CN114607409A - Construction method for connecting channel by freezing method - Google Patents
Construction method for connecting channel by freezing method Download PDFInfo
- Publication number
- CN114607409A CN114607409A CN202210284785.4A CN202210284785A CN114607409A CN 114607409 A CN114607409 A CN 114607409A CN 202210284785 A CN202210284785 A CN 202210284785A CN 114607409 A CN114607409 A CN 114607409A
- Authority
- CN
- China
- Prior art keywords
- freezing
- pipe
- tube
- embedded
- orifice
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/001—Improving soil or rock, e.g. by freezing; Injections
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Soil Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种隧道施工方法,尤其涉及一种用于冻结法连接通道的施工方法。The invention relates to a tunnel construction method, in particular to a construction method for connecting channels by a freezing method.
背景技术Background technique
目前,地下隧道之间的连接通道大都采用“水平冻结法土体加固,矿山暗挖法构筑”工艺进行施工,一般情况下,连接通道在主隧道贯通后再组织施工。At present, most of the connecting passages between underground tunnels are constructed by the process of "horizontal freezing method for soil reinforcement and mine excavation method". Generally, the connecting passages are constructed after the main tunnel is penetrated.
现有技术的冻结法连接通道中,冻结管钻孔施工主要流程为:按照冻结管设计位置及角度在管片上水钻开孔,安装孔口管、闸阀、孔口装置、密封件、盘根及压紧装置,冻结管钻孔施工,利用孔口管的旁通阀补偿注浆,闸阀、孔口装置、密封垫、盘根及压紧装置等密封装置拆除,孔口管与冻结管之间的环形空间焊接封闭,冻结管复测,冻结管打压试漏。钻孔施工需要在隧道管片上开孔安装孔口管,孔口管还需要打膨胀螺丝或钢筋与管片进行固定,工序较复杂,占用关键工期,同时孔口密封装置的止水效果较差。In the freezing method connection channel of the prior art, the main flow of the freezing pipe drilling construction is as follows: according to the design position and angle of the freezing pipe, water drilling holes are made on the segment, and the orifice pipe, gate valve, orifice device, seal, packing and Compression device, frozen pipe drilling construction, use the bypass valve of the orifice pipe to compensate for grouting, remove the sealing devices such as gate valve, orifice device, gasket, packing and pressing device, between the orifice pipe and the frozen pipe The annular space is welded and closed, the frozen tube is re-tested, and the frozen tube is pressed for leak testing. Drilling construction requires opening holes on the tunnel segment to install the orifice pipe, and the orifice pipe also needs to be fixed with expansion screws or steel bars and the segment. The process is complicated and takes up a critical construction period. At the same time, the orifice sealing device has poor water-stopping effect. .
现有技术的冻结法连接通道中,冻结孔封孔主要流程一般为:首先将孔口管和冻结管割除至管片内一定深度,然后利用砂浆或混凝土进行冻结管填充,利用钢板焊接封堵孔口管,在割除区域的管片侧墙上施工2根膨胀螺栓,最后砂浆抹平。冻结孔封孔工序较复杂,可靠性低,封堵速度慢,冻结加固体融沉后封孔处易产生渗漏,后续堵漏较困难。In the freezing method connection channel of the prior art, the main process of sealing the freezing hole is generally as follows: first, the orifice pipe and the freezing pipe are cut to a certain depth in the segment, then the freezing pipe is filled with mortar or concrete, and the steel plate is welded and sealed. For the orifice pipe, construct 2 expansion bolts on the side wall of the segment in the cut area, and then smooth it with mortar. The freezing hole sealing process is complicated, the reliability is low, and the sealing speed is slow. After the frozen solid is melted and settled, leakage is likely to occur at the sealing hole, and the subsequent plugging is difficult.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于提供一种用于冻结法连接通道的施工方法,能提高地下隧道冻结法连接通道的施工效率和施工质量,提高隧道的外观质量。The purpose of the present invention is to provide a construction method for the freezing method connection channel, which can improve the construction efficiency and construction quality of the underground tunnel freezing method connection channel, and improve the appearance quality of the tunnel.
本发明是这样实现的:The present invention is realized in this way:
一种用于冻结法连接通道的施工方法,包括以下步骤:A construction method for connecting a channel by a freezing method, comprising the following steps:
步骤1:安装主隧道管片;Step 1: Install the main tunnel segment;
所述的步骤1包括以下分步骤:Described
步骤1.1:在主隧道管片中预留冻结孔,并在冻结孔中预埋预埋管;Step 1.1: Reserve a freezing hole in the main tunnel segment, and pre-embed the pre-embedded pipe in the freezing hole;
步骤1.2:通过闷头旋接并临时封闭预埋管;Step 1.2: Screw and temporarily seal the embedded pipe through the bulkhead;
步骤2:冷冻管钻孔施工;Step 2: Drilling the frozen pipe;
所述的步骤2包括以下分步骤:Described
步骤2.1:卸下闷头,并在预埋管上旋接孔口管,孔口管的内端位于主隧道管片内,孔口管的外端延伸至隧道内部;Step 2.1: Remove the bulkhead, and screw the orifice pipe on the embedded pipe, the inner end of the orifice pipe is located in the main tunnel segment, and the outer end of the orifice pipe extends to the inside of the tunnel;
步骤2.2:在孔口管的外端上同轴连接冻结管密封装置;Step 2.2: Coaxially connect the freezing tube sealing device on the outer end of the orifice tube;
步骤2.3:将冻结管同轴插入冻结管密封装置和孔口管,使冻结管密封装置密封包裹在冻结管上;Step 2.3: Insert the freezing tube coaxially into the freezing tube sealing device and the orifice tube, so that the freezing tube sealing device is tightly wrapped on the freezing tube;
步骤2.4:在冻结管密封装置上连接油脂旁通球阀,使油脂旁通球阀通过注入油脂并密封冻结管;Step 2.4: Connect the grease bypass ball valve to the freezing pipe sealing device, so that the grease bypass ball valve can be injected with grease and seal the freezing pipe;
步骤2.5:冻结管进行钻进施工,并在钻进施工过程中保持油脂的注入;Step 2.5: Freeze the pipe for drilling construction, and keep grease injection during drilling construction;
步骤3:冻结管钻进施工完成后,停止冻结法施工,进行冻结孔封孔;Step 3: After the frozen pipe drilling is completed, the freezing method construction is stopped, and the frozen hole is sealed;
所述的步骤3包括以下分步骤:Described
步骤3.1:排放冻结管内的盐水,拆除封堵板和孔口管;Step 3.1: Drain the brine in the freezing tube, remove the blocking plate and the orifice tube;
步骤3.2:割除部分冻结管,使切割后的冻结管的一端位于预埋管内;Step 3.2: Cut off part of the frozen tube, so that one end of the cut frozen tube is located in the embedded tube;
步骤3.3:通过闷头旋接并封闭预埋管;Step 3.3: Screw and seal the embedded pipe through the bulkhead;
步骤3.4:在闷头与封闭预埋管之间以及冻结管内注入封孔砂浆;Step 3.4: inject sealing mortar between the bulkhead and the closed embedded pipe and into the freezing pipe;
步骤3.5:利用封孔砂浆抹平主隧道管片的内壁。Step 3.5: Use sealing mortar to smooth the inner wall of the main tunnel segment.
在预埋所述的预埋管时,预埋管的轴向与冻结管的设计插入轴向一致,并将预埋管与主隧道管片内部的钢筋结构连接。When pre-embedding the pre-embedded pipe, the axial direction of the pre-embedded pipe is consistent with the design insertion axis of the frozen pipe, and the pre-embedded pipe is connected with the steel structure inside the main tunnel segment.
在预埋所述的预埋管时,同步预埋手孔盒子,手孔盒子与预埋管的端部同轴固定连接。When the pre-embedded pipe is pre-embedded, the hand-hole box is pre-embedded simultaneously, and the hand-hole box is coaxially and fixedly connected with the end of the pre-embedded pipe.
在通过所述的闷头临时封闭预埋管时,在闷头与预埋管之间设置填料。When the pre-buried pipe is temporarily closed by the bulkhead, a filler is arranged between the bulkhead and the pre-buried pipe.
若所述的闷头与预埋管之间填充有填料,在卸下闷头时同步清理填料。If the filler is filled between the bulkhead and the pre-embedded pipe, the filler should be cleaned simultaneously when the bulkhead is removed.
所述的步骤2.5包括以下分步骤:The described step 2.5 includes the following sub-steps:
步骤2.5.1:在孔口管上安装注浆旁通球阀,并通过注浆旁通球阀向孔口管内补偿注浆加固;Step 2.5.1: Install the grouting bypass ball valve on the orifice pipe, and compensating grouting into the orifice pipe through the grouting bypass ball valve;
步骤5.2.5:拆除冻结管密封装置,并通过封堵板封闭孔口管的外端与冻结管连接部位处的间隙。Step 5.2.5: Remove the freezing tube sealing device, and seal the gap at the connection between the outer end of the orifice tube and the freezing tube through the blocking plate.
所述的注浆旁通球阀向孔口管与冻结管之间的间隙内注入双液水泥浆。The grouting bypass ball valve injects two-liquid cement slurry into the gap between the orifice pipe and the freezing pipe.
所述的封堵板位圆环形结构,封堵板的外圈边缘与孔口管的外端焊接固定,封堵板的内圈与冻结管的外壁焊接固定。The said blocking plate has a circular structure, the outer ring edge of the blocking plate is welded and fixed with the outer end of the orifice pipe, and the inner ring of the blocking plate is welded and fixed with the outer wall of the freezing pipe.
在通过所述的闷头封闭预埋管时,若冻结孔内预埋有手孔盒子,将闷头与手孔盒子焊接加固。When the pre-embedded pipe is closed by the bulkhead, if a hand-hole box is pre-embedded in the freezing hole, the bulkhead and the hand-hole box are welded and strengthened.
本发明与现有技术相比,具有如下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
1、本发明由于设有预埋管,预埋管根据冻结孔位置直接预埋在主隧道管片内,安装可靠性高,不破坏主隧道管片的主筋等结构,且能旋接闷头,在未进行冻结法连接通道施工时临时封堵预埋管,确保主隧道的施工,并能旋接孔口管,用于安装冻结管并进行注浆加固,拆装方便,大大提高了冻结法连接通道施工的效率。1. Because the present invention is provided with a pre-embedded pipe, the pre-embedded pipe is directly embedded in the main tunnel segment according to the position of the freezing hole, the installation reliability is high, the structures such as the main bars of the main tunnel segment are not damaged, and the bulky head can be screwed together, The pre-buried pipe is temporarily blocked when the freezing method is not used to connect the channel construction to ensure the construction of the main tunnel, and the orifice pipe can be screwed to install the frozen pipe and perform grouting reinforcement. It is easy to disassemble and assemble, which greatly improves the freezing method. Linkage construction efficiency.
2、本发明由于设有冻结管密封装置,能提高冻结法连接通道施工时冻结管与孔口管之间的密封性,避免外界水土渗入隧道内部,也避免了外界水土流失。2. The present invention is provided with a freezing pipe sealing device, which can improve the sealing performance between the freezing pipe and the orifice pipe during the construction of the freezing method connecting channel, prevent the outside water and soil from infiltrating into the tunnel, and also avoid the outside water and soil loss.
3、本发明由于采用了封堵板焊接封堵孔口管的外端与冻结管的连接处,并在拆除空口管和割除冻结管后采用闷头封堵冻结孔,施工流程简单易操作,能大大提高施工效率,且使冻结加固体融沉后封孔处不易产生渗漏,同时结合封孔砂浆磨平,保证了主隧道管片的外观质量。3. In the present invention, the connection between the outer end of the orifice tube and the freezing tube is welded and sealed by the plugging plate, and the freezing hole is blocked with a bulky head after removing the empty orifice tube and cutting the freezing tube. The construction process is simple and easy to operate, and it can be The construction efficiency is greatly improved, and the sealed hole is not easy to leak after the frozen solid is melted.
附图说明Description of drawings
图1是本发明用于冻结法连接通道的施工方法中步骤1的施工示意图;Fig. 1 is the construction schematic diagram of
图2是图1中B处的放大示意图;Fig. 2 is the enlarged schematic diagram at B in Fig. 1;
图3是本发明用于冻结法连接通道的施工方法中步骤2的施工示意图;Fig. 3 is the construction schematic diagram of
图4是图3中A处的放大示意图;Fig. 4 is the enlarged schematic diagram at A place in Fig. 3;
图5是图3中C处的放大示意图;Fig. 5 is the enlarged schematic diagram at C place in Fig. 3;
图6是本发明用于冻结法连接通道的施工方法中步骤2.5.1的施工示意图;Fig. 6 is the construction schematic diagram of step 2.5.1 of the present invention for the construction method of freezing method connection channel;
图7是本发明用于冻结法连接通道的施工方法中步骤2.5.2的施工示意图;Fig. 7 is the construction schematic diagram of step 2.5.2 of the present invention for the construction method of freezing method connection channel;
图8是本发明用于冻结法连接通道的施工方法中步骤3的施工示意图。FIG. 8 is a schematic view of the construction of
图中:1主隧道管片,11冻结孔,12预埋管,121预埋凸缘,122密封圈,123止水圈,13闷头,131第一限位凸缘,132旋接部,14填料,15手孔盒子,2冻结管,3孔口管,31注浆旁通球阀,32第二限位凸缘,4冻结管密封装置,41油脂旁通球阀,411油脂,42第二密封垫,43第一密封垫,44端部压板,45孔口装置,46固定件,47第三密封垫,5封堵板,6封孔砂浆。In the figure: 1 main tunnel segment, 11 freezing hole, 12 embedded pipe, 121 embedded flange, 122 sealing ring, 123 water stop ring, 13 bulkhead, 131 first limit flange, 132 screw connection, 14 Packing, 15 Hand Hole Box, 2 Freeze Tube, 3 Orifice Tube, 31 Grouting Bypass Ball Valve, 32 Second Limit Flange, 4 Freeze Tube Seals, 41 Grease Bypass Ball Valve, 411 Grease, 42 Second Seal Pad, 43 First gasket, 44 End pressure plate, 45 Orifice device, 46 Fixing piece, 47 Third gasket, 5 Blocking plate, 6 Blocking mortar.
具体实施方式Detailed ways
下面结合附图和具体实施例对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings and specific embodiments.
一种用于冻结法连接通道的施工方法,包括以下步骤:A construction method for connecting a channel by a freezing method, comprising the following steps:
请参见附图1和附图2,步骤1:安装主隧道管片1。Please refer to Figure 1 and Figure 2, Step 1: Install the
所述的步骤1包括以下分步骤:Described
步骤1.1:在主隧道管片1中预留冻结孔11,并在冻结孔11中预埋预埋管12。Step 1.1: Reserve a freezing
优选的,在预埋所述的预埋管12时,预埋管12的轴向与冻结管2的设计插入轴向一致,并将预埋管12与主隧道管片1内部的钢筋结构连接。Preferably, when the
优选的,在预埋所述的预埋管12时,同步预埋手孔盒子15,手孔盒子15与预埋管12的端部同轴固定连接。Preferably, when the
所述的预埋管12的一端形成有预埋凸缘121,预埋凸缘121浇筑在主隧道管片1内,预埋管12的另一端固定连接有手孔盒子15,可通过手孔盒子15预留操作空间,便于后续冻结法施工作业时使用,手孔盒子15可与预埋管12焊接固定。One end of the
所述的预埋管12的外壁上设有止水圈123,预埋管12通过止水圈123密封预埋在主隧道管片1内。止水圈123可采用橡胶材质制成,确保预埋管12在主隧道管片1内的预埋密封性。The outer wall of the embedded
步骤1.2:通过闷头13旋接并临时封闭预埋管12。Step 1.2: Screw and temporarily seal the embedded
优选的,在通过所述的闷头13临时封闭预埋管12时,在闷头13与预埋管12之间设置填料14,避免施工过程中砂浆等堵塞预埋管12,填料14可采用泡沫材料。Preferably, when the
所述的预埋管12的内壁上形成有内螺纹,孔口管3的一端和闷头13的一端均形成有外螺纹,使孔口管3能通过内螺纹和外螺纹旋接在预埋管12上,闷头13能通过内螺纹和外螺纹旋接在预埋管12上。通过内外螺纹咬合旋接,拆装方便,安装可靠性高。The inner wall of the embedded
所述的闷头13的另一端边缘处形成有第一限位凸缘131,闷头13连接在预埋管12上时,第一限位凸缘131能贴合在手孔盒子15的内壁上。第一限位凸缘131可起到限位、定位的作用,确保闷头13可靠连接在预埋管12上,第一限位凸缘131与闷头13可采用一体成型制作。A first limiting
所述的闷头13的另一端形成有旋接部132,旋接部132可采用M30六角螺母并一体成型在闷头13上,便于闷头13的旋接控制。The other end of the
请参见附图3至附图5,步骤2:冻结管钻孔施工。Please refer to Figures 3 to 5, Step 2: Freeze pipe drilling construction.
所述的步骤2包括以下分步骤:Described
步骤2.1:卸下闷头13,并在预埋管12上旋接孔口管3,孔口管3的内端位于主隧道管片1内,孔口管3的外端延伸至隧道内部。Step 2.1: Remove the
优选的,若所述的闷头13与预埋管12之间填充有填料14,在卸下闷头13时同步清理填料14。Preferably, if the
所述的孔口管3的一端边缘处形成有第二限位凸缘32,孔口管3连接在预埋管12上时,第二限位凸缘32能贴合在手孔盒子15的内壁上。第二限位凸缘32可起到限位、定位的作用,确保孔口管3可靠连接在预埋管12上,第二限位凸缘32与孔口管3可采用一体成型制作。A
所述的预埋管12的内壁上设有密封圈122,两个密封圈122分别位于内螺纹的两端,使预埋管12能通过密封圈122与孔口管3密封连接,预埋管12能通过密封圈122与闷头13密封连接。密封圈122可采用橡胶材质制成,保证预埋管12与闷头13或孔口管3连接时的密封性。The inner wall of the embedded
步骤2.2:在孔口管3的外端上同轴连接冻结管密封装置4。Step 2.2: On the outer end of the
所述的密封装置包括第二密封垫42、第一密封垫43、端部压板44和孔口装置45;第一密封垫43通过固定件46固定设置在孔口装置45的一端与冻结管2之间,且第一密封垫43能密封贴合在冻结管2的表面上;端部压板44设置在孔口装置45的另一端,第二密封垫42通过固定件46固定设置在孔口装置45的另一端与端部压板44之间,且第二密封垫42能密封贴合在冻结管2的表面上;第一密封垫43、第二密封垫42、孔口装置45和冻结管2之间形成密封空腔。The sealing device includes a
步骤2.3:将冻结管2同轴插入冻结管密封装置4和孔口管3,使冻结管密封装置4密封包裹在冻结管2上。Step 2.3: Insert the freezing
优选的,所述的第一密封垫43和第二密封垫42均为圆环形结构,第一密封垫43和第二密封垫42的外圈边缘均与孔口装置45的外圈边缘齐平,第一密封垫43和第二密封垫42的内圈边缘处弯曲形变并压紧贴合在冻结管2的表面上。利用弯曲形变的第一密封垫43和第二密封垫42可靠压紧冻结管2,确保第一密封垫43和第二密封垫42内圈处的密封性,也保证了密封空腔的密封性,从而保证了止水效果。Preferably, the
所述的孔口装置45包括一个或若干个孔口装置单元,孔口装置单元呈圆环形结构,若干个孔口装置单元通过固定件46依次同轴连接。优选的,孔口装置单元的数量可根据实际需求增减,可设置一个或多个,设置多个孔口装置单元时可增大组合式密封装置的密封区域,从而提高密封止水效果。The
每相邻两个所述的孔口装置单元之间均设有第三密封垫47,第三密封垫47能密封贴合在冻结管2的表面上,第三密封垫47位于第一密封垫43与第二密封垫42之间,并将密封空腔分隔成若干个相互独立的密封空腔单元。通过第三密封垫47在若干个孔口装置单元间组合形成多腔密封止水,密封空腔单元相互独立,互不影响,以确保密封止水的安全性、有效性和密封性。A third sealing gasket 47 is provided between every two adjacent orifice device units. The third sealing gasket 47 can seal and fit on the surface of the freezing
所述的第三密封垫47为圆环形结构,第三密封垫47的外圈边缘与孔口装置单元的外圈边缘齐平,第三密封垫47的内圈边缘处弯曲形变并压紧贴合在冻结管2的表面上,且第一密封垫43、第二密封垫42和第三密封垫47的弯曲形变方向一致。通过弯曲形变的第三密封垫47可靠压紧冻结管2,保证了密封空腔单元的密封性和独立性,确保并提高每一道密封空腔单元的密封止水效果。The third sealing gasket 47 has a circular structure, the outer edge of the third sealing gasket 47 is flush with the outer ring edge of the orifice device unit, and the inner ring edge of the third sealing gasket 47 is bent, deformed and pressed tightly. It is attached to the surface of the freezing
所述的端部压板44为圆环形结构,端部压板44的圆环宽度略大于孔口装置45的圆环宽度,使端部压板44的外圈边缘与孔口装置45的外圈边缘齐平,端部压板44的内圈直径略小于孔口装置45内圈直径且略大于冻结管2的外径。通过端部压板44的内圈边缘对第二密封垫42形成阻挡和限位,防止第二密封垫42的弯曲形变方向改变而导致密封失效。The
步骤2.4:在冻结管密封装置4上连接油脂旁通球阀41,使油脂旁通球阀41通过注入油脂411并密封冻结管2。Step 2.4: Connect the grease
优选的,每个孔口装置单元上均连接有至少一个油脂旁通球阀41,以保证油脂411的注入,每个密封空腔单元内均通过油脂旁通球阀41注入有油脂411。Preferably, at least one grease
步骤2.5:冻结管2进行钻进施工,并在钻进施工过程中保持油脂411的注入。Step 2.5: Freeze the
请参见附图6和附图7,所述的步骤2.5包括以下分步骤:Please refer to accompanying drawing 6 and accompanying drawing 7, described step 2.5 comprises the following sub-steps:
步骤2.5.1:在孔口管3上安装注浆旁通球阀31,并通过注浆旁通球阀31向孔口管3内补偿注浆加固。Step 2.5.1: Install the grouting
优选的,所述的注浆旁通球阀31向孔口管3与冻结管2之间的间隙内注入双液水泥浆。Preferably, the grouting
步骤2.5.2:拆除冻结管密封装置4,并通过封堵板5封闭孔口管3的外端与冻结管2连接部位处的间隙。Step 2.5.2: Remove the freezing
优选的,所述的封堵板5位圆环形结构,封堵板5的外圈边缘与孔口管3的外端焊接固定,封堵板5的内圈与冻结管2的外壁焊接固定。Preferably, the 5-position annular structure of the blocking plate, the outer edge of the blocking
请参见附图8,步骤3:冻结管2钻进施工完成后,停止冻结法施工,进行冻结孔封孔。通过冻结管2进行冻结法施工地下隧道的连接通道采用现有工艺进行,此处不再赘述。Please refer to FIG. 8, step 3: after the drilling of the freezing
所述的步骤3包括以下分步骤:Described
步骤3.1:排放冻结管2内的盐水,拆除封堵板5和孔口管3。焊接固定的封堵板5可采用切割方式拆除,孔口管3可利用螺纹旋动拆除。Step 3.1: Drain the brine in the freezing
步骤3.2:割除部分冻结管2,使切割后的冻结管2的一端位于预埋管12内,避免冻结管2外露而影响冻结孔11的封孔和主隧道管片1内壁的抹平。Step 3.2: Cut off part of the
步骤3.3:通过闷头13旋接并封闭预埋管12。步骤3.3中闷头13的旋接与步骤1.2中的闷头13的旋接方式一致,但步骤3.3中无需填充填料14,此处不再赘述。Step 3.3: Screw and seal the embedded
步骤3.4:在闷头13与封闭预埋管12之间以及冻结管2内注入封孔砂浆6,用于填充闷头13与封闭预埋管12之间和冻结管2内的空间,确保冻结孔11内部的完全填充,达到有效的封堵效果。封孔砂浆6可采用水泥砂浆。Step 3.4: Inject sealing mortar 6 between the
优选的,在通过所述的闷头13封闭预埋管12时,若冻结孔11内预埋有手孔盒子15,将闷头13与手孔盒子15焊接加固,确保闷头13的安装可靠、牢固。Preferably, when the
步骤3.5:利用封孔砂浆6抹平主隧道管片1的内壁,恢复主隧道管片1的原结构。Step 3.5: Use the sealing mortar 6 to smooth the inner wall of the
以上仅为本发明的较佳实施例而已,并非用于限定发明的保护范围,因此,凡在本发明的精神和原则之内所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the present invention. within the scope of protection.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210284785.4A CN114607409B (en) | 2022-03-22 | 2022-03-22 | Construction method for connecting passages using the freezing method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210284785.4A CN114607409B (en) | 2022-03-22 | 2022-03-22 | Construction method for connecting passages using the freezing method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN114607409A true CN114607409A (en) | 2022-06-10 |
| CN114607409B CN114607409B (en) | 2025-06-17 |
Family
ID=81865762
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210284785.4A Active CN114607409B (en) | 2022-03-22 | 2022-03-22 | Construction method for connecting passages using the freezing method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN114607409B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117684991A (en) * | 2023-12-18 | 2024-03-12 | 北京中煤矿山工程有限公司 | A construction method for deep freezing orifice pipe and mechanical seal |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008019663A (en) * | 2006-07-14 | 2008-01-31 | Maeda Corp | Tunnel construction method |
| KR20140080852A (en) * | 2012-12-20 | 2014-07-01 | 두산건설 주식회사 | Freezimg pipe and ground freezing method using freezimg pipe |
| CN110056359A (en) * | 2019-04-10 | 2019-07-26 | 中铁十二局集团有限公司 | The freezing hole construction method of tunnel freezing curtain |
| CN111022059A (en) * | 2019-12-24 | 2020-04-17 | 中交路桥建设有限公司 | Freezing hole construction process |
-
2022
- 2022-03-22 CN CN202210284785.4A patent/CN114607409B/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008019663A (en) * | 2006-07-14 | 2008-01-31 | Maeda Corp | Tunnel construction method |
| KR20140080852A (en) * | 2012-12-20 | 2014-07-01 | 두산건설 주식회사 | Freezimg pipe and ground freezing method using freezimg pipe |
| CN110056359A (en) * | 2019-04-10 | 2019-07-26 | 中铁十二局集团有限公司 | The freezing hole construction method of tunnel freezing curtain |
| CN111022059A (en) * | 2019-12-24 | 2020-04-17 | 中交路桥建设有限公司 | Freezing hole construction process |
Non-Patent Citations (1)
| Title |
|---|
| 胡向东;陈蕊;: "双层越江隧道联络通道冻结法施工技术", 低温建筑技术, no. 05, 28 October 2006 (2006-10-28) * |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117684991A (en) * | 2023-12-18 | 2024-03-12 | 北京中煤矿山工程有限公司 | A construction method for deep freezing orifice pipe and mechanical seal |
Also Published As
| Publication number | Publication date |
|---|---|
| CN114607409B (en) | 2025-06-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102561977B (en) | High-pressure high-flow water burst hole drilling safety system, mounting process thereof and service process | |
| CN106838463B (en) | The fastener inserts and usage of longitudinal overall stiffness after raising rectangular top plumber | |
| CN110822180A (en) | Wall pipe assembly | |
| CN114718579A (en) | Combined sealing device for drilling construction of freezing pipe of freezing method connecting channel | |
| CN115163134A (en) | Multi-sealing waterproof structure for ultra-large-diameter shield segment joints and bolt holes | |
| CN110630297B (en) | Method for treating water leakage of segment joint in shield tunnel in operation period | |
| CN114607409A (en) | Construction method for connecting channel by freezing method | |
| CN205370597U (en) | A system's leaking stoppage and drainage structures for tunnel seepage is administered | |
| CN115726821A (en) | A water-stop packing device with a reserved hole | |
| CN110762287A (en) | A water-stop structure suitable for curve pipe jacking interface under high water pressure condition | |
| CN220647236U (en) | Leak stopping repair structure of prestressed steel cylinder concrete pipe | |
| CN206233896U (en) | For the anti-pumping blocking of gas pumping and the outer plugging device of drainage holes | |
| CN211574318U (en) | Pressure water piping plugging device | |
| CN114440008B (en) | Anti-seepage water-stopping casing and construction method thereof | |
| CN216896164U (en) | Waterproof and sealing structure of through-wall pipes | |
| KR100241472B1 (en) | A device for closing the working hole of sewer pipe | |
| KR100749550B1 (en) | How to repair and repair leaks in water pipes | |
| CN115573373A (en) | Plugging device and method for underground concrete permeable wall | |
| CN209855833U (en) | Slip casting leak-proof stop plug | |
| CN209468762U (en) | A new type of grouting device | |
| CN219733415U (en) | Extrusion sealing internal fixation type micro-disturbance grouting device | |
| CN209555927U (en) | The mini-valve tube of two fluid grouting core pipe design | |
| CN219081540U (en) | Coal mine gas extraction hole plugging device | |
| CN218597085U (en) | Sealing protection device suitable for hydraulic gallery drain hole orifice | |
| CN220647245U (en) | A leak-stopping device with water and pressure for water supply pipeline maintenance |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |