断面不小于隧道开挖面积的2/3,长度不得小于20m。Specifically, when cleaning the excavated section of the tunnel, about 1500 cubic meters of sandy mudstone cave slag was reserved in advance for the back pressure of the tunnel face to ensure the safety and stability of the tunnel face and to avoid the occurrence of larger-scale mud and gushing. Mud incident. The above-mentioned back pressure soil body 1 extends all the way to the stop wall 4, its cross-section shall not be less than 2/3 of the tunnel excavation area, and its length shall not be less than 20m.

为了确保掌子面稳定,给后续施工提供安全且充足的施工空间,采用抗渗等级为P8的C30砼浇筑止浆墙4对隧道塌方体和掌子面2进行封闭。进一步地,为了确保止浆墙4墙体稳定,以及给施工机具提供一个安装平台,在止浆墙4前方及下部土体内注水泥-水玻璃双液浆进行墙角混凝土3施工。上述墙角混凝土3施工时,在止浆墙4的墙脚预埋22根竖向注浆导管(φ60mm,长度6m),注浆材料采用水泥-水玻璃双液浆,水泥浆水灰比W:C=1:1,水泥浆液与水玻璃浆液体积比为1:1,水泥采用42.5级硅酸盐水泥。注浆压力为0.5-1.5Mpa,浆液初凝时间要求在3-5分钟。注浆时,应根据现场实际情况适当调整配合比。In order to ensure the stability of the tunnel face and provide a safe and sufficient construction space for subsequent construction, C30 concrete with an impermeability grade of P8 was used to cast the grout stop wall 4 to seal the tunnel collapse body and the tunnel face 2. Further, in order to ensure the stability of the grout stop wall 4 and to provide an installation platform for the construction equipment, cement-water glass double slurry is poured into the soil in front of the grout stop wall 4 and in the lower part to carry out the construction of the corner concrete 3 . During the construction of the above-mentioned corner concrete 3, 22 vertical grouting pipes (φ60mm, length 6m) are pre-buried at the foot of the grouting wall 4. The grouting material adopts cement-water glass double-liquid slurry, and the water-cement ratio of cement slurry is W:C =1:1, the volume ratio of cement slurry and water glass slurry is 1:1, and the cement adopts 42.5 grade Portland cement. The grouting pressure is 0.5-1.5Mpa, and the initial setting time of the slurry is required to be 3-5 minutes. When grouting, the mix ratio should be appropriately adjusted according to the actual situation on site.

在隧道已开挖段的反压土体1上方邻近止浆墙4的10m范围内施工多个临时支撑5,每一临时支撑5均其与上台阶拱架焊接连接,且相邻临时支撑5的间距为1m。必要时,增加竖撑控制竖向沉降,同时每榀两侧打设Φ42锁脚锚管各2根,长度6m并注浆加固。A plurality of temporary supports 5 are constructed within 10m of the back pressure soil body 1 in the excavated section of the tunnel adjacent to the grout wall 4. Each temporary support 5 is welded to the upper step arch, and the adjacent temporary supports 5 The spacing is 1m. If necessary, increase the vertical support to control the vertical settlement, and at the same time, set 2 Φ42 locking foot anchor pipes on both sides of each truss, with a length of 6m and grouting reinforcement.

第三步,在止浆墙4上埋设双液注浆导管6,对止浆墙4后方的土体围岩进行止水加固;The third step is to embed a double-liquid grouting conduit 6 on the grouting wall 4, and perform water-stop reinforcement on the soil surrounding rock behind the grouting wall 4;

具体地,双液注浆导管6采用φ42mm、长度6m的注浆管,沿水平方向在止浆墙4上均匀埋设18根,出浆口位于止浆墙4后方的隧道塌方土体和隧道围岩内。注浆初期,浆液主要用于填充土层孔隙,当土层孔隙被注入的浆液填充密实后,注浆压力不断上升,后期注入的浆液不断充挤土层直至达到超固结状态。Specifically, the double-liquid grouting conduit 6 is a grouting pipe with a diameter of 42 mm and a length of 6 m, and 18 are evenly buried on the grouting wall 4 along the horizontal direction. Inside the rock. In the initial stage of grouting, the grout is mainly used to fill the pores of the soil layer. When the pores of the soil layer are filled and compacted by the injected grout, the grouting pressure continues to rise, and the injected grout in the later stage continues to fill the soil layer until it reaches an over-consolidated state.

第四步,在止浆墙4前侧施工导向墙7,并在导向墙7顶部沿斜向上方向安装延伸至止浆墙4背后的管棚孔口管,再施工大管棚8注浆,进一步对止浆墙4后上方的土体围岩进行注浆加固;In the fourth step, the guide wall 7 is constructed on the front side of the slurry stop wall 4, and the pipe shed orifice pipe extending to the back of the slurry stop wall 4 is installed on the top of the guide wall 7 along the oblique upward direction, and then the large pipe shed 8 is constructed for grouting, Further grouting reinforcement is performed on the soil surrounding rock above and behind the grout stop wall 4;

由于已施工初支断面不能满足导向墙的断面尺寸,故需要破除原有初支面、拆除原有钢拱架和箍筋网片,之后再施工导向墙7。具体地,先安装用于穿设注浆大管棚8的孔口管,然后按照纵向间距50cm安装两榀临时I20a型钢拱架,环向连接Q235钢板260×240mm,t=12mm,M20高强螺栓加固,拱架间使用HRB400Φ22连接钢筋纵向连接,环向间距1m内侧单层布置,完成导向墙7施工。上述导向墙7与止浆墙4的间距为注浆大管棚8管长的1/5。Since the constructed initial support section cannot meet the section size of the guide wall, it is necessary to break the original initial support surface, remove the original steel arch and stirrup mesh, and then construct the guide wall 7. Specifically, first install the orifice pipe used to pass through the grouting large pipe shed 8, then install two temporary I20a steel arches according to the longitudinal spacing of 50cm, and circumferentially connect Q235 steel plates 260×240mm, t=12mm, and M20 high-strength bolts For reinforcement, HRB400Φ22 connecting steel bars are used to connect the arches longitudinally, and the inner side is arranged in a single layer with a circumferential spacing of 1m, and the construction of the guide wall 7 is completed. The distance between the guide wall 7 and the grouting wall 4 is 1/5 of the pipe length of the grouting large pipe shed 8 .

注浆大管棚8采用37根长度为20m的Φ89注浆管,分别穿入孔口管后,沿斜向上方向打入掌子面2。上述每一根注浆大管棚8均穿设在导向墙7顶部的孔口管中,大管棚8环向间距35cm,每根大管棚8内设置3根Φ22钢筋进行加固。之后,按照由下至上顺序先冲洗管内沉积物,再进行注浆。单孔注浆压力按照设计要求值进行,持续注浆10min,当进浆速度为开始进浆速度的1/4或进浆量达到设计进浆量时注浆方可结束。通常情况下,注浆大管棚8的注浆料采用水灰比为1:1(重量比)水泥浆液,注浆初压0.5~1.0MPa,注浆终压达到2.0MPa。The large grouting pipe shed 8 adopts 37 Φ89 grouting pipes with a length of 20m. After respectively passing through the orifice pipes, they are driven into the face 2 obliquely upward. Each of the above-mentioned grouting large pipe sheds 8 is passed through the orifice pipe on the top of the guide wall 7, the large pipe sheds 8 are circumferentially spaced 35cm, and three Φ22 steel bars are arranged in each large pipe shed 8 for reinforcement. After that, the sediment in the pipe is washed first, and then grouting is carried out according to the order from bottom to top. The single-hole grouting pressure is carried out according to the design requirements, and the grouting is continued for 10 minutes. When the grouting speed is 1/4 of the initial grouting speed or the grouting amount reaches the designed grouting amount, the grouting can end. Under normal circumstances, the grouting of the grouting large pipe shed 8 adopts a cement slurry with a water-cement ratio of 1:1 (weight ratio), the initial grouting pressure is 0.5-1.0 MPa, and the final grouting pressure reaches 2.0 MPa.

第五步,依次开挖已施工初支段前方的加固土体,直至塌陷区下方时,在注浆大管棚8之间布设超前小导管9并注浆,采用大管棚8注浆和超前小导管9注浆两种方法同时加固拱顶围岩,进行掌子面2开挖喷射支护;The fifth step is to excavate the reinforced soil in front of the constructed initial support section in turn, until below the subsidence area, arrange the advanced small conduits 9 between the grouting large pipe sheds 8 and grouting, and use the large pipe shed 8 for grouting and grouting. Two methods of grouting ahead of the small conduit 9 simultaneously reinforce the surrounding rock of the vault, and carry out excavation and jetting support for the tunnel face 2;

上述超前小导管9采用Φ42*4mm的导管,其纵向间距2m(纵向搭接1.5米),环向间距35cm,打入角度30-45°,3.5m/根,且塌方段初支混凝土喷射厚度为28cm。The above-mentioned small leading conduits 9 are conduits of Φ42*4mm, the longitudinal distance is 2m (longitudinal overlap is 1.5 meters), the circumferential distance is 35cm, the driving angle is 30-45°, 3.5m/piece, and the initial concrete spray thickness of the collapse section is is 28cm.

第六步,按照步骤五重复施工,并进行二衬施工和地表塌陷区回填。The sixth step, repeat the construction according to the fifth step, and carry out the secondary lining construction and the backfilling of the surface subsidence area.

在进行第五步时,如果确认掌子面2可以正常开挖作业,那么,重复第五步按照正常施工工序进行隧道开挖,施工时加强监控量测,同时开挖中下台阶及仰拱,继续跟进施作二衬,二衬施工采用复合式衬砌的形式,应用整体式液压模板台车施工。初期支护完成后,为了有效地控制隧身形变,仰拱尽量紧跟开挖面施工,仰拱填充采用栈桥平台以解决洞内运输问题,并进行全幅一次性施工。In the fifth step, if it is confirmed that the tunnel face 2 can be excavated normally, then repeat the fifth step to carry out tunnel excavation according to the normal construction process, strengthen monitoring and measurement during construction, and excavate the middle and lower steps and the inverted arch at the same time. , Continue to follow up the construction of the second lining, the second lining construction adopts the form of composite lining, and the integral hydraulic formwork trolley is used for construction. After the initial support is completed, in order to effectively control the deformation of the tunnel body, the inverted arch is constructed as closely as possible to the excavation surface, and the invert arch is filled with a trestle platform to solve the transportation problem in the tunnel, and a full-width one-time construction is carried out.

在隧道开挖时,还应进行地表塌陷区回填,其具体施工步骤如下:During tunnel excavation, backfilling of the surface subsidence area should also be carried out. The specific construction steps are as follows:

S1,选取塌坑附近50m范围内较平整的地段,进行地面硬化,作为加工拌制回填料的场地;S1, select a relatively flat area within 50m of the collapse pit, and perform ground hardening as a site for processing and mixing backfill;

S2,拌制回填料机械进场后,采用P.O42.5普通硅酸盐袋装水泥与掺合发泡剂进行回填料拌制,上述回填料具有自流平、自密实的特性;S2, after the mixing and backfilling machinery enters the site, use P.O42.5 ordinary silicate bagged cement and admixed foaming agent to mix backfilling, the above-mentioned backfilling has the characteristics of self-leveling and self-compacting;

S3,在塌坑30m外安装发泡机,按照每次灌注高度为2m的工作标准,将回填料灌注至原地表以下10m处结束第一次回填工作;S3, install a foaming machine 30m away from the collapsed pit, and according to the working standard of 2m per injection height, inject the backfill to 10m below the original surface to complete the first backfill work;

S4,采用素土进行二次回填,直至与原地表平齐;S4, use plain soil for secondary backfill until it is flush with the original surface;

S5,在素土以上施做30cm厚石灰土进行封顶隔水处理。S5, apply 30cm thick lime soil above the plain soil for capping and water-proof treatment.

需要说明的是,在本发明的描述中,诸如“前”、“后”、“左”、“右”、“垂直”、“水平”、“内”、“外”等指示的方位或位置关系的术语是基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。It should be noted that, in the description of the present invention, the orientations or positions indicated such as "front", "rear", "left", "right", "vertical", "horizontal", "inner", "outer", etc. The terminology of the relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation , so it should not be construed as a limitation of the present invention.

Claims (9)

1. A construction method for treating tunnel collapse is characterized by comprising the following steps:
firstly, marking, covering and intercepting drainage in a tunnel surface subsidence area;
secondly, cleaning the excavated section of the tunnel, filling the back pressure soil body while cleaning sludge, back pressure filling a mechanical equipment construction channel, constructing corner concrete and grout stop wall concrete in front of the tunnel face, and constructing temporary supports above the back pressure soil body in time;
thirdly, embedding a double-liquid grouting guide pipe in the grout stopping wall, and performing water stopping reinforcement on the soil body surrounding rock behind the grout stopping wall;
fourthly, constructing a guide wall in front of the grout stop wall, installing a pipe shed orifice pipe extending to the back of the grout stop wall on the top of the guide wall along the obliquely upward direction, constructing large pipe sheds for grouting, and further grouting and reinforcing the soil body surrounding rock above the back of the grout stop wall;
fifthly, excavating a reinforced soil body in front of the constructed primary support section in sequence until the reinforced soil body is below a subsidence area, laying a small advanced guide pipe between the grouting large pipe sheds and grouting, reinforcing vault surrounding rock simultaneously by adopting two methods of large pipe shed grouting and small advanced guide pipe grouting, and excavating and spraying support on a tunnel face;
and sixthly, repeating the construction according to the fifth step, and carrying out secondary lining construction and backfilling of the surface subsidence area.
2. The construction method for treating tunnel collapse according to claim 1, characterized in that: when the concrete of the corner in front of the tunnel face is constructed in the second step, the vertical grouting guide pipe is buried in the back-pressure soil body in front of the grout stopping wall, and then grouting reinforcement is carried out to prevent the grouting pressure from causing the pressure of the soil body behind the grout stopping wall to push the grout stopping wall.
3. The construction method for treating tunnel collapse according to claim 1, characterized in that: and the temporary supports in the second step are welded with the arch center of the upper step, and the distance between every two adjacent temporary supports is 1 m.
4. The construction method for treating tunnel collapse according to claim 1, characterized in that: and in the third step, when grouting is carried out through the double-liquid grouting guide pipe, the slurry firstly fills the soil pore space behind the grout stopping wall, and then continuously fills and extrudes the soil layer until the soil surrounding rock behind the tunnel face is reinforced.
5. The construction method for treating tunnel collapse according to claim 1, characterized in that: and in the fourth step, each grouting large pipe shed is arranged in an orifice pipe at the top of the guide wall in a penetrating mode.
6. The construction method for treating tunnel collapse according to claim 1, characterized in that: and in the fourth step, grouting the large pipe shed for at least 10min, wherein the grouting speed is 1/4 of the starting grouting speed, or the grouting is finished when the grouting amount reaches the designed grouting amount.
7. The construction method for treating tunnel collapse according to claim 1, characterized in that: and in the fifth step, the spraying thickness of the primary concrete is 28 cm.
8. The construction method for treating tunnel collapse according to claim 1, wherein the concrete construction steps of backfilling the surface collapse area in the sixth step are as follows:
firstly, selecting a relatively flat section within a range of 50m near a collapsed pit, and hardening the ground to be used as a field for processing and mixing backfill;
secondly, after the stirred backfill is mechanically fed, stirring backfill by adopting P.O42.5 common silicate bagged cement and a blended foaming agent;
thirdly, installing a foaming machine outside the collapsed pit by 30m, and filling backfill materials to a position 10m below the original surface to finish the first backfilling work;
fourthly, backfilling for the second time by adopting plain soil until the plain soil is level to the original surface;
fifthly, applying lime soil with the thickness of 30cm above the plain soil for capping and water-resisting treatment.
9. The construction method for treating tunnel collapse according to claim 8, wherein: and during the first backfilling, the foaming machine backfills for 2 meters every time.
CN202210263406.3A 2022-03-17 2022-03-17 Construction Methods for Handling Tunnel Collapse Pending CN114622917A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210263406.3A CN114622917A (en) 2022-03-17 2022-03-17 Construction Methods for Handling Tunnel Collapse

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210263406.3A CN114622917A (en) 2022-03-17 2022-03-17 Construction Methods for Handling Tunnel Collapse

Publications (1)

Publication Number Publication Date
CN114622917A true CN114622917A (en) 2022-06-14

Family

ID=81901387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210263406.3A Pending CN114622917A (en) 2022-03-17 2022-03-17 Construction Methods for Handling Tunnel Collapse

Country Status (1)

Country Link
CN (1) CN114622917A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115450654A (en) * 2022-09-27 2022-12-09 中国建筑土木建设有限公司 Collapse treatment method of volcanic ash geological tunnel
CN115961985A (en) * 2023-02-22 2023-04-14 成都和拓土木工程有限公司 Reverse concrete backfilling method for tunnel collapse section
CN116006186A (en) * 2022-12-13 2023-04-25 福建省地质工程勘察院 The construction structure and construction method of microbial grouting to deal with soil tunnel collapse
CN116084962A (en) * 2023-03-13 2023-05-09 中电建十一局工程有限公司 Safe construction method for treating sudden and large collapse body by long pipe shed in tunnel
CN116181369A (en) * 2023-02-22 2023-05-30 成都和拓土木工程有限公司 Fast and safe implementation of grouting reinforcement for hard rock crushing and water-rich tunnel section
CN120426059A (en) * 2025-07-08 2025-08-05 中铁十九局集团有限公司 Advanced pipe roof high-pressure controlled grouting device and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110748350A (en) * 2019-10-28 2020-02-04 中国石油大学(华东) Method for quickly treating collapse of urban subway tunnel passing through water-rich sand layer section
CN111305027A (en) * 2020-03-04 2020-06-19 桂林电子科技大学 Rapid repair construction method and repair structure for pavement collapse in karst area
CN112228082A (en) * 2020-10-29 2021-01-15 中铁一局集团有限公司 A tunnel collapse treatment method for combined grouting of pipe shed and advanced small conduit
CN112983467A (en) * 2021-04-08 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Treatment method for tunnel gate closing type large collapse
CN113685191A (en) * 2021-09-09 2021-11-23 中国水利水电第四工程局有限公司 Method for treating collapse of carbonaceous slates in water during tunnel excavation
CN114109442A (en) * 2021-10-18 2022-03-01 中铁十局集团第一工程有限公司 Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110748350A (en) * 2019-10-28 2020-02-04 中国石油大学(华东) Method for quickly treating collapse of urban subway tunnel passing through water-rich sand layer section
CN111305027A (en) * 2020-03-04 2020-06-19 桂林电子科技大学 Rapid repair construction method and repair structure for pavement collapse in karst area
CN112228082A (en) * 2020-10-29 2021-01-15 中铁一局集团有限公司 A tunnel collapse treatment method for combined grouting of pipe shed and advanced small conduit
CN112983467A (en) * 2021-04-08 2021-06-18 中国电建集团成都勘测设计研究院有限公司 Treatment method for tunnel gate closing type large collapse
CN113685191A (en) * 2021-09-09 2021-11-23 中国水利水电第四工程局有限公司 Method for treating collapse of carbonaceous slates in water during tunnel excavation
CN114109442A (en) * 2021-10-18 2022-03-01 中铁十局集团第一工程有限公司 Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115450654A (en) * 2022-09-27 2022-12-09 中国建筑土木建设有限公司 Collapse treatment method of volcanic ash geological tunnel
CN116006186A (en) * 2022-12-13 2023-04-25 福建省地质工程勘察院 The construction structure and construction method of microbial grouting to deal with soil tunnel collapse
CN115961985A (en) * 2023-02-22 2023-04-14 成都和拓土木工程有限公司 Reverse concrete backfilling method for tunnel collapse section
CN116181369A (en) * 2023-02-22 2023-05-30 成都和拓土木工程有限公司 Fast and safe implementation of grouting reinforcement for hard rock crushing and water-rich tunnel section
CN116084962A (en) * 2023-03-13 2023-05-09 中电建十一局工程有限公司 Safe construction method for treating sudden and large collapse body by long pipe shed in tunnel
CN120426059A (en) * 2025-07-08 2025-08-05 中铁十九局集团有限公司 Advanced pipe roof high-pressure controlled grouting device and method
CN120426059B (en) * 2025-07-08 2025-10-21 中铁十九局集团有限公司 Advanced pipe shed high-pressure control grouting device and method

Similar Documents

Publication Publication Date Title
CN114622917A (en) Construction Methods for Handling Tunnel Collapse
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN101936167A (en) Construction method of bridge underpinning combined with shield construction across bridge pile foundation
CN103321246B (en) Construction Method of Foundation Pit Using Underground Diaphragm Wall
CN108952732A (en) A kind of excavation construction method suitable for rich water fault belt large cross-section tunnel
JP7540678B1 (en) System and method for backfilling narrow excess trenches in a mine with liquefied hardened soil
CN1067453C (en) Foundation pit slope flat anchor spray net supporting method
CN105464668A (en) Technology for controlling floor heave of soft rock roadway
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN112031814B (en) Cave-entering construction method for crossing shallow-layer high-load highway
CN115710912A (en) Narrow roadway foundation pit supporting process
CN114411756A (en) Construction method and construction device for open-cut foundation pit of water-rich sand layer subway station without precipitation
CN110117959A (en) One kind closing on rivers base pit stand construction
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN117927275A (en) Waterproof construction method for underground excavation channel of subway
CN113846695B (en) Reverse construction method basement construction method
CN115341910A (en) A tunnel construction method with complex geological conditions under expressway and tunnel
CN115596468A (en) A construction method for communication passages used in soft soil tunnels
CN113266362B (en) A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination